NOTICE TO ALL PROPOSERS ADDENDUM NO. 1 TO THE … · guidance on what constitutes "good faith...

28
Addendum No. 1 Page 1 of 2 10119108 ANG-ECF Hangar In Kind Replacement August 10, 2020 7250 South Tucson Boulevard, Suite 300, Tucson, Arizona 85756 TEL 520-573-8100 FAX 520-573-8008 www.flytucson.com NOTICE TO ALL PROPOSERS ADDENDUM NO. 1 TO THE REQUEST FOR QUALIFICATIONS FOR TUCSON AIRPORT AUTHORITY PROJECT 10119108 ANG-ECF HANGAR IN KIND REPLACEMENT AUGUST 10, 2020 The following Addendum dated August 10, 2020 shall be made a part of the Request for Qualifications (RFQ) dated July 24, 2020 for TAA Project 10119108 – ANG-ECF Hangar In Kind Replacement. GENERAL 1. The Pre-Submittal Conference Summary dated August 5, 2020 and associated sign-in sheets are attached to this Addendum No. 1. RESPONSES TO QUESTIONS Q. Would you consider removing the requirement for 12 point Times New Roman (Item 4, end of first paragraph), page 9, and substituting a minimum font requirement of 10 with no font restrictions? 12 point fonts are extremely large and not typically used in responses to RFQs in the AEC industry. Further, firms use specific fonts to customize their presentations. I might suggest that you ask only that the fonts be minimum 10 point and readable. A. No, we will not be changing the font requirement. Q. Would you consider making the submittal electronic instead of paper given the COVID-19 pandemic? Most public agencies have converted to this method, either through email submission or a special submittal port created for this purpose. We are reluctant to have any of our employees hand-deliver our submission in person to your offices and do not anticipate the ability to complete it in time to use a logistics company such as USPS, UPS, or FedEx. A. One (1) original and six (6) copies of the SOQ should be submitted to TAA and should be clearly labeled with the project title and the Respondent’s name and addressed to the attention of Ray Valdez. SOQs can be submitted in-person, via UPS or FedEx. TAA is also requesting that one pdf be submitted electronically to DropBox (https://www.dropbox.com/request/7yv5tfryJiGqCdm8jULe). Both the hard copies and the DropBox submittal must be received by 2:00 pm, Wednesday, August 26, 2020.

Transcript of NOTICE TO ALL PROPOSERS ADDENDUM NO. 1 TO THE … · guidance on what constitutes "good faith...

  • Addendum No. 1 Page 1 of 2 10119108 ANG-ECF Hangar In Kind Replacement August 10, 2020 7250 South Tucson Boulevard, Suite 300, Tucson, Arizona 85756 TEL 520-573-8100 FAX 520-573-8008 www.flytucson.com

    NOTICE TO ALL PROPOSERS

    ADDENDUM NO. 1

    TO THE REQUEST FOR QUALIFICATIONS FOR

    TUCSON AIRPORT AUTHORITY PROJECT

    10119108 ANG-ECF HANGAR IN KIND REPLACEMENT

    AUGUST 10, 2020 The following Addendum dated August 10, 2020 shall be made a part of the Request for Qualifications (RFQ) dated July 24, 2020 for TAA Project 10119108 – ANG-ECF Hangar In Kind Replacement. GENERAL 1. The Pre-Submittal Conference Summary dated August 5, 2020 and associated sign-in sheets are attached to this Addendum No. 1.

    RESPONSES TO QUESTIONS

    Q. Would you consider removing the requirement for 12 point Times New Roman (Item 4, end of first paragraph), page 9,

    and substituting a minimum font requirement of 10 with no font restrictions? 12 point fonts are extremely large and not

    typically used in responses to RFQs in the AEC industry. Further, firms use specific fonts to customize their

    presentations. I might suggest that you ask only that the fonts be minimum 10 point and readable.

    A. No, we will not be changing the font requirement.

    Q. Would you consider making the submittal electronic instead of paper given the COVID-19 pandemic? Most public agencies have converted to this method, either through email submission or a special submittal port created for this purpose. We are reluctant to have any of our employees hand-deliver our submission in person to your offices and do not anticipate the ability to complete it in time to use a logistics company such as USPS, UPS, or FedEx.

    A. One (1) original and six (6) copies of the SOQ should be submitted to TAA and should be clearly labeled with the project title and the Respondent’s name and addressed to the attention of Ray Valdez. SOQs can be submitted in-person, via UPS or FedEx. TAA is also requesting that one pdf be submitted electronically to DropBox (https://www.dropbox.com/request/7yv5tfryJiGqCdm8jULe). Both the hard copies and the DropBox submittal must be received by 2:00 pm, Wednesday, August 26, 2020.

    https://www.dropbox.com/request/7yv5tfryJiGqCdm8jULe

  • Addendum No. 1 Page 2 of 2 10119108 ANG-ECF Hangar In Kind Replacement August 10, 2020 7250 South Tucson Boulevard, Suite 300, Tucson, Arizona 85756 TEL 520-573-8100 FAX 520-573-8008 www.flytucson.com

    Q. Would you consider making the requested OSHA 300A forms and the Workers Compensation Experience Modifier Rate (EMR) forms not count towards the 20 page limit? You are requesting 5 years of OSHA 300As, which are minimum 1 page each, 3 pages each for the entire report.

    A. The OSHA 300A forms and the Workers Compensation Experience Modifier Rate (EMR) forms are not counted towards the 20 page limit. Please attach them as an Exhibit / Appendix.

    Q. You also request submitters to provide a proposed project schedule (Item A-2-e) and a discussion of major issues our team has identified on this project and how we intend to address those issues (Item D-2). The RFQ does not describe or list TAA’s desired schedule, start or preferred completion date, nor any issues that TAA anticipates on this project. Will these be discussed in the pre-submittal conference or otherwise provided to proposers to that we can answer these questions mindfully?

    A. TAA plans to award the contract approximately November 1, 2020 and desires to have the project completed by November 1, 2021. With plans completed in approximately 1-2 months, please provide your proposed schedule. Also include major issues you identify on this project and how your firm would address those issues.

    Q. Item E states that the submitter’s Quality Control Plan must be provided to TAA for approval and acceptance prior to beginning any work. There is no request here for a summary of that plan. Is that the intent of this section? As it is, it is a statement not a question or request. Please advise as to whether a response is required to Item E.

    A. Submitters shall submit their recommended Quality Control Plan. This plan may be negotiated with the successful contractor.

    Q. Item H is also a statement regarding not providing Cost or Price information. Can we assume there is no

    response required for Item H?

    A. There is no response required for Item H. Cost or Price information should not be submitted with the SOQ.

    End of Addendum #1

  • Pre-Submittal Meeting 1 10119108 ANG-ECF Hangar In Kind Replacement August 5, 2020

    PRE-SUBMITTAL CONFERENCE SUMMARY Project No. /Name: 10119108 ANG-ECF Hangar in Kind Replacement Date: August 5, 2020 Time: 10:00 AM Location: Tucson Airport Authority (TAA) Administration via WebEx Funding: TAA Procurement Officer: Ray Valdez Project Director: David Moore SIGN IN AND INTRODUCTIONS 1. See attached Sign-in Sheet for attendees. 2. Ray Valdez welcomed all attendees and made brief introductions. He indicated that the minutes of the pre-submittal conference will be distributed to all meeting attendees and RFQ holders of record. Further addenda, if any, will be distributed to pre-submittal meeting attendees and firms on the RFQ Holders List. GENERAL INFORMATION

    1. TAA intends to award this contract by November 1, 2020 and desires to complete project on/before November 1, 2021. 2. The estimated construction cost of the project is $8,000,000.00.

    3. The project will be funded by TAA funds. 4. The selected Respondent will provide pre-construction services, including constructability and phasing review; conceptual cost estimating services, scheduling, value engineering, and other preconstruction services, and (ii) potential construction services as the Construction Manager at Risk 5. TAA shall not be held responsible for any oral instructions. Any changes to this RFQ will be in the form of an addendum, which will be furnished to all registered RFQ holders and pre-submittal meeting attendees. 6. This RFQ does not obligate TAA to award the contract to any firm nor to pay any cost incurred in the proposal process or in the preparation of Statements of Qualifications (SOQs) submitted in response to this RFQ. Firms may be required to attend interviews in Tucson at a time and place to be announced. Expenses associated with such travel will be solely the responsibility of the firms. TAA reserves the right to reject any and all SOQs or to accept any firm which is deemed to be advantageous to the public and TAA. 7. The SOQ and other requested information must be completed, in its entirety, to the best of Respondent’s ability and the Respondent must represent and warrant that all information contained therein is true and correct to the best of Respondent’s knowledge.

    8. No representative or agent of the Respondent may contact any member of the staff or Selection Committee, any member or director of TAA or any other agent or consultant of TAA, either directly or indirectly.

  • Pre-Submittal Meeting 2 10119108 ANG-ECF Hangar In Kind Replacement August 5, 2020

    Questions related to the RFQ or SOQ process may be directed in writing to Ray Valdez by email at [email protected]. Any communication, or attempted communication, with any person other than Ray Valdez shall, in the sole discretion of TAA, be grounds for disqualification of the firm. 9. Until an award and execution of a contract by TAA, only the name of each Respondent on the short list may be made available to the public. All other information received by TAA in response to this RFQ or contained in the SOQs shall be confidential. The SOQs shall be open to public inspection after the contract is awarded and executed by TAA. To the extent the firm designates and TAA concurs, trade secrets and other proprietary data contained in the firm’s SOQ will be kept confidential. 10. Any questions that the Respondents may have about the RFQ or the project should be emailed to Ray Valdez by no later than 2:00 pm on Monday, August 17th. TAA will issue the minutes of the pre-submittal conference and written responses to any questions received to all RFQ holders by email and/or facsimile on or before Monday, August 10th. 11. DBE. It is the policy of TAA to ensure that Disadvantaged Business Enterprise firms (“DBEs”) have a fair and equal opportunity to participate in TAA's contracts. Specifically, it is the goal of TAA to ensure that, to the extent reasonably possible and consistent with other legal requirements that: (a) DBEs are not discriminated against in the award and administration of TAA's contracts; (b) a level playing field is created on which DBEs can compete fairly for TAA's contracts; and (c) any barriers to the participation of DBEs in TAA's contracts are removed. If a proposer or sub consultant of the proposer are certified as DBE, the work performed by both shall be counted towards meeting the aspirational goal. Any work performed by a non-DBE proposer or subconsultant shall not. TAA has set an aspirational 7% (7% of the dollar value of the contract) DBE participation goal for this contract. The firm must make a "good faith effort" to meet the stated aspirational participation goal. The firm should consult Appendix A of the DBE Regulations for guidance on what constitutes "good faith efforts.” As a matter of responsibility, firms must complete and submit the “Statement of Proposed DBE Utilization” in the form provided, with its submittal, including evidence of good faith effort related to TAA’s goal if the 7% aspirational goal is not met in part or in full. Firms and firms' subcontractor/subconsultant who are submitting as DBEs must be certified DBEs in Arizona in good standing prior to the date submittals are due. TAA recognizes current DBE certifications by the ADOT, City of Phoenix, and City of Tucson. For information regarding DBE firms recognized by TAA, or if you have any questions about TAA's DBE Program, please contact Veronica Ruiz-Ronquillo, TAA DBE Liaison Officer, at 520-573-8100. The successful proposer will be required to submit the following information: (1) the names and addresses of DBE firms that will participate in the contract; (2) a description of the work that each DBE firm will perform; (3) the percentage amount of participation of each DBE firm participating; (4) written documentation of the bidder/proposer’s commitment to use a DBE subcontractor whose participation it submits to meet the aspirational contract goal; and (5) if the proposer cannot meet the aspirational DBE goal in part or in full, evidence of good faith effort undertaken by the proposer as described in Appendix A to 49 CFR Part 26. To count toward meeting a goal, each DBE firm must be certified in a NAICS code applicable to the kind of work the firm would perform on the contract. As a condition of the agreement between the parties, the firm awarded the contract will be required to report DBE participation efforts listing (1) all certified DBE subconsultants who will be working on the Project, including work performed by firm’s own forces if firm is a DBE and (2) the estimated amount of dollars that will be paid to any DBE subconsultant providing services. This information will be reported on a

    mailto:[email protected]

  • Pre-Submittal Meeting 3 10119108 ANG-ECF Hangar In Kind Replacement August 5, 2020

    form to be provided by TAA. In addition, firm must provide written confirmation from each DBE of its participation in the firm’s work. Firm will be required to track all payments to DBEs working on the Project. At the completion of the Project, firm will be required to complete and submit a final certification of payments to DBE firms on a form to be provided by TAA. PROPOSAL REQUIREMENTS 1. Ray Valdez reminded the firms to carefully review the SOQ requirements described in Section IV on page 6. 2. Respondents should review the insurance requirements on page 5 of the RFQ to confirm that they can comply. 3. Respondents are to provide complete OSHA 300A Summary of Work Related Injuries and Illnesses along with your Workers Compensation Experience Modifier Rate. These documents will not be counted towards the 20 page limit. SOQs submitted without these required documents will not be considered. 4. Client references provided in the SOQs should not include TAA. 5. Failure on the part of a Respondent to provide any portion of the required documentation may be cause for rejection of the SOQ. In the event of any conflict between any of the SOQ documents, resolution thereof shall be at TAA's sole discretion. 6. SOQs are due on or before 2:00 pm local Tucson time on Wednesday, August 26, 2020 at TAA’s Administration Building, and must be time stamped by the receptionist to record TAA’s receipt of the SOQ. SOQs submitted after that time may not be accepted. 7. One (1) original and six (6) copies of the SOQ should be submitted to TAA and should be clearly labeled with the project title and the Respondent’s name and addressed to the attention of Ray Valdez. SOQs can be submitted in-person, via UPS or FedEx. TAA is also requesting that one pdf be submitted electronically to DropBox (https://www.dropbox.com/request/7yv5tfryJiGqCdm8jULe). Both the hard copies and the DropBox submittal must be received by 2:00 pm, Wednesday, August 26, 2020. 8. SOQs may be withdrawn either personally or by written request any time before the scheduled date and time of receipt. SELECTION PROCESS (insert method)

    1. TAA is conducting a selection process in accordance with the requirements of Title 34 A.R.S. to select one firm to provide CMAR/construction services for the project listed in the RFQ. 2. SOQs from interested firms will be evaluated by an in-house Selection Committee, which will rank the SOQs based on qualifications only and select three to five Respondents to be short-listed. All Respondents will be notified as to which firms have been selected for the short-list. 3. The short-listed Respondents will be interviewed by the Selection Committee in person or via WebEx.

    https://www.dropbox.com/request/7yv5tfryJiGqCdm8jULe

  • Pre-Submittal Meeting 4 10119108 ANG-ECF Hangar In Kind Replacement August 5, 2020

    4. The Selection Committee will prepare a final ranking of the short-listed firms, which shall be submitted to the TAA Vice President of Planning & Engineering Department for final review and selection of the highest ranked Respondent. SCOPE OF WORK

    1. Project Director provided a briefing of the project.

    DISCUSSION:

    The floor was opened to questions and answers and discussion followed. The following questions were presented: Q. When are you anticipating that construction will begin? A. Construction shall begin upon completion of the design. Q. Is wet fire sprinkler system water or foam? A. The fire sprinkler system shall be water. Q. Can the bridging documents be posted with the Addendum A. We are providing the attached bridging documents for informational purposes only. Specifics regarding the design will be a collaboration between the awarded firm and the design professional. Proposers should not be overly concerned about what is contained in the bridging documents and should provide TAA with their technical approach to a CMAR construction project Q. Is the existing Aero Hanger to be demolished and/or is the EDF currently built or will be built as part of this project? A. The existing Hanger demolition is not in the scope of this project. Q. B.2. Location of principal office - is this corporate, district or local permanent office we will use? A. Please include the principal office that will be responsible for this project. Q. Is the old hangar demolition part of this scope? A. No, the demolition of the existing hanger will not be part of this scope. Q. Does the $8M include preconstruction costs, or is that a separate budget?

  • Pre-Submittal Meeting 5 10119108 ANG-ECF Hangar In Kind Replacement August 5, 2020

    A. The estimate of $8M does include the pre-construction costs. Q. B.2. % staff local - is local AZ, County or Tucson? A. Firms (including staff) do not need to be located within a certain geographical area; DBE Certification pertains to a firm being certified in the State of Arizona as a DBE certified firm. Q. What is the expectation for filling out the DBE form at this time? Since the subs need to be procured under ARS statute and subs selected as a team (while meeting the DBE goal) it would be unproductive to fallout the DBE utilization form at this time. We can commit to a good faith effort to meet the goal. A. The DBE forms should be completed and submitted for anticipated pre-construction costs only. The construction DBE form shall be completed at a later date. Q. Is the wet pipe system a High Expansion foam system? A. It is a wet pipe system only, not a high expansion foam system. Q. Please clarify the Statement "Contract maximum total of five (5) years depending upon funding availability and program needs." Will this be phased or extend for that long of a period of time? A. TAA intends to begin construction as soon as possible after the design is completed, based on funding. The contract can extend up to five (5) years if funding is not readily available. Q. Do WBE's count toward DBE goal? A. No, sole WBE firms (not DBE firms) will not count towards the goal. Q. Item E states that the submitter’s Quality Control Plan must be provided to TAA for approval and acceptance prior to beginning any work. There is no request here for a summary of that plan. Is that the intent of this section? A. Submitters shall submit their recommended Quality Control Plan. This plan may be negotiated with the successful contractor. Q. Is there any aircraft parking apron associated with this project? A. Yes, there is an aircraft parking apron in front of the hangar area.

  • Pre-Submittal Meeting 6 10119108 ANG-ECF Hangar In Kind Replacement August 5, 2020

    Q. What information do you want to see in our SOQ about #E, the Quality Control Plan? A. We want to see what your recommendations are for a quality control plan. Please submit your recommendations. Q. Item H - No Price or Cost Information - Just to confirm, no dollar amounts are expected in the SOQ so this item does not get addressed in the proposal? A. Correct, contractors shall not submit price or cost information with their submittal. Q. Will you be answering questions that had been sent in via e-mail before today’s call? A. Yes, all other questions submitted via email have been listed and answered in Addendum #1. Attendees were reminded that the last day for questions was Monday, August 17, 2020 by 2:00 pm and the SOQ due date and time is Wednesday, August 26th, 2020 by 2:00 pm. The conference adjourned at 10:38 a.m. Attendees were invited to conduct a site visit on their own. The above is intended to be a summary of the proceedings as recalled by Ray Valdez. The proceedings were tape-recorded and the tape is on file in the TAA’s Planning & Engineering Department. cc: File A

  • Tucson Airport Authority

    7250 S. Tucson Blvd, Ste. 300

    Tucson, AZ 85756

    (520) 573-8100

    Date: August 5, 2020 Time: 10:00 a.m Location:

    PHONE

    Ray Valdez TAA (520) 573-4871 [email protected]

    David Moore TAA (520) 573-5116 [email protected]

    Veronica Ruiz-Ronquillo TAA (520) 573-4892 [email protected]

    Mike Smejkal TAA (520) 573-4856 [email protected]

    Kathy Myers TAA (520) 573-4823 [email protected]

    Mark Koester Stantec Consulting [email protected]

    Jessica Bateman RYTAN Construction [email protected]

    Leslie West AE Marketing Inc. [email protected]

    Andy Platt Agate Construction [email protected]

    Dan Smith AvAirPros [email protected]

    Riley Rasmussen Barker Contracting [email protected]

    Jennifer Mohs BFL [email protected]

    Dena Curnow BFL Construction [email protected]

    Andrew Krogman BlueScope Construction [email protected]

    NAME ORGANIZATION EMAIL ADDRESS

    ATTENDANCE SIGN IN SHEET

    10119108 ANG-ECF Hangar in Kind Replacement

    Pre-Submittal Conference - WebEx

    Tucson Airport Authority

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • Tucson Airport Authority

    7250 S. Tucson Blvd, Ste. 300

    Tucson, AZ 85756

    (520) 573-8100

    Date: August 5, 2020 Time: 10:00 a.m Location:

    PHONENAME ORGANIZATION EMAIL ADDRESS

    ATTENDANCE SIGN IN SHEET

    10119108 ANG-ECF Hangar in Kind Replacement

    Pre-Submittal Conference - WebEx

    Tucson Airport Authority

    Jerry Morgan Brasfield & Gorrie [email protected]

    John Hall Brasfield & Gorrie [email protected]

    Tim Kozain Brasfield & Gorrie [email protected]

    Andrew Pierson Centrex Constuction [email protected]

    Kevin Riley Darling Geomatics (520) 298-2725 [email protected]

    David Landis DPR Construction [email protected]

    Matthew Thrower DPR Construction [email protected]

    Kenny Shepherd Haydon Building Corp (602) 339-0675 [email protected]

    Stephanie Tuttle Haydon Building Corp [email protected]

    Bill Sanders Hensel Phelps [email protected]

    Brian Earnst Hensel Phelps [email protected]

    Jeff Stoddard Hensel Phelps [email protected]

    Rosemary Middleton Hensel Phelps [email protected]

    Pete McGhee IMEG [email protected]

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • Tucson Airport Authority

    7250 S. Tucson Blvd, Ste. 300

    Tucson, AZ 85756

    (520) 573-8100

    Date: August 5, 2020 Time: 10:00 a.m Location:

    PHONENAME ORGANIZATION EMAIL ADDRESS

    ATTENDANCE SIGN IN SHEET

    10119108 ANG-ECF Hangar in Kind Replacement

    Pre-Submittal Conference - WebEx

    Tucson Airport Authority

    Michael Hunter JE Dunn [email protected]

    Bonnie Wayland Johnson Carlier [email protected]

    Kevin Kwake Johnson Carlier [email protected]

    Laura Shivers Johnson Carlier [email protected]

    Rhonda Zayas Johnson Carlier [email protected]

    Michele Fulkerson Kappcon Inc [email protected]

    Joseph Beeman Lawrence Construction [email protected]

    Shannon Murray Lloyd Construction [email protected]

    Matthew Seery MW Morrissey Construction [email protected]

    LaMonte Forgays Q&D Construction [email protected]

    Josh Marks Rider Levett Bucknall [email protected]

    Walter Hoge Rio West Inc. [email protected]

    Brad Hoge Rio West Inc. [email protected]

    Brent Gettinger Steadfast [email protected]

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • Tucson Airport Authority

    7250 S. Tucson Blvd, Ste. 300

    Tucson, AZ 85756

    (520) 573-8100

    Date: August 5, 2020 Time: 10:00 a.m Location:

    PHONENAME ORGANIZATION EMAIL ADDRESS

    ATTENDANCE SIGN IN SHEET

    10119108 ANG-ECF Hangar in Kind Replacement

    Pre-Submittal Conference - WebEx

    Tucson Airport Authority

    Elizabeth Tipton Steadfast [email protected]

    Jason Lopez Sturgeon Electric [email protected]

    David Ollanik Sundt Construction [email protected]

    Ian McDowell Sundt Construction [email protected]

    Mike Hill Sundt Construction [email protected]

    Samantha Hopkins Sundt Construction [email protected]

    Anthony Jeffers

    Christian

    Hal White

    Ivana Buljubasic

    Jake Parduhn

    Joe Malisewski

    Laura Nichols

    Marcy Irwin

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]

  • Stantec Project Number:

    Client Project Number: 10119108

    The professional's seal on the cover sheet represents that the information on the cover sheet is accurate in designer's professional opinion but does not assume professional responsibility for documents sealed by others that are referenced on the cover sheet. All professionals sealing drawings as a part of the design are professionally responsible for their own sealed documents.

    BRIDGING DOCUMENTS

    10/25/2019

    ANG-ECF HANGAR REPLACEMENT

    181710627

  • GRAPHIC LEGEND

    LINETYPE LEGEND

    MATERIAL LEGEND

    COLUMN GRID LINE

    EXISTING COLUMN GRID LINE

    ELEVATIONELEVATION NUMBERSHEET WHERE IT IS SHOWN

    EXTERIOR

    BUILDING SECTIONSECTION NUMBERSHEET WHERE IT IS SHOWN

    WALL SECTIONSECTION NUMBERSHEET WHERE IT IS SHOWN

    DETAIL INDICATOR FOR SMALL CONDITIONSDETAIL NUMBERSHEET WHERE IT IS SHOWN

    DETAIL CALLOUTDETAIL NUMBERSHEET WHERE IT IS SHOWN

    PLAN NORTH

    NORTH ARROW

    1i

    1t

    101

    A1

    A-101

    A1

    A-101

    A1

    A-101

    A1

    A-101

    A1

    A-101

    A1

    A-101

    A1

    A-101

    INTERIOR

    ROOM NAME

    DOOR NUMBER

    PARTION/WALL TYPE

    FURNITURE, MILLWORK, FIXTURE OR ACCESSORY

    KEYNOTE

    1t WINDOW/LOUVER TYPE

    1 REVISION

    XX

    XX

    ROOM NAMEA101

    ?

    STACKED PARTITION/ WALL TYPE

    UPPER PARTITION

    LOWER PARTITION

    AXXXMXXX

    CENTER LINE

    PROPERTY LINE

    LIMIT OF CONTRACT

    DEMOLITION

    HIDDEN

    MATCHLINEMATCHLINE

    SEE XX/X-XXX

    CONCRETE

    CONCRETE MASONRY UNIT

    ALUMINUM

    BATT INSULATION

    CEMENTITIOUS FIREPROOFING

    CONCRETE, STUCCO, PLASTER, OR GYPSUM BOARD (ELEVATION)

    SOIL

    GLASS

    FINISH WOOD (SECTION / END)

    POROUS FILL (GRAVEL) OR ROOF BALLAST

    ROUGH WOOD FRAMING AND BLOCKING (SECTION / END)

    PLYWOOD

    RIGID OR FOAM INSULATION

    STEEL

    The

    Con

    tract

    or sh

    all v

    erify

    and

    be

    resp

    onsib

    le fo

    r all d

    imen

    sions

    . DO

    NO

    T sca

    le th

    e dr

    awin

    g -a

    ny e

    rrors

    or o

    miss

    ions

    shal

    l be

    repo

    rted

    to S

    tant

    ec w

    ithou

    t del

    ay.

    The

    Cop

    yrig

    hts t

    o al

    l des

    igns

    and

    dra

    win

    gs a

    re th

    e pr

    oper

    ty o

    f Sta

    ntec

    . Rep

    rodu

    ctio

    n or

    use

    for a

    ny p

    urpo

    se o

    ther

    than

    that

    aut

    horiz

    ed b

    y St

    ante

    c is

    forb

    idde

    n.

    ORIGINAL SHEET - ARCH D

    Drawing No.Revision:

    Permit/Seal

    File Name: N/A

    Title

    PRELIMINARY

    NOT FOR

    CONSTRUCTIONNot for permits, pricing or other official purposes. This document has not been

    completed or checked and is for general information or comment only.

    Revi

    sion

    ByAp

    pdYY

    YY.M

    M.D

    DIss

    ued

    ByAp

    pdYY

    YY.M

    M.D

    D

    1

    A

    2 3 4 5

    B

    C

    D

    YYYY.MM.DDDsgn. Chkd.Dwn.

    TUC

    SON

    INTE

    RNAT

    IONA

    L AIR

    PORT

    Project No.:

    Con

    sulta

    nt

    Scale:

    1011

    9108

    ANG

    -EC

    F HA

    NGAR

    REP

    LAC

    EMEN

    T (B

    RIDG

    ING

    DO

    CUE

    MEN

    TS)

    181710627

    10/2

    4 /20

    19 4

    :33:

    5 2 P

    M

    As indicated

    G-001

    100%

    BRI

    DG

    ING

    DO

    CUM

    ENTS

    Author CheckerDesigner 2019.10.25

    SHEET INDEX &GENERAL NOTES

    Stan

    tec

    Arch

    itect

    ure

    Inc.

    1050

    17t

    h St

    reet

    Sui

    te A

    200

    Den

    ver,

    CO

    802

    65-2

    016

    Tel:

    (303

    ) 295

    -171

    7 •

    ww

    w.st

    ante

    c.co

    m

    GENERAL NOTES

    1 THE FOLLOWING GENERAL NOTES APPLY TO THE ENTIRE SET OF DRAWINGS AND ARE NOTSPECIFIC TO ANY ONE DISCIPLINE.

    2 IT IS THE CONTRACTORS RESPONSIBILITY TO REVIEW AND COORDINATE THE WORK OFALL SUB-CONTRACTORS, TRADES AND SUPPLIERS WITH REQUIREMENTS OF THECONTRACT BEFORE COMMENCING CONSTRUCTION, AND ASSURE THAT ALL PARTIES AREAWARE OF ALL REQUIREMENTS, REGARDLESS OF WHERE THE REQUIREMENTS OCCUR INTHE CONTRACT DOCUMENTS, WHICH MIGHT AFFECT THE WORK OF THAT PARTY.

    3 THE WORK DESCRIBED BY THE DRAWINGS OF ANY ONE DISCIPLINE MAY BE AFFECTED BYTHE WORK DESCRIBED ON DRAWINGS OF ANOTHER DISCIPLINE AND MAY REQUIRE CROSSREFERENCE. PARTIAL SETS OF DRAWINGS ARE INCOMPLETE AND SHOULD NOT BEDISTRIBUTED OR UTILIZED BY THE CONTRACTOR.

    4 THE DRAWINGS AND SPECIFICATIONS ESTABLISH MINIMUM REQUIREMENTS FOR THEDESIGN AND CONSTRUCTION OF THE PROJECT.

    5 ARCHITECT IS NOT RESPONSIBLE FOR ACCURACY OF EXISTING CONDITIONS SHOWN INTHESE DOCUMENTS. GC SHALL CONTACT ARCHITECT IMMEDIATELY IF ANYDISCREPANCIES OCCUR IN THE FIELD.

    6 THE CONTRACTOR SHALL IDENTIFY AND NOTIFY IN WRITING TO THE ARCHITECTCONFLICTS BETWEEN THE WORK OF DIFFERENT PARTIES, AND DISCREPANCIES BETWEENTHE DOCUMENTS AND THE ACTUAL CONDITIONS AT THE EARLIEST POSSIBLE DATE SO ASTO ALLOW REASONABLE AND ADEQUATE TIME FOR THE CONFLICT TO BE RESOLVEDWITHOUT DELAYING THE WORK. ALL DEVIATIONS FROM THAT WHICH IS REQUIRED BY THECONTRACT DOCUMENTS MUST BE APPROVED IN ADVANCE BY THE ARCHITECT ANDOWNER PRIOR TO PROCEEDING.

    7 THE GENERAL NOTES, SYMBOLS AND DEFINITIONS APPLICABLE TO EACH DISCIPLINE CANBE FOUND AT THE FRONT OF EACH DISCIPLINE’S SET OF DRAWINGS AND IS LISTED ASPART OF THE OVERALL PROJECT INDEX OF DRAWINGS.

    8 BASIC FIRE PROTECTION AND EXITING CONCEPTS ARE ILLUSTRATED BY THE LIFE SAFETYAND CODE PLANS ON THE ‘G’ SERIES SHEETS. THE CONTRACTOR SHALL BE FAMILIAR WITHREQUIREMENTS AND CONSTRUCTION SHALL BE IN COMPLIANCE WITH REFERENCED FIRERATED ASSEMBLY TESTS AND STANDARDS.

    9 THE ARCHITECTURAL DRAWINGS ESTABLISH, COORDINATE, AS WELL AS TAKEPRECEDENCE FOR THE FINISHED APPEARANCE AND EXACT LOCATION OF ALL EXPOSEDELEMENTS OF THE WORK OF ALL TRADES, INCLUDING THAT WORK WHICH IS ILLUSTRATEDPRIMARILY ON DRAWINGS OF OTHER DISCIPLINES.

    10 THE DRAWINGS MAY MAKE REFERENCE TO AND/OR ILLUSTRATE ITEMS WHICH ARE NOTPART OF THE WORK OF THE CONTRACT. THESE ‘NOT IN CONTRACT’ ITEMS AS INDICATEDARE REFERENCED AND/OR ILLUSTRATED FOR THE CONTRACTORS REFERENCE,INFORMATION AND COORDINATION ONLY.

    11 THE CONTRACTOR IS RESPONSIBLE TO COMPLY WITH ALL APPLICABLE LAWS, CODES,REGULATIONS AND ORDINANCES OF THE PLACE (CITY, COUNTY,DISTRICT, AND STATE)WHERE THE PROJECT IS LOCATED.

    12 THE CONTRACTOR SHALL OBTAIN ALL REQUIRED PERMITS AND SIMILAR RELEASESREQUIRED FOR THE CONSTRUCTION AND OCCUPANCY OF THE PROJECT. THECONTRACTOR SHALL FURNISH COPIES OF ALL SUCH ITEMS TO THE OWNER ANDARCHITECT WITHIN 10 DAYS OF RECEIPT OF SUCH ITEMS. IF PERMITS ARE ISSUEDSUBJECT TO CERTAIN CONDITIONS OR REVISIONS TO THE WORK OR IF PERMITS AREDELAYED FOR ANY REASON, THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE OWNERAND ARCHITECT.

    13 THE CONTRACTOR SHALL COORDINATE AND OBTAIN ALL REQUIRED INSPECTIONS OFWORK, INCLUDING THAT PERFORMED BY OWNER. CONTRACTOR SHALL REGULARLYUPDATE OWNER AND ARCHITECT REGARDING THE STATUS OF INSPECTIONS.

    14 THE CONTRACTOR SHALL TAKE PRECAUTIONS TO MAINTAIN AND PROTECT NEW WORK ASWELL AS EXISTING SYSTEMS AND ELEMENTS WHICH ARE TO REMAIN. ANY DAMAGE TOSUCH SYSTEMS AND ELEMENTS SHALL BE IMMEDIATELY REPAIRED IN A MANNERACCEPTABLE TO THE ARCHITECT. IF SATISFACTORY REPAIRS CANNOT BE MADE, THECONTRACTOR SHALL REPLACE SYSTEMS AND ELEMENTS WITH NEW PRODUCTSACCEPTABLE TO THE ARCHITECT. ALL REPAIRS AND REPLACEMENT COSTS SHALL BE THEFINANCIAL RESPONSIBILITY OF THE CONTRACTOR.

    15 THE CONTRACTOR SHALL COORDINATE ALL WORK WITH APPLICABLE UTILITY PROVIDERS.

    16 THE CONTRACTOR SHALL COORDINATE ALL MECHANICAL CHASE SIZES WITH MECHANICALSUB-CONTRACTOR AND NOTIFY ARCHITECT WITH DISCREPANCIES IN THE FIELD.

    17 THE DRAWINGS SHALL NOT BE REPRODUCED FOR SUBMITTALS. DRAWINGS OR PORTIONSTHEREOF USED FOR SUBMITTALS WILL BE REJECTED AND RETURNED TO THECONTRACTOR WITHOUT THE APPROVAL OF THE ARCHITECT.

    18 THE CONTRACTOR SHALL PROVIDE AND COORDINATE ALL BLOCK-OUTS, SLEEVES,INSERTS, BOLTS, PLATES, ETC. FOR ALL TRADES PRIOR TO PLACING CONCRETE ORMASONRY.

    19 THE CONTRACTOR SHALL BE SOLELY RESPONSIBLE FOR MEANS, METHODS ANDSEQUENCES OF CONSTRUCTION.

    20 THE CONTRACTOR SHALL PROMPTLY REMOVE AND PROPERLY DISPOSE OF ALLCONSTRUCTION AND DEMOLITION DEBRIS. THE CONTRACTOR SHALL OBTAIN APPROVALOF OWNER FOR DETAILS RELATED TO ALL SITE ACCESS AND REMOVAL PLANS.

    21 THE CONTRACTOR SHALL BECOME FAMILIAR WITH AND COMPLY WITH OWNER’SPROCEDURES FOR MAINTAINING A SECURE SITE AND BUILDING.

    22 EACH INSTALLER SHALL EXAMINE THE SUBSTRATE CONDITION AND/OR SITE CONDITIONSWHICH AFFECT THE QUALITY OF EACH PRODUCT TO BE INSTALLED. IF ANY CONDITIONSEXIST WHICH WILL HAVE A DETRIMENTAL EFFECT ON THE QUALITY OF THE INSTALLATION,THE INSTALLER SHALL IMMEDIATELY ADVISE THE CONTRACTOR. INSTALLATION SHALL NOTPROCEED UNTIL THE UNSATISFACTORY CONDITIONS ARE CORRECTED. INSTALLATION OFPRODUCTS SHALL SIGNIFY ACCEPTANCE BY THE INSTALLER OF THE SUBSTRATECONDITIONS.

    23 THE CONTRACTOR SHALL MAINTAIN A CURRENT/UPDATED RECORD SET OF DRAWINGS ONSITE AT ALL TIMES.

    24 FOR THE PURPOSE OF PRICING/ESTIMATES, WHEN THERE IS A CONFLICT/DISCREPANCY INTHE DRAWINGS AND/OR SPECIFICATIONS, THE CONTRACTOR SHALL PRICE THE HIGHERCOST ITEM.

    25 CONTRACTOR AND SUBCONTRACTOR SHALL NOT SCALE CONSTRUCTION DOCUMENTS.

    26 ALL FINISH MATERIALS SHALL CONFORM TO I.B.C. FOR FLAME SPREAD AND SMOKEDEVELOPMENT, REFER TO SPECIFIC MATERIAL SPECIFICATION SECTION FOR ADDITIONALREQUIREMENTS.

    27 THE CONTRACTOR SHALL COORDINATE INFORMATION THAT IS PART OF ONE OR MORESEPARATE BID PACKAGES WITH ADDITIONAL INFORMATION ISSUED IN THE BID PACKAGE.THE MULTIPLE BID PACKAGES SHALL CONSTITUTE A COMPLETE PROJECT.

    28 THE CONTRACTOR SHALL COORDINATE ALL LOCATIONS AND SIZES OF HOUSEKEEPINGPADS WITH MECHANICAL AND ELECTRICAL SUB-CONTRACTORS.

    29 TOUCH UP FIREPROOFING AT SUPPORT BEAMS/TRUSSES AS REQUIRED TO MEET FIREPROOFING REQUIREMENTS.

    30 THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING A DUST BARRIER AT BASEBUILDING FACILITIES THROUGHOUT CONSTRUCTION.

    31 THE CONTRACTOR SHALL PROTECT ALL EXISTING BASE BUILDING ELEMENTS.

    ABBREVIATIONS

    QT QUARRY TILE

    QTY QUANTITY

    R RADIUS / RISER

    RA RETURN AIR

    RB RUBBER BASE / RESILIENT BASE

    RBR RUBBER

    RCP REFLECTED CEILING PLAN

    RD ROOF DRAIN

    REBAR REINFORCED STEEL BAR

    REC RECESSED

    REF REFERENCE / REFRIGERATOR

    REINF REINFORCED / REINFORCEMENT

    REM REMOVE

    REQD REQUIRED

    REV REVISION

    RGD INS RIGID INSULATION

    RH RIGHT HAND

    RL ROOF LEADER

    RLG RAILING

    RM ROOM

    RO ROUGH OPENING

    ROW RIGHT OF WAY

    RP REFERENCE POINT

    RTG RATING

    RTU ROOF TOP UNIT

    RVL REVEAL

    S SOUTH

    SALV SALVAGE

    SAN SANITARY

    SB SPLASH BLOCK

    SCHED SCHEDULE / SCHEDULED

    SCHEM SCHEMATIC

    SCP SCUPPER

    SCWD SOLID CORE WOOD DOOR

    SEC SECOND

    SECT SECTION

    SF SQUARE FOOT / SQUARE FEET / SUPPLY FAN

    SGL SINGLE

    SHT SHEET

    SHT MTLFLASH

    SHEET METAL FLASHING

    SHTHG SHEATHING

    SIM SIMILAR

    SLNT SEALANT

    SM SHEET METAL / SMALL / SURFACE MOUNTED

    SMACNA SHEET METAL AIR CONDITIONING CONTRACTOR'SNATIONAL ASSOCIATION

    SPEC SPECIFICATION(S)

    SPLY SUPPLY

    SPRT SUPPORT

    SQ SQUARE

    SST STAINLESS STEEL

    STC SOUND TRANSMISSION CLASS

    STD STANDARD

    STL STEEL

    STL JST STEEL JOIST

    STOR STORAGE

    STRUCT STRUCTURAL

    SURF SURFACE

    SUSP SUSPENDED

    SYMM SYMMETRICAL

    T TREAD

    T&B TOP AND BOTTOM

    T&G TONGUE AND GROOVE

    TBD TO BE DETERMINED

    TEL TELEPHONE

    TEMP TEMPERATURE / TEMPORARY

    TERR TERRAZZO

    THK THICK / THICKNESS

    THRES THRESHOLD

    THRU THROUGH

    TMPD GL TEMPERED GLASS

    TO TOP OF ____

    TOC TOP OF CONCRETE / TOP OF CURB

    TOJ TOP OF JOIST

    TOM TOP OF MASONRY

    TOP TOP OF PARAPET / TOP OF PAVEMENT

    TOS TOP OF STEEL / TOP OF SLAB

    TOW TOP OF WALL

    TRTD TREATED

    TS TUBE STEEL

    TYP TYPICAL

    UBC UNIFORM BUILDING CODE

    UC UNDERCUT

    UL UNDERWRITER'S LABORATORIES

    UNFIN UNFINISHED

    UNO UNLESS NOTED OTHERWISE

    UR URINAL

    UTIL UTILITY

    VAR VARIES

    VCT VINYL COMPOSITION TILE

    VERT VERTICAL

    VEST VESTIBULE

    VIF VERIFY IN FIELD

    VNR VENEER

    VTR VENT THROUGH ROOF

    VWC VINYL WALL COVERING

    W WEST / WIDTH / WIDE

    W/ WITH

    W/O WITHOUT

    WBL WOOD BLOCKING

    WC WATER CLOSET / WALL COVERING

    WD WOOD / WOOD DOOR

    WDW WINDOW

    WF WIDE FLANGE

    WGL WIRED GLASS

    WH WATER HEATER / WEEP HOLE

    WP WATERPROOFING / WORKING POINT

    WR WATER RESISTANT / WEATHER RESISTANT

    WT WEIGHT

    WWF WELDED WIRE FABRIC

    YD YARD / YARDS

    ABBREVIATIONS

    FL FLOW LINE / FLOOR LINE

    FLR FLOOR / FLOORING

    FLUOR FLUORESCENT

    FR FRAME / FIRE RATED / FIRE RETARTANT

    FT FOOT / FEET / FIRE TREATED / FULLY TEMPERED

    FTG FOOTING

    FURG FURRING

    FURN FURNISH / FURNITURE

    FUT FUTURE

    FVC FIRE VALVE CABINET

    GA GAGE

    GAL GALLONS

    GALV GALVANIZED

    GC GENERAL CONTRACTOR

    GEN GENERAL / GENERATOR

    GI GALVANIZED IRON

    GL GLASS / GROUND LEVEL

    GLZ GLAZING

    GND GROUND

    GYP BD GYPSUM BOARD

    GYP SHTG GYPSUM SHEATHING BOARD.

    HC HANDICAPPED ACCESSIBLE / HOLLOW CORE

    HD HEAD / HEAVY DUTY

    HDW HARDWARE

    HDWD HARDWOOD

    HM HOLLOW METAL

    HORIZ HORIZONTAL

    HP HIGH POINT / HORSEPOWER / HIGH PRESSURE

    HT HEIGHT

    HVAC HEATING VENTILATION AND AIR CONDITIONING

    HW HOT WATER

    HWH HOT WATER HEATER

    ID INSIDE DIAMETER / INTERIOR DESIGN

    IF INSIDE FACE / INTAKE FAN

    IN INCHES

    INCAND INCANDESCENT

    INCL INCLUDING

    INSTL INSTALL

    INSUL INSULATE / INSULATION

    INT INTERIOR / INTERNAL

    INV INVERT

    INV EL INVERT ELEVATION

    J BOX JUNCTION BOX

    JAN JANITOR

    JAN CLO JANITOR CLOSET

    JT JOINT

    KIT KITCHEN

    LAB LABORATORY

    LAM LAMINATE

    LAV LAVATORY

    LBS POUNDS

    LF LINEAR FEET

    LH LEFT HAND

    LLH LONG LEG HORIZONTAL

    LLV LONG LEG VERTICAL

    LPT LOW POINT

    LT LIGHT

    LTG LIGHTING

    LVR LOUVER

    MAINT MAINTENANCE

    MAS MASONRY

    MATL MATERIAL

    MAX MAXIMUM

    MECH MECHANICAL

    MED MEDIUM

    MEMB MEMBRANE

    MFG MANUFACTURING

    MFR MANUFACTURER

    MIN MINIMUM

    MISC MISCELLANEOUS

    ML METAL LATH

    MO MASONRY OPENING

    MOD BIT MODIFIED BITUMEN

    MR MOISTURE RESISTANT

    MS MOP SINK

    MTD MOUNTED

    MTL METAL

    MULL MULLION

    N NORTH

    N/A NOT APPLICABLE

    NCOMBL NONCOMBUSTIBLE

    NEG NEGATIVE

    NIC NOT IN CONTACT

    NO NUMBER

    NOM NOMINAL

    NTS NOT TO SCALE

    O/O OUT TO OUT

    OA OVERALL / OUTSIDE AIR

    OC ON CENTER

    OD OUTSIDE DIAMETER / OUTSIDE DIMENSION

    OF OUTSIDE FACE

    OF/CI OWNER FURNISHED/CONTRACTOR INSTALLED

    OF/OI OWNER FURNISHED/OWNER INSTALLED

    OFF OFFICE

    OH OPPOSITE HAND / OVERHEAD / OVERHANG

    OPNG OPENING

    OPP OPPOSITE

    ORD OVERFLOW ROOF DRAIN

    ORIG ORIGINAL

    ORN ORNAMENTAL

    ORS OVERFLOW ROOF SCUPPER

    PAT PATTERN

    PBD PARTICLE BOARD

    PCC PRECAST CONCRETE

    PERF PERFORATED

    PERM PERMANENT

    PL PLATE / PROPERTY LINE

    PLAM PLASTIC LAMINATE

    PLAS PLASTER / PLASTIC

    PLBG PLUMBING

    PLY PLYWOOD

    PNL PANEL

    POL POLISHED

    PR PAIR / PIPE RAIL

    PREFAB PREFABRICATED

    PREFIN PREFINISHED

    PRELIM PRELIMINARY

    PREP PREPARATION

    PROJ PROJECT

    PT PAINT / PRESSURE TREATED

    PT CONC POST TENSION CONCRETE

    PTD PAINTED / PAPER TOWEL DISPENSER

    PTN PARTITION

    PVC POLYVINYL CHLORIDE

    PVMT PAVEMENT

    ABBREVIATIONS

    AB ANCHOR BOLT

    ACT ACOUSTICAL TILE

    ADJ ADJACENT/ADJUSTABLE

    AFF ABOVE FINISH FLOOR

    AFG ABOVE FINISH GRADE

    AHU AIR HANDLING UNIT

    ALT ALTERNATE NO.

    ALUM ALUMINUM

    ANOD ANODIZED

    ANSI AMERICAN NATIONAL STANDARDS INSTITUTE

    APPD APPROVED

    APPROX APPROXIMATELY

    ARCH ARCHITECT

    ASSY ASSEMBLY

    AUTO AUTOMATIC/AUTOMATION

    AVG AVERAGE

    AWI AMERICAN WOODWORKING INSTITUTE

    AWT ACCOUSTICAL WALL TREATMENT

    B/B BACK TO BACK

    BD BOARD

    BL BUILDING LINE

    BLDG BUILDING

    BLKG BLOCKING

    BLST BALLAST

    BM BEAM/BENCH MARK

    BOS BOTTOM OF STEEL

    BOT BOTTOM

    BRG BEARING

    BSMT BASEMENT

    BTWN BETWEEN

    BUR BUILT UP ROOFING

    C / C CENTER TO CENTER

    CAB CABINET

    CB CATCH BASIN

    CBB CEMEMTITOUS BACKER BOARD

    CEM CEMENT

    CEM PLAS CEMENT PLASTER

    CER CERAMIC

    CF CUBIC FOOT / FEET

    CF/CI CONTRACTOR FURNISHED/CONTRACTOR INSTALLED

    CF/OI CONTRACTOR FURNISHED/OWNER INSTALLED

    CFLG COUNTER FLASHING

    CFMF COLD FORMED METAL FRAMING

    CG CORNER GUARD

    CIP CAST IN PLACE

    CJ CONTROL JOINT / CONSTRUCTION JOINT

    CL CENTERLINE

    CLG CEILING

    CLO CLOSET

    CLR CLEAR

    CLT CLEAT

    CMU CONCRETE MASONRY UNIT

    CO CLEAN OUT

    COL COLUMN

    CONC CONCRETE

    COND CONDITION

    CONST CONSTRUCTION

    CONT CONTINUE / CONTINUATION / CONTINUOUS

    CONTR CONTRACTOR

    COORD COORDINATE

    COP COPING

    CORR CORRIDOR

    CPT CARPET

    CSK COUNTER SUNK

    CT CERAMIC TILE

    CTR CENTER

    CU FT CUBIC FOOT / CUBIC FEET

    CU YD CUBIC YARDS

    CW COLD WATER

    D DEPTH / DEEP

    DBL DOUBLE

    DEG DEGREE

    DEL DELETE

    DEMO DEMOLITION

    DET DETAIL

    DETN DETENTION

    DF DRINKING FOUNTAIN

    DIA DIAMETER

    DIAG DIAGONAL

    DIM DIMENSION

    DISP DISPENSER

    DMPF DAMPPROOFING

    DN DOWN

    DR DOOR / DRAIN

    DS DOWNSPOUT

    DTL DETAIL

    DWG DRAWING

    E EAST

    EA EACH

    EIFS EXTERIOR INSULATION FINISH SYSTEM

    EJ EXPANSION JOINT

    EL REFERENCE ELEVATION

    EL EASEMENT LINE

    ELEC ELECTRIC / ELECTRICAL

    ELEV ELEVATOR / ELEVATION

    EMER EMERGENCY

    ENCL ENCLOSURE

    ENGR ENGINEER / ENGINEERING

    EOS EDGE OF SLAB

    EPDM ETHYLENE PROPYLENE DIENE MONOMOR

    EQ EQUAL

    EQL SP EQUALLY SPACED

    EQUIP EQUIPMENT

    EST ESTIMATE

    ETC ET CETERA

    EW EACH WAY

    EWC ELECTRIC WATER COOLER

    EXIST EXISTING

    EXP EXPOSED / EXPAND / EXPANSION

    EXT EXTERIOR / EXTERNAL / EXTINGUISHER

    F / F FACE TO FACE

    F F EL FINISHED FLOOR ELEVATION

    FA FIRE ALARM / FACE AREA / FRESH AREA

    FACP FIRE ALARM CONTROL PANEL

    FD FLOOR DRAIN

    FDTN FOUNDATION

    FDV FIRE DEPARTMENT VALVE CABINET

    FE FIRE EXTINGUISHER

    FEC FIRE EXTINGUISHER CABINET

    FF INSUL FOIL BACKED INSULATION

    FH FIRE HYDRANT / FIRE HOSE

    FHC FIRE HOSE CABINET

    FIN FINISH

    FIN GR FINISHED GRADE

    FIXT FIXTURE

    DRAWING LIST

    NO. DRAWING NAME

    GENERALG-000 COVER SHEETG-001 SHEET INDEX & GENERAL NOTESG-002 LIFE SAFETY & CODE INFORMATIONG-003 HANGAR LIFE SAFETY PLANS

    CIVILC-001 SITE PLANC-002 UTILITY PLAN

    ARCHITECTUREA-101 LEVEL 01 HANGAR FLOOR PLANA-102 MEZZANINE HANGAR FLOOR PLANA-105 HANGAR ROOF PLANA-121 LEVEL 01 HANGAR RCPA-201 OVERALL HANGAR ELEVATIONSA-301 HANGAR SECTIONS & WALL SECTIONSA-601 DOOR SCHEDULEA-611 WINDOW SCHEDULEA-621 FINISH SCHEDULE & FINISH PLANA-901 AXONOMETRICS

  • The

    Con

    tract

    or sh

    all v

    erify

    and

    be

    resp

    onsib

    le fo

    r all d

    imen

    sions

    . DO

    NO

    T sca

    le th

    e dr

    awin

    g -a

    ny e

    rrors

    or o

    miss

    ions

    shal

    l be

    repo

    rted

    to S

    tant

    ec w

    ithou

    t del

    ay.

    The

    Cop

    yrig

    hts t

    o al

    l des

    igns

    and

    dra

    win

    gs a

    re th

    e pr

    oper

    ty o

    f Sta

    ntec

    . Rep

    rodu

    ctio

    n or

    use

    for a

    ny p

    urpo

    se o

    ther

    than

    that

    aut

    horiz

    ed b

    y St

    ante

    c is

    forb

    idde

    n.

    ORIGINAL SHEET - ARCH D

    Drawing No.Revision:

    Permit/Seal

    File Name: N/A

    Title

    PRELIMINARY

    NOT FOR

    CONSTRUCTIONNot for permits, pricing or other official purposes. This document has not been

    completed or checked and is for general information or comment only.

    Revi

    sion

    ByAp

    pdYY

    YY.M

    M.D

    DIss

    ued

    ByAp

    pdYY

    YY.M

    M.D

    D

    1

    A

    2 3 4 5

    B

    C

    D

    YYYY.MM.DDDsgn. Chkd.Dwn.

    TUC

    SON

    INTE

    RNAT

    IONA

    L AIR

    PORT

    Project No.:

    Con

    sulta

    nt

    Scale:

    1011

    9108

    ANG

    -EC

    F HA

    NGAR

    REP

    LAC

    EMEN

    T (B

    RIDG

    ING

    DO

    CUE

    MEN

    TS)

    181710627

    10/2

    4/20

    19 1

    2:43

    :48

    PM

    1/2" = 1'-0"

    G-002

    100%

    BRI

    DG

    ING

    DO

    CUM

    ENTS

    Author CheckerDesigner 2019.10.25

    LIFE SAFETY & CODEINFORMATION

    Stan

    tec

    Arch

    itect

    ure

    Inc.

    1050

    17t

    h St

    reet

    Sui

    te A

    200

    Den

    ver,

    CO

    802

    65-2

    016

    Tel:

    (303

    ) 295

    -171

    7 •

    ww

    w.st

    ante

    c.co

    m

    4.3 AIR LEAKAGE INFILTRATION RATE .04 CFM/FT2

    0 - 3.0% OF ROOF U-0.65, SHGC-0.35

    SKYLIGHT

    PF ≥ 0.5, N ORIENTATION SHGC-0.40

    PF ≥ 0.5, SEW ORIENTATION SHGC-0.40

    0.2 ≤ PF < 0.5, N ORIENTATION SHGC-0.37

    0.2 ≤ PF < 0.5, SEWORIENTATION

    SHGC-0.30

    PF < 0.2, N ORIENTATION SHGC-0.33 9.0 ENERGY EFFICIENCY SEE INTERNATIONAL ENERGY CONSERVATION CODE

    PF < 0.2, SEW ORIENTATION SHGC-0.25

    ENTRANCE DOORS U-0.83 SIGNAGE TO CONFORM TO REQUIREMENTS OF IBC CHAPTER 11.

    OPERABLE U-0.65 BUILDING ACCESSIBLE ROUTE, ENTRANCES, FACILITIES, AND

    FIXED U-0.50 8.0 ACCESSIBILITY

    WINDOW FRAMES (IBC 907)

    GLAZING DETECTION SYSTEMS

    4.2 GLAZING VERTICAL FENESTRATION 7.4 FIRE ALARM SEE ELECTRICAL NARRATIVE

    HEATEDR-7.5 FOR 12" BELOW + R-5 FULL

    SLAB(IBC 906)

    UNHEATED NO REQUIREMENT EXTINGUISHERS ADDITIONAL REQUIRED BY AIRCRAFT TOWING VEHICLES AND WELDING APPARATUS'

    SLAB ON GRADE 7.3 PORTABLE FIRE AT EXIT LOCATIONS - MAX. TRAVEL DISTANCE TO EXTINGUISHER = 75'

    METAL FRAMED R-13 + R-5ci (IBC 905)

    METAL BUILDING R-13 + R-5ci 7.2 STANDPIPE SYSTEMS NOT REQUIRED

    MASS R-5.7ci

    WALLS (IBC 903)

    SYSTEM

    METAL BUILDINGS R-19 + R11 LS 7.1 AUTOMATIC SPRINKLER PROVIDED

    4.1 OPAQUE THERMAL ROOFS

    NFRC 100 SYSTEMS

    IECC REQUIRED 7.0 FIRE PROTECTION

    4.0 BUILDING ENVELOPE - CLIMATE ZONE 2B (IBC 714)

    6.7 PENETRATIONS RATING AS REQUIRED FOR ASSEMBLY

    (IBC 705) *PER IBC TABLE 705.8

    PROTECTION (IBC 711)

    3.9 OPENING *UNLIMITED UNPROTECTED OPENINGS ASSEMBLIES

    6.6 HORIZONTAL NOT REQUIRED

    X > 10 II-B

    601 & 602) X (FEET) CONSTRUCTION (IBC 709)

    (IBC TABLE DISTANCE = TYPE OF 6.5 SMOKE BARRIERS NOT REQUIRED

    FIRE RATINGS SEPARATION

    3.8 EXTERIOR WALL FIRE (IBC 708)

    6.4 FIRE PARTITIONS 1 HOUR IF REQUIRED

    ROOF CONSTRUCTION NON-COMBUSTIBLE 0 - HR

    FLOOR CONSTRUCTION NON-COMBUSTIBLE 0 - HR

    -INTERIOR NON-COMBUSTIBLE 0 - HR (IBC 713)

    -EXTERIOR NON-COMBUSTIBLE 0 - HR 6.3 SHAFT ENCLOSURES NOT REQUIRED

    NON-BEARING WALLS ANDPARTITIONS

    - INTERIOR NON-COMBUSTIBLE 0 - HR (IBC 707)

    - EXTERIOR NON-COMBUSTIBLE 0 - HR 6.2 FIRE BARRIERS NOT REQUIRED

    (IBC TABLE 601) BEARING WALLS

    RATINGS STRUCTURAL FRAME NON-COMBUSTIBLE 0 - HR (IBC 706)

    3.7 FIRE RESISTANCE ELEMENT MATERIAL RATING 6.1 FIRE WALLS NOT REQUIRED

    CONSTRUCTION

    70,000 SF FOR S-1 6.0 FIRE-RESISTANT

    ALLOWED: 92,000 SF FOR B

    (IBC 1020.4) *With Sprinkler System

    DISTANCE

    S-1 32,087 CORRIDOR B & S-1 *50'

    B 2,010

    (IBC 506) PROPOSED: 34,097 5.10 DEAD END OCCUPANCY MAX. DISTANCE

    3.6 BUILDING AREA GROSS SQ. FT.

    *With Sprinkler System

    *MEZZANINE IS CONSIDERED A PORTION OF STORY BELOW (PER IBC 505.2)

    *WITH AUTOMATIC SPRINKLER SYSTEM (PER IBC 504.3)

    ALLOWED: *75' 3 (IBC TABLE 1020.1) B & S-1 *0

    (IBC 504) PROPOSED: 49' - 6 1/4" 1 RATING OCCUPANCY RATING

    3.5 BUILDING HEIGHT FEET STORIES 5.9 CORRIDOR FIRE FIRE-RESISTANCE

    (IBC 602) (IBC TABLE 1020.2) NOT LESS THAN 36" SERVING OCCUPANT LOAD OF LESS THAN 50

    CONSTRUCTION II-B NON-COMBUSTIBLE MATERIALS 5.8 CORRIDOR WIDTH NOT LESS THAN 44"

    3.4 TYPE OF TYPE

    (IBC 1009.1 & 1011.2) *Stairways serving an occupant load of less than 50 shall have a width not less than 36"

    (IBC TABLE 508.4) 5.7 STAIR WIDTH 44" MINIMUM CLEAR WIDTH*

    SEPARATION B & S-1 0 HOURS *With Sprinkler System

    3.3 OCCUPANCY OCCUPANCY HOURS

    B & S-1 150*0.2=30" 150*0.2=30"

    (IBC 302.1) PROPOSED:

    CLASSIFICATION STORAGE (AIRCRAFT HANGAR STORAGE AND REPAIR) S-1

    OCCUPANCY BUSINESS B B & S-1 *0.2 0.2

    3.2 BUILDING USE & USE GROUP (IBC 1005.3) OCCUPANCY STAIRWAYS COMPONENTS

    5.6 EGRESS WIDTHS OTHER EGRESS

    - METAL STUD AND GYPSUM BOARD FRAMED WALLS WITH ACOUSTICAL PANEL CEILINGS; FINISH FLOORS IN SELECT AREAS

    DESCRIPTION - SINGLE STORY PRE-FABRICATED BUILDING, INSULATED STEELBUILDING WITH CORRUGATED METAL SIDING AND ROOF ALLOWED: 136'-6" MINIMUM

    3.1 BUILDING HANGAR BAY FACILITY WITH OFFICES AND SHOP SPACE PROPOSED: 164'

    (IBC 1007.1.1) BETWEEN EXITS

    3.0 BUILDING 5.5 EXIT SEPARATION DISTANCE

    (IBC 1108.2.2.1) ALLOWED: 1 - 500 2

    2.2 PARKING DATA STANTEC CIVIL TEAM TO PROVIDE PROPOSED: 116 6

    (IBC TABLE 1006.3.1) OCCUPANTS OF EXITS

    5.4 NUMBER OF EXITS MIN. NUMBER

    LINES *With Sprinkler System

    2.1 DISTANCE TO LOT STANTEC CIVIL TEAM TO PROVIDE (IBC TABLE 1006.2.1) S-1 SEE L.S. PLANS *100'

    TRAVEL B SEE L.S. PLANS *100'

    2.0 SITE 5.3 COMMON PATH OF OCCUPANCY PROPOSED MAX. ALLOWED

    JURISDICTION (IBC TABLE 1017.2) *With Sprinkler System, Based on S-1 Occupancy

    HAVING TRAVEL DISTANCE ALLOWED: *250' MAXIMUM

    1.4 AUTHORITY CITY OF TUCSON PLANNING AND DEVELOPMENT SERVICES 5.2 EXIT ACCESS PROPOSED: SEE LIFE-SAFETY PLANS

    ICC/ANSI A117.1-2009 ACCESSIBLE AND USABLE BUILDINGS AND FACILITIES

    INTERNATIONAL FUEL GAS CODE, 2018 EDITION; TUCSON AMENDMENTS

    INTERNATIONAL FIRE CODE, 2018 EDITION; TUCSON AMENDMENTS TOTAL 31,897 116

    INTERNATIONAL ENERGY CONSERVATION CODE, 2018 EDITION; TUCSON AMENDMENTS

    INTERNATIONAL MECHANICAL CODE, 2018 EDITION; TUCSON AMENDMENTS

    INTERNATIONAL PLUMBING CODE, 2018 EDITION; TUCSON AMENDMENTS B 2,845 150 19

    1.3 CODES IN EFFECT INTERNATIONAL BUILDING CODE, 2018 EDITION; TUCSON AMENDMENTS S-1 29,052 300 97

    AREA NAME AREA (NSF) FACTOR OCCUPANTS

    1.2 SITE ADDRESS TUCSON INTERNATIONAL AIRPORT; TUSCON, ARIZONA (IBC TABLE 1004.1.2) LOAD

    5.1 OCCUPANT LOADS OCCUPANT

    1.1 OWNER TUCSON AIRPORT AUTHORITY

    EGRESS

    1.0 GENERAL 5.0 LIFE SAFETY -

    BUILDING CODE DATA - ANG-ECF HANGAR

    1/2" = 1'-0"G-002A4 VICINITY MAP

    NOT TO SCALE

    SITE

    2 + 1 Urinal (Mens) 3 (Womens) 2 (Mens) 2 (Womens) 1

    (58 OL/sex) 2:50 + 8/50 = 2.16/sex 58/40 = 1.45/sex 58/100 = 0.58

    B 1:25 for first 50 and 1:50 for the remainder 1:40 for first 80 and 1:80 for the remainder 1:100

    Provided 1 (Mens) 1 (Womens) 1 (Mens) 1 (Womens) 1

    Required 0.40 + 0.49 = 0.89/sex 0.25 + 0.49 = 0.74/sex 0.19 + 0.097 = 0.287

    (49 OL/sex) 49/100 = 0.49/sex 49/100 = 0.49/sex 97/1000 = 0.097

    S-1 1:100 1:100 1:1000

    (10 OL/sex) 10/25 = 0.40/sex 10/40 = 0.25/sex 19/100 = 0.19

    B 1:25 for the first 50 and 1:50 for the remainder 1:40 for the first 80 and 1:80 for the... 1:100

    Male & Female Male & Female

    FOUNTAINS

    OCCUPANCY WATER CLOSETS LAVATORIES DRINKING

  • RE

    F

    AREA

    DIA

    GONA

    L

    EX

    IT T

    RA

    VE

    L D

    IST

    AN

    CE

    A

    EX

    IT T

    RA

    VE

    L D

    IST

    AN

    CE

    B

    CO

    MM

    ON

    PA

    TH

    A

    EX

    IT T

    RA

    VE

    L D

    IST

    AN

    CE

    C

    EXIT TRAVEL DISTANCE D

    UP

    CODE LEGEND

    PHASING LEGEND

    3

    A B C D G J

    2

    F HE

    4

    8

    1

    5

    6

    7

    9

    AREA

    OLF

    OCC

    1901

    S-1

    ASSEMBLY QA

    6

    300

    AREA

    OLF

    OCC

    800

    S-1

    AVIONICS LAB

    6

    150

    AREAOLF

    OCC

    56

    S-1

    WATER

    1

    300

    AREAOLF

    OCC

    104

    S-1

    MECH

    1

    300

    AREA

    OLF

    OCC

    64

    S-1

    ELEC

    1

    300

    AREA

    OLF

    OCC

    62

    S-1

    TELECOM

    1

    300

    AREA

    OLFOCC

    22729

    S-1

    HANGAR BAY

    45500

    AREA

    OLF

    OCC

    59

    S-1

    COMP

    1

    300

    AREA

    OLF

    OCC

    143

    S-1

    DUST BOOTH

    1

    300

    AREA

    OLF

    OCC

    1921

    S-1

    STOCK ROOM

    6

    300

    AREA

    OLFOCC

    364

    S-1

    PARTS ROOM

    1300

    AREAOLF

    OCC

    260

    B

    CUSTOMER OFFICE

    2

    150

    AREA

    OLFOCC

    60

    B

    JANITOR CLOSET

    1300

    AREA

    OLFOCC

    641

    B

    BREAK ROOM

    4150

    AREA

    OLFOCC

    397

    B

    REPAIR STATION OFFICE

    3150

    AREA

    OLFOCC

    114

    B

    UNISEX RR

    250

    AREA

    OLF

    OCC

    1367

    S-1

    SHEET METAL SHOP

    4

    300

    AREA

    OLF

    OCC

    288

    S-1

    PAINT BOOTH

    1

    300

    AREA

    OLFOCC

    2219

    S-1

    GROUND SUPPORT

    7300

    AREA

    OLFOCC

    178

    B

    WOMENS RR

    350

    AREA

    OLFOCC

    177

    B

    MENS RR

    350

    FE FE

    FE

    FE FE

    FE

    FE

    FE

    FE

    AREA

    OLFOCC

    182

    B

    LOCAL ENGINEERING OFFICE

    4150

    FE

    FE

    1 HOUR FIRE BARRIER

    2 HOUR FIRE BARRIER

    3 HOUR FIRE BARRIER

    4 HOUR FIRE BARRIER

    EXIT ACCESS TRAVEL PATH

    MAX BLDG DIAG

    MAX COMMON PATH OF EGRESS

    BUILDING DIAGONAL

    OCCUPANCY CLASSIFICATION

    AREA

    OCCUPANCY LOAD FACTOR

    NUMBER OF OCCUPANTS

    ASSEMBLYA-3

    AREA 528 SF

    OLF15

    OCC 36

    FIRE EXTINGUISHER CABINET

    74 OCCUPANT EGRESS LOAD

    FIRE EXTINGUISHERFE

    FEC

    FIRE ALARM CONTROL PANEL

    FACP

    PROPOSED WALL FOR FUTURE EXPANSION (NOT IN CONTRACT)

    PROPOSED DOOR FOR FUTURE EXPANSION(NOT IN CONTRACT)

    G JH

    4

    8

    5

    6

    7

    9

    AREA

    OLFOCC

    2369

    B

    FUTURE OFFICES

    20150

    3000

    The

    Con

    tract

    or sh

    all v

    erify

    and

    be

    resp

    onsib

    le fo

    r all d

    imen

    sions

    . DO

    NO

    T sca

    le th

    e dr

    awin

    g -a

    ny e

    rrors

    or o

    miss

    ions

    shal

    l be

    repo

    rted

    to S

    tant

    ec w

    ithou

    t del

    ay.

    The

    Cop

    yrig

    hts t

    o al

    l des

    igns

    and

    dra

    win

    gs a

    re th

    e pr

    oper

    ty o

    f Sta

    ntec

    . Rep

    rodu

    ctio

    n or

    use

    for a

    ny p

    urpo

    se o

    ther

    than

    that

    aut

    horiz

    ed b

    y St

    ante

    c is

    forb

    idde

    n.

    ORIGINAL SHEET - ARCH D

    Drawing No.Revision:

    Permit/Seal

    File Name: N/A

    Title

    PRELIMINARY

    NOT FOR

    CONSTRUCTIONNot for permits, pricing or other official purposes. This document has not been

    completed or checked and is for general information or comment only.

    Revi

    sion

    ByAp

    pdYY

    YY.M

    M.D

    DIss

    ued

    ByAp

    pdYY

    YY.M

    M.D

    D

    1

    A

    2 3 4 5

    B

    C

    D

    YYYY.MM.DDDsgn. Chkd.Dwn.

    TUC

    SON

    INTE

    RNAT

    IONA

    L AIR

    PORT

    Project No.:

    Con

    sulta

    nt

    Scale:

    1011

    9108

    ANG

    -EC

    F HA

    NGAR

    REP

    LAC

    EMEN

    T (B

    RIDG

    ING

    DO

    CUE

    MEN

    TS)

    181710627

    10/2

    4/20

    19 1

    2:43

    :51

    PM

    As indicated

    G-003

    100%

    BRI

    DG

    ING

    DO

    CUM

    ENTS

    Author CheckerDesigner 2019.10.25

    HANGAR LIFE SAFETYPLANS

    Stan

    tec

    Arch

    itect

    ure

    Inc.

    1050

    17t

    h St

    reet

    Sui

    te A

    200

    Den

    ver,

    CO

    802

    65-2

    016

    Tel:

    (303

    ) 295

    -171

    7 •

    ww

    w.st

    ante

    c.co

    m

    EGRESS ACCESS

    CODE TRAVEL NAME CODE DISTANCES

    AREA DIAGONAL 273'-2"

    COMMON PATH A 97'-6"

    EXIT TRAVELDISTANCE A

    154'-10"

    EXIT TRAVELDISTANCE B

    228'-2"

    EXIT TRAVELDISTANCE C

    94'-7"

    EXIT TRAVELDISTANCE D

    126'-4"

    1/16" = 1'-0"G-003A4 LEVEL 01 HANGAR LIFE SAFETY PLAN

    1/16" = 1'-0"G-003C4 MEZZANINE HANGAR LIFE SAFETY PLAN (FUTURE)

    NORTH

    NORTH

  • © 2019 Microsoft Corporation © 2019 DigitalGlobe ©CNES (2019) Distribution Airbus DS

    X

    XX

    XX

    FO

    FO

    FO

    FO

    FO

    ORIGINAL SHEET - ARCH D

    \\us

    1310

    -f01\

    shar

    ed_p

    roje

    cts\

    1817

    1062

    7\02

    _civi

    l\de

    sign\

    draw

    ing\

    shee

    t_file

    s\10

    627-

    C-0

    01SP

    .dw

    g20

    19/1

    0/24

    3:1

    5 PM B

    y: W

    right

    , Jim

    (Tuc

    son)

    ww

    w.st

    ante

    c.co

    mTe

    l.

    Stan

    tec

    5151

    E. B

    ROAD

    WAY

    BLV

    D. S

    UITE

    400

    TUC

    SON,

    AZ 8

    5711

    -371

    252

    0-75

    0-74

    74

    Drawing No.Revision:01

    Permit/Seal

    File Name: N/A

    Title

    The

    Con

    tract

    or sh

    all v

    erify

    and

    be

    resp

    onsib

    le fo

    r all d

    imen

    sions

    . DO

    NO

    T sca

    le th

    edr

    awin

    g - a

    ny e

    rrors

    or o

    miss

    ions

    shal

    l be

    repo

    rted

    to S

    tant

    ec w

    ithou

    t del

    ay.

    The

    Cop

    yrig

    hts t

    o al

    l des

    igns

    and

    dra

    win

    gs a

    re th

    e pr

    oper

    ty o

    f Sta

    ntec

    . Rep

    rodu

    ctio

    nor

    use

    for a

    ny p

    urpo

    se o

    ther

    than

    that

    aut

    horiz

    ed b

    y St

    ante

    c is

    forb

    idde

    n.

    PRELIMINARYNOT FOR

    CONSTRUCTIONNot for permits, pricing or other officialpurposes. This document has not been

    completed or checked and is for generalinformation or comment only.

    Revis

    ion

    ByAp

    pdYY

    YY.M

    M.D

    DIss

    ued

    ByAp

    pdYY

    YY.M

    M.D

    D

    1

    A

    2 3 4 5

    B

    C

    D

    YYYY.MM.DDDsgn. Chkd.Dwn.BSH JWWBSH 2019.10.18

    Tusc

    on In

    tern

    atio

    nal A

    irpor

    t

    Project No.:

    Con

    sulta

    nt

    Scale:

    1011

    9108

    ANG

    -EC

    FHA

    NGAR

    REP

    LAC

    EMEN

    T(B

    RIDG

    ING

    DO

    CUE

    MEN

    TS)

    181710627

    N

    CENTERLINE TAXILANE (ADG III)

    EDGE OF TAXILANEEXISTING SOLARARRAY FENCEPROTECT IN PLACE

    EXISTING AOA FENCETO BE REMOVED

    SIDA GATE 79

    MATCH INTOEXISTING TAXIWAY

    TAXIWAY C

    HANGAR

    NEW DPSHANGAR

    AERO PARK DRIVE

    EXISTING AOA FENCEPROTECT IN PLACE

    EXISTING DRAINAGESWALE

    3

    4

    NEW 24' DOUBLESWING GATE

    RAYTHEON

    DETENTION BASIN

    NEW AOA FENCE(27' CLEAR)

    3

    NEW APRON PAVEMENT SECTION(SEE GEOTECHNICAL REPORT)

    NEW TAXILANE PAVEMENT SECTION(SEE GEOTECHNICAL REPORT)

    TRENCH DRAIN AT HANGAR DOOR -DRAIN TO SAND/OIL SEPARATOR

    NEW STABILIZED DECOMPOSEDGRANITE TRUCK TURN AROUND(SEE GEOTECHNICAL REPORT)

    NEW CONCRETE PAD

    NEW 36" PIPE (4) CULVERT WITHHEADWALL (AIRCRAFT RATED)

    NEW AOA FENCE

    AOA FENCE CROSSES THE EXISTINGDRAINAGE WAY

    NEW DRAINAGE CHANNEL

    NEW PARKING LOT PAVEMENT(SEE GEOTECHNICAL REPORT)

    NEW DELIVERY ROAD PAVEMENT(SEE GEOTECHNICAL REPORT)

    NEW CONCRETE SIDEWALK

    NEW CONCRETE LOADING PAD

    NEW MICROWAVE TOWER LOCATION(BY OTHERS)

    2

    1

    4

    5

    5

    6

    7

    8

    9

    10

    6

    2

    8

    10

    7

    7

    12

    11

    12

    13

    13

    14

    C - 00100 00 ofSheet:

    SITE PLAN

    1" = 50'

    11

    141

    2

    EXISTING AOA FENCETO BE REMOVED

    AutoCAD SHX TextE

    AutoCAD SHX TextE

    AutoCAD SHX TextTWA

    AutoCAD SHX TextE

    AutoCAD SHX TextTWA

    AutoCAD SHX TextE

    AutoCAD SHX TextTWA

    AutoCAD SHX TextS

    AutoCAD SHX TextTWA

    AutoCAD SHX TextS

    AutoCAD SHX TextS

    AutoCAD SHX TextS

    AutoCAD SHX TextS

    AutoCAD SHX TextE

    AutoCAD SHX TextE

    AutoCAD SHX TextTWA

    AutoCAD SHX TextS

    AutoCAD SHX Text0

    AutoCAD SHX Text50'

    AutoCAD SHX Text100'

    AutoCAD SHX TextHORIZONTAL

  • X

    XX

    XX

    FO

    FO

    FO

    FO

    FO

    P

    18'' ST

    12'' W 12'' W 12'' W

    8'' W

    12'' W

    ORIGINAL SHEET - ARCH D

    \\us

    1310

    -f01\

    shar

    ed_p

    roje

    cts\

    1817

    1062

    7\02

    _civi

    l\de

    sign\

    draw

    ing\

    shee

    t_file

    s\10

    627-

    C-0

    01UT

    .dw

    g20

    19/1

    0/24

    3:0

    5 PM B

    y: W

    right

    , Jim

    (Tuc

    son)

    ww

    w.st

    ante

    c.co

    mTe

    l.

    Stan

    tec

    5151

    E. B

    ROAD

    WAY

    BLV

    D. S

    UITE

    400

    TUC

    SON,

    AZ 8

    5711

    -371

    252

    0-75

    0-74

    74

    Drawing No.Revision:01

    Permit/Seal

    File Name: N/A

    Title

    The

    Con

    tract

    or sh

    all v

    erify

    and

    be

    resp

    onsib

    le fo

    r all d

    imen

    sions

    . DO

    NO

    T sca

    le th

    edr

    awin

    g - a

    ny e

    rrors

    or o

    miss

    ions

    shal

    l be

    repo

    rted

    to S

    tant

    ec w

    ithou

    t del

    ay.

    The

    Cop

    yrig

    hts t

    o al

    l des

    igns

    and

    dra

    win

    gs a

    re th

    e pr

    oper

    ty o

    f Sta

    ntec

    . Rep

    rodu

    ctio

    nor

    use

    for a

    ny p

    urpo

    se o

    ther

    than

    that

    aut

    horiz

    ed b

    y St

    ante

    c is

    forb

    idde

    n.

    PRELIMINARYNOT FOR

    CONSTRUCTIONNot for permits, pricing or other officialpurposes. This document has not been

    completed or checked and is for generalinformation or comment only.

    Revis

    ion

    ByAp

    pdYY

    YY.M

    M.D

    DIss

    ued

    ByAp

    pdYY

    YY.M

    M.D

    D

    1

    A

    2 3 4 5

    B

    C

    D

    YYYY.MM.DDDsgn. Chkd.Dwn.BSH JWWBSH 2019.10.18

    Tusc

    on In

    tern

    atio

    nal A

    irpor

    t

    Project No.:

    Con

    sulta

    nt

    Scale:

    1011

    9108

    ANG

    -EC

    FHA

    NGAR

    REP

    LAC

    EMEN

    T(B

    RIDG

    ING

    DO

    CUE

    MEN

    TS)

    181710627

    N

    CENTERLINE TAXILANE (ADG III)

    EDGE OF TAXILANEEXISTING SOLARARRAY FENCEPROTECT IN PLACE

    EXISTING AOA FENCETO BE REMOVED

    SIDA GATE 79

    MATCH INTOEXISTING TAXIWAY

    TAXIWAY C

    HANGAR

    NEW DPSHANGAR

    AERO PARK DRIVE

    EXISTING AOA FENCEPROTECT IN PLACE

    EXISTING DRAINAGESWALE

    3

    RAYTHEON

    DETENTION BASIN

    NEW WATER MAIN (SIZE ASSHOWN)

    NEW WATER SERVICE LINE WITHMETER

    NEW FIRE HYDRANT

    NEW 4" BCS

    NEW 8" STORM SEWER LINEFROM TRENCH DRAIN

    NEW SAND/OIL SEPARATOR

    NEW ELECTRICAL PME

    NEW ELECTRIC TRANSFORMER

    NEW ELECTRIC CONDUIT BANK1-4" TO TRANSFORMER2-6" STUBS ACROSS TAXILANE

    NEW 18" STORM DRAIN PIPE TODISCHARGE STRUCTURE

    NEW 4" FIRE SERVICE TO FIRERISER ROOM

    NEW PRIVATE MANHOLE

    2

    7

    8

    6

    5

    4

    3

    2

    1

    9

    1

    1

    3 4

    5

    10

    6

    7

    8

    9

    9

    10

    C - 00200 00 ofSheet:

    UTILITY PLAN

    1" = 50'

    1

    11

    11

    12

    12

    9

    AutoCAD SHX TextE

    AutoCAD SHX TextE

    AutoCAD SHX TextTWA

    AutoCAD SHX TextE

    AutoCAD SHX TextTWA

    AutoCAD SHX TextE

    AutoCAD SHX TextTWA

    AutoCAD SHX TextS

    AutoCAD SHX TextTWA

    AutoCAD SHX TextS

    AutoCAD SHX TextS

    AutoCAD SHX TextS

    AutoCAD SHX TextS

    AutoCAD SHX TextE

    AutoCAD SHX TextE

    AutoCAD SHX TextTWA

    AutoCAD SHX TextS

    AutoCAD SHX Text0

    AutoCAD SHX Text50'

    AutoCAD SHX Text100'

    AutoCAD SHX TextHORIZONTAL

  • RE

    F

    UP

    A4A-201

    B2 A-20

    1

    D4A-201

    B4 A-20

    1

    3

    A B C D G J

    2

    F HE

    4

    8

    1

    5

    6

    7

    9

    A-301D4_______

    A-301A4_______

    104SHEET METAL SHOP

    102GROUND SUPPORT

    101STOCK ROOM

    107HANGAR BAY

    108TELECOM/SECURITY

    109ELEC 111

    MECH

    112RISER

    116AVIONICS LAB

    117PARTS ROOM

    118LOCAL ENGINNERING OFFICE

    121CUSTOMER OFFICE

    122BREAK ROOM

    124UNISEX RR

    103PAINT BOOTH

    105DUST BOOTH

    106COMP

    119JANITOR

    123REPAIR STATION OFFICE

    13' -

    0"

    16' -

    0"

    104B

    105

    103

    104A

    102B

    101B

    102A

    101A

    101C

    107B

    107C

    123

    118

    119

    121

    124

    117B

    113B

    113C

    113A

    108

    109

    111 112

    104C

    106

    102C

    107A

    113ASSEMBLY QA

    114WOMENS RR

    115MENS RR

    SS

    TELECOM ELEC

    CONDENSATE COLLECTION

    FOR SS

    27' - 3 1/4" 12' - 11" 10' - 6 1/2" 61' - 4" 61' - 4" 10' - 6 1/2" 12' - 11" 27' - 3 1/4"224' - 1 1/2"

    1' - 2

    1/2"

    26' -

    2"26

    ' - 2"

    26' -

    2"26

    ' - 2"

    26' -

    2"26

    ' - 2"

    1' - 2

    1/2"

    159'

    - 4 1/

    2"

    114

    116

    10.03

    08.05

    08.05

    08.05

    08.05

    08.05

    13.01

    22.03

    22.08

    22.11

    22.09

    10.10

    08.05

    22.12

    22.09

    22.09

    22.07

    22.0722.07

    22.10

    22.04

    22.1122.11

    22.1122.11

    08.15

    125B

    117A

    115

    OWS

    50' - 8 3/4" 122' - 8" 50' - 8 3/4"

    08.01

    08.01

    08.01

    08.01

    08.01

    22.02

    08.01

    08.01

    08.01

    08.01

    08.01

    08.01

    08.0108.01

    08.01

    08.01 08.01 08.0108.01

    08.01

    08.01

    113D

    08.05

    08.01

    08.01

    08.01

    08.01

    08.01

    10.01

    08.01

    01.01

    01.01

    01.01

    10.07

    10.07

    10.07

    10.07

    10.07

    10.0710.07

    10.07

    10.07

    10.07

    10.07

    10.07

    07.03

    07.03

    07.03

    07.03

    07.04

    07.04

    07.04

    07.04

    W04

    W03

    W02

    W01

    W05

    WA02

    WA02 WA02

    WA02

    WA02

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    A4A-611

    C3 A-61

    1C4 A-61

    1B2 A-61

    1

    BL

    BL

    BL

    BLCONDENSER

    PAD

    03.03

    10.13

    ENTRY CORRIDOR125

    27.01

    125A

    WA01

    WA01

    13.02

    WA01

    WA01

    WA01

    WA01

    WA01

    WA01

    WA01

    WA01 WA01

    WA01

    WA01

    WA01

    WA01

    WA01

    WA01

    WA01

    WA01 WA01

    WA01

    WA01

    WA01

    WA01

    WA01

    WA01

    WA01

    WA01

    40' - 5" 10' - 2 3/4" 3' - 0" 116' - 11" 3' - 0" 10' - 7 1/4" 19' - 7 3/4" 20' - 3 3/4"

    32' -

    10 3/

    4"3'

    - 0"

    55' -

    10 3/

    4"10

    ' - 0"

    14' -

    2 3/4"

    10' -

    0"33

    ' - 4 1

    /4"

    8' - 8

    "3'

    - 0"

    23' -

    3"3'

    - 0"

    17' -

    2 1/2"

    3' - 0

    "34

    ' - 0 1

    /2"12

    ' - 0"

    10' -

    5 1/2"

    6"11 1/

    4"4'

    - 2"

    2' - 9

    3/4"

    8' - 0

    "4'

    - 4 3/

    4"20

    ' - 0"

    3' - 1

    1 1/4"

    24' - 0"

    10' - 0"

    12' -

    2 3/4"

    36' -

    8 3/4"

    20' -

    9"20

    ' - 10

    3/4"

    13' -

    9 1/4"

    9' - 3

    "8'

    - 6 1/

    4"11

    ' - 5 1

    /2"3'

    - 10"

    22' -

    0"

    CLEA

    R5'

    - 5 1/

    2"CL

    EAR

    7' - 1

    1"

    CLEAR8' - 5"

    2' - 1 1/4"CLEAR

    17' - 2 3/4"

    CLEA

    R9'

    - 0"

    2' - 2

    "CL

    EAR

    9' - 0

    "

    20' - 6 3/4" 7' - 3 1/4" 12' - 1 1/2"

    12' - 5 1/4" 15' - 0" 13' - 0" 10' - 3 3/4" 122' - 8" 10' - 9 1/4" 12' - 10" 5' - 10" 6' - 0" 9' - 6" 5' - 9 1/2"

    WA01WA01

    The

    Con

    tract

    or sh

    all v

    erify

    and

    be

    resp

    onsib

    le fo

    r all d

    imen

    sions

    . DO

    NO

    T sca

    le th

    e dr

    awin

    g -a

    ny e

    rrors

    or o

    miss

    ions

    shal

    l be

    repo

    rted

    to S

    tant

    ec w

    ithou

    t del

    ay.

    The

    Cop

    yrig

    hts t

    o al

    l des

    igns

    and

    dra

    win

    gs a

    re th

    e pr

    oper

    ty o

    f Sta

    ntec

    . Rep

    rodu

    ctio

    n or

    use

    for a

    ny p

    urpo

    se o

    ther

    than

    that

    aut

    horiz

    ed b

    y St

    ante

    c is

    forb

    idde

    n.

    ORIGINAL SHEET - ARCH D

    Drawing No.Revision:

    Permit/Seal

    File Name: N/A

    Title

    PRELIMINARY

    NOT FOR

    CONSTRUCTIONNot for permits, pricing or other official purposes. This document has not been

    completed or checked and is for general information or comment only.

    Revi

    sion

    ByAp

    pdYY

    YY.M

    M.D

    DIss

    ued

    ByAp

    pdYY

    YY.M

    M.D

    D

    1

    A

    2 3 4 5

    B

    C

    D

    YYYY.MM.DDDsgn. Chkd.Dwn.

    TUC

    SON

    INTE

    RNAT

    IONA

    L AIR

    PORT

    Project No.:

    Con

    sulta

    nt

    Scale:

    1011

    9108

    ANG

    -EC

    F HA

    NGAR

    REP

    LAC

    EMEN

    T (B

    RIDG

    ING

    DO

    CUE

    MEN

    TS)

    181710627

    10/2

    4/20

    19 1

    2:42

    :41

    PM

    1" = 10'-0"

    A-101

    100%

    BRI

    DG

    ING

    DO

    CUM

    ENTS

    Author CheckerDesigner 2019.10.25

    LEVEL 01 HANGARFLOOR PLAN

    Stan

    tec

    Arch

    itect

    ure

    Inc.

    1050

    17t

    h St

    reet

    Sui

    te A

    200

    Den

    ver,

    CO

    802

    65-2

    016

    Tel:

    (303

    ) 295

    -171

    7 •

    ww

    w.st

    ante

    c.co

    m

    1" = 10'-0"A-101A4 LEVEL 01 HANGAR FLOOR PLAN

    FLOOR PLAN NOTES

    1 SEE SHEET G-001 FOR GENERAL NOTES, ABBREVIATIONS, ANDANNOTATION SYMBOLS

    2 UTILITIES SHOWN FOR REFERENCE ONLY3 STRUCTURAL FRAME TO BE SIZED BY PEMB MANUFACTURER4 INTERIOR DIMENSIONS ARE TAKEN FROM CENTERLINE GRID,

    RIGHT SIDE OF STUD, OR FACE OF FINISH5 EXTERIOR DIMENSIONS ARE TAKEN FROM BUILDING LINE

    (EXTERIOR FACE OF GIRT)6 MEZZANINE IS TO BE FRAMED FOR FUTURE EXPANSION7 ALL INTERIOR PARTITIONS UP TO DECK TO BE SUPPLIED WITH

    SLIP-TYPE HEAD RUNNERS SIZED TO ACCOMODATE BUILDINGDEFLECTION

    SHEET NOTES

    01.01 TEMPORARY WALL - FUTURE DEMOLITION FOR USE OFMEZZANINE

    03.03 DESIGN-BUILD TO SIZE CONDENSER PAD APPROPRIATELY05.01 STRUCTURAL STEEL FRAMING - REF: PEMB MFR07.03 SHEET METAL FLASHING AND TRIM - DOWNSPOUT; SHEET

    FLOW ACROSS PARKING, REF: CIVIL07.04 SHEET METAL FLASHING AND TRIM - DOWNSPOUT; REF:

    CIVIL08.01 HOLLOW METAL DOORS AND FRAMES08.05 OVERHEAD COILING DOOR08.15 HANGAR DOOR, SIX PANEL POCKETED W/MAN DOOR - REF:

    DOOR SCHEDULE10.01 SAFETY STRIPING10.03 CHAIN LINK FENCE PARTITION10.07 FIRE EXTINGUISHERS - WALL MOUNTED WITH HANGER10.10 BATH ACCESSORIES - ADA BENCH10.13 ALUMINUM ENTRY CANOPY - ACCENT PAINT13.01 CONTROLLED ENVIRONMENT ROOMS - PAINT BOOTH; UNIT

    TO BE RELOCATED FROM EXISITNG SPACE13.02 CONTROLLED ENVIRONMENT ROOMS - DUST BOOTH; UNIT

    TO BE RELOCATED FROM EXISITNG SPACE22.02 TRENCH DRAIN TO OIL/WATER SEPERATOR22.03 PLUMBING FIXTURES - EMERGENCY EYEWASH /SHOWER22.04 COMMERCIAL PLUMBING FIXTURES - DRINKING FOUNTAIN22.07 COMMERCIAL PLUMBING FIXTURES - WATER CLOSET : WALL

    MOUNTED22.08 COMMERCIAL PLUMBING FIXTURES - ADA_SHOWER HEAD &

    HANDLE22.09 COMMERCIAL PLUMBING FIXTURES - ADA_WATER CLOSET :

    WALL MOUNTED22.10 COMMERCIAL PLUMBING FIXTURES - ADA_URINAL : WALL

    MOUNTED22.11 COMMERCIAL PLUMBING FIXTURES - ADA_LAVATORY22.12 COMMERCIAL PLUMBING FIXTURES - MOP SINK27.01 DATA COMMUNICATIONS TOWER: SHOWN FOR LOCATION,

    PROVIDED BY OTHERSWA01 5/8" GYPSUM BOARD ON 6" METAL STUD @ 16" 0.C.; UP TO

    DECKWA02 METAL WALL PANEL ASSEMBLY TO BE MANUFACTURER

    STANDARD; DESIGNED TO MEET IECC 2018 THERMALINSULATION REQUIREMENTS

    NORTH

  • PHASING LEGENDA4A-201

    B2 A-20

    1

    D4A-201

    B4 A-20

    1

    3

    A B C D G J

    2

    F HE

    4

    8

    1

    5

    6

    7

    9

    A-301D4_______

    A-301A4_______

    4 1/4"

    10 1/

    4"

    27' - 3 1/4" 12' - 11" 10' - 6 1/2" 61' - 4" 61' - 4" 10' - 6 1/2" 12' - 11" 27' - 3 1/4"224' - 1 1/2"

    50' - 8 3/4" 122' - 8" 50' - 8 3/4"

    1' - 2

    1/2"

    26' -

    2"26

    ' - 2"

    26' -

    2"26

    ' - 2"

    26' -

    2"26

    ' - 2"

    1' - 2

    1/2"

    159'

    - 4 1/

    2"

    FUTURE MEZZANINE BUILD-OUTMAXIMUM 30 OCCUPANTS

    01.01

    01.01

    01.01

    05.14

    W06W06

    A4A-611

    C3 A-61

    1C4 A-61

    1B2 A-61

    1

    BL

    BL

    BL

    BL

    10.12

    10.12

    10.13

    PROPOSED WALL FOR FUTURE EXPANSION (NOT IN CONTRACT)

    PROPOSED DOOR FOR FUTURE EXPANSION(NOT IN CONTRACT)

    The

    Con

    tract

    or sh

    all v

    erify

    and

    be

    resp

    onsib

    le fo

    r all d

    imen

    sions

    . DO

    NO

    T sca

    le th

    e dr

    awin

    g -a

    ny e

    rrors

    or o

    miss

    ions

    shal

    l be

    repo

    rted

    to S

    tant

    ec w

    ithou

    t del

    ay.

    The

    Cop

    yrig

    hts t

    o al

    l des

    igns

    and

    dra

    win

    gs a

    re th

    e pr

    oper

    ty o

    f Sta

    ntec

    . Rep

    rodu

    ctio

    n or

    use

    for a

    ny p

    urpo

    se o

    ther

    than

    that

    aut

    horiz

    ed b

    y St

    ante

    c is

    forb

    idde

    n.

    ORIGINAL SHEET - ARCH D

    Drawing No.Revision:

    Permit/Seal

    File Name: N/A

    Title

    PRELIMINARY

    NOT FOR

    CONSTRUCTIONNot for permits, pricing or other official purposes. This document has not been

    completed or checked and is for general information or comment only.

    Revi

    sion

    ByAp

    pdYY

    YY.M

    M.D

    DIss

    ued

    ByAp

    pdYY

    YY.M

    M.D

    D

    1

    A

    2 3 4 5

    B

    C

    D

    YYYY.MM.DDDsgn. Chkd.Dwn.

    TUC

    SON

    INTE

    RNAT

    IONA

    L AIR

    PORT

    Project No.:

    Con

    sulta

    nt

    Scale:

    1011

    9108

    ANG

    -EC

    F HA

    NGAR

    REP

    LAC

    EMEN

    T (B

    RIDG

    ING

    DO

    CUE

    MEN

    TS)

    181710627

    10/2

    4/20

    19 1

    2:42

    :45

    PM

    As indicated

    A-102

    100%

    BRI

    DG

    ING

    DO

    CUM

    ENTS

    Author CheckerDesigner 2019.10.25

    MEZZANINE HANGARFLOOR PLAN

    Stan

    tec

    Arch

    itect

    ure

    Inc.

    1050

    17t

    h St

    reet

    Sui

    te A

    200

    Den

    ver,

    CO

    802

    65-2

    016

    Tel:

    (303

    ) 295

    -171

    7 •

    ww

    w.st

    ante

    c.co

    m

    1" = 10'-0"A-102A4 MEZZANINE HANGAR FLOOR PLAN

    FLOOR PLAN NOTES

    1 SEE SHEET G-001 FOR GENERAL NOTES, ABBREVIATIONS, ANDANNOTATION SYMBOLS

    2 UTILITIES SHOWN FOR REFERENCE ONLY3 STRUCTURAL FRAME TO BE SIZED BY PEMB MANUFACTURER4 INTERIOR DIMENSIONS ARE TAKEN FROM CENTERLINE GRID,

    RIGHT SIDE OF STUD, OR FACE OF FINISH5 EXTERIOR DIMENSIONS ARE TAKEN FROM BUILDING LINE

    (EXTERIOR FACE OF GIRT)6 MEZZANINE IS TO BE FRAMED FOR FUTURE EXPANSION7 ALL INTERIOR PARTITIONS UP TO DECK TO BE SUPPLIED WITH

    SLIP-TYPE HEAD RUNNERS SIZED TO ACCOMODATE BUILDINGDEFLECTION

    SHEET NOTES

    01.01 TEMPORARY WALL - FUTURE DEMOLITION FOR USE OFMEZZANINE

    05.14 PROTECTIVE GUARDRAIL 42" IN HEIGHT, 1 1/2" PIPE ANDTUBING, WITH STRUCTURAL CONNECTION TO FLOOR ANDWALL

    10.12 ALUMINUM TURNBUCKLE STYLE CANOPY10.13 ALUMINUM ENTRY CANOPY - ACCENT PAINT

    NORTH

  • A4A-201

    B2 A-20

    1

    D4A-201

    B4 A-20

    1

    3

    A B C D G J

    2

    F HE

    4

    8

    1

    5

    6

    7

    9

    A-301D4_______

    A-301A4_______

    2:12

    05.05

    2:12

    05.05

    05.0505.05

    07.0207.02

    27' - 3 1/4" 12' - 11" 10' - 6 1/2" 61' - 4" 61' - 4" 10' - 6 1/2" 12' - 11" 27' - 3 1/4"224' - 1 1/2"

    1' - 2

    1/2"

    26' -

    2"26

    ' - 2"

    26' -

    2"26

    ' - 2"

    26' -

    2"26

    ' - 2"

    1' - 2

    1/2"

    159'

    - 4 1/

    2"

    08.11

    08.11

    08.11

    08.11

    08.11 08.11

    08.11

    08.11

    08.11

    08.11

    A4A-611

    C3 A-61

    1C4 A-61

    1B2 A-61

    1

    BL

    BL

    BL

    BL

    27.01

    23' -

    10"

    2' - 0

    "50

    ' - 1 1

    /4"2'

    - 0"

    64' -

    1 1/2"

    2' - 0

    "15

    ' - 6 1

    /4"

    10' - 0" 15' - 3 3/4"

    10' - 0" 15' - 3 3/4"

    10' - 0" 15' - 3 3/4"41

    ' - 10

    1/4"

    2' - 0

    "56

    ' - 1 1

    /4"2'

    - 0"

    57' -

    7 1/4"

    10' - 0" 79' - 6 1/4"

    10' - 0" 79' - 6 1/4"

    41' -

    10 1/

    4"2'

    - 0"

    56' -

    1 1/4"

    2' - 0

    "57

    ' - 7 1

    /4"

    79' - 6" 10' - 0"

    79' - 6" 10' - 0"

    23' -

    10"

    2' - 0

    "50

    ' - 1 1

    /4"2'

    - 0"

    64' -

    1 1/2"

    2' - 0

    "15

    ' - 6 1

    /4"15' - 2 1/2" 10' - 0"

    15' - 2 1/2" 10' - 0"

    15' - 2 1/2" 10' - 0"

    07.03

    07.03

    07.03

    07.03

    07.04

    07.04

    07.04

    07.04

    The

    Con

    tract

    or sh

    all v

    erify

    and

    be

    resp

    onsib

    le fo

    r all d

    imen

    sions

    . DO

    NO

    T sca

    le th

    e dr

    awin

    g -a

    ny e

    rrors

    or o

    miss

    ions

    shal

    l be

    repo

    rted

    to S

    tant

    ec w

    ithou

    t del

    ay.

    The

    Cop

    yrig

    hts t

    o al

    l des

    igns

    and

    dra

    win

    gs a

    re th

    e pr

    oper

    ty o

    f Sta

    ntec

    . Rep

    rodu

    ctio

    n or

    use

    for a

    ny p

    urpo

    se o

    ther

    than

    that

    aut

    horiz

    ed b

    y St

    ante

    c is

    forb

    idde

    n.

    ORIGINAL SHEET - ARCH D

    Drawing No.Revision:

    Permit/Seal

    File Name: N/A

    Title

    PRELIMINARY

    NOT FOR

    CONSTRUCTIONNot for permits, pricing or other official purposes. This document has not been

    completed or checked and is for general information or comment only.

    Revi

    sion

    ByAp

    pdYY

    YY.M

    M.D

    DIss

    ued

    ByAp

    pdYY

    YY.M

    M.D

    D

    1

    A

    2 3 4 5

    B

    C

    D

    YYYY.MM.DDDsgn. Chkd.Dwn.

    TUC

    SON

    INTE

    RNAT

    IONA

    L AIR

    PORT

    Project No.:

    Con

    sulta

    nt

    Scale:

    1011

    9108

    ANG

    -EC

    F HA

    NGAR

    REP

    LAC

    EMEN

    T (B

    RIDG

    ING

    DO

    CUE

    MEN

    TS)

    181710627

    10/2

    4/20

    19 1

    2:42

    :48

    PM

    1" = 10'-0"

    A-105

    100%

    BRI

    DG

    ING

    DO

    CUM

    ENTS

    Author CheckerDesigner 2019.10.25

    HANGAR ROOF PLAN

    Stan

    tec

    Arch

    itect

    ure

    Inc.

    1050

    17t

    h St

    reet

    Sui

    te A

    200

    Den

    ver,

    CO

    802

    65-2

    016

    Tel:

    (303

    ) 295

    -171

    7 •

    ww

    w.st

    ante

    c.co

    m

    1" = 10'-0"A-105A4 HANGAR ROOF PLAN

    SHEET NOTES

    05.05 STRUCTURAL STANDING SEAM METAL ROOF; METALPANELS AND INSULATION DESIGNED TO MEET IECC 2018REQUIREMENTS

    07.02 SHEET METAL FLASHING AND TRIM - GUTTER07.03 SHEET METAL FLASHING AND TRIM - DOWNSPOUT; SHEET

    FLOW ACROSS PARKING, REF: CIVIL07.04 SHEET METAL FLASHING AND TRIM - DOWNSPOUT; REF:

    CIVIL08.11 UNIT SKYLIGHTS27.01 DATA COMMUNICATIONS TOWER: SHOWN FOR LOCATION,

    PROVIDED BY OTHERS

    ROOF PLAN NOTES

    1 DIMENSIONS ARE TAKEN FROM CENTERLINE GRID ORFACE OF WALL

    NORTH

  • APC: 2x4 LAY-IN CEILING SYSTEM

    GYP: GYPSUM BOARD CEILING

    RCP LEGEND

    OPEN TO DECK

    3

    A B C D G J

    2

    F HE

    4

    8

    1

    5

    6

    7

    9

    A-301D4_______

    A-301A4_______

    GYP 9' - 0"

    PAINT BOOTH103

    DUST BOOTH105

    SHEET METAL SHOP104

    COMP106

    GROUND SUPPORT102

    STOCK ROOM101

    HANGAR BAY107

    TELECOM/SECURITY108 ELEC

    109

    MECH111

    RISER112

    ASSEMBLY QA113

    AVIONICS LAB116

    PARTS ROOM117

    LOCAL ENGINNERING OFFICE118

    JANITOR119

    CUSTOMER OFFICE121

    REPAIR STATION OFFICE123 BREAK ROOM122

    APC 9' - 0"

    APC 9' - 0"

    APC 9' - 0"

    UNISEX RR124

    APC 9' - 0"

    APC 9' - 0"

    GYP 9' - 0"

    GYP 9' - 0"

    WOMENS RR114

    MENS RR115

    08.11

    08.11

    08.11

    08.11

    08.11 08.11

    08.11

    08.11

    LINE OF MEZZANINE ABOVE

    APC 9' - 0"

    27' - 3 1/4" 12' - 11" 10' - 6 1/2" 61' - 4" 61' - 4" 10' - 6 1/2" 12' - 11" 27' - 3 1/4"224' - 1 1/2"

    1' - 2

    1/2"

    26' -

    2"26

    ' - 2"

    26' -

    2"26

    ' - 2"

    26' -

    2"26

    ' - 2"

    1' - 2

    1/2"

    159'

    - 4 1/

    2"

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    05.01

    BL

    BL

    BL

    BL

    10.13

    10.12

    10.12

    26.02

    26.02

    26.0226.0226.0226.0226.0226.02

    26.02 26.02 26.02 26.02 26.02 26.02 26.02

    26.02 26.02 26.02 26.02 26.02 26.02 26.02

    26.02 26.02 26.02 26.02 26.02 26.0226.02 26.02

    26.02 26.02 26.02 26.02 26.0226.02 26.02

    26.0226.02

    26.0226.0226.0226.02 26.0226.02

    26.04 26.04 26.04

    26.04 26.04 26.0426.04 26.04 26.04

    26.04 26.04 26.04

    26.04 26.04

    26.04 26.0426.05 26.05

    26.05 26.05

    26.03 26.03 26.03 26.03

    26.03

    26.03

    26.0426.04

    26.04 26.04

    26.04 26.04

    26.0426.0426.04

    26.04 26.04 26.04

    26.0426.0426.04 26.04 26.04 26.04

    26.04 26.04 26.04 26.04 26.04 26.04

    26.0226.02

    26.02

    26.02 26.02

    26.0526.05

    26.05

    26.05

    26.05

    26.05

    26.05 26.05

    26.05

    26.05

    26.05

    26.05

    26.03 26.03

    26.03

    27.01

    The

    Con

    tract

    or sh

    all v

    erify

    and

    be

    resp

    onsib

    le fo

    r all d

    imen

    sions

    . DO

    NO

    T sca

    le th

    e dr

    awin

    g -a

    ny e

    rrors

    or o

    miss

    ions

    shal

    l be

    repo

    rted

    to S

    tant

    ec w

    ithou

    t del

    ay.

    The

    Cop

    yrig

    hts t

    o al

    l des

    igns

    and

    dra

    win

    gs a

    re th