Operation of SAWS New Groundwater Desal Plant - Richard Donat
-
Upload
twca -
Category
Environment
-
view
68 -
download
1
Transcript of Operation of SAWS New Groundwater Desal Plant - Richard Donat
TWCA
Richard DonatExecutive Management Analyst, Engineering and Construction
San Antonio Water SystemBrackish Groundwater Desalination Project
March 1, 2017
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 2
Outline• Water Challenges • Project Background• Project Challenges• Facility Highlights
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 3
Water Supply Challenges
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 4
Why Brackish Inland Desalination
• Large volumes of available brackish water
• Resource close to San Antonio
• Identified in the SAWS 2005 Water Management Plan
• Diversification• Untapped resource
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 5
Desalination Program
• Phase I (2016) – 12 MGD – 13,440 Acre-feet / year– (~53,000 Households)
• Source Water– Lower Wilcox Formation– 12 Production wells (~1,500’ avg. depth)
• Treatment Process– Reverse Osmosis
• Concentrate Disposal– 2 Injection wells (5,000’ avg. depth)
General Information
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 6
Project Cost
• Project Cost: $192.7 million, $1,177 $/AF• Began producing water November 9, 2016
Phase I
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 7
Challenges• State and Local Groundwater
Regulation• Public Perception• Stakeholder Buy in• Funding/Value Engineering• Real Estate• Concentrate Disposal• Design • Construction • Operational
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 8
Concentrate DisposalOptions Considered
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 9
Design
• Prevent Membrane fouling – Open System vs. Closed
System– Pre-treatment
• Finish water quality standards
• Short design timeline– Multiple sub-consultants
Challenges
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 10
Construction Challenges
• Budget– Managing a budget
without owner contingency
• Schedule– Record Rainfall (2 yrs.)
• Complicated Construction– 13 Work Packages
Challenges
$
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 11
Operational
• Learning curve – Fully automated plant– Bring in operators early– 1 month RDT & 3 months
commissioning phase• Operational– Raw Water
• Cartridge Filters/Turbidity– Fouling– Meeting Finished Water Goals
Challenges
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 12
Stage 1
Stage 2
Reverse Osmosis Primary Trains
Stage 1
Stage 2
Stage 1
Stage 2
Stage 1
Stage 2
Lower Wilcox Wellfield
Pre-Filters
13.11 mgd
2 mgd
Anti-Scalant
Reverse Osmosis
Concentrator Trains
Stage 3
Stage 3
8.88 mgd 1.11 mgd
Injection Wells
12 mgd
1.11 mgd
H2SO4
Calcite Contactors
30%
70%
CO2
Degasifiers
NaOH Cl2
Process DiagramOperational
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 13
Construction 2014 to PresentBuilding Success
June 2014 April 2015
December 2016February 2016
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 14
Treatment Facility
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 15
Three Water Supplies at H2Oaks
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 16
Water Supply and Educational CenterEducation and Outreach
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 17
Water Supply and Educational CenterEducation and Outreach
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 18
Grand Opening FestivitiesJanuary 27, 2017
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 19
Thank you
TWCA
Richard DonatExecutive Management Analyst, Engineering and Construction
San Antonio Water SystemBrackish Groundwater Desalination Project
March 1, 2017
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 21
Regulatory
• State and Local Groundwater Regulation– 16 Groundwater
Management Areas– 100 Groundwater Districts
• Challenges:– Desired Future Conditions
(DFCs)– Groundwater Permits
Challenges
http://www.tceq.state.tx.us/assets/public/permitting/watersupply/groundwater/maps/gcdmap.pdf
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 22
Stakeholder Buy in
• Large project many different stakeholders across SAWS
• Partnering sessions with SAWS upper management
• Desal plant visits across the United States
• Outreach to San Antonio elected officials and SAWS Board of Trustees– Addressed Project concerns
• Construction Manager, Program Manager, and SAWS Workshops
Challenges
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 23
BudgetingDeveloping Cost Estimates
*For comparison purposes all estimates assume 5% annual debt service*2009/2010 Estimate 10 MGD / 2012 Estimate 10.9 MGD / 2014 Estimate 12 MGD
• Economy• Increase Plant
Capacity• Scope/Vision
Change• New
Information• Estimates vs.
Actual Bids
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 24
Funding
• Rate approval through SAWS board of Trustees and City Council
• Texas Water Development Board (TWDB) Low Interest Loans
• Construction estimates greater than budget estimates– Value Engineering– $17.7M reduction
Funding Sources for the ProgramInterest
Rate$/acre-
foot$/1,000 gallons
5% $1,370 $4.20 4% $1,266 $3.89 3% $1,177 $3.60
*Without and interest rate reduction SAWS would need to lower the capital cost by $40M to achieve $1,177 / acre-foot
March 1, 2017
SAWS Brackish Groundwater Desalination ProjectPage 25
Real Estate
• Purchasing land needed for well field– 3,200 acres already owned– Additional 2,800 acres
purchased – Takes time• Land is leased back for
agriculture and grazing– Livestock
• Working with neighbors– Public Meeting
Challenges