Net Metering implementation in Indian States
for Rooftop Solar Deployment
- State in Focus : Madhya Pradesh
23 September 2015
Partnership to Advance Clean Energy - Deployment
(PACE-D)
Technical Assistance Program
2
Renewable Energy Energy Efficiency Cleaner Fossil
USD 20 million, five year bilateral
program between the U.S. and India
to accelerate clean energy
deployment (2012-2017)
Being implemented by Nexant Inc.
and a consortium of Indian and U.S.
partners.
Program Overview
5
Tasks under Renewable Energy Component
Institutional Development and
Strengthening of State Policy & Regulatory
Framework for RE Deployment
Improve capacity of SNAs and SERCs, and develop
enabling policy and regulatory environment for market
deployment of RE
Create a RE market via demonstration of techno-
commercially viable pilots in the off-grid/storage domain
and develop a national level apex RE institution
Market-driven RE Technology
Deployment
Technical Assistance and Capacity
Building to Develop and Implement
Innovative Finance Mechanisms
Identify and design innovative financing
mechanisms to facilitate deployment of market-
driven RE
Capacity Building, Training, Outreach,
Dissemination and Sharing of Best
Practices
Improve capacities of stakeholders on policy,
regulatory and technical aspects for large-scale
RE deployment
Regulator Partnership
Build partnerships between regulators in India & the
U.S. to bolster institutional capacity & practices in
market
Microfinance Support Program
Enhance microfinance lending for RE
technologies - particularly for women and energy
access in rural areas
Solar Rooftop BESCOM’s Solar PV Rooftop Program
launched [1.5 MW (16.5 MW- pipeline)]
Solar rooftop program for Rajasthan designed
IOCL
• 5MW Rooftop deployment at 3 refineries
• Policy Directive by IOCL - all buildings to
deploy rooftop solar
• Proposed 30 MW rooftop deployment on
refineries, petrol pumps etc.
Indian Railways : 50 MW Solar Rooftop
Program
Solar Rooftop Evaluation Tool – launched
for use by Banks and Developers
4 Solar Rooftop Training Programs
Solar Pumping Grid Connected Solar Pumping with BESCOM:
Design of Pilot under Surya Raitha Scheme : 2 MW (256 pumps; INR 21 Cr)
Shared Service Model for Decentralized Solar Water
Pumping: 0.05 MW
Training & Capacity Building Solar Energy Training Network (SETNET)
Launched with 35 partners
National Workshop on Clean Energy
Regulations & Policies Organized
Microfinance Support Program
Clean Energy Lending Program launched with 7 MFIs
Pilot lending projects initiated with 2 MFI’s - 10000
solar products sold in 3 months
1,234 person hours of training delivered
Renewable Energy Financing Decentralized Distributed Generation Debt Fund
with The Climate Group (corpus Rs. 2.5 Crore)
Green Bonds - IIFCL (500 Cr.), IREDA & Yes Bank
Infrastructure Debt Fund (IDF-MF) with IIFCL ~ Rs.
1000 Cr.
Distributed Renewable Energy Community Fund
with CREDA
PACE-D TA Program - Renewable Energy Achievements
9
Sector Installed by SECI (MW) Installed by States (MW) Total installed (MW)
Commercial 10.9 17.2 28.9
Government 3.0 4.9 7.3
Hospital 1.6 0.5 2.1 Institutional (Schools,
Collages) 2.2 5.1 8.3
Religious institution 0.6 7.5 7.6
Residential 0.0 0.3 0.3
Total 18.35 35.532 54.187
• India’s solar rooftop market potential
~124 GW
• India has set an ambitious target of 40
GW by 2022
• 13 States have notified Solar Policy’s
supporting grid connected rooftop
systems
• 19 states/ UTs have notified regulations
for net metering/feed-in-tariff mechanisms
India’s solar rooftop journey has just started - the sector has the potential for rapid scale
up – right now the sector is still in infancy
Policy and Regulation
Program Design
Process Design and Standardization
Financing
Capacity Building
Knowledge Creation
Programmatic approach : working on policy advisory, program and process
design, capacity building of key stakeholders and knowledge creation
Rajasthan and Karnataka
Indian Oil & Indian Railways
BESCOM & JVVNL
(IREDA & TATA Cleantech)
NISE/ BESCOM/ JVVNL
MNRE & GERMI
• Identifying opportunities (IOCL & IR - Refineries, retail outlets and stations/ workshops)
• Defining potential/ location of sites – 3 refineries (IOCL), 4 workshops/ stations (IR)/ 500 retail outlets
• Feasibility Analysis and Business Case Development (IOCL/ IR)
• Allotment of Incentives/ deployment support (IOCL)
• Bid design and financial feasibility analysis
• Implementation Support (5 MW (IOCL) / 50 MW (IR))
Program Design & Development
• Mapping process for interconnection for state utilities (BESCOM & JVVNL)
• Designing forms, formats, systems and procedures for rooftop for BESCOM & JVVNL
• Identifying Best Practices for Implementation & assisting adoption of standards and empanelment of suppliers
Process Design
We have been using the programmatic approach to address a number of diverse yet
critical solar rooftop eco-system areas for sola rooftop deployment – the most critical of
which have been Program Design and Process Design
• Designing the Net Metering Framework for Solar Rooftop Program Roll out (Rajasthan)
• Supporting Utility Petition for rooftop & release of regulation (Rajasthan)
• Designing Alternate Incentive Structures for Rooftop Promotion (e.g. Feed in Tariffs for Karnataka)
Policy & Regulation
• Best Practices Guide for Promotion of Solar Rooftop
• Solar Rooftop Evaluation Tool for FI’s
• Training Program design for Utilities and key stakeholders on solar rooftop
Capacity Building/ Financing & Knowledge
Management
However we feel that designing the appropriate incentive structures and backing
these up with the right tools like training and knowledge management are equally
important in the medium to long term
13
Broad Objectives
Energy Security Reduction of
Losses
Reducing burden
from Utilities
Optimizing
Infrastructure
Investment
Development of Solar Rooftops
Rooftop Policy/Regulations
Defining Roles
Framing
Guidelines Incentive/
Subsidy
Setting Targets
Market Models Gross Metering Net Metering
Self Owned or
3rd Party Owned
Self Owned or
3rd Party Owned Implementation Framework by Utilities
Case to case
basis
On available
capacity
Policy Regulation Implementation
Department of New &
Renewable Energy,
Government of Madhya
Pradesh (No Role in
Implementation)
Madhya Pradesh State
Electricity Regulatory
Commission
(Minimal Role in
Implementation)
State Distribution
Company/ Consumers/
System Providers/
Channel Partners
(Key Role in
Implementation)
Development Stages & Key Stakeholders
Cost Benefit Analysis and
Investment
Application/ Identification of
system provider
Consumer
System design
Meeting technical standards
and utility requirements
System Provider
Process design &
integration with utility
business practices
Formats and Forms
Utility
15
Broad requirements for designing “Implementation Framework”
Phase -1 Information
Access
Phase-2 Application
Process
Phase-3 Application Screening
Phase-4 Installation/ Inspection
Phase -5 Post
Installation
To develop information bank for Consumers to educate them with respect to solar rooftop, Connectivity requirement , safety etc.
To develop Multi User Application
form required for availing net
metering facility/
connectivity
Developing process to
examine and Shortlist the application based on
technical and safety
parameters
To Approve & Inspect the
rooftop facility before
interconnection with the grid
To perform period checks/
inspections Metering, and monitoring of
technical parameters
and Network Condition
Process flow diagram
Applicant collects the application
form and other key documents
(Web portal, Sub Division)
Applicant submits the duly filled
Application form (sub division )
Utility performs general screening
of application form
Utility performs technical
screening of application form
Utility approves the
Interconnection Application
If, Application form fails to
clear technical screening -
seek relevant information
Utility shall provide
suggestions and reasons for
rejection of application
Applicant installs rooftop
facility and Informs utility for
commissioning test
Utility conducts the
commissioning test and
authorizes operations
If the rooftop facility fails to
clear the Commissioning test
Utility shall provide suggestions and
reasons for failure
Applicati
on
Pro
cess
Uti
lity
Revie
w
Pro
cess
Inst
allati
on a
nd C
om
mis
sionin
g
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
If required, Utility will
sign Interconnection
agreement with
consumer
If, Application form fails to
clear general screening
If, Application clear general
screening, utility signal go-a-head
If, Application clear technical
screening, utility signal go-a-head
Inspection by CEI
The serviced RR docket
will be sent to S.Div. for
Billing
If, Application form fails to
clear general screening
17
Fast Track eligibility is determined based upon the following :
• Electrical System Conditions
₋ System Capacity
₋ Voltage level (location, type of line at the Point of Interconnection)
₋ Network Condition (Feeder Capacity, DT loading, Sub Station )
₋ Code, Standards, Certification Requirements
• The capacity of solar rooftop generating facility should not exceed the particular limit
fixed by the utility (Generally system below 10 kW capacity)
• Pre-approved modules, Inverter and other key components are utilised by the system
installer
Eligibility for Fast Track Process
For Fast Track Process – empanelment of specific vendors is key
18
Institutional Setup Required for the Utility
Utility HQ
Division
Sub-Division
Sub Station
• Framing Guidelines, Information Manual, Forms/Formats, Agreements • Approving Equipment suppliers/Vendors, Equipment models, Meters etc. ???? • Managing the overall implementation framework • Organising training programmes for utility staff and key stakeholders • Establishing multiple communication channels for consumers
• Signing of agreements??? Like commercial agreements / PPA • Monitoring Grievance/Complaints registered by the consumer • Recording and managing operations of the grievance handling cell
• Metering and billing of energy supplied to or injected from the SRT facility • Records of Net Metering applications and consumers • Application screening and interconnection approvals • Monthly invoice for net energy billed to consumer/ payment to consumers • Status update of application forms/complaints • Providing information to consumers about the process, forms, formats
• General and technical feasibility study of application form • Pre and post installation Inspection of solar rooftop facility • Commissioning and synchronisation of solar rooftop facility • Meter reading and maintenance of safety of the network
• Who signs the PPA - ESCOM HQ or the Divisions?
• Identifying certified inverters and meters – Who does that/ at what level/ what is the process/ how does this
information trickle down or up to the operations ?
• PPA – How is the PPA rate decided if subsidy has not been committed to ?
• Overall institutional structure and roles and responsibilities at different levels
• Training, capacity building and technical backstopping for utility personnel
• Customer interactions and awareness generation
19
Issues faced by Utilities
20
Typical Net Metering Framework Application Form
Application Register
Feasibility Report format
Approval Letter
Commissioning Letter
Synchronizing Report format
Bill format
PPA
Guidelines for Utility
Schematic diagram
FAQs
Application form for Eligible consumers to apply for Net metering facility
Application register for utility to make record of net metering applications
Feasibility report format for utility to record technical feasibility parameters of project
Approval letter for consumers on approval of technical feasibility of their project
Commissioning letter for consumers on commissioning of their project
Synchronizing letter for successful synchronisation of the project with the utility grid
Bill format for consumers opting for net metering facility from Utility
PPA between the Utility and consumers for sale/purchase of surplus solar energy
Guidelines for Utility staff for implementation of net metering
Schematic diagram for net metered system for utility and consumer reference
Frequently asked questions for providing clarification to Interested/eligible consumers
21
Typical Issues
Availability, Testing and Procurement of Net Meters Guidelines for Consumers Online Submission of fees with application form
• Consumers should be able to apply and pay fees / deposits online
Capacity building of implementation staff • Ground staff’s competency to be built to resolve day to day consumers’
queries
Promotion of Scheme • reach of scheme will be restricted if only through web portal
Grievance Handling – Solar help desk Empanelment of implementing agencies Publishing one time standard approved drawings by CEI instead of
insisting on approved drawings for every SRTPV installation.
22
PACE-D comments on MP draft Net Metering Policy…...(1/2)
Target
Capacity
adopt specific targets with clear timelines for achieving these
targets.
Gross
Metering
include Gross Metering i.e. FIT route as an alternative option for
eligible consumers to develop and implement solar rooftops
Business
Models
include different business models for the promotion of solar
rooftops in the final policy document.
Eligibility and
other
Conditions
also cover eligible consumers, mechanisms for identifying suitable
locations, advice on permissible system size for different consumer
categories, connectivity levels, equipment standards etc.
23
Promotional
Incentives
provide more incentives for rooftop developers for at least first
five years of policy operation.
Sale of
Surplus
power
Sale of Surplus Power should be replaced with “surplus power
generated after fulfilling captive consumption requirements shall
be purchased by the distribution utility at APPC”
Registration
and Post
registration
process
project registration process should be covered in detail with
technical conditions, Interconnection requirements to avail Net
Metering facility by consumers
PACE-D comments on MP draft Net Metering Policy…...(2/2)
24
Scope and
Application
to primarily focus on developing solar distributed generation
through net metering. The draft regulation allows other RE
technologies also to take part under the Net metering scheme
Target
Capacity specify the target capacity under the regulations
Capacity of
distribution
transformer
allow maximum of 50-75% of available distribution transformer
capacity for net metering arrangement.
Individual
project
capacity
specify project capacity (Max/Min) for an individual consumer
under the net metering arrangement to be in-line with the
sanctioned load or contracted load or contracted demand of the
consumer.
PACE-D comments on MP draft Net Metering Regulations…...(1/2)
25
Energy
Accounting
and
Settlement
the settlement of energy credits that remain un-utilized at the
end of the financial year should be settled and credited as per the
Solar Feed in Tariff determined by the Commission on annual
basis..
Provisions
for Safety add provisions with respect to safety in the final regulations
Interconnect
ion Process
add detailed process for Interconnection of Solar PV Rooftop
Systems
Fees and
Timelines
the timelines for processing the application and fees/charges to
be paid by consumers should also be included in the final
regulation.
PACE-D comments on MP draft Net Metering Regulations…...(2/2)
• developing the overall implementation framework required for implementation of net metering
• establishment of institutional framework required to implement Net Metering Scheme
• training, capacity building and technical backstopping for utility personnel – developing capacity of key personals by holding Stake holder
consultations, knowledge exchange programs with other State utilities and regulatory bodies
• sharing of key information, notes, inputs etc. as and when required for implementation of Net Metering.
26
PACE-D Assistance to MP DISCOMs
Key Partners: RE Component
Design and development of
innovative financing mechanisms Microfinance Partners
Capacity to design and implement
supportive policies and regulations
Implementation of techno-commercially
viable pilots
Thank You !
Yuvaraj Dinesh Babu, Chief of Party, USAID PACE-D
• Issue net metering regulations
• Amending existing regulations
• Drafting/ approving Model PPA/Net Metering agreement
• Interconnection agreement approval
• Approving tariff for Net export
• Clarity on OA charges, wheeling, Banking etc.
Regulatory Commission
• Accessing Information
• Evaluating potential Opportunity
• Meeting & engaging utility
• Engaging system provider/technical expert
• Cost benefit Analysis
• Filling application forms and formats
• Preparing relevant documents
• Financing the system
Eligible Consumer • System design
• Network layout design
• Preparing Line diagrams
• Following technical standards
• Following utility guidelines
• Meeting with utility (if required)
• Assisting consumer in getting clearances /Approvals
• Educating/supporting consumer
System Installer
• Information manual
• Establishing multiple channels
• Drafting forms, formats etc.
• Invite/ Accept applications
• System Study, load flow study
• Inspection, Monitoring
• Changes in metering and billing system
• Safety and Protection
Distribution Utility
29
Key Stakeholders of Net Metering
Step
-1
Information Access
Step
-2
Application Filling & Submission St
ep-3
General Application Screening Step
-4
Technical Application Screening
31
1. Utility will develop information channel to disseminate information to Eligible Consumers
2. Consumer will collate information and will evaluate other potential opportunities
3. Once consumer is convinced, will proceed to next stage of filling application
1. Consumer provides all the required information
2. Consumer submits the application form (online or in person)
3. Upon receiving utility provides acknowledgement receipt
4. Consumer tracks application status
1. Utility performs general screening based on information provided by the consumer
2. On clearing general screening consumer is required to provide details for technical screening
3. If general screening is not cleared, application will be rejected
1. Technical information provided by the consumer shall be evaluated
2. If utility finds it feasible it clears the application to next level
3. If utility find some complication it will suggest other possible options to consumers to proceed further
Major Steps for Interconnection
32
Step
-5
Document Submission
Step
-6
Modification required for interconnection St
ep-7
Interconnection Approval & Project Installation
Step
-8
Inspection & Commissioning
1. To evaluate the feasibility of interconnection, Utility will require additional Information from applicant
2. Electrical line diagram, Cert. from structural Engr., Ownership proof, Safety measures, grounding protection etc.
1. In case the application fails the technical screening, utility will suggest possible modification to accommodate the proposed interconnection
2. On acceptance of modification, The cost of modification shall be borne by the applicant
1. On finalising the modification in the proposed application utility shall approve the interconnection
2. Utility shall give go-a-head signal to consumer for project installation
3. Applicant will install the SRTPV facility on utility guidelines
1. On Completion of project installation, applicant will inform the utility for final inspection & Commissioning
2. Utility will perform final inspection clears the inspection test
3. Utility will synchronies and commission the plant
Major Steps for Interconnection
33
Procedure for Interconnection Approval – Fast track process Steps Fast Track Process
Eligibility
Consumer are eligible to take part in fast track process based on the following conditions • System Capacity • Module (type, Model, Standard, Manufacturers etc.) • Inverter (Model, Make, Technical specification etc.) • Voltage level (location, type of line at the Point of Interconnection) • Network Condition (Feeder Capacity, DT loading, Sub Station ) • Code, Standards, Certification Requirements
Application Review
Screening • Location of Interconnection, Equipment to be installed • Aggregate generation on proposed line including the proposed SRTPV • Proposed SRTPV, Inverter Specifications and Operation Parameters • Study of maximum fault current of distribution circuit • Study of impact on protective device and other equipment connected on the same
network • Study of type of Interconnect (Single or 3 phase) including line configuration and
transformer connections • Checking of phase imbalance, if Interconnection is single phase • Checking the limit of cumulative generation capacity on the network
Interconnection Agreement/PPA
(if Required)
• On passing the screening process, the utility approves the interconnection application and will sign interconnection agreement (depends on utility regulatory requirements for different consumer categories)
• If the application fails the screening, then the utility may provide another opportunity to make system modification and suggest way forward