October 21, 2003H.J. Krebs1 LST Mechanical Design Review Handling & Installation Fixtures Design and...
-
Upload
derrick-riley -
Category
Documents
-
view
214 -
download
0
Transcript of October 21, 2003H.J. Krebs1 LST Mechanical Design Review Handling & Installation Fixtures Design and...
October 21, 2003 H.J. Krebs 1
LST Mechanical Design Review
Handling & Installation Fixtures Design and Fabrication Status
H.J. KrebsOctober 10, 2003
October 21, 2003 H.J. Krebs 4
Installation & Handling Fixtures Status• Center Gap Plate Fixture
– Purpose• Remove and reinstall the upper and lower center gap plates
on the FWD end to enable removal of RPCs and installation of brass absorber plates and LSTs
– Needed• 2004
– Responsible person• Jim Krebs
– Status• Design and drawings complete• Fabrication complete
October 21, 2003 H.J. Krebs 7
Installation & Handling Fixtures Status• Solenoid Support Arm Fixture
– Purpose• Remove and reinstall the upper and lower solenoid support
arms on the FWD end used to react axial loads. This will enable removal of the upper and lower FWD corner blocks.
– Needed• 2004, 2005
– Responsible person• Jim Krebs
– Status• Design and drawings complete• Fabrication complete
October 21, 2003 H.J. Krebs 10
Installation & Handling Fixtures Status• Corner Block Adaptors
– Purpose• Moves corner block rigging connection in Z direction to more
convenient location. There are two basic adaptors corresponding to the mid & lower corner blocks and right and left hand units to correspond with east and west.
– Needed• 2004 (lower), 2005 (mid & lower)
– Responsible person• Jim Krebs
– Status• Design and drawings complete for lower adaptor• Fabrication complete
October 21, 2003 H.J. Krebs 13
Installation & Handling Fixtures Status• Adaptor Installation Fixture
– Purpose• Used to install and remove the adaptors on the mid
& lower corner blocks.
– Needed• 2004, 2005
– Responsible person• Jim Krebs
– Status• Design and drawings complete• Fabrication complete
October 21, 2003 H.J. Krebs 15
Installation & Handling Fixtures Status• Corner Block C-Hooks
– Purpose• Supports corner block dead load from crane during removal and
reinstallation process. There are three C-Hook designs corresponding to the lower, mid & upper corner bocks.
– Needed• 2004(lower & upper), 2005 (all)
– Responsible person• Jim Krebs
– Status• Upper
– Design and drawings complete– Fabrication in process
• Mid– Initial CG calculations complete– No drawings at this time (not needed until 2005)
• Lower– CG calculations verified– No drawings at this time
October 21, 2003 H.J. Krebs 17
Installation & Handling Fixtures Status• Corner Block Receptacle & Lift Eye
– Purpose• Supports corner block vertically to release C-Hook
and to lift corner block and load on truck using conventional rigging.
– Needed• 2004, 2005
– Responsible person• Allen Constable
– Status• Design not yet started on receptacle• Lift eye fabrication in process
October 21, 2003 H.J. Krebs 19
Installation & Handling Fixtures Status• Flux Bar Handling Fixture
– Purpose• Used to remove and reinstall the flux bars that are located
behind the corner blocks. The flux bars must be removed to access layer 18. The handling fixture for the side flux bars may be different than that used for the top & bottom.
– Needed• 2004 (top & bottom), 2005 (sides)
– Responsible person• Jim Krebs
– Status• Design and drawings not yet started – December?
October 21, 2003 H.J. Krebs 20
Installation & Handling Fixtures Status• Brass Installation Fixtures
– Purpose• Install brass plates in steel flux return gaps. Top & bottom
fixtures are different than side fixtures. There is a separate presentation devoted to these fixtures.
– Needed• 2004 (top & bottom fixtures), 2005 (side fixtures)
– Responsible person• Allen Constable
– Status• Top & Bottom
– Design complete– Fabrication
» Parts in shop» Remaining parts on order
• Sides– Design scheduled to begin 12-8-03
October 21, 2003 H.J. Krebs 21
Installation & Handling Fixtures Status• Brass Cambering Fixture
– Purpose• Modifies brass plate camber in field if steel gap is
shaped different than expected.
– Needed• 2004, 2005
– Responsible person• Allen Constable
– Status• Preliminary design complete• Fabrication is not yet started
October 21, 2003 H.J. Krebs 22
Installation & Handling Fixtures Status• Forward End Plug Handling Fixture & Spreader
– Purpose• Used to remove and reinstall the FWD end plug halves in the
FWD end doors. Spreader bar needed to route rigging slings on each side (+Z & -Z) of the FWD end doors.
– Needed• 2005
– Responsible person• Jim Krebs
– Status• Design and drawings are complete• Fabrication is complete
October 21, 2003 H.J. Krebs 26
Installation & Handling Fixtures Status• Forward End Plug Receivers
– Purpose• There are one each of a R.H. & L.H. receiver. These
receivers support the FWD end plug halves in their normally installed orientation to allow the end plug handling fixture to be removed. The receivers will be used to transport the end plug halves to IR-12.
– Needed• 2005
– Responsible person• Allen Constable
– Status• Design scheduled to begin 11-19-03• Fabrication is not yet started
October 21, 2003 H.J. Krebs 27
Installation & Handling Fixtures Status• EMC Load Transfer Fixture
– Purpose• Transfers EMC gravitational load to flux return upper
earthquake support beams to allow removal of FWD mid corner plates. There is a separate presentation devoted to this fixture.
– Needed• 2005
– Responsible person• Richard Boyce
– Status• Design and drawings are in conceptual design phase• Fabrication is not yet started
October 21, 2003 H.J. Krebs 28
Installation & Handling Fixtures Status• Installation Platforms & Positioners
– Purpose• These devices are used to position fixtures and personnel in
the proper orientation and elevation relative to the flux return steel. There are three basic devices: a vertical elevating platform, a horizontal angled positioner, and a device that will pull existing RPCs from their corresponding barrel slots. There is a separate presentation devoted to these devices
– Needed• 2004 (elevator, RPC puller), 2005 (all)
– Responsible person• Les Dittert
– Status• Design and drawings are complete• Fabrication is not yet started
October 21, 2003 H.J. Krebs 29
Conclusions & Comments• Barrel RPC removal, brass and LST installation
require the development of several handling and installation fixtures.
• The LST installation equipment is not included in this presentation. (See Bill Sands talk)
• The design and fabrication of these fixtures are on schedule for the 2004 down.
• Our goal is to have these fixtures available as early as possible to take advantage of any potential schedule advancement.