NDG / Westmount Neighbourhood Committee...Closed to traffic since February 28, 2016 Reopening...

18
NDG / Westmount Neighbourhood Committee July 11, 2016

Transcript of NDG / Westmount Neighbourhood Committee...Closed to traffic since February 28, 2016 Reopening...

NDG / Westmount

Neighbourhood Committee

July 11, 2016

2

Presentation outline

Dust control measures

Feedback on previous questions

Dismantling of Saint-Jacques overpass

Reopening of rue Saint-Rémi

Construction of the A-15 south ramp toward R-136 east

Route 136 east

Closure of exit 2 – rue Atwater

Construction of the new Atwater exit

Closure of Avenue Greene

3

Dust Control Measures

Continuous water spreading and street cleaning – 2 tankers and 2

mechanical sweeper at all times

4 tanker dedicated to spread worksite access and roads

An additional tanker on dry and windy days

Use of water canons during dismantling

Installation of wheel washers at the two exits of the Turcot yard (to come)

Speed limit on worksite at 30 km/h

Superintendent dedicated to monitor street cleanliness and dust control

Daily inspections by the superintendent of street and worksite access

cleanliness

4

Feedback on Previous Questions

1. Snow removal of detour for cyclists

2. Consulting cyclist associations to put in place detour roads

3. Noise barrier on rue Saint-Jacques

4. Planting in available spaces: boul. de Sainte-Anne-de-Bellevue area

Boul. de Sainte-Anne-de-Bellevue

5

Feedback on Previous Questions

5. Use of plant screens

6. Brown snake : indigenous species

7. Invested percentage in public transportation vs road infrastructures

8. Relocation of the fence located in the Saint-Jacques escarpment

9. Landscaping: indigenous or native varieties planned in the area

10. Landscaping: invasive plants

CDN-NDG Borough

11. Addition of a 60 minutes parking on chemin Upper-Lachine and parking

permit for visitors

12. Safety of the Upper-Lachine/Girouard intersection

13. Raising the Upper-Lachine overpass guardrails

6

Reconstruction of Saint-Jacques Overpass

Weekend of July 8 Dismantling from Friday to Monday – 24 hours a day

7

Reconstruction du pont Saint-Jacques

Fin de semaine du 9 juillet

INSÉRER QUELQUES PHOTOS DES TRAVAUX DE LA

1re FIN DE SEMAINE

8

Reconstruction of Saint-Jacques Overpass

Weekend of July 15 Dismantling from Friday to Monday – 24 hours a day

9

Reconstruction of Saint-Jacques Overpass

Weekend of July 15 Complete closure of A-15

10

Main detour by :

A-20, A-13, A-40

Reconstruction of Saint-Jacques Overpass

11

Reopening of Saint-Rémi Street

Closed to traffic since February 28, 2016

Reopening planned at the end of August 2016

12

Ramp A-15 South to R-136 East

Temporary retaining wall and excavation

A-15 N A-20 E to A-15 N

A-720 E to A-15 N

A-15 S to A-720 E

A-15 S

Temporary noise barrier

Temporary retaining wall Extended temporary noise barrier

Excavation zone

13

Ramp A-15 South to R-136 East

Nonstop operation 24 hours per

day, 7 days a week

Construction of the temporary

retaining wall July 5 to the end of September 2016

14

Construction of R-136 East

Closure of exit no. 2 - Atwater Street

Complete closure

July 10 to fall 2016

15

Construction of R-136 East

New Atwater exit

Backfilling, dismantling and drainage works and construction of a

retaining wall

Temporary structure

Construction of new permanent pavement

16

Construction of R-136 East

Closure of Greene Avenue

Complete

closure

Duration:

1 month

Time period:

fall 2016

Sidewalk on

east side is

preserved

Closure Local traffic

17

NDG-Westmount neighbourhood committee

September 12, 2016

Sud-Ouest neighbourhood committee

August 10, 2016

Website dedicated to the project: www.turcot.gouv.qc.ca

Twitter @MTQ_Turcot

Monthly electronic bulletins (subscribe via the Turcot website)

Dedicated telephone line: 514 873-1372

Turcot email: [email protected]

For More Information

18

www.turcot.gouv.qc.ca