NDG / Westmount Neighbourhood Committee...Closed to traffic since February 28, 2016 Reopening...
Transcript of NDG / Westmount Neighbourhood Committee...Closed to traffic since February 28, 2016 Reopening...
2
Presentation outline
Dust control measures
Feedback on previous questions
Dismantling of Saint-Jacques overpass
Reopening of rue Saint-Rémi
Construction of the A-15 south ramp toward R-136 east
Route 136 east
Closure of exit 2 – rue Atwater
Construction of the new Atwater exit
Closure of Avenue Greene
3
Dust Control Measures
Continuous water spreading and street cleaning – 2 tankers and 2
mechanical sweeper at all times
4 tanker dedicated to spread worksite access and roads
An additional tanker on dry and windy days
Use of water canons during dismantling
Installation of wheel washers at the two exits of the Turcot yard (to come)
Speed limit on worksite at 30 km/h
Superintendent dedicated to monitor street cleanliness and dust control
Daily inspections by the superintendent of street and worksite access
cleanliness
4
Feedback on Previous Questions
1. Snow removal of detour for cyclists
2. Consulting cyclist associations to put in place detour roads
3. Noise barrier on rue Saint-Jacques
4. Planting in available spaces: boul. de Sainte-Anne-de-Bellevue area
Boul. de Sainte-Anne-de-Bellevue
5
Feedback on Previous Questions
5. Use of plant screens
6. Brown snake : indigenous species
7. Invested percentage in public transportation vs road infrastructures
8. Relocation of the fence located in the Saint-Jacques escarpment
9. Landscaping: indigenous or native varieties planned in the area
10. Landscaping: invasive plants
CDN-NDG Borough
11. Addition of a 60 minutes parking on chemin Upper-Lachine and parking
permit for visitors
12. Safety of the Upper-Lachine/Girouard intersection
13. Raising the Upper-Lachine overpass guardrails
6
Reconstruction of Saint-Jacques Overpass
Weekend of July 8 Dismantling from Friday to Monday – 24 hours a day
7
Reconstruction du pont Saint-Jacques
Fin de semaine du 9 juillet
INSÉRER QUELQUES PHOTOS DES TRAVAUX DE LA
1re FIN DE SEMAINE
8
Reconstruction of Saint-Jacques Overpass
Weekend of July 15 Dismantling from Friday to Monday – 24 hours a day
11
Reopening of Saint-Rémi Street
Closed to traffic since February 28, 2016
Reopening planned at the end of August 2016
12
Ramp A-15 South to R-136 East
Temporary retaining wall and excavation
A-15 N A-20 E to A-15 N
A-720 E to A-15 N
A-15 S to A-720 E
A-15 S
Temporary noise barrier
Temporary retaining wall Extended temporary noise barrier
Excavation zone
13
Ramp A-15 South to R-136 East
Nonstop operation 24 hours per
day, 7 days a week
Construction of the temporary
retaining wall July 5 to the end of September 2016
14
Construction of R-136 East
Closure of exit no. 2 - Atwater Street
Complete closure
July 10 to fall 2016
15
Construction of R-136 East
New Atwater exit
Backfilling, dismantling and drainage works and construction of a
retaining wall
Temporary structure
Construction of new permanent pavement
16
Construction of R-136 East
Closure of Greene Avenue
Complete
closure
Duration:
1 month
Time period:
fall 2016
Sidewalk on
east side is
preserved
Closure Local traffic
17
NDG-Westmount neighbourhood committee
September 12, 2016
Sud-Ouest neighbourhood committee
August 10, 2016
Website dedicated to the project: www.turcot.gouv.qc.ca
Twitter @MTQ_Turcot
Monthly electronic bulletins (subscribe via the Turcot website)
Dedicated telephone line: 514 873-1372
Turcot email: [email protected]
For More Information