OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis...

download OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

of 34

Transcript of OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis...

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    1/34

    1

    From Vision towards BankableRenewable Energy ProjectsSt. Kitts and Nevis Example

    IRENA-CARILEC Renewable Ener Forum Bermuda Se t 17 2012

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    2/34

    2

    OAS: Background

    The General Secretariat of the Organization ofAmerican States (GS/OAS) is the premier forum for

    multilateral dialogue and concerted action in Latin

    America and the Caribbean.

    GS/OAS serves 34 member states of the hemisphere

    Representative Offices in most of its member states

    Department of Sustainable Development

    Energy and Climate Change Mitigation Section

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    3/34

    3

    ECPA Caribbean Initiative

    Goals:I. Market conditioning: Promote sustainable energy policies

    II. Commercialization: Assist governments deploying and

    commercializing renewable energy projects

    III. Regional integration: Support dialogue to address long-termCaribbean energy security challenges and promoting regional

    integration

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    4/34

    4

    When is a project bankable?

    Starts with recognizing that what is needed to make a renewable energy

    project bankable is challenging for both developers seeking fundingand forfinanciers seeking a suitable investment.

    Our role is assisting in bridging the gap between developer andfinanciers needs to make a renewable energy project bankable.

    RE resourceassessment

    Marketconditioning

    Project ID /

    TechnologyTransfer

    ProjectFinancing

    Project Execution(Build/Own/Operate)

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    5/34

    5

    What is the basic check-list for a bankable project?

    Project objectives, design, scale, and conditions must be clearly defined

    and be able to fit within existing sectors/branches of interest;

    A (pre-)feasibility assessment needs to be performed(developer/investor (Bank/FI);

    Due diligence confirming technical and financial viability(public/industry (private)

    Environmental and operational standards/protocols compliance (notonly local laws but internationally accepted standards);

    Be the least-cost solution after CBA/Life Cycle Costs analysis of project;

    Investors Final spread sheet - All inputs needed to perform a comprehensivefinancial analysis (including O&M costs, energy price forecasts, expected savings,etc.) have to be in place.

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    6/34

    6

    Case Study: Federation of St. Kitts and Nevis

    Item Value

    Land Area

    269 km (total)

    176 km (St Kitts)

    93 km (Nevis)

    Population

    42,000 (total)

    30,000 (St Kitts)

    12,000 (Nevis)

    Geographic coordinates 17 20 N, 62 45 W

    SKN is the smallest OAS Member State

    Federal Ministry of

    Public Utilities, Energy,

    Housing & Works

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    7/34

    7

    Conditions in 2005

    In summer of 2005 SKN started transition fromagricultural based economy to a tourism industry

    Need to assess alternative uses of available land

    Economy needed to become diversified and morecompetitive and energy is a key ingredient in

    facilitating this transition

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    8/34

    8

    Energy Sector Conditions in 2005

    No Energy Plan or Policy in place (2005);

    100% dependent on imported fossil fuels for energy

    generation, transportation, and other uses;

    St. Kitts Electricity Department (Government

    Department) and NEVLEC (corporatized in 2000); Limited market size (ie. Electricity demand);

    Shift to tourism and banking in commercial sector (ie.

    high quality power requirements);

    Water sector created considerable demands for power

    sector;

    Considerable renewable energy natural resources.

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    9/34

    RE Development in SKN?

    What is the current energy situation?

    What are the RE resource potentials?Technical Perspective

    What is the long term vision of SKN?

    Is there a strategy in place to achieve vision?Political Perspective

    How conducive is the existing legal structuretowards RE deployment?Legislative Perspective

    Does SKN Govmnt have the required capacity toassess and close contractual RE Project deals?Institutional Perspective

    Can RE projects be identified on the short/mediumterm to attract investors?Project Development

    How can finance be secured for identified REprojects?Financing

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    10/34

    10

    Qualitative RE resource and supply mix assessment

    (2005-2006)

    http://www.gseii.org/PDF/NWS-E-2006-21.pdf
  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    11/34

    11

    St. Kitts (2005-2020)

    Nevis (2005-2020)

    0

    10

    20

    30

    40

    50

    2005 2010 2015 2020

    PeakDemandandOperational

    Capacity(MW)

    Year

    solar

    wind

    conventional

    low

    medium

    high

    0

    10

    20

    30

    40

    50

    2005 2010 2015 2020PeakDemandand

    OperationalCapacity

    (MW)

    Year

    geothermal

    wind

    conventional

    lowmedium

    high

    SKN Energy Outlook Scenarios (2006)

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    12/34

    12

    Solar Irradiation(2010)

    Bio-energy(2007)

    Geothermal Potential(2005)

    Renewable Energy Resource Mapping

    (20052011)

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    13/34

    13

    National Energy Outlook

    St. Kitts and Nevis (2005-2020)

    0

    10

    20

    30

    40

    50

    60

    70

    2005 2010 2015 2020

    PeakDemandandOperatio

    nalCapacity(MW)

    Year

    solar

    geothermal

    wind

    conventional

    low

    medium

    high

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    14/34

    National Energy Policy Development

    (20082011)

    Vision Statement:

    The Federation of St. Kitts and Nevis wants to become a

    twin-island nation with a sustainable energy sector where

    reliable, renewable, clean andaffordable energy services

    are provided to all its citizens.

    Federal Ministry of

    Public Utilities,

    Energy, Housing &

    Works

    Ministry of Natural

    Resources and

    Environment - NIA

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    15/34

    15

    SKN Policy Objectives

    #1 Sector Management: Secure efficient and well-coordinated planning and

    institutional management to guarantee sustainable and transparentperformance of supply, generation, distribution and end-use of energy

    #2 Diversify Energy Supply: Guarantee safe, reliable and affordable supplies

    of petroleum products and their efficient and clean handling while in

    parallel significantly increasing the deployment and utilization ofrenewable energy technologies in the Federation of St. Kitts and Nevis

    #3 Electricity Generation: Secure safe, efficient, reliable, affordable and

    environmentally friendly electricity generation and access by all

    consumers of St. Kitts and Nevis

    #4 Transportation: Efficient, environmentally clean and cost-effectivetransportation

    #5 Energy Use: Minimize energy input and achieve lowest possible energy

    intensity of economic services in all sectors of the society

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    16/34

    Wind - Nevis RE Assessment (2005), wind

    measurements (2007/08)

    National Commitments/Goals National Energy Policy (2011)

    Sustainable Energy Plan (ongoing)

    RE Policy

    RE Solicitations/Bidding (due diligence,2007)

    Utility/Developer ContractualFramework IPP legislation (2008)

    Standardized PPA (2008)

    PPA negotiations (2009)

    Commissioned (Aug 2010)

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    17/34

    17

    Geothermal Development Pathway

    St. Kitts and Nevis (2005-2020)Geothermal Resource Nevis (2010)

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    18/34

    Geothermal - Nevis Geo assessments +20 studies and OAS (2005)

    National Commitments/Goals National Energy Policy (2011) Sustainable Energy Plan (ongoing)

    Technology Specific Legislation i.e. Geothermal Resource Law (2008)

    Utility/Developer Contractual Framework IPP Geothermal Resource Contract (2008)

    Standardized PPA (2008)

    Pre-feasibility Interconnection N-SK (2008)

    Environmental Impact Assessment (2010)

    Interconnection Study Nevis-St. Kitts (Oct2012)

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    19/34

    Generalqualitative REresourceanalysis

    Targeted

    prefeasibilitystudies (Bio, Wind

    and Geo)

    Perform due

    diligence andLegal

    Assistance

    Prepare legaldocumenta-tion

    Facilitatenegotiations withdevelopers

    Close /signing of aPPA/contract

    StakeholdersConsultations

    Data CollectionMission andResearch

    Initial DraftNEP

    StakeholdersReview

    First NEPDraft

    CabinetConsultation/approval of NEP

    RE Development in SKN?

    2005 2007 2008 2009 Present2006 2010

    Quick Scan analysisof sector conditions

    CapacityBuilding

    Assessment

    MOUcreation of

    EnergyDepartment

    Development andapproval of TOR

    Financingstationary/

    office

    Establishment ofSKN EnergyDepartment

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    20/34

    20

    Is the Geo-Project in Nevis a bankable project?

    Project objectives,design, scale, and

    conditions must beclearly defined and be

    able to fit withinexisting

    sectors/branches ofinterest;

    A (pre-)feasibilityassessment needs to be

    performed(developer/investor

    (Bank/FI);

    Due diligenceconfirming technicaland financial viability

    (public/industry(private) ->

    interconnectionneeded

    Environmental andoperational

    standards/protocolscompliance (not only

    local laws butinternationally

    accepted standards);

    Be the least-costsolution after CBA/LifeCycle Costs analysis of

    project;

    Final spread sheet - Allinputs needed to

    perform acomprehensive

    financial analysis(including O&M costs,energy price forecasts,expected savings, etc.)

    have to be in place.

    DONEDONE DONE DONE

    Geothermal Resource in Nevis

    Project objectives, design,scale, and conditions mustbe clearly defined and beable to fit within existing

    sectors/branches ofinterest;

    A (pre-)feasibilityassessment needs to be

    performed(developer/investor

    (Bank/FI);

    Due diligence confirmingtechnical and financial

    viability (public/industry(private)

    Environmental andoperational

    standards/protocolscompliance (not only local

    laws but internationallyaccepted standards);

    Be the least-cost solutionafter CBA/Life Cycle Costs

    analysis of project;

    Final spread sheet - Allinputs needed to performa comprehensive financialanalysis (including O&M

    costs, energy priceforecasts, expected

    savings, etc.) have to be inplace.

    Electrical Interconnection NevisSt. Kitts

    DONE Ongoing Ongoing

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    21/34

    212005 2007 2008 2009 Present

    Global Sustainable Energy Islands Initiative (GSEII), see: www.gseii.org

    Eastern Caribbean Geothermal Project (GeoCaraib)

    US-Brazil Biofuels Initiative

    Caribbean Sustainable Energy Program (CSEP) and in 2010 with NRELunder Low Carbon Communities in the Caribbean (LCCC)

    Energy and ClimatePartnership of the

    Americas (ECPA), see:www.ecpamericas.org

    How have we been able to assist SKN?

    2006 2010

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    22/34

    22

    Lessons learned and recommendations

    Country vision and commitment is critical

    Need to focus multilateral assistance on capacity building for stats/data generation,gathering, analysis, monitoring and evaluation (compliance to NEP);

    Specific resource assessments (bio, wind, geothermal) are required for someislands for others not;

    OAS Strength is Presence, Continued Engagement, Liaison, and Spokesperson

    Synchronization among multilaterals, development entities, etc.

    Island Communities are united but not uniform

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    23/34

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    24/34

    24

    Energy and Climate Change Mitigation

    Department of Sustainable Development - DSD

    Executive Secretariat for Integral Development - SEDI

    Organization of American States

    1889 F St. N.W. Washington, D.C. 20006, USA

    T. 202.458.6261

    F. 202.458.3560

    www.oas.org; www.oas.org/dsd

    www.sepa-americas.net

    www.ecpamericas.org

    ing. Kevin de Cuba, MSc.Senior Energy Specialist

    [email protected]

    http://www.oas.org/dsdhttp://www.sepa-americas.net/http://www.ecpamericas.org/mailto:[email protected]:[email protected]://www.ecpamericas.org/http://www.sepa-americas.net/http://www.sepa-americas.net/http://www.sepa-americas.net/http://www.oas.org/dsd
  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    25/34

    25

    OAS: Policy Organization and Development Strategy

    St. Kitts Electricity Company (SKELEC) as per 2011Unit Technology Capacity (MW) Installation year#1 Mirrlees KV12 3.6 1971#2 Mirrlees KV12 3.6 1971#3 Mirrlees K8 3.5 1987#4 Caterpillar 3616 (#1) 4.4 1989

    #5 Caterpillar 3616 (#2) 4.4 1995

    #6 Mirrlees 12MB430 7.9 1999

    #7 Mirrlees 8MB430 6.1 1999

    Total 33.5

    Nevis Electricity Company (NEVLEC) as per 2011Unit Technology Capacity (MW) Installation year#2 Blackstone 0.9 1983

    #3 Blackstone 0.9 1985

    #4 Blackstone 2 1990

    #7 EMD (GM) 2.5 1992

    #5 Blackstone 2.2 1996

    #6 Blackstone 2.5 1996

    #8 Wartsila 2.7 2003

    Total 13.7

    WindWatt Ltd.Unit Technology Capacity (MW) Installation year

    Maddens farm Vergnet Wind Turbines (8x275kW) 2.2 2010

    Total 15.9

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    26/34

    26

    OAS: Policy Organization and Development Strategy

    St. Kitts Nevis Regional

    Wind Solar Wind Geothermal RETsFossil

    fuels

    Short term (1-3 yrs)

    Installed Capacity (MW) 5.4 - 2.2 10.0 - -

    Average power output (MW) 2.3 - 0.9 9.0 - -

    Sum additional average

    capacity (MW)12.3

    Timing 2011 - 2010 2012 - -

    Medium term (3-10 yrs)

    Installed Capacity (MW) 10.0 5.0 10.0 35.0 - -

    Average power output (MW) 4.2 2.0 4.2 33.0 - -

    Sum additional average

    capacity (MW)43.4 - -

    Timing 2014 2014 2015 2015 - -

    Long term (10-20 yrs) Installed Capacity (MW) 50.0 (20.0) -30.0

    Timing 2021 2021

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    27/34

    27

    Geothermal Development

    Technical Assistance, Geo-Carabes (2005ongoing)

    I. Technical: Assess the resource/technicalpotential for the several sites and electricityinterconnection scenario = Reduce resourceuncertainty and development risks

    II. Policy/Legal: Reform legal framework andDevelop Local/Regional Capacity = Reducecontract/policy uncertainties, expeditelicensing/permitting, and strengthen local inputs

    III. Financial: Prepare Geothermal Drilling Risk Fund= Reduce financial risks associated with initialcommercial exploration

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    28/34

    28

    Pre-feasibility study electrical interconnection

    NevisSt. Kitts (2008)

    Resources: >98% imported fossil fuels (1.1 MW wind in Nevis and 5 MW windin planning for St. Kitts) and WTE.

    Electricity Price: >US$.40/MWh

    http://www.oas.org/dsd/reia/Documents/St.%20Kitts%20-%20RenewableEnergyProjectsandInter-connectionAssessment.pdfhttp://www.oas.org/dsd/reia/Documents/St.%20Kitts%20-%20RenewableEnergyProjectsandInter-connectionAssessment.pdf
  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    29/34

    Geothermal: Opening doors for economic development

    Development Opportunities: -Interconnection between St.

    Kitts and Nevis

    -Strengthen power grid = attract

    new investment (tourism, hightech, light to heavy

    industry/minerals)

    -Water processing (desalination)

    -Interconnection with PuertoRico (and/or other islands)

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    30/34

    30

    World Bank Assessment: Energy Supply

    Interconnections and Regional Sources of Energy (2011)

    Interconnections MW Energy

    Source

    Km Viability (Nexant Analysis)

    Nevis St. Kitts 50 Geothermal 5 Highly economic

    Nevis Puerto Rico 400 Geothermal 400 Highly economic if displaced fuel

    is HFO

    Not economic if displaced fuel is

    LNG

    Nevis US Virgin Islands 80 Geothermal 320 Only marginally economic even

    though it displaces distillate

    Saba-St. Maarten 100 Geothermal 60 Highly economic if displaced fuel

    is distillate and St. Maarten can

    accept 100 MW

    Dominica - Martinique 100 Geothermal 70 Marginally economic if displaced

    fuel is pipeline gas

    More economic if displaced fuel

    is higher cost

    Source: Garner and Hansen (2011)

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    31/34

    31

    World Bank Assessment: Energy Supply

    Interconnections and Regional Sources of Energy (2011) - Cntd

    Interconnection MW Energy

    Source

    Km Viability (Nexant Analysis)

    Dominica - Guadeloupe 100 Geothermal 70 Moderately economic if

    displaced fuel is pipeline gas

    Highly economic if displaced fuel

    is HFO

    US (Florida) - Cuba 400 Coal-fueled

    steam plant,

    gas fueled

    combined

    cycle

    400 Highly economic if displaced fuel

    is HFO

    Dominican Republic Haiti (Land

    Connection)

    250 HFO 560 Not economic unless export is

    from lower cost unit/fuel

    combination

    ECGP Tobago- Barbados-

    Martinique(St. Lucia)

    Guadeloupe

    Up to 100

    MMs cf/d

    Natural gas 1000 Highly economic if displaces HFO

    and diesel

    Source: Garner and Hansen (2011)

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    32/34

    32

    Energy SupplyInterconnections and

    Regional Sources of Energy (2011)

    According to recent World Bank Study, Relying on diesel

    and HFO is the most costly solution

    There are multiple fuel and power supply options that

    offer cost-effective alternatives to the current situation,

    including, pipeline gas, shipped LNG, and renewables

    (geothermal, wind) interconnected via submarine cable

    Investment requirements are large but production costs

    saving are huge

    A variety ofprivate, public and IFI support will benecessary

    Requires countries to improve legal, regulatory and

    institutional framework and cross-country cooperation

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    33/34

    World Bank preliminary analysis of supply alternatives

    ECPA US State OAS/KEMA/NREL: pre-feasibility study of

    SKN Puerto Rico interconnection (Oct 2012)

    Other regional studies:

    -PR-USVI (US DOE/NREL)

    -PR-DR (World Bank)

    -Dominica-Martinique-Guadeloupe (EU/France)

    (Pre)-feasibility studies of interconnections (2011ongoing)

  • 7/30/2019 OAS (Kevin de Cuba), From Vision towards Bankable Renewable Energy Projects, St. Kitts and Nevis Example

    34/34

    34

    Snapshots of Several Caribbean

    Interconnection Scenarios (Source: Nexant Study/World Bank)

    Eastern Caribbean Gas Pipeline Proposed RouteDominica Interconnections

    Northern Ring Interconnections AlternativePuerto Rico and St. Kitts and Nevis US Virgin Islands Interconnections