Operation of SAWS New Groundwater Desal Plant - Richard Donat

25
TWCA Richard Donat Executive Management Analyst, Engineering and Construction San Antonio Water System Brackish Groundwater Desalination Project March 1, 2017

Transcript of Operation of SAWS New Groundwater Desal Plant - Richard Donat

Page 1: Operation of SAWS New Groundwater Desal Plant - Richard Donat

TWCA

Richard DonatExecutive Management Analyst, Engineering and Construction

San Antonio Water SystemBrackish Groundwater Desalination Project

March 1, 2017

Page 2: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 2

Outline• Water Challenges • Project Background• Project Challenges• Facility Highlights

Page 3: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 3

Water Supply Challenges

Page 4: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 4

Why Brackish Inland Desalination

• Large volumes of available brackish water

• Resource close to San Antonio

• Identified in the SAWS 2005 Water Management Plan

• Diversification• Untapped resource

Page 5: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 5

Desalination Program

• Phase I (2016) – 12 MGD – 13,440 Acre-feet / year– (~53,000 Households)

• Source Water– Lower Wilcox Formation– 12 Production wells (~1,500’ avg. depth)

• Treatment Process– Reverse Osmosis

• Concentrate Disposal– 2 Injection wells (5,000’ avg. depth)

General Information

Page 6: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 6

Project Cost

• Project Cost: $192.7 million, $1,177 $/AF• Began producing water November 9, 2016

Phase I

Page 7: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 7

Challenges• State and Local Groundwater

Regulation• Public Perception• Stakeholder Buy in• Funding/Value Engineering• Real Estate• Concentrate Disposal• Design • Construction • Operational

Page 8: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 8

Concentrate DisposalOptions Considered

Page 9: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 9

Design

• Prevent Membrane fouling – Open System vs. Closed

System– Pre-treatment

• Finish water quality standards

• Short design timeline– Multiple sub-consultants

Challenges

Page 10: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 10

Construction Challenges

• Budget– Managing a budget

without owner contingency

• Schedule– Record Rainfall (2 yrs.)

• Complicated Construction– 13 Work Packages

Challenges

$

Page 11: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 11

Operational

• Learning curve – Fully automated plant– Bring in operators early– 1 month RDT & 3 months

commissioning phase• Operational– Raw Water

• Cartridge Filters/Turbidity– Fouling– Meeting Finished Water Goals

Challenges

Page 12: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 12

Stage 1

Stage 2

Reverse Osmosis Primary Trains

Stage 1

Stage 2

Stage 1

Stage 2

Stage 1

Stage 2

Lower Wilcox Wellfield

Pre-Filters

13.11 mgd

2 mgd

Anti-Scalant

Reverse Osmosis

Concentrator Trains

Stage 3

Stage 3

8.88 mgd 1.11 mgd

Injection Wells

12 mgd

1.11 mgd

H2SO4

Calcite Contactors

30%

70%

CO2

Degasifiers

NaOH Cl2

Process DiagramOperational

Page 13: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 13

Construction 2014 to PresentBuilding Success

June 2014 April 2015

December 2016February 2016

Page 14: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 14

Treatment Facility

Page 15: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 15

Three Water Supplies at H2Oaks

Page 16: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 16

Water Supply and Educational CenterEducation and Outreach

Page 17: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 17

Water Supply and Educational CenterEducation and Outreach

Page 18: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 18

Grand Opening FestivitiesJanuary 27, 2017

Page 19: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 19

Thank you

Page 20: Operation of SAWS New Groundwater Desal Plant - Richard Donat

TWCA

Richard DonatExecutive Management Analyst, Engineering and Construction

San Antonio Water SystemBrackish Groundwater Desalination Project

March 1, 2017

Page 21: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 21

Regulatory

• State and Local Groundwater Regulation– 16 Groundwater

Management Areas– 100 Groundwater Districts

• Challenges:– Desired Future Conditions

(DFCs)– Groundwater Permits

Challenges

http://www.tceq.state.tx.us/assets/public/permitting/watersupply/groundwater/maps/gcdmap.pdf

Page 22: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 22

Stakeholder Buy in

• Large project many different stakeholders across SAWS

• Partnering sessions with SAWS upper management

• Desal plant visits across the United States

• Outreach to San Antonio elected officials and SAWS Board of Trustees– Addressed Project concerns

• Construction Manager, Program Manager, and SAWS Workshops

Challenges

Page 23: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 23

BudgetingDeveloping Cost Estimates

*For comparison purposes all estimates assume 5% annual debt service*2009/2010 Estimate 10 MGD / 2012 Estimate 10.9 MGD / 2014 Estimate 12 MGD

• Economy• Increase Plant

Capacity• Scope/Vision

Change• New

Information• Estimates vs.

Actual Bids

Page 24: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 24

Funding

• Rate approval through SAWS board of Trustees and City Council

• Texas Water Development Board (TWDB) Low Interest Loans

• Construction estimates greater than budget estimates– Value Engineering– $17.7M reduction

Funding Sources for the ProgramInterest

Rate$/acre-

foot$/1,000 gallons

5% $1,370 $4.20 4% $1,266 $3.89 3% $1,177 $3.60

*Without and interest rate reduction SAWS would need to lower the capital cost by $40M to achieve $1,177 / acre-foot

Page 25: Operation of SAWS New Groundwater Desal Plant - Richard Donat

March 1, 2017

SAWS Brackish Groundwater Desalination ProjectPage 25

Real Estate

• Purchasing land needed for well field– 3,200 acres already owned– Additional 2,800 acres

purchased – Takes time• Land is leased back for

agriculture and grazing– Livestock

• Working with neighbors– Public Meeting

Challenges