North Hoyle and RhylFlats Offshore Wind Farms - snh.org.uk · PDF fileRWEInnogy 7/17/2009 PAGE...
Transcript of North Hoyle and RhylFlats Offshore Wind Farms - snh.org.uk · PDF fileRWEInnogy 7/17/2009 PAGE...
North Hoyle and Rhyl Flats
Offshore Wind Farms:
Review of good practice in monitoring,
construction and operation
Jamie May
RWE Innogy 7/17/2009 PAGE 2
RWE npower renewables (NRL)
> UK subsidiary of RWE Innogy, a pan-European renewable energy company
> Offshore wind projects operating, in development and in construction across the UK, Netherlands, Germany and Belgium.
> NRL currently owns and operates 533MW.
> Now operates 150MW of offshore wind in total.
> 7 onshore wind farms (196MW), 11 hydro stations (18MW) in Scotland,
> Further 2700MW Offshore Wind in UK development, excluding Round 3.
North Hoyle, N. Wales
RWE Innogy 7/17/2009 PAGE 3
Offshore Projects
Offshore Wind interests throughout the UK
Gwynt y Môr, Rhyl Flats, North Hoyle
Greater Gabbard
Inch Cape
Triton Knoll
RWE Innogy 7/17/2009 PAGE 4
North Hoyle: Background
> First commercial UK Offshore Wind Farm, built in 2003.
> 60MW consisting of 30 Vestas V80 2MW turbines.
> 87.4% availability (after 3rd year of operation, 2007). Improved in 2008.
> Generates enough electricity to meet the average annual needs of 40,000 homes.
> Total project capital cost of £81m, £1.35m/MW.
RWE Innogy 7/17/2009 PAGE 5
North Hoyle from Bryn-llwyn AONB Viewpoint 2003
RWE Innogy 7/17/2009 PAGE 6
North Hoyle: FEPA Key Facts
> First UK offshore wind project to complete its FEPA monitoring campaign
> 5 years of monitoring
> Studies from CEFAS, ESS, CMACS, CFCM, MarineSeen, Osiris, COWRIE
> Surveys going back to 2001
> Additional research into foundation colonisation
> Final report can be viewed and downloaded at: http://www.npower-renewables.co.uk/northhoyle/environment.asp
RWE Innogy 7/17/2009 PAGE 7
Key environmental assessment predications tested
by the FEPA monitoring
> Benthic ecology unaffected bar minor and localised impacts from construction which would rapidly recover.
> Extensive colonisation of the turbines will occur allowing an increase in local species diversity and productivity.
> Assumed disturbance of Red Throated Diver and Scoter at up to 2km during wind farm operation, no disruption to flight paths and no direct habitat loss.
> No significant impact on Liverpool Bay or Eastern Irish Sea Marine Mammal populations.
RWE Innogy 7/17/2009 PAGE 8
2m Beam Trawl Programme
> 22 sites; 2m beam; chain mat; 4mm cod end; 300m tows
> surveyed annually in August 2001 and autumn 2003-2006
> Only likely to detect changes attributable to OWF if very large.
RWE Innogy 7/17/2009 PAGE 9
Beam Trawl Conclusions
32 species recorded from the
trawls over 5 year period
No evidence to suggest that the
fish and epifaunal marine
communities altered when
compared to 2001 baseline
Major trends in abundance and
diversity evident across all the
monitoring sites including near-
field and far-field controls and
across all survey years appear
to be within the bounds of
natural variation.
RWE Innogy 7/17/2009 PAGE 10
Colonisation Surveys 2004
> Large shoals of juvenile whiting were observed around all the underwater structures studied:
> 6 monopiles studied (in place for c 1 yr)
> Turbines were operating during surveys
RWE Innogy 7/17/2009 PAGE 11
Colonisation Survey 2008
>Much poorer visibility
>Juvenile Cod and Plaice were observed on the seabed in proximity to turbines
>Whiting seen but unconfirmed abundance
RWE Innogy 7/17/2009 PAGE 12
Marine Mammals
Monthly Harbour Porpoise Sightings
0
1
2
3
4
5
6
7
8
Jan-03
Mar-03
May-03
Jul-03
Sep-03
Nov-03
Jan-04
Mar-04
May-04
Jul-04
Sep-04
Nov-04
Jan-05
Mar-05
May-05
Jul-05
Sep-05
Nov-05
Jan-06
Mar-06
May-06
Jul-06
Sep-06
Nov-06
Jan-07
Month
Number of Harbour Porpoise
Post-constructionPre-construction
During Construction
> Ad hoc sightings during environmental surveys
> Sightings largely in winter/spring.
> NB 1 data have not been standardised by effort or conditions.
> Gaps in 2005 data collection
RWE Innogy 7/17/2009 PAGE 13
0
100
200
300
400
500
600
700
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Month
Maximum and Average Monthly counts of Atlantic Grey
Seal
1960
1970
1980
1990
2001
2002
2003
2005
Hilbre Island Grey Seal Data Records
During
construction
Yr 1 post-
construction
First piling
events
RWE Innogy 7/17/2009 PAGE 14
FEPA Bird Monitoring Objectives
1. Determine if the wind farm causes a change in bird use and behaviour
2. Determine if there is a barrier effect to movement of birds through the site.
3. Determine the distribution of Common Scoter in Liverpool Bay, through
continued contribution to the aerial survey.
Supplementary conditions:
4. If Objective 3 shows change in the Common Scoter population, monitor the
benthos to determine if the change is a result of a change in food supply.
5. If Objectives 1 or 2 reveal significant use of North Hoyle by populations of
conservation concern, at heights that could incur a risk of collision, a
programme of collision risk monitoring will be implemented.
RWE Innogy 7/17/2009 PAGE 15
Bird Survey Limitations
Phase Boat Aerial
Pre-
Construction
3 4
Construction 11 4
Operation 33 15
> Only a few surveys were made in
the pre-construction period and
these were in winter months only.
> Boat surveys.
> -No control site (reference site).
-Transect paths not consistent.
> Aerial surveys.
- Unable to survey the wind farm
itself after construction.
- Identification to species groupings
only.
RWE Innogy 7/17/2009 PAGE 16
Flight height and barrier effect
<2.5m 2-5m-
20m
>20m
Auk sp. 191 27 0
Diver sp. 51 14 3
Gannet 28 121 12
Kittiwake 30 291 32
Scoter
sp.
3264 6786 2
Shag sp. 183 179 82
Tern sp. 0 26 1
> Flight directions of scoter appear
to be largely influenced by the
boat.
> Species seen flying within the wind
farm included cormorants, gulls,
terns, gannet and scoter.
> The wind farm may have had an
inhibitory effect, but it has not
been a barrier.
RWE Innogy 7/17/2009 PAGE 17
Ornithological Conclusions> Little statistical evidence of changes in numbers or distribution of any
species.
> No evidence of a barrier effect of the wind farm.
> Few birds of key species were seen flying at rotor blade heights
> Power of tests for changes caused by wind farm is low:
– Few pre-construction surveys.
– No control site for boat surveys.
> Inadequate baseline information implies little value in extra survey work
for this site.
> Boat survey methods are not efficient for studying movements through or
around site.
RWE Innogy 7/17/2009 PAGE 18
Rhyl Flats: Background
> NRLs second Round 1 project
> Originally developed by C.O.W.L. and
bought by NRL in 2002 (EIA by ERM)
> 90MW consisting of 25 Siemens 3.6MW
turbines.
> Constuction started 2007
> Nearing completion, all turbines erected,
first generation was during the summer,
full operation expected before end of
year.
> Total project cost ca. £190m
RWE Innogy 7/17/2009 PAGE 19
Rhyl Flats Project Area
RWE Innogy 7/17/2009 PAGE 20
Sole Spawning Areas: Piling restrictions
> Issue of subsea noise impacts upon sole
spawning raised by Licensing Authority
> Retrospective condition added to FEPA
Licence in 2008.
> No piling between Mar - mid May.
> NRL had identified Sole spawning
hotspots in Liverpool Bay. Negotiation
with Cefas and MFA to stage piling
activity.
> Flexible approach agreed to installation
sequence starting with southernmost
foundation positions in mid April.
RWE Innogy 7/17/2009 PAGE 21
Marine Mammal Observer Monitoring
> Agreed MMO methodology with CCW
with buy-in from JNCC
> Dedicated survey vessel and team
with authority over piling contractor.
> Visual + acoustic monitoring 500m
“zone of harm” to ensure the area is
devoid of marine mammals for a
period of 30 minutes prior to soft-start.
> Soft start piling ramping up SPL to full
force after 20 minutes.
RWE Innogy 7/17/2009 PAGE 22
Underwater Noise at 500m from piling vessel
RWE Innogy 7/17/2009 PAGE 23
Subsea Noise Measurement
RWE Innogy 7/17/2009 PAGE 24
Soft Start compared with full piling force
RWE Innogy 7/17/2009 PAGE 25
Rhyl Flats: Construction Timing Restriction - birds
RWE Innogy 7/17/2009 PAGE 26
Rhyl Flats: Construction Timing Restriction - birds
RWE Innogy 7/17/2009 PAGE 27
Vessel Routing Plan: Common Scoter Avoidance
RWE Innogy 7/17/2009 PAGE 28
Rhyl Flats FEPA Monitoring: Positives
> Successfully extended the cable construction season into the winter by
demonstrating reduced Common Scoter numbers between Oct-Dec
> Monitoring in that period showed no impact in distribution of Scoter from
construction activity
> 30000 bird within the wind farm survey area – only a few hundred flying at rotor
height – i.e. at risk of collision.
> Successfully agreed reduced survey effort to key migration times between
October and March for SPA species Red Throated Diver and Common Scoter.
> Successfully negotiated sole spawning timing restricted with agreed flexible
approach to installation sequence.
RWE Innogy 7/17/2009 PAGE 29
Thank YouJamie May
Offshore Site Acquisition Manager
01793 896324