Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8...

13
Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate HSE, Statoil 1st International Conference on Clean Development Mechanisms Riyadh, Saudi Arabia 19-21. September 2006

Transcript of Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8...

Page 1: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

Norwegian Carbon Capture and Storage Projects

Helge Lund, President & CEOCapital Markets Update8 June 2005

Tor Fjæran, Senior Vice President Corporate HSE, Statoil

1st International Conference on Clean Development MechanismsRiyadh, Saudi Arabia 19-21. September 2006

Page 2: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

2

Carbon Capture and Storage Projects

Sleipner

Snøhvit

Norway

Halten CO2

Page 3: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

3

The Sleipner experience – our starting point

• Started in 1996 separating and injecting 1 mill. tons CO2 annually

• Storing in saline aquifer above reservoir

• Global demostration case

1996 1999 2001

Page 4: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

4

Page 5: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

5

Sleipner CO2 dissolution model

After 25 yrs After 400 yrs

After 600 yrs After 3000 yrs After 5000 yrs

Source: Gemini No. 1, 2004 (NTNU and Sintef)

Page 6: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

6

Snøhvit LNG – offshore piped and stored CO2

• Starts in 2007

• Piped CO2 from onshore LNG plant

• Storing 700.000 tons CO2

annually

• Injecting below reservoir

Page 7: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

7

Snøhvit – Gas and CO2 flow

OFFSHORE

CO2

Wellstream

ONSHORE

Page 8: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

8

Reinjecting 700.000 tons CO2/year

Page 9: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

9

The Halten CO2 Project

Page 10: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

10

Halten CO2 value chain principles

Power

plant

2011/12

Heidrun

2018/24Gas

EOR OilEOR Oil

CO2Capture

2011/12

CO2quotas

Draugen

2011/12

Electricity

Heat

Electricity

Electricity CO2 Oil Gas

Page 11: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

11

An Industrial Solution

A win-win-win for:

• Industry

– Large-scale CO2 for EOR

– Improved security of supply

•Environment

– Reduction of CO2 and NOx emissions through offshore electrification

– Industrial utilisation of greener fossil fuel technologies with a global market potential

• Society

– Prolonged field life and increased oil recovery

– National electricity grid benefits

Society

Environment

Industry

Page 12: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

12

R&D key to future solutions

TRUST

COST

Storage

Capture

OK!Transport- Pipeline - Ship

SACSCASTOR-S

CO2STORE

CO2SINK

CO2ReMoVe ?

Dynamis ?ENCAP

CASTOR-C Hypogen Coal?

Hypogen Gas?

2005

CO2NET

GESTCO

Page 13: Norwegian Carbon Capture and Storage Projects Helge Lund, President & CEO Capital Markets Update 8 June 2005 Tor Fjæran, Senior Vice President Corporate.

13

Summary and conclusions

• CCS technically proven

• Enormous potential

• Value chain approach

• Financial mechanisms key to initiate projects

• Key element in meeting the global climate challenge