New microsoft office word document (2)

20
Support Package Upgrade by using SUM[Software update manager] Posted on April 29, 2013 by Sabarish Vasudevan What is SP upgrade: A Support Package contains a collection of error corrections. You can only import complete Support Packages and in a specified sequence. Each correction in a Support Package is documented in an SAP Note. After you have imported a Support Package, you must perform the Modification Adjustment using transaction SPAU. Basis responsiblity to maintain the system at latest level or N-1 level at MAX. Prerequisites: Import thing is before start the SP upgrade maintain the kernel at latest level. or skip the kernel part while generating stack for SP upgrade. Make sure to put the maintenance certificate before kick off SP upgrade. Delete the old spool number in SAP system before start the SP upgrade. Maintain minimum 48 GB free in Database to run SUM tool. Here am going to do SP upgrade by using SUM tool. So before start using read the SUM manual for quick action. Note: SUM tool have the option to upgrade both ABAP + JAVA stack at same time. Step 1:Download SUM[Software update manager] latest version from service market place In my case am using SUM 1.0 SP06. PFB

description

New microsoft office word document (2)

Transcript of New microsoft office word document (2)

Page 1: New microsoft office word document (2)

Support Package Upgrade by using SUM[Software update manager]Posted on April 29, 2013 by Sabarish Vasudevan

What is SP upgrade:

A Support Package contains a collection of error corrections. You can only import complete Support Packages and in a specified sequence. Each correction

in a Support Package is documented in an SAP Note. After you have imported a Support Package, you must perform the Modification Adjustment using

transaction SPAU. Basis responsiblity to maintain the system at latest level or N-1 level at MAX.

Prerequisites:

Import thing is before start the SP upgrade maintain the kernel at latest level. or skip the kernel part while generating stack for SP upgrade.

Make sure to put the maintenance certificate before kick off SP upgrade.

Delete the old spool number in SAP system before start the SP upgrade.

Maintain minimum 48 GB free in Database to run SUM tool.

Here am going to do SP upgrade by using SUM tool. So before start using read the SUM manual for quick action.

Note: SUM tool have the option to upgrade both ABAP + JAVA stack at same time.

Page 2: New microsoft office word document (2)

Step 1:Download SUM[Software update manager] latest version from service market place In my case am using SUM 1.0 SP06. PFB

Please make a

note of HTTP Listening port number. In my case -4239

Page 3: New microsoft office word document (2)

Step 2: How to

start the SUM tool? Here am going to share the step by screen shots to open the SUM tool. PFB for your reference.

Page 4: New microsoft office word document (2)

Step 3: Here i

was done SP upgrade for dual stack. As i stated earlier we can upgrade ABAP+JAVA at the same time to reduce the downtime.

Fill the OS

level password ie SIDADM password.

Page 5: New microsoft office word document (2)

Step 4: We

have successfully generated stack.XML file before start the SP upgrade and put into EPS\In folder and specify as same below.[For how to generate

stack.XML file, refer my blog]

Step 5:Refer

SAP note 1707161 and do the needful i.e update the keyword below to proceed further.

Page 6: New microsoft office word document (2)

  Step 6:

Complete the initialization part ans click next.

  Step

7:Provide DDIC[000 Client] user password to extract the system information

Page 7: New microsoft office word document (2)

  Step 8:

SPAM version is too low to proceed further so we have imported latest version of SPAM.

Page 8: New microsoft office word document (2)

  Step

9:Currently extraction phase running on. Middle of extraction phase SAP recommended notes missing from our system, so first implement the below listed

SAP notes to proceed further steps.

 

Page 9: New microsoft office word document (2)

 

  Step 10: We

have moved to configuration phase, ie very import phase like back bone of our SP upgrade.

Page 10: New microsoft office word document (2)

  In this

configuration phase we can set the number of parallel process should run during our SP upgrade.  

Page 12: New microsoft office word document (2)

Step 11:  Currently configuration part running on. it will give the system information.

Page 14: New microsoft office word document (2)

At this phase, handover the system to developer and capture the SPAU and SPDD correction in transport number and fill the same below as well.

Step 12: Beauty of SUM tool concepts is, create the shadow system and upgrade it first then if successful means copy the same to  our original

system

Page 15: New microsoft office word document (2)

Now here ABAP phase completed successfully. we will go for JAVA part.

Page 18: New microsoft office word document (2)

 

java got completed successfully.

Step 14: Likewise checks run for both ABAP+JAVA.

Preprocessing phase-Shadow system to be created end of preprocessing phase.

Execution phase- upgrade the shadow system first and check if SP upgrade is successful?

Postprocessing phase-copy the shadow instance ie upgraded system to our target system.

Page 20: New microsoft office word document (2)

 

Finally we have successfully completed SP upgrade by using SUM[Software update manager].