Net CONE for the ISO-NE Demand Curve

17
Copyright © 2013 The Brattle Group, Inc. PRESENTED TO PRESENTED BY Net CONE for the ISO-NE Demand Curve Final Proposal NEPOOL Markets Committee Samuel Newell, Brattle Chris Ungate, Sargent & Lundy March 12, 2014

description

Net CONE for the ISO-NE Demand Curve. Final Proposal. NEPOOL Markets Committee. Samuel Newell, Brattle Chris Ungate , Sargent & Lundy. March 12, 2014. Agenda. Responses to Stakeholder Comments, and Associated Revisions Electrical Interconnection Network Upgrade Costs - PowerPoint PPT Presentation

Transcript of Net CONE for the ISO-NE Demand Curve

Page 1: Net CONE for the  ISO-NE Demand Curve

Copyright © 2013 The Brattle Group, Inc.

PRESENTED TO

PRESENTED BY

Net CONE for the ISO-NE Demand CurveFinal Proposal

NEPOOL Markets Committee

Samuel Newell, BrattleChris Ungate, Sargent & Lundy

March 12, 2014

Page 2: Net CONE for the  ISO-NE Demand Curve

| brattle.com2

Agenda  Responses to Stakeholder Comments, and Associated Revisions

▀ Electrical Interconnection Network Upgrade Costs▀ Oil Inventory and Other Non-Depreciable Assets▀ CT E&AS RTR Payback▀ CC E&AS Representative Units ▀ Electricity Forwards and PER/PFP Assumption▀ Consideration of Lumpiness▀ Summary of Changes

  Recommendation▀ Principles for Selecting Reference Technology▀ Review of Reference Technologies▀ Recommended Net CONE Based on CC▀ Locational Net CONE

Page 3: Net CONE for the  ISO-NE Demand Curve

| brattle.com3

Electrical Interconnection▀ Based on stakeholder feedback, we re-visited

network upgrade cost assumption▀ Transmission costs reported in Section 15.5

Applications show that the average historical cost of network upgrades beyond the generator lead was $35/kW (2013$)

▀ We adopt the reasonable assumption that generic future projects expect to pay the same on a $/kW basis, plus $1.1m for ½ mile lead based on S&L estimate

Transmission Costs from 15.5 Applications

Source: ISO-NE assembled from publicly available Section 15.5 Applications.

Technology Initial Costs (2013$)

Final Costs (2013$)

Net CONE Impact(2018$/kW-mo)

LM6000 $7.1m $7.2m +0.01

LMS100 $7.1m $7.7m +0.04

Frame CT $7.1m $15.8m +0.27

CC $7.1m $26.2m +0.37

ProjectSummer

CapabilityPTF

CostsPTF

CostsMW 2013$ 2013$/kW

Historic Data from 15.5 ApplicationsBucksport 157 264,385 2 Westbrook 523 17,703,195 34 Rumford Power 245 21,264,979 87 Maine Independence 490 29,602,411 60 Androscoggin Energy 128 3,050,416 24 Newington Energy 521 1,478,685 3 Lake Road 726 20,458,743 28 Milford Power 485 12,237,377 25 Berkshire Power 236 9,954,560 42 AES Granite Ridge 662 37,456,491 57 ANP Bellingham 466 8,964,340 19 ANP Blackstone 441 24,582,786 56 RISE 516 4,992,490 10 Fore River 683 22,644,863 33 Mystic 8 & 9 1,396 57,578,223 41 Kendall 154 3,050,094 20 Total 7,827 275,284,036 35

Expected Costs for Future Projects (assuming same cost per KW)LM6000 173 6,100,000 35 LMS100 188 6,600,000 35 Frame CT 417 14,700,000 35 CC 715 25,100,000 35

Page 4: Net CONE for the  ISO-NE Demand Curve

| brattle.com4

Oil Inventory and Other Non-Depreciable Assets

  Stakeholders requested that we review how fuel inventory and working capital are accounted for in the financial model

▀ As the fuel inventory will hold residual value at the end of the economic life, we credited back to the capital costs the present value of the fuel inventory in 2038 based on long-term EIA escalation rates (+2.4%/year)

▀ Relatedly, we updated our calculation of depreciable costs based on accepted GAAP principles, which specifies that land, fuel inventory and working capital be considered non-depreciable

Technology

Fuel Credit Impact

($/kW-mo)

Non-Depreciable Assets Impact

($/kW-mo)

Total Net CONE Impact

($/kW-mo)LM6000 -0.05 +0.09 +0.04LMS100 -0.06 +0.09 +0.03Frame CT -0.06 +0.07 +0.01CC -0.04 +0.05 +0.01

Page 5: Net CONE for the  ISO-NE Demand Curve

| brattle.com5

Real-Time Reserve Charge-Backs and Other E&AS Adjustments to CTs

  Real-Time Reserve Charge-Backs: To better estimate CT E&AS revenues, we incorporated data from ISO-NE on forward reserve obligation charges

▀ Portfolios with FRM will receive real-time reserve revenues that will later be charged back▀ Using only asset-specific market settlement data over-estimates CT E&AS as the obligation

charges occur after the settlement at the portfolio level▀ Adding ISO-NE’s portfolio-level charge-back data reduces the CT E&AS by $0.13/kW-mo

  Heat Rates: We adjusted fuel costs for the Frame CT and LMS100 based on their heat rates relative to the LM6000 sample plants

  Calculation Adjustments: We adjusted our calculation of the E&AS margin across the plants in our sample from a simple average to capacity-weighted average; also we resolved a fuel cost calculation issue during our final audits of the analysis

Technology

Initial E&AS

($/kW-mo)

Calculation Adjustments

($/kW-mo)

RTR Charge Back

($/kW-mo)

Heat Rate

($/kW-mo)

Net CONE Impact

($/kW-mo)LM6000 $1.95 $1.86 $1.73 $1.73 +0.22LMS100 $1.95 $1.86 $1.73 $1.74 +0.21Frame CT $1.95 $1.86 $1.73 $1.72 +0.23

Page 6: Net CONE for the  ISO-NE Demand Curve

| brattle.com6

CC E&AS Representative Units  Based on stakeholder feedback, we refined our approach for selecting the representative

CC plants used to calculate historical E&AS revenues▀ We received market revenue data from ISO-NE for 20 plants▀ We removed 6 plants with average realized heat rates above 8,000 Btu/kWh▀ We removed 6 plants with fuel costs that are not represented by Algonquin Citygates prices due

to firm gas capacity, alternative sources of fuel, or plants with gas pricing based on Iroquois▀ We removed 2 plants with different operations mode such as district heating and low CF (<20%)

  The remaining 6 plants have an average capacity factor of 58% and average heat rate of 7,400 Btu/kWh; the CC E&AS increases by $0.04/kW-mo due to this change

Technology

Initial E&AS

($/kW-mo)

Updated Units

($/kW-mo)

Net CONE Impact

($/kW-mo)CC $3.37 $3.41 -0.04

Page 7: Net CONE for the  ISO-NE Demand Curve

| brattle.com7

Forward Curves▀ Stakeholders requested futures data be used

even if volume is thin▀ We show Open Interest for ICE, which

expresses the amount of forward contracts actually doing daily mark-to-market settlement on these prices

▀ We also compared to other sources available (NYMEX, ICE, Platts), which are in close agreement

▀ We will use ICE data in E&AS analysis instead of previous average of NYMEX and OTC as it more often used and is publicly available

TechnologyInitial E&AS ($/kW-mo)

Final E&AS ($/kW-mo)

Net CONE Impact

($/kW-mo)LM6000 $1.73 $1.67 +0.06LMS100 $1.74 $1.69 +0.05Frame CT $1.72 $1.66 +0.06CC $3.41 $3.33 +0.08

Mass Hub On-Peak Futures and Open Interest (ICE)

Mass Hub On-Peak Futures (All Sources)

Sources: See appendix.

Page 8: Net CONE for the  ISO-NE Demand Curve

| brattle.com8

H Value for PER/PFP Estimates▀ Stakeholders were concerned that assuming H = 10.9 for estimating PER and PFP

is inconsistent with the electricity futures▀ We have reviewed the implied market heat rate from the ICE forward curves for

gas and electricity and agree that the lowest H case (H = 5.8) is a better assumption for our analysis

▀ At H = 5.8, the PER deduction will be $0.43/kW-mo and the PFP payment will be $0.06/kW-mo; this contributes $0.37 to Net CONE, which is $0.41/kW-mo less than the initial analysis

Year Gas (ACG) On-Peak Electric (Mass Hub) On-Peak MHR($/MMBtu) ($/MWh) (btu/kWh)

Annual July/Aug Annual July/Aug Annual July/AugHistorical

2010 $5.32 $4.93 $56.35 $72.45 10,598 14,7092011 $5.05 $4.92 $53.00 $60.46 10,496 12,2912012 $3.96 $3.62 $41.67 $49.59 10,511 13,6882013 $7.04 $4.12 $65.63 $53.59 9,327 13,012

ICE - FuturesBal. 2014 $6.91 $4.72 $72.89 $67.75 10,553 14,3522015 $7.47 $4.37 $71.84 $58.65 9,614 13,4092016 $6.76 $4.14 $63.26 $56.88 9,351 13,7542017 $6.33 $4.25 $53.58 $50.33 8,465 11,8382018 $6.40 $4.25 $52.68 $48.78 8,229 11,4672019 $6.51 $4.38 $54.08 $52.53 8,304 12,002

ICE Futures and Implied Market Heat Rates

Sources and Notes: ICE futures were obtained from www.theice.com. Trades are averaged from Feb 20 to Feb 28, 2014

Page 9: Net CONE for the  ISO-NE Demand Curve

| brattle.com9

Why Lumpiness Should Not Add to Net CONE

▀ The demand curve was designed so that Net CONE is the long-term average prices an entrant can expect, not their entry price

▀ Our curve design and simulations are consistent with lumpiness and other sources of volatility making entry more likely when P > Net CONE, at the higher end of our price distributions

▀ Consider a simple example where a 600 MW unit enters at point A and clears with 600 MW overhang (worst case for lumpiness); with 300 MW/yr load growth, the next auction clears about 300 MW to the right, at point B. The following auction adds 300 MW load, so we’re back at point A and the cycle repeats− The entrant earns Net CONE on average, and the curve

achieves the reliability objectives of 1-in-10, with average quantity at about 1% above NICR (addressing reliability asymmetry)

− If instead, we moved the curve up so the price at NICR + 1% were the entry price (pt. C) rather than Net CONE, we’d over-procure, with an average reserve margin at D

Page 10: Net CONE for the  ISO-NE Demand Curve

| brattle.com10

Summary of Impacts on Net CONE

Adjustments CC Frame CT LMS100 LM6000Feb 27 Values $11.71 $8.95 $17.85 $20.60 Added Network Upgrades Costs +0.37 +0.27 +0.04 +0.01 Oil Inventory and Non-Depreciable Assets +0.01 +0.01 +0.03 +0.04 Updated CC E&AS Representative Units -0.04 --- --- --- Adjusted CT E&AS for Payback and HR --- +0.23 +0.21 +0.22 Substituted ICE Futures +0.09 +0.06 +0.05 +0.06 Reduced H to 5.8 -0.41 -0.41 -0.41 -0.41

Removed Lumpiness -0.64 -0.64 -0.64 -0.64

Updated Values $11.08 $8.47 $17.13 $19.88

Page 11: Net CONE for the  ISO-NE Demand Curve

| brattle.com11

Agenda  Responses to Stakeholder Comments, and Associated Revisions

▀ Electrical Interconnection Network Upgrade Costs▀ Oil Inventory and Other Non-Depreciable Assets▀ CT E&AS RTR Payback▀ CC E&AS Representative Units ▀ Electricity Futures and PER/PFP Assumption▀ Consideration of Lumpiness▀ Summary of Changes

  Recommendation▀ Principles for Selecting Reference Technology▀ Review of Reference Technologies▀ Recommended Net CONE Based on CC▀ Locational Net CONE

Page 12: Net CONE for the  ISO-NE Demand Curve

| brattle.com12

Principles for Selecting a Reference Technology

  Objective▀ Estimate Net CONE that supports prices that are on a long-term average basis just high enough to attract

sufficient new investment to meet resource adequacy objectives

  Criteria for selecting the Reference Technology to meet the objective▀ Reliably able to help meet load

− Complies with all environmental regulations− Dispatchable technology that could be available to generate whenever capacity is scarce

▀ Likely to be economic for merchant entry as part of long-term equilibrium− Demonstrated commercial interest by merchant developers, as evidenced by projects recently completed, under

construction, or in the queue in New England or the rest of U.S.− Estimated Net CONE is not so high as to make it implausible that the technology would be part of the long-term mix of

resources entering the market− Available as standardized, utility-scale commercial plants without inherent constraints on the amount that could enter

▀ Can estimate Net CONE with low uncertainty− Cost estimates have less uncertainty, based on established, standardized technologies− E&AS estimates have less uncertainty relative to other technologies

  Additional considerations▀ Several technologies might be economic in a long-term equilibrium, with the same long-term average Net

CONE, even if not currently economic due to temporary market conditions− It is important not to switch reference technologies back and forth over time, particularly not in pursuit of the technology

whose Net CONE is temporarily lowest, as doing so will tend to under-procure− If multiple technologies meet the criteria, taking an average of their Net CONEs could help stabilize market outcomes and

reduce the risk of estimation errors

Page 13: Net CONE for the  ISO-NE Demand Curve

| brattle.com13

Criteria:1. Reliably able to help

meet load during scarcity

2. Likely economic 3. Estimate with limited uncertainty

Technology

Meets Environ. Regulations Dispatchable

Recently Built or Proposed

Net CONE Estimate

Accuracy of Capital and FOM Cost Estimates

Accuracy of E&AS Estimate

2x0 LMS100188 MW

Yes Yes Limited $17.13/ kW-mo

Well established technology

Similar magnitude, uncertainties exist

2x0 Frame CT417 MW

Yes Yes Very limited

$8.47/ kW-mo

Well established technology, but less experience

with SCR

Similar magnitude, uncertainties exist

2x1 CC715 MW

Yes Yes Numerous $11.08/ kW-mo

Well established technology

Similar magnitude, uncertainties exist

Review of Reference Technologies

Page 14: Net CONE for the  ISO-NE Demand Curve

| brattle.com14

Net CONE Recommendation  We recommend the 2x1 CC as the Reference Technology with Net CONE at $11.08/kW-mo

▀ CCs are clearly part of the equilibrium mix, so how wrong could choosing it be?− Clear signals from merchant developers through past, current, and proposed projects− Near-lowest Net CONE

▀ CC Net CONE estimation uncertainty is no higher than for CTs− Most experience with technology− CC E&AS estimation uncertainty is not demonstrably higher than CTs in New England

▀ Since the Frame CT’s Net CONE is lower, choosing it could risk under-procurement if it cannot actually be built at the cost we estimated− The lack of commercial activity suggests the possibility of risks or costs that are not captured in our

analysis (alternatively, perhaps the SCR capability is too new to be showing up in projects yet but will soon; also possible that CTs just aren’t as economic as CCs in places where merchants are building)

− Our simulation analysis showed that the reliability risks of understating True Net CONE are much more serious than over-procurement risks of overstating True Net CONE

− In an FCM market with little history of merchant entry, launching a new demand curve that might not support sufficient entry could set up the new market for failure

▀ The Aero CTs’ Net CONE is too high to be plausibly part of the economic equilibrium mix of technologies

  Averaging multiple reference technologies could help stabilize market outcomes and reduce the risk of estimation errors; however, we recommend only the CC here

▀ The reasons we identified for not 100% relying on turbines in ISO-NE suggest not relying on them 50% either

Page 15: Net CONE for the  ISO-NE Demand Curve

| brattle.com15

Locational Net CONE  CC CONE for NEMA/Boston is only slightly higher than rest-of-pool (ROP)

▀ Assumed the plant would be located in Lowell, MA▀ Modified the ROP analysis based on labor and land costs, resulting in only a

$0.21/kW-mo increase in CONE

  Connecticut CONE would be even closer to ROP due to labor rates even closer to ROP’s (based on Middletown/Meriden/Bristol/New Britain/New Haven), but didn’t quantify it precisely

  Energy prices have been pretty uniform across ISO-NE

  Overall, the differences appear to small for us to recommend differentiating the Net CONE value across New England

Page 16: Net CONE for the  ISO-NE Demand Curve

| brattle.com16

Appendix

Page 17: Net CONE for the  ISO-NE Demand Curve

| brattle.com17

Sources for Forward Curves  ICE: Obtained from www.theice.com

  NYMEX: Obtained from Ventyx Velocity Suite

  OTC: Compiled by OTC Global Holdings and downloaded from SNL Financial

  Platts: Purchased on March 4, 2014

  Note: All futures were traded as of Feb 27, 2014, except for Platts, which was traded on March 3, 2014