Ntpc Btps Electrical Project Report 2013

download Ntpc Btps Electrical Project Report 2013

of 98

Transcript of Ntpc Btps Electrical Project Report 2013

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    1/98

    BADARPUR THERMAL

    POWER STATION

    SUMMER TRAINING REPORT(03

    RDJUNE 201306

    THJULY 2013)

    BY:

    Pratinav Kanth (VT1095)

    B.Tech EEE 2nd

    year

    DTU (Delhi Technological University) formerly DCE

    http://www.google.co.in/url?sa=i&rct=j&q=ntpc+logo&source=images&cd=&cad=rja&docid=4NcK0XW6v5ghJM&tbnid=FXEuEeuMIsnzJM:&ved=0CAUQjRw&url=http://www.cpjimt.com/RecruitComp.htm&ei=6GjRUYmkC8zqrQeu3YGoAQ&bvm=bv.48572450,d.bmk&psig=AFQjCNEk6A8x7KGtasa1TXPlltZOGAap9Q&ust=1372764724529926http://answers.ind.in/f/4266-logo-dtu.htmlhttp://www.google.co.in/url?sa=i&rct=j&q=ntpc+logo&source=images&cd=&cad=rja&docid=4NcK0XW6v5ghJM&tbnid=FXEuEeuMIsnzJM:&ved=0CAUQjRw&url=http://www.cpjimt.com/RecruitComp.htm&ei=6GjRUYmkC8zqrQeu3YGoAQ&bvm=bv.48572450,d.bmk&psig=AFQjCNEk6A8x7KGtasa1TXPlltZOGAap9Q&ust=1372764724529926http://answers.ind.in/f/4266-logo-dtu.html
  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    2/98

    This is to certify that PRATINAV KANTH (2K11/EL/052), student of

    2011-2015 batch of EEE (Electrical and Electronics Engineering) in 2nd

    year of Delhi Technological University (formerly DCE) has successfully

    completed his summer training at BTPS (Badarpur Thermal Power

    Station) NTPC limited, New Delhi for 5 weeks from 03rd

    June to 06th

    July 2013.

    Training In-Charge,

    Badarpur Thermal Power Station,

    NTPC limited,

    Badarpur, New Delhi

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    3/98

    ACKNOWLEDGEMENT

    With profound respect and gratitude, I take the opportunity to convey my

    thanks to all those at my University who made this training possible.

    Here at National Thermal Power Corporation Limited, Badarpur Thermal

    Power Station, Badarpur, New Delhi I do extend my heartfelt thanks to

    Ms. Rachana Singh Bhal for providing me this opportunity to be a part of

    this esteemed organization. I am extremely grateful to Mr. G. D. Sharma,

    Superintendent of In-Plant Training at BTPS-NTPC, Badarpur for hisguidance during the whole training period. I am extremely grateful to all

    the technical staff of BTPS-NTPC for their help, co-operation and

    guidance that helped me a lot during the course of training. I have learnt a

    lot working with and under them and I will always be indebted of them for

    this value addition in me.

    Finally, I am indebted to all whosoever have contributed in this report

    work and friendly stay at Badarpur Thermal Power Station,NTPC, Badarpur, New Delhi.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    4/98

    CONTENTS

    NTPCABOUT THE COMPANY

    BTPS (Badarpur Thermal Power Station), BADARPUR

    EMD-I (Electrical Maintenance DepartmentI)

    EMD-II (Electrical Maintenance DepartmentII)

    C & I (Control and Instrumentation)

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    5/98

    NTPC (NATIONAL THERMAL

    POWER CORPORATION)

    LIMITED

    ABOUT THE COMPANY

    Indias largest power company, NTPC was set up in 1975 to acceleratepower development in India. NTPC is emerging as a diversified power

    major with presence in the entire value chain of the power generation

    business. Apart from power generation, which is the mainstay of the

    company, NTPC has already ventured into consultancy, power trading, ash

    utilisation and coal mining. NTPC ranked 341stin the 2010, Forbes

    Global 2000 ranking ofthe Worlds biggest companies.NTPC became a

    Maharatna company in May 2010, one of the only four companies to be

    awarded this status.

    The total installed capacity of the company is 39,174 MW (including JVs)

    with 16 coal based and 7 gas based stations, located across the country. In

    addition under JVs, 7 stations are coal based & another station uses

    naphtha/LNG as fuel. The company has set a target to have an installed

    power generating capacity of 128,000 MW by the year 2032. The capacity

    will have a diversified fuel mix comprising 56% coal, 16% Gas, 11%

    Nuclear and 17% Renewable Energy Sources(RES) including hydro. By

    2032, non fossil fuel based generation capacity shall make up nearly 28%

    of NTPCs portfolio.

    NTPC has been operating its plants at high efficiency levels. Although the

    company has 17.75% of the total national capacity, it contributes 27.40%

    of total power generation due to its focus on high efficiency.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    6/98

    In October 2004, NTPC launched its Initial Public Offering (IPO)

    consisting of 5.25% as fresh issue and 5.25% as offer for sale by

    Government of India. NTPC thus became a listed company in November

    2004 with the Government holding 89.5% of the equity share capital. In

    February 2010, the Shareholding of Government of India was reduced

    from 89.5% to 84.5% through Further Public Offer. The rest is held by

    Institutional Investors and the Public.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    7/98

    At NTPC,People before Plant Load Factoris the mantra that guides all

    HR related policies. NTPC has been awarded No.1, Best Workplace in

    India among large organisations and the best PSU for the year 2010, by the

    Great Places to Work Institute, India Chapter in collaboration with The

    Economic Times.

    The concept of Corporate Social Responsibility is deeply ingrained in

    NTPC's culture. Through its expansive CSR initiatives, NTPC strives to

    develop mutual trust with the communities that surround its power

    stations.

    VISION AND MISSION

    VISION

    To be the worlds largest and best power producer, powering Indias growth.

    MISSIONDevelop and provide reliable power, related products and services at

    competitive prices, integrating multiple energy sources with innovative and eco-

    friendly technologies and contribute to society.

    CORE VALUESBE COMMITTED

    B Business Ethics

    E Environmentally & Economically Sustainable

    C Customer Focus

    O Organisational & Professional PrideM Mutual Respect & Trust

    M Motivating Self & others

    I Innovation & Speed

    T Total Quality for Excellence

    T Transparent & Respected Organisation

    E Enterprising

    D Devoted

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    8/98

    STRATEGIES

    TECHNOLOGICAL INITIATIVE

    Introduction of steam generators (boilers) of the size of 800 MW.

    Integrated Gasification Combined Cycle (IGCC) Technology.

    Launch of Energy Technology Centre -A new initiative for developmentof technologies with focus on fundamental R&D.

    The company sets aside up to 0.5% of the profits for R&D.

    Roadmap developed for adopting Clean Development

    Mechanism to help get / earn Certified Emission Reduction

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    9/98

    CORPORATE SOCIAL RESPONSIBILITY

    As a responsible corporate citizen NTPC has taken up number of CSRinitiatives.

    NTPC Foundation formed to address Social issues at national level.

    NTPC has framed Corporate Social Responsibility Guidelines committingup to 0.5% of net profit annually for Community Welfare Measures on

    perennial basis.

    The welfare of project affected persons and the local population around

    NTPC projects are taken care of through well drawn Rehabilitation andResettlement policies.

    The company has also taken up distributed generation for remote ruralareas.

    PARTNERING GOVERNMENT IN VARIOUS INITIATIVES

    Consultant role to modernize and improvise several plants across thecountry.

    Disseminate technologies to other players in the sector.

    Consultant role partnership in excellence programme for improvementof PLF of 15 power stations of SEBs.

    Rural Electrification work under Rajiv Gandhi Gramin Vidyutikaran.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    10/98

    ENVIRONMENT POLICIES

    ENVIRONMENT POLICY & ENVIRONMENT MANAGEMENT

    SYSTEM

    For NTPC, the journey extends much beyond generating power. Right from its

    inception, the company had a well defined environment policy. More than just

    generating power, it is committed to sustainable growth of power.

    NTPC has evolved sound environment practices.

    NATIONAL ENVIRONMENT POLICY

    The Ministry of Environment and Forests and the Ministry of Power and NTPC

    were involved in preparing the draft Environment Policy (NEP) which was later

    approved by the Union Cabinet in May 2006.

    NTPC ENVIRONMENT POLICY

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    11/98

    Since its inception NTPC has been at the forefront of Environment

    management. In November 1995, NTPC brought out a comprehensive document

    entitled NTPC Environment Policy and Environment Management System.

    Amongst the guiding principles adopted in the document are the company's pro-

    active approach to environment, optimum utilisation of equipment, adoption olatest technologies and continual environment improvement. The policy also

    envisages efficient utilisation of resources, thereby minimising waste,

    maximising ash utilisation and ensuring a green belt all around the plant for

    maintaining ecological balance.

    ENVIRONMENT MANAGEMENT, OCCUPATIONAL HEALTH AND

    SAFETY SYSTEMS

    NTPC has actively gone for adoption of the best international practices on

    environment, occupational health and safety areas. The organisation has pursued

    the Environmental Management System (EMS) ISO 14001 and the

    Occupational Health and Safety Assessment System OHSAS 18001 at its

    different establishments. As a result of pursuing these practices, all NTPC

    power stations have been certified for ISO 14001 & OHSAS 18001 by reputed

    national and international certifying agencies.

    POLLUTION CONTROL SYSTEMS

    While deciding the appropriate technology for its projects, NTPC integrates

    many environmental provisions into the plant design. In order to ensure that

    NTPC complies with all the stipulated environment norms, following state-of-

    the-art pollution control systems / devices have been installed to control air and

    water pollution:

    Electrostatic Precipitators

    Flue Gas Stacks

    Low-NOX Burners

    Neutralisation Pits

    Coal Settling Pits / Oil Settling Pits

    DE & DS Systems Cooling Tower

    Ash Dykes & Ash Disposal Systems

    Ash Water Recycling System

    Dry Ash Extraction System (DAES)

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    12/98

    Liquid Waste Treatment Plants & Management System

    Sewage Treatment Plants & Facilities

    Environmental Institutional Set-up

    Following are the additional measures taken by NTPC in the area ofEnvironment Management:

    Environment Management During Operation Phase

    Monitoring of Environmental Parameters

    On-Line Data Base Management

    Environment Review

    Up gradation & Retrofitting of Pollution Control Systems

    Resources Conservation Waste Management

    Municipal Waste Management

    Hazardous Waste Management

    Bio-Medical Waste Management

    Land Use / Bio-diversity

    Reclamation of Abandoned Ash ponds

    Green Belts, Afforestation & Energy Plantations

    EVOLUTION

    NTPC was set up in 1975 in 100% by the ownership ofGovernment of India. In the last 30 years NTPC has grown into

    the largest power utility in India.

    In 1997, Government of India granted NTPC status of

    Navratna being one of the nine jewels of India, enhancing the

    powers to the Board of directors.

    1975

    1997

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    13/98

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    14/98

    NTPC HEADQUARTERS

    NTPC Limited is divided in 8 Headquarters

    Sr No. Headquarter City

    1 NCRHQ Delhi

    2 ER-I, HQ Patna

    3 ER-II, HQ Bhubaneshwar

    4 NRHQ Lucknow

    5 SR HQ Hyderabad

    6 WR-I HQ Mumbai

    7 Hydro HQ Delhi

    8 WR-II HQ Raipur

    NTPC PLANTS

    1. THERMAL COAL BASED

    Sr No. City State Installed Capacity

    1 Singrauli Uttar Pradesh 2,000

    2 Korba Chhattisgarh 2,600

    3 Ramagundam Andhra Pradesh 2,600

    4 Farakka West Bengal 2,100

    5 Vindhyachal Madhya Pradesh 3,260

    6 Rihand Uttar Pradesh 2,500

    7 Kahalgaon Bihar 2,340

    8 Dadri Uttar Pradesh 1,820

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    15/98

    9 Talcher Orissa 3,000

    10 Unchahar Uttar Pradesh 1,050

    11 Talcher Orissa 460

    12 Simhadri Andhra Pradesh 1,500

    13 Tanda Uttar Pradesh 440

    14 Badarpur Delhi 705

    15 Sipat Chhattisgarh 2320

    16 Sipat Chhattisgarh 1980

    17 Bongaigaon Assam 750

    18 Mouda Maharashtra 1000 (2x500 MW)

    19 Rihand Uttar Pradesh 2*500 MW

    20 Barh Bihar 3300 (5x660 MW)

    Total 31,495MW

    2. COAL BASED (Owned by JVs)

    Sr. No. Name of the JV City State Installed Capacity

    1 NSPCL Durgapur West Bengal 120

    2 NSPCL Rourkela Orissa 120

    3 NSPCL Bhilai Chhattisgarh 574

    4 NPGC Aurangabad Bihar 1980

    5 M.T.P.S Kanti Bihar 110

    6 BRBCL Nabinagar Bihar 1000

    Total 3904MW

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    16/98

    3. GAS BASED

    Sr. No. City State Installed Capacity

    1 Anta Rajasthan 419

    2 Auraiya Uttar Pradesh 652

    3 Kawas Gujarat 645

    4 Dadri Uttar Pradesh 817

    5 Jhanor Gujarat 648

    6 Kayamkulam Kerala 350

    7 Faridabad Haryana 430

    Total 3995MW

    OVERALL POWER GENERATION

    Unit 1997-98 2006-07 % of increase

    Installed Capacity MW 16,847 26,350 56.40

    Generation MUs 97,609 1, 88,674 93.29

    No. of employees No. 23,585 24,375 3.34

    Generation/employee MUs 4.14 7.74 86.95

    The table below shows the detailed operational performance of coal based stations over the years.

    OPERATIONAL PERFORMANCE OF COAL BASED NTPC STATIONS

    Unit: 97-98 98-99 99-00 00-01 01-02 02-03 03-04 04-05 05-06 06-07

    Generation BU: 106.2 109.5 118.7 130.1 133.2 140.86 149.16 159.11 170.88 188.67

    PL %: 75.20 76.60 80.39 81.8 81.1 83.6 84.4 87.51 87.54 89.43

    Availability Factor: 85.03 89.36 90.06 88.54 81.8 88.7 88.8 91.20 89.91 90.09

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    17/98

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    18/98

    POWER BURDEN

    India, as a developing country is characterized by increase in demand for

    electricity and as of moment the power plants are able to meet only about 60

    75% of this demand on an yearly average. The only way to meet therequirement completely is to achieve a rate of power capacity addition

    (implementing power projects) higher than the rate of demand addition. NTPC

    strives to achieve this and undoubtedly leads in sharing this burden on the

    country.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    19/98

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    20/98

    In 1978 the management of the plant was transferred to NTPC, from CEA. The

    performance of the plant increased significantly and steadily after take over by

    NTPC till 2006, but now the plant is facing various issues.

    Being an old plant, Badarpur Thermal Power Station (BTPS) has little

    automation. Its performance is deteriorating due to various reasons, like aging,

    poor quantity and quality of cooling water etc. It receives cooling water fromAgra Canal, which is an irrigation canal from Yamuna river. Due to rising water

    pollution, the water of Yamuna is highly polluted. This polluted water when

    goes into condenser, adversely affect life of condenser tubes, resulting in

    frequent tube leakages. This dirty water from tube leakage gets mixed into feed

    water cycle causes numerous problems, like frequent boiler tube leakages, and

    silica deposition on turbine blades.

    Apart from poor quality, the quantity of water supply is also erratic due to lackof co-ordination between NTPC and UP irrigation which manages Agra Canal.

    The quality of the coal supplied has degraded considerably. At worst times,

    there were many units tripping owing to poor quality. The poor coal quality also

    put burdens on equipment, like mills and their performance also goes down. The

    coal for the plant is fetched from far away, that makes the total fuel cost double

    of coal cost at coalmine. This factor, coupled with low efficiency due to aging

    and old design makes electricity of the plant costlier. With new splurge in no of

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    21/98

    power plant, the distribution company does not purchase full power from it.

    Presently the management is headed by Mr. N. K. Kothari, General manager.

    INSTALLED CAPACITY

    Stage Unit Number Installed Capacity (MW) Date of Commissioning Status

    First 1 95 July, 1973 Running

    First 2 95 August, 1974 Running

    First 3 95 March, 1975 Running

    Second 4 210 December, 1978 Running

    Second t 5 210 December, 1981Running

    INTRODUCTION

    A thermal power station is a power plant in which the prime-

    moveris steam driven. Water is heated, turns into steam and spins a steam

    turbine which drives an electrical generator. After it passes through the turbine,

    the steam is condensed in a condenserand recycled to where it was heated; this

    is known as a Rankine cycle. The greatest variation in the design of thermal

    power stations is due to the different fuel source. Almost

    all coal, nuclear, geothermal, solar thermal electric, and waste incineration

    plants, as well as many natural gas power plants are thermal. Natural gas is

    frequently combusted in gas turbines as well as boilers. The waste heat from a

    gas turbine can be used to raise steam, in a combined cycleplant that improves

    overall efficiency. Power plants burning coal, fuel oil, or natural gas are often

    calledfossil-fuel power plants. Some biomass-fuel thermal power plants have

    appeared also. Non-nuclear thermal power plants, particularly fossil-fuel plants,

    which do not use co-generation, are sometimes referred to as conventional

    ower plants.

    http://en.wikipedia.org/wiki/Watt#Megawatthttp://en.wikipedia.org/wiki/Power_planthttp://en.wiktionary.org/wiki/prime_moverhttp://en.wiktionary.org/wiki/prime_moverhttp://en.wikipedia.org/wiki/Steamhttp://en.wikipedia.org/wiki/Steam_turbinehttp://en.wikipedia.org/wiki/Steam_turbinehttp://en.wikipedia.org/wiki/Electrical_generatorhttp://en.wikipedia.org/wiki/Condensationhttp://en.wikipedia.org/wiki/Surface_condenserhttp://en.wikipedia.org/wiki/Rankine_cyclehttp://en.wikipedia.org/wiki/Coalhttp://en.wikipedia.org/wiki/Nuclear_powerhttp://en.wikipedia.org/wiki/Geothermal_powerhttp://en.wikipedia.org/wiki/Solar_thermal_electrichttp://en.wikipedia.org/wiki/Incinerationhttp://en.wikipedia.org/wiki/Incinerationhttp://en.wikipedia.org/wiki/Natural_gashttp://en.wikipedia.org/wiki/Flue-gas_emissions_from_fossil-fuel_combustionhttp://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Boilerhttp://en.wikipedia.org/wiki/Waste_heathttp://en.wikipedia.org/wiki/Combined_cyclehttp://en.wikipedia.org/wiki/Fuel_oilhttp://en.wikipedia.org/wiki/Fossil-fuel_power_planthttp://en.wikipedia.org/wiki/Fossil-fuel_power_planthttp://en.wikipedia.org/wiki/Fossil-fuel_power_planthttp://en.wikipedia.org/wiki/Biomasshttp://en.wikipedia.org/wiki/Co-generationhttp://en.wikipedia.org/wiki/Co-generationhttp://en.wikipedia.org/wiki/Biomasshttp://en.wikipedia.org/wiki/Fossil-fuel_power_planthttp://en.wikipedia.org/wiki/Fuel_oilhttp://en.wikipedia.org/wiki/Combined_cyclehttp://en.wikipedia.org/wiki/Waste_heathttp://en.wikipedia.org/wiki/Boilerhttp://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Flue-gas_emissions_from_fossil-fuel_combustionhttp://en.wikipedia.org/wiki/Natural_gashttp://en.wikipedia.org/wiki/Incinerationhttp://en.wikipedia.org/wiki/Incinerationhttp://en.wikipedia.org/wiki/Solar_thermal_electrichttp://en.wikipedia.org/wiki/Geothermal_powerhttp://en.wikipedia.org/wiki/Nuclear_powerhttp://en.wikipedia.org/wiki/Coalhttp://en.wikipedia.org/wiki/Rankine_cyclehttp://en.wikipedia.org/wiki/Surface_condenserhttp://en.wikipedia.org/wiki/Condensationhttp://en.wikipedia.org/wiki/Electrical_generatorhttp://en.wikipedia.org/wiki/Steam_turbinehttp://en.wikipedia.org/wiki/Steam_turbinehttp://en.wikipedia.org/wiki/Steamhttp://en.wiktionary.org/wiki/prime_moverhttp://en.wiktionary.org/wiki/prime_moverhttp://en.wikipedia.org/wiki/Power_planthttp://en.wikipedia.org/wiki/Watt#Megawatt
  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    22/98

    Commercial electric utilitypower stations are usually constructed on a large

    scale and designed for continuous operation. Electric power plants typically

    use three-phase electrical generators to produce alternating current (AC) electric

    power at a frequency of 50 Hz or 60 Hz. Large companies or institutions may

    have their own power plants to supply heating or electricity to their facilities.

    BASIC PRINCIPLE AND STEPS OF OPERATION OF THERMAL

    POWER PLANT

    The Rankine cycle is a cycle that converts heat into work. The heat is supplied

    externally to a closed loop, which usually uses water. This cycle generates about

    90% of all electric power used throughout the world. The Rankine cycle is thefundamental thermodynamic underpinning of the steam engine

    The Rankine cycle most closely describes the process by which steam-

    operated heat engines most commonly found in power generation

    plants generate power.

    http://en.wikipedia.org/wiki/Electric_utilityhttp://en.wikipedia.org/wiki/Three-phasehttp://en.wikipedia.org/wiki/Electrical_generatorhttp://en.wikipedia.org/w/index.php?title=Utilty_frequency&action=edit&redlink=1http://en.wikipedia.org/wiki/Hertzhttp://en.wikipedia.org/wiki/Heatinghttp://en.wikipedia.org/wiki/Steam_enginehttp://en.wikipedia.org/wiki/Heat_enginehttp://en.wikipedia.org/wiki/Power_stationhttp://en.wikipedia.org/wiki/Power_stationhttp://en.wikipedia.org/wiki/Power_stationhttp://en.wikipedia.org/wiki/Power_stationhttp://en.wikipedia.org/wiki/Heat_enginehttp://en.wikipedia.org/wiki/Steam_enginehttp://en.wikipedia.org/wiki/Heatinghttp://en.wikipedia.org/wiki/Hertzhttp://en.wikipedia.org/w/index.php?title=Utilty_frequency&action=edit&redlink=1http://en.wikipedia.org/wiki/Electrical_generatorhttp://en.wikipedia.org/wiki/Three-phasehttp://en.wikipedia.org/wiki/Electric_utility
  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    23/98

    The efficiency of a Rankine cycle is usually limited by the working fluid.

    Without the pressure reaching super critical levels for the working fluid, the

    temperature range the cycle can operate over is quite small: turbine entry

    temperatures are typically 565C (the creep limit of stainless steel) and

    condenser temperatures are around 30C. This gives a theoretical Carnot

    efficiency of about 63% compared with an actual efficiency of 42% for a

    modern coal-fired power station. This low turbine entry temperature (compared

    with a gas turbine) is why the Rankine cycle is often used as a bottoming cyclein combined-cycle gas turbinepower stations.

    .

    One of the principal advantages the Rankine cycle holds over others is that

    during the compression stage relatively little work is required to drive the pump,

    the working fluid being in its liquid phase at this point. By condensing the fluid,

    the work required by the pump consumes only 1% to 3% of the turbine power

    and contributes to a much higher efficiency for a real cycle. The benefit of this

    is lost somewhat due to the lower heat addition temperature. Gas turbines, forinstance, have turbine entry temperatures approaching 1500C. Nonetheless, the

    efficiencies of actual large steam cycles and large modern gas turbines are fairly

    well matched.

    http://en.wikipedia.org/wiki/Critical_point_(thermodynamics)http://en.wikipedia.org/wiki/Creep_(deformation)http://en.wikipedia.org/wiki/Carnot_efficiencyhttp://en.wikipedia.org/wiki/Carnot_efficiencyhttp://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Combined_cyclehttp://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Combined_cyclehttp://en.wikipedia.org/wiki/Gas_turbinehttp://en.wikipedia.org/wiki/Carnot_efficiencyhttp://en.wikipedia.org/wiki/Carnot_efficiencyhttp://en.wikipedia.org/wiki/Creep_(deformation)http://en.wikipedia.org/wiki/Critical_point_(thermodynamics)
  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    24/98

    FOUR PROCESS OF RANKINE CYCLE

    Process 1-2: The working fluid is pumped from low to high pressure. As the

    fluid is a liquid at this stage the pump requires little input energy.

    Process 2-3: The high pressure liquid enters a boiler where it is heated at

    constant pressure by an external heat source to become a dry saturated

    vapour. The input energy required can be easily calculated using mollier

    diagram orh-s chart orenthalpy-entropy chart also known as steam tables.

    Process 3-4: The dry saturated vapour expands through a turbine, generating

    power. This decreases the temperature and pressure of the vapour, and some

    condensation may occur. The output in this process can be easily calculated

    using the Enthalpy-entropy chart or the steam tables.

    Process 4-1: The wet vapour then enters a condenserwhere it is condensed at

    a constant temperature to become a saturated liquid.

    EQUATIONS OF RANKINE CYCLE

    In general, the efficiency of a simple Rankine cycle can be defined as:

    Each of the next four equations is easily derived from the energy and mass

    balance for a control volume. Defines the thermodynamic efficiency of

    the cycle as the ratio of net power output to heat input. As the work required by

    the pump is often around 1% of the turbine work output, it can be simplified.

    http://en.wikipedia.org/wiki/Mollier_diagramhttp://en.wikipedia.org/wiki/Mollier_diagramhttp://en.wikipedia.org/wiki/H-s_charthttp://en.wikipedia.org/wiki/Enthalpy-entropy_charthttp://en.wikipedia.org/wiki/Steam_tablehttp://en.wikipedia.org/wiki/Turbinehttp://en.wikipedia.org/wiki/Enthalpy-entropy_charthttp://en.wikipedia.org/wiki/Surface_condenserhttp://en.wikipedia.org/wiki/Boiling_pointhttp://en.wikipedia.org/wiki/Energyhttp://en.wikipedia.org/wiki/Mass_balancehttp://en.wikipedia.org/wiki/Mass_balancehttp://en.wikipedia.org/wiki/Thermodynamic_efficiencyhttp://en.wikipedia.org/wiki/Thermodynamic_efficiencyhttp://en.wikipedia.org/wiki/Mass_balancehttp://en.wikipedia.org/wiki/Mass_balancehttp://en.wikipedia.org/wiki/Energyhttp://en.wikipedia.org/wiki/Boiling_pointhttp://en.wikipedia.org/wiki/Surface_condenserhttp://en.wikipedia.org/wiki/Enthalpy-entropy_charthttp://en.wikipedia.org/wiki/Turbinehttp://en.wikipedia.org/wiki/Steam_tablehttp://en.wikipedia.org/wiki/Enthalpy-entropy_charthttp://en.wikipedia.org/wiki/H-s_charthttp://en.wikipedia.org/wiki/Mollier_diagramhttp://en.wikipedia.org/wiki/Mollier_diagram
  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    25/98

    STEPS OF OPERATION

    1. COAL SUPPLYafter haulers drop off the coal, a set of crushers and

    conveyors prepare and deliver the coal to the power plant. When the plant

    needs coal, coal hoppers crush coal to a few inches in size and conveyor

    belts bring the coal inside.

    2. COAL PULVERISERthe belts dump coal into a huge bin (pulveriser),

    which reduces the coal to a fine powder. Hot air from nearby fans blows the

    powdered coal into huge furnaces (boilers).

    3. BOILERthe boiler walls are lined with many kilometres of pipe filled

    with water. As soon as the coal enters the boiler, it instantly catches fire and

    burns with high intensity (the temperatures inside the furnace may climb to

    1,300 C). This heat quickly boils the water inside the pipes, changing it into

    steam.

    4. PRECIPITATORS AND STACKas the coal burns, it produces

    emissions (carbon dioxide, sulphur dioxide and nitrogen oxides) and ash. Thegases, together with the lighter ash (fly ash), are vented from the boiler up

    the stack. Huge air filters called electrostatic precipitators remove nearly all

    the fly ash before it is released into the atmosphere. The heavier ash (bottom

    ash) collects in the bottom of the boilers and is removed.

    5. TURBINE AND GENERATORmeanwhile, steam moves at high speed

    to the turbines, massive drums with hundreds of blades turned at an angle,

    like the blades of a fan. As jets of high-pressure steam emerge from the

    pipes, they propel the blades, causing the turbine to spin rapidly. A metal

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    26/98

    shaft connects the turbine to a generator. As the turbine turns, it causes an

    electro-magnet to turn inside coils of wire in the generator. The spinning

    magnet puts electrons in motion inside the wires, creating electricity.

    6. CONDENSORS AND COOLING WATER SYSTEMNext, the steamexits the turbines and passes over cool tubes in the condenser. The

    condensers capture the used steam and transform it back to water. The cooled

    water is then pumped back to the boiler to repeat the heating process. At the

    same time, water is piped from a reservoir or river to keep the condensers

    constantly cool. This cooling water, now warm from the heat exchange in the

    condensers, is released from the plant.

    7. WATER PURIFICATIONto reduce corrosion, plants purify water foruse in the boiler tubes. Wastewater is also treated and pumped out to holding

    ponds.

    8. ASH SYSTEMSAsh is removed from the plant and hauled to disposal

    sites or ash lagoons. Ash is also sold for use in manufacturing cement.

    9. TRANSFORMER AND TRANSMISSION LINEStransformers

    increase the voltage of the electricity generated. Transmission lines then

    carry the electricity at high voltages from the plant to substations in cities and

    towns.

    ESSENTIALS OF STEAM POWER PLANT EQUIPMENT

    Steam is an important medium of producing mechanical energy. Steam has the

    advantage that, it can be raised from water which is available in abundance it

    does not react much with the materials of the equipment of power plant and is

    stable at the temperature required in the plant Steam is used to drive steam

    engines, steam turbines etc. Steam power station is most suitable where coal is

    available in abundance. Thermal electrical power generation is one of the major

    methods. Out of total power developed in India about 60% is thermal. For a

    thermal power plant the range of pressure may vary from 10 kg/cm2 to super

    critical pressures and the range of temperature may be from 250C to650C.The average all India Plant load factor (P.L.F.) of thermal power plants

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    27/98

    in 1987-88 has be worked out to be 56.4% which is the highest P.L.F. recorded

    by thermal sector so far.

    Coal Handling

    Coal delivery equipment is one of the major components of plant cost. The

    various steps involved

    in coal handling are as follows :

    (i) Coal delivery(ii) Unloading(iii) Preparation(iv) Transfer(v) Outdoor storage(vi) Covered storage(vii) In plant handling(viii) Weighing and measuring(ix) Feeding the coal into furnace.(i) COAL DELIVERY: The coal from supply points is delivered by

    ships or boats to power stations situated near to sea or river whereas

    coal is supplied by rail or trucks to the power stations which are

    situated away from sea or river. The transportation of coal by trucks is

    used if the railway facilities are not available.

    (ii) UNLOADING: The type of equipment to be used for unloading thecoal received at the power station depends on how coal is received at

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    28/98

    the power station. If coal is delivered by trucks, there is no need of

    unloading device as the trucks may dump the coal to the outdoor

    storage. Coal is easily handled if the lift trucks with scoop are used. In

    case the coal is brought by railway wagons, ships or boats, the

    unloading may be done by car shakes, rotary car dumpers, cranes, grabbuckets and coal accelerators. Rotary car dumpers although costly are

    quite efficient for unloading closed wagons.

    (iii) PREPARATION: When the coal delivered is in the form of big lumpsand it is not of proper size, the preparation (sizing) of coal can be

    achieved by crushers, breakers, sizers driers and magnetic separators.

    (iv) TRANSFER: After preparation coal is transferred to the dead storageby means of the following system :

    BELT CONVEYOR: It consists of an endless belt moving over a pair of end

    drums (rollers). At some distance a supporting roller is provided at the centre.

    The belt is made, up of rubber or canvas. Belt conveyor is suitable for the

    transfer of coal over long distances. It is used in medium and large power plants.

    The initial cost of the system is not high and power consumption is also low.

    The inclination at which coal can be successfully elevated by belt conveyor is

    about 20. Average speed of belt conveyors varies between 200-300 r.p.m. This

    conveyor is preferred than other types.

    ADVANTAGES OF BELT CONVEYOR

    1. Its operation is smooth and clean.

    2. It requires less power as compared to other types of systems.

    3. Large quantities of coal can be discharged quickly and continuously.

    4. Material can be transported on moderates inclines.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    29/98

    COAL STORAGE

    The coal is stored by the following methods :

    (i) STOCKING THE COAL IN HEAT: The coal is piled on the ground up to

    10-12 m height. The pile top should be given a slope in the direction in which

    the rain may be drained off.

    The sealing of stored pile is desirable in order to avoid the oxidation of coal

    after packing an air tight layer of coal. Asphalt, fine coal dust and bituminous

    coating are the materials commonly used for this purpose.

    (ii) UNDER WATER STORAGE: The possibility of slow oxidation and

    spontaneous combustion can be completely eliminated by storing the coalunder water.

    Coal should be stored at a site located on solid ground, well drained, free

    Of standing water preferably on high ground not subjected to flooding.

    (iii) IN PLANT HANDLING: From the dead storage the coal is brought to

    covered storage (Live storage) (bins or bunkers). In plant handling may include

    the equipment such as belt conveyors, screw conveyors, bucket elevators etc. to

    transfer the coal.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    30/98

    STEAM GENERATOR/BOILER

    The boiler is a rectangular furnace about 50 ft (15 m) on a side and 130 ft (40

    m) tall. Its walls are made of a web of high pressure steel tubes about 2.3 inches

    (60 mm) in diameter. Pulverized coal is air-blown into the furnace from fuelnozzles at the four corners and it rapidly burns, forming a large fireball at the

    centre.

    That circulates through the boiler tubes near the boiler perimeter. The water

    circulation rate in the boiler is three to four times the throughput and is typically

    driven by pumps. As the water in the boiler circulates it absorbs heat and

    changes into steam at 700 F (370 C) and 3,200 psi (22.1MPa). It is separated

    from the water inside a drum at the top of the furnace. The saturated steam isintroduced into superheat pendant tubes that hang in the hottest part of the

    combustion gases as they exit the furnace. Here the steam is superheated to

    1,000 F (540 C) to prepare it for the turbine.

    The steam generating boiler has to produce steam at the high purity, pressure

    and temperature required for the steam turbine that drives the electrical

    generator. The generator includes the economizer, the steam drum, the chemical

    dosing equipment, and the furnace with its steam generating tubes and thesuperheater coils. Necessary safety valves are located at suitable points to avoid

    excessive boiler pressure. The air and flue gas path equipment include: forced

    draft (FD) fan, air preheater (APH), boiler furnace, induced draft (ID) fan, fly

    ash collectors (electrostatic precipitator or baghouse) and the flue gas stack.

    For units over about 210 MW capacities, redundancy of key components is

    provided by installing duplicates of the FD fan, APH, fly ash collectors and ID

    fan with isolating dampers. On some units of about 60 MW, two boilers per unit

    may instead be provided.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    31/98

    BOILER FURNACE AND STEAM DRUM

    Once water inside the boiler or steam generator, the process of adding the latent

    heat of vaporization or enthalpy is underway. The boiler transfers energy to the

    water by the chemical reaction of burning some type of fuel.

    The water enters the boiler through a section in the convection pass called the

    economizer. From the economizer it passes to the steam drum. Once the water

    enters the steam drum it goes down the down comers to the lower inlet water

    wall headers. From the inlet headers the water rises through the water walls and

    is eventually turned into steam due to the heat being generated by

    The burners located on the front and rear water walls (typically). As the water isturned into steam/vapour in the water walls, the steam/vapour once again enters

    the steam drum.

    The steam/vapour is passed through a series of steam and water separators and

    then dryers inside the steam drum. The steam separators and dryers remove the

    water droplets from the steam and the cycle through the water walls is repeated.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    32/98

    This process is known as natural circulation. The boiler furnace auxiliary

    equipment includes coal feed nozzles and igniter guns, soot blowers, water

    lancing and observation ports (in the furnace walls) for observation of the

    furnace interior. Furnace explosions due to any accumulation of combustiblegases after a tripout are avoided by flushing out such gases from the combustion

    zone before igniting the coal. The steam drum (as well as the superheater coils

    and headers) have air vents and drains needed for initial start-up. The steam

    drum has an internal device that removes moisture from the wet steam entering

    the drum from the steam generating tubes. The dry steam then flows into the

    superheater coils. Geothermal plants need no boiler since they use naturally

    occurring steam sources. Heat exchangers may be used where the geothermal

    steam is very corrosive or contains excessive suspended solids. Nuclear plantsalso boil water to raise steam, either directly passing the working steam through

    the reactor or else using an intermediate heat exchanger.

    FUEL PREPARATION SYSTEM

    In coal-fired power stations, the raw feed coal from the coal storage area is first

    crushed into small pieces and then conveyed to the coal feed hoppers at theboilers. The coal is next pulverized into a very fine powder. The pulverisers may

    be ball mills, rotating drum grinders, or other types of grinders. Some power

    stations burn fuel oil rather than coal. The oil must kept warm (above its pour

    point) in the fuel oil storage tanks to prevent the oil from congealing and

    becoming unpumpable. The oil is usually heated to about 100C before being

    pumped through the furnace fuel oil spray nozzles.

    Boilers in some power stations use processed natural gas as their main fuel.

    Other power stations may use processed natural gas as auxiliary fuel in the event

    that their main fuel supply (coal or oil) is interrupted. In such cases, separate gas

    burners are provided on the boiler furnaces.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    33/98

    FUEL FIRING AND IGNITE SYSTEM

    From the pulverized coal bin, coal is blown by hot air through the furnace coal

    burners at an angle which imparts a swirling motion to the powdered coal to

    enhance mixing of the coal powder with the incoming preheated combustion airand thus to enhance the combustion. To provide sufficient combustion

    temperature in the furnace before igniting the powdered coal, the furnace

    temperature is raised by first burning some light fuel oil or processed natural gas

    (by using auxiliary burners and igniters provide for that purpose).

    AIR PATH

    External fans are provided to give sufficient air for combustion. The forced draft

    fan takes air from the atmosphere and, first warming it in the air preheater for

    better combustion, injects it via the air nozzles on the furnace wall. The induced

    draft fan assists the FD fan by drawing out combustible gases from the furnace,

    maintaining a slightly negative pressure in the furnace to avoid backfiring

    through any opening. At the furnace outlet and before the furnace gases are

    handled by the ID fan, fine dust carried by the outlet gases is removed to avoidatmospheric pollution. This is an environmental limitation prescribed by law,

    and additionally minimizes erosion of the ID fan.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    34/98

    AUXILIARY SYSTEMS

    FLY ASH COLLECTION

    Fly ash is captured and removed from the flue gas by electrostatic precipitators

    or fabric bag filters (or sometimes both) located at the outlet of the furnace and

    before the induced draft fan. The fly ash is periodically removed from the

    collection hoppers below the precipitators or bag filters. Generally, the fly ash is

    pneumatically transported to storage silos for subsequent transport by trucks or

    railroad cars.

    BOTTOM ASH COLLECTION AND DISPOSAL

    At the bottom of every boiler, a hopper has been provided for collection of the

    bottom ash from the bottom of the furnace. This hopper is always filled with

    water to quench the ash and clinkers falling down from the furnace. Some

    arrangement is included to crush the clinkers and for conveying the crushed

    clinkers and bottom ash to a storage site.

    BOILER MAKE-UP WATER TREATMENT PLANT AND STORAGE

    Since there is continuous withdrawal of steam and continuous return of

    condensate to the boiler, losses due to blow-down and leakages have to be made

    up for so as to maintain the desired water level in the boiler steam drum. For

    this, continuous make-up water is added to the boiler water system. The

    impurities in the raw water input to the plant generally consist of calcium and

    magnesium salts which impart hardness to the water. Hardness in the make-up

    water to the boiler will form deposits on the tube water surfaces which will leadto overheating and failure of the tubes. Thus, the salts have to be removed from

    the water and that is done by a WTP plant. That we will discuss later.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    35/98

    WATER DEMINERALISING TREATMENT PLANT (DM)

    A DM plant generally consists of cation, anion and mixed bed exchangers. The

    final water from this process consists essentially of hydrogen ions andhydroxide ions which is the chemical composition of pure water. The DM

    water, being very pure, becomes highly corrosive once it absorbs oxygen from

    the atmosphere because of its very high affinity for oxygen absorption. The

    capacity of the DM plant is dictated by the type and quantity of salts in the raw

    water input. However, some storage is essential as the DM plant may be down

    for maintenance.

    For this purpose, a storage tank is installed from which DM water iscontinuously withdrawn for boiler make-up. The storage tank for DM water is

    made from materials not affected by corrosive water, such as PVC. The piping

    and valves are generally of stainless steel. Sometimes, a steam blanketing

    arrangement or stainless steel doughnut float is provided on top of the water in

    the tank to avoid contact with atmospheric air. DM water make-up is generally

    added at the steam space of the surface condenser (i.e., the vacuum side). This

    arrangement not only sprays the water but also DM water gets deaerated, with

    the dissolved gases being removed by the ejector of the condenser itself.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    36/98

    ELECTRIC GENERATOR

    The steam turbine-driven generators have auxiliary systems enabling them to

    work satisfactorily and safely. The steam turbine generator being rotating

    equipment generally has a heavy, large diameter shaft. The shaft thereforerequires not only supports but also has to be kept in position while running. To

    minimize the frictional resistance to the rotation, the shaft has a number of

    bearings. The bearing shells, in which the shaft rotates, are lined with a low

    friction material like Babbitt metal. Oil lubrication is provided to further reduce

    the friction between shaft and bearing surface and to limit the heat generated.

    BARRING GEAR OR TURNING GEAR

    Barring gear is the term used for the mechanism provided for rotation of the

    turbine generator shaft at a very low speed (about one revolution per minute)

    after unit stoppages for any reason. Once the unit is "tripped" (i.e., the turbine

    steam inlet valve is closed), the turbine starts slowing or "coasting down". When

    it stops completely, there is a tendency for the turbine shaft to deflect or bend if

    allowed to remain in one position too long. This deflection is because the heat

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    37/98

    inside the turbine casing tends to concentrate in the top half of the casing, thus

    making the top half portion of the shaft hotter than the bottom half. The shaft

    therefore warps or bends by millionths of inches, only detectable by monitoring

    eccentricity meters. But this small amount of shaft deflection would be enoughto cause vibrations and damage the entire steam turbine generator unit when it is

    restarted. Therefore, the shaft is not permitted to come to a complete stop by a

    mechanism known as "turning gear" or "barring gear" that automatically takes

    over to rotate the unit at a preset low speed. If the unit is shut down for major

    maintenance, then the barring gear must be kept in service until the temperatures

    of the casings and bearings are sufficiently low.

    CONDENSER

    The surface condenser is a shell and tube heat exchanger in which cooling water

    is circulated through the tubes. The exhaust steam from the low pressure turbine

    enters the shell where it is cooled and converted to condensate (water) by

    flowing over the tubes as shown in the adjacent diagram. Such condensers use

    steam ejectors or rotary motor-driven exhausters for continuous removal of air

    and gases from the steam side to maintain vacuum.For best efficiency, thetemperature in the condenser must be kept as low as practical in order to achieve

    the lowest possible pressure in the condensing steam. Since the condenser

    temperature can almost always be kept significantly below 100

    C where the

    vapour pressure of water is much less than atmospheric pressure, the condenser

    generally works under vacuum. Plants operating in hot climates may have to

    reduce output if their source of condenser cooling water becomes warmer;

    unfortunately this usually coincides with periods of high electrical demand forair conditioning. The condenser generally uses either circulating cooling water

    from a cooling tower to reject waste heat to the atmosphere, or once-through

    water from a river, lake or ocean.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    38/98

    FEEDWATER HEATER

    A Rankine cycle with a two-stage steam turbine and a single feedwater heater.

    In the case of a conventional steam-electric power plant utilizing a drum boiler,

    the surface condenser removes the latent heat of vaporization from the steam as

    it changes states from vapour to liquid. The heat content (btu) in the steam is

    referred to as Enthalpy. The condensate pump then pumps the condensate waterthrough a feedwater heater. The feedwater heating equipment then raises the

    temperature of the water by utilizing extraction steam from various stages of the

    turbine. Preheating the feedwater reduces the irreversibilitys involved in steam

    generation and therefore improves the thermodynamic efficiency of the system.

    This reduces plant operating costs and also helps to avoid thermal shock to the

    boiler metal when the feedwater is introduced back into the steam cycle.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    39/98

    SUPERHEATER

    As the steam is conditioned by the drying equipment inside the drum, it is piped

    from the upper drum area into an elaborate set up of tubing in different areas of

    the boiler. The areas known as superheater and reheater. The steam vapour picks

    up energy and its temperature is now superheated above the saturationtemperature. The superheated steam is then piped through the main steam lines

    to the valves of the high pressure turbine.

    DEAERATOR

    A steam generating boiler requires that the boiler feed water should be devoid of

    air and other dissolved gases, particularly corrosive ones, in order to avoidcorrosion of the metal. Generally, power stations use a deaerator to provide for

    the removal of air and other dissolved gases from the boiler feedwater. A

    deaerator typically includes a vertical, domed deaeration section mounted on top

    of a horizontal cylindrical vessel which serves as the deaerated boiler feedwater

    storage tank.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    40/98

    There are many different designs for a deaerator and the designs will vary from

    one manufacturer to another. The adjacent diagram depicts a typical

    conventional trayed deaerator. If operated properly, most deaerator

    manufacturers will guarantee that oxygen in the deaerated water will not exceed

    7 ppb by weight (0.005 cm3/L).

    AUXILIARY SYSTEMS IN ELETRIC GENERATOR

    OIL SYSTEM

    An auxiliary oil system pump is used to supply oil at the start-up of the steam

    turbine generator. It supplies the hydraulic oil system required for steam

    turbines main inlet steam stop valve, the governing control valves, the bearing

    and seal oil systems, the relevant hydraulic relays and other mechanisms. At a

    preset speed of the turbine during start-ups, a pump driven by the turbine main

    shaft takes over the functions of the auxiliary system.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    41/98

    GENERATOR HEAT DISSIPATION

    The electricity generator requires cooling to dissipate the heat that it generates.

    While small units may be cooled by air drawn through filters at the inlet, larger

    units generally require special cooling arrangements. Hydrogen gas cooling, inan oil-sealed casing, is used because it has the highest known heat transfer

    coefficient of any gas and for its low viscosity which reduces windage losses.

    This system requires special handling during start-up, with air in the chamber

    first displaced by carbon dioxide before filling with hydrogen. This ensures that

    the highly flammable hydrogen does not mix with oxygen in the air. The

    hydrogen pressure inside the casing is maintained slightly higher than

    atmospheric pressure to avoid outside air ingress. The hydrogen must be sealedagainst outward leakage where the shaft emerges from the casing. Mechanical

    seals around the shaft are installed with a very small annular gap to avoid

    rubbing between the shaft and the seals. Seal oil is used to prevent the hydrogen

    gas leakage to atmosphere. The generator also uses water cooling. Since the

    generator coils are at a potential of about 15.75kV and water is conductive, an

    insulating barrier such as Teflon is used to interconnect the water line and the

    generator high voltage windings. Demineralised water of low conductivity is

    used.

    GENERATOR HIGH VOLTAGE SYSTEM

    The generator voltage ranges from 10.5 kV in smaller units to 15.75 kV in

    larger units. The generator high voltage leads are normally large aluminium

    channels because of their high current as compared to the cables used in smaller

    machines. They are enclosed in well-grounded aluminium bus ducts and are

    supported on suitable insulators. The generator high voltage channels are

    connected to step-up transformers for connecting to a high voltage electrical

    substation (of the order of 220 kV) for further transmission by the local power

    grid. The necessary protection and metering devices are included for the high

    voltage leads. Thus, the steam turbine generator and the transformer form one

    unit. In smaller units, generating at 10.5kV, a breaker is provided to connect it

    to a common 10.5 kV bus system.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    42/98

    OTHER SYSTEMS

    MONITORING AND ALARM SYSTEM

    Most of the power plants operational controls are automatic. However, at times,

    manual intervention may be required. Thus, the plant is provided with monitors

    and alarm systems that alert the plant operators when certain operating

    parameters are seriously deviating from their normal range.

    BATTERY SUPPLIED EMERGENCY LIGHTING &COMMUNICATION

    A central battery system consisting of lead acid cell units is provided to supply

    emergency electric power, when needed, to essential items such as the power

    plant's control systems, communication systems, turbine lube oil pumps, and

    emergency lighting. This is essential for safe, damage-free shutdown of the units

    in an emergency situation.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    43/98

    EMD-I(Electrical Maintenance

    Division I)

    It is responsible for the maintenance of:

    1. HT/LT MOTORS TURBINE & BOILER SIDE

    Boiler Side Motors:

    For units 1, 2, 3

    1. ID Fans 2 in no.

    2. FD Fans 2 in no.

    3. PA Fans 2 in no.

    4. Mill Fans 3 in no.

    5. Ball mill fans 3 in no.

    6. RC feeders 3 in no.

    7. Slag Crushers 5 in no.

    8. DM Make up Pump 2 in no.

    9. PC Feeders 4 in no.

    10. Worm Conveyor 1 in no.

    11. Furnikets 4 in no.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    44/98

    For stage units 1, 2, 3

    1. I.D Fans 2 in no.

    2. F.D Fans 2 in no.3. P.A Fans 2 in no.

    4. Bowl Mills 6 in no.

    5. R.C Feeders 6 in no.

    6. Clinker Grinder 2 in no.

    7. Scrapper 2 in no.

    8. Seal Air Fans 2 in no.

    9. Hydrazine & Phosphorous Dozing 2 in no.

    2. COAL HANDLING PLANT (C.H.P)

    The old coal handling plant caters to the need of units 2,3,4,5 and 1 whereas the

    latter supplies coal to units 4 and V.O.C.H.P. supplies coal to second and third

    stages in the advent coal to usable form to (crushed) form its raw form and send

    it to bunkers, from where it is send to furnace.

    MAJOR COMPONENTS

    1. WAGON TIPPLER: Wagons from the coal yard come to the tippler and are

    emptied here. The process is performed by a slip ring motor of rating: 55 KW,

    415V, 1480 RPM. This motor turns the wagon by 135 degrees and coal falls

    directly on the conveyor through vibrators. Tippler has raised lower system

    which enables is to switch off motor when required till is wagon back to its

    original position. It is titled by weight balancing principle. The motor lowers the

    hanging balancing weights, which in turn tilts the conveyor. Estimate of theweight of the conveyor is made through hydraulic weighing machine.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    45/98

    2. CONVEYOR: There are 14 conveyors in the plant. They are numbered so

    that their function can be easily demarcated. Conveyors are made of rubber and

    more with a speed of 250-300m/min. Motors employed for conveyors has a

    capacity of 150 HP. Conveyors have a capacity of carrying coal at the rate o400 tons per hour. Few conveyors are double belt, this is done for imp.

    Conveyors so that if a belt develops any problem the process is not stalled. The

    conveyor belt has a switch after every 25-30 m on both sides so stop the belt in

    case of emergency. The conveyors are 1m wide, 3 cm thick and made of

    chemically treated vulcanized rubber. The max angular elevation of conveyor is

    designed such as never to exceed half of the angle of response and comes out to

    be around 20 degrees.

    3. ZERO SPEED SWITCH: It is safety device for motors, i.e., if belt is not

    moving and the motor is on the motor may burn. So to protect this switch

    checks the speed of the belt and switches off the motor when speed is zero.

    4. METAL SEPARATOR: As the belt takes coal to the crusher, No metal

    pieces should go along with coal. To achieve this objective, we use metal

    separators. When coal is dropped to the crusher hoots, the separator drops metal

    pieces ahead of coal. It has a magnet and a belt and the belt is moving, thepieces are thrown away. The capacity of this device is around 50 kg. .The CHP

    is supposed to transfer 600 tons of coal/hr, but practically only 300-400 tons

    coal is transfer

    5. CRUSHER: Both the plants use TATA crushers powered by BHEL. Motors.

    The crusher is of ring type and motor ratings are 400 HP, 606 KV. Crusher is

    designed to crush the pieces to 20 mm size i.e. practically considered as the

    optimum size of transfer via conveyor.

    6. ROTATORY BREAKER: OCHP employs mesh type of filters and allows

    particles of 20mm size to go directly to RC bunker, larger particles are sent to

    crushes. This leads to frequent clogging. NCHP uses a technique that crushes

    the larger of harder substance like metal impurities easing the load on the

    magnetic separators.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    46/98

    3. MILLING SYSTEM

    1. RC BUNKER: Raw coal is fed directly to these bunkers. These are 3 in no.

    per boiler. 4 & tons of coal are fed in 1 hr. the depth of bunkers is 10m.

    2. RC FEEDER: It transports pre crust coal from raw coal bunker to mill. The

    quantity of raw coal fed in mill can be controlled by speed control of aviator

    drive controlling damper and aviator change.

    3. BALL MILL: The ball mill crushes the raw coal to a certain height and then

    allows it to fall down. Due to impact of ball on coal and attraction as per the

    particles move over each other as well as over the Armor lines, the coal gets

    crushed. Large particles are broken by impact and full grinding is done byattraction. The Drying and grinding option takes place simultaneously inside the

    mill.

    4. CLASSIFIER: It is equipment which serves separation of fine pulverized

    coal particles medium from coarse medium. The pulverized coal along with the

    carrying medium strikes the impact plate through the lower part. Large particles

    are then transferred to the ball mill.

    5. CYCLONE SEPARATORS: It separates the pulverized coal from carrying

    medium. The mixture of pulverized coal vapour caters the cyclone separators.

    6. THE TURNIKET: It serves to transport pulverized coal from cyclone

    separators to pulverized coal bunker or to worm conveyors. There are 4

    turnikets per boiler.

    7. WORM CONVEYOR: It is equipment used to distribute the pulverized coal

    from bunker of one system to bunker of other system. It can be operated in bothdirections.

    8. MILL FANS: They are of 3 types:

    Six in all and are running condition all the time.

    (a) ID Fans: Located between electrostatic precipitator and chimney.

    Type-radical

    Speed-1490 rpm

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    47/98

    Rating-300 KW

    Voltage-6.6 KV

    Lubrication-by oil(b) FD Fans: Designed to handle secondary air for boiler. 2 in number and

    provide ignition of coal.

    Type-axial

    Speed-990 rpm

    Rating-440 KW

    Voltage-6.6 KV

    (c) Primary Air Fans: Designed for handling the atmospheric air up to 50

    degrees Celsius, 2 in number

    And they transfer the powered coal to burners to firing.

    Type-Double suction radial

    Rating-300 KW

    Voltage-6.6 KV

    Lubrication-by oil

    Type of operation-continuous

    9. BOWL MILL: One of the most advanced designs of coal pulverizes

    presently manufactured.

    Motor Specification

    Squirrel cage induction motor

    Rating-340 KW

    Voltage-6600KV

    Curreen-41.7A

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    48/98

    Speed-980 rpm

    Frequency-50 Hz

    No-load current-15-16 A

    4. NEW COAL HANDLING PLANT

    1. WAGON TIPPLER:

    Motor Specification

    (i) H.P 75 HP

    (ii) Voltage 415, 3 phase

    (iii) Speed 1480 rpm

    (iv) Frequency 50 Hz

    (v) Current rating 102 A

    2. COAL FEED TO PLANT:

    Feeder motor specification

    (i) Horse power 15 HP

    (ii) Voltage 415V,3 phase

    (iii) Speed 1480 rpm

    (iv) Frequency 50 Hz

    3. CONVEYORS:

    10A, 10B

    11A, 11B

    12A, 12B

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    49/98

    13A, 13B

    14A, 14B

    15A, 15B16A, 16B

    17A, 17B

    18A, 18B

    4. TRANSFER POINT 6

    5. BREAKER HOUSE

    6. REJECTION HOUSE

    7. RECLAIM HOUSE

    8. TRANSFER POINT 7

    9. CRUSHER HOUSE

    The coal arrives in wagons via railways and is tippled by the wagon tipplers intothe hoppers. If coal is oversized (>400 mm sq) then it is broken manually so that

    it passes the hopper mesh. From the hopper mesh it is taken to the transfer point

    TP6 by conveyor 12A ,12B which takes the coal to the breaker house , which

    renders the coal size to be 100mm sq. the stones which are not able to pass

    through the 100mm sq of hammer are rejected via conveyors 18A,18B to the

    rejection house . Extra coal is too sent to the reclaim hopper via conveyor 16.

    From breaker house coal is taken to the TP7 via Conveyor 13A, 13B. Conveyor

    17A, 17B also supplies coal from reclaim hopper, From TP7 coal is taken by

    conveyors 14A, 14B to crusher house whose function is to render the size o

    coal to 20mm sq. now the conveyor labourers are present whose function is to

    recognize and remove any stones moving in the conveyors . In crusher before it

    enters the crusher. After being crushed, if any metal is still present it is taken

    care of by metal detectors employed in conveyor 10.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    50/98

    5. SWITCH GEAR

    It makes or breaks an electrical circuit.

    1. ISOLATION: A device which breaks an electrical circuit when circuit isswitched on to no load. Isolation is normally used in various ways for purpose

    of isolating a certain portion when required for maintenance.

    2. SWITCHING ISOLATION: It is capable of doing things like interrupting

    transformer magnetized current, interrupting line charging current and even

    perform load transfer switching. The main application of switching isolation is

    in connection with transformer feeders as unit makes it possible to switch out

    one transformer while other is still on load.3. CIRCUIT BREAKERS: One which can make or break the circuit on load

    and even on faults is referred to as circuit breakers. This equipment is the most

    important and is heavy duty equipment mainly utilized for protection of various

    circuits and operations on load. Normally circuit breakers installed are

    accompanied by isolators

    4. LOAD BREAK SWITCHES: These are those interrupting devices which

    can make or break circuits. These are normally on same circuit, which are

    backed by circuit breakers.

    5. EARTH SWITCHES: Devices which are used normally to earth a particular

    system, to avoid any accident happening due to induction on account of live

    adjoining circuits. These equipments do not handle any appreciable current at

    all. Apart from this equipment there are a number of relays etc. which are used

    in switchgear.

    LT SWITCHGEAR

    It is classified in following ways:-

    1. MAIN SWITCH: Main switch is control equipment which controls or

    disconnects the main supply. The main switch for 3 phase supply is available for

    the range 32A, 63A, 100A, 200Q, 300A at 500V grade.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    51/98

    2. FUSES: With Avery high generating capacity of the modern power stations

    extremely heavy carnets would flow in the fault and the fuse clearing the fault

    would be required to withstand extremely heavy stress in process.

    It is used for supplying power to auxiliaries with backup fuse protection. Rotaryswitch up to 25A. With fuses, quick break, quick make and double break switch

    fuses for 63A and 100A, switch fuses for 200A, 400A, 600A, 800A and 1000A

    are used.

    3. CONTRACTORS: AC Contractors are 3 poles suitable for D.O.L Starting

    of motors and protecting the connected motors.

    4. OVERLOAD RELAY: For overload protection, thermal over relay are bestsuited for this purpose. They operate due to the action of heat generated by

    passage of current through relay element.

    5. AIR CIRCUIT BREAKERS: It is seen that use of oil in circuit breaker may

    cause a fire. So in all circuits breakers at large capacity, air at high pressure is

    used, which is maximum at the time of quick tripping of contacts. This reduces

    the possibility of sparking. The pressure may vary from 50-60 kg/cm^2 for high

    and medium capacity circuit breakers.

    HT Switch Gear

    1. MINIMUM OIL CIRCUIT BREAKER: These use oil as quenching

    medium. It comprises of simple dead tank row pursuing projection from it. The

    moving contracts are carried on an iron arm lifted by a long insulating tension

    rod and are closed simultaneously pneumatic operating mechanism by means oftensions but throw off spring to be provided at mouth of the control the main

    current within the controlled device.

    Type-HKH 12/1000c

    Rated Voltage-66 KV

    Normal Current-1250A

    Frequency-5Hz

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    52/98

    Breaking Capacity-3.4+KA Symmetrical

    3.4+KA Asymmetrical

    360 MVA Symmetrical Operating Coils-CC 220 V/DC

    FC 220V/DC

    Motor Voltage-220 V/DC

    2. AIR CIRCUIT BREAKER: In this the compressed air pressure around 15kg per cm^2 is used for extinction of arc caused by flow of air around the

    moving circuit. The breaker is closed by applying pressure at lower opening and

    opened by applying pressure at upper opening. When contacts operate, the cold

    air rushes around the movable contacts and blown the arc.

    It has the following advantages over OCB:-

    i. Fire hazard due to oil are eliminated.

    ii. Operation takes place quickly.

    iii. There is less burning of contacts since the duration is short and consistent.

    iv. Facility for frequent operation since the cooling medium is replaced

    constantly.

    Rated Voltage-6.6 KV

    Current-630 A

    Auxiliary current-220 V/DC

    3. SF6 CIRCUIT BREAKER: This type of circuit breaker is of construction to

    dead tank bulk oil to circuit breaker but the principle of current interruption is

    similar o that of air blast circuit breaker. It simply employs the arc extinguishing

    medium namely SF6. The performance of gas. When it is broken down under an

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    53/98

    electrical stress. It will quickly reconstitute itself

    Circuit Breakers-HPA

    Standard-1 EC 56 Rated Voltage-12 KV

    Insulation Level-28/75 KV

    Rated Frequency-50 Hz

    Breaking Current-40 KA

    Rated Current-1600 A

    Making Capacity-110 KA

    Rated Short Time Current 1/3s -40 A

    Mass Approximation-185 KG

    Auxiliary Voltage

    Closing Coil-220 V/DC

    Opening Coil-220 V/DC

    Motor-220 V/DC

    SF6 Pressure at 20 Degree Celsius-0.25 KG

    SF6 Gas Per pole-0.25 KG

    4. VACUUM CIRCUIT BREAKER: It works on the principle that vacuum is

    used to save the purpose of insulation and it implies that pr. Of gas at which

    breakdown voltage independent of pressure. It regards of insulation and

    strength, vacuum is superior dielectric medium and is better that all other

    medium except air and sulphur which are generally used at high pressure.

    Rated frequency-50 Hz

    Rated making Current-10 Peak KA

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    54/98

    Rated Voltage-12 KV

    Supply Voltage Closing-220 V/DC

    Rated Current-1250 A Supply Voltage Tripping-220 V/DC

    Insulation Level-IMP 75 KVP

    Rated Short Time Current-40 KA (3 SEC)

    Weight of Breaker-8 KG

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    55/98

    EMD-II(Electrical Maintenance

    Division II)

    This division is divided as follows:

    GENERATOR AND AUXILIARIES

    GENERATOR FUNDAMENTALS

    The transformation of mechanical energy into electrical energy is carried out by

    the Generator. This Chapter seeks to provide basic understanding about the

    working principles and development of Generator.

    WORKING PRINCIPLE

    The A.C. Generator or alternator is based upon the principle of electromagnetic

    induction and consists generally of a stationary part called stator and a rotating

    part called rotor. The stator housed the armature windings. The rotor houses the

    field windings. D.C. voltage is applied to the field windings through slip rings.

    When the rotor is rotated, the lines of magnetic flux (viz magnetic field) cut

    through the stator windings. This induces an electromagnetic force (e.m.f.) in

    the stator windings. The magnitude of this e.m.f. is given by the followingexpression.

    E = 4.44 /O FN volts

    0 = Strength of magnetic field in Webers.

    F = Frequency in cycles per second or Hertz.

    N = Number of turns in a coil of stator winding

    F = Frequency = Pn/120

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    56/98

    Where P = Number of poles

    n = revolutions per second of rotor.

    From the expression it is clear that for the same frequency, number of polesincreases with decrease in speed and vice versa. Therefore, low speed hydro

    turbine drives generators have 14 to 20 poles were as high speed steam turbine

    driven generators have generally 2 poles.

    GENERATOR COMPONENT

    This deals with the two main components of the Generator viz. Rotor, its

    winding & balancing and stator, its frame, core & windings.

    ROTOR

    The electrical rotor is the most difficult part of the generator to design. It

    revolves in most modern generators at a speed of 3,000 revolutions per minute.

    The problem of guaranteeing the dynamic strength and operating stability o

    such a rotor is complicated by the fact that a massive non-uniform shaft

    subjected to a multiplicity of differential stresses must operate in oil lubricated

    sleeve bearings supported by a structure mounted on foundations all of which

    possess complex dynamic be behaviour peculiar to them. It is also an

    electromagnet and to give it the necessary magnetic strength

    The windings must carry a fairly high current. The passage of the current

    through the windings generates heat but the temperature must not be allowed to

    become so high, otherwise difficulties will be experienced with insulation. To

    keep the temperature down, the cross section of the conductor could not be

    increased but this would introduce another problems. In order to make room for

    the large conductors, body and this would cause mechanical weakness. The

    problem is really to get the maximum amount of copper into the windings

    without reducing the mechanical strength. With good design

    And great care in construction this can be achieved. The rotor is a cast steel

    ingot, and it is further forged and machined. Very often a hole is bored through

    the centre of the rotor axially from one end of the other for inspection. Slots are

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    57/98

    then machined for windings and ventilation.

    ROTOR WINDING: Silver bearing copper is used for the winding with mica

    as the insulation between conductors. A mechanically strong insulator such as

    micanite is used for lining the slots. Later designs of windings for large rotorincorporate combination of hollow conductors with slots or holes arranged to

    provide for circulation of the cooling gas through the actual conductors. When

    rotating at high speed. Centrifugal force tries to lift the windings out of the slots

    and they are contained by wedges. The end rings are

    Secured to a turned recess in the rotor body, by shrinking or screwing and

    supported at the other end by fittings carried by the rotor body. The two ends o

    windings are connected to slip rings, usually made of forged steel, and mountedon insulated sleeves.

    ROTOR BALANCING: When completed the rotor must be tested for

    mechanical balance, which means that a check is made to see if it will run up to

    normal speed without vibration. To do this it would have to be uniform about its

    central axis and it is most unlikely that this will be so to the degree necessary for

    perfect balance. Arrangements are therefore made in all designs to fix adjustable

    balance weights around the circumference at each end.

    STATOR

    STATOR FRAME: The stator is the heaviest load to be transported. The major

    part of this load is the stator core. This comprises an inner frame and outer

    frame. The outer frame is a rigid fabricated structure of welded steel plates,

    within this shell is a fixed cage of girder built circular and axial ribs. The ribs

    divide the yoke in the compartments through which hydrogen flows into radial

    ducts in the stator core and circulate through the gas coolers housed in the

    frame. The inner cage is usually fixed in to the yoke by an arrangement of

    springs to dampen the double frequency vibrations inherent in 2 pole generators.

    The end shields of hydrogen cooled generators must be strong enough to carry

    shaft seals. In large generators the frame is constructed as two separate parts.

    The fabricated inner cage is inserted in the outer frame after the stator core hasbeen constructed and the winding completed.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    58/98

    STATOR CORE: The stator core is built up from a large number of 'punching"

    or sections of thin steel plates. The use of cold rolled grain-oriented steel can

    contribute to reduction in the weight of stator core for two main reasons:

    a) There is an increase in core stacking factor with improvement in laminationcold Rolling and in cold buildings techniques.

    b) The advantage can be taken of the high magnetic permeance of grain-oriented

    steels of work the stator core at comparatively high magnetic saturation without

    fear or excessive iron loss of two heavy a demand for excitation ampere turns

    from the generator rotor.

    STATOR WINDINGS: Each stator conductor must be capable of carrying therated current without overheating. The insulation must be sufficient to prevent

    leakage currents flowing between the phases to earth. Windings for the stator

    are made up from copper strips wound with insulated tape which is impregnated

    with varnish, dried under vacuum and hot pressed to form a solid insulation bar.

    These bars are then place in the stator slots and held in with wedges to form the

    complete winding which is connected together at each end of the core forming

    the end turns. These end turns are rigidly braced and packed with blocks o

    insulation material to withstand the heavy forces which might result from ashort circuit or other fault conditions. The generator terminals are usually

    arranged below the stator. On recent generators (210 MW) the windings are

    made up from copper tubes instead of strips through which water is circulated

    for cooling purposes. The water is fed to the windings through plastic tubes.

    GENERATOR COOLING SYSTEM

    The 200/210 MW Generator is provided with an efficient cooling system to

    avoid excessive heating and consequent wear and tear of its main components

    during operation. This Chapter deals with the rotor-hydrogen cooling system

    and stator water cooling system along with the shaft sealing and bearing cooling

    systems.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    59/98

    ROTOR COOLING SYSTEM

    The rotor is cooled by means of gap pick-up cooling, wherein the hydrogen gas

    in the air gap is sucked through the scoops on the rotor wedges and is directed to

    flow along the ventilating canals milled on the sides of the rotor coil, to thebottom of the slot where it takes a turn and comes out on the similar canal

    milled on the other side of the rotor coil to the hot zone of the rotor. Due to the

    rotation of the rotor, a positive suction as well as discharge is created due to

    which a certain quantity of gas flows and cools the rotor. This method of

    cooling gives uniform distribution of temperature. Also, this method has an

    inherent advantage of eliminating the deformation of copper due to varying

    temperatures.

    HYDROGEN COOLING SYSTEM

    Hydrogen is used as a cooling medium in large capacity generator in view of its

    high heat carrying capacity and low density. But in view of its forming an

    explosive mixture with oxygen, proper arrangement for filling, purging and

    maintaining its purity inside the generator have to be made. Also, in order toprevent escape of hydrogen from the generator casing, shaft sealing system is

    used to provide oil sealing. The hydrogen cooling system mainly comprises of a

    gas control stand, a drier, an liquid level indicator, hydrogen control panel, gas

    purity measuring and indicating instruments,

    The system is capable of performing the following functions :

    I. Filling in and purging of hydrogen safely without bringing in contact with

    air.

    II. Maintaining the gas pressure inside the machine at the desired value at all

    the times.

    III. Provide indication to the operator about the condition of the gas inside the

    machine i.e. its pressure, temperature and purity.

    V. Continuous circulation of gas inside the machine through a drier in order

    to remove any water vapour that may be present in it.

    V. Indication of liquid level in the generator and alarm in case of high level.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    60/98

    STATOR COOLING SYSTEM

    The stator winding is cooled by distillate.Turbo generators require water cooling arrangement over and above the usual

    hydrogen cooling arrangement. The stator winding is cooled in this system by

    circulating demineralised water (DM water) through hollow conductors. The

    cooling water used for cooling stator winding calls for the use of very high

    quality of cooling water. For this purpose DM water of proper specific

    resistance is selected. Generator is to be loaded within a very short period if the

    specific resistance of the cooling DM water goes beyond certain preset values.The system is designed to maintain a constant rate of cooling water flow to the

    stator winding at a nominal inlet water temperature of 40 degrees Celsius.

    Rating of 95 MW Generator-

    Manufacture by Bharat heavy electrical Limited (BHEL)

    Capacity - 117500 KVA

    Voltage - 10500V

    Speed - 3000 rpm

    Hydrogen - 2.5 Kg/cm2

    Power factor - 0.85 (lagging)

    Stator current - 6475 A

    Frequency - 50 Hz

    Stator winding connection - 3 phase

    Rating of 210 MW Generator-

    Manufacture by Bharat heavy electrical Limited (BHEL)

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    61/98

    Capacity - 247000 KVA

    Voltage (stator) - 15750 V

    Current (stator) - 9050 AVoltage (rotor) - 310 V

    Current (rotor) - 2600 V

    Speed - 3000 rpm

    Power factor - 0.85

    Frequency - 50 Hz

    Hydrogen - 3.5 Kg/cm2

    Stator winding connection - 3 phase star connection

    Insulation class - B

    TRANSFORMER

    A transformer is a device that transfers electrical energy from one circuit to

    another by magnetic coupling without requiring relative motion between its

    parts. It usually comprises two or more coupled windings, and in most cases, a

    core to concentrate magnetic flux. An alternating voltage applied to one winding

    creates a time-varying magnetic flux in the core, which includes a voltage in the

    other windings. Varying the relative number of turns between primary and

    secondary windings determines the ratio of the input and output voltages, thustransforming the voltage by stepping it up or down between circuits. By

    transforming electrical power to a high-voltage, _low-current form and back

    again, the transformer greatly reduces energy losses and so enables the

    economic transmission of power over long distances. It has thus shape the

    electricity supply industry, permitting generation to be located remotely from

    point of demand. All but a fraction of the worlds electrical power has passed

    through a series of transformer by the time it reaches the consumer.

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    62/98

    BASIC PRINCIPLES

    The principles of the transformer are illustrated by consideration of a

    hypothetical ideal transformer consisting of two windings of zero resistance

    around a core of negligible reluctance. A voltage applied to the primary windingcauses a current, which develops a magneto motive force (MMF) in the core.

    The current required to create the MMF is termed the magnetizing current; in

    the ideal transformer it is considered to be negligible, although its presence is

    still required to drive flux around the magnetic circuit of the core. An

    electromotive force (MMF) is induced across each winding, an effect known as

    mutual inductance. In accordance with faradays law of induction, the EMFs are

    proportional to the rate of change of flux. The primary EMF, acting as it does inopposition to the primary voltage, is sometimes termed the back EMF. Energy

    losses An ideal transformer would have no energy losses and would have no

    energy losses, and would therefore be 100% efficient. Despite the transformer

    being amongst the most efficient of electrical machines with ex the most

    efficient of electrical machines with experimental models using superconducting

    windings achieving efficiency of 99.85%, energy is dissipated in the windings,

    core, and surrounding structures. Larger transformers are generally more

    efficient, and those rated for electricity distribution usually perform better than95%. A small transformer such as plug-in power brick used for low-power

    consumer electronics may be less than 85% efficient. Transformer losses are

    attributable to several causes and may be differentiated between those originated

    in the windings, sometimes termed copper loss, and those arising from the

    magnetic circuit, sometimes termed iron loss. The losses vary with load current,

    and may furthermore be expressed as no load or full load loss, or at an

    intermediate loading. Winding resistance dominates load losses contribute toover 99% of the no-load loss can be significant, meaning that even an idle

    transformer constitutes a drain on an electrical supply, and lending impetus to

    development of low-loss transformers. Losses in the transformer arise from:

    Winding resistance current flowing through the windings causes resistive

    heating of the conductors. At higher frequencies, skin effect and proximity

    effect create additional winding resistance and losses. Hysteresis losses each

    time the magnetic field is reversed, a small amount of energy is lost due to

    hysteresis within the core. For a given core material, the loss is proportional to

  • 7/28/2019 Ntpc Btps Electrical Project Report 2013

    63/98

    the frequency, and is a function of the peak flux density to which it is subjected.

    Eddy current Ferromagnetic materials are also good conductors, and a solid core

    made from such a material also constitutes a single short-circuited turn trough

    out its entire length. Eddy currents therefore circulate with in a core in a planenormal to the flux, and are responsible for resistive heating of the core material.

    The eddy current loss is a complex function of the square of supply frequency

    and inverse square of the material thickness. Magnetostriction Magnetic flux in

    a ferromagnetic material, such as the core, causes it to physically expand and

    contract slightly with each cycle of the magnetic field, an effect known as

    magnetostriction. This produces the buzzing sound commonly associated with

    transformers, and in turn causes losses due to frictional heating in susceptible

    cores. Mechanical losses In addition to magnetostriction, the alternatingmagnetic field causes fluctuating electromagnetic field between primary and

    secondary windings. These incite vibration within nearby metal work, adding to

    the buzzing noise, and consuming a small amount of power. Stray losses

    Leakage inductance is by itself loss less, since energy supplied to its magnetic

    fields is returned to the supply with the next half-cycle. However, any leakage

    flux that intercepts nearby conductive material such as the transformers support

    structure will give rise to eddy currents and be converted to heat. Coolingsystem Large power transform