NSTXU NBI Upgrade OverviewNSTXU NBI Upgrade Overview
Timothy N. Stevenson
Princeton Plasma Physics LaboratoryNSTX Upgrade Project
Office of Science ReviewPPPL LSB 318
12/11/12 & 12/12/12
NSTX-UNSTX-U Supported by
Culham Sci CtrYork U
Chubu UFukui U
Hiroshima UHyogo UKyoto U
Kyushu UKyushu Tokai U
NIFSNiigata UU Tokyo
JAEAInst for Nucl Res, Kiev
Ioffe InstTRINITI
Chonbuk Natl UNFRI
KAISTPOSTECH
Seoul Natl UASIPP
CIEMATFOM Inst DIFFER
ENEA, FrascatiCEA, Cadarache
IPP, JülichIPP, Garching
ASCR, Czech Rep
Coll of Wm & MaryColumbia UCompXGeneral AtomicsFIUINLJohns Hopkins ULANLLLNLLodestarMITLehigh UNova PhotonicsORNLPPPLPrinceton UPurdue USNLThink Tank, Inc.UC DavisUC IrvineUCLAUCSDU ColoradoU IllinoisU MarylandU RochesterU TennesseeU TulsaU WashingtonU WisconsinX Science LLC
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
Disassemble & evaluate a TFTR BL
Decon a TFTR DT BL
Refurbish BL
Lift BL over wall – Clearance OK
Add second NBI & Services in NTC
Connect Power & Controls
Aim wider (modify VV)
Rearrange NTC to fit
Capability to run either or both
NBI Power x 2 for NSTXU
GRD Requirements for NBI System
NSTX Test Cell circa May 2012
(Last Lehman Review)
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
NSTXU NBI Job Performance
3
* Job completed
Control NBI NBI Planned Earned Actual
NSTXU NBI Project Cost (all k$) Account BAC EAC Value Value Cost CPI SPI
(through 10/31/12) Manager (BCWS) (BCWP) (ACWP)
Job: 2420 - 2nd NBI Sources* Cropper 1094 61 99 99 63 1.57 1.00
Job: 2425 - BL Relocation Atnafu 1803 1563 1067 905 699 1.29 0.85Job: 2430 - 2nd NBI Decontamination* Stevenson 2057 2070 2057 2057 2070 0.99 1.00
Job: 2440 - 2nd NBI Beamline Cropper 1979 1560 1367 1526 1116 1.37 1.12
Job: 2450 - 2nd NBI Services Atnafu 4506 4401 684 1217 1113 1.09 1.78
Job: 2460 - 2nd NBI Armor Tresemer 700 902 392 585 717 0.82 1.49
Job: 2470 - 2nd NBI Power Ramakrishnan 3335 3286 375 1031 772 1.34 2.75
Job: 2475 - 2nd NBI Controls Cropper 2611 2403 946 1450 1242 1.17 1.53
Job: 2480 - 2nd NBI/TVPS Duct Blanchard 1952 1938 656 1382 1454 0.95 2.11Job: 2485 - Vacuum Pumping System Blanchard 388 454 90 169 236 0.72 1.88Job: 2490 - NTC Equipt Relocations Perry 3535 3380 1442 1690 1440 1.17 1.17
Job: 7300 - NB2 Management Stevenson 1278 1225 616 616 563 1.09 1.00Job: 7400 - Health Physics Support Stevenson 2507 1706 1820 1854 1053 1.76 1.02
Total NBI Upgrade BL2 27745 24949 11611 14581 12538 1.16 1.26
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
NSTXU Test Cell General Arrangement
NSTXUNSTXU
BL1BL1
BL2BL2
Power cablesPower cablesTTC South WallTTC South Wall
Helium Cryo LinesHelium Cryo Lines
PlatformsPlatforms
New RacksNew Racks
HVEHVE
NBI Duct/TVPSNBI Duct/TVPS
NSTX Gallery/DARMNSTX Gallery/DARM
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
NSTXU Test Cell General Arrangement
NSTX Test Cell - 11/14/12NSTX Test Cell - 11/14/12
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
NBI Relocation in progress…
6
• Complete relocation plan includes: Box Lid- 90 inch Flange 1Q FY13- Source Platform 1Q FY13- Magnet & Stand 1Q FY13- Ion Dump 1Q FY13- Calorimeter
1Q FY13- DeWar 1Q FY13- High Voltage Enclosures (3)
o 2-3 Q FY13 SE Door conduit removed SE Door Ducts removed SE Door Duct bypasses installed SE Shield Lintel removal BL Box modifications completed BL Lift fixture designed and approved Relocation process using air castors
- Beam box and Lido Remainder moved conventionally Moving day started in September…
• Complete relocation plan includes: Box Lid- 90 inch Flange 1Q FY13- Source Platform 1Q FY13- Magnet & Stand 1Q FY13- Ion Dump 1Q FY13- Calorimeter
1Q FY13- DeWar 1Q FY13- High Voltage Enclosures (3)
o 2-3 Q FY13 SE Door conduit removed SE Door Ducts removed SE Door Duct bypasses installed SE Shield Lintel removal BL Box modifications completed BL Lift fixture designed and approved Relocation process using air castors
- Beam box and Lido Remainder moved conventionally Moving day started in September…
TFTR Test Cell & SE Door
2425
TTC 9/12/12 – a day before major relocations began
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 7
NBI Relocation required significant preparation…
SE Door conduit removed
SE Door Ducts removed
SE Door Duct bypasses installed
SE Shield Lintels removed
BL Box modifications completed for air castors
Lid Stand changes completed for air castors
Sheet steel runways installed into South High Bay (not shown here)…
SE Door conduit removed
SE Door Ducts removed
SE Door Duct bypasses installed
SE Shield Lintels removed
BL Box modifications completed for air castors
Lid Stand changes completed for air castors
Sheet steel runways installed into South High Bay (not shown here)…
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 8
NBI Lid Relocation: TTC 9/19/12 after the lid move
Component refurbishment almost completedNorth side
Component refurbishment almost completedNorth side
Cleanup of TTC begun on 102’ and South side…
Cleanup of TTC begun on 102’ and South side…
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
BL Lift fixture completed and load tested. Air castor system operational.
9
2425
Reentrant hook lift fixture design for better clearance over the NTC
South Shield Wall
Lift fixture fabrication in RESA Tech Shop
Air castor system used on BL and Lid move from TTC to NTC South High Bay through door
Show time…
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
NSTXU Test Cell Beam Box move– 9/13/12
Photo: Elle Starkman
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
NBI BL Box Relocation… TTC, South High Bay, Over the wall
11
2425
And on the vent stack…And on the vent stack…
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 12
NBI BL Lid Relocation… same as Box move but more involved 2425
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 13
NBI BL Alignment… 110, 120, 130 cm tangency radii 2425
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 14
NBI BL Alignment… completed 2425
• Install supports
• Fabricate shims
• Install spiders
• Install jacking systems
• Setup optical alignment
• Survey height from BL1 and VV
• Install shims
• Survey trajectory from metrology
• Set and reset BL
• Confirm alignment
• Verify alignment
• Install supports
• Fabricate shims
• Install spiders
• Install jacking systems
• Setup optical alignment
• Survey height from BL1 and VV
• Install shims
• Survey trajectory from metrology
• Set and reset BL
• Confirm alignment
• Verify alignment
“Bullseye…”“Bullseye…”
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 15
Calorimeter Upgrade –
• Parts fabrication completed
• Double bellows installation completed
• Double drive system needs replaced with correct parts
• External support structure work order in shop
Calorimeter Upgrade –
• Parts fabrication completed
• Double bellows installation completed
• Double drive system needs replaced with correct parts
• External support structure work order in shop
BL Refurbishment: Ion Dump and Calorimeter – in progress
Ion Dump Replacement -
• Fabrication complete
• Leakchecking complete
• Reassembly in progress
• Thermocouples complete…
Ion Dump Replacement -
• Fabrication complete
• Leakchecking complete
• Reassembly in progress
• Thermocouples complete…
2440
BL1 Calorimeter Upgrade: Double bellows double drive
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 16
90 inch flange refurbishment –
• Parts fabrication completed
• Feedthroughs fabricated, leakchecked, and installed
• OMAs reassembled and leakchecked
90 inch flange refurbishment –
• Parts fabrication completed
• Feedthroughs fabricated, leakchecked, and installed
• OMAs reassembled and leakchecked
BL Refurbishment: 90 inch flange refurbishment in progress 2440
& Bending Magnet ready for installation…& Bending Magnet ready for installation…
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
Penetrations for water systems, power cabling, and cryogenic services
17
Penetration drilling required an articulated lift with adequate reach and ratings6 power supply – 4 ft.2 cryogenic piping – 6 ft.2 water system piping (floor) – 2 ft.
Penetration drilling required an articulated lift with adequate reach and ratings6 power supply – 4 ft.2 cryogenic piping – 6 ft.2 water system piping (floor) – 2 ft.
LN Cryo line installationSupply and Vent wall lines completeAwaiting BL platform to finish Articulated lift craned into and out of NTC…
LN Cryo line installationSupply and Vent wall lines completeAwaiting BL platform to finish Articulated lift craned into and out of NTC…
24502470
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
Cryogenics Line LN and LHe piping fabrication in progress in NBI shop
18
2450
LHeManifold& South
Wall
LHeManifold& South
Wall
LNPipe
NitrogenManifold
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
Liquid Nitrogen and Vent installation in NTC completed along walls…
19
2450
• Extend existing LN System service for BL2
• Connects to BL1 now
• Build scaffold catwalk to access
• Cut into system
• Tee for BL2
• Piping supply and vent lines on North and West wall
• Connections to BL2 LN manifolds & LHe deWar
• LHe lines will connect to existing system in TFTR TC with penetrations into NTC…
• Extend existing LN System service for BL2
• Connects to BL1 now
• Build scaffold catwalk to access
• Cut into system
• Tee for BL2
• Piping supply and vent lines on North and West wall
• Connections to BL2 LN manifolds & LHe deWar
• LHe lines will connect to existing system in TFTR TC with penetrations into NTC…
NTC North Wall & Catwalk NTC North Wall & Catwalk LN Supply
Nitrogen Vent line
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 20
NBI Mechanical: Cryogenics Services & SF6 line
NTC
South Wall Cryo LHe valvesSouth Wall Cryo LHe valves
Operate either BL1 or BL2 or both…
Liquid Helium manifold fabrication in progress and ready for S wall…
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 21
NSTXU NBI Power & Controls
Routing, Penetrations, Installation Procedures revisedfor improved penetration locations. All 6 Penetrations completed.
Routing, Penetrations, Installation Procedures revisedfor improved penetration locations. All 6 Penetrations completed.
NB Switchyard
NBPC Bldg
138’
100’
Pumproom
TFTR TC
TFTR TC Basement
MER
AccelDecelFil&ArcMagPLC F/OPS F/O
All new cabling here…All new cabling here…
24702475
NSTX TC
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 22
… and high voltage triax cable successfully tested here to 150 kV.
Temporary hipot testing area in D site MG BuildingTemporary hipot testing area in D site MG Building
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 2323
Update NB N4ABC Power Supply controls to current status – done
Mimic existing NSTX BL1 Controls scheme for BL2 but move NTC racks - done
Reactivate N4 Local Control Centers, Hardwired Interlock System – in progress
Turn BL2 Plasma Current Interlocks on (chassis still in use for BL1) - OK
Add additional plasma interlock to prevent long pulse into armor- Ip & IpR - OK
Expand I/O for PLC control of BL and Services but use existing PLC – I/O received
Expand Thermocouple Scanning System to include BL2 & the ARMOR - OK
Fold BL2 into EPICS & timing pages – in progress
Update NBOS LabView Operator interface so existing staff can run 2 BLs - software in progress
No new problems - many new drawings completed
Update NB N4ABC Power Supply controls to current status – done
Mimic existing NSTX BL1 Controls scheme for BL2 but move NTC racks - done
Reactivate N4 Local Control Centers, Hardwired Interlock System – in progress
Turn BL2 Plasma Current Interlocks on (chassis still in use for BL1) - OK
Add additional plasma interlock to prevent long pulse into armor- Ip & IpR - OK
Expand I/O for PLC control of BL and Services but use existing PLC – I/O received
Expand Thermocouple Scanning System to include BL2 & the ARMOR - OK
Fold BL2 into EPICS & timing pages – in progress
Update NBOS LabView Operator interface so existing staff can run 2 BLs - software in progress
No new problems - many new drawings completed
NSTXU NBI Controls System modifications in progress…
Work Scope very similar to BL1 with updates to current status
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 24
NSTXU NBI Power Supply Controls - One Line Diagram
NBI NBPS One Line Diagram
Update electronics & control circuits completeUpdate electronics & control circuits complete 2475
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
N4ABC Local Control Center upgrade and wiring in progress
25
2475
• New NI chassis and LabView adds BL operator control purview
• Software upgrades designed and coded
• Additional NI and computing interfaces provide timing and data transfer with NSTX central computing and eliminates CAMAC
• Wiring changes in progress…
• New NI chassis and LabView adds BL operator control purview
• Software upgrades designed and coded
• Additional NI and computing interfaces provide timing and data transfer with NSTX central computing and eliminates CAMAC
• Wiring changes in progress…
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
N4ABC High Voltage Power Supply controls modifications completed
26
NBI Switchyard Disconnect Switch Remote Control Mod/Reg Grad Grid Divider and Controls chassis modifications
2475
New GGD here
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
Mod/Reg: Grad Grid Divider fabrication and assembly completed
27
2475
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
NBI Duct and Torus Vacuum Pumping System (TVPS) PROGRESS…
28
40” Torus Isolation (Gate) Valve received
24802485
TVPS valves, hardware, TMPs, and
shields on order
TVPS valves, hardware, TMPs, and
shields on orderCutting flanges…
Spool section & supports
Circular bellowsExit spool piece
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
NBI Duct Exit Spool Piece and BL TIV installed on Exit of BL…
29
24802485
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
VV Modification Bay JK weldments repaired in Tech Shop…
30
• Bay JK and port extension weldments procured and received;
HOWEVER…
• No weld prep and poor weld quality from vendor
SO…
• PPPL Tech Shop repair and rewelding completed
• Additional welds added for better integrity
• Vacuum prep and annealing heat cycle complete
• Leakchecking done…
• Bay JK and port extension weldments procured and received;
HOWEVER…
• No weld prep and poor weld quality from vendor
SO…
• PPPL Tech Shop repair and rewelding completed
• Additional welds added for better integrity
• Vacuum prep and annealing heat cycle complete
• Leakchecking done…
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
VV Bay JK Modification in progress…
31
2480
• Bay JK and port extension weldments final machining completed;
• Final metrology performed
• JK Pieces ready for installation on VV
• Lift fixture fabricated and tested
• Rectangular bellows completed; rectangular flange on order – due Jan. 13
• Full duct assembly and leacheck off line planned 2-3 Q FY 13
• Install after testing…
• Bay JK and port extension weldments final machining completed;
• Final metrology performed
• JK Pieces ready for installation on VV
• Lift fixture fabricated and tested
• Rectangular bellows completed; rectangular flange on order – due Jan. 13
• Full duct assembly and leacheck off line planned 2-3 Q FY 13
• Install after testing…Bay JK Weldment and
Port Extension
Rectangular Bellows FlangesOn order and progressing at
vendor
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012
NBI Armor fabrication done and installation in progress…
32
2460
Bay H supports need to befield fit and aligned using backing platesbefore final welding…
OKOK
• Backing plates fabricated
• Manifolds complete
• Carbon tiles machined
• Stiffener pieces fabrication done
• Braze/weld in shop
• Align/assemble/install/leakcheck
• Backing plates fabricated
• Manifolds complete
• Carbon tiles machined
• Stiffener pieces fabrication done
• Braze/weld in shop
• Align/assemble/install/leakcheck
Supports aligned using metrology and tack welded in place to determine field fit changes…
Bay H Port cover modifications for feedthroughs in progress.
Bay H
NSTX-UNSTX-U NSTX Upgrade Project - Office of Science Review Dec. 11-12, 2012 33
NBI BL2 Upgrade GRD Requirements achieved
General Arrangement maintained by Construction Manager to avoid interferences
BL refurbishment almost completed…
Tech Shop, Health Physics, and Work Control Center support has been excellent
Relocation to NTC – major BL and Lid moves completed
Services fabrication and installation has begun – water line S/C planned later this FY
Power - cables received & installation S/C planned later this FY
Controls progress has been tremendous on BL and NBPS
Floor space has been achieved by use of gallery and new elevated platforms
Duct procurements, shop work orders, and fabrication going strong
VV modifications have begun – parts are here and ready
Armor support installation has started and armor fabrication progressing well
Preoperational testing planned to begin in FY 14
Cost and schedule indices have tracked well to date – CPI and SPI greater than 1.1
Schedule still adequate for NBI activities – not critical path
NSTXU NBI project is progressing on task, under cost, on time…
NBI BL2 Upgrade GRD Requirements achieved
General Arrangement maintained by Construction Manager to avoid interferences
BL refurbishment almost completed…
Tech Shop, Health Physics, and Work Control Center support has been excellent
Relocation to NTC – major BL and Lid moves completed
Services fabrication and installation has begun – water line S/C planned later this FY
Power - cables received & installation S/C planned later this FY
Controls progress has been tremendous on BL and NBPS
Floor space has been achieved by use of gallery and new elevated platforms
Duct procurements, shop work orders, and fabrication going strong
VV modifications have begun – parts are here and ready
Armor support installation has started and armor fabrication progressing well
Preoperational testing planned to begin in FY 14
Cost and schedule indices have tracked well to date – CPI and SPI greater than 1.1
Schedule still adequate for NBI activities – not critical path
NSTXU NBI project is progressing on task, under cost, on time…
NSTXU NBI: Conclusion