MT Continuum StatusMT Continuum Status
15-17 Feb 11
Jake Aplanalp, AIM Pgm MgrGerry Cullison, SSP
Mark Campbell, LM SS for SSPMike French, LSI
Jamie Stewart, AIM team
MT Continuum Prototype ProjectMT Continuum Prototype Project• Strategic Systems Programs (SSP) re-engineering 30+ week
training pipeline for TRIDENT Ballistic Submarine (SSBN) Missile Techs (MTs) into blended just-enough/just-in-time ILE-conformant Instructor Led (ILT) and self-paced segments
• AIM CPM and LO Module toolsets part of SSP’s baseline business process for this re-engineering
• First major end-to-end design, development, and maintenance project that’s defining CPM/LO Module business rules and data exchange mechanisms
• MT Continuum team:
– SSP / contractors - Requirements Owners– NAWCTSD / AIM team - CPM/LO Module support– LSI, Inc. - ISD and self-paced content design/development
Application to Other CommunitiesApplication to Other Communities• Based on NETC-mandated JDTA as fleet
performance requirement basis for learning content design and development
• Closely coordinated with NAVEDTRA 136 development
• NETC N7 staff recommended as “Poster Child” for ongoing NETC Continuum effort with all Centers
• Integrated development and maintenance environment for blended, SCORM and 136-compliant learning content
Project StatusProject Status• Plan, Analyze and Design Completed
– JDTA– Establishment of initial 3 major projects– Approval of revised 11-project structure
• Approval of learning objectives• Approval of ISD considerations elements
• Production Phase Kickoff Pending– Will be followed by export of 11 projects from
CPM to LO Module for production development in AIM I Rel 4.1 on fedsun
AIM Tool UsageAIM Tool Usage• Dedicated MT Continuum Prototype CPM and
AIM I Rel 4.1 instances hosted in Orlando
• Local AIM I Rel 4.1 instances running at GD-AIS Pittsfield (SMEs) and at LSI Jax (ISD/CD)
• Bi-directional data exchange between LO Module and LSI Venus.net LDC authoring toolset in place
• Excellent feedback from MT Continuum team on enhanced functionality and performance needed in CPM & LO Module
AIM Tool UsageAIM Tool Usage(contd)(contd)
• Status:– Per GD-AIS feedback, performance-enhanced
version of AIM I Rel 4.1 running locally in Pittsfield and Jax as well as on Orlando server
– Per GD-AIS feedback, significant enhancements made to AIM I Rel 4.1 storyboard functions/output
– Several additional enhancements recommended by GD-AIS incorporated into AIM I Rel 4.1 (Jan 11 delivery)
– AIM team resolved performance and reliability issues with Orlando fedsun Metaframe instance
Issues/ConcernsIssues/Concerns• “End to end” surveillance/maintenance test on
TLO/ELO in process to:– confirm existing change impact identification
functionality in CPM and LO Module
– identify near-term updates
– refine longer-term enhancements• Testing begun by Mark Campbell and Mike Lueken (LMMS) w/
favorable results• Identified critical issues addressed as part of AIM I Rel 4.1 and
5.0• Further testing surveillance testing on LDC is still required
and ongoing with Rel 4.1 by Jamie Swaim (CSF)• Team continues to refine versioning business rules/process
11
Modernized AIMModernized AIM
Modernized AIM cantie the entire
process together
Modernized AIM cantie the entire
process together
Learning Content
DvlpAnd
Maint(complete ILT / storyboards for learner-directed
content)
[LO Module]
LearningContent Planning
and Design(learning objectives,
content outline, content mgmt data)
[CPM]
Baseline Performance
Reqts
Performance Reqts
(Navy Job Duty Task Analysis /
Competency data)
LearningContent
Storage andDelivery
(learning object aggregations
managed via ties to learning objectives)
Performance Reqts
Updates
Content Outline Draft w Versioned
Learning Objectives
and Metadata
Versioned Learning Objective Updates
Baseline ILT Learning Content
Versioned ILT Learning
Content Updates
Change Impact
Reporting(based on
performance reqts updates;
specifies learning
objectives that may need changing)
Change Impact Reporting
(based on learning objective updates; specifies learning objects that may need changing)
List of learning objects
linked to impacted learning
objectives
Learner-directed Content
Development and Maintenance
[Venus]
List of learning objects
linked to impacted
tech data
Baseline and Updated Learner-directed Learning Content
AIM focus areas
Other govt repositories
COTS/GOTS CBT toolsets
Technical Data Repository
Links to Authoritative Tech Data / Updates
MT Continuum ProcessMT Continuum Process
12
LO ModuleOutputs:- complete ILT lessons/sections- storyboards for learner-directed content incl. metadata, links to IETMs, SME inputs on narrative, interactions, & graphicsInputs:- updated storyboard content from Venus.net
CPM
- baseline JTA data- learning objectives- content outline
- content mgmt data)
Content Outline Draft w Versioned Learning Objectives and Metadata
Versioned Learning Objective Updates
Change Impact
Reporting(based on
performance reqts updates;
specifies learning
objectives that may need changing)
Change Impact Reporting
(based on learning objective and tech
data updates; specifies learning objects that may need changing)
List of learning objects linked to impacted
learning objectives
Venus.net
LDC Dvlp/Maint
- amplify and finalize storyboard data from LO Module- dvlp initial LDC lessons/sections- coord review comments- finalize LDC content- export data back to LO Module
List of learning objects
linked to impacted tech data
Baseline and
updated run-time learner-directed content
Technical Data Repository
Links to Authoritative Tech Data / Updates
Baseline Learning Content
Versioned Learning Content Updates
CM’d source files for LDC
Lessons/Sections
?????
metadata,links to IETMs, SME inputs on
narrative, interactions, &
graphics
Updated metadata and graphics files
FRM Inputs on EnhancementsFRM Inputs on Enhancements
• Item 4.2.4.37: Add support to update Section content using the No-Change Change capability like AIM I.
• Item 4.2.4.38: Add ‘Select Later IETM’ functionality in the LO Module to update your Section’s IETM links with a later version of an IETM without having to reselect nodes