Myanma electrical outlook u kyaw swar soe naing
-
Upload
ye-phone-hlaing -
Category
Business
-
view
4.693 -
download
11
description
Transcript of Myanma electrical outlook u kyaw swar soe naing
Myanmar Electricity Outlook
March 29, 2012 Yangon, MYANMAR
Kyaw Swar Soe Naing (Executive Engineer, MEPE)
U Kyaw Kyaw (Chief Engineer, YESB)
Ministry of Electric Power (2)
The Republic of the Union of Myanmar
Demand Scenario
with reference to
Outline of presentation
Ministry of Electric Power (2)
1. Organization of Electric Power
2. Policy, Goal and Objectives of Electric Power
3. Demand Forecast and Power Supply Position of 30 years plan
(2001 to 2030)
3.1 Demand Forecast of 30 years plan
3.2 Power Supply Position of 30 years plan
4. Background History of Generation Growth & Power
Consumption up to 2011
5. Assessment on 30 years plan for ten years
6. Future work, Plan and Conclusion
1. Organization of Electric Power
Ministry of Electric Power (2)
Ministry of Electric Power (1)
- Implementation of Hydropower
Projects
- Hydropower Generation
- Thermal Power Generation from
Coal
Ministry of Electric Power (2)
- Thermal Power Generation from Gas
- Operation and Maintenance of Power
system
- Implementation of Transmission Lines
and Substations Projects
- Distribution of Electricity throughout
the Country
In order to effectively carry out to fulfill the electricity requirement for the
economic development, nation-building and multi-sector development tasks, on 15th
May 2006 the Ministry of Electric Power has been reorganized as two Ministries;
Organization of Electric Power
Hydropower Generation
Enterprise
Department of
Hydropower Planning
Minister
Department of Hydropower
Implementation
Deputy Minister
Planning & Policy matters Development of New
Hydroelectric Power Projects
Operation and maintenance of
(14) existing hydroelectric power
stations and (1) coal fired thermal
power station.
Acting as a Secretariat to the
Ministry Investigation, Design &
Technology, Construction
Selling the electricity to the
Ministry of Electric Power (2)
Ministry of Electric Power (1)
Department of
Electric Power
Minister
Deputy Minister
Myanma Electric
Power Enterprise
Electricity Supply
Enterprise
Yangon City Electri-
city Supply Board
Planning & Policy
matters
Thermal Generation Supply electricity to
the whole country
except Yangon
division. Acting as a
Secretariat to the
Ministry
Control & Operation of
the National Grid
Construct
distribution lines &
substations within
States & Divisions
Construction &
Maintenance for
transmission lines and
substations
Purchase the electricity
from MOEP 1 and other
JV Co.
Selling Electricity to ESE
& YESB
Supply electricity to
Yangon division only
Construct distribution
lines & substation in
Yangon division
(Subsists on own
fund)
Ministry of Electric Power (2)
Distribution Generation
YESB (MOEP 2)
Transmission
End User
HPGE (MOEP 1)
MEPE (MOEP 2)
MEPE (MOEP 2) ESE (MOEP 2)
JV/IPP
7 Generation Transmission Distribution
Electricity Supply to Consumer
Voltage
(kV)
Nos. of
Line
Length
miles km
230 42 2,020.23 3,250.55
132 39 1,480.76 2,382.54
66 137 2,245.93 3,613.70
Total 218 5,746.92 9,246.79
Existing Transmission Lines
Voltage
(kV)
Nos. of
Substation
Capacity
(MVA)
230 25 3,280
132 25 1,578.5
66 96 1,983.1
Total 146 6,841.6
Existing Substations
8
National Grid System
- In National Grid System of Myanmar, there are 28 Nos. of
Power Generating Stations, i.e. (17) Hydropower Stations, (1)
Coal Fire Power Plant, (10) Gas Turbine Power Plants
(including 4 Combined Cycle in Yangon).
- The major electric power generating stations feed electricity
into the National Grid System with 230 kV, 132 kV and 66 kV
transmission lines and substations.
Existing Facilities of Electric Power Sector in Myanmar, 2011-2012
2. Policy, Goals and Objectives of Electric Power
Ministry of Electric Power (2)
• To employ gas turbine power generation only for short term and
rely on hydroelectric power as a vital source of energy
sufficiency
10
• To generate and distribute more electricity for economic
development
• To reduce losses and conserve electric energy for future energy
sufficiency
• To promote electricity production from new and renewable
sources of energy
Policy for Electric Power Sector
Ministry of Electric Power (2)
11
Goals and Objectives
(1) To employ the hydro power generation as a base load and the
gas turbine generation as a peak load
(2) To perform the combined cycle power generation in the gas
turbine power stations in order to conserve the fuel
consumption
(3) To expand the National Grid System, whereby enlarged and
developing industrial zones can be electrified and also the
electrification of towns and villages by diesel generating sets
will be eliminated
(4) To enhance the quality of the power system in the transmission
and distribution sectors according to the technical standards
Ministry of Electric Power (2)
12
(5) To reduce the power interruption frequency and duration
(6) To improve the reliability and stability of the power system
(7) To reduce the loss of electricity incurred in transmission and
distribution
(8) To provide the policy and technical know how to use
alternative energy such as bio-mass in remote area, where
electricity through the National Grid is not accessible
(9) To promote the development of non-conventional energy
resources such as wind, solar, geothermal and tidal energy to
meet the future power demand
Ministry of Electric Power (2)
Goals and Objectives
30 years Plan Committee
In 2001, Ministry of Electric Power founded a committee as
follow to establish the 30 years plan for electricity sector, to
adequate supply to the growth electricity demand.
Minister C h a i r m a n
Deputy Minister Deputy Chairman
Director General (Department of Electric Power) Member
Director General (Department of Hydro Power) Member
Managing Director (Myanma Electric Power Enterprise) Member
Consultant of Ministry of Electric Power Member
Chief Engineer, MEPE Member
Deputy Chief Engineer (admin), MEPE Member
Deputy Chief Engineer (Gas Turbine PP.), MEPE Member
Deputy Chief Engineer (Distribution), MEPE Member
Director (Account), MEPE Member
Deputy Director General (admin), DEP Member
Director (Planning for Distribution), DEP Member
Ministry of Electric Power (2)
3. Demand Forecast and Power Supply Position
of 30 years plan (2001 to 2030)
No.
States and
Divisions in
Myanmar
MW
1 Kachin 2061
2 Kayar 3909
3 Kayin 17021
4 Chin 1312
5 Sagine 2400
6 Tanintharyi 692
7 Pegu 483
8 Magway 122
9 Mandalay 3482
10 mon 292.4
11 Rakhine 246
12 shan 7700
Total 39720
5% 10%
43%
3%
6%
2%
1%
0%
9%
1%
1% 19%
Kachin
Kayar
Kayin
Chin
Sagine
Tanintharyi
Pegu
Magway
Mandalay
mon
Rakhine
Hydro Power Resources in Myanmar
-It can be said that about half (43%) of the hydro power resource of Myanmar
is in Kayin state, and the second largest resource (19%) is in Shan state.
NOTE: This figure was shown in 30 years plan. Update data shows 92 promising projects, total installed capacity
about 46000 MW. The difference takes place in Hydro power resources in Kachin State.
UPPER
YEYWA
(280 MW)
SINEDIN
(76.5 MW)
KANZAUK
28
S
N
EW
80
BALUCHAUNG-3
(48 MW)
4
120
THAUK-YE-KHAT-2
(120 MW)14
SITTAUNG
4
MINHLA
130
11
13
KUTKHAI
Figures in black color near Transmission Lines indicate the line length in miles.
80
YE
82
THAHTAY
CHAUNG
(111 MW)
ANN
40
INGON
PATHEIN
THARYARGONE
BALUCHAUNG-2
(6x28 MW)
THATON
MAWLAMYINE
MOEGOKE
HLAINGTHARYARATHOKE
73
SHWESARYAN
OHNTAW
OKSHITPIN
TAUNGOO
100
MYITTHA
(40 MW)
HAKA
THEINNI
FALAM
20
30
THAINGIN
KONHEIN
MONG-NAUNG
MONG-HSU
38
NAUNG
MONG
MINE YAL
MYITKYINA
140
SHWELI (3)
( 1050 MW )
UPPER
KENG TAWNG
(51 MW)
MAEI
KYAUK PHYU
NGAPYAWDAING
SHWEDAUNG
KAMARNAT
MYAUNG TAGAR
SHWEMYO
NAMSAN
35
90
35
MOGAUNG
NABAR
40
75
55
TOUNGUP
42
YENGBYE
MANSAN
90
THAPYAYWA
95
WINEMAW10
TANT YANN
33
HOPONG
25
20
11
WANSIN
146
14SANE
TAUNGTAWKWIN
35
76
Future Plan of Myanmar Power Grid 13. 5.2011
NAYPYITAW-1
100
96
30
MAUBIN
117
5.31
MANN
70
60
HSI
HSAING
DAGON(EAST)
10
THAKETA
230 kV ( Future )
132 kV ( Future )
66 kV ( Future )
500 kV ( Future )
Hydro-power Station ( Existing )
Hydro-power Station ( Future )
Power Station
132 kV ( Existing )
230 kV ( Existing )
66 kV ( Existing )
Substation
132 kV ( Future )
230 kV ( Future )
66 kV ( Future )
500 kV ( Future )
Transmission Line
132 kV ( Existing )
66 kV ( Existing )
230 kV ( Existing )
30 years Plan and Strategy
Plan -Electricity productions by employing the gas turbines power generations
only for short term
-Relying on the hydro electric power generation as one important source of
energy sufficiency.
-The projects to generate and distribute more electricity for economic
development and to reduce the losses of electric energy for future energy
sufficiency of Myanmar nation
-To promote electricity production from new and renewable energy resource
Strategy -To develop all the available energy resources for the electricity productions
-To improve electricity production level with the existing energy resources
-To study the unsuppressed electricity demands.
Methodology on Demand Forecast (2001)
Three cases of the growth of Electricity Demand 1. Low Growth
-In historical trend of generation, electricity consumption is generally increased about
2.0 times in 10 years (within decade).
-assumed doubling of the demand in every ten year
2. Base Case
-assumed growth rate of demand taking into account experience in Thailand
-Estimated growth of electricity is 1.0 % and 1.5% greater to the demand of Low
Growth
3. High Growth
-The growth of economy is high and GDP is greater than 7.0% per annum
-Estimated growth of electricity is 1.0% and 1.5% greater to the demand of Base Case
Methodology on Demand Forecast
5
6
7
8
9
10
11
12
13
14
Low Growth Base Case High Growth
The trend of the growth of electricity demand in three cases
The percentage of the growth of electricity demand will
relatively increase to 2021, and the percentage of the growth will
decline from 2021 to 2031.
(%)
Ministry of Electric Power (2)
3.1 Demand Forecast of 30 years plan (2001 to 2030)
0
4000
8000
12000
16000
20000 2
00
0-2
00
1
20
01
-20
02
20
02
-20
03
20
03
-20
04
20
04
-20
05
20
05
-20
06
20
06
-20
07
20
07
-20
08
20
08
-20
09
20
09
-20
10
20
10
-20
11
20
11
-20
12
20
12
-20
13
20
13
-20
14
20
14
-20
15
20
15
-20
16
20
16
-20
17
20
17
-20
18
20
18
-20
19
20
19
-20
20
20
20
-20
21
20
21
-20
22
20
22
-20
23
20
23
-20
24
20
24
-20
25
20
25
-20
26
20
26
-20
27
20
27
-20
28
20
28
-20
29
20
29
-20
30
Low Growth Base Case High Growth
Provision of power
export to Thailand
Provision of power
export to India
MW
Demand Forecast for 30 years
Provision of electricity power export to Thailand and India were sharply
increased in demand forecast for all cases at the 30 years plan. About 5000 MW
(40 % of demand) was planned to export.
0
20
40
60
80
100
120
0
200
400
600
800
1000
(2001-2002)
start
(2005-2006)
Finish
(2010-2011) (2015-2016) (2020-2021) (2025-2026) (2030-2031)
Maximum demand per person (kWh) Population (million)
Kil
o w
att
hou
r (k
Wh)
Po
pu
lati
on
(m
illi
on
)
Electricity consumption by one person
-Myanmar population is assumed to expand from an estimated 52.18
millions in 2001 to 95.33 million in 2031, an annual average rate of
increase of 2.1 %.
-Because of growth GDP, the electricity consumption per person is also
increased.
Ministry of Electric Power (2)
3.2 Power Supply position of 30 years plan (2001 to 2030)
Installed and Firm capacity in 30 years plan
0
5000
10000
15000
20000
25000 2
00
0-2
00
1
20
01
-20
02
20
02
-20
03
20
03
-20
04
20
04
-20
05
20
05
-20
06
20
06
-20
07
20
07
-20
08
20
08
-20
09
20
09
-20
10
20
10
-20
11
20
11
-20
12
20
12
-20
13
20
13
-20
14
20
14
-20
15
20
15
-20
16
20
16
-20
17
20
17
-20
18
20
18
-20
19
20
19
-20
20
20
20
-20
21
20
21
-20
22
20
22
-20
23
20
23
-20
24
20
24
-20
25
20
25
-20
26
20
26
-20
27
20
27
-20
28
20
28
-20
29
20
29
-20
30
Low Growth Base Case High Growth Installed Firm
-To ensure adequate power supply sufficiently to the growth electricity demand,
installed capacity will reach more 5000 MW than high growth demand.
-Firm capacity also required over of the high growth demand
MW
Note: Firm power represents amount of energy that can be generated by a power plant with a certain probability.
0
5000
10000
15000
20000
25000
20
00
-20
01
20
01
-20
02
20
02
-20
03
20
03
-20
04
20
04
-20
05
20
05
-20
06
20
06
-20
07
20
07
-20
08
20
08
-20
09
20
09
-20
10
20
10
-20
11
20
11
-20
12
20
12
-20
13
20
13
-20
14
20
14
-20
15
20
15
-20
16
20
16
-20
17
20
17
-20
18
20
18
-20
19
20
19
-20
20
20
20
-20
21
20
21
-20
22
20
22
-20
23
20
23
-20
24
20
24
-20
25
20
25
-20
26
20
26
-20
27
20
27
-20
28
20
28
-20
29
20
29
-20
30
hydro install Thermalinstall
Hydro and Thermal Installed in 30 years Plan
-Installed capacity of power plants was determined generally above the generation
-Hydropower will play a major role in future electricity power generation.
MW
Strategy to improve the installed capacity in 30 years Plan
Short term and Long term projects Short terms projects include build up natural gas used Combine Cycle Power
plants and small Hydro Power plants. Long term projects include build up Hydro
Power plants to supply the domestic as well as export electricity to neighboring
countries considering the economical aspects
Strategy Strategy considered that Hydro power will be employed in base load and natural gas
turbine power plant will be employed in peak load.
Hydropower will play a major role in future electricity power generation and the
country requires to produce and develop the other energy resources.
Ministry of Electric Power (2)
5. Background History of
Generation Growth &Power Consumption up to 2011
27
Historical Growth of Peak Load
0
200
400
600
800
1000
1200
1400
1600
1800
1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
Meg
a w
att
(M
W)
-Considering peak load during each year, the trend of growth of electricity
demand can be considered.
-Peak load has grown from 322 MW in 1989 to 1533 MW in 2011.
-Growth was fairly steady up to 2004, almost no growth from 2004 to 2007,
and then accelerated to about 8.8 %/year up to 2011.
28
Historical Growth of Generation & Consumption
0
2000
4000
6000
8000
10000
19
88
-19
89
19
89
-19
90
19
90
-19
91
19
91
-19
92
19
92
-19
93
19
93
-19
94
19
94
-19
95
19
95
-19
96
19
96
-19
97
19
97
-19
98
19
98
-19
99
19
99
-20
00
20
00
-20
01
20
01
-20
02
20
02
-20
03
20
03
-20
04
20
04
-20
05
20
05
-20
06
20
06
-20
07
20
07
-20
08
20
08
-20
09
20
09
-20
10
20
10
-20
11
Generation Consumption
GW
h
losses
-The growth of annual generation and consumption is gradual increase to 2010
-However, Generation and consumption are accelerated in 2010 and 2011.
(GW
h)
Electricity Consumptions
-General purpose and Industrial used over 85 % of the total consumptions.
-General purpose used and Industrial used consumptions are almost same for
every year.
-The growth of consumptions are almost same for two cases.
0
1000
2000
3000
4000
5000
6000
7000
General Purpose Industrial
NOTE: General purpose used based on the used of House Hold
Grid System Isolated Total
(MW) (MW) (MW) (% )
Installed Capacity 3,360.90 100.08 3,460.98 100.00%
Hydroelectric 2,526.00 33.34 2,559.34 73.95%
Gas 714.90 - 714.90 20.66%
Coal 120.00 - 120.00 3.47%
Diesel - 63.02 63.02 1.82%
Bio Mass - 3.72 3.72 0.10%
73.95%
20.66%
3.47% 1.82% 0.10%
Hydroelectric Gas Coal Diesel Bio Mass
30
Installed Capacity in Year 2011
Growth of Installed Capacity up to 2011 M
ega
wat
t (
MW
)
-Although the growth of the installed capacity of thermal power plant is greater
between 1985 and 2005, that of Hydel power plant become greater since 2005.
-In 2011, the installed capacity of Hydel power plant become much greater
than that of thermal power plant
0
500
1000
1500
2000
2500
3000
3500
4000 1974
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
Hydro Thermal Coal
GW
h
Share of Electricity Generation up to 2011
-Same as installed capacity, the generation of hydel power is lower than that of
thermal power till 2005-2006.
-Since 2006-2007, the generation of hydel power become greater than that of
thermal power and much higher in 2010-2011
0
2000
4000
6000
8000
10000
Hydel Thermal
Note: After 2007, generation of Hydel represents generation of MOEP 1
Conclusion on Trend of Generation and Consumption
-Although annual generation is around 1100 MW, peak load has reached to
1533 MW in 2011. it shows that the generation was not supply enough to the
country consumer level.
-At present, any amount supply available would be fully consumed.
Demand was suppressed.
-Hydro power sources become highly dominated in the demand area as the
installed capacity is increased.
-The generation from Hydel power play a major role in these years and future
electricity power generation.
Therefore, the future development relies solely on development of hydro
power and is being carried out annually.
4. Assessment on 30 years plan for ten years
Ministry of Electric Power (2)
losses Meg
a w
att
(MW
)
Assessments on forecast with generation and consumption
-Till now, the generation has not reach to the demand forecast.
-Considering peak load as the demand, demand forecast is not much differed from the demand
forecast.
-However, annual generation and consumption reached only about 50% of the demand forecast.
0
200
400
600
800
1000
1200
1400
1600
1800
2000
2000-2001 2001-2002 2002-2003 2003-2004 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 2009-2010 2010-2011
Low Growth Base Case High Growth Generation Consumption Peak load
Comparison of installed capacities
0
500
1000
1500
2000
2500
3000
3500
4000
2001-2002 2002-2003 2003-2004 2004-2005 2005-2006 2006-2007 2007-2008 2008-2009 2009-2010 2010-2011
Installed (2010) Installed (Forecast)
Meg
a w
att
(MW
)
-The difference between the installed capacities in 2010 and forecast is about
1000 MW in 2011. Lack of the installations of the power plants in both hydro
power and thermal power.
-Forecast is much differed from actual in 2006 to 2009.
-However, installed capacities become closer to forecast since 2009.
Assessments on 30 years plan
-Ten years has passed for 30 years plan and the 2001 projection
was different from the actual situation.
-Till now, the generation has not reach to the demand.
-The difference between the installed capacities in 2010 and
forecast is about 1000 MW because the lack of power plants
installations in both hydro power and thermal power.
-Installed capacities become closer to forecast since 2009.
-The installations of new power plant are required to meet the
rapid growth of the electricity demand and to maintain the
electricity supply at a satisfactory level.
5. Future Works, Plan and Conclusion
Ministry of Electric Power (2)
-2001 demand projection did not consider the project demand based on consumer
categories and divers of energy. Therefore, MOEP2 have to revise the demand
forecast.
Currently, MOEP 2 receives a consulting services (Conlenco, Switzerland) to
prepare for a system planning study including demand projection.
-Planning for future development relies on Hydro power, MOEP1 develops a list
of potential power projects and it seeks potential developers.
-Based on hydro power plant, connections between generation sources to load
centers then is being carried out.
-Mostly, thermal power plant are using the fuel as natural gas to generate power in
peak load and have been used to reduce the low voltage.
Myanmar oil and gas enterprise (MOGE) prepare its production plan and allocate
gas for power generation.
Future Works and Plan
Ministry of Electric Power (2)
Ministry of Electric Power (2)
-Another way to meet the increasing demand is to accelerate the
development of the electricity productions with the clean energy. 30 years
plan considered 100 MW wind turbine power plant in third year term
project.
At present, Engineers from Ministry of Electric Power No.2 and Gunkul Co.
Ltd are working feasibility studies to investigate the possibilities to install
Wind Turbine Power plants totally 1000 MW.
Furthermore, the possibility of the installations of power plant using with
Solar Power for the central of Myanmar are being investigated.
Future Works and Plan
Conclusion
-To meet this substantial electricity demands, a high senior official group
established by MEP prepared 2001 demand projection.
Although the 2001 demand projection (30 years plan) was simplistic and
having requirements, the actual demands seem closer to the forecast in 2011.
However, consideration made since the country consumption level was very
low, the demand will become much higher than the forecast.
-The demand forecast require to revise including the linkage between the
project demand, resources availability (fuel mix outlook), technical
specifications and cost parameters.
-Although Hydro power is conducted for base load, gas turbine CCPP
technology are also expected to follow in the electricity generation for the
generation in summer, peak load and to reduce the voltage drop.
-The sustainable and renewable energy such as solar energy, wind energy
and geothermal energy will be necessary to use to provide the electricity
widely.
Thank You
for
Your Kind Attention!!
42
0
2000
4000
6000
8000
10000
12000
14000 2
00
0-2
00
1
20
01
-20
02
20
02
-20
03
20
03
-20
04
20
04
-20
05
20
05
-20
06
20
06
-20
07
20
07
-20
08
20
08
-20
09
20
09
-20
10
20
10
-20
11
20
11
-20
12
20
12
-20
13
20
13
-20
14
20
14
-20
15
20
15
-20
16
20
16
-20
17
20
17
-20
18
20
18
-20
19
20
19
-20
20
20
20
-20
21
20
21
-20
22
20
22
-20
23
20
23
-20
24
20
24
-20
25
20
25
-20
26
20
26
-20
27
20
27
-20
28
20
28
-20
29
20
29
-20
30
Low Growth (No Export Program) Low Growth (with Export Program)
Provision of power
export to Thailand
Provision of power
export to India
MW
Export and No Export Program
-Considering Export program, the demand will reach to 12000 MW
-Without Export program, the demand will reach to 7000 MW
-The demand forecast estimated about 40 % of demand to export.
NOTE: No export program = No Provision of Power to Thailand at 2010 and India at 2015.
(estimated data based on estimated demand in 2011, 1533 MW)
Investment Opportunities in Power Sector
44
Generation
For the Generation Sub Sector, Foreign Direct Investment (FDI)
can be done by the permission from Foreign Investment
Commission under the Law and Procedure of Foreign Investment
(1988), in the form of Joint Venture and Build-Operate-Transfer
(BOT) system for suitable power generation projects.
Local investors are also allowed to participate in the scheme of
Independent Power Producer (IPP) for hydropower projects.
Investment Opportunities in Power Sector
45
Transmission and Distribution
For the Transmission and Distribution Subsectors under
Ministry of Electric Power No. (2), there have been no projects
to be implemented by Foreign Direct Investment (FDI)
permitted so far.
The procurement of required Transmission Line Materials and
Substation Equipment from foreign countries are funded either
by Government Budget or Foreign Loan.
Civil Works and Electrical Installation Works are undertaken by
Local Construction Companies under the supervision of
MOEP2.
Investment Opportunities in Power Sector
46
Transmission and Distribution
As in the other countries, EPC (Engineering, Procurement and
Construction) Contract and Turnkey Projects are not yet
practiced.
In order to submit the tender for supply materials, Local and
Foreign Companies need to request the registration in Mailing
List of MOEP (2).
Registered companies are invited tender and MOEP (2) evaluate
by opened tender system.
47
Tax Obligations
The JV Company shall be levied on the following taxation:
- 5% commercial tax
- 2% income tax
- 2% withholding tax
Exemptions and Reliefs from taxes can be submitted to
Myanmar Foreign Investment Commission:
- exemption from income-tax for a period extending to 3
consecutive years, inclusive of the year of
commencement
- relief from income-tax on profits if reinvested therein
within 1 year after the reserve is made
Future Plan of Generation Power Stations (48 projects)
Sr. Name of Project Installed Capacity
(MW)
Implementing
Agency
1 Upper Baluchaung 29 NEO Co.
2 Anya Phya 9 Delco Co.
3 Upper Sedawgyi 64 Htoo Co.
4 Thakyak 20 Yuzana Co.
5 Belin 280 Asia World Co.
6 Kawthaung (Coal) 6 Thanphyothu Co.
7 Yenam 1,200 CPI (China)
48
Generation Type Nos. of Project Installed Capacity (MW)
Hydropower 45 35,578.5
Coal 2 606.0
Gas 1 450.0
Total 48 36,634.5
Future Plan of Power Generating Stations (48 project)
Sr. Name of Project Installed Capacity (MW) Implementing Agency
8 Kawanglangphu 2,700 CPI (China)
9 Pisa 2,000 CPI (China)
10 Laza 1,900 CPI (China)
11 Wutsok 1,800 CPI (China)
12 Chibwe 3,400 CPI (China)
13 Gawlan (Nawchankha) 100 YPIC (China)
14 Lawndin (Nawchankha) 435 YPIC (China)
15 Wuxhongze (Nawchankha) 60 YPIC (China)
16 Hkankan (Nawchankha) 140 YPIC (China)
17 Tongxinqiao (Nawchankha) 320 YPIC (China)
18 Nantabat (Kachin) 200 Guodian(China)
19 Tapain (2) 168 DUHD (China)
20 Konlon (Upper Thanlwin) 1,400 Hanergy(China)
21 Naungpha 1,000 Hydro China
22 Mangtaung 200 Hydro China
49
Future Plan of Generation Power Stations (48 projects)
Sr. Name of Project Installed Capacity (MW) Implementing Agency
23 Htamanthi 1,200 NHPC (India)
24 Shwesaye 660 NHPC (India)
25 Laymyo 600 CDOI (China)
26 Laymyo (2) 90 CDOI (China)
27 Tuzxing (Nampon) 105 CDOI (China)
28 Hanna(Nampon) 45 CDOI (China)
29 Thakhwa(Nampon) 150 CDOI (China)
30 Palaung(Nampon) 105 CDOI (China)
31 Bawlakhe(Nampon) 180 CDOI (China)
32 Nantabat (Kayah) 180 Guodian(China)
33 Heku (Namlwai) 88 YNPG (China)
34 Kengyan (Namlwai) 28 YNPG (China)
35 Mongwa (Namlwai) 50 YNPG (China)
36 Wantapeng (Namlwai) 25 YNPG (China)
50
Future Plan of Power Generation Stations (48 projects)
Sr. Name of Project Installed Capacity (MW) Implementing Agency
37 Keng Tong (Namlwai) 96 YNPG (China)
38 Solu (Namlwai) 165 YNPG (China)
39 Mongtong (Upper
Thanlwin)
7,110 Three Gorges + EGAT
40 Ywathit 4,000 CDOI (China)
41 Hutgyi 1,360 Sinohydro + EGAT
42 Taninthayi 600 Italia-Thai
43 Shweli (2) 520 Huaneng Lancang
44 Mawleik 520 Guodian(China)
45 Kalewa(Coal) 600 Guodian(China)
46 Saingdin 76.5 CDOI
47 Nankha 200 YNPG (China)
48 Yangon Thilawa (Gas) 450 BKB (Korea)
Total (48) Nos 36,634.5 MW
51
Future Plan of Transmission Lines Future Plan of Substations
Voltage
(kV)
Nos. of
Line
Length
miles km
500 6 1,693.0 2724.04
230 80 5,894.0 9483.45
132 12 410.5 660.49
66 33 1,222.1 1966.36
Total 131 9,219.6 14834.34
Voltage
(kV)
Nos. of
Substation
Capacity
(MVA)
500 10 5,000
230 25 2,360
132 10 675
66 31 340
Total 76 8,375
52
Transmission Lines and Substations (Future Plan)
In order to reinforce the present National Grid System and to
facilitate power transmission from new generating stations to
National Grid System, Ministry of Electric Power No.(2) has a
long term plan of 131 Transmission Lines and 76 Substations
in future.
UPPER
YEYWA
(280 MW)
SINEDIN
(76.5 MW)
KANZAUK
28
S
N
EW
80
BALUCHAUNG-3
(48 MW)
4
120
THAUK-YE-KHAT-2
(120 MW)14
SITTAUNG
4
MINHLA
130
11
13
KUTKHAI
Figures in black color near Transmission Lines indicate the line length in miles.
80
YE
82
THAHTAY
CHAUNG
(111 MW)
ANN
40
INGON
PATHEIN
THARYARGONE
BALUCHAUNG-2
(6x28 MW)
THATON
MAWLAMYINE
MOEGOKE
HLAINGTHARYARATHOKE
73
SHWESARYAN
OHNTAW
OKSHITPIN
TAUNGOO
100
MYITTHA
(40 MW)
HAKA
THEINNI
FALAM
20
30
THAINGIN
KONHEIN
MONG-NAUNG
MONG-HSU
38
NAUNG
MONG
MINE YAL
MYITKYINA
140
SHWELI (3)
( 1050 MW )
UPPER
KENG TAWNG
(51 MW)
MAEI
KYAUK PHYU
NGAPYAWDAING
SHWEDAUNG
KAMARNAT
MYAUNG TAGAR
SHWEMYO
NAMSAN
35
90
35
MOGAUNG
NABAR
40
75
55
TOUNGUP
42
YENGBYE
MANSAN
90
THAPYAYWA
95
WINEMAW10
TANT YANN
33
HOPONG
25
20
11
WANSIN
146
14SANE
TAUNGTAWKWIN
35
76
Future Plan of Myanmar Power Grid 13. 5.2011
NAYPYITAW-1
100
96
30
MAUBIN
117
5.31
MANN
70
60
HSI
HSAING
DAGON(EAST)
10
THAKETA
230 kV ( Future )
132 kV ( Future )
66 kV ( Future )
500 kV ( Future )
Hydro-power Station ( Existing )
Hydro-power Station ( Future )
Power Station
132 kV ( Existing )
230 kV ( Existing )
66 kV ( Existing )
Substation
132 kV ( Future )
230 kV ( Future )
66 kV ( Future )
500 kV ( Future )
Transmission Line
132 kV ( Existing )
66 kV ( Existing )
230 kV ( Existing )
Sr.
No.
Voltage
Level
Line
(mile)
Substation
(MVA)
1. 500kV 263 1500
2. 230kV 1697.31 1400
3. 132kV 85 100
4. 66kV 342 130
Total 2,387.31 3,130
For the short term plan, 35
projects of transmission
line and substations within
year 2011-12 to 2015-16
have to be implemented.
Transmission Lines and Substations (Future Plan)
53
Conclusion on Demand Forecast of 30 years plan
-Three scenarios were prepared based only on historical
consumption and assumed the growth of demand.
-Project demand based on consumer categories, divers of energy
etc., were not considered in demand forecast.
-There was neither separation of the domestic demand and
demand for export. Export demand forecast is about 40 % of the
annual demand forecast.
-Since 2001, it has not been revised in a systematic manner
though some update has been carried out.