New North Atlanta High School Weekly Construction Report · New North Atlanta High School Weekly...
Transcript of New North Atlanta High School Weekly Construction Report · New North Atlanta High School Weekly...
New North Atlanta High School
Weekly Construction Report September 27th, 2013
Page 1
NNAHS Weekly Progress Report September 27, 2013
THIS WEEK September 23, 2013 – September 27, 2013
Hillside Building: Completion in end of November, 2013
Picture 1: Hillside letters installed Picture 2: Retaining wall by softball field nearing completion
Picture 3: Stage lighting nearing completion Picture 4: Gymnasium concourse ceiling grid installation
New North Atlanta High School
Weekly Construction Report September 27th, 2013
Page 2
NNAHS Weekly Progress Report September 27, 2013
Hillside Building (cont’d): Completion in end of November, 2013
Picture 5: Acoustic panels installed in gymnasium Picture 6: Lockers installed in gymnasium locker rooms
Picture 7: Coaches bathrooms nearing completion Picture 8: Gymnasium painting
New North Atlanta High School
Weekly Construction Report September 27th, 2013
Page 3
NNAHS Weekly Progress Report September 27, 2013
Hillside Building (cont’d): Completion in end of November, 2013
Picture 9: Proscenium scrim panels installed in auditorium Picture 10: Auditorium concession appliances installed
Picture 11: VCT installed in auditorium corridor Picture 12: Gymnasium storefront installation
New North Atlanta High School
Weekly Construction Report September 27th, 2013
Page 4
NNAHS Weekly Progress Report September 27, 2013
NEXT WEEK
September 23 – September 27, 2013
Auditorium Beginning millwork at stage.
Continuing orchestra pit net installation.
Continuing mainstreet tile.
Continuing speaker installation.
Finishing auditorium corridor VCT. (picture 11)
Finishing mainstreet lighting
Finishing proscenium scrim panels at theater stage. (picture 9)
Finishing dance room mirrors and ballet barres.
Finishing stage lighting installation. (Picture 3)
Finishing auditorium corridor ceiling tile. (Picture 4)
Gymnasium Beginning basketball court wood flooring.
Beginning tile installation in coaches’ bathrooms. (picture 7)
Continuing gymnasium door hanging.
Continuing gymnasium paint. (picture 8)
Continuing polishing concrete flooring in gymnasium.
Continuing railings at concourse.
Continuing acoustic panels in gymnasium (Picture 5)
Finishing locker installation. (picture 6)
Finishing epoxy floors in bathrooms.
Finishing athletic storage cages and sealing floors.
Sitework Beginning discuss cage (picture2)
Beginning tree planting
Beginning concrete flatwork at north end of gymnasium.
Continuing sidewalks between concessions building, softball field and tennis courts.
Continuing irrigation at softball and baseball field.
Finishing installation of coping on roof.
Finishing plaza paving.
Finishing coping on roof