Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
-
Upload
charlotte-hood -
Category
Documents
-
view
219 -
download
0
Transcript of Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
2
Vacuum Progress Since Oct 6th (Last Quarter)
• Found “Short” on Lead Can• Cryo Platform installed with Dewer• ALL Cryostat Insulating Vacuum is Leak Check Certified!• Pressure tested Nitrogen & Helium Circuits • Removed AD Cryo Test Box (Frig check out complete)• Indium Resistance Measurements (Bolts tightened)• “Cold Leak” Found: Electrical Isolators on Interconnects
replaced – Leak Checked OK– Isolators on Lean Can (6) Inspected, – Will be replaced when parts arrive– Isolators on hairpin not accessible
3
Magnet Progress Since Oct 6th (Last Quarter)
• Installed Top Yoke! – All Yoke Vertically & Radially aligned– Horizontal ear shims installed, but bolts are still loose (pole
alignment)– Steel “make-up” plates installed
• All 3 Cryostats Shimmed, Vertically & Radially aligned, and bolted & pinned in place– Support of Inner Upper coil transferred to upper yoke– Jack bolts removed from Outer Coil– Push Rods installed– Transport radial stops replaced – All strain gauges repaired or documented
• Poles are clean! – Ready to Install
4
Electrical Progress Since Oct 6th (Last Quarter)
• Waterfall support structure & cable tray Installed• Ring Cable Tray Installed• Dump resistor mounted on roof (cables go outside)• Bruckner PS fully checked out & Installed in Hall
– Connected to building Power
• Dump Trip Cabinet Installed & connected to PS• Quench Protection Rack rebuilt & Installed in Hall• Electrical Grounding Infrastructure mostly in place
5
Instrumentation Progress Since Oct 6th (Last Quarter)
• LCW Systems and Instrumentation Installed• Controls cabinets in Computer Room being filled• Built & Routing cables for
– Ring Instrumentation – LCW Instrumentation
• ODH System Operational
6
The MC-1 Building
• Door Locks / Card readers installation
• Need Training to enter• Mezzanine has a
Source box• All Phones installed
– Ctrl Rm = xMuon
• Internet in MC-1
• G-2 Hall is Now ODH Ø– No additional training is
necessary– If alarms go off, Leave.
• If using a ladder on Cryo platform use fall
protection tie-offs
7
Upcoming Jobs
• Install Cryostat Pumping Manifolds (CMP’s) and Turbos• Install Poles• Wire Instrumentation on LCW & program PLC• Install permanent vent lines for vacuum pumps• Install Stairs to Ring Center• Install air system for valves• Connect Quench Protection Rack (QPR) to UPS• Dump Resistor connected outside• Transfer line fabrication & Installation
8
Milestones/Schedule
• Vacuum Pump Down – April 6• Cool down to Nitrogen – April 13• Cool Down to Helium – April 27• Begin Power Up – May 11• Full Power – May 22• Beam Commissioning – March 28, 2017• Data Taking – September 28, 2017
Project Schedule
2/12/15Polly | Muon g-2 Project9/11
MC-1 (GPP)g-2 Cryo Plant (AIP)
Ring AssemblyShim Field
Prep Chambers/Install
Construct/Install Sub-systems
Accelerator Modifications
Ring cold ready for operations (May 2015)
Experiment ready for operations (Jan 2017)Accelerator ready for ops (Mar 2017)
Ring Cold
Detector/DAQ Commission
BeamTune-up
Physics Production Running
Analysis Tools DevelopmentMock Data
2nd Results
Construction (Project & Muon Campus):
Operations (Laboratory):
Analysis (Collaboration):
1-2 x BNL statistics
~5-10 x BNL21 x BNL
Final Results
1st Results
FY17 Shutdown