NCSX VACUUM VESSEL PL Goranson Comprehensive Final Design Review May 05, 2005 Vacuum Vessel Supports...
-
Upload
regina-nichols -
Category
Documents
-
view
217 -
download
0
Transcript of NCSX VACUUM VESSEL PL Goranson Comprehensive Final Design Review May 05, 2005 Vacuum Vessel Supports...
NCSX VACUUM VESSELPL Goranson
Comprehensive Final Design Review May 05, 2005
Vacuum Vessel SupportsHeating/Cooling System
NCSX
NCSXTalk Overview
STATUS
VACUUM VESSEL SUPPORT DESIGN
VACUUM VESSEL HEATING/COOLING SYSTEM DESIGN
ISSUES
CONCLUSION
NCSXStatus
Drawings• Vacuum Vessel Coolant Tube System
Drawings checked, not signed
• Vacuum Vessel Coolant Header AssemblyDrawings checked, not signed
• Vacuum Vessel Supports Vertical support rod drawings checked, and signed, not releasedLateral support drawings checked and signed, not released
• Vacuum Vessel NB Port Metal Seals and Seal TemplateDrawings complete, template procured, rings in fabrication
• Vacuum Vessel Heating/Cooling System & Diagnostics Top Assembly50% complete; not required for procurement
ICD• ICD-12-142-0001 Vacuum Vessel and Modular Coil Assembly Clearances
not signed• ICD-12-14-3-0001 Insulation
Complete• ICD-123-171-0001 VV/Cryostat Coolant Tube Interface
Complete• ICD-12-125-0001 VV Local I&C
Complete• ICD-123-310-0001 VV Magnetic Diagnostics
Complete• ICD-12-400-0001 VV Grounding
not signed• ICD-12-64-0001VV Cooling/Heating Requirements
Complete• ICD-12-4-5-0002 VV Port Resistance Heaters
Complete• ICD-121-300-0001 VV Diagnostic Port Allocation and Orientation
Complete
NCSXStatus Continued
DAC• NCSX-12-001-00 VV Local Thermal Analysis
Complete• NCSX-12-002-00 Vacuum Vessel Heating/Cooling Distribution System Thermo-hydraulic Analysis
not signed• NCSX-12-003-00 Vacuum Vessel Heat Balance Analysis
Complete• NCSX-12-004-00 Vacuum Vessel Support Rod Analysis
Complete• NCSX-12-005-00 Diagnostic Port Flange Weld Stress Resulting From Loss of Power Fault Condition
Complete• NCSX-12-006-00 Port 4 Weld Stress During Bake-out
Complete• NCSX-12-007-00 Design Basis Analysis VV Structural Analysis/Seismic Analysis
not signed
Coolant Tube Build To SpecificationDraft complete, not signed
VV SRDComplete
FMECADraft commented, not signed
CHITSOutstanding chits from PBR resolved
VV Supports
NCSX
VV Support Design Overview NCSX
• Six overhead support rods
carry weight of VV• Lateral supports, 120o apart,
react lateral and out-of plane
loads-Three take CW load (toroidal)
-Three take CCW load (toroidal)
-Two take radial load
- Four take overturning moment
• Six lower rods react vertical
magnetic loads
VV Support Loads NCSX
• VV Weight 24,000 lbs Including flange extensions, covers, and NB Transition Ducts
• Diagnostic weight (per ICD) 10,750 lbs
• Lateral out-of plane (radial) ?
• Lateral vacuum radial 3,200 lbs
• Rotational (toroidal) magnetic 0 (halo?)
• Vertical magnetic loads ± 16,800 lbs
• Future PFC internals 13,250 lbs
VV Support Capability NCSX
Critical component is commercial rod end.• Nominal dead load, including diagnostics and PFC
internals is 8,000 lbs each. Assumes no lower support rods.
• Rod end ultimate load is 29,300 lbs – Safety factor is 3.7 static, 3.41 during vertical disruption.– Failure mode is permanent deformation, not catastrophic
separation.
• Lower supports could potentially remove 2,840 lbs from each upper support.
Upper Support Rod NCSX
• Self-aligning design permits thermal growth– MC shell/VV relative movement 5/8”(radial)– shell end is spherical nut/washer– vv end is commercial spherical rod end/threaded lug
• Adjusted for nominal VV height at 40 C
• Shell end insulated (thermally and electrically) with G-11CR washer/spacer
• Titanium alloy rod for high strength, low thermal conductivity, low permeability
• ¾” diameter
Upper Support Rod Drawing NCSX
Lower Support Rod NCSX
• Six units react magnetic loads from VV
• VV end identical to upper support
• MC end is self-aligning & spring loaded- suspended between Bellville Washer stackswith 0.43” stroke
- self-contained subassembly- both upward and downward preload adjustable- permits 0.205 relative thermal growth during bakeout
• MC end insulated with G-11CR washer/spacer
• Titanium rod for high strength, low thermal conductivity, low permeability
Lower Support Rod Drawing NCSX
Lateral Support NCSX
Design Requirements• Permit radial and vertical
growth• React lateral, radial imbalance forces• Adjust lateral & rotational
alignment of vessel• Electrical isolation for VV
Baseline Design Change• FDR design reacted loads
from pads on NB transition duct into shell mounted pads
• MIE does not have NB Ducts
FDR DESIGN
MIE Lateral Support Design NCSX
Design Features• Modification kit reacts load into NB blankoff flange• Utilizes baseline MC pads with
no changes• Retrofit onto NB blankoff port
–installed in field
MIE DESIGN
Support Rod Temperature Distribution NCSX
• Thickening shell end insulation reduces gradient, raises end, average temperature
• Baseline is 0.125”
• Loss is only 5.2 watts
SUPPORT ROD TEMPERATURE DISTRIBUTION AS A FUNCTION OF END INSULATION THICKNESS
Bakeout at 350 C
-100
-50
0
50
100
150
200
250
300
350
400
0 5 10 15 20 25
ROD ELEMENT (1.52 cm each)
RO
D T
EM
PE
RA
TU
RE
(C)
VV
Shell
0.5 inch insulation around rod G-10 on endLosses range from 3.2 w to 5.2 w.
0.125"
0.5"
0.25"
Heating/Cooling System Design
NCSX
Coolant System Design Status
• Tubing drawings checked– 5/16” O.D. 316L annealed stainless tubing– Held with weld studs, clamps, and Grafoil® gaskets
• Helium Supply/Return Header and Support drawings checked
• Tubing thermal analysis complete - Thermal performance acceptable- Thermal coef. mismatch not a concern
total differential growth only 0.2” in 17 feet.temperature ramped during bakeoutgaskets permit movement
• Discussions with tube bending vendors are in progress
• Draft build-to specification for Coolant Tubes complete, in comment cycle
NCSX
NCSX
Coolant Tube Installation
Tubing Design Concept
Reflects vendor comments• Tube tolerance requires robust design mounting
clip.• Installation of studs must be done at assy of
tubes on to VV. • Vendor will work from xyz coordinate table, not
models.
NCSX
Mounting Clip Design
• Compensates for misalignment in tube pair.+ 1/16 lateral (each)+ 1/8 vertical (each)
• Utilizes self aligning nut.
• Maintains 1/8” clearance for magnetic loops.
1.250.645
5/16 DIA1/16
1/32
5/16 STUD.062
1.65
Gasket omitted for clarity
1.0
Ø.412
10.0°
R 0.44
.156
0.38
1/16" kerf
0.045
.06
SPS TLN 1035 C -5N spherical nut
0.50
optional
NCSX
Vertical Port (12) Tube Supports
• One support near VV- the flange end is
supported by header
• Uses commercial (Jiffy) clips on elevated mount
plate- permits ½” insulation
under the tubes.- maximizes routing
space for cables/wires• No gasket
- decouple thermal load
NCSX
Tube Fabrication
• Vendor can not fab in one piece.– Tubes hit bender or floor
before completion.• 3-4 piece design will be used.
– Body tube– Upper Port Tube– Lower Port Tube– Possibly a mid-plane splice
• Weld together at assembly• Only 2 configurations of Port
Tubes are required.
NCSX
NCSXTypical CNC Bending Machine
• Bends clockwise and counterclockwise rotation. • Simultaneous head rotation around part, with collet rotation. • Stacked bend rollers with die shifter can bend tubes up to four different radii • Optional push bending technique enables bending coils
Tube Configuration-planNCSX
Tube Configuration-elevationNCSX
Typical Tube DrawingNCSX
Supply Header Configuration
Following VG show assembly and configuration of Tubing, Headers, and Cryostat interface.
• Order is flexible, headers can go on first or last.
• Competing interfaces not shown- Magnetic Loops- Thermocouples- Heaters- Insulation
NCSX
NCSXTubes Installed on VV
NCSXHeaders Installed
NCSX Tubes Installed on Port
NCSXInterface Flange Installed
Cryostat Interface-elevation NCSX
• Headers lie within Cryostat wall.
- Gives access for diagnostics above flange
- Requires only 4 bellows/port
• Insulation is backfill with Nanogel® beads.
CRYOSTAT
Boot
1" Insulation (Microtherm)
0.5" Insulation (Microtherm)
1 1/4" Pipe Ring Headers
Bellows Seal
Port Flange
5/16" Coolant Tubes (390 C)
"U" Bracket
Flange Heater Leads/ Thermo- couples/ Loops
Port Extension
Mount Post
4.38 Ref
Insulation fill (Nanogel beads)
(150 C)
(80 K)
6.0
1
Notes 1. Feedthrough shown is projected view. Actual location lies within 6" region.
Cryostat Interface Flange Provisions NCSX
8 generic 2.75” CF flanges are provided at each interface
• Cost effective means to get gas seal between Cryostat/VV
• O-rings are adequate
• 3 flanges for thermocouple hookups (18 top/19 bottom pairs required)
-10 pair positions on each flange
-20 thermocouple positions total
-Backups not connected)
• 4 flanges for magnetic loop hookups
-19 pins each
- 38 wire pairs (loops) total
• 1 flange for heater hookups
- 4 pairs (includes backups)
Coolant Circuit Schematic NCSX
Diagram is for full Field Period
• WBS 12 interface extends through electric break.
• Tubing alternates to two header systems, giving a degree of redundancy.
- 2 ring headers on each side of port 12.
CRYOSTAT BOUNDARY 1
3 5
63
TOP
7
VERTICAL PORT
WBS12 Interface (TYP)
1 1/4" Ring Header
1 1/4" Ring Header
1 3
5
63
2 4
6
64
7 8
1 1/4" Ring
Flow
Break
Shutoff
BOTTOM
1 1/4" Ring Header
Flow
Break
Shutoff
2 4
6
Break Break
2 4
6 8
Rupture Disk
Rupture Disk
64
VACUUM VESSEL
Temperature Monitor
Pressure Monitor
Shutdown Controller
2" Supply Header
2" Supply Header
Cryostat Helium Detector
Check Valve
5/16" tubing (64 per field period)
Check Valve
2" Return Header
2" Return Header
CRYOSTAT BOUNDARY
CRYOSTAT BOUNDARY
CRYOSTAT BOUNDARY
Reference Calculation DocumentsNCSX-CALC-12-002 Vacuum Vessel Heating/Cooling Distribution System Thermo-hydraulic AnalysisNCSX-CALC-12-003 Vacuum Vessel Heat Balance Analysis
Design Assumptions-Insulation- 75% efficiency- Microtherm or equivalent insulation- VV 2.54 cm - Port, 3.81 cm inside MC, 5 cm outside MC - Areas between MC assemblies filled- Port ends 2.54 cm
System Design ParametersCoolant paths 192 parallelTube ID 0.63 cm (.25”)Average length 5.5 mCoolant Gaseous HeliumOperating Pressure 20 atmos. abs
NCSX
Heating/Cooling Calculations
Bakeout at 350 C• 17 kW required
Idle Operation at 20 C• 4.6 kW required
Thermo-hydraulics at bakeoutPressure drop 0.12 atmosEntrance Velocity 22 m/sTemperature drop 17 KFlow rate 731 k/hr (285 cfm)Capable of 24 kW with He skid upgrade
NCSX
Results-Heating
Heat Removal (14.4 MJ shot)• 16 kW
Thermo-hydraulicsPressure drop 0.22 atmos.Entrance Velocity 24.5 m/sAverage bulk temperature rise 4.9 KFlow rate 1660 kg/hr (305 cfm)Coolant entrance temperature 20 C
VV does not return to room temperature at this flow rate • Bulk temperature rise is somewhat less than calculated - 1-D model does not take into account the partial VV coverage by the tubes• Ratcheting discussed in later view graph, covered by DAC.
NCSX
Results - Cooling
NCSX-CALC-12-001-00- Local Thermal Analysis - Freudenberg
Analyzes cool down time, thermal ratcheting, clamp spacing, and thermal stresses in VV.
Thermal Criteria – As set forth in SRD
• Cool down in 15 minutes for:
• 14.4 MJ pulse
• Even heat distribution
• VV returns to re-pulse temperature of 40-80 C
Results
• Cooling clamps on staggered 4” X 10” spacing pattern meets criteria.– Space is maximum, nominal spacing is much closer– Compacts at upper and lower regions
• VV stresses are acceptable
NCSX
Vacuum Vessel Cool down Analysis
NCSXVV Steady State Temperature As Function of Clamp Spacing
288
293
298
303
308
313
318
323
328
333
338
343
0 2 4 6 8 10 12
Vertical Spacing Between Cooling Tube Clamps (inches)
4 Inch Horizontal Spacing
8 Inch Horizontal Spacing
Ste
ad
y s
tate
te
mp
era
ture
(K
)
• 14.4 MJ
• 15 minute cool down
• Temperature shown is max temp between clamps.
NCSXVV Temperature Response
• 14.4 MJ
• 15 minute cool down
• Temperature shown is max temp between clamps.
• Clamps on 4 X 10 grid (about average)
Ref. NCSX-CALC-12-001-00- Local Thermal Analysis - Freudenberg
NCSX
Vacuum Vessel Stress
4 X 10 spacing – 38Ksi
Coolant Tube Build-to Specification NCSX
Specification Covers the following:
• Applicable drawing and models. Drawings tabulate bending coordinates.
• Number of assemblies being fabricated (32 types, 6 of each)
• Standards, including stainless tubing, welding.
• QA Requirements for:weldingcleaningweld inspectionmetrologyleak checkingpermeability
• Contour tolerances are captured by drawings
FMECA NCSX
Conn ector not hooked up
CRYOSTAT BOUNDARY
VERTICAL PORT
VACUUM VESSEL
Temperature Monitor
Signal Conditioner
Heater Current Controllers
Heater Power Supply
Port Thermocouple
Heater Tape
Typical Inner and Outer Port Extension
Programmable Process/Temperature
Controller
Feedthrough (WBS 7)
VV Body Thermocouple
Coolant Tube System
Power WBS 12 Interface
WBS 12 Interface
Diagnostic Flange (WBS 12)
Electrical Isolation
Connectors Thermocouples
CRYOSTAT BOUNDARY
Includes Heating/Cooling System Off-Normal Operation
• Loss of coolant
• Loss of heaters
• Abnormal port flange and/or VV temperature
System integration of temperature monitoring and control
• Resistance Heaters
• Helium Coolant System
• Emergency shutdown
Vacuum Vessel Temperature Control System
Issues NCSX
Supports• Lateral supports not yet analyzed
Heating/Cooling• R&D prototype of Coolant Tube may be required.
Bidders are nervous about the complexity of the geometry.
Conclusion – VV Supports NCSX
• Support system strength is adequate for present and future operation. Analysis included the weight of port extensions, NB transition ducts, diagnostics, and upgrade PFCs.
• Support thermal isolation reduces the thermal load to the MC to an inconsequential level.
• The system permits thermal growth during temperature cycling.
• The system is adjustable and can align the VV in 6 axes.
• The system provides electrical isolation.
• Wherever possible, the system uses off-the-shelf commercial components.
Conclusion – Heating/Cooling System NCSX
• The system can provide adequate heat for idle and bakeout operation.
• The system can provide sufficient cooling to cool down the VV in the prescribed 15 minutes and stay within maximum steady state temperature requirement set forth in the SRD.
• The system is adequately insulated to reduce MC and Cryostat thermal loads to a manageable level.
• The stresses induced into the VV by thermal gradients are within safe levels.
• Provisions have been made to monitor temperatures, analyze them, and provide compensation in the event they are outside the design thresholds
• Interfaces through the Cryostat are provided which accommodates all of the cooling lines as well as local diagnostics, heater lines, and magnetic loops.
• Consequences of off-normal operation have been studied and documented in a FMECA.
• Commercial vendors were consulted to comment on the designs.