04/19/2023 Mubarraz Surge Tank 1
Replace Mobile Radio System – Eastern ProvinceContract No. 6600024815
BI – 10 – 00112
Site : Mubarraz Surge TankScope Of Work : Battery Upgrade
04/19/2023 Mubarraz Surge Tank 2
Table Of Content
• Objective• Methodology• Step By Step Installation Procedure• Site Pictures• Loss Prevention And Safety
04/19/2023 Mubarraz Surge Tank 3
OBJECTIVE• The Objective of this document is as follows
• To describe the process and provide the necessary procedures required to implement the installation of the new batteries by replacing the old ones.
METHODOLOGY• Work Areas
• The tabulation below identifies the site location where the new Batteries including Disconnect Switch will be installed
04/19/2023 Mubarraz Surge Tank 4
STEP BY STEP INSTALLATION PROCEDURES• The following procedures will be conducted to attain a satisfactory
completion of this work. The work will be done in five-phases. The phases are as follows
– Phase I. Installation of temporary battery bank and temporary battery disconnect switch, dismantling and removing of existing battery bank and
disconnect switch.– Phase II. Installation of new battery rack, battery cell, battery cables and disconnect
switch– Phase III. Applying initial charge to newly installed battery cells and
discharge/recharge– Phase IV. Acceptance test newly installed battery string.– Phase V. Connecting the new battery string to the existing DC Rectifier.
04/19/2023 Mubarraz Surge Tank 9
Installed New 2 – 50 Sqmm Cable in the Existing Rectifier
Before After
04/19/2023 Mubarraz Surge Tank 14
LOSS PREVENTION AND SAFETY
During the installation SC/ACES personals will observe the Saudi Aramco Procedures to eliminate the rise of accidents and/or minimize incidents, which will eventually lead to injuries to personals and/or damage to equipment. Accordingly, and will follow Saudi Aramco Safety Procedures.
Thanks Dc Power Department