M/S. PAWAN FORMALIN PVT. LTD. - Welcome to...
Transcript of M/S. PAWAN FORMALIN PVT. LTD. - Welcome to...
M/S. PAWAN FORMALIN PVT. LTD. (New Proposed Project to Manufacture
Formaldehyde, Hexamine along with Resins) (Formaldehyde-1800MT/Month,
Hexamine-90 MT/Month, Urea Formaldehyde Resin-250 MT/month,
Melamine Formaldehyde Resin-250 MT/month, Urea Formaldehyde Molding Powder-250 MT/month)
Survey NO. 24/P, Village: Jambudiya, Taluka: Morbi,
District: Rajkot, Gujarat.
Rapid Environmental Impact Assessment Report As per High Court Stay Order No.
C/SCA/1782/2013 dated 9/12/2013 (Copy Enclosed in Chapter – 10 on pg. no. 10.6)
Prepared By:
T. R. Associates Ganesh Meridian, Block No.: - C, Office No. 605-A,
Opp. Kargil Petrol Pump, Nr. Sola Over Bridge, S. G. Highway, Ahmedabad-380060.
Email : [email protected] [email protected] Mo. No. 9825371099 YEAR - 2014
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates F
No. Condition Compliance status Page no.
1 Executive summary of the project. Given in ch-10 10.1-10.23
2 Justification of the project Given in the section 1.3 of
chapter-1
1.2
3 Photographs of proposed plant site Given in the section 1.13 of
Chapter-1
1.16
4 Promoters and their back ground Given in the section 1.4 of
chapter-1
1.5
5 Regulatory framework Given in the section 1.12 of
chapter-1
1.15
6 A map indicating location of the project and
distance from severely polluted area.
Project site location is given
in Fig. 1.0,1.1,1.2
1.6, 1.9-1.10
A Google map showing
distance from severely
polluted area from project
site is given in Annexure - B
78
7 Project location and plant layout.
Project location is shown in
Google map figure 1.2
1.10
Plant lay-out is given in the
chapter-2 Fig. no. 2.6
2.18
8 Infrastructure facilities including power sources. Given in the chapter-2
section no. 2.5.5
2.17
9
Total cost of the project along with total capital cost
and recurring cost/annum for environmental
pollution control measures.
Given in chapter - 8 8.1-8.2
10
Project site location along with site map of 10 km
area and site details providing various industries,
surface water bodies, forests etc.
Project site location along
with site map of 10 km area
is shown in topo map given
in the chapter-1, fig. 1.1
1.9
A Google map showing
nearest surface water bodies
& forests from project site is
given in Annexure – B.
79
Details of nearby industries
are shown in chapter – 3.5,
section - 3.5.5
3.5.15-
3.5.16
11
Present land use based on satellite imagery for the
study area of 10 km radius. Details of land
availability for the project along with supporting
Land use based on satellite
imagery for the study area of
10 km radius is shown in
3.4.15-
3.4.16
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates G
document. Chapter 3.4, section – 3.4.1 &
3.4.2
Details of land availability for
the project is shown in
section 2.6, table 2.4
2.17
Land documents are attached
as Annexure - C
81
12
Location of National Park/Wild life
sanctuary/Reserve Forest within 10 km radius of
the project.
Paneli reserve forest at 2.07
KM in ENE direction.
And 3.1 km in SSW direction
from our location. Image is
shown in Annexure B.
80
13. Details of the total land and break-up of the land use
for green belt and other uses. Section 2.6, table 2.4
2.17
14. List of products along with the production
capacities
Chapter-1, Section 1.1
1.1
15. Detailed list of raw materials required and source,
mode of storage and transportation.
Chapter – 2, Section 2.5.1,
table – 2.3 2.14-2.16
16. Manufacturing process details along with the
chemical reactions and process flow chart.
Given in the Chapter-2,
section no. 2.4 2.3-2.13
17.
Site-specific micro-meteorological data using
temperature, relative humidity, hourly wind speed
and direction and rainfall is necessary.
Given in section-3.1.1 3.1.2-3.1.6
18.
Ambient air quality monitoring at 6 locations within
the study area of 5 km. aerial coverage from project
site as per NAAQES notified on 16th September,
2009. Location of one AAQMS in downwind
direction.
Locations are given in Fig. no.
3.1.3 & table 3.1.4
AAQ results are given in table
– 3.1.5 to 3.1.8
3.1.9-3.1.12
19.
One season site-specific micro-meteorological data
using temperature, relative humidity, hourly wind
speed and direction and rainfall and AAQ data
(except monsoon) for PM10, SO2, NOx including
VOCs shall be collected. The monitoring stations
shall take into account the pre-dominant wind
direction, population zone and sensitive receptors
including reserved forests. Data for water and noise
monitoring shall also be included.
One season site-specific
micro-meteorological data
are given in Annexure A
1-77
AAQ data for PM10, PM2.5, SO2,
NOx including VOCs is shown
in table 3.1.5 to 3.1.8
3.1.10-
3.1.12
Monitoring stations are
shown in table – 3.1.4 & fig.
3.1.3
3.1.9-3.1.10
water monitoring data are
shown in Section – 3.3.1.1 &
3.3.1-3.3.3
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates H
fig. 3.3.1
noise monitoring data are
shown in table – 3.2.2
3.2.2-3.2.4
20.
Air pollution control measures viz. Multi-cyclone
and bag filter etc. shall be proposed for the effective
control of gaseous emissions within permissible
limits.
Given in section 2.10.2 in
table 2.10 2.26
21. Control methanol emission from drying section.
Not applicable.
22. Details of VOC monitoring system in the working
zone environment, if any
Latest technology will be provided in the working zone environment. We will be doing VOC monitoring twice a year.
23. Name of all the solvents to be used in the process
and details of solvent recovery system. Not applicable.
24. Design details of ETP, incinerator, boiler, scrubbers
/bag filters etc.
ETP – section 2.9.1
Incinerator – N.A.
Flue gas stack- table- 2.9
Scrubber – NA
MDC fig. 2.10
2.23
2.25
4.10-4.15
2.26
25. Details of water and air pollution and its mitigation
plan.
Water pollution & its
mitigation plan – section
2.9.1
Air pollution & its mitigation
plan – section 2.10
2.20-2.24
2.24-2.26
26 Action plan to control and monitor secondary
fugitive emission from all the sources.
Fugitive emission causes are
given in the chapter-2,
section 2.10.3.
2.26
27
Determination of atmospheric inversion level at the
project site and assessment of ground level
concentration of pollutants from the stack emission
based on site specific meteorological features. Air
quality modeling for proposed plant.
Given in Section 4.3.4.2 table
–4.2, 4.3, 4.4,
Fig. – 4.1, 4.2, 4.3
4.9-4.16
28
Permission for the drawl of ground water from
CGWA. Water balance chart including quantity of
effluent generated recycled and reused and
discharged.
We will apply after getting EC
Water balance – Fig-2.6 2.22
29 Action plan for ‘Zero’ discharge of effluent shall be
included. Given in the section – 2.9.1 2.20-2.24
30 Treatment of phenol in the effluent, if any. Not Applicable
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates I
31
Ground water quality monitoring minimum at 6
locations shall be carried out. Geological features
and Geo-hydrological status of the study area and
ecological status (Terrestrial and Aquatic).
Ground water quality
monitoring – table – 3.3.1 3.3.5
Geological features and Geo-
hydrological status of the
study area, section – 3.4.3
3.4.5-3.4.10
Ecological status (Terrestrial
and Aquatic) section - 3.4.7
3.4.20-
3.4.55
32
The details of solid and hazardous wastes
generation, storage, utilization and disposal
particularly related to the hazardous waste calorific
value of hazardous waste and detailed
characteristic of the hazardous waste. Action plan
for the disposal of fly ash generated from boiler
shall be included.
Details of solid & hazardous
waste is given in section 4.6.5
in chapter 4,
4.30-4.31
Action plan for fly ash –
Section –9.4 9.8-9.9
33
Precautions to be taken during storage and
transportation of hazardous chemicals shall be
clearly mentioned and incorporated.
Given in chapter-7, section
no. 7.6 7.6-7.13
34 Authorization/Membership for the disposal of
solid/hazardous waste in TSDF. We will apply after getting EC.
35 List of hazardous chemicals (as per MSIHC rule)
with toxicity levels. Section 7.5 7.4-7.5
36.
A write up on “Safe Practice” followed for methanol
handling, storage, transportation and unloading to
be submitted
Given in Section 7.6.1 7.6-7.7
37 A write up on “Treatment of workers affected by
accidental spillage of methanol/Phenol”.
Phenol is not used so it is not applicable.
Treatment of workers
affected by accidental
spillage of methanol is given
in section 7.10
7.17-7.18
38. Locating the plant in open area instead of covered
to be reviewed in view of safety consideration. Section 7.13 7.28-7.29
39 An action plan to develop green belt in 33 % area Section – 4.7 4.32-4.37
40
Action plan for rainwater harvesting measures at
plant site shall be included to harvest rainwater
from the roof tops and storm water drains to
recharge the ground water.
Section - 4.8 4.38-4.50
41. Details of occupational health programme.
Section 7.8
7.14
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates J
(i) To which chemicals, workers are exposed
directly or indirectly.
(ii) How the workers are evaluated concerning their
exposure to chemicals during pre-placement and
periodical medical monitoring
(iii) Liver function tests (LFT) during pre-placement
and periodical examination.
(iv) Whether these chemicals are within Threshold
Limit Values (TLV)/ Permissible Exposure Levels as
per ACGIH recommendation.
(v) What measures company has taken to keep
these chemicals within PEL/ TLV.
(vi) What are onsite and offsite emergency plan
during chemical disaster.
It will be below the values
given in Section 7.5
As per given in Section 7.5
Section 7.5
Section 7.5
Section 7.5
Section 7.14
7.4
7.4
7.4
7.4
7.4
7.30-7.37
42 Details of occupational health surveillance
programme. Section 7.7 7.13-7.14
43. Socio-economic development activities shall be in
place.
Chapter-3.5, section 3.5.1,
3.5.2, 3.5.3 3.5.1-3.5.15
44.
At least 5 % of the total cost of the project shall be
earmarked towards the Enterprise Social
Commitment based on Public Hearing issues and
item-wise details along with time bound action plan
shall be prepared and incorporated.
We will provide 1.5 % of the
total profit in CSIR activity.
45.
Detailed Environment management Plan (EMP)
with specific reference to details of air pollution
control system, water & wastewater management,
monitoring frequency, responsibility and time
bound implementation plan for mitigation
Measure shall be provided.
Environment management
Plan (EMP) with reference to
air pollution - Section 2.10
2.24-2.27
Environment management
Plan (EMP) with reference to
water & wastewater
management - Section 2.9
2.20-2.24
Monitoring frequency Table
5.2 5.3-5.4
Responsibility and Time
bound implementation plan
for mitigation measure shall
be provided - Section 9.5
9.9-9.12
46. EMP shall include the concept of waste-
minimization, recycle / reuse / recover techniques,
Energy conservation, and natural resource
Section - 9.4 9.8-9.9
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates K
conservation.
47.
Corporate Environmental Responsibility
(a) Does the company have a well laid down
Environment Policy approved by its Board of
Directors? If so, it may be detailed in the EIA report.
Section 9.3.3
9.3-9.4
(b) Does the Environmental Policy prescribe for
standard operating process/ procedures to bring
into focus any infringement / deviation / violation
of the environmental or forest norms / conditions?
If so, it may be detailed in the EIA report.
Section 9.5.2, 9.5.3, 9.5.4.
9.10-9.12
(c) What is the hierarchical system or
Administrative order of the company to deal with
the environmental issues and for ensuring
compliance with the EC conditions? Details of this
system may be given.
Section 9.5.2 9.10
(d) Does the company has a system of reporting of
non compliance / violations of environmental
norms to the Board of Directors of the company and
/ or shareholders or stakeholders at large? This
reporting mechanism should be detailed in the EIA
report.
Yes, the company has a system of reporting
of non compliance / violations of
environmental norms to the Board of
Directors of the company
48.
Expansion/modernization proposals:
1. Copy of all the Environmental Clearance(s)
including Amendments thereto obtained for the
project from MOEF/SEIAA shall be attached as an
Annexure. A certified copy of the latest
Monitoring Report of the Regional Office of the
Ministry of Environment and Forests as per
circular dated 30th May, 2012 on the status of
compliance of conditions stipulated in all the
existing environmental clearances including
Amendments should be provided. In addition,
status of compliance of Consent to Operate for
the ongoing Iexisting operation of the project
from SPCB shall be attached with the EIA-EMP
report.
This project is New project so these
conditions are not applicable.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates L
2. In case the existing project has not obtained
environmental clearance, reasons for not taking
EC under the provisions of the EIA Notification
1994 and/or EIA Notification 2006 shall be
provided. Copies of Consent to Establish/No
Objection Certificate and Consent to Operate (in
case of units operating prior to EIA Notification
2006, CTE and CTO of FY 2005-2006) obtained
from the SPCB shall be submitted. Further,
compliance report to the conditions of consents
from the SPCB shall be submitted.
49.
Any litigation pending against the project and/or
any direction/order passed by any Court of Law
against the project, if so, details thereof.
Not applicable
50.
Public hearing to be conducted and issues raised
and commitments made by the project proponent
on the same should be included in EIA/EMP Report
in the form of tabular chart with financial budget for
complying with the commitments made.
Public hearing minutes is shown in
Annexure – D (Page no. 88-111)
51. A tabular chart with index for point wise
compliance of above TORs. As shown in pages F-L
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates N
INDEX
EIA REPORT
1.0 Introduction 1.1 -1.16 1.1 Identification of Project 1.1 1.2 Purpose of Project 1.1 1.3 Need of the project and its importance in the country 1.2 1.4 Promoters and their back ground 1.5 1.5 Project Location 1.5 1.6 Siting Criteria 1.7 1.7 Scope of the Work 1.11 1.8 Impact Assessment Methodologies 1.13 1.9 Environment Management Plan 1.13 1.10 Disaster Management Plan and Occupational Safety 1.14 1.11 Post Study Monitoring Plan 1.14 1.12 Regulatory Frame Work 1.15 1.13 Site Visit Photos 1.16 2.0 TECHNICAL DESCRIPTION OF THE PROJECT 2.1-2.28 2.1 Type and Importance of the project 2.1 2.2 Location 2.1 2.3 Proposed Product Details 2.2 2.4 Products and Manufacturing Process 2.3 2.4.1 Formaldehyde (37%) 2.3 2.4.2 Urea Formaldehyde Resin (U.F. Resin) 2.6 2.4.3 Melamine Formaldehyde Resin 2.8 2.4.4 Hexamine 2.10 2.4.5 U.F. Moulding Powder 2.12 2.5 List of raw materials 2.14 2.5.1 Requirement and storage of raw material 2.14 2.5.2 Storage 2.16 2.5.3 Handling 2.16 2.5.4 Transportation 2.16 2.5.5 Infrastructural Facilities 2.17 2.6 The detailed Area break up for proposed unit 2.17 2.7 Details of Plant and Machineries 2.19 2.8 Requirement of Resources 2.20 2.8.1 Fuel Requirement 2.20 2.8.2 Energy Requirement 2.20 2.9 Environmental Pollution and Control Measures 2.20 2.9.1 Water Pollution 2.20 2.10 Air Pollution 2.24 2.10.1 Flue Gas Emission 2.24 2.10.2 Process Gas Emission 2.24 2.10.3 Fugitive Emission 2.26 2.11 Hazardous / Solid Waste Generation 2.27 2.12 Noise Pollution 2.27
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates O
2.13 Cleaner Production 2.28 3.0 DESCRIPTION OF ENVIRONMENT 3.1.1-3.5.18 3.1 AIR ENVIRONMENT 3.1.1 Micrometeorological Data 3.1.2 3.1.1.1 Meteorological Data From IMD (Secondary Data) 3.1.2 3.1.1.2 Meteorology –Data Generated at the plant site(Primary Data) 3.1.4 3.1.2 selection of AAQ stations 3.1.6 3.1.3 Existing AAQ(Pre-project) status 3.1.7 3.1.4 Results and Discussion 3.1.12 3.2 NOISE ENVIRONMENT 3.2.1 Impact Assessment of Noise Environment 3.2.2 3.2.2 Existing Noise Levels 3.2.2 3.2.3 Methodology of Noise measurement 3.2.4 3.2.4 Data Analysis 3.2.5 3.3 WATER ENVIRONMENT 3.3.1 Water Quality 3.3.1 3.3.1.1 Sample collection and analysis 3.3.1 3.3.1.2 Method of Water Sampling 3.3.3 3.3.1.3 Data Analysis 3.3.4 3.3.1.4 Impacts 3.3.4 3.3.2 Conclusions 3.3.4 3.4 LAND ENVIRONMENT 3.4.1 Methodology of sample collection and analysis 3.4.1 3.4.2 Soil Data analysis 3.4.4 3.4.3 Geo-Hydrological Features 3.4.5 3.4.3.1 Introduction 3.4.5 3.4.3.2 Geology 3.4.5 3.4.3.3 Land Characteristics 3.4.6 3.4.3.4 Rain fall 3.4.6 3.4.3.5 District wise status of ground water Development in Gujarat 3.4.7 3.4.3.6 General Information of Taluka 3.4.8 3.4.3.7 Climate 3.4.8 3.4.3.8 Geohydrology 3.4.8 3.4.3.9 Ground water condition 3.4.8 3.4.3.10 Depth of Ground Water Table 3.4.9 3.4.3.11 Feasibility of Source at and around Dada Nagar Village &
Project area 3.4.9
3.4.4 Land Use Status 3.4.10 3.4.5 Land use & land cover classification results 3.4.10 3.4.5.1Data Used 3.4.11 3.4.5.2 Methodology 3.4.12 3.4.5.3 Interpretation Of Remote Sensing Data 3.4.12 3.4.6 Topography of the study area 3.4.19 3.4.7 Ecology and Bio diversity 3.4.20
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates P
3.4.7.1 Data Collection And Field Visit 3.4.20 3.4.7.2 Detail Methodology 3.4.21 3.4.7.3 Intensive survey and compilation of primary field data 3.4.23 3.4.7.4 Biodiversity Status 3.4.24 3.4.7.4.1 Floral Status 3.4.25 3.4.7.4.2 Faunal Status 3.4.29 3.4.7.4.3 Threatened Plants And Animals And Conclusion Note 3.4.35 3.5 SOCIO ECONOMIC ENVIRONMENT 3.5.1 Introduction 3.5.1 3.5.2 Socioeconomics 3.5.1 3.5.3 Amenities 3.5.9 3.5.4 Site Specific Studies 3.5.15 3.5.5 List of industries 3.5.15 3.5.6 Culture 3.5.17 3.5.7 Organization & Manpower 3.5.17 3.5.8 Impacts of the proposed Project 3.5.17 4.0 ANTICIPATED IMPACTS AND MITIGATION MEASURES 4.1-4.54 4.1 Introduction 4.1 4.2 Impacts on environment during Construction Phase 4.3 4.2.1 Impact on Land use 4.3 4.2.2 Impact on Soil Environment 4.3 4.2.3 Impact on Air Quality 4.3 4.2.4 Impact on Water Quality 4.4 4.2.5 Impact on Noise Levels 4.4 4.2.6 Impact on Terrestrial Ecology 4.4 4.2.7 Impact on Aquatic Ecology 4.4 4.2.8 Impact on Demography and Socio-economics 4.4 4.2.9 Public Expectation 4.6 4.3 Identification of Potential Impacts during Operational Phase 4.6 4.3.1 Impact on Soil 4.7 4.3.2 Impact on Topography 4.7 4.3.3 Impact on Climate 4.8 4.3.4 Impact on Air Environment 4.8 4.3.5 Impact on Water Environment 4.16 4.3.6 Impact on Noise Environment 4.16 4.3.7 Impact on Ecology 4.18 4.3.8 Impact on Socio-Economics 4.18 4.4 Environment Management Plan 4.19 4.5 Environment Management Plan during Construction 4.20 4.5.1 Site Preparation 4.20 4.5.2 Air Quality 4.21 4.5.3 Water Quality 4.21 4.5.4 Noise Levels 4.21 4.5.5 Ecological Aspects 4.22 4.5.6 Storage of Hazardous Materials 4.22 4.5.7 Site Security 4.22 4.5.8 Migrant Laborers 4.23 4.6 Environmental Management Plan (EMP) during Operational Stage 4.24 4.6.1 Soil Quality 4.25
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates Q
4.6.2 Air Quality Management 4.25 4.6.3 Water Management 4.26 4.6.4 Noise Level Management 4.30 4.6.5 Solid & Hazardous Waste Management 4.30 4.7 Green Belt Development 4.32 4.8 Rain Water Harvesting 4.38 4.9 Monitoring Of Water Consumption 4.53 4.10 Other Information 4.53 4.11 Occupational Health Surveillance 4.54 5.0 ENVIRONMENTAL MONITORING ASPECTS 5.1-5.14 5.1 Implementation Schedule of Mitigation Measures 5.1 5.1.1 Introduction 5.1 5.1.2. Institutional Arrangements for Pollution Control 5.1 5.1.2.1 Organization at Site5.6.1 Organization at Site 5.1 5.2 Environmental Monitoring 5.2 5.2.1 Monitoring and Reporting Procedure 5.3 5.2.2 Methodology for Ambient Air Quality Assessment 5.4 5.2.3 Methodology for Flue Quality Assessment 5.7 5.2.3.1 Stack Gas Monitoring 5.7 5.2.4 Methodology for Water Quality Assessment 5.7 6.0 DISASTER MANAGEMENT PLAN 6.1-6.7 6.1 Introduction – Disaster 6.1 6.2 Types Of Disaster 6.1 6.3 Identification of Major Hazards 6.2 6.4 Objectives of the Plan 6.2 6.4.1 Basis of Plan 6.2 6.4.2 Post Disaster Analysis and Evaluation 6.3 6.4.3 General Recommendations 6.3 6.4.4 The availability, organization, and utilization of resources for
emergency 6.3
6.4.5 Emergency response 6.4 6.4.6 Fire Fighting Facilities 6.6 6.4.7 Other Key Personnel 6.6 7.0 RISK ASSESSMENT 7.1-7.61 7.1 INTRODUCTION OF COMPANY 7.1
7.2 OBLECTIVE, PHILOSOPHY & METHODOLOGY OF RISK ASSESSMENT 7.2 7.3 DETAILS OF RAW MATERIALS 7.3 7.4 DETAILS OF FINISHED PRODUCTS 7.3 7.5 LIST OF HAZARDOUS CHEMICALS ALONGWITH THEIR TOXICITY LEVEL
AS PER MSIHC RULES 7.4
7.6 HAZARD IDENTIFICATION AND PREVENTIVE MEASURES 7.6 7.6.1. Raw Material Storage hazards and controls 7.6 7.6.2. Process hazards and controls 7.8 7.6.3. General Hazards & controls 7.9
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates R
7.6.4 Safe Practice for Handling, Storage, Transportation and Unloading of Hazardous Chemicals:
7.11
7.6.5.: Safe Practice for Handling, Storage, Transportation and Unloading of Ammonia:
7.12
7.7 Occupational Health Surveillance Programme 7.13 7.8 Occupational Health Programme 7.14 7.9 Chemicals Which Are Exposed To Workers Directly Or Indirectly 7.15 7.10 Treatment Of Workers Affected By Acccidental Spillage Of Methanol 7.17 7.11 Do’s And Donts’ 7.19 7.12 Risk Analysis And Consequence Analysis 7.21 7.13 Risk Reduction Measurement& Recommendation In View Of Safety
Consideration 7.28
7.14 On Site Emergency Plan 7.30 7.15 Material Safety Data Sheet 7.38 8.0 COST ANALYSIS 8.1-8.2 8.1 Capital Cost 8.1 8.2 Environmental Protection Cost 8.2 9.0 ENVIRONMENTAL MANAGEMENT SYSTEM 9.1-9.12 9.1 Introduction 9.1 9.2 Formation of an Environmental Management System 9.1 9.3 Implementation of an Environmental Management System 9.2 9.4 Concept of Waste-Minimization, Recycle/Reuse/Recover Techniques,
Energy Conservation, and Natural Resource Conservation 9.8
9.5 Institutionalizing Corporate Environmental Responsibility 9.9 10.0 Executive Summary – English & Gujarati 10.1-10.23 11.0 DISCLOSURE OF CONSULTATIONS 11.1-11.10 11.1 Introduction of M/s. T.R. Associates 11.1 11.2 Copy of Stay order 11.6
ANNEXURES
A Primary Meteorological Data 1-77 B Google map showing Distance From Severely Polluted Area From Project
Site & Google Map Showing Surface Water Bodies And Reserve Forest From Project Site.
78-80
C Land Documents 81-87 D Public Hearing Minutes (Dt: 11-2-2015) 88-111
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates S
LIST OF TABLES
No. List of Tables Page No.
1.0 Siting Criteria 1.7 1.1 Salient Features with in 10 km radius surroundings. 1.10 1.2 Scope of work 1.12
2.1 List of Proposed Product 2.2 2.2 Raw materials Consumption in MT/Month 2.14
2.3 Packing, storage & transportation details of Raw Material and Product 2.16
2.4 Area Break up for proposed unit 2.17
2.5 Equipments required for resin plant, Hexamine & Formaldehyde Plant 2.19
2.6 Employment Detail 2.20 2.7 Water consumption and Waste water Generation details 2.21 2.8 Capacity of ETP units 2.24 2.9 Flue Gas stacks details 2.25
2.10 Technical Details of MDC- Multi Cyclone Dust Collector 2.26 2.11 Solid Waste/Hazardous Waste details 2.27
3.1.1 Monthly Mean values of Metrological Data for 3 Months 3.1.3
3.1.2 Monthly Mean values of Meteorological Data for 3 Month (Primary Data) 3.1.5
3.1.3 Air Parameters analyzed and sampling duration 3.1.7 3.1.4 Ambient Air Quality - Methodology 3.1.8 3.1.4 (a)
Ambient Air Quality sampling site 3.1.10
3.1.5 Ambient Air Quality Monitoring Results Name of the pollutant: Particulate Matter (PM10) 3.1.10
3.1.6 Ambient Air Quality Monitoring Results Name of the pollutant: Particulate Matter (PM2.5) 3.1.10
3.1.7 Ambient Air Quality Monitoring Results Name of the pollutant: SO2 3.1.11
3.1.8 Ambient Air Quality Monitoring Results Name of the pollutant: Nitrous Oxides (NOx) 3.1.12
3.2.1 Hourly Noise data (Day and Night timings in Leq dB (A)) 3.2.6 3.3.1 Water Quality - Physico-chemical Analysis of Ground Water 3.3.5 3.3.2 Water Quality - Physico-chemical Analysis of Surface Water 3.3.6 3.4.1 Physicochemical Parameters of the soil 3.4.4 3.4.2 Land use Details 3.4.14 3.4.3 Field Survey 3.4.21 3.4.4 Taxonomic Status of plant species: M/s. Pawan Formalin Pvt. Ltd. 3.4.25 3.4.5 Life form Status of plant species: M/s. Pawan Formalin Pvt. Ltd. 3.4.25 3.4.6 Common Tree species: M/s. Pawan Formalin Pvt. Ltd. 3.4.26 3.4.7 Wild/Forest Tree species: M/s. Pawan Formalin Pvt. Ltd. 3.4.27
3.4.8 Status of Agriculture and Other Crop Species Recorded: M/s. M/s. Pawan Formalin Pvt. Ltd. 3.4.28
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates T
3.4.9 Taxonomical Status of Herpetofauna: M/s. Pawan Formalin Pvt. Ltd. 3.4.29
3.4.10 Overall Status of Terrestrial and Aquatic Birds: M/s. Pawan Formalin Pvt. Ltd. 3.4.30
3.4.11 Overall Status of Mammals: M/s. Pawan Formalin Pvt. Ltd. 3.4.34
3.4.12 Habitat-wise checklist of Plant Species recorded in and around the M/s. Pawan Formalin Pvt. Ltd. 3.4.37
3.5.1 Population Composition 3.5.2 3.5.2 Occupational Structure 3.5.6 3.5.3 Literacy Status 3.5.8 3.5.4 Amenities (Educational Facilities) 3.5.10
4.1 Flue Gas Stack Details 4.9 4.2 Predicted 24 Hourly Short term incremental concentration of SPM 4.15 4.3 Predicted 24 Hourly Short term incremental concentration of SO2 4.15 4.4 Predicted 24 hourly short term incremental Concentrations of NOx 4.16 4.5 Permissible Noise Exposures for Industrial Workers 4.17 4.6 Negative Impacts and Mitigations during Construction Phase 4.23 4.7 Water consumption and Waste Water Generation details 4.27 4.8 Capacity of ETP units 4.30 4.9 Hazardous waste generation and their disposal 4.31
4.10 Categorization of the area for project and greenbelt 4.32 4.11 Recommended Plant Species for Green Belt Development 4.35 4.12 Negative Impacts and Mitigations during Operational Phase 4.51
5.1 Implementation of Schedule 5.1 5.2 Monitoring Schedule for Environmental Parameters 5.3 5.3 Methodology for ambient air quality assessment 5.5 5.4 National ambient quality standards 5.6 5.5 Tolerance limit for drinking water as per IS-10500 1991 5.9
5.6 Primary water quality criteria for various uses of fresh water as per CPCB for prevention and control of water pollution (1979) 5.11
5.7 General standards for discharge of effluents 5.12
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates U
LIST OF FIGURES
No. List of Figures Page No.
1.0 Index Map 1.6
1.1 Topo map showing 10 km radius around the plant site 1.9
1.2 Google map showing plant site 1.10
2.0 Process Flow Diagram of Formaldehyde 2.4
2.1 Process Flow Diagram of Urea Formaldehyde Resin 2.7
2.2 Process Flow Diagram of Melamine formaldehyde resin 2.9
2.3 Process Flow Diagram of Hexamine 2.11
2.4 Process Flow Diagram of U.F. Moulding Powder 2.13
2.5 Plant Lay-Out 2.18
2.6 Water Balance Diagram 2.22
2.7 Flow Diagram of ETP 2.23
3.1.1 Meteorological Wind Rose Diagram for November-2012 to January 2013 (Secondary data) 3.1.4
3.1.2 Meteorological Wind Rose Diagram for October-2013 to December 2013 (Primary Data) 3.1.6
3.1.3 Map Showing Ambient Air Quality Locations 3.1.9
3.2.1 Topo Map Showing Noise Sampling Locations 3.2.3
3.3.1 Topo Map showing Water Quality Locations 3.3.2
3.4.1 Map showing Soil Sampling Locations 3.4.3
3.4.2 Land use Map 3.4.15
3.4.3 High Resolution Satellite Image showing 10 km radius around the plant site 3.4.16
3.4.4 Topographical Map 3.4.17 3.4.5 Infrastructure facilities 3.4.18 3.4.6 Google image showing in and around the Project Location. 3.4.22
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates V
3.5.1 Percentage of Population distribution 3.5.4 3.5.2 Distribution of workers 3.5.7 3.5.3 Literacy levels 3.5.9
4.1 Ground Level Concentration of SPM 4.12
4.2 Ground Level Concentration of SO2 4.13
4.3 Ground Level Concentration of NOx 4.14
4.4 Water Balance Diagram 4.28
6.1 On Site Disaster Management Plan 6.4
9.1 Model structure showing information flow 9.10
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.1
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.2
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.3
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.4
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.5
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.6
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.7
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.8
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.9
Proposed Project
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.10
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.11
Nazarbaug railway station(10.1 km)
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.12
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.13
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.14
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.15
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 1.16
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2.0 TECHNICAL DESCRIPTION OF THE PROCESS
2.1 Type and Importance of the project
The proposed products like Resins (Melamine Formaldehyde Resin, and Urea Formaldehyde
Resin), Hexamine, U.F. Moulding Powder & Formaldehyde are very useful Chemical
compounds. It has many important applications in many areas or fields. They have got several
advantages as listed below in our daily life.
These Resins are used to manufacture Laminated Sheets, and these laminated sheets are very
useful for furniture and other similar application in making magnetic slots and other
electrical appliances.
The main use of Hexamineis in the production of powdery or liquid preparations of phenolic
(phenol formaldehyde) resins and phenolic resin molding compound, where it is added as a
hardening component.
Medical professionals usehexamineas an antibiotic to treat urinary tract infections. The
specific medication used is called methenamine hippurate, which is formed by the
combination of hexamineand hippuric acid.
Hexaminetablets are used by fire-protection laboratories as a clean and reproducible fire
source to test the flammability of carpets and rugs.
Hexamineis also used in rubber and textile adhesives, in paints and lacquers, in the
photographic industry, in the production of deodorants and hair fixers.
2.2 Location
The proposed plant is located at Survey No.: 24/P, Village: Jambudiya, Taluka: Morbi, District:
Morbi-Rajkot – 363642 and Gujarat State. The base map and topo map showing features around
10 km radius from plant site are showing Fig. 1.1.
The total land area is 10060 Sq. Mt. of which 3096 Sq. Mt. is for greenbelt area development.
M/s. T. R. Associates 2.1
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2.3 Proposed Product Details
The details of proposed final product and intermediate products are shown in Table 2.1.
Table 2.1 Details of Proposed Final Product
No. ProductTotal Quantity
( MT/Month)
Total Quantity
( MT/Day)
1. Formaldehyde (37%) 1800 60
2. Urea Formaldehyde Resin 250 8.3
3. Melamine Formaldehyde Resin 250 8.3
4. U.F. Moulding Powder 250 8.3
5. Hexamine 90 3
M/s. T. R. Associates 2.2
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Products and Manufacturing Process
2.4.1 Formaldehyde (37%)
Manufacturing Process:
1. Feed Methanol, air, water vapour
Catalyst: Silver
The methanol in the measuring storage tank is pumped up to an elevated tank by a
methanol pump. After being controlled by measuring, the methanol coming out from the
elevated tank flows into an evaporator for vaporization of which the temperature is
controlled within 440C ~ 470C and the liquid level is controlled as 50%, then the
vaporized methanol gets into a super heater. The heat for the vaporization of methanol is
provided by the 700C circulating fluid in the 1st formaldehyde absorber.
3. The air is filtered by a filter before being delivered to the evaporator by a blower. It
mixes with the methanol in the evaporator and enters into then super heater together. The
air flow is regulated by the blower through frequency conversion to control the flow ratio
of air to methanol (A/M=1.8 ~1.95).
When the pressure gets stable, the vapour (0.3 MPa) gets into a mist eliminator for
dehumidification through the pipeline before entering into the superheat. The flow ratio
of air to methanol shall be controlled at desired level. In the formaldehyde production
technique using silver as catalysis, the water vapour is an inert gas which does not
participate in chemical reactions. The added water vapour changes the explosive range of
the methanol and air, the production of formaldehyde thereby becomes far from the
explosive area and stays safe and reliable.
After the flow rates are regulated and proportioned, the methanol, air and water vapour
enter into the super heater and the superheating temperature shall be controlled at 2000C.
Then, these materials enter into a reactor.
In the reactor, under the catalysis of silver at 6500C, the methanol is dehydrated and
oxidised, generating Formaldehyde. Dehydration reaction is an endothermic reaction and
oxidation reaction is an exothermic reaction, but the heat release is more than that can
adsorbed, therefore the reaction system is a state of heat energy surplus. The water
M/s. T. R. Associates 2.3
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
vapour is not involved in reactions but it can absorb a lot of heat of reaction, maintaining
the temperature at 6500C.
Chemical Reaction:
CH3OH CH2O + H2 - 20Kcal ------1
CH3OH + ½ O2 CH2O + H2O + 38 Kcal ------2
1-2=18Kcal
The 6500C reaction gas leaves the reaction and gets into heat exchanger. For the heat exchanger,
the medium is water. The outlet temperature of heat exchanger is 1600C. The water absorbs heat,
forming the water vapour of 0.35 MPa which will be used to arranging the raw materials for
production in the super heater after its pressure stabilized.
The generated gases of about 160° C enter into 1st and 2nd formaldehyde absorber in proper order
and get absorbed by the cooled circulating fluid through spraying. The temperature of the
circulating fluid at the bottom of 1st absorber shall be control at 70° C and fluid is pumped to the
evaporator by circulating pump to supply the heat for the evaporation of methanol. In the 1st
absorber, the concentration shall be controlled as 37%, and temperature of the top shall be
controlled at 45° to 50° C. The circulating fluid is also a composition of the Formaldehyde
product by this technique. The temperature of the top of 2nd absorber shall be controlled at 30° to
35° C and keep adding water from top to control the release of formaldehyde.
M/s. T. R. Associates 2.4
EIA
Prep
arat
ion
for t
he P
ropo
sed
Plan
t for
For
mal
dehy
de, H
exam
ine
& Re
sin
Man
ufac
turin
g of
M/s
Paw
an F
orm
alin
Pvt
. Ltd
Fig
2.0
: Pro
cess
Flo
w o
f Fo
rmal
dehy
de (3
7 %
):
M/s
. T
. R. A
ssoc
iate
s
2
.5
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2.4.2 Urea Formaldehyde Resin (U.F. Resin)
Manufacturing Process:
1. Formaldehyde is taken in a jacketed reaction vessel to which urea powder is added slowly
and the mixture is then stirred well.
2. After about 15 minutes a solution of caustic soda (NaOH) is added to the mixture to make
it alkaline.
The mixture is then heated by hot Thermic fluid to raise its temperature gradually up to
85° C.
4. The process is continued till the solution becomes clear.
It is there after cooled gradually to a temperature of 10° to 15° C higher than room
temperature and the methanol solvent is added to reduce viscosity.
6. After reducing the Viscosity, The solution is then stored in a storage tank.
Chemical Reaction:
M/s. T. R. Associates 2.6
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Mass Balance:
UF Resin
Reaction Vessel
Cooling
Dilution
Stirring & heating
Fig. 2.1 Process Flow Diagram of Urea formaldehyde resin
M/s. T. R. Associates 2.7
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2.4.3 Melamine Formaldehyde Resin
Manufacturing Process:
1. Formaldehyde is taken in a jacketed reaction vessel to which melamine powder is
added slowly and the mixture is then stirred well.
2. After about 15 minutes a solution of caustic soda (NaOH) is added to the mixture
to make it alkaline.
3. The mixture is then heated by hot Thermic fluid/Steam to raise its temperature
gradually up to 85° C.
4. The process is continued till the solution becomes clear.
5. It is there after cooled gradually to a temperature of 10° to 15° C higher than room
temperature and the methanol solvent is added to reduce viscosity.
6. After reducing the Viscosity, The solution is then stored in a storage tank.
Reaction Chemistry:
M/s. T. R. Associates 2.8
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Mass Balance
MF Resin
Reaction Vessel
Cooling
Dilution
Stirring & heating
Fig. 2.2 Process Flow Diagram of Melamine formaldehyde resin
M/s. T. R. Associates 2.9
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2.4.4 Hexamine:
Hexamine is being produced by reaction of formaldehyde with ammonia. The Formaldehyde is
taken in the form of formaldehyde gas and is introduced in the reactor containing saturated
solution of Hexamine. Ammonia from the Ammonia storage tank is evaporated and purged in the
reactor where it reacts with the Formaldehyde to produce Hexamine as per following reaction.
Chemical Reaction:
6HCHO + 4 NH3 (CH2)6 N4 + 6H20
Formaldehyde Ammonia Hexamine Water
The Reaction between Formaldehyde and Ammonia is exothermic in nature. The heat of reaction
is utilized in evaporating the water, which is formed during reaction. As the reactions proceed
and the upper saturation limit exceeds, the hexamine start crystallizing in the mother Liquor. The
mother liquor containing hexamine crystal is withdrawn though slurry pumps and pumped to
centrifuge where the crystals are separated out. These crystals are dried in rotary drum dried and
packed in jute bags for dispatch.
The mother liquor from centrifuge is re-circulated back to the reactor.
This is a highly energy efficient process where in the heat of gaseous formaldehyde and heat of
reaction are utilized to evaporate the water formed during the reaction. No extra steam is
required in reactor and only a small quantity of steam is required for drying of crystallized
hexamine.
M/s. T. R. Associates 2.10
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Process Flow Diagram:
M/s. T. R. Associates 2.11
1550 to 1575 kg of Methanol
510 to 515 kg
950 kg99 Water and traces of
Ammonia
1000 kg
140 kg output recycled intoprocess
Input 2090 KG Output 2090 KG
Formaldehyde
Ammonia
Reactor
Centrifuge
Vacuum
HEXAMINE
Spent MotherLiquor
Exhaust
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Fig. 2.3 Process Flow Diagram of Hexamine
2.4.5 U.F. Moulding Powder:
Manufacturing processSame as urea Formaldehyde resin up to liquid Resin After formation of UreaFormaldehyde resin Wood pulp Hexamine and Zinc Stearate MagnesiumStearate Zinc Sulphate etc added as blending material up to solidify thematerial and finally it will be grinded to convert into powder form
M/s. T. R. Associates 2.12
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Mass balance:
UF Modling Powder
Reaction Vessel
Cooling
Blender
Stirring & heating
Grinding
drying
Fig. 2.4 Process Flow Diagram of UF Moulding Powder
M/s. T. R. Associates 2.13
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
List of raw materials :
List of raw materials are given in the Table 2.2.
Table 2.2 Raw materials Consumption in MT/Month
Sr. No. Name of raw materialsConsumption
Mt/MonthFormaldehyde- 1800 MT/Month
1 Methanol 810Urea Formaldehyde Resin-250 MT/Month
1 Formaldehyde 1252 Urea 843 Caustic (NaOH) 0.0834 Methanol 42
Melamine Formaldehyde Resins-250 MT/Month1 Formaldehyde 1252 Melamine 843 Caustic (NaOH) 0.0834 Methanol 42
Hexamine-90 MT/Month1 Ammonia 46.352 Methanol 141.75
UF Molding powder-250 MT/Month1 Formaldehyde 1672 Urea 303 Caustic (NaOH) 0.54 Wood Pulp 505 Metallic Stearate 9.56 Zinc Sulphite 57 Barium Powder 83.758 Hexamine 8.75
M/s. T. R. Associates 2.14
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2.5.1 Requirement and storage of raw material
For the manufacturing of proposed products various raw materials will be requiredIndustry will provide adequate and proper storage facilities for all the raw materialsand the finished product The quantity of raw material consumption for proposedmanufacturing is shown in the Table 2 2 A detail of regarding product and rawmaterial storage packing transportation is shown in Table 2 3
Table 2.3 Packing, storage & transportation details of Raw Material and Product
No. DescriptionPhysical
Form
Type of Packing /
Storage/ Mode of
storage
Transportation
Capacity
of
storage
Raw Materials
1 Methanol Liquid M.S.(U/G Tank) Road/Railway 25 KL
2 Urea Solid Industrial Plastic Bag Road/Railway 100 MT
3 Caustic (NaOH) Solid Woven sack Bag Road/Railway 5 MT
4 Melamine Solid Industrial Plastic Bag Road/ Railway 100 MT
5 Ammonia Gas Cylinder Road/ Railway 25 MT
6 Wood Pulp Solid Industrial Plastic Bag Road/Railway 14 MT
7 Metallic Stearate Solid Industrial Plastic Bag Road/Railway 3 MT
8 Zinc Sulphite Solid Industrial Plastic Bag Road/ Railway 2 MT
9 Barium Powder Solid Industrial Plastic Bag Road/ Railway 2.5 MT
M/s. T. R. Associates 2.15
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Products
1Formaldehyde
(37%)Liquid
Industrial Plastic grade
Tank
Captive consumption &
rest will be transported
by road, rail & ship
100KL x
4
2
Urea
Formaldehyde
Moulding
Powder
Semi solid Stored in Plastic Bags
It will be transported by
road, rail & ship60 MT
3
Melamine
Formaldehyde
Resin
Semi solid Stored in S.S. Tank
It will be transported by
road, rail & ship 50MT
4
Urea
Formaldehyde
Resin
Semi solidStored in Storage tank
of MS lined with FRP
It will be transported by
road, rail & ship 50MT
5 Hexamine Solid Plastic BagsIt will be transported by
road, rail & ship35 MT
M/s. T. R. Associates 2.16
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2.5.2 Storage
Industry will provide adequate and proper storage facilities for all the raw materials and finished
products. Corrosive substances will be stored away from the moisture. Solid raw material
will be stored in covered area and liquid raw material will be stored in closed horizontal
tank. Hazardous chemicals and solid wastes will be stored away from other plant activities.
The storage yard of chemicals will be isolated and it will be equipped with all necessary
safety measures. In cover-shed area provide natural ventilation system, which consider as 15
% open area of all covered area.
2.5.3 Handling
All the raw materials and finished products will be handled as per the standard practice. For
proper handling, company will adapt good housekeeping technology to entire shed. To avoid
any leakage or spillage of chemicals from all storage tanks, third party will inspects transfer
lines, valves, fittings and every joint periodically.
2.5.4 Transportation
All the necessary precautions will be taken while carrying out transport of the above materials as
per the Hazardous Rules of transportation. The vehicles for transportation of raw materials and
products will be parked at specified loading facilities where there will be a provision of fire
extinguishers. The finished product will be transported by road, rail and ship route.
2.5.5 Infrastructural Facilities
The total available area for proposed project is 10060 m2 and unit proposes to develop Green
Belt area 3096 m2 of total area of plot.
Power requirement for the proposed project will be taken from Paschim Gujarat Vij Corporation
Ltd. (PGVCL) in tune of 300 HP.
Industry is nearer National Highway – 8A (0.1 Km)
M/s. T. R. Associates 2.17
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2.6 The detailed Area break up for proposed unit
The detailed Area break up for proposed unit is shown in Table 2.4
Table 2.4 Area Break up for proposed unit
Sr.
No.Details Area, m2 %
1 Built – Up Area 4216 41.902 Green Belt 3096 30.773 Open/ Road Area 2748 27.33
Total Plot Area 10060 100
M/s. T. R. Associates 2.18
EIA
Prep
arat
ion
for t
he P
ropo
sed
Plan
t for
For
mal
dehy
de, H
exam
ine
& Re
sin
Man
ufac
turin
g of
M/s
Paw
an F
orm
alin
Pvt
. Ltd
Fig
. 2.5
Pla
nt L
ay-O
ut
M/s
. T
. R. A
ssoc
iate
s
2
.19
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2.7 DETAILS of Plant and Machineries
For the production of various products various plants and machineries will berequired The details of equipments are as mentioned in table 2 5
Table 2.5 Equipments required for Resin, Hexamine & Formaldehyde plant
SN Name of Machinery Capacity No. of Units
1 Small Industrial Boiler 1 MT hr 1
2 D G Set 300 KVA 1
3 M F Reaction Vessel 6 KL 2
4 U F Reaction Vessel 15 KL 1
5 Dryer 1 5 MT 2
6 Hexamine Reactor Crystallizer 15 KL 1
7 Formaldehyde Reactor Shell tube 2 5 MT hr 1
8 Cooling tower 250 TR 1
9 Chilling Plant 15 TR 1
Note: The project would draw electricity from Paschim Gujarat Vij Corporation Ltd. to
the tune of 300 HP.
M/s. T. R. Associates 2.20
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2.8 Requirement of Resources
2.8.1 Fuel Requirement
The unit proposes to use Coal / White Coal as fuel for Boiler. The requirement will be 2.314
MT/Day.
2.8.2 Energy Requirement
Total Energy requirement for the proposed project will be estimated as 300 HP, which will be
fulfilled from the Paschim Gujarat Vij Corporation Ltd.
Table 2 6 Employment Detail
PParticular No of personsResidential employees 20
Non Residential employees 10Total 30
2.9 Environmental Pollution and Control Measures
2.9.1 Water Pollution
Water Consumption
The water requirement of the unit will be satisfied through Bore well. The Industrial water
consumption for proposed plant will be 64 KL/Day (Fresh water: 57.3 KL/D, Reuse water: 6.7
KL/D), which will be used for various industrial purpose. In it, Domestic water consumption for
proposed unit will be 2.35 KL/Day. The unit will develop Green Belt Area within the industrial
premises hence the water requirement for gardening purpose will be 8 KL/day. So therefore, the
total water requirement will be 65.45 KL/ Day.
Waste Water Generation
The total Waste water Generation will be 6.65 KL/ Day. In this the domestic waste water will be
2.2 KL/Day and it will go to soak pit through septic tank. Waste Water will be generated from
Cooling reject, Boiler blowdown and R.O Reject will be about 6.65 KL/day from manufacturing
M/s. T. R. Associates 2.21
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
process. This will be treated in the Multi Effect Evaporator. Treated water will be reused in
process. Thus industry will maintain ZERO DISCHARGE.
The Category wise details of water consumption and wastewater generation are shown in Table
2.7 and in Fig. 2.6.
Table 2 7 Water consumption and Waste water Generation details
No SourceWater
ConsumptionKL Day
Waste WaterGeneration
KL Day1 Domestic 2 35 2 2
2 Gardening8
Fresh 5 8 Re use2 2
Nil
3 Industriala R O 49 5
b Cooling 14 1 4c Steam Boiler 1 0 25
Industrial Water ConsumptionWaste Water Generation
64Fresh 57 3Reuse 6 7
6 65
Total Water Consumption WasteWater Generation
65 45 8 85
M/s. T. R. Associates 2.22
EIA
Prep
arat
ion
for t
he P
ropo
sed
Plan
t for
For
mal
dehy
de, H
exam
ine
& Re
sin
Man
ufac
turin
g of
M/s
Paw
an F
orm
alin
Pvt
. Ltd
Fig
26
Wat
erBa
lanc
eDi
agra
m
M/s
. T
. R. A
ssoc
iate
s
2
.23
Sour
ceof
Wat
erSu
pply
Bore
well
Tota
l65
45KL
Day
Dom
estic
Use
235
KLda
y
Cool
ing
14KL
day
Indu
stria
lUse
64KL
D
22
KLda
ygo
esto
soak
pit
thro
ugh
sept
icta
nk
ETP
MEE
665
KLda
y
Drin
king
use
015
KLDa
y
14
KLD
Gar
deni
ng8
KLD
Fres
hwa
ter
573
KLD
Recy
cle
wat
er6
7KL
D
6KL
D
07
KLD
Boile
r1
KLD
Boile
rBl
owdo
wn0
25KL
DCo
nden
sat
e0
7KL
D
Two
Phas
eR
OPr
oces
s49
KLD
Reje
ct5
KLD
Man
ufac
turi
ngPr
oces
s44
KLD
22
KLD
58
KLD
Sewa
geTr
eatm
ent
Plan
t2
2KL
Day
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Waste Water Management System Proposed Effluent Treatment PlantEffluent Treatment Plant
Process:
• Industrial wastewater generated due to Reverse manufacturing process, cooling andboiler blowdown will be collected in Primary Collection tank and equalized the effluentto make homogeneous mixture.
Then this effluent will be sent to Multi Effect Evaporator.
The condensed water will be reused in the process.
Fig. 2.7 Flow Diagram of ETP
M/s. T. R. Associates 2.24
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Table 2.8 Capacity of ETP units
Sr. No. Name of the units Volume Lit. No. of Unit
1 Collection Tank 10000 2
2 Multi Effect Evaporator 600 L/Hr 1
2 10 Air Pollution
The main source of gaseous emission is flue gas emission from stack attached toBoiler and D G Set There will be negligible chance of fugitive emission due tohandling and storage of raw material
2 10 1 Flue Gas Emission
The stack attached to Boiler and D G Set will be the main source of flue gasemission The details of the same are given here in Table 2 9
M/s. T. R. Associates 2.25
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Table 2 9 Flue Gas stacks details
NoStackattached
toFuel used
StackHeig
ht
Expected
pollutan
t
Qualityof
pollutant
APCSyste
m
1 Boiler1 MT Hour
Coal WhiteCoal2 314
MT Day
30 MeterSPMSO2
NOX As perGPCBNorms
Multicyclone DustCollect
or
2 D G Set300 KVA
HSD 35 LiterHour 6 0 Meter HC
CO
Note D G Set will be only used when power failure
Stack height will be provided as per GPCB guidelines for the proper dispersion ofpollutants into the atmosphere The unit will provide Multi Clone Dust Collectorwith Boiler as an air pollution control measures to control the emission ofparticulate matter the flue gas emission will remain well within gaseousemission norms prescribed by the GPCB CPCB The technical specifications ofproposed Multi cyclone Dust Collector are given in Table 2 10
M/s. T. R. Associates 2.26
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
Table 2 10 Technical Details of MDC Multi Cyclone Dust Collector
Type of Source Steam Boiler package wet backHeating Capacity 1 MT Hr
Fuel used in steam boiler Bio Coal CoalTemperature at Inlet 235 oC
Specific Gravity of Dust 1 29Input Dust Load 8 kg 24 hr
Efficiency 78Pressure Drop 106 mm WC
No Size of Cylinder 5 nosNo of Ash Discharge Cone 1 no
Ash Discharge Air Lock Rotary Valve
2 10 3 Fugitive Emission
The chance of fugitive emission within premises is mainly due to storage, handling and
loading, unloading of raw materials.
Other sources of fugitive emission are as follows:
Leaks from pressurized process equipment generally occur through valves, pipe
connection, mechanical seals or related equipment.
Proposed measures to control fugitive emission:
To minimize & control leaks at process facilities operators carry out regular leak detection
test and repair activities. Routine inspections of process equipment with gas detectors can
be used to identify leaks & estimate the leak rate in order to decide an appropriate
corrective action. Proper routine maintenance of equipment reduces the likelihood of leaks.
Formaldehyde will be transferred through the closed vessel system. Only caustic will be
transferred manually. But it is in very less quantity. In that case the industry will provide
mask and safety material for that.
As per GFR, industry will carry out monitoring the ambient air quality twice in a year.
M/s. T. R. Associates 2.27
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2 11 Hazardous solid waste Generation
The Solid waste Hazardous waste will be discarded containers and ETP sludgeThe details of hazardous waste generation and handling Management aregiven in Table 2 11
Table 2 11 Solid Waste Hazardous Wastedetails
No Description Category Quantity Mode of Disposal
1 Used Oil 5 125 Litre
Month
Collection storage and used withinpremises as a lubricant sold to
registered recycler
2Discarded
Plastic bags33 3
6940Nos Month
Collection storage sell to authorizedvendor
3 ETP Sludge 34 316 25
MT MonthCollection storage disposed at
TSDF site
2 12 Noise Pollution
One of the potential pollutants Noise is an unwanted and excessive sound whichis harmful to health and diminishes the quality of life
The major source of noise pollution will be DG Set and the ancillary sources willbe manufacturing process within premises and transportation within and outsidethe premises
M/s. T. R. Associates 2.28
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
2 13 Cleaner Production
M/s. T. R. Associates 2.29
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.1
3.0 DESCRIPTION OF ENVIRONMENT
3.1 AIR ENVIRONMENT
Clean air is essential to our health and to the environment. But since the industrial
revolution, the quality of the air we breathe has deteriorated considerably - mainly as a
result of human activities. Rising industrial and energy production, the burning of fossil
fuels and the dramatic rise in traffic on our roads all contribute to air pollution in our
towns and cities which, in turn, can lead to serious problems for both health and the
environment.
An air quality assessment is a required component of the Application for an Environmental
Assessment Certificate (Application) for submission to the Ministry of Environment and
Forest (MoEF), with the objective to develop the Expansion of Chlorinated Paraffin Project.
A thorough understanding of baseline air quality is a prerequisite to the air quality
environmental assessment (EA).
The baseline refers to the collective level of air contaminants contained in the larger air
shed, rather than local measurements. These contaminants may arise from natural or
anthropogenic (manufactured) sources. Understanding the appropriate background
concentration of air pollutants is critical in assessing overall (cumulative) air quality, which
incorporates background values and adds the predicted incremental increase from the
Project emission sources.
Availability of reliable, public domain air quality data covering remote areas of central and
surroundings allow the determination of the most likely baseline concentrations of
relevant air contaminants near the Project. Several databases were identified and analyzed
by T.R. Associates using such references as the number of monitored criteria of CPCB,
instrumentation, location, the monitoring period, and the relevance to the Project with
respect to level of development. The final selection was narrowed to the following data
Meteorological conditions on synoptic scale
Topography of the study area
Representation of regional background levels
Representation of plant site
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.2
Representation of cross sectional distribution in the downward direction
Influence of the existing sources if any, are to be kept at minimum
Inclusion of major distinct villages to collect the baseline status
3.1.1 Micrometeorological Data
Micro-meteorological data within the project area during the air quality survey period is an
indispensable part of air pollution study. The meteorological data recorded during survey
period is very useful for proper interpretation of the baseline information as well as serves
as an input, to predictive models for air quality impacts.
To understand meteorological scenario primary generated and secondary data collected.
This data is used in the interpretation of wind scenario. The data collected from the both
sources are summarized as follows
Meteorological
data
Primary data: Parameters like Wind speed and its direction,
Temperature, Humidity and Rainfall collected and computed to
hourly results using Automatic Weather Station (90 days) near to
the plant site at >10m height.
Secondary data
A. Secondary data has been collected from the nearest IMD source
(Rajkot) for November 2012 to January 2013 for temperature,
Humidity, Rainfall, wind speed and direction.
3.1.1.1 Meteorological Data (Secondary Data)
As per the historical data (IMD), collected at (Rajkot for 3 months November 2012 to
January 2013), the daily maximum temperature recorded in the month of December 2012
(34.80C) and the daily minimum temperature was recorded in the month of January 2013
(7.7oC). Similarly the maximum humidity levels were recorded in the month of November,
December & January 2013 (100%) and the minimum humidity levels recorded in the
month of January 2013 (8 %). The maximum mean wind speed (8.75 km/hr) was recorded
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.3
in the month of January 2013 where the minimum mean wind speed (6.5 km/hr) in the
month of November 2012.
Table No 3.1.1 Monthly Mean values of Meteorological Data for 3 Month (Secondary Data)
Month Air Temperature .c Humidity % Mean Wind
Speed kmph Max. Min. Max. Min.
November
2012 34.5 15.1 100 16 6.5
December
2012 34.8 9.7 100 11 8.25
January
2013 32.8 7.7 100 08 8.75
Source: As per IMD, Rajkot 3 Months Data
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.4
Fig. 3.1.1 Meteorological Wind Rose Diagram for November 2012 to January 2013 (Secondary data)
3.1.1.2 Meteorology – Data generated at plant site (Primary data)
Meteorology of the study zones plays an important role in the study of air pollution.
Micrometeorological conditions at the proposed project site regulate the dispersion and
dilution of air pollutants in the atmosphere. For this purpose a weather station was
installed near the plant site for three months (November 2013 to January 2014) and
recorded hourly observations for the parameters like Maximum and minimum
Temperatures (ºC), Relative Humidity (%), Wind Speed (km/hr), Wind direction and
Rainfall mm.
Meteorological conditions, of the site, regulates the transport and diffusion of air-pollutants
released into the atmosphere. Ambient temperature, wind speed, wind direction and
atmospheric stability are called primary or basic Meteorological Parameters because the
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.5
dispersion and diffusion of pollutants depend mainly on these Parameters. Humidity,
precipitation, pressure and visibility are secondary Meteorological Parameters as this
control the dispersion of the pollutants indirectly by affecting primary Parameters.
Table No 3.1.2 Monthly Mean values of Meteorological Data for 3 Month (Primary Data)
Month Air Temperature .c Humidity % Mean Wind
Speed kmph Max. Min. Max. Min.
November
2013 33 19 81 28 6.17
December
2013 33 19 73 28 6.78
January
2014 29 10 100 20 8.96
The hourly-recorded observations (wind velocity and wind directions) during 12 weeks
study period are shown in Annexure - A and they used in computing percentage
frequencies and are depicted in the form of ‘wind roses’ in Fig. 3.1.2.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.6
Fig. 3.1.2 Meteorological Wind Rose Diagram for November 2013 to January 2014 (Primary data)
3.1.2 Selection of AAQ stations
A network of seven ambient air-sampling locations has been selected for assessment of the
existing status of air environment within the study zone. The heights of the sampling
locations were kept between 3 to 6 m in all the locations. After reconnaissance of the area
and observing the topographical features and review of the available meteorological data
and local conditions the sampling sites were chosen which will be the representative of the
local areas under study.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.7
3.1.3 Existing AAQ (Pre-project) status
Ambient levels of pollutants such as PM10, PM2.5, SO2, NOX, CO, HCl, Cl2 and VOC are selected
for the sampling. The methodology of sampling and analysis in detail is given in the
following tables.
Table No 3.1.3 Air – Parameters analyzed and sampling duration
Attribute Parameter Frequency of Monitoring
AAQ
PM10, PM2.5, SO2,
NOx, CO, HCl, Cl2
and VOC at 7
locations
24 hr sampling for PM10, PM2.5, SO2, HCl, Cl2 and NOx
Sampling height varies between 3-6 m above ground
level.
Met. Data
Wind speed,
Direction,
Temperature, RH,
Solar radiation at
one center location
Primary data: Hourly data collected at site using AWS
Secondary data: Available 3 months data obtained
from IMD Rajkot-2012-2013.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.8
Table No 3.1.4 Ambient Air Quality - Methodology
Pollutant Method of analysis Va
riab
les
Dus
t PM10 Particulate Matter 10 IS 5182 (Part 23) (RA 2006)
PM2.5 Respirable Suspended Particulate Matter
STP No. TRA/STP/AA/02 Based on manual instrument manufactures.
Gase
s
SO2 Sulfur dioxide IS 5182 (Part 2): 2001 (RA 2002)
NOx Nitrous Oxides IS 5182 (Part 6): 2006 (RA 2002)
HC Non Methyl Hydrocarbon IS 5182 (Part 10): 2006
VOC VOC IS 5182 (Part 11): 2006
Various statistical parameters like standard deviation, geometric mean, minimum;
maximum concentrations and different percentiles have been computed from the data
generated during sampling in all sampling stations (Tables 3.1.5 to 3.1.9).
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.9
Fig. 3.1.3 Map showing Ambient Air Quality locations
A1 A7
A6
A5 A4
A2
A3
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.10
Table No 3.1.4 (a) Ambient Air Quality sampling site
*= indicate the down wind Direction
Table 3.1.5 Ambient Air Quality Monitoring Results
Name of the pollutant: Particulate Matter (PM10)
All the following results are expressed in μg/m3
No. Location Min. Percentile
Max. AM SD GM 35th 50th 85th 98th
1 Project site 63.2 72.4 72.9 75.7 78.8 79.8 73.2 3.1 73.1
2 Nava Jambudiya 67.2 71.6 72.4 75.6 77.1 77.2 72.5 2.6 72.4
3 Juna Jambudiya 67.2 71.6 72.4 76.0 78.7 80.2 72.8 3.2 72.7
4 Rafaleshwar 67.4 71.9 71.9 75.7 78.6 79.8 72.5 3.0 72.4
5 Jodhpar 64.5 71.9 72.8 77.2 77.7 77.7 73.6 3.5 73.5
6 Bhadiyad 68.6 72.4 72.6 76.1 77.2 77.7 73.3 2.4 73.3
7 Paneli 63.2 71.9 72.5 76.1 80.1 80.3 73.0 3.6 72.9
Table 3.1.6 Ambient Air Quality Monitoring Results
Name of the pollutant: Particulate Matter (PM2.5)
All the following results are expressed in μg/m3
Code Air Location Distance in km
Direction
A1 Project site - -
*A2 Nava Jambudiya 0.85 NW
*A3 Juna Jambudiya 1.25 SE
A4 Rafaleshwar 1.44 S
A5 Jodhpar 3 SW
A6 Bhadiyad 4.33 NW
A7 Paneli 4.3 E
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.11
No. Location Min. Percentile
Max. AM SD GM 35th 50th 85th 98th
1 Project site
33.8 38.6 39.0 43.0 44.1 44.7 39.7 3.1 39.6
2 Nava Jambudiya 34.5 38.7 39.0 42.2 42.9 43.0 39.7 2.2 39.7
3 Juna Jambudiya 33.8 40.5 42.2 43.1 44.2 44.4 40.9 2.8 40.8
4 Rafaleshwar 34.8 38.7 42.0 42.9 43.3 43.5 40.5 2.5 40.4
5 Jodhpar 30.1 38.9 42.2 43.2 43.3 43.3 40.5 3.3 40.3
6 Bhadiyad 33.5 38.6 41.2 43.0 43.5 43.7 40.2 3.1 40.0
7 Paneli 33.6 38.5 38.9 43.0 43.6 44.0 39.7 3.3 39.6
Table 3.1.7 Ambient Air Quality Monitoring Results
Name of the pollutant: SO2
All the following results are expressed in μg/m3
No. Location Min. Percentile
Max. AM SD GM 35th 50th 85th 98th
1 Project site 9.5 12.7 14.0 15.5 17.1 17.1 13.6 2.0 13.4
2 Nava Jambudiya 9.4 12.7 13.6 15.1 18.7 20.7 13.5 2.4 13.3
3 Juna Jambudiya 8.1 13.0 13.6 15.3 15.6 15.6 13.3 1.9 13.1
4 Rafaleshwar 8.5 13.4 14.0 15.1 18.8 19.1 13.9 2.1 13.7
5 Jodhpar 10.2 12.9 13.4 14.8 18.3 20.7 13.6 2.0 13.5
6 Bhadiyad 11.4 13.1 13.8 15.4 18.4 20.7 13.9 2.0 13.8
7 Paneli 8.1 12.7 13.1 14.6 15.2 15.3 12.9 1.8 12.8
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.1.12
Table 3.1.8 Ambient Air Quality Monitoring Results
Name of the pollutant: Nitrous Oxides (NOx)
All the following results are expressed in μg/m3
No. Location Min. Percentile
Max. AM SD GM 35th 50th 85th 98th
1 Project site 16.1 21.5 23.9 25.5 26.5 26.8 22.8 2.8 22.6
2 Nava Jambudiya 17.2 21.6 21.9 23.3 24.8 25.5 21.6 2.0 21.6
3 Juna Jambudiya 17.9 20.8 21.9 24.6 26.9 28.0 22.2 2.5 22.0
4 Rafaleshwar 16.2 21.2 22.5 24.9 25.9 25.9 22.2 2.6 22.0
5 Jodhpar 18.8 21.4 21.9 23.7 28.8 30.7 22.3 2.5 22.2
6 Bhadiyad 17.9 20.9 21.5 23.1 27.8 30.7 21.8 2.4 21.7
7 Paneli 14.4 21.3 22.4 23.5 24.5 24.7 21.6 2.4 21.4
VOC and HC were not detected in ambient air.
3.1.4 Results and Discussion
The maximum concentrations are recorded at Paneli with PM10 of 80.3 g/m3 respectively.
The maximum concentrations are recorded at Project Site with PM2.5 of 44.7 g/m3
respectively.
The maximum concentrations of SO2 found at the Nava Jambudiya, Jodhpar and Bhadiyad
with 20.7 g/m3 respectively.
Similarly the maximum concentration of NOx found at Jodhpar and Bhadiyad village with
30.7 g/m3. All the above results are found well within the prescribed limits of National
Ambient Air Quality standards.
Volatile organic compounds, Hydrochloric acid and Chlorine were found to be below
detectable limits or not detected.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.2.1
3.2 NOISE ENVIRONMENT
The word noise arose from the Latin word ‘nauseas’, it is a loud outcry or commotion that
is unpleasant, unexpected, or undesired with various frequencies over the audible range
due to the regular activities of the Mankind primarily Noise pollution (or environmental
noise) is displeasing human, animal or machine-created sound that disrupts the activity or
balance of humans or animals life. The source of most outdoor noise worldwide is mainly
evolved from Industries, constructions and transportation systems, including motor vehicle
noise, aircraft noise and rail noise, poor urban planning may give rise to noise pollution.
Noise can be defined as an unwanted sound. It interferes with speech and hearing and is
intense enough to damage hearing or is otherwise annoying. The definition of noise as
unwanted sound implies that it has an adverse effect on human beings and their
environment. Noise can also disturb natural wildlife and ecological system.
Industrial Noise resulting to noise pollution has many reasons such as industries being
close to human habitats which prevent the noise from decaying before it reaches human
ear. A determination is made of the micro scale impact by predicting anticipated noise
levels for each alternative during both construction and operational phases. Predicted
noise levels are compared with applicable standards or criteria in order to assess the
impact.
Sound is mechanical energy from a vibrating surface, transmitted by cyclic series of
compression and rarefaction of molecules of the materials through which it passes. Sound
can be transmitted through gases, liquids and solids. The number of compressions and
refractions of the air molecules in the unit of time is described as its frequency.
Frequency is expressed in hertz (Hz), which is the same as the number of cycles per second.
The physical description of sound concerns its loudness as a function of frequency. Noise in
general sound which comprises of many frequency components with different variations in
loudness over the audible frequency range.
Various noise scales have been introduced to describe, a single number, the response of an
average human to a complex sound made up of various frequencies at different loud levels,
the response of the human ear to sound is dependent on the frequency of the sound and
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.2.2
this has led to the concept of weighting scales. In the "A-weighting" scale, the sound
pressure levels for the lower frequencies and higher frequencies are reduced by certain
amounts before they are being combined together to give one single sound pressure level
value. This value is designated as dB (A). The dB (A) is often used as it reflects more
accurately the frequency response of the human ear. A perceived loud noise has a high dB
or dB (A) value and a soft noise has a low one. The human ear has peak response around
2,500 to 3,000 Hz and has a relatively low response at low frequencies.
3.2.1 Impact Assessment of Noise Environment
The environmental impact assessment of noise for the proposed project was carried out by
taking various factors into consideration like potential physiological responses, annoyance
and general community responses and also taking all the factors mentioned in the above
lines in to considerations the existing status of noise levels within the Study zone, which is
a primary requirement for impact assessment studies has been undertaken for the
monitoring of baseline noise levels.
3.2.2 Existing Noise Levels
Pre-project noise levels have been monitored at different points within the study zone and
on the spot measurement device manufactured by LUTRON SL4001 was used for this
purpose. Keeping in view of various local activities such as residential and Industrial
activities 7 noise level measurement locations were identified and the sites are depicted in
the Fig. 3.2.1
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.2.3
Fig. 3.2.1 Map Showing Noise Sampling Locations
N1 N7
N6
N5 N4
N2
N3
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.2.4
3.2.3 Methodology of Noise measurement
For Noise levels measured over a given period of time interval, it is possible to describe
important features of noise using statistical quantities. This is calculated using the percent
of the time as certain noise levels are exceeding the time interval. The notations for the
statistical quantities of noise level are given below
L10 is the noise level exceeded 10% of the time.
L50 is the noise level exceeded 50% of the time and
L90 is the noise level exceeded 90% of the time
Equivalent Sound Pressure Level (Leq)
The Leq is the equivalent continuous sound level, which is equivalent to the same sound
energy as the actual fluctuating sound measured in the same period. This is necessary
because sound from noise source often fluctuates widely during a given period of time.
This is calculated from the following equation
Leq=L50+(L10–L90)2/60
Code Air Location Distance in km Direction
N1 Project site - -
N2 Nava Jambudiya 0.85 NW
N3 Juna Jambudiya 1.25 SE
N4 Rafaleshwar 1.44 S
N5 Jodhpar 3 SW
N6 Bhadiyad 4.33 NW
N7 Paneli 4.3 E
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.2.5
Lday is defined as the equivalent noise level measured over a period of time during day (6
am to 10 pm). Lnight is defined as the equivalent noise level measured over a period of time
during night (10 pm. 6 am).
A noise rating developed by Environment Protection Agency, USEPA for specification of
community noise from all the sources is Day-Night Sound Level, (Ldn).
Hourly noise recorded data and Lday values (15 hours) Lnight (9 hours) and Ldn (24 hours)
are computed and tabulated.
Day–Night Sound levels (Ldn)
The noise rating developed for community noise from all sources is the Day-Night Sound
Level, (Ldn). It is similar to a 24 hr equivalent sound level except that during nighttime
period (10 pm to 6 am) A 10 dB (A) weighting penalty is added to the instantaneous sound
level before computing the 24 hr average.
This is time penalty is added to account for the fact that noise during night when people
usually sleep is judged as more annoying than the same noise during the daytime.
The Ldn for a given location in a community may be calculated from the hourly
Leq’S, by the following equation.
Ldn = 10 log {1/24 [15(10 Ld/10) + 9 (10 9Ln + 10 ) /10 ) ] }
Where Ld is the equivalent sound level during the day time (6 am to 10 pm) and Ln is the
equivalent sound level during the night time (10 pm to 6 am).
The statistical analysis is done for measured noise levels at 7 locations
3.2.4 Data Analysis
Sound levels will be recorded according to IS: 9989:1991. The recorded sound levels are
given in Table.3.2.1. Out of all the7 locations measured for noise levels, the sound levels
recorded at project site area is found to be 62.1 dB(A). Recorded Noise levels are found to
be within the standard limits.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.2.6
Table 3.2.1 Hourly Noise data (Day and Night timings in Leq dB (A))
Site code N-1 N-2 N-3 N-4 N-5 N-6 N-7
Hours
06:00 - 07:00 56.1 43.2 46.5 58.1 56.3 42.8 51.7
07:00 - 08:00 49.2 45.2 58.9 43.8 60.4 55.2 62.2
08:00 - 09:00 62.1 55.8 42.5 49.9 61 71.3 42.5
09:00 - 10:00 43.8 34.8 55.1 51 46.1 58.5 65.8
10:00 - 11:00 51.2 30.8 58.3 56 59.3 40.2 40.3
11:00 - 12:00 52.8 47.9 41.9 43.5 65.5 54.3 58.9
12:00 - 13:00 60.2 35.2 46.5 67.8 62.2 40.5 51.3
13:00 - 14:00 58.8 52.5 55.8 52.8 40.5 61.4 37.8
14:00 - 15:00 45.9 46.3 62.3 58.3 60 52.2 71
15:00 - 16:00 57.6 43.9 69.4 35.8 52.8 43.2 46.3
16:00 - 17:00 57.1 36.4 60.2 56.4 45.3 72.1 58.8
17:00 - 18:00 60.8 52.2 67.2 70.5 67.9 41.2 40.2
18:00 - 19:00 44.4 40.9 40.2 40.3 45.2 59.8 49.3
19:00 - 20:00 51.3 58.8 67 63.2 35.9 51.2 54.3
20:00 - 21:00 60.8 47.3 54.4 43.4 49.2 40.3 71.8
21:00 - 22:00 55.2 55.3 30.8 49.8 68.5 68 55.3
Minimum 43.8 30.8 30.8 35.8 35.9 40.2 37.8
Maximum 62.1 58.8 69.4 70.5 68.5 72.1 71.8
Day eq. 52.95 44.8 50.1 53.15 52.2 56.15 54.8
Day Limits 75 55 55 55 55 55 55
Sampling 01/11/2013 01/11/2013 02/11/2013 02/11/2013 05/11/2013 05/11/2013 06/11/2013
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 3.2.7
date
22:00 - 23:00 43.3 48.2 47.3 53.2 43.8 43.5 41.8
23:00 - 24:00 36.4 44.1 41.1 48.1 35.5 47.1 39.2
24:00 - 01:00 49.7 33.1 39.3 42.6 45.3 47.5 51.8
01:00 - 02:00 46.9 55.3 48.5 51.2 42.5 40.7 56.3
02:00 - 03:00 57.8 46.8 43.8 45.3 50.9 41.9 54.5
03:00 - 04:00 32.5 51.5 49.1 49.8 31.9 60.3 52.2
04:00 - 05:00 33.6 38.2 42.3 49.1 35.2 35.6 47.3
05:00 - 06:00 51.3 42.7 46.1 47.1 48.7 53.4 52.8
Minimum 32.5 33.1 39.3 42.6 31.9 35.6 39.2
Maximum 57.8 55.3 49.1 53.2 50.9 60.3 56.3
Night eq. 45.15 44.2 44.2 47.9 41.4 47.95 47.75
Limits 70 45 45 45 45 45 45
D/n eq 1.17 1.01 1.13 1.11 1.26 1.17 1.15
Sampling
date 01/11/2013 01/11/2013 02/11/2013 02/11/2013 05/11/2013 05/11/2013 06/11/2013
Area type Project site Residential Residential Residential Residential Residential Residential
Codes Station Name Codes Station Name
N-1 Project site N-5 Jodhpar
N-2 Nava Jambudiya N-6 Bhadiyad
N-3 Juna Jambudiya N-7 Paneli
N-4 Rafaleshwar
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.3.1
3.3 WATER ENVIRONMENT
Water is the most vital resource for all kinds of life. It should not only be available in
sufficient quantity but should be of good quality as well. Defilement of water, as a result of
human activities, industrial activities and consequent pollution of water, cause
deterioration of the water environment.
Studies on Water Environment aspects of ecosystem is important for Environmental
Impact Assessment to identify sensitive issues and take appropriate action by maintaining
‘ecological homeostasis’ in the early stages of development of the project. The objective of
this report is to define the present environment in which the proposed action is to occur, to
evaluate all possible eventualities, to ensure that all negative impacts are minimized, and to
demonstrate that proposed project has been appropriately announced to all interested
parties so that their concerns can be considered.
Water quality studies have been carried out in the study area to understand the availability
of water resources, possibility of water contamination and existing water quality.
3.3.1 Water Quality Water of high quality is essential to human life, and water of acceptable quality is essential
for agricultural, industrial, domestic and commercial uses; in addition, most recreation is
water based; therefore, major activities having potential effects on surface water are
certain to be of appreciable concern to the consumers.
3.3.1.1 Sample collection and analysis
The water resources in the study area may be classified into two major categories like
Surface and ground water sources.
Water samples were collected at 9 locations, out of which 2 samples was selected from
surface sources and 7 samples selected from ground water sources for physico-chemical
and biological studies. Parameters like pH, Temperature and DO collected at the time of
sampling. For other parameter analysis the samples were preserved as per the
recommended techniques for various elemental determinations as per `IS: 3025 (part I)
1987’ and brought to the Head laboratory situated at New Delhi. These parameters were
analyzed as per the procedures specified in ‘Standard Methods for Examination of Water
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.3.2
and Wastewater’ published by American Public Health Association (APHA). Ground water
samples results were compared with IS: 10500 specification and surface water samples
results were compared with CPCB standards.
Fig. 3.3.1 Map showing Water Quality Locations
GW1 GW7
GW6
GW5 GW4
GW2
GW3
SW2
SW1
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.3.3
Code Water Locations Direction
GW1 Project site -
GW 2 Nava Jambudiya NW
GW 3 Juna Jambudiya SE
GW 4 Rafaleshwar S
GW 5 Jodhpar SW
GW 6 Bhadiyad NW
GW 7 Paneli E
SW 1 Macchu River SW SW 2 Paneli Lake NE
3.3.1.2 Method of Water Sampling
The following procedures were used while sampling
Washing the bottles/cans with distilled water prior to the sampling
Before collection of water the bottles/cans are again washed 2-3 times with the
same water
For surface water, Bottles were lowered to a minimum depth of 30 cm below
water surface
At each point Different sets of water samples were collected so as cover all the
parameters
Meticulous attention is taken in proper numbering at the site
Sterilized bottles were used for the samples that are to be analyzed for bacteria
Civil supply water pipeline taps are sterilized before collection for
bacteriological analysis
Parameters like pH, conductivity and temperature were analyzed in the field
conditions and the results were reconfirmed after getting to the laboratory.
DO is fixed and titrated in the field itself.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.3.4
Appropriate preservatives are added, depending upon the elements to be
analyzed and marked accordingly (IS: 3025 (part I) 1987)
All the water samples collected in the ice box, were immediately transported to
the laboratory and free zed at <5oC analysis
Field observations were noted in the field notebook
As far as possible photographs were taken in almost all sampling points
All the parameters have been analysed as per APHA, 20th edition & IS: 3025.
3.3.1.3 Data Analysis
The physicochemical and biological analysis of the collected sample results are given in
Table 3.3.1.
The pH of the ground water samples varying from 7.01 to 7.62 indicating basic nature.
Hardness, alkalinity, chlorides, sulfates are found to be below the prescribed limits.
However sulfates are found to be lower than the required limits. No carbonates were
detected in all the samples. Ground and surface water results are given Table No. 3.3.1 &
3.3.2.
3.3.1.4 Impacts
No significant impact is anticipated on ground water depletion because the water
requirement is met from bore well. The water procured from bore well will be recycled and
zero discharge.
3.3.2 Conclusions
All the parameters for the Ground Water are found to be within the limits.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.3.5
Table 3.3.1 Water Quality - Physico-chemical Analysis of Ground Water
Note: Permissible Limit is applicable in the absence of Alternate source
B.D.L=Below Detection Limit, D.L. = Detection Limit
Sr.
NO.
Test Parameters Result IS : 10500
Sample Code & Location Units Site 1 Project Site
Site 2 Nava
Jambudiya
Site 3 Juna
Jambudiya
Site 4 Rafaleshwa
r
Site 5 Jodhpar
Site 6 Bhadiyad
Site 7 Paneli
Desirabl
e
Permissib
le
1 Colour Hazen 3.5 1.0 5.5 4.0 3.0 6.0 3.0 5 25 2 Odour -- Unobj. Unobj. Unobj. Unobj. Unobj. Unobj. Unobj. Unobj. Unobj. 3 Taste -- Agr. Agr. Agr. Agr. Agr. Agr. Agr. Agr. Agr. 4 Turbidity NTU 1.3 <1.0 1.8 1.5 1.0 2.0 1.2 5 10 5 pH value -- 7.27 7.15 7.62 7.01 7.25 7.56 7.22 6.5 to 8.5 6.5 to 8.5 6 Total Hardness (as CaCO3) mg/l 215 247 198 234 195 256 390 300 600 7 Calcium Hardness mg/l 141 156 129 145 138 159 0.18 NS NS 8 Magnesium Hardness mg/l 74 91 69 89 57 97 560 NS NS 9 Calcium (as Ca) mg/l 67.6 74.8 61.9 69.6 66.2 76.3 <0.05 75 200
10 Magnesium (as Mg) mg/l 17.9 22.1 16.7 21.6 13.8 23.5 1620 30 100 11 Chlorides (as Cl) mg/l 235 188 246 184 292 168 208 250 1000 12 Iron (as Fe) mg/l 0.22 0.31 0.18 0.17 0.28 0.11 0.20 0.3 1.0 13 Dissolved solids(TDS) mg/l 745 642 786 629 814 619 718 500 2000 14 TSS mg/l 10 8 12 11 10 12 10 NS NS
15 Copper (as Cu) mg/l B.D.L (DL=0.04)
B.D.L (DL=0.04)
B.D.L (DL=0.04)
B.D.L (DL=0.04)
B.D.L (DL=0.04)
B.D.L (DL=0.04)
B.D.L (DL=0.04) 0.05 1.5
16 Manganese (as Mn) mg/l B.D.L (DL=0.02)
B.D.L (DL=0.02)
B.D.L (DL=0.02)
B.D.L (DL=0.02)
B.D.L (DL=0.02)
B.D.L (DL=0.02)
B.D.L (DL=0.02) 0.10 0.3
17 Sulfate (as SO4) mg/l 72 65 84 78 59 64 76 200 400 18 Nitrate (as NO3) mg/l 2.1 1.5 1.7 2.6 1.3 1.0 2.5 45 100 19 Fluoride (as F) mg/l 0.35 0.63 0.39 0.46 0.51 0.48 0.36 1.0 1.5
20 Phenolic Compounds mg/l B.D.L (DL=0.1)
B.D.L (DL=0.1)
B.D.L (DL=0.1)
B.D.L (DL=0.1)
B.D.L (DL=0.1)
B.D.L (DL=0.1)
B.D.L (DL=0.1) 0.001 0.002
21 Mercury (as Hg) mg/l B.D.L
(DL=0.0005)
B.D.L (DL=0.0005
)
B.D.L (DL=0.0005)
B.D.L (DL=0.0005
)
B.D.L (DL=0.0005
)
B.D.L (DL=0.0005
)
B.D.L (DL=0.0005
) 0.001 0.001
22 Cadmium (as Cd) mg/l B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005) 0.01 0.01
23 Selenium (as Se) mg/l B.D.L (DL=0.001)
B.D.L (DL=0.001)
B.D.L (DL=0.001)
B.D.L (DL=0.001)
B.D.L (DL=0.001)
B.D.L (DL=0.001)
B.D.L (DL=0.001) 0.01 0.01
24 Arsenic (as As) mg/l B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005) 0.05 0.05
25 Cyanide (as CN) mg/l B.D.L B.D.L B.D.L B.D.L B.D.L B.D.L B.D.L 0.05 0.05
26 Lead (as Pb) mg/l B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005)
B.D.L (DL=0.005) 0.05 0.05
27 Zinc (as Zn) mg/l 2.1 0.9 1.3 2.3 1.5 2.7 3.1 5 15
28 Anionic detergents (as MBAS) mg/l B.D.L
(DL=0.1) B.D.L
(DL=0.1) B.D.L
(DL=0.1) B.D.L
(DL=0.1) B.D.L
(DL=0.1) B.D.L
(DL=0.1) B.D.L
(DL=0.1) 0.2 1.0
29 Chromium (as Cr6+) mg/l B.D.L (DL=0.03)
B.D.L (DL=0.03)
B.D.L (DL=0.03)
B.D.L (DL=0.03)
B.D.L (DL=0.03)
B.D.L (DL=0.03)
B.D.L (DL=0.03) 0.05 0.05
30 Polynuclear Aromatic Hydro carbons g/lit
B.D.L (DL=0.0001
)
B.D.L (DL=0.0001
)
B.D.L (DL=0.0001)
B.D.L (DL=0.0001
)
B.D.L (DL=0.0001
)
B.D.L (DL=0.0001
)
B.D.L (DL=0.0001
) -- --
31 Mineral Oil mg/l B.D.L (DL=0.01)
B.D.L (DL=0.01)
B.D.L (DL=0.01)
B.D.L (DL=0.01)
B.D.L (DL=0.01)
B.D.L (DL=0.01)
B.D.L (DL=0.01) 0.01 0.03
32 Pesticides mg/l B.D.L
(DL=0.000025)
B.D.L (DL=0.0000
25)
B.D.L (DL=0.00002
5)
B.D.L (DL=0.0000
25)
B.D.L (DL=0.0000
25)
B.D.L (DL=0.0000
25)
B.D.L (DL=0.0000
25) Absent 0.001
33 Alkalinity mg/l 244 266 238 252 234 276 296 200 600
34 Aluminium (as Al) mg/l B.D.L (DL=0.01)
B.D.L (DL=0.01)
B.D.L (DL=0.01)
B.D.L (DL=0.01)
B.D.L (DL=0.01)
B.D.L (DL=0.01)
B.D.L (DL=0.01) 0.03 0.2
35 Boron mg/l B.D.L (DL=0.05)
B.D.L (DL=0.05)
B.D.L (DL=0.05)
B.D.L (DL=0.05)
B.D.L (DL=0.05)
B.D.L (DL=0.05)
B.D.L (DL=0.05) 1 5
36 Coliform MPN Absent Absent Absent Absent Absent Absent Absent Absent 10
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.3.6
Table 3.3.2 Water Quality - Physico-chemical Analysis of Surface Water
No. Characteristics Units SW – 1 Macchu River
SW -2 Paneli Lake
Tolerance Limits
1. Colour Hazen 29 25 300 2. pH -- 7.41 7.95 6.5-9.0 3. Conductivity mhos/cm 1168 1208 -- 4. DO mg/l 3.0 3.2 4 5. COD mgO2/l 71 51 - 6. BOD(3 days at 270C ) mgO2/l 24 16 3 7. TDS mg/l 964 1102 1500 8. Chlorides as Cl mg/l 282 439 600 9. Free Ammonia mg/l 0.48 0.2 -- 10. Total Hardness as
CaCO3 mg/l 351 294 300
11. Calcium as Ca++ mg/l 66.7 68.16 75 12. Magnesium as Mg++ mg/l 51.5 36.95 30 13. Sodium as Na mg/l 68 52 -- 14. Potassium as K mg/l 39 35 -- 15. Sulphate as SO4 mg/l 86 79 400 16. Nitrate as NO3 mg/l 3.5 2.6 50 17. Fluoride as F mg/l 0.5 0.4 1.5 18. Copper as Cu mg/l B.D.L(DL=0.04) B.D.L(DL=0.04) 1.5 19. Iron as Fe mg/l 1.3 2.1 50 20. Zinc as Zn mg/l 1.8 1.9 15 21. Boron as B mg/l B.D.L(DL=0.05) B.D.L(DL=0.05) 2 22. Arsenic as As mg/l B.D.L(DL=0.004) B.D.L(DL=0.004) 0.2 23. Lead as Pb mg/l B.D.L(DL=0.005) B.D.L(DL=0.005) 0.1 24. Pesticides g/l Absent Absent - 25. Sodium Adsorption
Ratio meq/l 1.51 1.26 26
26. Total Coliform MPN/100ml 117 87 5000 DL: Detectable limit ; BDL: Below Detectable Limit
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.1
3.4 LAND ENVIRONMENT
Studies on land and biological aspects of ecosystem are important for Environmental
Impact Assessment to identify sensitive issues and take appropriate action by maintaining ‘ecological Homeostasis in the early stages of development of the project. The objective of
this report is to define the present environment in which the proposed action is to occur, to
evaluate all the possible eventualities, to ensure that all negative impacts are minimized
and to demonstrate that the proposed project has been appropriately announce to all the
interested parties so that their concerns can be considered.
The Land Use/ Land Cover gives a detailed idea to understand how the land use for
proposed activity will affect the change in land use pattern, Status of vegetation & land
cover. The land use study also gives idea of necessary Planning of environment
conservation issues directly or indirectly associated with project area. The land use/ land
cover mapping of 5 km & 10 km radius area encompassing the project site was taken up by
using visual image interpretation of satellite image of goggle earth.
For this purpose baseline data (biotic and abiotic factors) has been studied around 10 km
radius of the project.
3.4.1 Methodology of sample collection and analysis
Soil
For soil quality analysis 7 sampling sites were chosen to understand physico-chemical and
biological status of the soil. The sampling sites are marked in Fig.3.4.1. This will establish
the baseline characteristics and will facilitate identifying the contamination if any due to
the proposed project.
Collection of soil samples and analysis
Disturbed soil samples were collected from the rotary cuttings and bailers and also from
split spoon samplers. Un-disturbed tube samples were collected using thin walled tubes.
Soil samples were collected such that structure and moisture content of the soil do not get
altered. In accordance with IS: 2720, split samples were carefully extracted from the
samplers.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.2
Meticulous was paid to collect adequate amount of composite soil samples for analysis.
The samples were packed in dependable, waterproof containers and marking specified
accurately and distinctly. All the soil samples and core boxes were carefully transported to
the testing laboratory. All ‘Soil sampling and analysis’ will be followed and done by Indian Standard IS – 2720.
Parameters analyzed for soil samples were pH, EC, Texture, Heavy metals, Organic carbon,
porosity, Bulk density, Nitrogen, Potassium, Magnesium, sulphates etc.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.3
Fig. 3.4.1 Map showing Soil Sampling Locations
S1 S7
S6
S5 S4
S2
S3
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.4
Code Water Locations Direction
S1 Project site -
S2 Nava Jambudiya NW
S3 Juna Jambudiya SE
S4 Rafaleshwar S
S5 Jodhpar SW
S6 Bhadiyad NW
S7 Paneli E
3.4.2 Soil Data Analysis
The pH of the soil extract varied from 6.9 to 7.8. In terms of soil pH the soil characteristics varied from ‘Slightly alkaline’ in nature. Organic carbon in soils ranged from 1.8 to 3.1
revealing the distribution more than sufficient. Nitrogen values ranged between 155 to 195
mg/kg. The Phosphorus levels ranged between 115 to 160 mg/kg indicating its presence is
less. Soil potassium varied from 35 to 60 mg/kg.
Table: 3.4.1 Physicochemical Parameters of the soil
Sr
No. Test Parameters
Result
Site 1 Project Site
Site 2 Nava jambudiya
Site 3 Juna jambudiya
Site 4 Rafaleshwar
Site 5 Jodhpar
Site 6 Bhadiyad
Site 7 Paneli
1.
2.
3.
4.
5.
6.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.5
7.
8.
9.
10.
11.
3.4.3 Geo-Hydrological Features
3.4.3.1 Introduction:-
Repaid urban, industrial and Agricultural growth and its continuous expansion around
Morvi Town, has created problems related to water supply, Sewerage/ effluent disposal
leading to ground water depletion and pollution. The present report in corporate
hydrogeology and ground water scenario based on the scientific information with special
reference to Recharge Activity around Morvi town to envisage appropriate remedial
measures keeping environmental impact of Morvi development in view.
3.4.3.2 Geology:-
Around Morvi and Wankaner area Sandstone is exposed. The oldest rock formations
exposed in the area are sandstones & Shale of Jura- Cretaceous age. These sandstones area
overlain by Deccan traps basalts of upper cretaceous to lower Eocene age. The sandstone
belongs to sedimentary group of rocks. It occupies most of the area of SW Part of Morvi
district. The Sandstone is pinkish white to violet in colour and serves very good aquifer
sandstone exceeds 400 mts. in the thickness consisting of medium to coarse grained
sandstones intercalated with red, grey and black sheds with occasional thin coal strings.
Basalt formation is exposed on LHs of road Morvi to Halvad nr. Unchi Mandal
village. Many varieties of basaltic rock formation of upper cretaceous to Eocene Deccan
Traps are known to occur and a part from typical dark grey fine grained variety, layer of
amygdaloidal and prophyritic basalt are also common. It has no primary porosity & permeability but the fractures’, weathered zones, fissures, dyke, lineament present in it to
provide secondary porosity.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.6
3.4.3.3 Land / Soil Characteristic :-
The soils are generally developed from sandstone and basalt formation and are coarse in
texture with satisfactory internal drainage. The sub soil condition below the existing
ground level are almost uniform in nature. Sub soil is composed of Clay mixed with little
fine grained silty sand, moram and Kankar with low resistivity due to clay and soil
moisture. The area is covered with recent to sub recent alluvial deposits comprising of
brownish clay mixed with little fine grained sand, silty sand. The Soil below ground level
consist of top silty low plastic soil layer having no swelling nature. Blackish brown to
yellowish brown clayey silt or sand silt layer extends to the depth of 2 to 3 mts.
3.4.3.4 Rain Fall:- The average annual rainfall (1980 to 1990) is 506 mm. (10 years) average rain fall of (1991
to 2000) 10 years is 438 mm and average rain fall of last 10 years is 701 mm contributed
mainly by Southwestern monsoon active from June to Mid September. Dependable Rainfall
is 660 mm.
Rainfall Data Rainfall Data in Descending Order
Sr.No. Year Rainfall in mm Year Rainfall in mm
1 1991 213 1994 1082
2 1992 460 2010 1048
3 1993 320 2006 989
4 1994 1082 2007 886
5 1995 423 2005 756
6 1996 417 2008 730
7 1997 596 2011 715
8 1998 468 2003 709
9 1999 229 2004 660
10 2000 245 1997 596
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.7
11 2001 428 1998 468
12 2002 332 2009 468
13 2003 709 1992 460
14 2004 660 2001 428
15 2005 756 1995 423
16 2006 989 1996 417
17 2007 886 2002 332
18 2008 730 1993 320
19 2009 468 2012 312
20 2010 1048 2000 245
21 2011 715 1999 229
22 2012 312 1991 213
Dependable Rainfall = N X P / 100 =22 X 40 /10 = 8.8
i.e. = 9th Year i.e. = 660 mm
3.4.3.5 District wise status of ground water Development in Gujarat (1997):-
Rajkot & Morvi District:-
1) Gross draft MCM :- 684.73
2) Total Recharge MCM :- 1230.24
3) Utilisable Recharge MCM :- 984.192
4) Stage of Development (%) :- 69.6
Source G.O.G 1999
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.8
3.4.3.6 General Information of Taluka:-
Total number of villages = 121
Total area of Taluka in km2.= 1697.30
Saline area = 590.34 km2.
Fresh water area = 1187.96 km2.
Hard rock area = 848.65 km2.
Aluminum area = 848.65 km2
Feasibility = Open well, DCB, DTH Bores and deep
Tube well (DR)
Ground water Balance – 18.73 MCM/ Year
3.4.3.7 Climate:-
The climate of the area is semi arid and is characterized by a hot summers. May is the
hottest month with mean daily maximum temperature of 43.40 C. The area has semi arid
climate with drought frequency of 34%.
3.4.3.8 Geohydrology :-
The litho logical logs of exploratory bore holes, electrical logging results by govt. agencies
in and around Morvi Taluka have been studied to understand the subsurface geology and
the aquifer system. These bore holes have penetrated the thick sequence of Jura-
Cretaceous age down to 200 + m depth.
3.4.3.9 Ground Water Condition:-
In geohydrological conditions are controlled by different geological formations of the area.
Sandstone formation due to its high porosity and permeability serves as very good water
bearing aquifer. In sandstone area tube wells, DCB, are feasible. In the area under
investigation, ground water occurs both under phreatic and confined condition in
aranaceous horizons. The occurrence and movement of ground water is mainly controlled
by primary porosity of intergranular pore spaces. Ground water is being developed
extensively by means of Tube well from deep confined aquifers for water supply both in
domestic, industrial and agricultural sector.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.9
3.4.3.10 Depth of Ground Water Table:-
Shallow aquifer (Phreatic) development (up to 30m depth) in the area is limited due to
rapid urbanization inferior quality and low yields. In general the ground water occurs
under water table condition & confined condition where water level ranges from 20 to 25
mts depth depending upon the rock type. Pumping water level of the area is 40 to 50 mts.
tube wells and DCB yield portable water up to 150 mts. depth and Quality deteriorates with
depth.
3.4.3.11 Feasibility of Source at Rajpur, Taluka Kadi :-
Area around Morvi Town is checked on ground water prospect Map, prepared by National
Remote Sensing Agency, Dept. of SPAC, G.O.I. Hyderabad, map sheet no. 41J13 for feasibility
of source. The detail is as under
Hydro geomorphic unit APD -12
Hydro Geomorphic units/ land form: PD–53
(Pediment 53) Sandstone formation
Geological sequence/ Rock type :- Lower cretaceous Dharangadhara
group formation
Depth of water table of the area : 8-13 m in Dug well, 8-13 m in Borewell
Recharge condition : Limited
Aquifer Material in Sandstone Rock : P.R. Permeable Rock (SST)
Type of Well of the area
T.W. Tubewell – 85-120 mts.depth,80-100 LPM
Homogeneity in the unit & success rate of well – Moderate
Quality of water –Potable
Ground water irrigated area – NIL
Recharge structure suitability and priority – Moderate
RP = Recharge Pit, RB = Recharge Bore
Remarks (Problems/Limitations)
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.10
Sandstone forms the aquifer more suitable for constructing tubewell. Recharge structure
required to improve Ground water reserves and quality. It is reported that the ground
water level are declining due to reserved of closely spaced tubewell.
3.4.4 Land Use Status
The land-use & land cover map of the 10 km radius study area from the project site has
been prepared using IRS P6 LISS-III satellite image procured from NRSC (National Remote
sensing Centre), Hyderabad. Land use pattern of the study area as well as the catchment
area was carried out by standard methods of analysis of remotely sensed data and followed
by ground truth collection (Bench mark) and interpretation of satellite data. The outcome
of land use study has been presented below in subsequent table and figures. The data was
processed through ArcGIS Software tools available with ESRI Package. The Land use map of
the 10 Km study area is presented in Fig 3.4.2
3.4.5 Land use & land cover classification results Land Cover is the physical material at the surface of the earth (it include grass, asphalt,
trees, bare ground, water, etc.) whereas Land use is the human use of land.
Land Use involves the management and modification of natural environment or wilderness
into built environment such as fields, pastures, and settlements. It has also been defined as
"the arrangements, activities and inputs people undertake in a certain land cover type to
produce, change or maintain it".
There is no one ideal classification of land use and land cover, and i t is unlikely that one
could ever be developed. There are different perspectives in the classification process, and
the process itself tends to be subjective, even when an objective numerical approach is
used.
Concepts concerning land cover and land use activity are closely related and in many cases
have been used interchangeably. The purposes for which lands are being used commonly
have associated types of cover, whether they are forest, agricultural, residential, or
industrial.
Remote sensing image-forming devices do not record activity directly. The remote sensor
acquires a response which is based on many characteristics of the land surface, including
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.11
natural or artificial cover. The interpreter uses color, tones, textures, shapes, size, patterns,
and site associations to derive information about land use activities from what is basically
information about land cover.
To begin with, there is considerable diversity of opinion about what constitutes land use,
although present use of land is one of the characteristics that are widely recognized as
significant for planning and management purposes.
The classification must be scientifically defensible presenting a logical progression of its
applicability over large areas, amenable for use with remote sensor data. The classification
scheme is adopted for extracting information for on most possible land use/land cover
classes in general and all the agricultural seasons in particular and hence enable to repeat
the process at regular time intervals.
The present Land use / Land cover map for the proposed project activity is prepared by
current vintage of satellite image. This report thus will enable assessing the impact on land
use pattern in the study area due to the proposed project activity.
3.4.5.1 DATA USED
Current vintage data of Indian Remote Sensing satellite IRS P6 LISS III digital FCC (False
Color Composite) has been used for preparation of Land use/ Land cover thematic map of
study area. Survey of India toposheet as a reference map on 1:50,000 scale has been used
for preparation of base layer data like road, rail network, village and mine site and for geo
referencing of satellite image.
Technical Details
Satellite Image - IRS P6 LISS III
Satellite Data Source - NRSC, Hyderabad
Software Used - Earth Resources Data Analysis System (ERDAS) Imagine 9.2 and
ArcGis10.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.12
3.4.5.2 METHODOLOGY
Land use / Land cover map preparation, Base map creation; Geometric and Radiometric
correction of satellite image has been processed using ERDAS Imagine 9.2 Software.
Salient features of the adopted methodology are given below:
Acquisition of satellite data.
Preparation of base map from Survey of India toposheets.
Data analysis using visual interpretation techniques.
Ground truth studies or field checks.
Finalization of the map.
Digitization using heads up vectorisation method.
Area calculation for statistics generation.
3.4.5.3 INTERPRETATION OF REMOTE SENSING DATA
Satellite images are composed of array of grid, each grid has a numeric value that is known
as digital number. Smallest unit of this grid is known as a pixel that captures reflectance of
ground features represented in terms of Digital number, each representing specific land
features. Using image classification technique, the satellite data is converted into thematic information, map based on the user’s knowledge about the ground area. Hybrid technique has been used i.e. visual interpretation and digital image processing for identification of
different land use and vegetation cover classes based on spectral signature of geographic
feature.
Spectral signature represents various land use classes. Image interpretation keys are
developed based on image characteristics like color, tone, size, shape, texture, pattern,
shadow, association etc, which enables interpretation of satellite images for ground
feature. Training sites are then assigned based on their spectral signature and
interpretation elements. Using image classification algorithm land use map is generated.
A total of eleven land use/land cover classes have been demarcated in the study area
following Level I, II and III classification (Table 3.4.2). A thematic map suitable for 1:25,000
scale map generation incorporating these classified categories has been prepared and
considering that the area of the project is considerably small a large scale map is prepared
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.13
(Fig.3.4.2). The area as a whole represents plain area with very gentle sloping to nearly
level area & to the north of area is main canals flowing from east to west and it is also
observed that the major stream ( Macchu ) are linked with these two main river channel (
Macchu )debouche into the Little rann of kutchchh. Medium level industrial zone covered
for 15.40 sq km, the total land area of scrub land covered 11.94 sq km and 171.83 sq km
area covered under agriculture land as well as plantation / Horticulture 0.46 sq km has
developed mainly in the area adjacent to the rivers.
The adjoining area of project site is totally agricultural land including Kharif ,Rabi and
Summer crop, constitute the dominant category of land use covering as much as 171.83 sq
km of the total area. Active river canal forming the perennial water body together with the
numerous open & wastelands form a major and minor land cover category. Active river and
its tributaries flowing into it cover about 15.50 sq km of the total project area. Due to large
seasonal variation in discharge of these rivers, the area coverage of this category various in
space and time. The consistently shifting nature of the (canal name) and consequent bank
migration has resulted in large uncultivated & rural settlement along the active plain area
towards the site location. These areas (3.73 sq km) are perennially waterlogged dry and
settlement development area the project site is located within the uncultivated land area
significant distribution. The land use for settlement is mostly confined to the ‘rural and urban settlement’ (built up-rural) 20.48 sq km and land without scrub feature 45.44 sq km
of the total area & as such there is no current fallow land because the satellite used is of
March month when most of the crop is towards senence or maturity . Barren rocky land ie
0.51 sq km is observed along the rivers and due to rains erosion can been seen across it
along with plantation on the top and forest plantation is observed around kalikanagar ie
29.69 sq km .
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.14
S.No. LULC Class Area (Sq.Km2) Percentage
1 Built up land (Urban/Rural) 20.48 6.50
2 Industry 15.40 4.89
3
Kharif crop land
171.83
Rabi crop land
Zaid cropland
Double/triple crop land 54.55
4 Plantations / Horticulture 0.46 0.15
5 Forest 29.69 9.42
6 Land with scrub 11.94 3.79
7 Land without scrub 45.44 14.43
8 Barren Rocky 0.51 0.16
9 Waterlogged 3.73 1.18
10
Water bodies:
Rivers/Streams/Lakes/canal 15.50 4.92
TOTAL 314.16 100
Table 3.4.2 Land use Details
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.15
Fig.
3.4
.2 L
and
Use
Map
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.16
Fi
g. 3
.4.3
Hig
h R
esol
utio
n Sa
telli
te im
age
show
ing
10 k
ms
radi
us a
roun
d th
e pl
ant s
ite
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.17
Fi
g. 3
.4.4
Top
ogra
phic
al M
ap
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.18
Fig
3.4.
5 In
fras
truc
ture
map
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.19
3.4.6 Topography of the study area
THE AREA OF THE PROJECT SITE (M/S. PAWAN FORMALIN P. LTD) IS LOCATED IN
THE NORTHERN PART OF MORBI DISTRICT OF GUJARAT STATE.
The topographic feature & drainage pattern of the study area has been studied from
SRTM3, 2008 data having resolution of 3 arc seconds. The toposheet have been analysed
using GIS application to generate the contour line at interval of 10 Kms considering one
elevated area in the study region. Further, the digital elevation data have been analysed to
determine the slope & elevation profiles of the each individual villages of the study area as
well as whole study area to ascertain the landform of the villages and study area.
It has been observed that the major area of study area is levelled plain to nearly level with
small slopes. Two areas in the study region have been noticed with considerably medium
slope near village Kalikanagar making the landform of small slopes indicating small plain
with the elevation profile. Over all slope direction of the study area is noticed towards
south to north.
The maximum elevation and higher slope is found near eastern part of Kalikanagar, paneli
and Gidach village where a medium height is situated.
The generated streams indicated that the most of the area are covered by main stream ie
Machu river flowing through the Northern area and downstream merges with major river
ie. Machu . Besides it is also observed that the minor stream are linked with these two main
drainage channel and are sufficient to take care of draining the runoff during probable high
rainfall to avoid flooding in the region.
Topography of the area is characterized by dominating plain area with very gentle sloping
to nearly level area.
DIGITAL ELEVATION MODEL
Digital Elevation Models are data files that contain the elevation of the terrain over a
specified area, usually at a fixed grid interval over the "Bare Earth". The intervals between
each grid points will always be referenced to some geographical coordinate system. This is
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.20
usually either latitude-longitude or UTM (Universal Transverse Mercator) coordinate
systems. The closer are together the grid points, more detailed information will be in the
file. The detail s of the peaks and valleys in the terrain will be better modelled with small
grid spacing than when the grid interval s are very large. Elevations other than at the
specific grid point locations are not contained in the file. As a result peak points and valley
points not coinciding with the grid will not be recorded in the file. For practical purpose
this "Bare Earth" DEM is generally synonymous with a Digital Terrain Model (DTM)
3.4.6.1 DATA USED
DEM Data: Shuttle Radar Topographic Mission (SRTM) data
Software Used: ERDAS Imagine 9.2 & Arc GIS 10.
PHYSIOGRAPHY AND DRAINAGE PATTERN
The area of the project site is located in the northern part of Morbi District of Gujarat state.
Topography of the area is characterized by very gentle sloping area to level to nearly level.
A Seasonal river, i .e. Machu River, drains through the study area and merges into Little
Rann of Kutchchh .
3.4.7 Ecology and Bio diversity
3.4.7.1 DATA COLLECTION AND FIELD VISIT
In order to understand the ecological status of different habitats, status of biodiversity in
and around the proposed project area, the field work was carried out from December to
February 2014 (winter season). Simultaneously, data analysis and report preparation was
carried out from November 2013 till December 2014. Summary of the field surveys are
given in Table 3.4.3.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.21
Table: 3.4.3 Field Survey
Month Particular
Nov. 2013 Collection and compilation of secondary data on
biodiversity in and around the project sites.
Dec. 2013 Field survey and collection of primary data on
flora, fauna, local interview to collect crops data
and traditional data on medicinal and wild life
information
Nov. 2013-Jan. 2014 Data entry, Data analysis & Report Preparation
3.4.7.2 DETAIL METHODOLOGY
3.4.7.2.1 Secondary data collection
Collection and collation of project related secondary information including Biodiversity,
Cropping pattern, Land use-Land cover (LuLc) data etc.
Analysis of GOOGLE maps with available project document conducted our first rapid
survey of the project area to identify existing major habitat types within the study area
(Agriculture hedges and road side habitats LIKE etc.; Wasteland, open scrub and
gauchar land LIKE in and around the villages of etc.; and Riverine/Wetlands, i.e., village
ponds, tanks and dry nallah LIKE).
In addition relevant documents and maps were also obtained from project
authority/client and EIA consultant.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.22
Fig.: 3.4.6 Google image showing in and around the Project Location .
3.4.7.2.2 Compilation of available information and rapid reconnaissance
Status of land use and habitat types was studied within the 5km radius identified as
the buffer zone of the proposed project site. In addition, rapid survey of the project
area been conducted to identify existing major habitat types within it (Wilderness
area: Reserve Forest, Open Scrub and Prosopis Dense; Agriculture hedges and along
road side; Wasteland and gauchar land; and Wetlands: village ponds, tanks, small
nallah and riverine). The following areas under each habitat category been surveyed
to collect biodiversity data:
Riverine/wetland/
Nallah
Forest/
Open Scrub
Agriculture
Hedge/Road side
Wasteland/
Gauchar
-Machchhu river
-Paneli talav
-Kaldhari nallah
-Matel nallah
-Someshwar nallah
-Nava dhuva nallah
-Paneli RF
-Nr.Lakdhirpur
-Nr.Paneli vidi
-Nr.Makansar
-Nr.Ratavirda vidi
-Pipri-Trajpu road
-Makansar-
Rafleshwar road
-Paneli road
-Dhuva road
-Navagam road
-Nr.Paneli village
-Nr.Lakdhirpur
-Nr.Rata Virda
-Nr.Didar village
-Latifar vidi
-Nr.Rafleshwar
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.23
Collection and collation of project related secondary information from client and
consultant.
After several consultation with project authority and based on available areas under
each habitat, the number of plots and size of plots been finalized and selected plots
are eventually distributed and systematic randomized sampling design been
employed for collection of biodiversity data within buffer zone.
3.4.7.3 Intensive survey and compilation of primary field data
Intensive field approach involved mainly the survey-based primary data collection
on various biodiversity components of the project objectives.
The field data collection mainly included biodiversity assessment of different life
forms of floral species such as; trees, shrubs, climbers, herbs and grass. Status of
floral diversity was assessed in representative habitats of each type like; wastelands
which include: open scrub forest and Prosopis juliflora thickets, semi-wilderness
area, agricultural hedge, near human habitation, plantation, stream and river beds
and wetlands (inland).
Faunal diversity was also assessed by inventorying the major group like
herpetofauna, birds and mammals.
Status of herpetofauna was assessed using Intensive Time Constrained Search
Method covering different micro habitats (Welsh, 1987, Welsh and Lind 1991). This
intensive search was made in different habitat types randomly selected.
Avifaunal status was assessed both in terrestrial and aquatic habitats. Total count or
flock count method was adopted to assess the status of aquatic birds in the existing
water bodies (Sridharan 1989 and Bhupathy 1991). Point count method was used to
assess the status of terrestrial birds (Bibby et al., 1992 and Hutto et al., 1986). The
second technique adopted was area search method (Dieni and Jones 2002), a time
area constrained survey technique that has been widely and commonly used in
several bird monitoring programs.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.24
Status and distribution of different mammal species was quantified using Direct
count Vehicle transects (travelling between the sampling location) (Burnham et al.
1980) and indirect evidences within the survey areas (Rodgers 1988 and Sale and
Berkmuller, 1988). Indirect evidences like, Pellet, dung, tracks (Thommpson et al
1989, Allen et al 1996), scat count (Henke and knowlton 1995) and other signs were
enumerated using standered method for nocturnal species (Daniels 1992). Presence
of different faunal species was also substantiated by interviewing the local people
and experts with pictorial representation.
In addition to the field survey information on various wildlife species in and around
the project sites were collected through village survey and interviewing the
maldharies (traditional livestock grazers), farmers and elders from each adjoin
village of project sites. This information was used to estimate the numbers of the
significant species exist within buffer zone, and their possible movement pattern
between diverse habitats.
Secondary information (published and un-published) on the status of the wildlife
species from different sources was also gathered and discussed.
3.4.7.4 Biodiversity Status
This section discuses the ecological status of biota for the Pawan Formalin Pvt. Ltd. The
baseline status of biota (plant and animals) discussed at various site-specific as well as
habitat specific.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.25
3.4.7.4.1 Floral Status
Within the sample plots of the study areas, a total of 130 plant species belong to 112 genera
and 53 families were recorded. In addition, dicotyledons are dominant plant group and
representated by 118 species (90.77%) (Table 3.4.4). In addition, maximum species (102
Nos.) were recorded from agriculture and road side habitat and followed by
wasteland/gauchar habitat (87 species), forest/open scrub habitat (79 species) and
riverine/wetland/nallah areas (45 species) (Table 3.4.12).
Table 3.4.4. Taxonomic Status of plant species: Pawan Formalin Pvt. Ltd.
Taxonomical status Dicotyledons Monocotyledons Overall
Families 48 5 53
Genera 101 11 112
Species 118 12 130
Relative % 90.77 % 9.23 % 100 %
Status of Life form
Study area reported 130 plant species and they formed 14 sub-categories of lifeforms
within five main categories. Among the life forms, herb was dominated by recording 50
species and contributed maximum of 38.46% of the total list of plants followed by trees (36
species and 27.69%). Third dominating life form was shrub species (25) and shared
19.23%. The contribution other life forms was less than 10% of the species list (Table
3.4.5).
Table 3.4.5. Life form Status of plant species: Pawan Formalin Pvt. Ltd.
Life Form Nos. Relative %
Herb Aquatic Herb 1
50 38.46 Herb 49
Grass Grass 8 9 6.92
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.26
Life Form Nos. Relative %
Sedge 1
Climber Climber 6
10 7.69 Parasite 1
Twiner 2
Woody Twiner 1
Shrub Sarmentose Shrub 1
25 19.23 Shrub 13
Straggling Shrub 4
Under Shrub 7
Tree Tree 29 36 27.69
Small Tree 7
TOTAL 130 130 100.00
Common/Domestic Tree species
Only 11 common tree species were identified with a total of 36 trees within the sample plots of the
study area. Among the species, Acacia nilotica, Azadirachta indica and Leucaena latisiliqua was
enumerated maximum times in and around the settlement areas (Table 3.4.6 & Table 3.4.12).
Table 3.4.6. Common Tree species: Pawan Formalin Pvt. Ltd.
Sr.No Species Name Local Name Habit Family
1 Acacia nilotica (L.) Del. subsp. indica(Bth.) Brenan
Deshi Baval, Bavar Tree Mimosaceae
2 Ailanthus excelsa Roxb. MotoArduso Tree Simaroubaceae
3 Albizia lebbeck (L.) Bth. Karo Sirish Tree Mimosaceae
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.27
Sr.No Species Name Local Name Habit Family
4 Azadirachta indica A. Juss. Limbdo, Neem Tree Meliaceae
5 Derris indica (Lam.) Bennet Karanj Tree Fabaceae
6 Eucalyptus globulus Labill. Nilgiri Tree Myrtaceae
7 Ficus benghalensis L. Vad Tree Moraceae
8 Ficus religiosa L. Piparo, Piplo Tree Moraceae
9 Leucaena latisiliqua (L.) Wt. & Arn. Liso Bavar Tree Mimosaceae
10 Peltophorum pterocarpum (DC.) Backer ex Heyne Tamrafali Tree Caesalpiniaceae
11 Polyalthia longifolia (Sonn.) Thw. Asopalav Tree Annonaceae
Wild/Forest Tree Species
Within the study area only 4 wild/forest tree species have been recorded which were belonging to
4 families and 4 genera. Since the area are dominant with agriculture habitat, and hence, very few
trees were recorded under this category (Table 3.4.7 & Table 3.4.12) and it indicates low
density of wild tree species in and around the study area.
Table 3.4.7. Wild/Forest Tree species: Pawan Formalin Pvt. Ltd.
Sr.No Species Name Local Name Habit Family
1 Balanites aegyptiaca (L.) Del. Hingor, Ingoriyo
Small Tree Balanitaceae
2 Holoptelea integrifolia (Roxb.) Planch. Kanaji Tree Ulmaceae
3 Prosopis cineraria (L.) Druce Khijado Tree Mimosaceae
4 Zizyphus mauritiana Lam. Mota Bor Small Tree Rhamnaceae
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.28
Status of Agriculture Crops
Based on the intensive field survey in and around the agricultural area and dialogue with the local
farmers a total of 10 species have been listed from the study area as crop species. Fruit and
vegetable crops were found cultivated along the agricultural hedges in a small extent of area (Table
3.4.8 & Table 3.4.12). In the study area, Kapas (Gossypium herbaceum), Bajri (Pennisetum
typhoides) and Ghahun (Triticum asetivum) are the major crops cultivated extensively.
Table 3.4.8. List of Agriculture and Other Crop Species Recorded: Pawan Formalin
Pvt. Ltd.
Sr.No Species Name Local Name Habit Family Season
1 Citrus limon (L.) Burm. Limbu Small Tree Rutaceae All
2
Gossypium herbaceum auct. Non L. var. acerifolium (Guill. & Perr.) Chevalier
Kapas Shrub Malvaceae
Monsoon
3 Momordica charantia L. Karela Climber Cucurbitaceae All
4
Pennisetum typhoides A. Rich.
Bajri, Bajaro Grass Poaceae
Summer
Monsoon
5 Through Interviewed Ghahun Grass Poaceae Winter
6 Through Interviewed Tal Herb Pedaliaceae Monsoon
7 Through Interviewed Mag Phali Herb Fabaceae Monsoon
8 Through Interviewed Jovar Herb Poaceae Monsoon
9 Through Interviewed Jiru Herb Apiaceae Winter
10 Through Interviewed Variari Herb Apiaceae Winter
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.29
3.4.7.4.2 Faunal Status
Herpetofauna
The buffer zone area covering 5 km radius reported overall 7 species belong to 7 genus and 6
families. Within the buffer zone, among the habitats types maximum of five species were enered
along the Dhavat village (discussed and collected information from local people) followed by three
species in agriculture areas and two species in other habitats (Table 3.4.9).
Table: 3.4.9.Taxonomical Status of Herpetofauna: Pawan Formalin Pvt. Ltd.
Family & Species name Common and Local Name IUCN Status
FROGS/ Ranidae
1 Euphlyctis cyanophlyctis Skittering Frog (Dedako) LR-nt
LIZARDS/ Gekkonidae
2 Hemidactylus brookii Spotted Indian House Gecko (Garodi) LR-lc
AGAMIDS/ Agamidae
3 Calotes versicolor Indian Garden Lizard (Kachindo) LR-nt
4 Sitana ponticeriana Fan-Throated Lizard (Kachindi) LR-lc
SNAKES/ Boidae
5 Eryx johnii Eastern Red Sand Boa (Dhomalo) LR-lc
SNAKES/ Colubridae
6 Ptyas mucosa Indian Rat Snake (Nag) LR-nt
TURTLES/ Trionychidae
7 Lissemys punctata Indian Mud or Flap-shell Turtle (Kachbo)
-
LR-nt- Lower risk near threatened and LR-Ic- Lower risk least concern
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.30
Birds (Terrestrial and Aquatic)
Status of terrestrial and aquatic birds was assessed during latter part of winter and summer and
reported a total of 38 species belongs to 37 genera and 31 families in the buffer zone of study area
(Table 3.4.10). Habitat specific abundance resulted more contribution was from agriculture and
habitation areas; and there is no any permanent aquatic habitat existing within it, therefore
during the study period aquatic avifauna was reported from the nearby wetland and
reservoir.
Table 3.4.10: Overall Status of Terrestrial and Aquatic Birds: Pawan Formalin Pvt.
Ltd.
S. No.
Order, Family and Species Common English Name MS Sch. FG
GALLIRORMES
Phasianidae
1 Pavo cristatus Indian Peafowl R I G
ANSERIFORMES
Anatidae
2 Sarkidiornis melanotos Comb Duck R IV A
UPUPIFORMES
Upupidae
3 Upupa epops Common Hoopoe RM IV I
CORACIIFORMES
Coraciidae
4 Coracias benghalensis Indian Roller R IV I
Alcedinidae
5 Alcedo Hercules Common Kingfisher R IV P
Dacelonidae
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.31
S. No.
Order, Family and Species Common English Name MS Sch. FG
6 Halcyon smyrnensis White-throated Kingfisher R IV P
Cerylidae
7 Ceryle rudis Lesser Pied Kingfisher R IV P
Meropidae
8 Merops orientalis Green Bee-eater R IV I
CUCULIFORMES
Cuculidae
9 Eudynamys scolopacea Asian Koel R IV F
Centropodidae
10 Centropus sinensis Greater Coucal R IV O
PSITTACIFORMES
Psittacidae
11 Psittacula krameri Rose-ringed Parakeet R IV F
APODIFORMES
Apodidae
12 Apus affinis House(Little) Swift R IV I
STEIGIFORMES
Strigidae
13 Athene brama Spotted Owlet R IV C
COLUMBIFORMES
Columbidae
14 Columba livia Rock Pigeon R IV G
15 Streptopelia tranquebarica Red-collared Dove R IV G
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.32
S. No.
Order, Family and Species Common English Name MS Sch. FG
GRUIFORMES
Rallidae
16 Gallinula chloropus Common Moorhen R IV A
17 Fulica atra Common Coot R IV A
CICONIFORMES
Scolopacidae
18 Actitis hypoleucos Common Sandpiper R IV A
Charadriidae
19 Vanellus indicus Red-wattled Lapwing R IV I
Accipitridae
20 Accipiter badius Shikra R I C
21 Circius melanoleucos Pied Harrier RM I C
Falconidae
22 Falco tinnunculus Common Kestral RM IV C
Phalacrocoracidae
23 Phalacrocorax niger Little Cormorant R IV A
Ardeidae
24 Ardea cinerea Grey Heron RM IV A
25 Bubulcus ibis Cattle Egret R IV AI
Threskiornithidae
26 Threskiornis melanocephalus Black-headed Ibis RM IV A
27 Pseudibis papillosa Black Ibis R IV I
PASSERIFORMES
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.33
S. No.
Order, Family and Species Common English Name MS Sch. FG
Corvidae
28 Corvus splendens House Crow R V I
29 Dicrurus macrocercus Black Drongo R IV I
Muscicapidae
30 Saxicoloides fulicata Indian Robin R IV I
Sturnidae
31 Acridotheres ginginianus Bank Myna R IV I
32 Acridotheres tristis Common Myna R IV I
Hirundinidae
33 Hirundo daurica Red-rump Swallow R IV I
Pycnonotidae
34 Pycnonotus cafer Red-vented Bulbul R IV I
Sylviidae
35 Turdoides malcolmi Large Grey Babbler R IV G
Alaudidae
36 Galerida cristata Crested Lark R IV GI
Nectariniidae
37 Nectarinia asiatica Purple Sunbird R IV N
Passeridae
38 Passer domesticus House Sparrow R IV G
MS= Migratory Status, M= Migratory, R= Resident, RM= Resident migratory;
Sch= Schedule as per Wildlife Protection Act 1972; and FG= Feeding Guild, O= Omnivore,
G= Granevore, P= Pisivore, C= Carnivore, I= Insectivore, A= Aquatic.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.34
Status of mammals
As discussed with local people, within buffer zone only seven species of mammalian fauna was
reported and each belongs to separate family/group. None of the family reported more than one
species and showed low species richness (Table 3.4.11). Since the study area dominated by
agriculture habitat, mammalian fauna showed low species richness.
Table 3.4.11: Overall Status of Mammals: Pawan Formalin Pvt. Ltd.
S. No. Scientific Name Species Food Habit
WPA,1972
Status
Bovidae
1 Boselaphus tragocamelus (Pallas, 1766) Nilgai Herbivore
III
Canidae
2 Canis aureus (Linnaeus, 1758) Golden Jackal Omnivore II
Herpestidae
3 Herpestes edwardsii (E.Geoffroy Saint-Hilaire,1818) Grey Mongoose Omnivore
II
Hyaenidae
4 Hyaena hyaena (Linnaeus,1758) Striped Hyena Scavenger
-
Hystricidae
5 Hystrix indica (Kerr,1792) Indian Porcupine Herbivore
-
Suidae
6 Sus scrofa (Linnaeus,1758) Wild Boar Herbivore III
Anon. 1972. The Wildlife (Protection) Act, 1972. Ammended 1991. Natraj Publication, Dehra Dun. 154 p.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.35
3.4.7.4.3 THREATENED PLANTS AND ANIMALS AND CONCLUSION NOTE
This study reported a total of 130 plant species, 7 herpetofauna, 38 birds and 6 species of
mamamals from the buffer zone of Pawan Formalin Pvt.Ltd. However, no threatened biodiversity
reported with highest density or richness from the core and buffer zones of the study area.
In general, impact prediction methods argue that the foremost step in impact appraisal must
consider and identify project actions that are likely to bring significant changes in the project
environment. The present study determined to predict the likely impacts of the project in the
surrounding environment with specific to biological attributes covering habitats/ecosystems and
associated biodiversity. But, as discussed with client authority and surveyed in and around the
project sites, there are no true multi species forest type was recorded in the vicinity of the five
kilometer radii in and around the project site. It clearly indicates the low productive potential of the
terrestrial ecosystem. Since the project associated activities do not required any land nearby
ecological sensitive areas like rivers, forest and wilderness habitats, the terrestrial ecosystem is
considerably free from the project related impacts. Therefore the proposed project activities will
not have any impacts like: loss of true forest habitat, floral species composition and overall faunal
diversity.
While considering long-term impact by proposed project areas on vegetation and biodiversity,
appropriate mitigatory measures have been suggested to improve the vegetation cover and to
minimize the impacts on floral and faunal species in and around the vicible wilderness areas of
project sites. In addition, it has been suggested to plant several local tree and shrub species (with
following important specific terams) under afforestation program to improve their abundance
status as well as wilderness areas and several characteristics to improve adjoin land to project
areas:
Tree and shrub species which are tall and bearing larger canopy cover and leaf area with
different size classes (small, medium and larger) were suggested to maintain the different
canopy levels at vertical profile.
Many fruit trees and shrubs were in the selection list to attract birds, squiral and fruit eating
bats which are locally available.
Mostaly local tree and shrub species were recommended (See following list) to provide
habitat for faunal species, increase the species diversity and maintain the naturalness.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.36
List of plant species recommended to plant and improve vegetation cover in and around the project sites
Sr.No Species Name Local Name Habit Family
1 Acacia nilotica (L.) Del. subsp. indica(Bth.) Brenan
Deshi Baval, Bavar Tree Mimosaceae
2 Azadirachta indica A. Juss. Limbdo, Neem Tree Meliaceae
3 Derris indica (Lam.) Bennet Karanj Tree Fabaceae
4 Ficus benghalensis L. Vad Tree Moraceae
5 Ficus religiosa L. Piparo, Piplo Tree Moraceae
6 Cordia dichotoma Forst. Gunda Tree Ehretiaceae
7 Cordia gharaf (Forsk.) E.&.A. Nana Gunda, Liar Gundi Tree Ehretiaceae
8 Salvadora oleoides Decne. Piludi-Mithi Shrub Salvadoraceae
9 Salvadora persica L. Piludi-Khari Shrub Salvadoraceae
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.37
Tabl
e 3.
4.12
: H
abit
at-w
ise
chec
klis
t of P
lant
Spe
cies
rec
orde
d in
and
aro
und
the
Paw
an F
orm
alin
Pvt
. Ltd
.
Sr.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
1 Ab
elm
osch
us e
scul
entu
s (L
.) M
oenc
h Bh
inda
, Bh
indo
Un
der
Shru
b M
alva
ceae
√
2 Ab
utilo
n in
dicu
m (L
.) Sw
. sub
sp. i
ndic
um
Kans
ki
Unde
r Sh
rub
Mal
vace
ae
√ √
√ √
3 Ac
acia
nilo
tica
(L.)
Del
. su
bsp.
indi
ca(B
th.)
Bren
an
Des
hi B
aval
, Ba
var
Tree
M
imos
acea
e √
√ √
√ 4
Acal
ypha
indi
ca L
. D
adar
io,
Dad
ro
Her
b Eu
phor
biac
eae
√ √
√ √
5 Ac
hyra
nthe
s asp
era
L.
var.
arge
ntea
Hoo
k. f.
An
dhed
i, An
ghed
o H
erb
Amar
anth
acea
e √
√ √
√ 6
Achy
rant
hes a
sper
a L.
va
r. po
rphy
rist
achy
a H
k.
f. An
dhed
i H
erb
Amar
anth
acea
e √
√ √
√ 7
Aerv
a pe
rsic
a (B
urm
.f.)
Mer
rill
Gora
kh G
anjo
H
erb
Amar
anth
acea
e √
√
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.38
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
8 Ai
lant
hus e
xcel
sa R
oxb.
M
otoA
rdus
o
Tree
Si
mar
ouba
ceae
√
√ 9
Albi
zia
lebb
eck
(L.)
Bth.
Ka
ro S
iris
h Tr
ee
Mim
osac
eae
√
√
10
Alte
rnan
ther
a pu
ngen
s H
. B. &
K.
Kant
aro
Bhan
garo
H
erb
Amar
anth
acea
e
√
√ 11
Al
tern
anth
era
sess
ilis
(L.)
DC.
Ja
r Bha
ji, Ja
r Bh
anga
ro
Her
b Am
aran
thac
eae
√ √
√
12
Amar
anth
us sp
inos
us L
. Ja
ngal
i ta
ndal
jo
Her
b Am
aran
thac
eae
√
√ √
13
Amm
anni
a ba
ccife
ra L
. Ra
to Ja
l Agi
o,
Lal A
gio
Her
b Ly
thra
ceae
√
14
Arge
mon
e m
exic
ana
L.
Dar
udi
Her
b Pa
pave
rcea
e √
√ √
√ 15
As
para
gus r
acem
osus
W
illd.
var
. jav
anic
us
(Kun
th) B
aker
Sa
tavr
i Sa
rmen
tos
e Sh
rub
Lilia
ceae
√
√ 16
Az
adir
acht
a in
dica
A.
Juss
. Li
mbd
o,
Nee
m
Tree
M
elia
ceae
√
√ √
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.39
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
17
Bala
nite
s aeg
yptia
ca
(L.)
Del.
Hin
gor,
Ingo
riyo
Sm
all T
ree
Bala
nita
ceae
√
√
√ 18
Be
rgia
am
man
nioi
des
Roxb
. ex
Rot
h Ja
l Ukh
arad
H
erb
Elat
inac
eae
√ √
19
Boer
havi
a el
egan
s Ch
oisy
Ud
ha S
atod
o,
Punn
arva
H
erb
Nyc
tagi
nace
ae
√
√
20
Borr
eria
art
icul
aris
(L.f.
) F.N
. Will
. -
Her
b Ru
biac
eae
√ √
21
Boug
ainv
illea
spec
tabi
lis
Wild
. -
Stra
gglin
g Sh
rub
Nyc
tagi
nace
ae
√
22
Caja
nus c
ajan
(L.)
Mill
sp.
Tuve
r H
erb
Faba
ceae
√
23
Calo
trop
is pr
ocer
a (A
it.)
R. B
r.
Akad
o Sh
rub
Ascl
epia
dace
ae
√ √
√ √
24
Capp
aris
deci
dua
(For
sk.)
Edge
w.
Ker,
Kerd
o Un
der
Shru
b Ca
ppar
acea
e √
√ √
√ 25
Ca
ppar
is se
piar
ia L
. Ka
nthe
r St
ragg
ling
Capp
arac
eae
√ √
√ √
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.40
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
Shru
b
26
Caps
icum
ann
uum
L.
Mar
chi
Her
b So
lana
ceae
√
27
Card
iosp
erm
um
halic
acab
um L
. Ka
g D
oriy
u H
erb
Sapi
ndac
eae
√ √
28
Cari
ca p
apay
a L.
Pa
paya
, Pa
payu
Tr
ee
Cari
cace
ae
√
29
Cass
ia a
uric
ulat
a L.
Av
ar, A
val,
Aval
i Sh
rub
Caes
alpi
niac
eae
√
√ √
30
Cass
ia fi
stul
aL.
Garm
aro
Tree
Ca
esal
pini
acea
e
√ √
√ 31
Ca
ssia
occ
iden
talis
L.
Sund
aro,
Ka
sund
ro
Her
b Ca
esal
pini
acea
e √
√
√ 32
Ca
ssia
siam
ea L
am.
Kasi
d Tr
ee
Caes
alpi
niac
eae
√
√
33
Cass
ia to
ra L
. Ku
nwar
io
Her
b Ca
esal
pini
acea
e √
√
√ 34
Ca
yrat
ia ca
rnos
a (L
am.)
Gagn
ep.
Khat
Kh
atub
ado
Clim
ber
Vita
ceae
√
√
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.41
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
35
Celo
sia a
rgen
tea
L.
Lam
padi
, La
mpd
i H
erb
Amar
anth
acea
e √
√
36
Cenc
hrus
bifl
orus
auc
t. D
ham
an,
Anja
n Gr
ass
Poac
eae
√ √
√
37
Citr
us li
mon
(L.)
Burm
. Li
mbu
Sm
all T
ree
Ruta
ceae
√
38
Cleo
me
gyna
ndra
L. v
ar.
gyna
ndra
Gh
andh
atu
Her
b Ca
ppar
acea
e
√
39
Cler
oden
drum
iner
me
(L.)
Gaer
tn.
Vad
Men
dhi
Her
b Ve
rben
acea
e
√
40
Cler
oden
drum
m
ultif
loru
m (B
urm
.f.) O
. Ar
ni
Smal
l Tre
e Ve
rben
acea
e
√
41
Cocc
inia
gra
ndis
(L.)
Voig
t Ti
ndor
a,
Ghilo
da
Clim
ber
Cucu
rbita
ceae
√
√
√ 42
Co
ccul
us h
irsu
tus (
L.)
Die
ls
Vevd
i, Ve
vti
Stra
gglin
g Sh
rub
Men
ispe
rmac
eae
√ √
√
43
Cocu
s nuc
ifera
L.
Nar
iyer
Tr
ee
Arec
acea
e
√
√
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.42
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
44
Cold
enia
pro
cum
bens
L.
Ukha
rad
Her
b Bo
ragi
nace
ae
√
45
Conv
olvu
lus
mic
roph
yllu
s (Ro
th)
Sieb
. ex
Spr.
Dho
li Sa
nkha
vali
Her
b Co
nvol
vula
ceae
√
√
√ 46
Co
rcho
rus a
estu
ans L
. Ka
g Sh
ing,
Ch
unch
, Ch
hadh
ari
Her
b Ti
liace
ae
√ √
√
47
Cord
ia d
icho
tom
a Fo
rst.
Gund
a Tr
ee
Ehre
tiace
ae
√
√
48
Cord
ia g
hara
f (Fo
rsk.
) E.
&.A
. N
ana
Gund
a,
Liar
Gun
di
Tree
Eh
retia
ceae
√
√ 49
Cu
cum
is ca
llosu
s (Ro
ttl.)
Co
gn.
Gay
Vasu
kada
Cl
imbe
r Cu
curb
itace
ae
√ √
√
50
Cucu
mis
prop
heta
rum
L.
Kant
alo
Indr
anan
Cl
imbe
r Cu
curb
itace
ae
√ √
√
51
Cusc
uta
refle
xa R
oxb.
Am
arve
l Pa
rasi
te
Cusc
utac
eae
√ √
√
52
Cyno
don
dact
ylon
(L.)
Pers
. D
hrab
Gr
ass
Poac
eae
√ √
√ √
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.43
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
53
Cype
rus r
otun
dus L
. su
bsp.
rotu
ndus
Ch
iyo,
Mot
h Se
dge
Cype
race
ae
√ √
√ √
54
Dact
yloc
teni
um
aegy
ptic
um (L
.) P.
Be
auv.
-
Gras
s Po
acea
e √
√
55
Dalb
ergi
a sis
soo
Roxb
. Si
sam
Tr
ee
Faba
ceae
√
56
Datu
ra m
etel
L.
Dha
turo
Un
der
Shru
b So
lana
ceae
√
√
√ 57
De
loni
x re
gia
(Boj
.) Ra
f. Gu
lmoh
or
Tree
Ca
esal
pini
acea
e
√
58
Derr
is in
dica
(Lam
.) Be
nnet
Ka
ranj
Tr
ee
Faba
ceae
√
59
Dige
ra m
uric
ata
(L.)
Mar
t. Ka
njar
o,
Kane
jro
Her
b Am
aran
thac
eae
√ √
√
60
Dipt
erac
anth
us
pros
trat
us H
assk
. -
Her
b Ac
anth
acea
e √
√
61
Echi
noch
loa
colo
num
(L
.) Li
nk
Sam
o, Ji
riu
Gras
s Po
acea
e √
√
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.44
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
62
Echi
nops
ech
inat
us
Roxb
. Ut
kant
o Un
der
Shru
b As
tera
ceae
√
√
√ 63
Ec
lipta
pro
stra
ta (L
.) L.
M
ant.
Jal B
hang
ro
Her
b As
tera
ceae
√
√ √
√ 64
Eu
caly
ptus
glo
bulu
s La
bill.
N
ilgir
i Tr
ee
Myr
tace
ae
√
√
65
Euph
orbi
a hi
rta
L.
Dud
heli
Her
b Eu
phor
biac
eae
√ √
√
66
Euph
orbi
a ni
vulia
Bu
ch.-
Ham
. Va
d Th
or
Shru
b Eu
phor
biac
eae
√
√
67
Euph
orbi
a th
ymifo
lia L
. Sa
ni D
udhe
li H
erb
Euph
orbi
acea
e √
√
√ 68
Ev
olvu
lus a
lsino
ides
(L.)
L. v
ar. a
lsino
ides
Ka
ri
Sank
hava
il H
erb
Conv
olvu
lace
ae
√ √
√
69
Ficu
s ben
ghal
ensis
L.
Vad
Tree
M
orac
eae
√
√
70
Ficu
s rel
igio
sa L
. Pi
paro
, Pip
lo
Tree
M
orac
eae
√
√
71
Glin
us lo
toid
es L
. Ok
hara
d H
erb
Mol
lugi
nace
ae
√
√ √
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.45
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
72
Goss
ypiu
m h
erba
ceum
au
ct. N
on L
. var
. ac
erifo
lium
(Gui
ll. &
Pe
rr.)
Chev
alie
r
Kapa
s Sh
rub
Mal
vace
ae
√
73
Gran
gea
mad
eras
pata
na (L
.) Po
ir.
- H
erb
Aste
race
ae
√
√ √
74
Hel
iotr
opiu
m in
dicu
m L
. H
athi
Sun
dhi
Her
b Bo
ragi
nace
ae
√
√
75
Hel
iotr
opiu
m
oval
ifoliu
m F
orsk
. -
Her
b Bo
ragi
nace
ae
√ √
√ √
76
Hib
iscus
rosa
-sin
ensis
L.
Jasu
nd,
Jasv
anti
Shru
b M
alva
ceae
√ 77
H
olop
tele
a in
tegr
ifolia
(R
oxb.
) Pla
nch.
Ka
naji
Tree
Ul
mac
eae
√ √
√
78
Indi
gofe
ra li
nnae
i Ali.
Bh
onyg
ali
Her
b Fa
bace
ae
√ √
√
79
Ipom
oea
aqua
tica
Fors
k.
Nal
i Ni B
haji
Aqua
tic
Her
b Co
nvol
vula
ceae
√
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.46
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
80
Ipom
oea
fistu
losa
Mar
t. -
Stra
gglin
g Sh
rub
Conv
olvu
lace
ae
√ √
√ √
81
Kirg
anel
ia re
ticul
ata
(Poi
r.) B
aill.
Ka
mbo
i Sh
rub
Euph
orbi
acea
e
√
√ 82
La
unae
a pr
ocum
bens
(R
oxb.
) Ram
. & R
aj.
Mot
i Bho
yan
Patr
i H
erb
Aste
race
ae
√ √
√
83
Leuc
aena
latis
iliqu
a (L
.) W
t. &
Arn
. Li
so B
avar
Tr
ee
Mim
osac
eae
√
√
84
Lim
onia
aci
diss
ima
L.
Koth
i, Ko
tha
Tree
Ru
tace
ae
√
85
Lyco
pers
icon
ly
cope
rsic
um (L
.) Ka
rst.
Tam
ata,
Ta
mat
u H
erb
Sola
nace
ae
√
√
86
Mae
rua
oblo
ngifo
lia
(Foe
ak.)
A. R
ich.
H
emka
nd
Woo
dy
Twin
er
Capp
arac
eae
√ √
√
87
Man
gife
ra in
dica
L.
Ambo
, Ker
i Tr
ee
Anac
ardi
acea
e
√
88
Man
ilkar
a za
pota
(L.)
Van
Roye
n Ch
iku
Tree
Sa
pota
ceae
√
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.47
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
89
Mel
ia a
zeda
rach
L.
Baka
ni N
im,
Baka
nlim
do
Tree
M
elia
ceae
√
√ 90
M
ukia
mad
eres
pate
nsis
(L.)
M. R
oem
. An
khfu
tman
i Cl
imbe
r Cu
curb
itace
ae
√
√
91
Mur
raya
koe
nigi
i (L.
) Sp
r. M
itho
Lim
ado
Smal
l Tre
e Ru
tace
ae
√
√
92
Ner
ium
indi
cum
Mill
. La
l Kar
en
Shru
b Ap
ocyn
acea
e
√ 93
Oc
imum
San
ctum
L.
Tuls
i H
erb
Lam
iace
ae
√
94
Pelto
phor
um
pter
ocar
pum
(DC.
) Ba
cker
ex
Hey
ne
Tam
rafa
li Tr
ee
Caes
alpi
niac
eae
√
√
95
Penn
isetu
m ty
phoi
des A
. Ri
ch.
Bajr
i, Ba
jaro
Gr
ass
Poac
eae
√
96
Perg
ular
ia d
aem
ia
(For
sk.)
Chio
v.
Cham
ar
Dud
heli
Twin
er
Ascl
epia
dace
ae
√ √
√ √
97
Phyl
lant
hus f
rate
rnus
W
ebst
. Bh
oyan
Ri
ngan
i, H
erb
Euph
orbi
acea
e √
√ √
√
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.48
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
Bhon
ya A
mli
98
Poly
alth
ia lo
ngifo
lia
(Son
n.) T
hw.
Asop
alav
Tr
ee
Anno
nace
ae
√
√
99
Port
ulac
a qu
adri
fida
L.
Pat L
uni,
Zini
luni
H
erb
Port
ulac
acea
e √
√
100
Pros
opis
cine
rari
a (L
.) D
ruce
Kh
ijado
Tr
ee
Mim
osac
eae
√ √
√ √
101
Pros
opis
julif
lora
(Sw
.) D
C.
Gand
o Ba
val
Shru
b M
imos
acea
e √
√ √
√ 10
2 Pu
nica
gra
natu
m L
. D
adam
Sm
all T
ree
Puni
cace
ae
√
√
103
Rhyn
chos
ia m
inim
a (L
.) D
C. v
ar. m
inim
a N
ahni
Kam
al
Vel
Twin
er
Faba
ceae
√
√
√ 10
4 Ri
cinu
s com
mun
is L.
D
ivel
a,
Aran
da
Shru
b Eu
phor
biac
eae
√
105
Sacc
haru
m sp
. Ka
ns,
Dab
hado
Gr
ass
Poac
eae
√
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.49
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
106
Sacc
haru
m sp
onta
neum
L.
D
abh,
Kan
s Gr
ass
Poac
eae
√
√
107
Salv
ador
a ol
eoid
es
Dec
ne.
Pilu
di-M
ithi
Shru
b Sa
lvad
orac
eae
√ √
√ √
108
Salv
ador
a pe
rsic
a L.
Pi
ludi
-Kha
ri
Shru
b Sa
lvad
orac
eae
√ √
√ √
109
Sesb
ania
sesb
an (L
.) M
eer.
subs
p. se
sban
var
. se
sban
Ek
ad, S
heva
ri
Shru
b Fa
bace
ae
√
110
Sida
ova
ta F
orsk
. -
Her
b M
alva
ceae
√
√
√ 11
1 So
lanu
m su
ratt
ense
Bu
rm. f
. Bh
oyan
Ri
ngan
i H
erb
Sola
nace
ae
√ √
√
112
Sonc
hus a
sper
(L.)
Hill
. So
n Ch
udi
Her
b As
tera
ceae
√
√
113
Sorg
hum
hal
epen
se (L
.) Pe
rs.
Jang
li Ju
war
, Ba
ru
Gras
s Po
acea
e √
√
√ 11
4 Sy
zygi
um cu
min
i (L.
) Sk
ells
Ja
mbu
Tr
ee
Myr
tace
ae
√
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.50
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
115
Tam
arin
dus i
ndic
a L.
Am
bali,
Em
ali
Tree
Ca
esal
pini
acea
e
√
√ 11
6 Te
com
a st
ans (
L.) H
. B.
& K
. Pi
li N
im
Shru
b Bi
gnon
iace
ae
√
117
Tect
ona
gran
dis L
.f.
Sag
Tree
Ve
rben
acea
e
√ 11
8 Te
phro
sia p
urpu
rea
(L.)
Pers
. Sa
rpan
kho
Her
b Fa
bace
ae
√
√ √
119
Term
inal
ia ca
tapp
a L.
D
esi B
adam
Tr
ee
Com
bert
acea
e
√
√ 12
0 Th
espe
sia p
opul
nea
(L.)
Sol.
ex C
orr.
Pa
ras P
impr
o Sm
all T
ree
Mal
vace
ae
√
√
121
Tino
spor
a co
rdifo
lia
(Will
d.) M
iers
Ga
ro
Clim
ber
Men
ispe
rmac
eae
√ √
122
Trib
ulus
terr
estr
is L.
Go
khar
u H
erb
Zygo
phyl
lace
ae
√ √
√
123
Tric
hode
sma
ampl
exic
aule
Rot
h Un
dha
Fuli
Her
b Bo
ragi
nace
ae
√ √
124
Trid
ax p
rocu
mbe
nsi L
. Pa
rdes
hi
Her
b As
tera
ceae
√
√
√
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
M
/s. T
.R.A
ssoc
iate
s
3.
4.51
Sr
.
No
Spec
ies
Nam
e Lo
cal N
ame
Hab
it
Fam
ily
Hab
itat
Fore
st
/
Ope
n
Scru
b
Agri
cult
ure
Hed
ge/
Roa
d si
de
Riv
erin
e
/
wet
land
/Nal
lah
Was
tela
nd
/
Gauc
har
Bhan
gro
125
Triu
mfe
tta
rhom
boid
ea
Jacq
. Zi
pti
Unde
r Sh
rub
Tilia
ceae
√
√
√ 12
6 Ty
pha
angu
stat
a Bo
ry.
& C
haub
. Gh
a Ba
jari
u H
erb
Typh
acea
e √
√
127
With
ania
som
nife
ra (L
.) Ku
rz
Ashw
agan
dha
Unde
r Sh
rub
Sola
nace
ae
√ √
128
Xant
hium
stru
mar
ium
L.
Gada
riyu
H
erb
Aste
race
ae
√
√ √
129
Zale
ya re
dim
ita
(Mel
ville
) Bha
ndar
i var
. re
dim
ita
Beth
i Sat
odi
Her
b Ai
zoac
eae
√
√
130
Zizy
phus
mau
ritia
na
Lam
. M
ota
Bor
Smal
l Tre
e Rh
amna
ceae
√
√ √
√ TO
TAL
PLAN
T SP
ECIE
S R
ECO
RD
ED IN
EAC
H H
ABIT
AT
79
102
45
87
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.52
REFERENCE
Ali, S. (2002). Book of Indian Birds. Bombay Natural History Society and Oxford university
press. Thirteenth Edn.Pp. 326.
Anon. 1972. The Wildlife (Protection) Act. 1972. Amended 1991. Natraj Publication, Dehra
Dun. 154 p.
Bhandari, M. M. (1990). Flora of the Indian Desert. Scientific publishers. Jodhpur,
Rajasthan. 435 PP.
Bhupathy, S. 1991. Population and Resource Utilisattion of Waterfowl in Keoladeo National
Park, Bharatpur. Ph.D. Thesis, Rajasthan University, Jaipur.
Bibby, C.J., N.D., Burgerss and D.A. Hill. 1992b. Bird Census techniques, Academic Press,
London.
Daniels R.J.R 2005. Amphibians of Peninsular India. Universities press (India) Private
limited. First Edn. pp. 267.
Daniel J.C. 2002. The Book of Indian Reptiles and Amphibians. Bombay Natural History
Society and Oxford university press. pp. 238.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.53
Dieni, J.S. and jones, S.L. 2002. A field test of the area search method for measuring
breeding birds population, J. Field Ornithology, 73: 253-257.
Grimmett, R., Inskipp, C., Inskipp, T., 2006. Birds of the Indian Subcontinent. Oxford
University Press. New Delhi. Pp. 384.
Hocking D. (ed) 1983. Trees for Drylands. Oxford and IBH Publication Co Pvt Ltd. –New
Delhi. Pp 370.
Hutto, R.L., S.M. Pletsechel and P. Hendrick. 1986. A fixed radius point method for non
breeding season use. The Auk. 103: 593-602.
IUCN . 2000. Red List of Threatened Species. Species Survival Commission (SSC) IUCN,
Gland, Switzerland.
Kershaw, A.S. 1973. Sampling test of Comparison and application of quadrate measures
Pp: 21-39. In: Quantitative and Dynamic Plant Ecology. Second edition. William
Clowes and Sons Limited, London.
Molur, s and S. Walker 1998. Report of the workshop “Conservation Assessment and Management Plan for reptiles of India” (BCPP – Endangered species Project), Zoo
Outreach Organization, Conservation Breeding Specialist Group, India, Coimbatore,
India 175 pp.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.54
Molur S and S Walker (eds). 1998. Report of the Workshop “Conservation Assessment and Management Plan – CAMP for Mammals of India, (BCPP - Endangered Species
Project, Zoo Outreach Organisation, Conservation Breeding Specialist Group, India,
Coimbatore, India, 176 P.
Mueller-Dombois, D and H. Ellensberg. 1967. Aims and Methods of Vegetation Ecology.
John Wiley& Sons, New York.545.p.
Prater. S. H. (2005). The Book of Indian Animals. Bombay Natural History Society and
Oxford University press 12th Edn. pp. 316.
Ravi Chellam., Joshua, J., Williams, C.A. and Johnsingh A.J.T. 1994. Survey of potential
site for re-introduction of Asiatic Lions. Final Report. Wildlife Institute of India , 39
pp.
Rodgers, W.A. 1991. Technique for Wildlife Census in India, A field Manual. Technical
Manual. TM2. Wildlife Institute of India, Dehra Dun. India.81pp.
Sabnis, S.D and K.S. Rao 1983. Rare and Endangered Endemics of South Eastern Kutch. Pp
: 71-77. In: Assessment of Threatened Plants of India. S.K. Jain and R.R. Rao (eds).
Botanical Survey of India.
Sale, J.B. and K. Berkmuller, 1988. Manual of Wildlife Techniques for India. FAO, United Nation’s India Establishment of Wildlife Institute of India Dehra Dun.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
M/s. T.R.Associates 3.4.55
Shah, G. L. 1978. Flora of Gujarat State. University Press, Sardar Patel University. Vallabh
Vidyanagar.174 PP.
Singh, H.S. 2001. National Heritage of Gujarat. GEER foundation, Gandhinagar. 262.Pp.
WCMC 1994. Status Report as of 24th November 1994. Gujarat Print out from plant
database. BG-BASE World Conservation Monitoring Center, Cambridge. Chapman
and Hall, London.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.1
3.5. SOCIO ECONOMIC ENVIRONMENT
3.5.1 Introduction
Development of projects goes hand in hand with environmental impact and hence before
any project is undertaken the damages in relation to the benefits should be measured.
Unfortunately environmental issues are interdisciplinary, interactive, biological and
probabilistic and because the information is always deficient, the outcome has a
considerable degree of uncertainty or risk. This conflict between development and
conservation is difficult to reconcile. Environmental baseline, ecological reconnaissance
and environmental impact studies provide databases and quantitative assessment of
environmental factors related to development projects.
Any developmental activity will influence the socioeconomic conditions of the population
in the region and thus the Quality of Life (QOL). Socioeconomic survey is necessary in
EIA/EMP report preparation to predict the changes on social and economic status. Hence
baseline data for demographic characteristics, education, health, amenities and sensitive
locations existing in and around the project area have been studied in the study area. For
the study of socioeconomics 10 km radius around the site is selected.
The study area is an industrial base for sectors such as textiles, drugs, chemicals,
pharmaceuticals and agro and food processing industries. The most important sectors are
the Chemicals industries. The major language is Guajarati, Hindi and English with a
conglomeration of different cultures like Hindus, Muslims and the Christians. It is the
centre of Gujarati cultural activities and diverse traditions of different ethnic and religious
communities.
3.5.2 Socioeconomics
Village/town wise population, households, Occupation and Literacy status have been
collected based on Census, 2011 in the following aspects
1. Total population 08. Total worker females (main + marginal)
2. Population (0-6 years) 09. Main workers (Persons)
3. Literacy rate (Persons) 10. Marginal workers (Persons)
4. Literacy rate (Males) 11. Main workers (Persons)
5. Literacy rate (Females) 12. Non workers (Persons)
6. Total worker persons (main + marginal) 13. Non workers (Males)
7. Total worker males (main + marginal) 14. Non workers (Females)
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.2
3.5.2.1 Households A 'household' is usually a group of persons who normally live together and take their meals
from a common kitchen unless the exigencies of work prevent any of them from doing so.
Persons in a household may be related or unrelated or a mix of both. However, if a group of
unrelated persons live in a census house but do not take their meals from the common
kitchen, then they are not constituent of a common household. Each such person was to be
treated as separate households. The important link is finding out whether it was a
household or not was a common kitchen. There may be one member households, two
member households or multi-member households.
There are nearly households are found in the study area. The list of Households is
given in Table 3.5.1.
3.5.2.2 Population
Village/ town wise population composition as per 2011 census is listed in Table 3.5.1. The
male and female population is 39857 and 36351 respectively. The SC and ST population
from the total population is 11.60 and 2.44 % respectively.
The summarized data of population distribution is given in Table 3.5.1 and represented in
Fig 3.5.1.
Table 3.5.1 Population Composition
Population
299 1802 934 868 116 62 54 0 0 0
819 4228 2174 2054 113 61 52 0 0 0
461 2535 1229 1306 167 78 89 0 0 0
1564 7312 3983 3329 1218 660 558 327 191 136
1523 7605 4050 3555 1217 649 568 168 92 76
229 1169 596 573 0 0 0 52 30 22
704 4217 2205 2012 276 145 131 0 0 0
271 1440 730 710 66 39 27 0 0 0
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.3
103 568 285 283 5 4 1 0 0 0
139 731 373 358 67 36 31 8 3 5
182 1102 562 540 0 0 0 0 0 0
1008 4358 2352 2006 390 204 186 521 289 232
283 1669 829 840 22 14 8 0 0 0
3428 16637 8732 7905 2903 1535 1368 212 114 98
362 1852 951 901 284 153 131 0 0 0
87 445 229 216 0 0 0 0 0 0
98 520 270 250 0 0 0 0 0 0
151 671 360 311 165 88 77 31 13 18
136 754 415 339 0 0 0 26 14 12
593 3037 1555 1482 125 63 62 211 99 112
171 897 476 421 37 21 16 0 0 0
631 3165 1660 1505 554 294 260 36 20 16
1663 8041 4179 3862 1011 514 497 272 135 137
274 1453 728 725 101 53 48 0 0 0
*As per 2011 census data.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.4
Fig 3.5.1 Percentage of Population distribution 3.5.2.3 Occupational structure
Work is defined as participation in any economically productive activity with or without
compensation, wages or profit. Such participation may be physical and/or mental in nature.
Work involves not only actual work but also includes effective supervision and direction of
work. It even includes part time help or unpaid work on farm, family enterprise or in any
other economic activity. All persons engaged in 'work' as defined above are workers.
Persons who are engaged in cultivation or milk production even solely for domestic
consumption are also treated as workers. Occupational structure is divided in to 3
categories viz., Main workers, Marginal workers and Non workers.
The distribution data for workers and non workers is given in Table 3.5.2 and Fig 3.5.2.
Main workers: Those workers who had worked for the major part of the reference period
(i.e. 6 months or more) are termed as Main Workers. There are 28758 total main workers in
this area.
Marginal workers: Those workers who have not worked for the major point of the
reference period (i.e. less than 6 months) are termed as marginal workers. The total
marginal workers are 2214.
Non workers: All workers, i.e., those who have been engaged in some economic activity
during the last one-year, but are not cultivators or agricultural laborers or in Household
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.5
Industry, are 'Other-Workers (OW)'. The type of workers that come under this category of
'OW' include all government servants, municipal employees, teachers, factory workers,
plantation workers, those engaged in trade, commerce, business, transport banking,
mining, construction, political or social work, priests, entertainment artists, etc. In effect, all
those workers other than cultivators or agricultural laborers or household industry
workers are other workers. The total Non workers are 45236.
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
MM/s
. T.R
.Ass
ocia
tes
3
.5.6
Tabl
e 3.
5.2
Occ
upat
iona
l Str
uctu
re
No.
N
ame
Tota
l Wor
kers
M
ain
Wor
kers
M
argi
nal W
orke
rs
Non
Wor
kers
T M
F
T M
F
T M
F
T M
F
1 SA
NAL
A 88
5 47
5 41
0 87
2 47
4 39
8 13
1
12
917
459
458
2 LI
LAPU
R 21
61
1337
82
4 20
34
1306
72
8 12
7 31
96
20
67
837
1230
3
JOD
HPA
R 13
83
772
611
1089
68
9 40
0 29
4 83
21
1 11
52
457
695
4 JA
MBU
DIY
A 27
83
2246
53
7 26
98
2191
50
7 85
55
30
45
29
1737
27
92
5 M
AKAN
SAR
3140
24
19
721
3008
23
23
685
132
96
36
4465
16
31
2834
6
SART
ANPA
R 52
9 34
2 18
7 42
8 33
8 90
10
1 4
97
640
254
386
7 PA
NEL
I 18
80
1272
60
8 17
97
1221
57
6 83
51
32
23
37
933
1404
8
RATA
VIRD
A 56
2 41
1 15
1 54
4 40
2 14
2 18
9
9 87
8 31
9 55
9 9
GID
ACH
21
5 17
0 45
20
4 16
7 37
11
3
8 35
3 11
5 23
8 10
KA
LIKA
NAG
AR
332
215
117
223
208
15
109
7 10
2 39
9 15
8 24
1 11
LA
KHD
HIR
PUR
356
319
37
339
311
28
17
8 9
746
243
503
12
LALP
UR
1784
14
10
374
1683
13
81
302
101
29
72
2574
94
2 16
32
13
SOM
ALPA
R 85
8 47
3 38
5 85
7 47
2 38
5 1
1 0
811
356
455
14
TRAJ
PAR
5872
50
78
794
5529
48
34
695
343
244
99
1076
5 36
54
7111
15
BH
ADIY
AD
662
547
115
646
533
113
16
14
2 11
90
404
786
16
MAD
HPA
R 17
0 13
4 36
16
9 13
4 35
1
0 1
275
95
180
17
NAV
AGAM
30
1 15
4 14
7 15
2 14
1 11
14
9 13
13
6 21
9 11
6 10
3 18
GU
ND
A 47
3 26
5 20
8 26
6 22
4 42
20
7 41
16
6 19
8 95
10
3
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
MM/s
. T.R
.Ass
ocia
tes
3
.5.7
19
ADEP
AR
296
253
43
293
250
43
3 3
0 45
8 16
2 29
6 20
D
HUV
A 10
35
825
210
934
813
121
101
12
89
2002
73
0 12
72
21
AMRE
LI
369
300
69
369
300
69
0 0
0 52
8 17
6 35
2 22
PI
PLI
1224
10
04
220
1089
95
5 13
4 13
5 49
86
19
41
656
1285
23
GH
UNTU
30
21
2543
47
8 28
69
2473
39
6 15
2 70
82
50
20
1636
33
84
24
UNCH
I MAN
DAL
68
1 40
5 27
6 66
6 40
4 26
2 15
1
14
772
323
449
To
tal
3097
2 23
369
7603
28
758
2254
4 62
14
2214
82
5 13
89
4523
6 16
488
2874
8
*As p
er 2
011
cens
us d
ata.
Fi
g 3.
5.2
Dis
trib
utio
n of
Wor
kers
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.8
3.5.2.4 Literacy
A person aged 7 years and above who can both read and write with understanding any
language has been taken as literate. It is not necessary for a person to have received any
formal education or passed any minimum educational standard for being treated as
literate. People who were blind and could read in Braille are treated to be literates. A
person, who can only read but cannot write, is treated as illiterate. All children of age 6
years or less, even if going to school and have picked up reading and writing, are treated as
illiterates.
The total number of literates and illiterates are 47052 and 29156 respectively (Table 3.5.3
and Fig.3.5.3).
Table 3.5.3 Literacy status
No. Name Lit Ilit
Total Male Female Total Male Female
1 SANALA 856 540 316 946 394 552 2 LILAPUR 2798 1559 1239 1430 615 815 3 JODHPAR 1778 964 814 757 265 492 4 JAMBUDIYA 4208 2637 1571 3104 1346 1758 5 MAKANSAR 4183 2533 1650 3422 1517 1905 6 SARTANPAR 669 411 258 500 185 315 7 PANELI 2413 1487 926 1804 718 1086 8 RATAVIRDA 680 438 242 760 292 468 9 GIDACH 296 177 119 272 108 164
10 KALIKANAGAR 476 284 192 255 89 166 11 LAKHDHIRPUR 620 364 256 482 198 284 12 LALPUR 2813 1700 1113 1545 652 893 13 SOMALPAR 792 475 317 877 354 523 14 TRAJPAR 11020 6427 4593 5617 2305 3312 15 BHADIYAD 1179 703 476 673 248 425 16 MADHPAR 348 188 160 97 41 56 17 NAVAGAM 344 210 134 176 60 116
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.9
18 GUNDA 429 259 170 242 101 141 19 ADEPAR 484 312 172 270 103 167 20 DHUVA 1528 918 610 1509 637 872 21 AMRELI 628 366 262 269 110 159 22 PIPLI 2239 1273 966 926 387 539 23 GHUNTU 5332 3100 2232 2709 1079 1630 24 UNCHI MANDAL 939 531 408 514 197 317
*As per 2011 census data.
Fig 3.5.3 Literacy levels 3.5.3 Amenities
Education, Medical, Water availability, Post & Telegraph, Communication, Banking facilities
and Power supply are considered for the study. Village wise list of amenities are given in
table 3.5.4 (as per 2001 Census).
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.10
Table 3.5.4 Amenities (Educational facilities)
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.11
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.12
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.13
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.14
*As per 2001 census data Drinking Water: T -Tap Water TK -Tank Water TW -Tube Well Water HP -Hand Pump R -River Water O -others W -well water C -Canal L -Lake Educational: P -Primary School C -College M -Middle school H -High School PUC -senior secondary school S - Higher secondary school Medical: H -Allopathic Hospital PHC -Primary Health Center PHS -Primary Health Sub-Center CHW -Community Health Worker
Transportation: BS-Bus RS-Railway Station
Approach to Village: PR-Paved Road MR-Mud Road FP-Foot Path
Power Supply: EA-Electricity for all purposes
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.15
MCW -Maternity & Child Welfare FWC -Family welfare center D -Dispensary H -Hospital HD -Homeopathic Dispensary TB -T.B.Clinic Post, Telegraph and Telephone: PO -Post Office PH -Telephone Connection 3.5.4 Site Specific Studies
The following site specific studies were been conducted in order to study the present Socio-
Economic conditions prevailing around the plant site for the establishment of an
interactive environment between the residents of the area with the proponent which
would be helpful for the proponent for the assessment of the required developments of the
area.
This study was done by looking and maintaining a good understanding of that locality as
well as their socio-Economic status which can help in the assessment of their Socio-
Economic status, Costumes, Requirements for the development etc. For such benefits the
following site study has been conducted.
3.5.5 List of Industries
The study area is an industrial base for sectors such as textiles, drugs, chemicals,
pharmaceuticals and agro and food processing industries. The most important sectors of
investment and employment are the Textile and Chemicals industries. The study area also
has small scale industries which generates employment to a large number of people.
Engineering, chemical, textiles, and paper products are the chief small scale industry
sectors present. List of industries with in the 10 km radius are as follows.
Sr. No. Name of nearby industry 1. Sober Ceramic 2. Starware Ceramic 3. Vinod Industries 4. Dell Ceramic 5. Regal Sanitary 6. Comet Vitrified
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.16
7. Neelkanth Sanitary 8. Anand Papermill 9. Boss Sanitary
10. Lion Roofing 11. Prapat roofing 12. Hari enterprise 13. Nobel Industries 14. Bhavna Industries
Fig. 3.5.4 Google image showing nearby industries
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.17
3.5.6 Culture
It is the centre of Gujarati cultural activities and diverse traditions of different ethnic and
religious communities. Popular celebrations and observances include Uttarayan - Kite
festival and Navaratri with people performing Garba - folk dance of the state of Gujarat.
People in the area are known for their specialty of folk art such as embroidery work.
Although there is a diverse tradition the locality is not found to be affected due to the
proposed plant.
3.5.7 Organization and Manpower
In any commercial manufacturing company, it is very important to have a proper
organization. This is more so in case the manufacturing involves various processes and
different technical disciplines.
M/s Pawan Formalin Pvt. Ltd is a proposed plant in Gujarat. Management control and areas
of responsibility should be well defined. Hence, for the purpose of this report, the
organization required for proposed plant, after commissioning of the new facilities, has
been considered. Manpower requirements have been assessed keeping in view the degree
of automation & computerization envisaged, minimum paper work, round the clock
operations etc.
The total requirement is 30 consisting of 25 male employees and 5 female employees for
the execution of work. The plant is located in a good industrial belt and hence it will not be
difficult to get qualified and skilled people
3.5.8 Impacts of the proposed project
The industry provided direct and indirect Employment for many of the local population. It
will create employment (30) and helps to improve the social status of the local community.
The proposed project is within the existing site hence no Rehabilitation or land acquisition
is needed for this industry. This project is not expected to generate any significant public
controversy.
Other impacts of the proposed project are:
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T.R.Associates 3.5.18
Any industrial growth will improve economic status of the people either directly or
indirectly.
Creation of employment generation is an another positive impact anticipated from
this plant
The development of infrastructure (roads, lighting etc) may not only helpful for
transportation but also to improve aesthetic value of the site.
The proposed green belt plan also generates some employment (labor for plantation
development) and provide hygienic environment.
Non- workers comprises of 42.20% of the total population in the study area. This
intense unemployment fate can be for extent can be reduced.
A slight increase in traffic during construction would result as workers arrive and depart
the site and as materials and equipment are delivered. This temporary traffic increase
would represent only small fluctuations within the normal range.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.1
4.0 ANTICIPATED IMPACTS AND MITIGATION MEASURES
4.1 INTRODUCTION
Environmental Impact can be defined as any change in environmental conditions which
may be adverse or beneficial occurred due to an action or set of actions under
consideration.
Environmental impact can be assessed by identifying the sources of the impact and
predicting the same. The identification of environmental impacts has been made by co-
relating the relationship between project activity and environmental parameters. The
project activities of the proposed project are usually divided into two phases:
Construction phase - The activities like mining, excavation, erosion, building
construction, transportation of construction material etc. are usually consider in the
construction phase.
Operation phase - The activities like transportation & storage of raw materials and
finished products, manufacturing process, resource consumption, emergency disaster
and green belt development has been considered in the operation phase.
The next step is prediction of impacts which is an important component in
environmental impact assessment process. Several scientific techniques and
methodologies are available to predict impacts of project developmental activities on
environment. Such predictions are superimposed over the baseline (proposed project)
status of environmental quality to derive the ultimate scenario of environmental
conditions. The prediction of impacts helps to prepare the Environmental Management
Plan (EMP) required to be executed during the on-going activities for the proposed
project to minimize the adverse impacts on environmental quality.
The third important component of the environmental assessment is the evaluation.
Based on the identification & prediction of the nature of impact on the environment, the
impact can be evaluated qualitatively & quantitatively.
The mathematical models are the best tools to quantitatively describe the cause-effect
relationships between sources of pollution and different components of environment. In
case, mathematical models are not available or it is not possible to identify/validate a
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.2
model for a particular situation, predictions could be made through available scientific
knowledge and judgments.
The environmental impacts can be categorized as either primary or secondary.
Primary impacts are those, which are attributable directly to the project.
Secondary impacts are those, which are indirectly induced and typically include the
associated investment and changed pattern of social and economic activities by the
proposed action.
The impacts have been prepared for the proposed Plant assuming that the pollution
continues to remain the same during the operation of the project. The proposed project
would create impact on the environment in two distinct phases.
During the construction phase which may be regarded as temporary or short term;
and
During the operation phase which would have long-term effects.
The construction and operational phase of the proposed Project comprises of various
activities each of which may have an impact on some or other environmental
parameters. Various impacts during the construction and operation phase on the
environmental parameters have been studied to estimate the impact on the
environment. The environment impact due to proposed activities will be evaluated
considering the following parameters:
Land use
Soil Environment
Air Environment
Water Environment
Noise Environment
Ecology
Socio – Economic Environment
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.3
4.2 IMPACT ON ENVIRONMENT DURING CONSTRUCTION PHASE
This includes the following activities related to leveling of site, construction and erection
of main plant structures and equipment.
4.2.1 Impact on Land use
The total available land for the proposed plant (built-up area) is 4216 m2. Rest of the
area is used for plant utilities, road, and green belt development. The proposed plant
area is more or less flat which require minimum leveling.
The construction under this program would bring certain immediate changes in the land
use pattern of the proposed area as well as in the vicinity. Temporary sites will be used
for construction works or housing of construction workers.
4.2.2 Impact on Soil Environment
Since, the proposed project will need new premises; there will be construction activities
to be carried out. There will also be installation of new machineries & equipments. But
all this would not make a huge damage to the present condition of land. Further the area
of the plant is flat. Leveling would not be required. Thus, topography will also remain
unchanged after execution of the proposal.
Thus, the impact on the soil during the construction will for short terms & insignificant.
4.2.3 Impact on Air Quality
Impact of construction activities on air quality is a cause for concern mainly in the dry
months due to settling of dust particles. The main sources of emission during the
construction period are the movement of equipment at site and dust emitted during the
leveling, grading, earthworks, foundation works and other construction related activities.
The dust emitted during the above mentioned activities depend upon the type of soil being
excavated and the ambient humidity levels. The impact is likely to be for short duration and
confined locally to the construction site itself. The composition of dust in this kind of
operation is, however, mostly inorganic and non-toxic in nature.
Exhaust emissions from vehicles and equipment deployed during the construction phase
also result in marginal increase in the levels of SO2, NOX, SPM, CO and unburnt
hydrocarbons. The impact will, however, be marginal, and temporary in nature.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.4
4.2.4 Impact on Water Quality
Since the proposed project is a new project, it requires excess construction activities that
lead to adverse impact on the quality of water because large quantities of water will be
used for the construction activities. However, it will be used for the construction activities.
However, it will be for short period of time and temporary in nature. In addition, no
disposal of construction waste outside the plant and no leaching are anticipated. Thus the
quality and quantity of ground water will not have any permanent adverse impact.
4.2.5 Impact on Noise Levels
Heavy construction traffic for loading and unloading, fabrication and handling of
equipment and materials are likely to cause an increase in the ambient noise levels. The
areas affected are those close to the site. At the peak of the construction, marginal increase
in noise levels is expected to occur but they are temporary.
4.2.6 Impact on Terrestrial Ecology
Top soil will be lost during the construction of plant that may lead to soil erosion and
instability of ecosystem and loss of total biomass.
4.2.7 Impact on Aquatic Ecology
The construction of the plant is not likely to have any impact on aquatic eco-system, as
there are no water streams passing through the selected plant site.
4.2.8 Impact on Demography and Socio-economics
During the construction period, there will be increase in floating population. Additional
strain on civic amenities like road, transport, communication, drinking water, sanitation
and other facilities will take place, to meet the work force requirement. The project will
provide temporary employment of skilled and highly skilled manpower. Most of the people
will be employees of contractors/sub-contractors.
The non-workers [including marginal workers] in the 10 km radius study area constitute
about 44.27%. This indicates the availability of sizeable manpower required for the
construction activity.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.5
Most of the employees deployed during the construction period will be from local area.
During the construction phase there will be increased demand of services. These include
hotels, lodges, public transport (including taxis), etc. There will also be ample opportunities
for providing these services. In addition to the opportunity of getting employment as
construction laborers, the local population would also have employment opportunities in
related service activities like petty commercial establishments, small contracts/sub-
contracts and supply of construction materials for buildings and ancillary infrastructures
etc. Consequently, this may lead to economic upliftment of the area.
The influx of population is very limited. It is anticipated that there will be no social conflicts
between the guest and host communities in the initial stages of development.
The movement of work force to and from the place of work and the movement of vehicles
carrying equipment and construction material is expected to increase the stress on the
local transport and road network. However, considering the number of people deployed,
the impact on road/traffic is marginal and temporary.
Consumer Prices: Usually the local population will be affected by inflationary trend
sometime later, when prices of local services and produce, egg, fish, vegetables, milk, etc.
start rising. This will happen only when a sizeable staff of the project and other associate
companies settle permanently in the area. However any such rise in consumer prices is
anticipated because the influx of population due to the project activities is minimal.
Transport and Civil Construction: The transport companies would benefit from the
construction of the plant.
Services: The services like retail shops, banks, and automobile workshops; health care,
etc. will expand in and near the plant.
Employment: Large-scale influx of material and money tend to increase the employment
opportunities.
Transport: Transport services on the connecting road will improve further.
Traffic: The plant construction phase will also see a moderate increase in traffic.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.6
Development of Slums: The contractors have to necessarily provide basic amenities like
water supply, sanitation, electricity etc. at the labor camp to maintain hygienic condition
and aesthetics.
4.2.9 Public Expectation
Major occupation of the people in this area is industrial occupation. The people in the
area welcome the project, anticipating more jobs and more infrastructure facilities to the
local people, provided that the industry will not cause any pollution in the nearby
environment.
4.3 IDENTIFICATION OF POTENTIAL IMPACTS DURING OPERATIONAL PHASE
Both beneficial as well as potential adverse impacts may be expected on environment
from any development project due to its various activities associated with the
operations. The impacts may be direct or indirect, short or long term and reversible or
irreversible. However during the installation of proposed project, the size of the major
civil activities is insignificant, the impacts are of temporary. On the basis of the above
analysis, the potential significant impacts on the environment from the proposed project
are identified as below:
Soil Quality
Topography
Climate;
Air Quality;
Water Resources; Water Quality;
Noise Levels; Traffic;
Ecology and Demography and Socio-economics.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.7
4.3.1 Impact on Soil
The generation and disposal of sludge from the treatment units are the likely sources of
negative impact on the soil characteristics.
Similarly there may accidental spillage of oil during the transportation of vehicle.
The main hazardous waste are ETP sludge, used oil & discarded plastic bags & source are
material handling, storage, plant, machinery & ETP.
ETP sludge will be stored in the isolated hazardous waste storage area within premises
having leachate collection system & roof cover. ETP sludge generated from ETP will be
disposed off to TSDF site. Used oil will be reused within premises as a lubricant/ sold to
registered recycler. Discarded plastic bags will be reused within premises & sold to
approved scrap vendor.
The fugitive dust from the plant during operation is likely to be deposited in the nearby
areas. However, the proposed dust extraction and suppression measures at the source will
significantly reduce this possibility. Further, the proposed greenbelt comprising
diversified species not only increases the biomass, soil fertility, and productivity but also
helps as pollution sinks. However all precautions will be taken to minimize pollution in
terms of aerial spread.
4.3.2 Impact on Topography
The major envisaged topographical changes would be due to the manmade structures like
civil structures and including erection of stacks. Nearly 4216 sq. mt. of land will be
converted for built-up which has negative impact but the impact is not significant.
However, it will invite positive impacts by land leveling (not significant leveling is not
required) and diversified species green belt with flowing plants will also improve aesthetic
look of the area. Regular maintenance (watering, fertilizer, insecticides/ pesticidal
application, pruning etc.), will be carried out for green belt development during operation
phase by appointing a gardener for this purpose.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.8
4.3.3 Impact on Climate
The providing vegetation in the study area and the proposed green belt in the plant
premises will always have a cooling effect to offset any increase in temperature. The
thermal pollution is only confined to small distance and the proposed greenbelt not only
nullifies the thermal emissions but also it helps to keep surrounding ambient air cool.
4.3.4 Impact on Air Environment
The proposed project utilities like steam boiler will be required for production process,
which may have emission due to the combustion of fuel used in utility operation. D.G.
sets are also proposed for emergency power generation to meet the major requirements
of power during failure of supply from electricity department. Hence, considering these,
it is envisaged that during the operation phase impacts on air would arise due to the
fugitive emission mainly from operation of boiler and occasionally from DG set. Hence,
the study of impacts for the fugitive & stationary emissions have been conducted to
assess the potential impacts as well as to cite the efficiency of planned mitigation
measures and to suggested further mitigation requirements.
4.3.4.1 Stationary Emissions
The emission from Steam boiler will be the only source of SPM as it will be utilising Coal
/ White coal as fuel. The SPM level in final emission from the boiler will be within
statutory norms; as the boiler will be designed with internal baffles and other similar
control aspects, which will trap the SPM in hot air.
It has been noticed that minor quantity of SO2 & NOX will be released in environment.
This emission will reduce the impacts to acceptable level if adequate height of stack and
internal diameter at top is provided for uniform & proper velocity of emission. The stack
so design will help in efficient dispersion of SO2 to avoid high ground level concentration
in ambient air of surrounding area. Hence, it has been planned to provide stack of
adequate height from ground level with internal diameter at top considerable emission
of SO2. Similar to the above citation, impacts of emission of SO2 will be reduced to
acceptable level during normal operation with stack of adequate height & internal
diameter at top.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.9
Beside of SPM, SO2 & NOX emission will also be expected from Boiler and DG set. To
minimise the level of NOX in emission technology with low NOX burner will be used
wherever available from manufacturer. In addition to this, as mentioned above,
adequate stacks are planned for the DG sets, Boiler, which will be efficient to minimise
the impacts of residual NOX in emissions. As it has been mentioned in earlier paragraphs,
considerable emission of SPM, SO2 & NOX is anticipated from the utilities of the proposed
project. Hence it has become necessary to further study the impacts of the emission on
air quality to evaluate probable change in air quality parameters.
4.3.4.2 INPUT DATA FOR DISPERSION MODEL (AERMOD VIEW – 8.2)
A. Input data of Flue gas stack
The proposed unit will operate steam boiler to generate stream required during
manufacturing process. The details of flue gas stack are as follows:
Table 4.1: Flue Gas stacks details
Sr.
No.
Stack
attached
to
Height of
the stack
In meter
Fuel APC
System
Expected
Pollutant
GPCB
Limit
1
Steam Boiler
(1 MT)
30
(Common Stack)
Coal / White Coal
–2.314 MT/D
Multi cyclone
Dust Collector
PM
SO2
NOx
As per GPCB
Norms
2 D. G. Set
300 KVA 6 HSD 35
L/Hr -- HC
As per GPCB
Norms
Note: D.G. Set will be only used when power failure.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.10
Input data:
Stack Identification Boiler Stack
Stack Height 30.0 m
Vent Diameter 1.0 m
Exit stack gas velocity 1.8 m/s
Exit gas temperature 160 oC
Ambient temperature 27 oC
Particulate Matters 5.16 gm/sec
Sulfur Dioxide 0.219 gm/sec
Nitrogen Oxide 1.071 gm/sec
B. Primary Meteorological Data:
Primary meteorological data is used for Aermod View – 8.2. This data is attached as
Annexure – A.
4.3.4.3 Prediction and Assessment of Impact:
The Gaussian model is used to predict the centerline ground level concentrations of
suspended particulate matter, sulfur dioxide and nitrogen oxides in the surrounding
study area. The prediction is done in relation to the source strength and meteorological
conditions for the study period.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.11
The centerline ground level concentrations for Particulate Matter, Sulfur Dioxide and
Nitrogen Oxides in the study area for all the stability conditions are calculated for the
maximum emission load.
For the calculations, meteorological data like average wind speed, wind direction,
relative humidity, precipitation, dry bulb temperature, cloud cover, ceiling height,
emission rate of SPM, SOx & NOx and stack height & diameter during period November,
December 2013 and January 2014 is considered.
Predicted ground level concentrations of SPM, SO2 and NOx are presented in the Figure
4.1, 4.2, 4.3 and table 4.2, 4.3 & 4.4.
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
MM
/s. T
. R. A
ssoc
iate
s
4
.12
Fig.
No.
4.1
Gro
und
leve
l con
cent
rati
on o
f SPM
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
MM
/s. T
. R. A
ssoc
iate
s
4
.13
Fig.
No.
4.2
Gro
und
leve
l con
cent
rati
on o
f SO
2
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
MM
/s. T
. R. A
ssoc
iate
s
4
.14
Fig.
No.
4.3
Gro
und
leve
l con
cent
rati
on o
f NO
x
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.15
Table 4.2 Predicted 24 hourly short term incremental Concentrations of SPM
Sr. No.
Monitoring Stations
Existing monitored maximum SPM concentration μg/m3
Predicted SPM Concentration μg/m3
Total SPM Concentrations implementation of the proposed project μg/m3
1 Project site 79.8 9.5 89.3
2 Nava Jambudiya 77.2 9.5 86.7
3 Juna Jambudiya 80.2 9.5 89.7
4 Rafaleshwar 79.8 9.5 89.3
5 Jodhpar 77.7 4.5 82.2
6 Bhadiyad 77.7 9.5 87.2
7 Paneli 80.3 9.5 89.8
Table 4.3 Predicted 24 hourly short term incremental Concentrations of SO2
Sr. No.
Monitoring Stations
Existing monitored
maximum SO2 concentration
μg/m3
Predicted SO2 Concentration
μg/m3
Total SO2
Concentrations implementation of the proposed
project μg/m3
1 Project site 17.1 1.5 18.6
2 Nava Jambudiya 20.7 0.9 21.6
3 Juna Jambudiya 15.6 0.9 16.5
4 Rafaleshwar 19.1 1.5 20.6
5 Jodhpar 20.7 2.5 23.2
6 Bhadiyad 20.7 0.9 21.6
7 Paneli 15.3 1.5 16.8
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.16
Table 4.4 Predicted 24 hourly short term incremental Concentrations of NOx
Sr. No.
Monitoring Stations
Existing monitored maximum
NOx concentration
μg/m3
Predicted NOx Concentration
μg/m3
Total NOX Concentrations implementation of the proposed
project μg/m3
1 Project site 26.8 4.5 31.3
2 Nava Jambudiya 25.5 3 28.5
3 Juna Jambudiya 28.0 6.5 34.5
4 Rafaleshwar 25.9 7.5 33.4
5 Jodhpar 30.7 6.5 37.2
6 Bhadiyad 30.7 6 36.7
7 Paneli 24.7 6 30.7
After implementation of the proposed project, these concentrations are found to be well
below the permissible NAAQS norms for rural/residential zone and Industrial zone.
Therefore, the proposed activity is not likely to have any significant adverse impact on
the air environment.
4.3.5 Impact on Water Environment
Water is essential for domestic, agriculture, industry and commercial use. The industrial
activity can have direct impact on the end users. Impact on water environment due to
the proposed project will be in terms of water use, wastewater generation and its
disposal.
The main source of water supply for the industrial operations will be; the own bore
wells. The ground water is easily available in the surrounding area. There will be minor
negative impact on availability of natural water resources in the study area (Ground and
Surface Water).
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.17
4.3.6 Impact on Noise Environment
The incremental increase in noise levels due to the operation phase of the Plant has been
done. Noise levels are mainly generated from DG set and compressor house. The noise
sources have been defined with respect to plant center.
4.3.6.1 Observation
The noise due to operation of the proposed project will not have any bearing on the
baseline noise levels due to masking effect.
The operators, workers and other personnel within the plant, however, have to be
provided with protective measures such as earplugs at the noise generating units. The
noise protective enclosures shall be provided at the noise generating units. The
permissible noise exposure for the workers working at the noise sources is listed in the
following Table 4.5. Hence measures shall be taken to avoid such exposures.
Table 4.5 Permissible Noise Exposures for Industrial Workers
Exposure Time (in
hr/day)
Limit in dB
(A)
8 90
4 93
2 96
1 99
½ 102
¼ 105
1/8 108
1/16 111
1/32 (2 minutes or loss) 114
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.18
1 Exposure to continuous or intermittent noise louder than 115 dB (A) should not
be permitted.
2 Exposure to pulse or impact noise should not exceed 140 dB (Peak Acoustic
Pressure).
Green belt also acts as barriers for noise dispersion. So in addition to the plant noise
control measures, all the open areas within the plant premises and all along the plant
boundary will be provided with adequate green belt to diffuse the noise dispersion.
4.3.7 Impact on Ecology
The removal of herbaceous vegetation generally causes loosening of topsoil. It also leads
to soil erosion. The biomass will be reduced and leads destabilization of ecosystem.
However, such negative impacts would be reversible in to positive impacts by
development of thick green belt and in a course of time that leads sustainable ecosystem.
The impacts on natural vegetation and species diversity will be positive due to the
proposed plant. There will be few tree cutting and shrub removal will take place.
Wherever possibility is there, the entire tree will be uprooted and planted at different
places. The proposed green belt development scheme will enhance the biomass and leads
to sustainable development. The avenue plantation along the road side also acts as sinks of
vehicular emissions. The green belt will enrich soil organic matter thereby nitrogen. It will
help as noise barrier. Green belt control temperature and keep the surroundings cool. It
will attract avifauna and create suitable habitat to micro flora and fauna. The green belt
will help as a sink to dust and gaseous pollutants. On the whole it has a positive impact on
the environment.
4.3.8 Impact on Socio-Economics
The impacts of the proposed plant would begin to be felt with the start-up of the
operational activities.
The present trend of out migration for people is likely to reduce due to better employment
opportunities in the area;
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.19
The plant will result in considerable growth of service sector and will also generate new
industrial and business opportunities in the area. The ancillary facilities, would act, as an
active nucleus for business activities.
The socio-economic impacts discussed in the construction phase of the proposed plant will
also be manifested during the operation phase in the following manner.
Increase in consumer prices of indigenous produce and services, land prices, house rent
rates and labour prices.
Some increase in services catering to the additional population will occur due to the
setting up of the plant.
Influx of persons with higher spending power and different socio-cultural background
will improve the socio-cultural environment of the area.
Improvement in transport, communication, health and educational services.
Increase in employment due to large flow of financial and material resources through
increased business, trade commerce and service sector.
4.4 ENVIRONMENT MANAGEMENT PLAN
4.4.1 Introduction
Preparation of Environmental Management Plan (EMP) is required for formulation and
monitoring of Environmental Protection measures during and after commissioning of
project. The plan should indicate the details as to how various measures have been or
are proposed to be taken including cost components as may be required. Cost of
measures for environmental safe guards should be treated as an integral component of
the project cost and environmental aspects should be taken in to account at various
stages of the project.
a. Conceptualization : Preliminary environmental Assessment
b. Planning : Detailed studies of environmental Impacts and design
of safe guards
c. Execution : Implementation of Environmental safety measures
d. Operation : Monitoring of effectiveness of built in safe guards
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.20
The assimilative capacity of the study area is the maximum amount of pollution load that
can be discharged in the environment without affecting the designated use and is governed
by dilution, dispersion and removal due to natural physico-chemical and biological
processes. The Environment Management Plan (EMP) is required to ensure sustainable
development in the area of the proposed plant. Hence, it needs to be an all encompass plan
for which the proposed industry, Government, Regulating agencies like Pollution Control
Board working in the region and more importantly the affected population of the study
area need to extend their co-operation and contribution. The identification and
quantification of impacts based on scientific and mathematical modeling.
The Management Action Plan aims at controlling pollution at the source level to the
possible extent with the best available technology followed by treatment measures before
they are discharged.
The recycling and re-use of industrial waste not only reduces the waste generated but
can be an economic gain to the industry.
4.5 ENVIRONMENT MANAGEMENT PLAN (EMP) DURING CONSTRUCTION
The impacts during the construction phase on the environment would be basically of
transient nature and are expected to reduce gradually on completion of the construction
activities.
4.5.1 Site Preparation
Since the project site terrain is almost flat, some minimal leveling is only required.
Vegetation on topsoil is removed prior to commencement of bulk earthwork. During dry
weather conditions, dust may be generated by activities like excavation and
transportation through un-metalled roads. The dust will be suppressed using water
sprinkling and may continue after completion of construction, as there is a possibility of
heavy truck movement. The industry will make provision for water sprinklers.
The construction under this program would bring certain immediate changes in the land
use pattern of the proposed area as well as in the vicinity. There will be permanent
change (only in the buildup and storage area) in the land use pattern of the area.
As soon as construction is over the surplus earth will be utilized to fill up low-lying areas,
the rubbish will be cleared and all un-built surfaces reinstated. Cutting of trees will be
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.21
minimized as far as possible. Enough space will be kept for treatment and solid waste
disposal.
The maximum topsoil cover thickness at the plant site is about 1-m. The topsoil
removed during the leveling will be stacked separately and will be used during the
greenbelt development. Herbs and shrubs will be removed prior to commencement of
bulk earthwork. Removal of trees will be avoided as far as possible based on the
construction plan. Medium trees size trees will be uprooted and planted in the designed
green belt.
Greenbelt development program will start simultaneously along with civil constructions.
Proper planning during construction period will minimize the upper soil contamination.
So attentions shall be paid with minimum contamination to the soil.
4.5.2 Air Quality
Transportation of vehicles will result in marginal increase in the levels of SO2, NOX, SPM,
CO and unburnt hydrocarbons. The impact will, however, be marginal, and temporary in
nature. However, proper maintenance of vehicles can minimize emissions. Dust
suppression by covering and water sprinkling and maintenance of vehicles will be
carried out to keep air quality to the minimum negative impact on the surroundings. All
internal roads will be paved with Bitumen or Concrete to avoid dust emissions.
4.5.3 Water Quality
During construction period, in rainy season the water quality is likely to be affected due
to the construction work and loosening of topsoil. This is likely to increase the
suspended solids in the run-off during heavy precipitation. In order to reduce the
impact on water quality, temporary sedimentation tanks will be constructed for the
settlement of the suspended matter.
Temporary sanitation facilities (soak pits/septic tanks) will be set up for disposal of
sanitary sewage generated by the work force as per the prevailing labor laws. The overall
impact on water environment during construction phase due to proposed plant is likely to
be short term and insignificant and they will be managed by providing drinking water
facility and sanitation facilities at the site during construction phase.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.22
4.5.4 Noise Levels
The noise effect on the nearest inhabitants during the construction activity will be
negligible. However on site workers using high noise producing equipment will adopt
noise protection devices like earmuffs. Noise prone activities will be avoided to the
extent possible during night particularly during a period 9 PM to 6 AM in order to have
minimum environmental impact on the neighborhood environment. High noise
generating equipment, if used, will not be operated during the night to eliminate any
possible discomfort to the nearby residents. Community noise levels are not likely to be
affected because of the vegetation and likely attenuation due to the physical barriers.
Overall, the impact of noise generated on the environment is likely to be insignificant,
reversible and localized in nature and mainly confined to the day hours.
4.5.5 Ecological Aspects
During construction period, there could be clearing of herbs and shrubs in order to
prepare the site for construction. However, this will be mitigated by proper land scalping
and extensive plantation along with the construction of the plant. A comprehensive
green belt program will improve the ecological condition of the region.
4.5.6 Storage of Hazardous Materials
The hazardous materials used during the construction may include diesel, welding gas
and paints. These materials will be stored and handled according to the guidelines
specified under the Hazardous Waste (Management, Handling, & Transboundary
Movement) Rules, 2008 and amendments thereafter (by MoEF/CPCB). Some of the
precautions of storage include the following:
Dyked enclosures will be provided which will be able to contain complete contents of
the largest tank;
Diesel and other fuels will be stored in separate dyke enclosures;
Tanks having a diameter of more than 30 m will be separated by fire walls from
other storage tanks; and
The distance between the storage tanks will be at least half their height.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.23
4.5.7 Site Security
Adequate security arrangement will be made to ensure that the local inhabitants and the
stray cattle are not exposed to the potential hazards of construction activities.
4.5.8 Migrant Laborers
Safe and secure camping area will be provided for the migrant laborers during the
construction period. Adequate arrangements will be made for water supply, sanitation
and cooking fuels. The construction site will be provided with sufficient and suitable toilet
facilities for workers to allow proper standards of hygiene. These facilities would be
connected to a septic tank and maintained to ensure minimum environmental impact.
Table 4.6 Negative Impacts and Mitigations during Construction Phase
Constructional Impact
Discipline Negative
Impacts
Probable
Source
Mitigative Measures Remarks
Air Dust due to
construction
al activities
Civil
activities
Maintenance of vehicles and
Sprinkling of water in the
construction area and unpaved
roads.
The impacts
are temporary
Noise Increase in
noise level
Civil
activities
Maintenance of vehicles,
equipment with proper civil
planning will reduce increase in
noise levels. They will be kept in
good condition to keep the
noise level within 90 dB (A).
If necessary,
workers will
be provided
necessary
protective
equipment
e.g. ear plug,
earmuffs.
Water Increase in
suspended
solids due to
Loose soil at
constructio
n site
The land required for the built
up is 4216 m2. Soil erosion will
be kept minimum. A non-
scouring, non-silting storm
The impacts
are
temporary.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.24
Constructional Impact
Discipline Negative
Impacts
Probable
Source
Mitigative Measures Remarks
soil run-off. water drain will be laid from the
plant and a rainwater
harvesting structure is
proposed at a strategic location
to arrest the run-off water.
Terrestrial
Ecology
Clearing of
Vegetation
Soil erosion
and
reduction of
biomass
Leveling operations are
minimum. Sprinkling of water
and topsoil preservation and
Systematic plantation will
reduce soil erosion and double
the biomass.
The impact is
temporary.
Socio-
economy
Infusion of
labour and
health
Temporary
houses
Water supply and good sanitary
conditions with hygienic
environment will decrease
negative impact.
The change is
temporary
4.6 ENVIRONMENTAL MANAGEMENT PLAN (EMP) DURING OPERATIONAL STAGE
The EMP in the design stage endeavors to mitigate the problems related to health, safety
and environment at the process technology selection stage and at the design stage. The
proposed laminated sheet plant will be designed taking into account all applicable
standards/norms (IS, CPCB, MoEF and CREP guideline) both for regulatory and safety
purpose.
Environment management at design stage includes all the steps undertaken at the
design stage by the project proponents to meet the statutory requirements and towards
minimizing environmental negative impacts. The design basis for all process units will lay
special emphasis on measures to minimize pollutant generation and emission control at
source.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.25
4.6.1 Soil Quality
The generation and disposal of sludge from the treatment units are the likely sources of
negative impact on the soil characteristics.
Similarly there may accidental spillage of oil during the transportation of vehicle.
The negative impacts will be minimum as the solid waste generated in the plant
disposed off to the consumers in regular manner. Hence the impact of solid generated in
the plant is minimal.
The fugitive dust from the plant during operation is likely to be deposited in the nearby
areas. However, the proposed dust extraction and suppression measures at the source will
significantly reduce this possibility. Further, the proposed greenbelt comprising
diversified species not only increases the biomass, soil fertility, and productivity but also
helps as pollution sinks. However all precautions will be taken to minimize pollution in
terms of aerial spread.
Construction activities will bring a significant change to the topsoil of the project area
due to excavation, stacking of construction material etc. There will not be any significant
change in topography due to project.
Some construction activities will disturb the soil profile but that will be temporary and
having insignificant impact. Original form of the topsoil will be largely restored and even
enhanced due to activities like beautification of premises, development of garden etc.
4.6.2 Air Quality Management
Critical air pollutants from the plant are Particulates and Oxides of Sulfur and Nitrogen
and fugitive emission.
There is total 2 stack used for emission of pollutants.
The following methods of abatement will be employed for the air pollution control.
Proposed Air Pollution Control measures
Exhaust from both technological and ventilation equipment would be treated and
thrown to atmosphere at a height according to air pollution control norms. Multi cyclone
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.26
dust collector will be installed to control Particulate matter. Proper Stack heights have
been suitably selected (30 m for steam boiler) so as to ensure that ground level
concentration of pollutants remains within the permissible limits.
4.6.3 Water Management
The wastewater generated from the manufacturing process, boiler & cooling tower will
be treated in the effluent treatment plant. It will be finally evaporated in Multiple Effect
Evaporator & reused in process. So industry will maintain ZERO DISCHARGE.
Domestic effluent from the various buildings / sheds of the plant is conveyed through
separate drains to septic tanks. The effluent from the septic tank is disposed off through
soil percolation by providing dispersion trenches / soak pits.
Water Consumption
The water requirement of the unit will be satisfied through Bore well. The Industrial
water consumption for proposed plant will be 64 KL/Day (Fresh water: 57.3 KL/D,
Reuse water: 6.7 KL/D), which will be used for various industrial purpose. In it,
Domestic water consumption for proposed unit will be 2.35 KL/Day. The unit will
develop Green Belt Area within the industrial premises hence the water requirement for
gardening purpose will be 8 KL/day (Fresh 5.8 and 2.2 Reuse) So therefore, the total
water requirement will be 65.45 KL/ Day.
Waste Water Generation
The total Waste water Generation will be 6.65 KL/ Day. In this the domestic waste water
will be 2.2 KL/Day and it will go to soak pit through septic tank. Waste Water will be
generated from Cooling reject, Boiler blowdown and R.O Reject will be about 6.65
KL/day from manufacturing process. This will be treated in the Multi Effect Evaporator.
Treated water will be reused in process. Thus industry will maintain ZERO DISCHARGE.
The Category wise details of water consumption and wastewater generation are shown
in Table 4.7 and in Fig. 4.4
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.27
Table 4.7 Water consumption and Waste Water Generation details
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd
MM
/s. T
. R. A
ssoc
iate
s
4
.28
Fig.
4.4
Wat
er B
alan
ce D
iagr
am
Not
e: In
dust
ry w
ill m
aint
ain
Zero
dis
char
ge.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.29
Waste Water Management System
Effluent Treatment Plant
Process
Industrial wastewater generated due to manufacturing process, cooling, boiler & Scrubbing process will be collected in Primary Collection tank and equalized the effluent to make homogeneous mixture.
Then this effluent will be sent to Multi Effect Evaporator.
The condensed water will be reused in the process.
Fig. 4.5 Flow Diagram of ETP
Effluent Collected in
Collection cum equalization tank
Multi Effect Evaporator
Sludge sent to TSDF Site
Reused back in process
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.30
Table 4.8 Capacity of ETP units
Sr. No. Name of the units Volume Lit. No. of Unit
1 Collection Tank 10000 2
2 Multi Effect Evaporator 600 L/Hr 1
4.6.4 Noise Level Management
Due to technological reasons, it may not be practicable to entirely eliminate all noise but
the noise levels could be brought down to acceptable limits wherever possible. The
major equipment of high noise production can be identified as DG set. Various measures
include the reduction of noise at source, providing acoustic lagging for the equipment,
isolating the noise-producing instrument. Regular maintenance, arresting vibration and
oil/greasing shall be done to ensure that the noise limits are well below the limits. They
shall ensure that during day (6 AM to 10 PM) and night time (10 PM to 6 AM) noise Leq
values shall be below 75 and 70 dB (A) at the plant boundary as per the CPCB norms.
The specifications for procuring major noise generating machines/equipment will
include built in design requirements to have minimum noise levels meeting
Occupational Safety & Health Association (OSHA) requirement. Appropriate noise
barriers/shields, silencers etc. will be provided in the equipment, wherever feasible.
4.6.5 Solid & Hazardous Waste Management
The hazardous waste such as ETP sludge, used oil and discarded bags arises from ETP,
material handling & machinery. It shall be stored on own land earmarked for effective
management. The various type of solid waste generated should be stored separately in
scientific manner so that it should not adversely affect the air quality, becoming air
borne by wind or water regime during rainy season by flowing along with the storm
water.
The type and quantity of hazardous waste generated and their utilization is given in the
following table:
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.31
Table 4.9 Hazardous waste generation and their disposal
Sr.
No. Description Category Quantity Mode of Disposal
1 ETP Sludge 34.3 16.25
MT/Month
Collection, storage and
Disposal at TSDF Site
2 Used Oil 5.1 25 Lit./
Month
Collection, storage and used
within premises as a lubricant
/ sold to registered recycler.
3 Discarded Plastic
bags 33.3
6940 Nos./
Month.
Collection, storage & sell to
authorized vendor
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.32
4.7 GREEN BELT DEVELOPMENT
The proposed green belt development plan in and around the plant area is covering
3096 m2 of total land. The tolerant species with diversity will be planted which will help
in suppression of fugitive dust, attenuate noise levels and provide aesthetic background.
Nearly 465 plants (one hectare nearly 1500 plants) will be planted for the development
of green belt.
Table 4.10 Categorization of the area for project and greenbelt
Sr.
No. Details Area, m2 %
1 Built – Up Area 4216 41.90
2 Green Belt 3096 30.77
3 Open/ Road Area 2748 27.33
Total Plot Area 10060 100
In the layout the green belt is planned keeping in view of the following CPCB guidelines
The built-up are of the plant shall not be more than 50% of total area’. In this case
the built up is only 41.90 % out of the total area.
The green belt helps to check soil erosion, make the eco-system more sustainable, make
the climate more conductive and restore water balance. The main objective of the green
belt is to provide a barrier between the plant and the surrounding areas. The green belt
helps to capture the fugitive emissions and to attenuate the noise generated in the plant
apart from improving the aesthetics of the plant site.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.33
The green belt development program will go simultaneously in phased manner along with
the civil activities.
The green belt will be developed in such a way that the industry will not be seen from
the outside premises.
The published ‘Guidelines for developing Green belts’ by CPCB (2007) will be taken in to
consideration
Procedure for Transplantation of full-grown Trees Method
If trees are not very old they can be transplanted easily. The percentage of survival can
be hundred per cent if the work is done properly and during the rainy season. The
following steps are involved:
1. The sites where the trees are to be shifted should be selected first. The sites should
be free of overhead telephone or power lines. Large pits should be dug at these sites to
comfortably accommodate the ‘tree roots’ ball of earth.
2. Distance between pits depends on the variety. In case of short varieties with a small
spread, the distance should be 10 ft. for tall varieties with spreads of between 15 ft. and
20 ft. on either side, the distance should not be less than 30 feet.
3. When pits are dug at the selected sites, their sizes would depend on the
dimensions/age of the tree. For trees of medium size the pit size will be around 8 feet in
diameter and 5 feet deep.
4. Adequate quantity of soil and manure mixture @ 4:1 is necessary for each pit. A
little bone metal can also be added. To start with only about 6” soil mixture is to be filled
in each pit and watered well to form a puddle before the actual transplantation.
5. Before transplantation, the trees should be ‘extensively pruned’. That is, the foliage
should be completely removed and all the branches should be cut off with a pruning saw.
No other implement should be used. The cut surfaces should be painted with non-
synthetic white paint to anaesthetize these portions. ‘Extensive pruning’ helps in easier
‘replanting balance’ and handling, thereby reducing the shock effect. This also aids the
plant roots in recovering and adhering to the new soil and reduces transpiration and/or
loss of moisture.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.34
6. The trees are now ready for lifting or uprooting. A deep trench of at least 3 feet
away from the trunk in the case of trees with a girth of up to 6”. The depth of the trench
and its distance from the trunk would therefore vary with the size of the tree. The trench
should be dug to gradually coverage towards the base of the tree so that ‘tree roots’ ball
of earth can ultimately be detached from the ground.
7. The trees are then to be lifted with the help of a crane of suitable size. Before lifting,
a piece of gunny should be would round the trunk, with a few wooden batons secured
around the gunny pack on the outside by a steel wire rope. This will facilitate lifting
without injuring the bark. Immediately the ‘tree roots’ ball should be sprayed with
potassium phosphate solution and then wrapped and tied with a piece of very wet
gunny.
8. Before replanting, the soil at the base of the pit should be watered heavily after
which the uprooted tree along with the ‘tree roots’ ball should be lowered carefully into
the new pit with the help of crane.
9. The empty space in this pit is to be filled with the previously prepared mixture of
soil, bone and manure and thoroughly rammed in tightly, so that no air gaps are left
inside the soil. Air gaps could result in fungal infection to the roots. Sand can also be
added which will fill up the air gaps when watered.
10. The trunk can now be sprayed with Blytox, a copper sulphate compound whose
action is anti-fungicidal in nature.
11. The transplanted tree should be watered heavily at the base.
12. Guy ropes, angle iron or bamboos should be used for a few days to secure the tree
till the soil hardens around the transplanted tree to hold it erect.
13. Four to five days after transplantation the trunk can be sprayed with potassium
nitrate solution for facilitating the initiation of new shoots.
14. If rains are inadequate watering should continue for three months.
Wind breaker plant species will be (eg. Eucalytus, Casuarina, Polyanlthia etc.) will be
planted around the periphery of near boundary walls.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.35
Potted plants and climbers will be used on the roof tops. Money plants like climbers will
be used and make them to hang to avoid penetration dust inside the working areas.
These climbers will be sprinkled regularly to remove adhered dust particles.
Grass mat along with combination flowering shrubs will be planned along the rest
rooms. All the corners inside the rooms of administration building and along the stair
case, potted shrubs will be put and change time to time for watering, pruningand
fertilizing.
Choosing native plant species which suits to local environmental conditions will be
encouraging (percentage survival) and also for sustainable ecosystem development.
Plants with flowering will give good aesthetic look. Fast growing species with more
calorific value is preferable. Necessary help will be taken from the local DFO in
development of green belt. Based on the demand of nutrients by soil the fertilizer input
shall be given. These trees will be planted in about different rows with a tree density of
1500 trees/ha. The interspaces will be planted with grasses, bushes and hedges. More
number of rows is preferred in N & NE direction as wind is blowing from S & SW
direction. The treated sewage effluent from the plant will be used for watering the green
belt. The recommended plant species for green belt is given below given below: The
Greenbelt plan is depicted in Table-4.11.
Table 4.11 Recommended Plant Species for Green Belt Development
SI.
No Botanical Name
Common
Name
Ht. in
metres
Colour of the
flower
Flowering
time
1 Acacia arabica Babool 8.0-
10.0 Yellow
March-
May
2 Aegle marmelos
(V. limiled) Bel
8.0-
10.0
Greenish white
fruit plant
March-
April
3 Albizia lebbeck
(A.procera) Siris
10.0-
15.0
Pale-greenish
yellow April-May
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.36
4 Artocarpus
integrifolia Kathal 6.0-8.0
Feb.-
March
5 Anogeissus latifolia Dhaura 10.0-
15.0 Greenish Sept.-Jan.
6 Anacardium
occidentale Cashew 3.0-4.0 Cream Jan.-Feb.
7 Anthocephalus
cadamba Kadam
10.0-
15.0 Yellow Oct.-Dec.
8 Bauhinia variegata Kanchan 7.0-8.0
White-
variegated
with purple &
white
Feb.-April
9 Cassia fistula
Indian
Lambumum
Amaltas
9.0-
13.0 Yellow
March-
May
10 Cassia nodosa Pink "Mohur" 12.0-
14.0 Rose pink April-May
11 Casuarina
equisetifolia Jhau
10.0-
15.0
Flowers
inconspicuous
March-
May
12 Delonix regia Gold Mohur
Gul Mohur
8.0-
12.0
white-orange
Red April- June
13 Eucalyptus hydrid Blue Gum tree 20.0-
25.0 Cream May-June
14 Nyctanthes
arbortristic Siuli 2.0-3.0 White Oct.-Nov.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.37
15 Lagerstroemia
floreginae Jarul
7.0-
10.0 Liliac May-June
16 Mangifera indica Am 7.0-8.0 White Feb.-
March
17 Mimusops elengi Bakul 4.0-5.0 White Nov.-Dec.
18 Nerium odorum Karabi 2.0-4.0 Red, white Feb.-
March
19 Peltophorum
ferruginium Radhachura
10.0-
15.0 Golden-yellow May-Oct.
20 Pithecellobium dulce Jungle Jalebi 8.0-
10.0 White
March-
April
21 Putranjiva roxburghii Indian Amulet
tree
8.0-
10.0
Flowers
inconspicuous
March-
April
22 Polyalthea longifolia Debdaru Foliage March-
June
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.38
4.8 RAIN WATER HARVESTING
A. Introduction:-
Rainwater Harvesting is generally putting back rainwater in to the underground
formation, where it will be stored in underground reservoirs (Aquifer) so that we can
draw it whenever we need it.
“NEED”
To reduce ground water pollution.
To augment the ground water storage and decline of Water Level
To improve the quality of ground water.
To reduce the soil erosion.
To avoid flooding of roods.
The harvested rain water can be used for flushing, washing, gardening, irrigation, fire
fighting and even consumption with necessary treatment, Rain water is the purest form
of water available to us.
Components:-
Catchment
Collection system
Filtration unit
Storage system
Technology:-
1. Storage in artificial above or underground tanks.
2. Recharging aquifer directly through tube wells with necessary treatment.
3. Recharging aquifer by percolation / Soakage in the ground.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.39
Aquifers best suited for artificial recharge are those that absorb large quantities of water
and do not release them too quickly.
Theoretically this means that the vertical hydraulic conductivity is high while the
horizontal hydraulic conductivity is moderate. Most of the artificial recharge areas are
located in the alluvial plains because of many favorable conditions like availability of
infiltration waters and transmissivity of the aquifers.
Ground Water recharge Rate:-
The technical feasibility and economic viability of artificial recharge of Ground Water
has already been established by CGWB (UNDP/CGWB 1986) by siphen method.
Salient features of experiment of state govt. and PRL in 1977:-
1. Recharge rate : 590 LPM
2. Build up in the injection well :- 5.18 m
3. Drawdown in source well :- 0.70m
4. Build up in observation (V=40m) :-1.15m
5. Transmissivity :- 540 m2 /day
6. Permeability : 70 m / Day
7. Injection well efficiency : 56%
No. clogging in injection well was observed after 220 hrs of experiment. This method
was found more economical and cost at the time of experiment was found to be 45 paisa
per 1000 liters.
Method of Recharge:-
Artificial recharge is achieved by three methods namely by spreading by induced
recharge and by injection. The suitability of particular method is based on the hydro
geological condition. Our area is composed of deep aquifers with impervious over
burden hence injection method is most suitable. Water is fed directly in to the depleted
aquifers by providing a conduit access such as tubewell. Recharge by tubewell is the only
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.40
method for artificial recharge of confined aquifer or deep seated aquifers. The recharge
is instantaneous and there are no transit losses and evaporation losses. Artificial
recharge is an important aspect of ground water management as it provides storage
space free of cost, during dry period. The underground reservoirs can be used for
indefinite period, if properly operated.
Roof Top Rain Water Harvesting (R T R W H )
Introduction:-
In arid and semiarid areas rain water forms the only source of domestic water supply.
This is an ideal solution to water problem where there is no ground water (Saline
ground water) and surface sources are very far. This is ideally suited from the
economical point of view. Rain water is bacteriologicaly pure, free from, organic water
and soft in nature. To meet drinking water demand during the critical dry period of 90-
120 days roof top water harvesting is very useful. Ground water recharge or storage
from house of 100 Sq. m of roof top will be 55000 lits in one year, sufficient for a period
of four months for a family of five members.
In roof top rain water harvesting the rain water is collected from roof of the buildings
and stored in water tank or ground water reservoir for beneficial use in future. The size
of the catchment area and tank should be enough to supply sufficient water for the users
during this period.
B. Volume:-
Volume of tank can be calculated by the following formula.
V= (t x n x a) tat where
V= Volume of tank (litters)
T= Length of the dry season (days)
N= Number of people using the tank
A= Consumption per capita per days (litters)
ET= Evaporation loss during the dry period
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.41
Since evaporation from a closed storage tank is negligible the evaporation loss (et) can
be ignored (=Zero)
C. Need for R T R W H :- (Roof Top Rain Water Harvesting)
To meet ever increasing demand for water in urban areas.
To reduce the runoff which is chocking the storm drains
To avoid the flooding of roads
To augment the ground water storage and control decline of water levels
To reduce the ground water pollution
To improve the quality of ground water
To reduce the soil erosion
Rain water may be harnessed at place of need and may be utilized at time of need
The structures required for harvesting the rain water are simple, economical and
eco-friendly
D. Essential Components of the system
Roof Catchment
Gutters for collection of roof water
Down pipe to convey rain water from gutter to storage tank
“Foul Flush” to divert the contaminated run-off from roof (for initial wash out before
taking to storage tank
Filter/Mesh
Storage tank under ground
Water withdrawal arrangement (Hand Pump)
Dis-infection arrangement
E. Design Consideration:-
In the design system, the main criteria is the most economical combination of the
storage tank volume, systematic analysis of rainfall records and construction costs.
F. Selection of Site:-
o Site should be close to the house to reduce the cost of down pipe
o Site should have good drainage and should be away from the cattle shed and soak
pits etc. for cleanliness and hygiene surrounding the tank
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.42
o Site should be away from tress to prevent litters falling on the roof and structural
disturbance to the tank by roof propagation
o Site should be easily accessible for tapping water
G. Tips for Maintenance of the R R H S:-
Always keep the surroundings of the tank clean and hygienic
Remove Algae from the roof tiles and asbestos sheets before the monsoon
Drain the tank completely and clean from inside thoroughly before the monsoon
Clean the water channels (Gutters) often during rainy season and definitely before
the first monsoon rain
Avoid first 15 or 20 minutes of rain fall depending on the intensity of rain. Use the
first flush arrangement to drain off this first rain water
Change the filter media every rainy season
In coastal area the tank may be painted outside by corrosion resistant paint once in
3 years and in other areas lime (Calcium Carbonate) based white wash may be applied
not only for beauty but also for cleanliness
Withdraw water from the system at the rate of 5 lits/head/day. This will ensure
availability of water throughout the water scarcity period.
Cover all inlet and outlet pipes with closely knife nylon net or fine cloth or cap
during non-rainy season to avoid entry of insects, worms and mosquitoes.
The substances that go into the making of the roof should be non-toxic in nature
H. Recharge Tube well:-
This technique is applied for recharging the aquifer by constructing borewell by DTH rig
in Alluvium and basalt formation as under
Design and Methodology
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.43
A borewell of 300 mm diameter shall be drilled by DTH rig to the desired depth
depending on geological conditions. In Alluvium and basalt formation the depth should
be drilled for 120 to 150 m. in the project area.
Weathered zone of borewell shall be cased with perforated pipe
A 150mm diameter perforated UPVC/ AC Pressure pipe shall be lowered to the
entire depth of borewell.
Annular space between 150mm pipe and borewell wall shall be filled with gravel.
Top of the 150mm pipe shall be sealed with provision of Air vent.
A filter pit of suitable dimensions say, 2.5 x 2.5 x 2.5 m. shall be constructed around
borewell
Quality of water used for recharge should be that, the water is clean and free from
silt and any other contamination
a. Recharge tube well Design & Specification :-
Specification of deep tube well
300 mm dia X 150 mts. depth
Expected recharge- 10,000 lits/hrs
Clay packing 10 m to Ground level
Expected cost of Recharge tube well 3 lacs.
Tube well is to be drilled in alluvium cum basalt formation (DTH Bore).
Filter Pit for Recharge Tube well :-
Function:-
Main function is to reduce turbidity of raw water to reduce chocking of gravel pack.
Keep feeding filtered water to recharge well.
Importance:-
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.44
To sustain the recharge process.
To maintain the recharge rate.
The system is gravel less system, maintenance free, Provides effective sustainable
recharge rate transparent process etc.
I. Recharge pit around Tube well
Specification
Recharge pit size 2.5 x 2.5 x2.5 mts. Depth
Recharge unit:- Vee wire screen (ss304) size 150 mm X 300 mm dia length of unit 1.5
mts.
Provision for air vent should be done
150 mm size screen - Slot size 0.5 mm
300 mm size screen – Slot size 0.75 mm
Coarse sand packing between two screen space.(1.0 mm size coarse sand)
Diagram of recharge pit with borewell is attached.
One recharge tubewell of size 300 mm dia x 150 mts depth as per recharge tubewell
design is recharging 10,000 lits/hr. Hence one recharge tubewell can recharge 10,000 X
24 X 30 = 7200 m3 water/year with provision of 500 m3 water capacity of farm pond
(20x15x2m size) for continuous availability of water.
J. Recharge Pit in Pond:-
Recharge by recharge pit is the only method for artificial recharge of unconfined aquifer
or phreatic aquifers. The recharge is instantaneous and there are no transit losses and
evaporation losses. Artificial recharge is an important aspect of ground water
management as it provides storage space free of cost, during dry period. The
underground reservoirs can be used for indefinite period, if properly operated, and
quality of phreatic aquifer will be improved.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.45
It is a common observation that phreatic aquifers are not always hydraulically in
connection with the surface water. For effective recharge of rain water to the shallow
aquifer the less permeable horizons have to be penetrated so that the aquifer to be
recharged is made directly accessible. Recharge pits are structures which overcome the
difficulty of artificial recharge of phreatic aquifer from surface water source i.e. Farm
pond. Recharge pits are excavated of variable dimensions that are sufficient by deep to
penetrate less permeable strata. In many pits most of the infiltration occurs laterally
through that wall of the pit.
The lateral hydraulic conductivity is considerable larger than the vertical, non silty
water should be recharged whenever possible so as to minimize silt accumulation and
periodic removal costs. Attention to the geometry of recharge pit is important in order to
obtain the maximum infiltration rate. The small pits may be either used as small ponds
or back/filled by gravel-sand filter material over a thick layer o cobble-boulder in the
lower portion of the pit.
The bottom area of open pit may require periodic cleaning by manual methods as
mechanical equipment cannot be deployed. The top sand filter bed of filter packed pit
also requires periodical replacement.
Design of Recharge pit in pond
Size 3m dia X 3m depth
Filter media as under
1m depth coarse sand in top the pit
1m depth gravel in middle of the pit
1m depth boulder in bottom of the pit
Expected recharge 7000 lit/hr. hence 5040 m3 water/year (7000x24x30)
K. Trench cum borewell :-
This technique is applied for recharging the aquifer by constructing trench
cum borewell.
Design and Methodology»
A borewell of 300 mm diameter shall be drilled to the desired depth depending on
geological conditions.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.46
Weathered zone of borewell shall be cased with perforated pipe
A 150mm diameter perforated G. I. pipe/ PVC pipe shall be lowered to the entire
depth of borewell.
Annular space between 50mm pipe and borewell wall shall be filled with gravel. Top
of the 50mm pipe shall be sealed.
A pit of suitable dimensions say, 2 x 2 x 2m. shall be constructed around borewell
and shall be filled with gravel.
The side walls of the pit shall be provided with polythene lining.
Quality of water used for recharge should be such that, the water is clean and free
from silt and any other contamination
Expected recharge 5000 lit/hr. hence 12000 m3 water/year (5000x24x100)
L. Runoff Calculation :-
The Project area of Pawan Formalin Pvt. Ltd. at Jambudiya, Taluka Morvi , Dist. Morvi is
10060m2. The dependable Rainfall of the project area is 660 mm i.e. 0.660m.
Available Rain water for area 10060 m2 is 3730m3 water.
Total consumption of project area is 65450 lits/day i.e. 22976 m3 water per year. Hence
the total consumption is more than the rain water available for recharge from the
project area.
One recharge tubewell of size 300mm dia x 120 mts. depth as per recharge tubewell
design is recharging 10,000 lit. per hour. Hence one recharge tubewell can recharge
7200 m3 water per year with provision of 500 m3 water capacity of farm pond (20 x 15 x
2 m size) for continuous availability of water.
In Morvi District average 30 rainy days in a year and due to storage of 500 m3 capacity
of Farm pond 30 days in a year can recharge by one recharge tubewell if water is
available continuously for recharge.
The consumption of 22976 m3 water for the project area is to be recharged for reducing
environment impact. From the project area 3730 m3 water is available for recharge.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.47
Hence remaining 19246 m3 water are to be diverted to farm pond from outside of the
project area or 19246 m3 water can be recharge in the land of owner’s of the project or
recharge in Government Pond with trench cum borewell or recharge pit, pit can
recharge 7000 lit/hr i.e 7000x24x30=5040 m3 water.
M. Recommendations :-
Looking to the Geohydrology of the area, rainfall intensity, it is proposed to drill one
Recharge tubewell or Trench cum Borewell in one farm pond, having capacity of 500 m3
water for maximum recharging of 5520m3 rain water in project area.
Looking to the Geohydrology of the phreatic aquifer, it is proposed to construct one
recharge pit and two Trench cum Borewell in pond having capacity of more than 1100
m3 water outside the project area or village pond area or Farm pond of owner’s land for
maximum recharging of 19246 m3 rain water. Hence it is most economical viable option
for recharge activity for recharging total 20346 m3 water.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.48
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.49
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.50
Pawan Formalin Pvt. Ltd.. Map Sheet # 41J13 Project site : At Jamudiya, NH8A, Morvi-Wankaner Road, Morvi
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.51
Table 4.12 Negative Impacts and Mitigations during Operational Phase
Operational Impact
Disci-
pline
Negative Impacts Probable
Source
Mitigative Measures Remarks
Water Deterioration of
Ground water
quantity
Bore well The water conservation is
maximum with the adopted
technology i.e zero discharge’.
Negligible amount of
wastewater generated and it
will be treated and used
properly.
Minimum water
will be used in this
adopted
technology
Air Increase in Dust
and SO2 levels in
ambient air.
Stack
emissions, raw
material
storage and
transportation
Multi cyclone dust collector
will be installed to control
Particulate matter. Maximum
stack heights will be provided
for the proper dispersion of
pollutants. Motor able roads
in the plant area will be
paved to reduce dust
emission.
By using imported coal as fuel
the dust emissions will be
minimized.
The resultant air
quality will
confirm to the
stipulated
standards. The
installation of air
pollution control
equipment and
emissions will be
controlled under
specified norms.
Solid
waste
Dust and ash from
air pollution
control equipment.
Coal based
boiler
Ash will be disposed to brick
manufacturers.
The solid waste
generated from the
plant will be send
to authorized
reprocessor.
Ecolog Impact on plant Emissions Green belt shall be developed Proper green belt
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.52
y species from stack in such a way that they will
act as sinks to pollutant.
Pollution resistant/ tolerant
plant species shall be selected
to minimize damage to
vegetation. The increased
biomass and species diversity
will lead to sustainable
development of ecosystem.
planning with
diversified species
control soil
erosion, improve
Soil moisture and
organic matter and
leads to
sustainable
ecosystem.
Noise Increase in noise
levels in the plant
area.
Equipment in
main plant
and
auxiliaries.
Equipment will be designed
to conform to noise levels
prescribed by regulatory
agencies. Provision of green
belt and plantation would
further help in attenuating
noise.
Increase in
greenbelt
development,
proper equipment
maintenance can
minimize noise
emanation. The
employees
working in high
noise areas would
be provided
earplugs/ earmuffs
as protective
device.
Socio-
econo
my
More pressure on
existing amenities
like housing, water
demand etc.
Increase in
employment
employees/
laborers.
No land acquisition or
rehabilitation is needed as
Additional infrastructure
facilities will be created.
Creation of employment will
improve economic status of
the people residing within
study area.
Overall socio-
economic status of
the area is
expected to
improve. The
project will help to
meet the present
demand of the
product for some
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.53
extent in the
market.
4.9 MONITORING OF WATER CONSUMPTION
Continuous efforts will be made to reduce the water consumption and thereby to reduce
the wastewater generation. Flow meter will be installed for the entire major water inlet
and the flow rates will be continuously monitored. Periodic water audits will be
conducted to explore the possibilities for minimization of water consumption.
4.10 OTHER INFORMATION
Land
The proposed plant will not alter major land use pattern except plant erection.
Enough parking places will be provided.
The landscape will improve because of well planed green belt development and
bitumen roads.
Water
Zero discharge of water.
Flora
The proposed green belt will have more diversity and leads to sustainable
ecosystem and there is possibility to attract more birds.
Fauna
As the land requirement is only 10060 Sq. Mt., there will not be any significant
impact on the fauna. The green belt may attract avifauna.
Air Quality
There will be Multi cyclone dust collector provided for reducing stack emissions.
The stack heights will be 30 m to provide proper dispersion of pollutants.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 4.54
Noise
Proper acoustic enclosures will be provided at noise generating sources surrounded
by green belt
4.11 Occupational Health Surveillance
Occupational Health Surveillance shall be undertaken as regular exercise for all the
employees especially for those engaged in handling hazardous substances.
Occupational Health Centre (OHC) for medical examination of employees with all
the basic facilities will be established within the plant. All the first aid facilities shall be
provided.
The medical records of each employee shall be maintained separately. Pre-
employment medical examination shall be conducted.
All workers shall be medically tested once in a year and at the end of his term of
employment.
Noise levels at the critical areas will be monitored regularly and the workers at high
noise generating areas will undergo audiometric tests once in six months.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.1
5.0 ENVIRONMENTAL MONITORING ASPECTS
5.1 Implementation Schedule of Mitigation Measures
5.1.1 Introduction
The mitigation measures suggested above will be implemented so as to reduce the
impact on environment due to the operations of the proposed plant. In order to
facilitate easy implementation, mitigation measures are phased as per the priority
implementation. The priority of the implementation schedule is given in the following
Table-5.1.
Table -5.1 Implementation of Schedule
Recommended
control measures Time Requirement
Implementation Schedule
Immediate Progressive
Water pollution Before commissioning of the plant -
Noise pollution Along with the commissioning of the plant -
Ecosystem-Greenbelt
development Stage wise implementation -
Note: * indicates implementation of recommendations.
5.1.2 Institutional Arrangements for Pollution Control
5.1.2.1 Organization at Site
The environmental cell at the plant site in co-ordination with the environment
division at M/s. Pawan Formalin Pvt. Ltd., Gujarat will provide necessary services
on environmental issues during construction and operation of the project. This group
will be responsible for implementation of environmental management plan and
interaction with the environmental regulatory agencies, reviewing draft policy and
planning. This department interacts with Gujarat Pollution Control Board (GPCB),
MoEF, Central Pollution Control Board (CPCB) and other environment regulatory
agencies.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.2
5.2 Environmental Monitoring
An impact assessment study comprises two main phases:
Assessment of the present situation with regard to environmental problems; and
Prediction of the impact of future development and/or alteration in the operation and
design of existing installations.
Usually, as in the case of the present study, an impact assessment study is carried out
over a short period of time and the data cannot bring out all variations induced by
natural or by human activities. Therefore, regular monitoring program of the
environmental parameters is essential to take into account the changes in the
environment. The objective of monitoring is:
1. To verify the results of the impact assessment study in particular with regard to new
development;
2. To follow the trend of parameters which have been identified as critical;
3. To check or assess the efficiency of the pollution control measures;
4. To ensure that new parameters, other than those identified in the impact assessment
study, do not become critical through the commissioning of new installations;
5. To check assumption made with regard to the development and to detect deviations
in order to initiate necessary measures; and
6. To establish a database for future Impact Assessment Studies for new projects.
The attributes, which merit regular monitoring, are specified underneath
a. Air quality both at source and ambient atmosphere;
b. Water and wastewater quality;
c. Noise levels;
d. Ecological preservation and greenbelt development;
e. Socio-economic aspects.
The Post Project Monitoring to be carried out at the industry level is discussed below.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.3
5.2.1 Monitoring and Reporting Procedure
Regular monitoring of important and crucial environmental parameters is of immense
importance to assess the status of environment during plant operation. With the
knowledge of baseline conditions, the monitoring program can serve as an indicator for
any deterioration in environmental conditions due to operation of the plant and suitable
mitigatory steps could be taken in time to safeguard the environment. Monitoring is as
important as that of control of pollution since the efficiency of control measures can only be
determined by monitoring. The following routine monitoring program would therefore be
implemented.
A comprehensive monitoring program is suggested in Table 5.2. The environmental
attributes will be monitored as given below
Table 5.2 Monitoring Schedule for Environmental Parameters
No Particulars Monitoring
Frequency
Duration of
Sampling
Important Monitoring
Parameters
I Air Pollution & Meteorology
A Stack Monitoring
1 Stack (2 stacks) Once in a month 60 minutes SO2, NOx, PM, VOC
Temperature, velocity
B Ambient Air Quality Monitoring
1 Project site and 3 more
specified locations Once in a month
24 hrs
continuously
PM10, PM2.5, SO2, NOx,
HydroCarbon, Volatile Organic
Compound
C Meteorology
1
Meteorological data to be
monitored at the proposed
plant.
Daily Hourly data
for 24 hours
Wind speed and direction,
temperature, RH& RF
II Water and Wastewater Quality
A Effluents
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.4
1 Domestic & Sanitary
effluents Once in a month
24 hr
composite
pH, salts, COD, BOD, SO2, Cl,
O&G and metals
B Ambient Water quality
1 Surface Waste
Once in a season
except for heavy
metal which will
be monitored
annually once.
Grab
Parameters specified under
IS:2296 (Class C) and IS:10500,
1993
III Ambient Noise Levels
1
On the Plant Boundary
Any other location Once in 6 months
24 hr
continuous
with one hr
interval
-- 2
specified by CPCB
5.2.2 Methodology for Ambient Air Quality Assessment
5.2.2.1 Ambient Air Quality Monitoring
The Ambient Air quality shall be monitored at project Site and two upward and
downstream locations once every quarter for SPM, PM10, PM2.5, NOx & SO2, and CO levels
during the Construction Phase and Operational Phase. The Ambient Noise Levels shall also
be monitored once every six months.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.5
The following methodology shall be adopted for monitoring of Ambient Air Quality
Table 5.3 Methodology for Ambient Air Quality Assessment
Pollutant Method of analysis
Vari
able
s
Dus
t PM10 Particulate Matter 10 IS 5182 (Part 23) (RA 2006)
PM2.5 Respirable Suspended Particulate Matter
STP No. TRA/STP/AA/02 Based on manual instrument manufactures.
Gase
s
SO2 Sulfur dioxide IS 5182 (Part 2): 2001 (RA 2002)
NOx Nitrous Oxides IS 5182 (Part 6): 2006 (RA 2002)
HC Non Methyl Hydrocarbon IS 5182 (Part 10): 2006
VOC VOC IS 5182 (Part 11): 2006
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.6
The limits for AAQ as per CPCB is given in the following Table 5.4
Table 5.4 National Ambient Air Quality Standards
Central Pollution Control Board (CPCB) 18th November, 2009 India
Pollutants
Time
weighted
average
Concentration in Ambient Air
Method of Measurement Industrial Resi.
Rural & Other
areas
Ecological Sensitive
Area (Notified By
Central Govt.)
Sulphur
Dioxide (SO2)
Annual
Average * 50 g/m3 20 g/m3
1. Improved West and
Geake method
24 hours** 80 g/m3 80 g/m3 2. Ultraviolet fluorescence
Oxides of
Nitrogen (NO2)
Annual
Average * 40 g/m3 30 g/m3
1. Jacob & Hochheiser
Modified
(NaOH - NaAsO2) Method
24 hours* 80 g/m3 80 g/m3 2. Gas Phase
Chemiluminescence
Particulate
Matter (size >
10 m) (PM10)
Annual
Average * 60 g/m3 60 g/m3
1. Gravimetric
2. TOEM
3. Beta Attenuation 24 hours** 100 g/m3 100 g/m3
Particulate
Matter
(size > 2.5 m)
(PM2.5)
Annual
Average * 40 g/m3 40 g/m3 1. Gravimetric
2. TOEM
3. Beta Attenuation 24 hours** 60 g/m3 60 g/m3
Ozone (O3)
8 Hours** 100 g/m3 100 g/m3 UV. Photometeric
Chemilminescences
Chemical Method 1 Hour ** 180 g/m3 180 g/m3
Lead (Pb)
Annual
Average * 0.5 g/m3 0.5 g/m3
AAS /ICP Method after
sampling using EPM 2000
or equivalent filter paper.
ED-XRF Using Teflon
Filter
24 hours** 1.0 g/m3 1.0 g/m3
Carbon
Monoxide (CO)
8 hours** 2.0 mg/m3 2.0 mg/m3 Non dispersive infrared
spectroscopy 1 hour** 4.0 mg/m3 4.0 mg/m3
* Annual arithmetic mean of minimum of 104 measurements in a year taken twice a
week 24 hourly at uniform interval
** 24 hourly / 8 hourly values should be met 98% of the time in a year. However, 2%
of the time, it may exceed but not on two consecutive days
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.7
Note:
a) National Ambient Air Quality Standard: The levels of air quality with an adequate
margin of safety, to protect the public health, vegetation and property.
b) Wherever and whenever two consecutive values exceed the limit specified above for
the respective category, it would be considered adequate reason to institute regular
/ continuous monitoring and further investigations.
c) The State Government / State Board shall notify the sensitive and other areas in the
respective states within a period of six months from the date of Notification of
National Ambient Air Quality Standards.
5.2.3 Methodology for Flue Quality Assessment
5.2.3.1 Stack Gas Monitoring
The emissions from the stacks will be continuously monitored for exit concentration of
Sulphur dioxide, Oxides of Nitrogen and Particulate Matter. Sampling ports will be
provided in the stacks according to CPCB guidelines.
For Monitoring of Flue gas the method for ‘Measurement of Emissions from Stationary sources (IS: 11255)’ shall be adopted.
5.2.4 Methodology for Water Quality Assessment
All the treated effluents will be monitored regularly for the flow rate and quality to identify
any deviations in performance of effluent and sewage treatment plants. Appropriate
measures will be taken if the treated effluent quality does not conform to the permissible
limits.
In case of maintenance/ cleaning of the system the settling tanks effluent from circulation
system is required to be discharged, it should be treated suitably to conform to the
following standards.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.8
For analysis of water and waste water the methodology specified in ‘Standard Methods for Examination of Water and Wastewater’ published by American Public Health Association (APHA) or IS: 3025 method entitled ‘Measurement of water Pollutants’ can be adopted. Ground water samples results were compared with IS: 10500 specification and surface water samples results were compared with Class ‘C’ water quality fit for drinking after conventional treatment as per IS: 2296-1982 tolerance limits.
Effluent discharge
(a) All efforts should be made to reuse and re-circulate the water and to
maintain zero effluent discharge.
(b) Strom water / garland drain should be provided in the plant.
Some of the guidelines shall be followed for the proposed project for achieving this
zero discharge levels are:
Minimizing quantity of effluents through re-use to the maximum extent feasible;
Settling tanks blow down tanks and neutralization pits will be cleaned regularly in
order to avoid clogging. Sludge will be removed regularly and sufficient time will
be given for proper settling of solids; and
The treatment units will be operated regularly
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.9
Table 5.5 Tolerance Limits for Drinking Water as per IS – 10500 – 1991
(Clause 3.1)
No
Substance or
Characteristi
c
Requirem
ent
(Desirable
Limit)
Undesirable Effect
Outside the
Desirable Limit
Permissible
Limit in the
Absence of
Alternate
Source
Methods of
Test(Ref to
IS)
Remarks
1. PH Value 6.5 to 8.5 Beyond this range
the water will affect
the mucous
membrane &/ or
water supply system
No relaxation 3025 (Part
11) 1984
--
2. Iron ( as per )
mg/l, Max) 0.3 Beyond this limit
taste / appearance
are affected, have
adverse effect on
domestic uses and
water supply
structures, and
promote iron
bacteria.
1.0 53 of 3025 --
3. Chloride ( as
Cl mg/l, Max 250 Beyond this limit,
taste corrosion and
palatability are
affected
1000 3025 (part
32) 1988
Desirable Characters
4. Dissolved
Solids mg/l,
Max
500 Beyond this
palatability
decreases and may
cause gastro
2000 3025 (Part
16) 1984
--
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.10
intestinal irritation.
5. Calcium (as
Ca) mg/l, max 75 Encrustation in
water supply
structure and
adverse effects on
domestic use
200 3025 (Part
40) : 1994
---
6. Sulphate ( as
SO4) mg/l,
Max
200 Beyond this causes
gastro intestinal
irritation when
magnesium or
sodium are present
400
(see col 7)
3025 (part
24) 1986
May be
extended
up to 400
provided
(as mg)
does not
exceed 30
7. Nitrate (as
NO3) mg/l,
Max
45 Beyond this
methaemo-
globinemia
100 3025 (part
34) 1986
--
Bacteriological Examination
Organism Unit Guideline Value
Fecal Coli-forms Number / 100 ml 0
Total Coli-forms Number / 100 ml 10
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.11
Table 5.6 Primary Water Quality Criteria for Various uses of Fresh waters as per
CPCB for Prevention and Control of Water Pollution (1979)
No Characteristics A* B* C* D* E*
1 Dissolved Oxygen (DO), mg/l,
min. 6 5 4 4 -
2
Biochemical Oxygen demand
(BOD)
mg/l , max.
2 3 3 - -
3 Total coli-form organisms**.
MPN/100 ml. Max. 50 500 5000 - -
4 pH Value 6.5-8.5 6.5-8.5 6.0-
8.5 6.5-8.5 6.0-8.5
5 Free Ammonia (as N), mg/l. max - - - 1.2 -
6 Electrical conductivity, micro
mhos/cm max - - - - 22.50
7 Sodium absorption ratio, SAR
max - - - - 26.00
8 Boron, mg/l, max. - - - - 2.00
* Use classes
** If the coli-form is found to be more than the prescribed tolerance limits, the criteria for
coliforms shall be satisfied, if not more than 20% of samples show more than the tolerance
limits specified and not more than 5% of samples show values more than 4 times the
tolerance limit. There should be no visible discharge of domestic and industrial wastes into Class ‘A’ waters. In case of class ‘B’ and ‘C’ the discharge shall be so regulated / treated as to ensure maintenance of the stream standards.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.12
Table 5.7 General Standards for Discharge of Effluents
No. Parameter
Standards
Inland surface
water
Public
Sewers
Land for
irrigation
Marine coastal
areas
1. Colour and odour See Note 1 -- See Note 1 See Note 1
2. Suspended solids, mg/l,
Max. 100 600 200
a) For process waste
water-100
b) For cooling water
effluent - 10 percent
above total
suspended matter of
influent cooling
water
3. Particle size of
suspended solids.
Shall pass 850
micron IS Sieve
a) Floatable solids,
Max 3 mm.
b) Settle able solids
Max 850 microns.
4. Dissolved solids
(inorganic), mg/a, max. 2100 2100 2100 --
5. pH value 5.5 to 9.0 5.5 to 9.0 5.5 to 9.0
6. Temperature 0C, Max
Shall not exceed
40 in any
section of the
stream within
15 meters down
stream from the
effluent outlet.
45 at the point
of discharge --
45 at the point of
discharge.
7. Oil and grease, mg/l, max 10 20 10 20
8. Total residual chlorine,
mg/l, Max. 1.0 -- -- 1.0
9. Ammonical nitrogen (as
NH4+), mg/l, Max. 50 50 -- 50
10. Total Kjeldahl nitrogen 100 -- -- 100
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.13
(as N), mg/l, Max.
11. Free Ammonia (as NH3),
mg/l, Max. 5.0 -- -- 5.0
12. Biochemical oxygen
demand (5 days at 20 0C) 30 350 100 100
13. Chemical Oxygen
demand, mg/l, Max. 250 -- -- 250
14. Arsenic (as As), mg/l.,
Max. 0.2 0.2 0.2 0.2
15. Mercury (As Hg), mg/l,
Max. 0.01 0.04 -- 0.01
16. Lead (as Pb), mg/l, Max. 0.1 1.0 -- 1.0
17. Cadmium (as Cd), mg/l, 2.0 1.0 -- 2.0
18. Hexavalent chromium
(as Cr+6) mg/l, Max. 0.1 2.0 -- 1.0
19. Total chromium (as Cr),
mg/l, Max. 2.0 2.0 -- 2.0
20. Copper (as Cu), mg/l,
Max. 3.0 3.0 -- 3.0
21. Zinc (as Zn), mg/l, Max. 5.0 15 -- 15
22. Selenium(as Se), mg/l,
Max. 0.05 0.05 -- 0.05
23. Nickel (as Ni), mg/l, Max. 3.0 3.0 -- 5.0
24. Boron (as B), mg/l, Max. 2.0 2.0 2.0 --
25. Percent sodium, Max. -- 60 60 --
26. Residual sodium
Carbonate, mg/l, Max. -- -- 5.0 --
27. Cyanide (as CN-), Mg/l,
Max. 0.2 2.0 0.2 0.2
28. Chloride (as Cl-), mg/l
Max. 1000 1000 600 --
29. Fluoride (as F-), mg/l,
Max. 2.0 15 -- 15
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 5.14
30. Dissolved Phosphate (as
P), mg/l, Max. 5.0 -- -- --
31. Sulphate (as SO4-2), mg/l,
Max. 1000 1000 1000 --
32. Sulphide (as S), mg/l,
Max. 2.0 -- -- 5.0
33. Pesticides Absent Absent Absent Absent
34. Phenolic compounds (as
C6H5OH) mg/l, Max. 1.0 5.0 -- 5.0
35.
Radioactive materials :
Alpha emitters MC/ml.,
Max.
Beta emitters μc/ml.
Max.
10--7
10—6
10--7
10--6
10--8
10--7
10--7
10--6
Note
1. All efforts should be made to remove colour and unpleased odor as far as practicable.
2. The Standards mentioned in this notification shall apply to all the effluents discharged,
such as industrial mining and mineral processing activities, municipal sewage, etc.
3. Omitted by Rule 2 of the Environment (Protection) Fourth Amendment Rules, 1992
vide Notification G.S.R. 797(E) dated 01.10.1992, Gazette No. 396 dated 01.10.1992.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 6.1
6.1 INTRODUCTION
Disaster
An emergency is said to have arisen when operations in the plant are not able to cope
up with a potential hazardous situation i.e. loss of control of an incident cause the plant
to go beyond its normal operating conditions, thus creating danger. When such an
emergency evolves chain of events that affect the normal working within the factory
area and/ or which may cause injuries, loss of life, substantial damage to property and
environment both inside and outside the factory and a disaster is said to have
occurred.
The various steps involves in the process of Disaster Management can be summarized
as:
Minimize Risk Occurrence (Prevention)
Rapid Control (Emergency Response)
Effectively Rehabilitate Damaged Areas (Restoration)
Disaster Management Plan is involved by careful scrutiny and interlinking of :
Types and causes of disaster
Technical know-how
Resource availability
6.2 Types of Disaster
The various types of hazards are as follows
Natural Hazards
Technological or Manmade Hazards
The various type of Disaster that may occur is
Due to the fire and
Hurricane, cyclone and other natural calumniates.
Complex emergencies/conflicts, famine, displaced populations, industrial accidents
and transport accidents
6.2.1 Objectives of the Plan
The plan is developed to make best possible of Pawan Formalin Pvt. Ltd.,
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 6.2
Rescue the victims and treat them suitable.
Safe guard others (evacuating them to safer places).
Contain the incident and control it with minimum damage.
Identify the persons affected.
Preserve relevant records and equipment needed as evidence incase on inquiry.
Rehabilitate the affected areas.
6.3 IDENTIFICATION OF MAJOR HAZARDS
From the preliminary risk assessment study presented in Chapter 7 of this report,
some of the possible hazards are Formaldehyde, Methanol, phenol, melamine and
caustic.
6.4 OBJECTIVES OF THE PLAN
The plan will set into action immediately after a fire occurs inside the plant.
However fire hazard will be restricted to fuel tank storage area only and hence to
major disaster is envisage.
6.4.1 Basis of Plan
Pawan Formalin Pvt. Ltd. will prepare an onsite emergency plan. The basic
guidelines of the Plan are as given below:
Informative brochure on emergency will be distributed to each staff member of the
plant and telephone numbers of key personnel to be contacted during an emergency
will be placed at all the operator placement point in the plan.
Workers would be trained regularly on fire hazard drill and mock drill will be
organized once in a year from the safety and fire agency.
24 hours vehicle for service and in-plant first aid emergency kit would be provided.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 6.3
6.4.2 Post Disaster Analysis and Evaluation
When emergency is over, it is desirable to carry out a detailed analysis of the causes
of the accident, to evaluate the influence of various factors involved and to propose
methods to eliminate them in future. Simultaneously, the adequacy of the disaster
preparedness plan will be evaluated and any short comings will be rectified.
6.4.3 General Recommendations
All non-routine work etc. should be carried out under a permit system.
Adequate number of caution boards high lighting the hazards of chemicals to
be handled, eye bath and emergency showers should be provided at critical
location.
Adequate number of absorbents should be placed at accessible locations in the
tank farm area as well as in the pump house that would enable to contain spills
immediately.
Adequate color coding and labeling of the pipelines should be provided for
easy identification of products proposed to be handled through them.
The damage distance due to any failure could be reduced, by reducing the time
required to stop the leak, which in turn would reduce the quantity of spillage.
The response time could be reduced by installing /maintaining instruments,
effective communication system, etc.
It is recommended that rubber mats be provided in front of electrical panel of
the entire plant with a view to prevent employees from receiving electric
shocks.
It is suggested that all type of fire extinguishers be placed at appropriate places
for easy access in case of emergency.
6.4.4 The availability, organization, and utilization of resources for emergency
The organizational set-up necessary for chain of commands during emergency
situation, which may arise in the premises, is given in Fig. 6.1. The system is
described in following Subsections
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 6.4
Figure – 6.1 on Site Disaster Management Plan
Functions and Responsibilities of following persons;
Factory Manager
He shall be the main guiding person for direct emergency operations.
Safety officer
The main responsibility of safety officer is safety management.
The Safety management includes the implementation of prevention methods to
avoid incident or accident and handling of emergency in case of accident.
Skilled person
He shall be responsible for the operation and maintenance.
Skilled person
He shall be arranging the safety equipment accordingly.
He shall be followed the instruction of supervisor and officer.
6.4.5Emergency Response Room (Safety officer room)
The place identified as Emergency Response Center will be considered as the Security
Gate Office. The location of the Emergency Response Center may change in future as
Factory Manager
Safety officer
Un-skilled personSkilled person
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 6.5
per convenience. The facilities available at the Emergency Response Center shall
include:
1) Internal Telephone
2) External Telephone
3) Manual Fire/Emergency Siren
4) Siren Actuation Switch
5) Important Address and Telephone Numbers
6) Emergency Vehicles
7) Confined Space Entry Procedure
8) List of Antidote/actions to be taken in case of hazardous chemical/materials.
9) Material Safety Data Sheets of chemicals
10)A copy of On-Site Disaster Management Plan
All communications after General Shift working hours and on Sundays/ Holidays are
to be routed through the Security Gate Office.
General Rules
1) Follow sense of discipline and do not panic.
2) Do not rush and endanger your personnel safety
3) Use personnel protective equipment according to the situation
4) Do not block any passages, which may hinder the movement of emergency vehicles.
5) In case you have to shut down your plant operation, do it in an orderly manner as
per standard operating procedures.
6) In situation when you have to leave your work and evacuate to identify places out
of operating areas, do it in an orderly manner.
7) Follow instructions of the Safety officer.
8) Understand the Disaster Management Plan well and take interest in practice mock
drill.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 6.6
6.4.6 Fire Fighting Facilities
A. Fire Buckets / Fire Extinguishers
Fire buckets and portable fire extinguishers (2 nos.) will be provided in all the areas
depending upon the specific needs of the area. Some spare equipment will also be
maintained in the inventory at an identified fire & safety equipment store.
B. Fire Alarm Sirens
It shall be provided to alert all the employees inside the premises about the situation of
an emergency.
C. Sand Buckets
5 nos. of sand buckets will be provided within the industrial premises in case of
emergency fire.
D. Oxygen cylinder
1 no. of oxygen cylinder will be provided for emergency.
E. Safety Equipment
All types of personnel protective safety equipment required for handling the emergency
are to be arranged in the Wonder Industry site. Some of the protective equipment is as
follow:
Canister/Cartridge type masks
Dust Masks
PVC suits, Aprons
Safety showers/ Eye Wash fountains
Other personnel protective appliances, like safety glasses, gumboots, helmets, hand
gloves, face shields, safety belts, safety ladders, safety torches, blankets.
6.4.7 Other Key Personnel
All key personnel will wear red helmet for their identification and easy recognition.
The responsibilities and duties of key personnel include.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 6.7
1. Safety
The safety officer/ supervisor will carry out the following:
To provide necessary equipment like fire fighting equipment (FFE) and personal
protective equipment (PPE).
To accompany factory inspector during investigation of the emergency.
To train workers/ supervisors in safety and safe operating procedures.
To assist the site main controller, incident controller in preparing a brief report of
the incident.
2. Assembly Points:
The assembly points for gathering non-essentials workers / persons will be fixed
and will be clearly marked as per the wind direction.
3. Fire Control Arrangement:
Fire fighting trained personnel will be made available in all the shifts. The
responsibilities and duties include:
To fight the fire with available internal fire fighting equipment and to stop leakage
of liquid etc.
To provide personal protective equipment to the team.
To cordon the area and inform incident controller or site main controller about the
development of emergency.
To train the persons (essential workers) to use personal protective equipment and
fire-fighting equipment.
4. Medical Arrangement:
The responsibilities and duties include:
To provide first aid to the affected persons, and, if necessary, send them to hospitals
for further treatment.
To keep a list of blood groupings ready and update.
5. Transport Evacuation Arrangement:
For transportation of people, company’s vehicles, cars, rickshaws etc. will be
utilized.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.1
CHAPTER – 7 Risk Assessment 7.1. INTRODUCTION OF COMPANY M/s. Pawan Formalin Pvt. Ltd. is a small scale unit proposed to be located at Survey No.24/P, Village: Jambudiya, Taluka: Morbi, District: Morbi-Rajkot-363642, Gujarat. Details of unit as follow:
Sr. No. Details Compliance
1 Full Name and Address of unit :
M/s. Pawan Formalin PVT. LTD. Survey No.24/P, Vill.: Jambudiya, Taluka: Morbi, District: Morbi-Rajkot-363642, Gujarat
2 Telephone No. : --
3 Metrological Data : Latitude : 22° 47’ 06.87” N Longitude : 70° 54’ 05.61” E
4 Full Name and Address of the Occupier :
Kumar K. Kothi-Director M/s. Kanji Parshottam & Brothers, Opp. Gandhi Baugh. Near Union Bank of India, Morbi-363641
5 No. of Shift and Shift Timing : 2 nos. 6 No. of Staff : 30 nos. 7 Emergency Facilities
8
Nearest Railway station Nearest Police Station Nearest Fire Station Nearest Hospital/Dispensary
: : : :
Nazarbaug railway station: 10.1 km. City police station, Morbi: 13.8 km. Morbi fire brigade: 13 k.m. Krishna Multi Speciality Hospital, Morbi: 14 k.m.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.2
7.2. OBLECTIVE, PHILOSOPHY & METHODOLOGY OF RISK ASSESSMENT:
OBJECTIVE: The main objective of the Risk Assessment study is to determine damage due to major hazards having damage potential to life and property and provide a scientific basis to assess safety level of the facility. The secondary objective is to identify major risk in manufacture of chemicals, storage of chemicals and provide control though assessment. To prepare on- site, off site, disaster management plan for control of hazards. PHILOSOPHY: The main philosophy of risk assessment is to find out the real cause of accident and then based on it to suggest appropriate remedial measures to prevent its recurrence. To find out unsafe action negligence, omission or personal fault METHODOLOGY: To find out the quantitative Risk Assessment study as follow. Identify Vulnerable Zone for toxic dispersion, pool fire, Tank on fire (Thermal Radiation), Flash Fire, and Explosion over pressure (Vapor Cloud Explosion) by using software.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.3
7.3. DETAILS OF RAW MATERIALS
Sr. No. Name Of The Raw Material
Physical State Capacity Storage Material of
Construction No.
1 Formaldehyde Liquid 200 KL Tank S.S.-304 3
2 Methanol Liquid 100 KL Tank MS 3
3 Ammonia Gas 10 m3 Tank M.S.Bullet 2
4 Caustic Soda Solid 50 Kg Bags HDPE 113 bag/day
5 Melamine Solid 50 Kg Bags HDPE 56 bag/day
6 Urea Solid 50 Kg Bags HDPE 76 bags/day
7 Wood Pulp Solid 50 kg Bags HDPE 1000 bags/day
8 Metalic Stearate ? ? ? ? ?
9 Zinc Sulphite ? ? ? ? ?
10 Barium Powder Solid 50 kg Bags HDPE 1680 bags/day
7.4. DETAILS OF FINISHED PRODUCTS:
SR. NO. Intermediate Product QUANTITY Mt/Month Storage Physical State
1. Formaldehyde (37%) 1800 MS Tank Semi Liquid
2. Urea Formaldehyde Resin 250 MS Tank Semi Liquid
3. Melamine Formaldehyde Resin 250 MS Tank Semi Liquid
4. U. F. Molding Powder 250 --- ---
5. Hexamine 90
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.4
7.5. LIST OF HAZARDOUS CHEMICALS ALONGWITH THEIR TOXICITY LEVEL AS PER MSIHC RULES
Sr. no.
Chemicals TLV
Toxicity Level Flammable Limit
Chemical Class (As per MSIHC Rules)
LD50 Oral Mg/Kgs
LD50 Dermal Mg/ Kgs
LC 50 Mg/L
LEL%
UEL%
FP0C BP0C
Class (As per petroleum classification)
1 Formaldehyde
0.3/l ppm 100 270 203 6 36
.5
500C CC
600C CC
96 B
Flammable, Toxic, Hazardo
us
2 Methanol 200 ppm 5628 1580
0
64000 ppm/ 4 hr
6 36.5 12 0C 64.5 A
Very high
flammable
3 Ammonia
25 ppm TWA
35 ppm STEL 300 ppm IDLH
--- --- 2000 ppm/4 hr
16 25 --- -33.3 --- Hazardous and Toxic
4 Caustic Soda 2 mg/m3 N.A N.A N.A N.
A N.A N.A 1388 -- Hazardo
us
5 Melamine N.A 3161 1000 N.A N.A
N.A
93.3 0C N.A C
Slightly flammabl
e
6 Urea -- 8741 -- -- N.A
N.A N.A N.A -- N.A
7 Zinc Sulphate N.A N.A N.A N.A N.
A N.A
N.A N.A N.A Hazardous and Toxic
8 Barium Powder
? ? ? ? ? ? ? ? ? ? Note: CC: Close Cup, OC: Open Cup, N.A.: Not Available The Toxicity level of hazardous chemicals as per Manufacture, storage and import of Hazardous Chemical (Amendment) Rules, 2000 (MSIHC) is shown as below
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.5
Toxicity Index as per MSIHC Rule 2000
Sr. No
Toxicity Oral Toxicity LD50 (Mg/Kg)
Dermal Toxicity LD50 (Mg/Kg)
Inhalation Toxicity LD50 (Mg/Kg)
1 Extremely Toxic
<5 <40 <0.5
2 Highly Toxic
>5- 50 >40-200 >0.5-2
3 Toxic >50-200 >200-1000 >2-10
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.6
7.6. HAZARD IDENTIFICATION AND PREVENTIVE MEASURES 7.6.1. Raw Material Storage hazards and controls:
Sr. No.
Name of material stored
Quantity (Max)
Operating press/ temp
Hazard Rating Systems
Type of hazard / Risk involved
Persons Affected
(1) Formaldehyde 3 X 200 KL
NTP
TLV – 0.3 PPM (1 ppm) NFPA Ratings: Health - 3 Flammability - 2
Reactivity - 0 Flash Point: 500C
Flammable Very toxic by
inhalation. Very toxic in contact
with skin. Very toxic if
swallowed. Causes burns. Limited evidence of
a carcinogenic effect. Risk of serious
damage to the eyes. May cause
sensitization by skin contact.
Operators Maintenance Technicians
Control Measures: Dyke provision to storage tank Safety boards displayed on the tank Good ventilation must be provided Trap & collect spills with Sand or other inert solids Use an approved gas mask in un-ventilated areas if necessary because of fumes. Handling of Formaldehyde with Safety glasses, Nitrile or butyl rubber gloves
(2) Methanol 3 X 100 KL NTP
TLV – 200 PPM (8-hr TWA) STEL-250 PPM NFPA Ratings: Health: 1 Flammability: 3
Highly Flammable Toxic by inhalation Toxic when contact
with Skin Toxic if swallowed Danger of very
serious irreversible effects.
Operators Maintenance Technicians
Control Measures: Keep away from sources of ignition, tight closed container and dyke provision to storage tank Safety board’s displayed on the tank Effective ventilation must be provided. For accidental contact if you feel unwell, seek medical advice immediately Handling of Methanol with Safety gloves and protective clothing
B
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.7
Sr. No.
Name of material stored
Quantity (Max)
Operating press/ temp
Hazard Rating Systems
Type of hazard / Risk involved
Persons Affected
(3) Ammonia 2×10 m3 NTP
TLV: 25 ppm, STEL: 35 ppm, IDLH: 300 ppm
Explosion hazard moderate when exposed to flame.
When heated emits toxic fumes.
To fight fire, stop flow of gas.
Operators Maintenance Technicians
Control Measures: Storage should be cool, dry, well ventilated and protected from external heat source. Storage tank construction should be of integrity and double wall type known as ‘can in tank’ type.
Non refrigerated ammonia shall be stored in gas tight containers. There must be fire fighting extinguishers, personal protective equipment and notice of operating/handling instructions.
Vent line should be provided with loose fitting rain caps. The insulation of pipelines carrying Liquid Ammonia should be maintained properly. Proper selection of MOC of plant and equipment for handling ammonia is strongly recommended.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.8
7.6.2. Process hazards and controls:
Name of hazardous process and operation
Material in the process / operation
Type of hazard possible toxic gas release / fire / explosion / run away reaction / rupture, etc.
Control measured provided
Chilling plant
Steam & Cooled Water
Handling of refrigerent Cold burns
Annual inspections Safety interlocks to be provided Safety and pressure gauge valves fitted Properly supported and protected
against corrosion Testing of Jackets and joints of tubes
regularly
Reactor Vessel
Formaldehyde, Melamine, Urea
Exothermic Run-away reaction
Release of Heat and Flammable gases
Fire, Toxic gas release and Explosion
Raw Materials quantity must be controlled either volumetrically or gravimetrically.
Process control devices must be installed includes the use of sensors, alarms, trips and other control systems that either take automatic action or allow for manual intervention to prevent the conditions for uncontrolled reaction occurring.
High Temperature indicator valve and alarm system must be provided
Auto cutoff system must be provided after reaching of predetermined maximum safe temperature.
Pressure gauge is must provided. Safety Control valve is must be
provided. The Vessel Emergency Relief vent
should discharge to a suitably designed catch pot or should be so positioned that people working in the area and members of the public will not be in danger if the contents of the vessel are discharged.
Use skilled worker Proper selection of MOC Mechanical seal in all pumps and
reactors Transportation of finished product from
vessel to storage tank through
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.9
7.6.3. General Hazards & controls:
Type of Emergency
Identification of Area
Possible Causes Possible Results
Preventive/ control Measures
Fire Tank farm area
Fire due to Bottom nozzle failure
Damage of storage tank Pump discharge nozzle failure
Unloading road tanker hose rupture
Major fire in the tank farm, it may spread all over the company and surrounding area
May cause fatalities
Licensed and isolated storage tank farm.
Flame proof fittings. Earthling while unloading. Spark arrestor at main gate. Dip pipes on the tank for unloading.
Provision of dyke. Earthling of tanks and pumps.\
Get approval from an explosive department for plan approval, equipment layout & emergency control measures.
No electrical junction box close to storage materials.
Hot work permit system followed for hot working in the ware house.
Toxic Gas Release
Tank Farm Area and Reaction Vessel area
Cylinder blast Rupture of discharge valve Rupture of gas cylinder body Bursting of pipelines
Major gas exposure in the company and /or surrounding area of the company which resulting in irritation to respiratory track eyes and suffocation. More inhalation results in fatalities.
Storage Tank stored under shed and good ventilated area.
Procured by license holder party.
Fitted with valve protection cap.
Valve opened with special key.
Loading/unloading done safely.
Trained persons for Material Handling in Tank Farm and Storage Tank area.
Periodic hydraulic testing through competent person by supplier
Painted according to its color code.
Explosion All Material
Vapor explosion due
Improper discharge of
Flameproof electric installation areas & use
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.10
handling areas
to contact of spark to accumulated flammable vapor in confined area
static charge Use of non
FLP equipment for solvent handling
Metal to metal impact
Electrical short circuit
Open flame
spark less tools Isolated storage of Flammable material drums
Hot work permit for hot working in the plant
Earthling for human static charge
Good ventilated area for Flammable material storage
Material handling In Plant
Flammable, eye irritating & body accident
Fire and health Hazards
Trained employee Required PPE and Fire Protective equipment Provided
Good engineering practice Separate storage are with dyke valve system provided
Methanol, Formaldehyde. Ammonia and Melamine Fire Protective System
Storage and other Operation Area
Spillage, Leakage and overflow,
Fire Hazard
Required Fire Extinguisher Provided Flame Proof Electrical Fitting Proper Earthling
arrangement Fire Hydrant System with
Jockey Pump Gas Detector
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.11
7.6.4.: Safe Practice for Handling, Storage, Transportation and Unloading of Hazardous Chemicals: For Storage/Handling:
1. Separate from strong oxidant. & Keep it in well ventilated room. 2. Dyke wall shall be provided to all above ground storage tank. 3. Fire hydrant system shall be installed. 4. Safety shower and eye washer shall be installed near storage area. 5. Flame proof light fitting shall be provided at flammable storage area. 6. Proper selection of MOC for chemicals storage tank. 7. Sprinkler system shall be installed at flammable material storage area 8. Earthing/bonding shall be provided for static charges.. 9. Flame arrestor shall be provided on flammable material storage tank vent. 10. Level gauge and level measurement instrument shall be provided on material storage tank. 11. Lightening arrestor on all chimney and building shall be provided. 12. Hazardous material should be stored away from the plant and safe distance shall be maintained. 13. Safety permit system shall be followed for loading, unloading of hazardous chemical. 14. Fencing, caution note, hazardous identification board should be provided. 15. Only authorized person shall be permitted in storage tank area and register will be maintained.
For Transportation & Unloading:
1. Solvent shall be received by road tanker and stored in above ground storage
tank in separated bulk storage area. 2. Loading and unloading procedure shall be prepared for material received
through road tanker. 3. Earthing/bonding shall be provided for static charges.. 4. Flexible steel hose shall be used for unloading from the road tanker. 5. Flame proof electric motor shall be used during loading/unloading. 6. NRV shall be provided on pump discharge line. 7. Fixed pipeline with pumps shall be provided for transfer to vessel. 8. TERM CARD will be provided to all transporters and shall be trained for
transportation Emergency of hazardous chemicals. 9. Personal Protective Equipment (safety goggles, hand gloves, apron, masks,
gum boots etc.) shall be provided.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.12
7.6.5.: Safe Practice for Handling, Storage, Transportation and Unloading of Ammonia: For Storage/Handling:
Storage should be cool, dry, well ventilated and protected from external heat source. A plan should be prepared for readily and definitely approaching all shutoff valves to be used for isolating various parts of the storage facilities.
Gauge glass should be provided with excess flow check valves. The gauge glasses should not be longer than 120 cm and more than 60 cm between supports.
Storage tank construction should be of integrity and double wall type known as ‘can in tank’ type. Each storage tank shall be equipped with two relief valves mounted on a 3-way hand valve to provide means for repair of faulty valve.
Facilities for creating water curtains around the ammonia vapors if they leak out. However, care should be taken not to add water to the liquid ammonia else it will worsen the situation.
Non refrigerated ammonia shall be stored in gas tight containers. A flare stack should be provided to burn ammonia vapor in case safety valve fails to release ammonia pressure.
Leaks of ammonia should be searched for, preferably with Hydrochloric acid solution or with a small cylinder of the compressed SO2 gas. Because of the fire risk, sulfur candles should not be used.
There must be fire fighting extinguishers, personal protective equipment and notice of operating/handling instructions.
A bund wall should be provided outside the radius of storage area, which should not be less than 1 m in height. This bund should have minimum capacity to contain 20 % of ammonia content in the storage.
The bund should have impervious floor and provision for low point drain pit discharging flanged valve to remove any water collected. This flanged valve to remove any water collected. This flanged outlet valve should normally be kept closed.
A remote operated shutoff valve should be provided in the bottom outlet as close as possible to the storage tank/sphere/cylinder.
The isolation valves below the pressure relief valves should be kept locked open or interlocked in such a way that always at least one of the two is in open position.
Vent line should be provided with loose fitting rain caps. A multipoint continuously Ammonia monitors with alarm should be installed in the storage and ammonia handling areas.
Proper selection of MOC of plant and equipment for handling ammonia is strongly recommended.
Preventive maintenance plan is advisable. Avoid contact of ammonia with incompatible chemicals like mercury, chlorine, iodine, bromine, calcium, silver oxide and hypochlorite.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.13
For Transportation & Unloading:
In the ammonia tank, truck and railway wagon loading/unloading station, technical provision should be installed to prevent trucks or rail wagons from being driven away while hose is connected. This could be a barrier which is removed only after hose and /or the load arms have been put back in its position.
The insulation of pipelines carrying Liquid Ammonia should be maintained properly. Excess flow valve is must.
7.7. OCCUPATIONAL HEALTH SURVEILLANCE PROGRAMME Health surveillance is the monitoring of a person’s health to identify changes in health status due to occupational exposure to a hazardous substance. It includes biological monitoring. Ideally, the avoidance of work-related diseases should be achieved by the prevention or controlling exposures to hazardous substances in the workplace. Where a process cannot be designed or maintained to eliminate the risk of exposure, it may be necessary for workers to undergo health surveillance. Aims of health surveillance:
1. Identify those at increased risk Health surveillance is used to identify workers who have an increased risk of developing an occupational disease. For example, people who have existing skin, kidney, liver and eye disorders, heart problem; additionally smokers and pregnant women are at increased risk of being severely affected if exposed to Methanol. 2. Compliance with regulations Health surveillance is sometimes required by laws and codes of practice (for example, a worker exposed to lead in battery manufacture or a spray-painted exposed to isocyanates in two-pack paints). Each state or territory has regulations containing a schedule of hazardous substances for which health surveillance is mandated. 3. Early detection The major purpose of health surveillance is to detect adverse health effects at an early stage so that the worker may be protected from further injury, either by control of the process or by removal from exposure. 4. Evaluating effectiveness of control measures Health surveillance is not a control measure in itself and should not be the sole means of determining whether control measures are effective. However, it can provide useful information on the effectiveness of safe working practices. 5. Epidemiology and disease Health surveillance can be used to evaluate the health experiences of groups of workers exposed to specific hazardous agents or working within a particular industry.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.14
Workers should be made aware that health surveillance is sometimes necessary to ensure their ongoing health. Health surveillance is often used in addition to workplace monitoring. Workplace monitoring will only indicate the potential for exposure of workers to a hazardous substance. It can never be an indication of the actual amount of substance absorbed or the effect on the body of absorbing the hazardous substance. When a toxic substance (such as an industrial chemical) is present in the environment, it contaminates air, water, food, or surfaces in contact with the skin: environmental monitoring evaluates the amount of toxic agent in these media. As a result of absorption, distribution, metabolism, and excretion, a certain internal dose of the toxic agent (the net amount of a pollutant absorbed in or passed through the organism over a specific time interval) is effectively delivered to the body and becomes detectable in body fluids. Subsequent interaction with a receptor in the critical organ (the organ which, under specific conditions of exposure, exhibits the first or the most important adverse effect) leads to biochemical and cellular events. Both the internal dose and the elicited biochemical and cellular effects may be measured through biological monitoring.
7.8. OCCUPATIONAL HEALTH PROGRAMME The health & physical hazards caused due to toxic, irritant, corrosive, flammable
materials. All chemicals are within Threshold Limit Value as per ACGIH. Monitoring of occupational hazards like noise, ventilation, chemical exposure etc.
will be carried out regularly and its record will be maintained. Good housekeeping, use of PPE, Engineering controls, Enclosure processes, scrubber
system, display of safety boards, SOP of loading / unloading, local exhaust ventilation, safety shower etc. are important safety measures have taken to keep these chemicals within TLV. Appropriate personal protective equipment will be provided & ensure the usage of
them. Workers will be trained on safe material handling of hazardous chemicals. Prepare & display the safe operating procedure for hazardous chemicals storage,
handling & transporting or using. Periodical medical examination of the workers & Liver Function Testes will be done. Register (form no.37) for work place air monitoring will be done. Employee training and education will be carried out. Control the noise at source by substitution, isolation, segregation, barriers etc. Local Exhaust ventilation and scrubber should be installed where it is required to
reduce fumes, vapors, temperature and heat stress. Insulate all hot equipment to reduce air temperature. Reduce the level of physical activity by sharing workload with other or by using
mechanical means.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.15
7.9. CHEMICALS WHICH ARE EXPOSED TO WORKERS DIRECTLY OR INDIRECTLY
(1) Formaldehyde (2) Ammonia (3) Methanol
Pre-employment medical checkup and periodically medical examination will be
done. Liver function test will be done during pre-placement and periodical examination.
7.9.1. Hazardous chemicals are within the Tlv/pel as per acgih recommendation by using gas monitor & work place ambient air monitoring as per GFR
FORM NO.37 (Prescribed under Rule 12-B) Register containing particulars of monitoring of working environment required under section 7-A (a) (e) Name of the Department/Plant: Raw Materials, by-products and finished products involved in the process.
Sr. No. Name of raw materials Consumption
Mt/Month
Formaldehyde- 1800 MT/Month
1 Methanol 810
Urea Formaldehyde Resin-250 MT/Month
1 Formaldehyde 125
2 Urea 84
3 Caustic (NaOH) 0.083
4 Methanol 42
Melamine Formaldehyde Resins-250 MT/Month
1 Formaldehyde 125
2 Melamine 84
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.16
3 Caustic (NaOH) 0.083
4 Methanol 42
Hexamine-90 MT/Month
1 Ammonia 46.35
2 Methanol 141.75
UF Molding powder-250 MT/Month
1 Formaldehyde 167
2 Urea 30
3 Caustic (NaOH) 0.5
4 Wood Pulp 50
5 Metallic Stearate 9.5
6 Zinc Sulphite 5
7 Barium Powder 83.75
8 Hexamine 8.75
1. Particulars of sampling
Sr. No.
Location/Operation Mentioned
Identified Contaminant
Sampling Instruments Used
Air Borne Contamination
Average
No. of Sample
Range
1 2 3 4 5 6 Sr. No.
TWA concentration as given in second schedule)
Reference Method
Number of workers exposed at the location being monitored
Remarks Signature of person taking sample
Name (in block letters)
7 8 9 10 11 12
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.17
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.18
7.10. TREATMENT OF WORKERS AFFECTED BY ACCCIDENTAL SPILLAGE OF METHANOL
Hazards With Acute Exposure Contact with skin may cause severe burns or systemic poisoning. Systemic effects may occur from any route of exposure, especially after skin absorption.
Hazards With Chronic Exposure
Repeated or prolonged exposure to Ammonia may harm the respiratory system. Can irritate and inflame the airways. Methanol affects the central nervous system, liver, and kidneys.
Special Safety Precautions
Prevent contact with skin by wearing neoprene gloves, lab coat, and resistant apron. Wear safety glasses or a face shield if splashing may occur. Store in a cool, dry, well-ventilated area, away from heated surfaces or ignition sources. Skin contact requires immediate washing of the affected area with soap and water. Remove contaminated clothing and launder before wearing again.
Procedure for treating workmen after skin contact
Skin contact requires immediate flushing of the contaminated area with soap and water at a sink or emergency shower for a good fifteen minutes. Remove contaminated clothing. In case of eye contact, promptly flush the eyes with copious amounts of water for 15 minutes (lifting upper and lower lids occasionally) and obtain medical attention. If methanol is ingested, obtain medical attention immediately. If large amounts of methanol are inhaled, move the person to fresh air and seek medical attention at once. It is recommended to provide the safety shower and eyewash station in plant.
7.10.1. ANTIDOTES
Antidotes for Methanol Ethanol (30 % solution from inside, 5 % solution from outside i.e. by intravenous
injection) Epicake syrup In case of acidosis give sodium bicarbonate In case of delirium give diazepam 10 mg by intravenous injection Folinic acid (leucovorin 1 mg/kg iv, 4 hourly)
Antidotes for Ammonia Skin Contact: Wash with plenty of water for 15 min. and then wash with dilute lactic
acid and apply Soframycin cream.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.19
Eye Contact: Wash with plenty of water in eye fountain for 15 min. and then put one drop of 0.4% Benzocaine (Novocaine) solution in eye. Boric or Lactic acid solution eye drops can also be given.
Swallowed: If entered in throat then give smell through cotton dipped in ethanol or ether through nose. Administer Oxygen in case of breathing difficulty.
Antidotes for Formaldehyde Milk Activated Charcoal or Water
7.10.2.: Details of fire extinguishers:
TOTAL: 25 NOs.
7.10.3.: Minimization of the manual handling of hazardous substance
Whether moving materials manually or mechanically, your employees should know
and Understand the potential hazards associated with the task at hand and how to control. Their workplaces to minimize the danger.
Employers and employees should examine their workplaces to detect any unsafe or unhealthful conditions, practices, or equipment and take corrective action.
Provide flameproof electrical motor & transfer chemicals through the pipelines. Use specially designed pallets to hold, move raw materials, finished products through
work areas. Minimize lifting of raw materials, heavy loads by using appropriate platforms, trolleys
etc. Avoid the moving, manual handling of hazardous material.
SR. NO. TYPE OF FIRE EXTINGUISHERS CAPACITY EXISTING PROPOSED
1 ABC powder type 5 kg -
25 2 DCP powder type 5 kg -
3 CO2 gas type 5 kg -
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.20
7.11. DO’S AND DONTS’
Handling of Chemicals
Do’s Don’ts Know the hazards of the chemical before
handling. Know the antidotes for chemical, which you
are handling. Do keep material safety data sheet in locations
where chemicals are being handled and study it. Use appropriate personal protective
equipment like gloves, aprons, and respirator; face shield etc. depending upon nature of the work.
Label every chemical that you use and tightly close the container.
Use eye wash fountain / safety shower in case of splash of chemicals in the eye or body for at least 15 minutes.
Segregate toxic, flammable chemicals and keep them under control.
In addition to draining and closing valves, lines should be blanked before taking up maintenance work.
Provide proper ventilation at the chemical handling area to limit their concentration within prescribed level.
Do not store the chemicals that are incompatible with other chemicals.
Do not spill the chemicals. Do not dispose chemical without
neutralizing. Do not keep large inventory of
chemicals. Do not allow empty containers of
hazardous chemicals to be used by others. Do not use compressed air for
transferring chemicals. Do not stand near chemical transfer
pump while it is in operation with temporary hose connection.
Pouring of chemicals by hand or doing siphoning by mouth should never be adopted.
Chemicals drums should never be moved without protection.
Do not attempt to neutralize the acid / alkali on the skin. Use water only.
Do not use solvent for cleaning hands.
Material Handling
Do’s Don’ts Use proper lifting tool and tackle having
adequate capacity. Only authorized persons should operate
material handling equipments. Each tool, tackle or equipment should have
number and safe working load (SWL) marked on it.
Assess weight of the material, distance to be carried and hazards etc. before lifting the load.
Inspect and test all the lifting tools and tackles regularly as per Factory Rules.
Wear Personal Protective Equipments while handling of material.
Do not use the equipment for the purpose other than its design intention.
Do not allow personnel to move underneath lifted load.
Do not load the equipment above its safe working load.
Do not use makeshift arrangements for lifting equipment without inspection and test.
Do not use defective tool and tackles. Keep the tools & tackles free from
adverse effect of atmosphere by applying suitable protective coating.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.21
Wherever possible, mechanized material handling shall be adopted.
While lifting a load physically, keep the load as near as possible to the body with feet properly placed for body balance.
Bend knees, keep back straight, keep the load closed to the body and lift the load.
The angle between the legs of two leg sling should not exceed 90 degree.
Do not allow male and female adult to lift a load manually higher than 55 kgs and 30 kgs respectively.
Do not hold the load with tip of the fingers; grasp the load firmly with palm.
Fire Prevention
Do’s Don’ts Follow ‘NO SMOKING’ sign. Deposit oily rags and waste combustible
material in the identified containers and dispose them suitably.
Fire Hose used for any other purpose should be permanently marked and taken out of fire hydrant system.
Keep minimum inventory of flammable and combustible substances.
Take permission before breaking or removal of fire barrier and ensure subsequent relocation of fire barrier.
Check periodically the operability of fixed fire fighting system.
Attend any abnormality / deficiency with fire protection system promptly.
Provide earthling or bonding to prevent accumulation of static charges to tanks where flammable chemicals are stored / handled.
Use instruments that are intrinsically safe in explosive atmosphere.
Do not leave flammable material like acetone, kerosene etc. used as cleaning agent at the work area.
Do not over tighten fire hydrant valves with F-lever.
Do not allow wild grass growth around storage of the gas cylinders and switchyard.
Do not obstruct accessibility to the fire related equipment.
Do not destroy the inspection tag provided with the fire equipment.
Do not misuse fire-fighting equipment other than intended purpose.
Do not store the flammable material in the open container.
Do not use instruments that are not intrinsically safe in the explosive atmosphere.
House Keeping
Do’s Don’ts Assign places for everything and maintain
things at assigned places. Clean the area after completion of work. Use aisle space free for personnel and
material movement. Ensure adequate illumination and
ventilation for the job. Drop paper, plastic, glass, metal and bio-
Do not leave combustible materials in the work area.
Do not smoke in the area of work. Do not allow dust bin to overflow. Do not generate extra waste. Do not disturb the safety equipment from
assigned location. Do not block emergency switches and on/off
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.22
medical waste in a separate bin kept for this purpose.
Know the location where emergency equipment such as first aid box, fire fighting equipment, SCBA, Stretchers are kept.
Arrest all types of spills such as chemical, water, oil, air / gas, steam etc. and clean up the area immediately.
Ensure exits are indicated / painted for use during emergency.
switches of the equipment by storming of materials in front of work.
Do not leave cleaning agent like acetone, isopropyl alcohol, kerosene etc. at the work area after completion of work.
Do not block fire exit point by storing materials or by means.
Do not leave a spillage unattended.
7.12. RISK ANALYSIS AND CONSEQUENCE ANALYSIS
ALOHA is an air dispersion model, which you can use as a tool for predicting the movement and dispersion of gases. It predicts pollutant concentrations downwind from the sources of a spill, taking into consideration the physical characteristics of the spilled material. ALOHA also accounts for some of the physical characteristics of the release site, weather conditions, and the circumstances of the release. Like many computer programs, it can solve problems rapidly and provide results in a graphic, easy to use format. This can be helpful during an emergency response or planning for such a response. ALOHA provide output as amount of chemical discharged from the source as well as its concentration in air it takes into account different levels of concentrations for a specified chemical. Software used for calculation- ALOHA (Areal locations of Hazardous atmospheres) Aloha is a computer program designed especially for use by people responding to chemical accidents, as well as for emergency planning and training. ALOHA can predict the rates at which chemical vapors may escape into the atmosphere from broken gas pipes, leaking tanks and evaporating puddles. It can then predict how a hazardous gas cloud might disperse in the atmosphere after an accidental chemical release. ALOHA provides output as amount of chemical discharged from the source as well as its concentration in air it takes in to account different levels of concentrations for a specified chemical. Different concentration levels are given below: ERPG 1: is the maximum airborne concentration below which it is believed that nearly all individuals could be exposed for up to 1 hour without experiencing other than mild transient adverse health effects or perceiving a clearly defined, objectionable odor. ERPG 2: is the maximum airborne concentration below which it is believed that nearly all individuals could be exposed for up to 1 hour without experiencing or developing
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.23
irreversible or other serious health effects or symptoms which could impair an individual's ability to take protective action. ERPG 3: is the maximum airborne concentration below which it is believed that nearly all individuals could be exposed for up to 1 hour without experiencing or developing life-threatening health effects. IDLH: The Immediately Dangerous to Life or Health (IDLH) level. A chemical's IDLH is an estimate of the maximum concentration in the air to which a healthy worker could be exposed without suffering permanent or escape-impairing health effects. The consequence analysis has been done for selected scenarios. This has been done for weather conditions having wind speed 2.25 m/s.
Input data for aloha are as below:
(1) Methanol:
SITE DATA: Location: GUJARAT, INDIA Building Air Exchanges Per Hour: 0.82 (unsheltered single storied) Time: March 10, 2014 1445 hours ST (using computer's clock) CHEMICAL DATA: Chemical Name: METHANOL Molecular Weight: 32.04 g/mol AEGL-1 (60 min): 530 ppm AEGL-2 (60 min): 2100 ppm AEGL-3 (60 min): 7200 ppm IDLH: 6000 ppm LEL: 71800 ppm UEL: 365000 ppm Ambient Boiling Point: 64.7° C Vapor Pressure at Ambient Temperature: 0.31 atm Ambient Saturation Concentration: 313,709 ppm or 31.4% ATMOSPHERIC DATA: (MANUAL INPUT OF DATA) Wind: 3.33 meters/second from WNW at 3 meters Ground Roughness: open country Cloud Cover: 0 tenths Air Temperature: 37.6° C Stability Class: C No Inversion Height Relative Humidity: 30% SOURCE STRENGTH: Leak from hole in vertical cylindrical tank Flammable chemical escaping from tank (not burning) Tank Diameter: 5 meters Tank Length: 6.37 meters Tank Volume: 125 cubic meters Tank contains liquid Internal Temperature: 37.6° C Chemical Mass in Tank: 85.7 tons Tank is 80% full Circular Opening Diameter: 10 centimeters
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.24
Opening is 10 centimeters from tank bottom Ground Type: Concrete Ground Temperature: equal to ambient Max Puddle Diameter: Unknown Release Duration: ALOHA limited the duration to 1 hour Max Average Sustained Release Rate: 232 kilograms/min (averaged over a minute or more) Total Amount Released: 9,814 kilograms Note: The chemical escaped as a liquid and formed an evaporating puddle. The puddle spread to a diameter of 62 meters. THREAT ZONE: Model Run: Gaussian Red : 31 meters --- (7200 ppm = AEGL-3 (60 min)) Note: Threat zone was not drawn because effects of near-field patchiness make dispersion predictions less reliable for short distances. Orange: 61 meters --- (2100 ppm = AEGL-2 (60 min)) Yellow: 214 meters --- (530 ppm = AEGL-1 (60 min))
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.25
(2) Formaldehyde: SITE DATA: Location: GUJARAT, INDIA Building Air Exchanges Per Hour: 0.82 (unsheltered single storied) Time: March 10, 2014 1445 hours ST (using computer's clock) CHEMICAL DATA: Chemical Name: FORMALDEHYDE Molecular Weight: 30.03 g/mol AEGL-1 (60 min): 0.9 ppm AEGL-2 (60 min): 14 ppm AEGL-3 (60 min): 56 ppm IDLH: 20 ppm LEL: 70000 ppm UEL: 730000 ppm Ambient Boiling Point: 100.9° C Vapor Pressure at Ambient Temperature: 2.90e-005 atm Ambient Saturation Concentration: 29.2 ppm or 0.0029% Note: Not enough chemical data to use Heavy Gas option ATMOSPHERIC DATA: (MANUAL INPUT OF DATA) Wind: 3.33 meters/second from WNW at 3 meters Ground Roughness: open country Cloud Cover: 0 tenths Air Temperature: 37.6° C Stability Class: C No Inversion Height Relative Humidity: 30% SOURCE STRENGTH: Direct Source: 200 cubic meters Source Height: 0 Source State: Liquid Source Temperature: equal to ambient Release Duration: 1 minute Release Rate: 31,600 kilograms/sec Total Amount Released: 1,893,922 kilograms THREAT ZONE: Model Run: Gaussian Red : greater than 10 km --- (56 ppm = AEGL-3 (60 min)) Orange: greater than 10 km --- (14 ppm = AEGL-2 (60 min)) Yellow: greater than 10 km --- (0.9 ppm = AEGL-1 (60 min))
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.26
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.27
(3) Ammonia: SITE DATA: Location: GUJARAT, INDIA Building Air Exchanges Per Hour: 0.82 (unsheltered single storied) Time: March 10, 2014 1445 hours ST (using computer's clock) CHEMICAL DATA: Chemical Name: AMMONIA Molecular Weight: 17.03 g/mol AEGL-1 (60 min): 30 ppm AEGL-2 (60 min): 160 ppm AEGL-3 (60 min): 1100 ppm IDLH: 300 ppm LEL: 150000 ppm UEL: 280000 ppm Ambient Boiling Point: -33.5° C Vapor Pressure at Ambient Temperature: greater than 1 atm Ambient Saturation Concentration: 1,000,000 ppm or 100.0% ATMOSPHERIC DATA: (MANUAL INPUT OF DATA) Wind: 3.33 meters/second from WNW at 3 meters Ground Roughness: open country Cloud Cover: 0 tenths Air Temperature: 37.6° C Stability Class: C No Inversion Height Relative Humidity: 30% SOURCE STRENGTH: Leak from hole in horizontal cylindrical tank Flammable chemical escaping from tank (not burning) Tank Diameter: 2 meters Tank Length: 3.98 meters Tank Volume: 12.5 cubic meters Tank contains liquid Internal Temperature: 37.6° C Chemical Mass in Tank: 6.45 tons Tank is 80% full Circular Opening Diameter: 1 centimeters Opening is 10 centimeters from tank bottom Release Duration: ALOHA limited the duration to 1 hour Max Average Sustained Release Rate: 113 kilograms/min (averaged over a minute or more) Total Amount Released: 5,769 kilograms Note: The chemical escaped as a mixture of gas and aerosol (two phase flow). THREAT ZONE: Model Run: Heavy Gas Red : 298 meters --- (1100 ppm = AEGL-3 [60 min]) Orange: 827 meters --- (160 ppm = AEGL-2 [60 min]) Yellow: 2.0 kilometers --- (30 ppm = AEGL-1 [60 min])
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.28
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.29
7.13. RISK REDUCTION MEASUREMENT& RECOMMENDATION IN VIEW OF SAFETY CONSIDERATION Storage tank of Formaldehyde, Ammonia and methanol should be installed away from
the plant area. Wind indicator should be provided at the highest level of the plant to know the wind
direction. Automatic sprinkler system for the flammable material tanks (over ground tanks only)
may be provided as knock on effect in case of fire is possible. Containment dykes with proper sloping and collection sumps should be provided so that
any spillages in the bulk storage and other handling areas shall not stagnate and shall be quickly lead away to a safe distance from the source of leakage. This reduces the risk of any major fire on the bulk storages and the risk to the environment shall be minimized/ eliminated.
Inspection of the storage tanks as per prefixed inspection schedule for thickness measurement, joint and weld efficiency etc.
Provision of flameproof electrical fittings / equipment’s. Proper maintenance of earth pits. Strict compliance of security procedures like issue of identity badges for outsiders, gate
passes system for vehicles, checking of spark arrestors fitted to the tank lorries etc. Strict enforcement of no smoking. Periodic training and refresher courses to train the staff in safety fire fighting. Employee training and education will be carried out. Structural fireproofing in the process area could be considered as a safety measure in
the light of probable spill and fires in the area. Emergency drills should be carried out periodically to ensure preparedness must
continue. Wind indicator should be provided at the highest level of the plant to know the wind
direction. Many operations involve use of highly toxic/flammable materials and these needs to be
documented as SOPs. These must be made and kept updated on priority. Extensive training on use of Self Contained Breathing apparatus (SCBAs) must be
ensured for emergency control. Many of the raw materials used for resin are either toxic or flammable. It is therefore
important to ensure that these materials are stored in closed, well ventilated totally safe areas. A fire alarm system (heat and smoke detection) should be provided for the storage area where the material is stored as toxic fumes arise on combustion.
Loose drums of waste materials, often solvent laden, must be removed from the working areas and close watch kept.
Proper Earthing needs to be provided through plug type systems or through the agitators/liquid.
Ventilation should be provided for any enclosed are where hydrocarbon or toxic vapors may accumulate. Several such areas were noticed- these may be surveyed and tackled accordingly.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.30
All personnel should be trained in handling emergency situations and should be apprised of their role in handling emergency situation and to ensure adequacy of the emergency procedures simulated exercise should be carried out. This was found wanting.
Flame arrestor should be provided. Adequate number of caution boards highlighting the hazards of chemicals should be
provided at critical locations. The health & physical hazards caused due to toxic, irritant, corrosive, flammable
materials. All chemicals are within Threshold Limit Value as per ACGIH. Monitoring of occupational hazards like noise, ventilation, chemical exposure etc. will be
carried out regularly and its record will be maintained. Good housekeeping, use of PPE, Engineering controls, Enclosure processes, scrubber
system, display of safety boards, SOP of loading / unloading, local exhaust ventilation, safety shower etc. are important safety measures have taken to keep these chemicals within TLV.
Appropriate personal protective equipment will be provided & ensure the usage of them. Workers will be trained on safe material handling of hazardous chemicals. Prepare & display the safe operating procedure for hazardous chemicals storage,
handling & transporting or using. Local Exhaust ventilation and scrubber should be installed where it is required to reduce
fumes, vapors, temperature and heat stress. Reduce the level of physical activity by sharing workload with other or by using
mechanical means. Pre-employment medical checkup and periodically medical examination will be done.
Following FIRE safety devices WILL BE PROVIDED to protect from any malfunctioning of
plant equipments. Following fire protection systems will be provided. Water storage of adequate capacity to meet the requirements of water for firefighting
purposes. Fire hydrants and automatic sprinkler system. Diesel driven pumps and headers to
supply water to fire hydrant network. Adequate Portable fire extinguishers, sand bucket, wheeled fire & safety equipment
should be provided at the required places. Equipment required for personal safety like blankets, gloves, apron, gum boots, face
mask helmets, safety belts, first aid boxes etc. are provided. Proximity suits and self-contained breathing apparatus to be provided.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.31
7.14. ON SITE EMERGENCY PLAN
INTRODUCTION: An emergency in the premises has the potential to cause serious injury or loss of lives or extensive damage to the property and/or environment and serious disruption both inside and outside the plant. In such cases sometimes outside agencies are required to call for help in handling the situation. The causative factors like plant/equipment failure, human error, earth quake, sabotage etc. will normally manifest in various forms viz. Fire, Explosion, Toxic release, structure collapse etc. This OEP lays down the code of conduct of all personnel in the Plants and the procedures to be adopted by them in the event of an "Emergency". These procedures have been prepared taking into account the minimum strength of manpower available at all times in the premises. The individuals under the direction of the respective Team Leaders shall carry out the responsibilities assigned. The emergency procedures outlined are suitable for round the clock coverage including holidays. These emergency procedures shall be followed as outlined in the OEP during general shifts as well. OBJECTIVES: The overall objectives of OEP are: To control the situation and if possible eliminate as quickly as possible. To avoid confusion/panic and to attend the emergency with clear-cut line of action. To minimize the loss of property to the plant as well as to our neighborhood. To safe guard the non-affected areas. To alert the neighborhood. To arrange head-count and rescue operations. Treatment of the injured. To safeguard others by timely evacuation. To prevent any cascade of emergencies.
DEFINITION:
Environment as defined u/s 2(a) of the environment Protection Act includes water, air and land and the inter relationship which exists among and between water, air and land and human beings, other living creatures, plants, micro organism and property. Environment pollutant defined by the same Act as any solid, liquid or gaseous substances present in such concentration as may be tend to injurious to atmosphere.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.32
Hazardous substance is also defined by the same Act and hazardous process is defined by sec.2 (b) of the Factories Act. 1948. Hazard is a physical situation, which may cause human injury, damage to property or the environment or any combination of these criteria. Chemical Hazard is a hazard due to chemical (including its storage, process, handling etc.) and it is realized by fire, explosion, toxicity, corrosivity, radiation etc. Risk is a likelihood of an undesired event (i.e. accident, injury or death) occurring within a specified period or under specified circumstances. Individual risk is the frequency at which any individual may be expected to sustain a given level of harm from the realization of specific hazards. Social risk is a measure of chances of a number of people being effected by a single event or set of events and is often presented as f/n curves (i.e. frequency v/s number of people effected) The on-site emergency plan will deal with measures to prevent and control emergencies affecting public and the environment outside the premises. The manufacturer should provide the necessary information on the nature, extent and likely effects of such incidents. Disaster is a catastrophic situation in which the day-to-day patterns of life are, in many instances, suddenly disrupted and people are plunged into helplessness and suffering and as a result need protection, clothing, shelter, medical and social care and other necessities of life, such as: - i. Disasters resulting from natural phenomenon like earthquake, volcanic eruptions, storm, surges, cyclones, tropical storms, floods, landslides, forest fires and massive insect infestation. Also in this group, violent draught which will cause a creeping disaster leading to famine, disease and death must be included. ii. Second group includes disastrous events occasioned by man, or by man’s impact upon the environment, such as armed conflict, industrial accidents, factory fires, explosion and escape of toxic gases or chemical substances, river pollution, mining and other structural collapses; air, sea, rail and road transport accidents, aircraft crashes, collision of vehicles carrying inflammable liquids, oil, spills at sea, and dam failures.
ACCIDENT:
An accident is an unplanned event, which has a probability of causing personal injury or property damage or both. It may result in physical harm (injury or disease) to person (s), damage to property, loss to the company, a near miss or any combination of the effect.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.33
A Major accident is a sudden, unexpected, unplanned event, resulting from uncontrolled developments during and industrial activity, which causes or has a potential to cause i. Serious adverse effects immediate or delayed (death, injuries, poisoning or hospitalization) to a number of people inside the installations and/ or to persons outside the establishment. ii. Significant damage may be caused to crops, plants or animals or significant contamination of land waters or air. iii. An emergency intervention outside the establishment (evacuation of local population, stopping of local traffic). iv. Any combination of above.
EMERGENCY:
An emergency is the situation, which has potential to cause a large-scale damage or destruction to life or property or Environment or combination of these within or outside the factory. Therefore it is essential to have a laid down procedure to meet emergency systematically. In any industry, emergency can arise at any moment and this depends on the type of:
Structure Raw materials Machines Nearby Industries Location of the Industry etc.
NATURE OF EMERGENCY:
The "Emergency" specified in this plan will refer to occurrence of one or more of the following natural/manmade events.
Fire Explosion Release of Toxic Gas/Vapour Spillage of flammable liquid /gas Deliberate Sabotage, Terrorism, Air Raid etc. Natural Calamities: - Lightening, Storm, Earthquake, Flood etc. Collapsing of structure Overturning of tanker containing flammable / toxic substances.
MEDICAL HELP:
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.34
First Aid Boxes have been provided at various strategic locations. Requisite number employees are trained about First Aid, Liaison with nearest hospitals.
COMMUNICATION SYSTEM:
Alarm Raising for Emergency by blowing the sirens installed The siren will be used for raising the emergency alarm and also for all clear signals. Emergency Siren: The wailing alarm will be sounded intermittently at fixed interval
of 30 seconds for a period of two minutes in case of emergency, such alarm will signify the employees that an emergency has occurred and that the emergency services should be put into operation.
Incident Controller after assessing the situation will declare that emergency is over. Till the Incident Controller issues the declaration, all the leaders will adhere to the task and be present at the prescribed location.
All clear signal will be sounded through continuous siren for 1 minute. Even after the emergency is over a skeleton staff of the Rescue/Evacuation Team will be available at the site of emergency for at least 30 minutes to ensure that the situation is absolutely free from danger.
After the emergency is over, all the team leaders should meet at the Emergency Control Center and each team leader should submit a report to the Incident Controller about team performance and other details observed.
In addition to the above systems, Internal telephones, P.A.System, Mobile telephones, Computer System etc. will be used for communication.
If situation is beyond the control, the external agencies will be informed accordingly and asked for the help. Direct telephone, cell phone or messengers / runners may achieve this. ASSEMBLY POINT:
In case of emergency some locations are considered as Assembly Points. Depending on the wind direction and location of emergency, Assembly Point will be declared. The employees should run across the wind direction and not against the wind direction. Depending upon the location of the emergency the Incident Controller will fix the Assembly Point and Officer will announce the location of the Assembly Point. Employee’s attendance, visitors and contractors workmen register will be made available at the Assembly Point for head count. Emergency control center: Factory Manager Office will be declared as an Emergency control center. Emergency control center is facilities with:
1. Address and Telephone numbers of the Factory Inspectorate, Gujarat Pollution
Control Board, Police, Fire Brigade, Hospitals and OEP Team Members
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.35
2. Plant layout-indicating storage of hazardous materials, layout of fire Hydrants/extinguishers, entrances/exits, roads etc.
3. Portable P.A. System, Manual Siren, flood lights, Torches, Pickaxe, Saw, Nylon Ropes. 4. Fire Blankets / Fire Proximity Suit, Breathing Apparatus, First Aid Box etc. 5. List of employees with address, telephone number, blood group etc. 6. Material Safety Data Sheets of all chemicals handled.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.36
WIND SOCKS:
Wind direction will be determined with the help of installed windsocks. MOCK DRILL:
Mock drills are carried out regularly to familiarize the staff with their roles, fire protection equipment/system installed in the plant and use of personnel protective equipment. Senior officials monitor this and shortcomings are thoroughly studied and necessary corrective measures are taken.
PROCEDURES FOR MOCK DRILLS
Inform all the employees about mock drills and the signal to be given. Fix the date and location of the emergency for mock drills. Mock drills will be monitored by observers. Raise the siren for emergency. After hearing the siren the Incident Controller, Site Controller, Officers and Team Members should actuate the “On-site Emergency Plan”.
PROCEDURE ON NOTICING AN EMERGENCY
If anybody notices any situation, which may lead to a disaster, should be immediately
inform the Shift In-charge / site controller / Incident Controller / Fire & Safety Supervisor / Security.
Take charge of the situation as Incident Controller. Rush to the site of emergency to get the correct picture and then to Emergency
Control Center for speedy control over the situation by making an arrangement for raising the alarm.
On arrival of Team members, he shall assign duties as required and activate the On-Site Emergency Plan.
Ensure safety of the plant and the personnel in the plant. He will make an assessment of the emergency and decide on external assistance.
Communicate and Coordinate among the Incidents Controller/ Site Controller/ Factory manager/ fire safety supervisor etc. and will be the final authority on all matters related with management of emergency such as:
Fire fighting. Welfare and rescue operations. Arrange for Civil/Mechanical/Electrical work during emergency. Transport.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.37
INCIDENT CONTROLLER / SITE CONTROLLER:
Rush immediately to the scene of the fire/emergency, select and set out appropriate fire/emergency equipment. He will take the below mentioned actions at the earliest opportunity, if the fire/emergency is not controlled. He will Call the security personnel from their residences for additional manpower if
required. Regulate entry and exit of personal required for controlling the
fire/emergency. Restrict exit of personal required for controlling the fire/emergency. Arrange for Personnel Protective Equipment required for the emergency. Call, the local Fire Brigade, Police in case of necessity in consultation with the
Incident controller. Arrange transport facilities for removal of causalities to dispensary /
hospital. Take responsibility of law and order. Keep detailed records of the incident and progress of operations to fight the
emergency.
FACTORY MANAGER:
He will rush to the Emergency Control Centre and collect the information from the Incident Controller. Further he will,
Announce the location of the Assembly Point after getting information from Incident Controller / site controller.
Take the list of persons to be communicated internally and externally. Maintain liaison with the press, government agencies i.e. Police, Fire Brigade etc. and
the neighborhood regarding the emergency under instructions from Incident Controller.
Courteously Receive officers from the State Government or neighbors to the Administration Block only and inform to Incident Controller that they can be taken care off.
Take all the steps required for the welfare such as providing tea, snacks, emergency temporary Medical Center in consultation with the incident controller/site controller.
Disclose all the necessary information in the plant and media so as to avoid rumors and Confusion.
Also be responsible for the head counts at the Assembly Points. FIRE & SAFETY SUPERVISOR/ SHIFT INCHARGE & SECURITY:
Proceed to the scene; establish contact with firemen and incident controller to supplement efforts in fire fighting.
Assist in searching casualties and help to remove them to the medical center. Organize outside assistance in fire fighting and rescue operations if required.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.38
Mobilize personal protective equipment and safety appliances and assist personnel handling emergency in using them.
Keep and check on any new development of unsafe situation and report the same to Site Main Controller.
Collect and preserve evidence to facilitate future inquiries. Effectively cordon off the emergency area and will prevent unauthorized people
entering the scene. Permit the Fire tenders or Ambulance requisitioned by Incident Controller to the
plant. Ensure that vehicles and trolleys are sent out of the plant premises. Ensure that all the employees are conducted out of plant and assembled at Assembly
Point. Control Traffic Movement. Remove tankers, tanker drivers outside. Entry of unauthorized public to be prevented. Arrange for vehicles for shifting casualties and essential workers to safe assembly
points.
ENGINEERING/ OPERATION & MAINTENANCE:
Ensure the safety of the remaining part of the plant. Take necessary steps for plant shutdown in consultation with the site controller. Ensure that an Operator is immediately available at the Water Pump House for fire
fighting. Mobilize with necessary tools and tackles to handle any repair work on an
emergency basis.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.39
7.15. MATERIAL SAFETY DATA SHEET 7.15.1. MSDS of Formaldehyde
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.40
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.41
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.42
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.43
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.44
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.45
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.46
7.15.2. MSDS of Methanol:
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.47
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.48
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.49
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.50
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.51
7.15.3. MSDS of Ammonia
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.52
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.53
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.54
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.55
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.56
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.57
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.58
7.15.4. MSDS of Urea
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.59
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.60
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.61
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 7.62
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 8.1
8.0 COST ANALYSIS
8.1 Capital Cost
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 8.2
8.2 Environmental cost
Hazardous/solid waste management 1.0
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.1
9.0 ENVIRONMENTAL MANAGEMENT SYSTEM
9.1 Introduction
The earlier sections identified measures for environmental protection especially for
providing the necessary pollution control to comply with the standards stipulating the
limits for emitting pollutants in air, water or on land so that the assimilative capacity is
not exceeded.
Standards are stipulated by various regulatory agencies to limit the emission of
pollutants in air and water. Similarly, a mandatory practice is recommended for
preparing an Environment Statement each year in order to encourage the industries to
allow efficient use of resources in their production processes and reduce the quantities of
wastes per unit of product. This in itself is not sufficient since this does not provide an
assurance that its environmental performance not only meets, but also will continue to meet
legislative and policy requirements.
Hence, Environmental Management Systems (EMS) is suggested at the industry level for
ensuring that the activities, products and services of the region conform to the carrying
capacity (supportive and assimilative capacity). This is based on Bureau of Indian
Standard Specification IS: 13967 (1993): Environmental Management Systems -
Specification (equivalent to British Standard BS 7750). Since this is more in line with the
quality systems, it is recommended that the proposed plant develop one as outlined in
the following sub-sections.
The EMS - its set-up, role and responsibilities - is given subsequently.
9.2 Formation of an Environmental Management System
The environmental management system to be formed by the industry will enable it to
maximize its beneficial effects and minimize its adverse effects - with emphasis on
prevention. It will:
Identify and evaluate the environmental effects arising from the industry's proposed
activities, products and services to determine those of significance;
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.2
Identify and evaluate the environmental effects arising from incidents, accidents and
potential emergency situations;
Identify the relevant legislative and regulatory requirements;
Enable priorities to be identified and pertinent environmental objectives and targets
to be set;
Facilitate planning, control, monitoring, auditing and review activities to ensure that
the policy is complied with; and
Allow periodic evaluation to suit changing circumstances so that it remains relevant.
9.3 Implementation of an Environmental Management System
9.3.1 Commitment
It is essential that the top management of the industry is committed to development
of its activities in an environmentally sound manner and supports all efforts in
achieving this objective.
Experience has shown that all attempts to change the processes and production
methods, which reduce/prevent wastes and inefficient use of resources, ultimately
result not only in environmentally sound practices but also better business returns.
9.3.2 Preparatory Environmental Review
An industry with no formal environmental management system will first establish its
current position with regards to environment through a preparatory environmental
review. This will cover four areas:
Legislative and regulatory requirements;
Evaluation and registration of significant parameters and their environmental
impacts;
Review of environmental management practices and procedures; and
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.3
Assessment of feedback from investigation of previous environmental incidents and
non-compliance with legislation, regulations or policies and procedures.
The resulting report will address:
The nature and extent of problems and deficiencies;
The priorities to be accorded to rectify them; and
An improvement program designed to ensure that the personnel and material
resources required are identified and made available.
9.3.3 Environmental Policy
The industry's management will actively initiate, develop and support the
environmental policy, which is relevant to its activities, products and services and their
environmental effects.
Broadly this covers the following:
Be consistent with the occupational health and safety policy and other industrial
policies (such as quality policy);
Indicate which of the industrial activities are covered by the environmental
management system;
Be communicated and implemented at all levels of the industry; and
Be available publicly.
The corporate policy for Environmental Management is to create sound and eco-friendly
environment for sustainable development at all production projects, plan new projects
with environment -friendly considerations, plan regulative, ameliorative and mitigative
measures to protect environment and fully merge into the overall corporate policy for
achieving the targeted business goals of the Corporation.
Objectives: The environmental policy is framed specifically to fulfill the following
objectives:
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.4
Create a work environment which enhances/motivates production and productivity.
Create a residing environment for the enjoyment and peace of employee.
Encourage safe and scientific operations and other well-established engineering
practices.
Promoting awareness amongst the employees and the neighborhood population for
adopting environmentally friendly acceptable procedures and restricting environmental
degradation and pollution to the barest minimum
Establishing "Eco-label" for its finished products so as to promote domestic and
international markets.
To achieve communal harmony and peace amongst the employees and the local
villagers for heading fast towards "sustainable development". In environmental and
ecological planning, information about the context of the issue and about the inter-
relationship between natures is infused into the plan making process.
Sustaining human fulfillment and the resources that need to be sustained viz.' clean
air and water, individual and community welfare and well being, equity, maintaining
ecological process and bio-diversity.
Meaningful use of and within the leasehold areas and in the immediate neighborhood.
9.3.4 Organization and Personnel
To facilitate the implementation of the EMS, one of the most important aspects relate to
the organization and personnel. The related issues are:
Define and document the responsibility, authority and inter-relations of key
personnel involved in the implementation of the environmental policy, objectives and
environmental management system;
Identify the in-house verification requirements and procedures including resources
and personnel;
Appoint a Management Representative (MR);
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.5
Communicate to employees at all levels the importance of compliance with the
environmental policy, their role and responsibilities in achieving compliance, the
potential consequences of departures from the specified procedures and identify and
provide appropriate training; and
Establish and maintain procedures to ensure that contractors are made aware of the
environmental management system requirements and provisions.
9.3.5 Environmental Effects
The industry will establish and maintain procedures for:
Receiving, documenting and responding to internal as well as external
communications concerning environmental aspects and management;
Identifying, examining and evaluating the environmental effects of its activities
under normal and abnormal/emergency situations (including risk assessment) and
compiling significant effects in a register; and
Recording all legislative, regulatory and other policy requirements and codes in a
register.
9.3.6 Environmental Objectives and Targets
The objectives will be set with a view to realizing gradual and steady improvements in
environmental performance through application of best available and economically
viable technology.
The areas targeted for improvement will be those where improvements are most
necessary to reduce risks (to environment and industry) and liabilities. These will be
identified through cost-benefit analysis wherever practicable.
9.3.7 Environmental Management Program
The establishment of an environmental management program is the key to compliance
with the industry's environmental policy and achievement of the environmental
objectives and targets. It will designate the responsibility for achieving the targets at
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.6
each level and the means thereof. It will deal with the actions required for the
consequences of the industries past activities as well as address the life cycle of
development of new products so as to effectively control adverse impacts.
9.3.8 Environmental Management Manual and Documentation
The documentation is intended to provide an adequate description of the environmental
management system. The manual is expected to provide a reference to the
implementation and maintenance of the system.
9.3.9 Operational Control
The management responsibilities will be defined to ensure that the control, verification,
measurement and testing of environmental parameters within the industry are
adequately co-coordinated and effectively performed.
The control, verification, measurement and testing will be made through documented
procedures and work instructions defining the manner of conducting activities, the
absence of which can lead to violation of the environment policy.
In the event of non-compliance, procedures for investigation of the causative mechanism
will be established and the factors reported for corrective actions.
9.3.10 Environmental Management Records
The industry will establish and maintain a system of records to demonstrate compliance
with the environmental management systems and the extent of achievement of the
environmental objectives and targets. In addition, the other records (legislative, audit
and review reports) and management records will address the following:
Details of failure in compliance and corrective action;
Details of incidents and corrective action;
Details of complaints and follow-up action;
Appropriate contractor and supplier information;
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.7
Inspection and maintenance reports;
Product identification and composition data;
Monitoring data;
Environmental training records; and
House keeping.
9.3.11 Environmental Management Audits
The management audits are to determine whether the activities are conforming to the
environmental management systems and effective in implementing the environmental
policy. They may be internal or external, but carried out impartially and effectively by a
person properly trained for it. Broad knowledge of the environmental process and
expertise in relevant disciplines is also required. Appropriate audit programs and
protocols will be established.
9.3.12 Environmental Statement
As a mandatory requirement under the Environment Protection Rules (1986) as
amended through the Notification issued by the Ministry of Environment and Forests in
April 1993, an Environmental Statement will be prepared annually. This will include the
consumption of total resources (raw material and water per ton of product), quantity
and concentration of pollutants (air and water) discharged, quantity of hazardous and
solid waste generation, pollution abatement measures, conservation of natural
resources and cost of production vis-à-vis the investment on pollution abatement. The
intention of this statement is:
To identify the process/production areas where resources can be used more
efficiently through a comparison with the figures of a similar industry (thereby reducing
the consumption per unit of product);
To determine the areas where waste generation can be minimized at source and
through end of pipe treatment (thereby reducing the wastes generated and discharged
per unit of product); and
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.8
To initiate a self-correcting/improvement system through an internal analysis to
achieve cost reduction through choice of superior technology and more efficient
practices.
9.3.13 Environmental Management Reviews
The senior management will periodically review the Environmental Management
System (EMS) to ensure its suitability and effectiveness. The need for possible changes in
the environmental policy and objectives for continuous improvement will be ascertained
and revisions made accordingly.
EMS based on the above objectives will be formulated and implemented at the industry
level. Every department will be headed by Sr. Manager / Manager level officer belonging
to disciplines like Civil, Mechanical, Electrical, Instrumentation, Chemical, Metallurgical,
Information technology etc. The Environment Department will be headed by Manager
(Environment) and adequate staff will be provided for establishing environmental
controls within the plant.
9.4 Concept of Waste-Minimization, Recycle/Reuse/Recover Techniques, Energy
Conservation, and Natural Resource Conservation
Waste-minimization
Process optimization can be done by using latest technology equipment. Fly ash will
be sold to nearby brick manufacturers.
Recycle/reuse/recover
Zero discharge technology will be adopted. Dust collected from air pollution control
equipment and ash will be recycled in the in Cement manufacturing process. The main
source of hazardous waste generation is the ETP sludge from the effluent treatment
plant, which will be sent to TSDF. The ancillary source of hazardous waste generation
will be used/wasted oil which will be reuse or sell to MoEF approved scrap vendors,
discarded barrels/ drums/ bags/ liners /carboys from the raw material handling &
storage which will be decontaminated and reused or sold to GPCB approved scrap
vendors.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.9
Fly Ash disposal plan
Proposed Boiler Capacity: 1 MT
Fuel: Coal
Quantity: 2.314 MT/Day
Fly ash Calculation:
As per fuel characteristics; coal contain 38 % ash
Maximum Ash generated from proposed industry;
2.314 MT/Day X 38 % Ash = 0.88 MT/Day
So, Maximum 0.88 MT/Day Ash will be generated from the proposed Boiler.
It will be stored into silo with proper care and sold to bricks manufacturer.
Energy Conservation Measures
Latest Technology will be adopted
Natural Resource Conservation
To conserve ground water rain water harvesting will be carried out to store rain for
future use and also to recharge ground water.
9.5 Institutionalizing Corporate Environmental Responsibility
9.5.1 Introduction and Scope
Environment and natural resources are the prime source of all material inputs to
economic activities. The environment also acts as a receiver and sink of the various
kinds of waste generated through human activity. A proper balance between the
developmental needs and environmental concerns is necessary in order to pursue the
path of sustainable development.
Sustainable Development involves an enduring and balanced approach to economic
growth, social protection and justice, and environmental conservation.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.10
9.5.2 Corporate Environmental Policy Implementation
M/s Pawan Formalin Pvt. Ltd. shall specify an organizational structure to oversee the
effective implementation of Corporate Environmental Policy. This structure shall define
key responsibilities within the various levels of an organization for policy
implementation and shall include top to bottom and bottom to top involvement
throughout the Organization. A suggested model structure is provided below in Figure-
9.1.
FIGURE 9.1 Model structure showing information flow
The management shall ensure the availability of resources essential to implement the
corporate environmental policy across all its activities/projects. Resources shall include
human resources, organizational infrastructure, technology and financial resources.
Roles and responsibilities shall be defined, documented and communicated to facilitate
the effective implementation of the environment policy. As part of the existing
management structure, compliance management will also oversee the environmental
performance status inclusive of the conditions prescribed under various environmental
consents and clearances, as well as the corporate norms, standards and targets that
exceed the legal compliance requirements.
Factory Manager
Safety officer
Un-skilled person
Skilled
Director
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.11
9.5.3 Documentation
The organization shall clearly specify and document the following:
a. Resource allocation for effective implementation of environmental policy.
b. Defined responsibilities and roles.
c. Expected major measureable and perceivable results/deliverables, including corporate
targets.
All achieved milestones should be well supported by documentary evidence in the form of
photographs, monitoring records, and/or reports, wherever applicable.
9.5.4 Transparency in the implementation of Environmental Policy
Monitoring is crucial and needs to be conducted periodically. Monitoring helps those
involved with implementation of Environmental Policy to assess if progress is being
achieved in line with expectations. It serves to drive accountability and transparency,
and provides for learning to implement in future initiatives. Systematic and structured
reporting process will facilitate accountability and transparency between the
organizations and their internal and external stakeholders.
M/s Pawan Formalin Pvt. Ltd. shall implement a monitoring mechanism by its defined
organizational structure with clear roles and responsibilities for its project/activity
comprising of the following steps:
a. Creating a legal register specifying all the regulatory compliance conditions along with
the compliance conditions, clearance conditions that have been found by the Ministry
or other public authorities. Conducting a baseline assessment in order to be able to
monitor progress.
b. Monitoring, collecting and documenting data on the environmental performance.
c. Preparing Annual Environmental Performance report and including it in its Annual
Report.
M/s Pawan Formalin Pvt. Ltd. may communicate information on their environmental
performance in a structured manner to all their stakeholders and the public at large. The
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 9.12
management shall ensure that appropriate and necessary information that describes the organizations’ environmental performance is communicated throughout the company. This will allow the internal stakeholders to fulfill their responsibilities to help the
organization reach the planned environmental performance.
Chapter 10
EXECUTIVE SUMMARY IN
ENGLISH
&
GUJARATI
OF
M/s Pawan Formalin Pvt. Ltd. (New Formaldehyde, Hexamine & Resin
Manufacturing Project)
Survey No.: 24/P, Village: Jambudiya, Taluka: Morbi, District: Morbi-Rajkot, State: Gujarat
Pin – 363642
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.1
10.0 EXECUTIVE SUMMARY IN ENGLISH & GUJARATI
EXECUTIVE SUMMARY – ENGLISH
1 INTRODUCTION
PPPaaawwwaaannn FFFooorrrmmmaaallliiinnn PPPvvvttt... LLLtttddd... is a Private Limited company, proposing to manufacture
Formaldehyde, Hexamine along with Resins (Melamine Formaldehyde, Urea
Formaldehyde and U.F. Moulding Powder) at Survey NO. 24/P, Village: Jambudiya,
Taluka: Morbi, District: Morbi-Rajkot, Gujarat. Proposed unit will manufacture
Formaldehyde, Hexamine & resins for production within its premises and for sale
outside.
The total land area of company is 10060 m2 out of which 3096 Sq. Mt. land will be used
for greenbelt area development. The estimated cost of the Resin project is 3.6 Crore.
Total budget allocation towards Environmental Management Facilities will be Rs. 70.50
Lacs. Total 30 persons will be employed including skilled persons, unskilled persons
and office staff.
M/s. T. R. Associates is carried out EIA/EMP studies for Environmental Clearance from
Ministry of Environment and Forests, Govt. of India. Production details are given below:
No. Product Total Quantity
( MT/MMonth)
1. Formaldehyde (37%) 1800
2. Urea Formaldehyde Resin 250
3. Melamine Formaldehyde Resin 250
4. U.F. Moulding Powder 250
5. Hexamine 90
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.2
The proposed product Formaldehyde (37%), Hexamine, Melamine Formaldehyde Resin,
Urea Formaldehyde Resin & Urea Formaldehyde Moulding Powder falls under clause
No.5 (f) of category “A” as stated in Environment Impact Assessment Notification
published on 14th September 2006 and hence the project proponent has to obtain the
Environmental Clearance from New Delhi. As a part of this procedure, Public Hearing is
required to be carried out as per the notification as well as the TOR granted to the unit
by the Expert Appraisal Committee (Industry-2).
This study of Rapid Environment Impact assessment (EIA) is based on studies carried
out during the month November 2013 to January 2014. The environmental parameters
(ambient air, water, soil, noise, flora and fauna) selected for study are those, which are
likely to be most affected by the project. The study area is defined as an area within 5.0
Km. radius from center of the site. Socio-economic environment study is only carried
out for 10 Km. radius from center of the site.
Salient Features with in 10 km radius surroundings area as follows:
S.No Important Features Description
1 Location Survey No. 24/P, Village: Jambudiya, Taluka:
Morbi, Dist.: Morbi-Rajkot, 363642
2 Topomap
(10 km radius)
F42K13 & F42K14
3 Longitude 70° 54’ 05.61’’ E
4 Latitude 22° 47’ 06.87’’N
5 MSL 224 ft
6. Nearest power station PGVCL (Paschim Gujarat Vij Corporation Ltd.)
7 Proponent Name Mr. Kumar K. Hothi- 098795 30737
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.3
8 Corporate office address M/s. Kanji Parshottam & Brothers, Opp. Gandhi
Baugh, Near Union bank of INDIA, Morbi- 363641.
9 Temperature range 180 C to 450 C
10 Annual Rain fall 660 mm
11 Neatest Road NH – 8A (0.1 Km)
12 Nearest Railway station Nazarbaug railway station(10.1 km)
13 Nearest city Morbi (13.8 km)
14 Nearest village Jambudiya (1.5 km)
15 National HW NO NH: 8 A – 0.1 km
16 State HW No SH 321 (07 km)
17 Seismic Zone Zone-III (Less Active)
18 National Parks /
Sanctuary
Paneli reserve forest at 2.07 KM in ENE direction.
And 3.1 km in SSW.
2. AIR ENVIRONEMNT
The base line Ambient Air Quality (AAQ) status within 5 KM study area has been
assessed through a monitoring network of 7 AAQ sampling stations during Winter
season November – 2013 to January - 2014. Map showing 5 Km radius area is shown
here. Design of network for Ambient Air Quality monitoring locations were decided on
meteorology & available infrastructure facilities. The base-line Ambient Air Quality of
the study area was monitored for Particulate Matter (PM10 & PM2.5), Sulphur Dioxide
(SO2) and Oxides of Nitrogen (NOx). The result for the same is given here.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.4
GOOGLE IMAGE SHOWING PROJECT SITE
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.5
TOPOMAP SHOWING 10 KM RADIUS AREA FROM PROJECT SITE
Proposed project site –– PPawan Formalin Pvt. Ltd.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.6
Name of the Villages for baseline monitoring
AMBIENT AIR QUALITY WITHIN 5 KM RADIUS AREA
FOR November 2013 to January 2014
Pollutant Particular LOCATION
Project site
Nava Jambudiya
Juna Jambudiya Rafleshwar Jodhpar Bhadiyad Paneli
PM 2.5
μg/m3
Min 33.8 34.5 33.8 34.8 30.1 33.5 33.6
Max. 44.7 43.0 44.4 43.5 43.3 43.7 44.0
Avg. 39.7 39.7 40.9 40.5 40.5 40.2 39.7
PM 10
μg/m3
Min 63.2 67.2 67.2 67.4 64.5 68.6 63.2
Max. 79.8 77.2 80.2 79.8 77.7 77.7 80.3
Avg. 73.2 72.5 72.8 72.5 73.6 73.3 73.0
SOx
μg/m3
Min 9.5 9.4 8.1 8.5 10.2 11.4 8.1
Max. 17.1 20.7 15.6 19.1 20.7 20.7 15.3
Avg. 13.6 13.5 13.3 13.9 13.6 13.9 12.9
NOx
μg/m3
Min 16.1 17.2 17.9 16.2 18.8 17.9 14.4
Max. 26.8 25.5 28.0 25.9 30.7 30.7 24.7
Avg. 22.8 21.6 22.2 22.2 22.3 21.8 21.6
HC N.D N.D N.D N.D N.D N.D N.D N.D
VOC N.D N.D N.D N.D N.D N.D N.D N.D
Code Air Location Distance in km
Direction
A1 Project site - -
*A2 Nava Jambudiya 0.85 NW
*A3 Juna Jambudiya 1.25 SE
A4 Rafaleshwar 1.44 S
A5 Jodhpar 3 SW
A6 Bhadiyad 4.33 NW
A7 Paneli 4.3 E
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.7
3. WATER ENVIRONMENT
Analysis of Ground Water & Surface Water samples revealed that the both ground water
quality & surface water quality is satisfactory to serve for domestic purposes as per
drinking water quality standards IS: 10500
4. ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES
4.1 AIR ENVIRONMENT
The main source of gaseous emission is flue gas emission from stack attached to Steam
Boiler (1 MT/Hr.), D. G. Set (300 KVA).
Coal/White coal will be used as a fuel & the requirement shall be 2.314 MT/Day. Proper
stack height (30 M) will be provided for proper atmosphere dispersion. Multi cyclone
dust collector will be provided with Steam boiler. The probable emitted pollutants will
be SPM, SOx & NOx. However, it will be almost within the prescribed norms. Since HSD
will be used as a fuel for D. G. Set, which will be used in case of power failure, the flue
gas emission will also be well within prescribed norms and there will be no need of any
air pollution control measures for D. G. Set.
4.2 WATER ENVIRONMENT
Water requirement will be satisfied from bore-well. The total fresh water requirement
will be 65.45 KL/Day that will be required for domestic, Cooling (make up), steam
boiler, scrubbing & Sprinkling process, manufacturing process and gardening purpose.
Wastewater generation from the industrial activities will be 6.65 KL/D. This wastewater
generated from manufacturing process & rest of industrial activities will be treated in
Multi effect Evaporator and reused in process. Domestic effluent will be disposed off to
soak pit through septic tank.
Thus, there will not be any major impact on the water environment due to proposed
project.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.8
Water balance diagram and ETP flow diagram is shown below.
EFFLUENT TREATMENT PLANT DIAGRAM
ZERO DISCHARGE
WATER BALANCE DIAGRAM
EffluentCollected in
Collection cum equalization tank
Multi Effect Evaporator
Sludge sent to TSDF Site
Reused back in process
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.9
4.3 SOLID WASTE MANAGEMENT
The entire quantity of hazardous waste will be handled & disposed as per Hazardous
Waste (Management, Handling & Trans boundary Movement - Rules 2008 (amended
time to time). The main hazardous waste generation will be ETP waste, used oil &
Discarded Plastic Bags.
ETP waste will be disposed off at approved TSDF site, used oil will be reused within
premises as a lubricant or sold to registered recycler, and discarded plastic bags will be
sold to authorized vendor.
The unit will provided isolated area for the storage of hazardous waste. Thus, hazardous
waste management system provided by the unit will be adequate and there will not be
any major impact on the environment due to hazardous waste management.
4.4 GREEN BELT DEVELOPMENT
The unit proposes to provide total green belt area up-to 3096 Sq. Mt. area for
development. Thus, total water consumption will be 5.8 KL/D.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.10
5. ENVIRONMENT MONITORING PROGRAME
Monitoring of environmental factors will enable us to identify the changes in the
environmental impacts at various locations. To ensure the effective implementation of
the EMP, monitoring of ambient air quality, stack emissions, analysis & monitoring of
water environment and noise level will be carried out as required / specified by
statutory authority.
6. QUALITATIVE RISK ANALYSIS
Risk analysis and study have been carried out for identification of hazards, selection of
credible scenarios, Risk Mitigation measures etc. All the hazardous chemicals will be
stored and handled as per MSDS guidelines. Personal protective equipments will be
provided to the labors.
7. Project Benefits:
The proposed project will become beneficial to the surrounding area or community in
terms of infrastructural development, social development, employment and other
benefits.
The proposed project has a potential for employment of skilled, semiskilled and
unskilled employees during construction phase as well as operation phase. A total 30
nos. of person is likely to get employment due to the project. The project will spend 1.5
% of the total profit for socio-economic development & for nearby educational
institutes. The proposed project will be active in CSR Activity.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 10.11
8. Conclusion:
Negligible impacts will occur on air quality. However, all the necessary air
pollution control measures will be provided.
No ecological damage will occur.
No adverse impacts will occur on water environment.
Local employment opportunities will increase.
Various other environment parameters like Forest/ National Park/ Sanctuary
and Religious / Historical Places will not be affected.
Environment Management Plan has been formulated to control all the pollutant
parameters and Environment Management Cell has been set-up to ensure that
these parameters do not exceed the norms set out by the concerned authorities.
After commissioning of the proposed project the Environmental Management
Cell will take care of all the pollution control measures.
It can be concluded that positive implementation of mitigation measures and
environmental management plan during the construction & operational phase,
there will be negligible impact on the environment.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.12
EXECUTIVE SUMMARY – GUJARATI
સં ી ત અહવાલ
૧. તાવના:-
મેસસ પવન ફોમલીન ા. લ. એ ાઈવેટ લિમટડ કંપની છે. તાિવત એકમે ફોમા ડ હાઈડ ,
હ ાએમાઈન સાથે રઝીન (મેલેમાઈન ફોમા ડ હાઈડ, રુ યા ફોમા ડ હાઈડ અને .ુ એફ. મો ડ ગ પાવડર)
ઉ પ કરવા માટની દરખા ત કરલ છે. તથા એકમ સવ ન-ં૨૪/પી , ગામ :- ં ડુ યા, તા કુા:- મોરબી ,
જ લો:-મોરબી-રાજકોટ , જુરાત રાજય મા ંઆવેલો છે. ૂચત ઉ ોગ આ ોડ ટ ુ ંઉ પાદન બહાર
વેચવા માટ કરશે.
તાિવત એકમનો ુલ િવ તાર આશર ૧૦૦૬૦ મીટર છે. માથંી ૩૦૯૬ ચો.મી. જમીન ીન
બે ટ માટ ફાળવવામા ંઆવશે. આ એકમને થાિપત કરવાની ક મત િપયા ૩.૬ કરોડ થશે. માથંી
પયાવરણીય યવ થાપન પ ત માટ આશર ૭૦.૫૦ લાખ ફાળવવામા ંઆવશે. આશર ૩૦ માણસો ને
રોજગાર આપવામા ંઆવશે ક મા ં ુશળ કાર ગરો , બીન ુશળ કાર ગરો અને કાયાલયના કમચાર ઓ નો
સમાવેશ થાય છે.
મેસસ ટ . આર. એસોસીએ સ એ MoEF (Ministry Of Environment & Forest, Government Of
India) પાસેથી પયાવરણીય મં ૂર લેવા માટ EIA અને EMP અ યાસ કરલ છે.
ઉ પાદન િવગતો નીચે જુબ છે.
માકં ોડ ટ ુ ંનામ મતા ૧ ફોમા ડ હાઈડ ૧૮૦૦ મે.ટન/ માસ ૨ રુ યા ફોમા ડ હાઈડ રઝીન ૨૫૦ મે.ટન/ માસ ૩ મેલેમાઈન ફોમા ડ હાઈડ રઝીન ૨૫૦ મે.ટન/ માસ ૪ .ુએફ. મો ડ ગ પાવડર ૨૫૦ મે.ટન /માસ ૫ હ ામાઈન ૯૦ મે.ટન /માસ
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.13
અ ે ન ધનીય છે ક ફોમા ડ હાઈડ(૩૭%) , હ ામાઈન , .ુએફ.મો ડ ગ પાવડર , મેલેમાઈન
ફોમા ડ હાઈડ અને રુ યા ફોમા ડ હાઈડ રઝીન ુ ંઉ પાદન એ ૧૪ સ ટ. ૨૦૦૬ , EIA નોટ ફ કશન-
૨૦૦૬ ના િવભાગ-૫(એફ)મા ંઆવે છે થી તે માટ પયાવરણીય મં ૂર MoEF (Ministry Of
Environment & Forest, Government Of India), નવી દ હ પાસેથી લેવી જ ર છે. આથી પયાવરણીય
મં ૂર ( ENVIRONMENTAL CLEARANCE) મેળવવાની જ ર યાત રહલ છે. આ ક યાના ભાગ પે
લોક નુાવણી એ હરનામા માણે તથા એ પટ એ ાઈઝલ કમીટ એ િુનટ આપેલા TOR માણે
કરવામા ંઆવશે
ઝડપી પયાવરણ ૃ થકરણ અસર અ યાસ ( RAPID ENVIRONMENTAL IMPACT
ASSESSMENT STUDY) નવે બર ૨૦૧૩ થી આુર ૨૦૧૪ દરિમયાન કરવામા ંઆવેલ છે.
પયાવરણીય ઘટકો વા ક (આસપાસ ની હવા , પાણી , જમીન , વિન, વન પિતઓ અને ાણીઓ)
તાિવત એકમથી અસર પામી શક તેમ છે. , તેનો અ યાસ કરવામા ંઆ યો છે. તાિવત એકમ ક મા ં
લઈને ૫ કમી. િ યાના વ ળુાકાર િવ તારને અ યાિસત ે તર ક ન કરવામા ંઅવેલ છે. તાિવત
એકમને ક મા ંલઈને ૧૦ કમી િ યાના વ ળુાકાર િવ તારમા ંસામા ક-આિથક પયાવરણનો અ યાસ
કરવામા ંઆવેલ છે.
આસપાસના ૧૦ કમી િ યાના િવ તારની ુ ય લા ણકતાઓ નીચે માણે છે.
માકં ુ ય લા ણ તાઓ વણન ૧ થાન સવ ન-ં ૨૪/પી, ગામ :- ં ડુ યા,
તા કુો:- મોરબી, લો:- મોરબી-રાજકોટ, જુરાત.
૨ ટોપોમેપ (૧૦ કમી િ યા) F42K13, F42K14 ૩ અ ાશં ૨૨0૪૭’૦૬.૮૭’’N ૪ રખાશં ૭૦0૫૪’૦૫.૬૧’’E ૫ સ ુ ી તરના સરરાશ ૨૨૪ ટ ૬ પોને ટ ુ ંનામ મી. ુમાર ક હોથી . ૭ કોપ રટ ઓફસ ુ ંસરના ુ ં મે. કાન પરશોતમ & ધસ
,ગાધંી બાગ સામે , નુીયન બક ઓફ ઈ ડ યા પાસે મોરબી-૩૬૩૬૪૧
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.14
૮ વાિષક વરસાદ ૬૬૦ મીમી ૯ ન ક નો રોડ નેશનલ હાઈવે ૮ એ(૦.૧ કમી) ૧૦ ન ક ુ ંર વે ટશન નઝરબાગ ર વે ટશન (૧૦.૧ કમી) ૧૧ ન ક ુ ંશહર મોરબી (૧૩.૮ કમી) ૧૨ ન ક ુ ંગામ ં ડુ યા (૧.૫ કમી) ૧૩ રા ય ઉપવન- જગંલી ાણીઓ માટ ુ ંઅ યાર ય પાનેલી આર ત જગંલ ENE
દશામા ં2.07 કમી પર છે અને SSW દશામા ં3.1 કમી ૂર છે.
૧૪ તાપમાન ૧૮સે. થી ૪૫ સે. ૧૫ કંૂપ ઝોન ઝોન ૩ ઓ સ ય ૧૬ ન ક ુ ંિવજળ મથક પ ીમ જુરાત િવજ કોપ . લીમીટડ ૧૭ નેશનલ હાઈવે ૮એ(૦.૧૬ કમી) ૧૮ ટટ હાઈવે ૩૨૧ (૭ કમી)
૨. હવા ુ ંપયાવરણ (Air Environment) :-
વતમાન આસપાસની ( Ambient) હવાની ણુવ ા ણવા માટ તાિવત એકમ થળથી ૫
કમી િ યાના વ ળુાકાર િવ તારમા ં૭ અલગ અલગ થળેથી નવે બર ૨૦૧૩ થી આુર ૨૦૧૪
દરિમયાન ન નૂા લઈને તેની ચકાસણી કરવામા ંઆવી હતી. ૫ કમી ી યાનો વ ળુાકાર િવ તાર અ હ
દશાવલે છે. હવાની ણુવ ા ન કરવા માટના થળની પસદંગી વા શુા અને ન કની ા ત
િુવધાઓના આધાર ન કરલી હતા. હવાની ણુવ ા ન કરવા માટ પટ લુેટ મેટર( PM 10 & PM
2.5), સ ફર ડાયોકસાઈડ ( SO2) અને નાઈ ોજન ઓ સાઈડ( NOx)ની ચકાસણી કરવામા ંઆવી હતી.
ના પ રણામો નીચેના ટબલમા ંદશા યા જુબ છે.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.15
ગૂલ મેપ ો ટ સાઈટ
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.16
આસપાસના ૧૦ કમી િ યાનો િવ તાર
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.17
બેઝલાઈન મોનીટર ગ માટ ગામો ના નામ :-
૫ કમી િ યામા ં હવા ુપયાવરણ નવે બર ૨૦૧૩ થી આુર ૨૦૧૪
Pollutant Particular LOCATION
Project site
Nava Jambudiya
Juna Jambudiya
Rafleshwar Jodhpar Bhadiyad Paneli
PM 2.5
μg/m3
Min 33.8 34.5 33.8 34.8 30.1 33.5 33.6
Max. 44.7 43.0 44.4 43.5 43.3 43.7 44.0
Avg. 39.7 39.7 40.9 40.5 40.5 40.2 39.7
PM 10
μg/m3
Min 63.2 67.2 67.2 67.4 64.5 68.6 63.2
Max. 79.8 77.2 80.2 79.8 77.7 77.7 80.3
Avg. 73.2 72.5 72.8 72.5 73.6 73.3 73.0
SOx
μg/m3
Min 9.5 9.4 8.1 8.5 10.2 11.4 8.1
Max. 17.1 20.7 15.6 19.1 20.7 20.7 15.3
Code Air Location Distance in km Direction
A1 ો ટ સાઈટ - -
A2* નવા ં ડુ યા ૦.૮૫ SW
A3* ુના ં ડુ યા ૧.૨૫ SW
A4 રફાળે ર ૧.૪૪ S
A5 જોધપર ૩ NE
A6 ભડ યાડ ૪.૩૩ NW
A7 પાનેલી ૪.૩ SW
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.18
Avg. 13.6 13.5 13.3 13.9 13.6 13.9 12.9
NOx
μg/m3
Min 16.1 17.2 17.9 16.2 18.8 17.9 14.4
Max. 26.8 25.5 28.0 25.9 30.7 30.7 24.7
Avg. 22.8 21.6 22.2 22.2 22.3 21.8 21.6
HC N.D N.D N.D N.D N.D N.D N.D N.D
VOC N.D N.D N.D N.D N.D N.D N.D N.D
3.જળ પયાવરણ (Water Environment):-
ગૂભ જળ તેમજ જમીન પરના પાણીના ન નૂાઓના ણુવ ા પર ણ પરથી તારણ કાઢ શકાય
ક ગૂભ પાણી તેમજ જમીન પર ુ ંપાણી IS:૧૦૫૦૦ મા ંબહાર પાડવામા ંઆવેલ પીવાલાયક પાણીના
ધારાધોરણ જુબ છે.
૪. પયાવરણીય અસરો અને તેના શમન (મીટ ગેશન) માટના પગલા:ં-
૪.૧ હવા ુ ંપયાવરણ:-
હવાના ૂષણનો ુ ય ોત ચીમની માથંી થતા ૂગેસ ઉ સ ન ક ટ મ બોઈલર( ૧મે.
ટન/ કલાક) D.G.Set (૩૦૦ KVA) છે.
કોલસો/ હાઈટ કોલસો બળતણ તર ક વાપરવામા ંઆવશે ની જ રયાત ૨.૩૧૪ મે.ટન/ દવસ
રહશે. ચીમની ની ચાઈ ૩૦ મીટર રાખવામા ં આવશે. મ ટ સાય લોન ડ ટ કલે ટર, ટ મ બોઈલર સાથે
લગાવવામા ંઆવશે.સભંિવત બહાર ફકાતા ૂષકો SPM, SOX, NOx હશ.ે તેમ છતા ંઆ ૂષકો િનયત
ધોરણમા ંરહશે.
યાર HSD (HIGH SPEED DIESEL) D.G. SET મા ંબળતણ તર ક વાપરવામા ંઆવશે પાવર
ફઈલર વખતે વપરાશે તથા ૂગેસ એમીશન પણ િનયત ધોરણો ( PRESCRIBED STANDARD)મા ંહશે
તેથી D.G.Set માટ APCM જ ર નથી.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.19
૪.૨ પાણી ુ ંપયાવરણ :-
પાણીની જ રયાત બોરવેલમાથંી સતંોષવામા ંઆવશે. ુલ તા પાણીની જ ર યાત ૬૫.૪૫
કલોલીટર/ દવસ હશ.ે મા ઘરગ ુવપરાશ, ુલ ગ ટાવરમા ંવપરાશ, બ ગ અને ીકલ ગ ોસેસ
માટ વપરાશ, બોઈલરમા ંવપરાશ, બાગબગીચાના િવકાસ માટના ંપાણીના ંઅને ઉ પાદન યામા ં
વપરાશનો સમાવેશ થાય છે.
ઈ ડ અલ ોસેસ ારા ૬.૬૫ કલોલીટર/ દવસ ટ ુ ં ગં ુ પાણી ઉદભવશે. આમા ંઉ પાદનમા ં
કયામા ંઅને બી ઓ ોગીક કયા માથંી ગં ુપાણી િનકળશે. ઈ ડ યલ ોસેસના ગદંા પાણી ને
મ ટ ઈફ ટ ઈવોપરટરમા ં ટમે ટ આપી ફર થી વાપરવામા ંઆવશે. ડોમે ટ ક (ઘરગ )ુ ગદંા પાણીનો
િનકાલ સે ટ ક ટાકં - સોકપીટ સી ટમમા ંકરવામા ંઆવશે. તેથી તાિવત એકમથી જળ પયાવરણ પર
કોઈ મોટ અસર થશે નહ .
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.20
વોટર બેલે સ ડાયા ામ તથા ઈટ પી લો ડાયા ામ નીચે દશાવેલ છે.
ઈટ પી લો ડાયા ામ
વોટર બેલે સ ડાયા ામ
Effluent Collected in
Collection cum equalization tank
Multi Effect Evaporator
Sludge sent to TSDF Site
Reused back in process
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.21
૪.૩ સોલીડ વે ટ મેનેજમે ટ (મેનેજમે ટ હ ડલ ગ અને ા સ બાઉ વૂમે ટ)
હઝાડસ વે ટ િનયમ ,૨૦૦૮ જુબ બધાજ હઝાડસ વે ટ ુ ંિનયં ણ અને િનકાલ કરવામા ંઆવશે.
ુ ય હઝાડસ વે ટ, ઈટ પી કચરો, વપરાયે ુઓઈલ અને નકામી થેલીઓ છે.
વપરાયે ુઓઈલ એ જ જ યાએ ુ ીક ટ તર ક નુઃ વપરાશે અથવા ર સાઈકલરને વેચાશે ,
નકામી થેલીઓ મં ૂર થયેલ વે ડર ને વેચાશે. ઈટ પી કચરાનો મં ૂર થયેલ TSDF જ યાએ િનકાલ
કરવામા ંઆવશ.ે
એકમ હઝાડસ વે ટના સં હ માટ અલગ જ યા ફાળવશે આથી એકમ ારા અપાયેલી હઝાડસ
વે ટ મેનેજમે ટ પ ધિત રૂતી હશે અને હઝાડસ વે ટ મેનેજમે ટના લીધે પયાવરણ પર કોઈ મોટ અસર
નહ થાય.
૪.૪ ીન બે ટ ડવલોપમે ટ :-
એકમ આશર ૩૦૯૬ ચો.મી. ીન બે ટ િવ તારનો િવકાસ કરશ.ે નાથી જળવપરાશ ૫.૮
કલ/ દ. થશે.
૫.પયાવરણીય ચકાસણી યોજના:-
પયાવરણીય પ રબળોની ચકાસણી િવિવધ થળોએ પયાવરણીય અસરો તથા તેના ફરફારો
ઓળખવા માટ મદદ પ થશે.
આ હ થુી પયાવરણીય યવ થાપન યોજનાના પાલન માટ આસપાસની હવાની ણુવ ાની
ચકાસણી, ચીમનીમાથંી િનકળતા ૂષકો અનવે વિન માપદંડની ચકાસણી કાયદામા ંજણા યા જુબ
કરવામા ંઆવશે.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.22
૬. ણુા મક ર ક એના લિસસ:-
જોખમી રસાયણો માટ ર ક એનાલિસસ કરવામા ંઆવેલ છે. બધા જ જોખમી રસાયણોનો સં હણ
અને િનયં ણ MSDS ની માગદિશકા હઠળ કરવામા ંઆવશે. ય તગત ર ા મક સાધનો કાર ગરો ને
આપવામા ંઆવશે.
૭. ો ટ થી થતા લાભો:- ૂચત ો ટ આસપાસના િવ તારના સ દુાયના અથવા માળખાક ય િવકાસ , સામા ક િવકાસ ,
રોજગાર અને અ ય કાયદાઓની ટએ લાભદાયી બનશે.
ૂચત ો ટ ુશળ અને અધ ુશળ અને બન ુશળ કમચાર ઓને બાધંકામ તબ ો અને કામગીર તબ ા દરિમયાન રોજગાર આપવાની મતા ધરાવે છે. ૩૦ ટલા ય તઓને આ ો ટ ારા રોજગાર મળ શક છે. આ ો કટ સામા ક , આિથક િવકાસ માટ અને શૈ ણક સં થાઓ પાછળ ુલ ોફ ટના ૧.૫ % િપયા ખચ કરશે.
ૂચત ો ટ CSR ACTIVITY મા ં મતા જુબ કાયરત રહશે.
ઉપસહંાર :-
૧. હવાની ણુવ ા પર ન વી અસર થાય છે. જો ક હવા ૂષણ િનયં ણ માટના તમામ પગલા લેવામા ં આવશે
૨. કોઈ ઈકોલો કલ કુશાન થશે ન હ. ૩. જળ પયાવરણ પર કોઈ િત ળૂ અસર થશે ન હ. ૪. થાિનક રોજગાર ની તકો વધશે. ૫. િવિવધ પયાવરણીય પ રમાણો વા ક જગંલ, રા ય બગીચા, અ યાર ય અને ધામ ક તથા ઐતીહાિસક થળો પર કોઈ અસર થશે ન હ.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan formalin Pvt. Ltd
MM/s. T. R. Associates 10.23
૬. પયાવરણીય મેનેજમે ટ યોજના બધા ૂષણ પ રમાણોને િનયિં ત કરવા માટ ઘડવામા ંઆવી છે. અને આ પ રણામો સબંિધત સ ાિધકારો ારા થપાયેલ ધોરણ કરતા વધી ના ય એ પયાવરણ મેનેજમે ટ એકમ ારા ખાતર કરવામા ંઆવે છે.
૭. પયાવરણ મેનેજમે ટ સેલ ૂચત ો કટની શ આત પછ ૂષણ િનયં ણના ંપગલા ંલેશે. ૮. િન કષ એ ર તે કર શકાય ક બાધંકામ અને કાયરત તબ ા દરિમયાન કૂવામા ંઆવેલ પયાવરણીય સચંાલન યોજના અને શમનના પગલાનંા હકારા મક અમલીકરણ થી પયાવરણ પર થતી અસરોને ઘટાડ શકશ.ે
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 11.1
11.0 DISCLOSURE OF CONSULTANTS
11.1 Introduction of T. R. ASSOCIATES
T. R. ASSOCIATES is an organization working towards providing techno-economical
solutions through innovative ideas and indigenous technologies, in the field of
Pollution Control and Management. Having in-house facilities for Design, Execution,
Erection and Commissioning; T. R. Associates undertakes project from Concept to
Commissioning.
T. R. ASSOCIATES is enlisted as Environmental Consultants and are recognized as
Schedule-II Environmental Auditors by Gujarat Pollution Control Board.
SERVICES
T. R. Associates provides services in the areas,
Research & Development
Environment & Safety Consultation: Environmental Quality Monitoring
Engineering Designs
Environment & Safety Assessment: Environmental Impact Assessment
Environmental Audit
Safety Audit
Risk Assessment
Engineering Procurement & Commissioning: Effluent Treatment Plants
Sewage Treatment Plants
Common Effluent Treatment Plants
RO / UF / NF Plants
Operation & Maintenance of Treatment Plants
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 11.2
INFRASTRUCTURAL FACILITIES
Office Premises: Office area of around 930 sq. ft. is located in commercial area
on S. G. Highway, Opp. Gujarat High Court. The office and the
laboratory are located very near, which help in maintaining the
authenticity of the methodologies used for the analysis thus
helping in arriving at the quality solution timely.
Laboratory Facilities: Laboratory is a heart for any organization dealing in the
environmental field. T. R. Associates has a team of experience
personnel who are trained in sampling for air, water and
wastewater and for conducting Analysis, Treatability and
Feasibility studies at its own well-equipped laboratory.
Analytical Capability: The laboratory can undertake the qualitative and timely
analysis of all the environmental parameters concerning Air,
Water & Waste Water and Hazardous / Solid Waste.
R&D Facilities: Has established bench scale models for process development,
performance evaluation and process optimization.
Communication Facilities: Main facilities like office and laboratory are located very near thus aiding faster communication between the personnel’s thus helping at arriving to a solution faster. The infrastructure
is adequately equipped with Telephone connections, wi-fi
connection, Internet connection, Courier services etc. to have
faster communication with the outer world.
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 11.3
LIST OF INSTRUMENTS / EQUIPMENTS / MODEL
Magnetic Analytical Balance
pH meter
Conductivity Meter
COD Digestion Assembly
Incubator for BOD
Refrigerator for storage of samples and reagents
Digital UV Visible Spectrophotometer
Kjeldahl’s apparatus
Magnetic Stirrer with Hot Plate
Hot Plate
Other Glassware
Stack Monitoring Kits
High Volume Air Samplers
Respirable Dust Collector
PM2.5 Sampler
Wind Speed Meter
Wind Direction
Min. Max. Temperature Thermometer
Dry Bulb Wet Bulb
dB meter
Microscope with Halogen Lamp
Oven Temperature Controller
Muffle Furnace
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 11.4
EIA TEAM MEMBERS
This report was carried out by T.R. Associates with active co-operation from the project
proponent.
T.R. Associates team members worked upon this EIA report include:
EIA Coordinators: 1. Mr. T. R. Patel
Functional Area Experts:
Sr. No. Functional Areas Name of the Experts
1 AP Mr. T. R. Patel
2 WP Mr. T. R. Patel
3 SHW Mrs. Palak Thakkar
4 HG,GEO Mr. I. M. Patel
5 AQ Mrs. Hiral Shah
6 SC Dr. B.T. Patel
7 SE Mrs. Snehaben Patel
8 RH Mr. T. R. Patel
9 EB Dr. Pankaj Joshi
10 NV Mr. Rajendra Gohil
11 LU Mr. Vishwas Patel
Associate Functional Area Experts:
Sr. No. Functional Areas Name of the Experts
1 WP Mr. Malav P Dalwadi
2 WP Mr. Darshit Dave
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 11.5
Abbreviation
AP Air Pollution Prevention, Monitoring and Control
WP Water Pollution Prevention, Monitoring and Control
SHW Solid and Hazardous Waste Management
SE Socio Economy
EB Ecology & Biodiversity
HG Hydrology, Ground Water & Water Conservation
GS Geology & Soil
AQ Meteorology, Air Quality Modelling & Prediction
NV Noise & Vibration
LU Land use
RH Risk & Hazards
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 11.6
11.2 High Court Stay Order Copy Of T.R. Associates
Renewal Order Copy dated 9/12/2013
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 11.7
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 11.8
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 11.9
EIA Preparation for the Proposed Plant for Formaldehyde, Hexamine & Resin Manufacturing of M/s Pawan Formalin Pvt. Ltd
MM/s. T. R. Associates 11.10
AAnnexures
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
1 1
24 69
4 315
0 2013
11 1
2 23
70 4
315 0
2013 11
1 3
23 71
3 315
0 2013
11 1
4 22
76 2
292.5 0
2013 11
1 5
22 80
2 270
0 2013
11 1
6 22
80 2
292.5 0
2013 11
1 7
23 79
2 22.5
0 2013
11 1
8 24
71 3
45 0
2013 11
1 9
26 62
3 45
0 2013
11 1
10 29
51 5
67.5 0
2013 11
1 11
30 48
5 67.5
0 2013
11 1
12 30
46 6
45 0
2013 11
1 13
32 45
7 0
0 2013
11 1
14 33
38 8
22.5 0
2013 11
1 15
33 32
8 0
0 2013
11 1
16 33
34 8
337.5 0
2013 11
1 17
32 35
10 337.5
0 2013
11 1
18 31
40 8
337.5 0
2013 11
1 19
29 44
8 0
0 2013
11 1
20 27
49 8
22.5 0
2013 11
1 21
29 52
6 45
0 2013
11 1
22 29
56 6
67.5 0
2013 11
1 23
25 60
6 90
0 2013
11 1
24 24
62 5
90 0
2013 11
2 1
24 62
5 90
0 2013
11 2
2 23
64 3
90 0
2013 11
2 3
23 66
3 90
0 2013
11 2
4 22
68 2
67.5 0
2013 11
2 5
22 71
2 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
1
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
2 6
22 71
2 45
0 2013
11 2
7 23
71 2
45 0
2013 11
2 8
24 64
2 45
0 2013
11 2
9 27
54 3
22.5 0
2013 11
2 10
29 43
6 0
0 2013
11 2
11 31
35 8
0 0
2013 11
2 12
32 31
8 0
0 2013
11 2
13 33
28 10
0 0
2013 11
2 14
33 30
10 22.5
0 2013
11 2
15 33
31 10
0 0
2013 11
2 16
33 33
10 337.5
0 2013
11 2
17 32
35 11
315 0
2013 11
2 18
31 39
10 337.5
0 2013
11 2
19 29
43 8
0 0
2013 11
2 20
27 47
8 0
0 2013
11 2
21 26
52 6
22.5 0
2013 11
2 22
26 54
6 45
0 2013
11 2
23 25
58 6
67.5 0
2013 11
2 24
24 60
6 67.5
0 2013
11 3
1 24
62 5
67.5 0
2013 11
3 2
23 61
5 67.5
0 2013
11 3
3 23
64 3
3 0
2013 11
3 4
23 64
3 0
0 2013
11 3
5 22
68 3
315 0
2013 11
3 6
21 73
3 315
0 2013
11 3
7 21
73 3
315 0
2013 11
3 8
22 68
3 315
0 2013
11 3
9 25
56 5
0 0
2013 11
3 10
29 43
8 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
2
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
3 11
32 34
10 67.5
0 2013
11 3
12 33
32 10
67.5 0
2013 11
3 13
33 33
10 67.5
0 2013
11 3
14 32
34 10
67.5 0
2013 11
3 15
24 62
5 67.5
0 2013
11 3
16 23
61 5
67.5 0
2013 11
3 17
23 64
3 3
0 2013
11 3
18 23
64 3
0 0
2013 11
3 19
22 68
3 315
0 2013
11 3
20 21
73 3
315 0
2013 11
3 21
21 73
3 315
0 2013
11 3
22 22
68 3
315 0
2013 11
3 23
25 56
5 0
0 2013
11 3
24 29
43 8
45 0
2013 11
4 1
32 34
10 67.5
0 2013
11 4
2 23
73 2
315 0
2013 11
4 3
22 79
2 292.5
0 2013
11 4
4 22
81 2
270 0
2013 11
4 5
22 81
2 292.5
0 2013
11 4
6 23
79 2
22.5 0
2013 11
4 7
24 71
3 45
0 2013
11 4
8 26
62 3
45 0
2013 11
4 9
29 51
5 67.5
0 2013
11 4
10 30
48 5
67.5 0
2013 11
4 11
30 46
6 45
0 2013
11 4
12 32
45 7
0 0
2013 11
4 13
33 38
8 22.5
0 2013
11 4
14 33
32 8
0 0
2013 11
4 15
33 34
8 337.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
3
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
4 16
32 35
10 337.5
0 2013
11 4
17 31
40 8
337.5 0
2013 11
4 18
29 44
8 0
0 2013
11 4
19 26
54 6
45 0
2013 11
4 20
25 58
6 67.5
0 2013
11 4
21 24
60 6
67.5 0
2013 11
4 22
24 62
5 67.5
0 2013
11 4
23 23
61 5
67.5 0
2013 11
4 24
23 64
3 3
0 2013
11 5
1 23
64 3
0 0
2013 11
5 2
22 68
3 315
0 2013
11 5
3 21
73 3
315 0
2013 11
5 4
21 73
3 315
0 2013
11 5
5 22
68 3
315 0
2013 11
5 6
25 56
5 0
0 2013
11 5
7 29
43 8
45 0
2013 11
5 8
32 34
10 67.5
0 2013
11 5
9 23
73 2
315 0
2013 11
5 10
22 79
2 292.5
0 2013
11 5
11 22
81 2
270 0
2013 11
5 12
22 81
2 292.5
0 2013
11 5
13 23
79 2
22.5 0
2013 11
5 14
24 71
3 45
0 2013
11 5
15 26
62 3
45 0
2013 11
5 16
29 51
5 67.5
0 2013
11 5
17 30
48 5
67.5 0
2013 11
5 18
30 46
6 45
0 2013
11 5
19 32
45 7
0 0
2013 11
5 20
33 38
8 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
4
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
5 21
33 32
8 0
0 2013
11 5
22 33
34 8
337.5 0
2013 11
5 23
32 35
10 337.5
0 2013
11 5
24 31
40 8
337.5 0
2013 11
6 1
29 44
8 0
0 2013
11 6
2 27
49 8
22.5 0
2013 11
6 3
29 52
6 45
0 2013
11 6
4 29
56 6
67.5 0
2013 11
6 5
25 60
6 90
0 2013
11 6
6 24
62 5
90 0
2013 11
6 7
24 62
5 90
0 2013
11 6
8 23
64 3
90 0
2013 11
6 9
23 66
3 90
0 2013
11 6
10 22
68 2
67.5 0
2013 11
6 11
22 71
2 67.5
0 2013
11 6
12 22
71 2
45 0
2013 11
6 13
23 71
2 45
0 2013
11 6
14 24
64 2
45 0
2013 11
6 15
27 54
3 22.5
0 2013
11 6
16 29
43 6
0 0
2013 11
6 17
31 35
8 0
0 2013
11 6
18 32
31 8
0 0
2013 11
6 19
33 28
10 0
0 2013
11 6
20 33
30 10
22.5 0
2013 11
6 21
33 31
10 0
0 2013
11 6
22 33
33 10
337.5 0
2013 11
6 23
32 35
11 315
0 2013
11 6
24 31
39 10
337.5 0
2013 11
7 1
29 43
8 0
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
5
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
7 2
27 47
8 0
0 2013
11 7
3 26
52 6
22.5 0
2013 11
7 4
26 54
6 45
0 2013
11 7
5 25
58 6
67.5 0
2013 11
7 6
24 60
6 67.5
0 2013
11 7
7 24
62 5
67.5 0
2013 11
7 8
23 61
5 67.5
0 2013
11 7
9 23
64 3
3 0
2013 11
7 10
23 64
3 0
0 2013
11 7
11 22
68 3
315 0
2013 11
7 12
21 73
3 315
0 2013
11 7
13 21
73 3
315 0
2013 11
7 14
22 68
3 315
0 2013
11 7
15 25
56 5
0 0
2013 11
7 16
29 43
8 45
0 2013
11 7
17 32
34 10
67.5 0
2013 11
7 18
33 32
10 67.5
0 2013
11 7
19 33
33 10
67.5 0
2013 11
7 20
32 34
10 67.5
0 2013
11 7
21 31
31 10
45 0
2013 11
7 22
31 31
10 45
0 2013
11 7
23 31
30 11
45 0
2013 11
7 24
31 31
11 22.5
0 2013
11 8
1 30
33 11
22.5 0
2013 11
8 2
28 38
11 0
0 2013
11 8
3 26
45 10
0 0
2013 11
8 4
24 52
8 0
0 2013
11 8
5 23
55 8
22.5 0
2013 11
8 6
23 57
8 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
6
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
8 7
22 59
8 45
0 2013
11 8
8 22
61 6
22.5 0
2013 11
8 9
21 63
6 0
0 2013
11 8
10 21
63 6
0 0
2013 11
8 11
21 65
6 0
0 2013
11 8
12 20
68 5
22.5 0
2013 11
8 13
20 68
5 45
0 2013
11 8
14 19
68 5
45 0
2013 11
8 15
20 65
5 45
0 2013
11 8
16 21
59 5
45 0
2013 11
8 17
24 50
5 45
0 2013
11 8
18 26
43 6
45 0
2013 11
8 19
29 37
8 22.5
0 2013
11 8
20 30
33 8
22.5 0
2013 11
8 21
31 31
8 22.5
0 2013
11 8
22 31
31 8
0 0
2013 11
8 23
31 30
10 0
0 2013
11 8
24 31
30 10
0 0
2013 11
9 1
29 33
11 0
0 2013
11 9
2 28
37 10
0 0
2013 11
9 3
26 43
6 0
0 2013
11 9
4 24
48 6
0 0
2013 11
9 5
23 51
6 22.5
0 2013
11 9
6 23
53 7
22.5 0
2013 11
9 7
22 57
7 45
0 2013
11 9
8 22
57 5
45 0
2013 11
9 9
22 59
5 45
0 2013
11 9
10 21
61 6
45 0
2013 11
9 11
21 59
6 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
7
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
9 12
20 63
5 67.5
0 2013
11 9
13 19
63 5
67.5 0
2013 11
9 14
20 61
5 67.5
0 2013
11 9
15 21
59 5
90 0
2013 11
9 16
22 55
5 90
0 2013
11 9
17 24
48 6
67.5 0
2013 11
9 18
27 42
8 67.5
0 2013
11 9
19 29
37 8
45 0
2013 11
9 20
26 54
6 45
0 2013
11 9
21 22
71 2
45 0
2013 11
9 22
23 71
2 45
0 2013
11 9
23 24
64 2
45 0
2013 11
9 24
27 54
3 22.5
0 2013
11 10
1 29
43 6
0 0
2013 11
10 2
31 35
8 0
0 2013
11 10
3 32
31 8
0 0
2013 11
10 4
33 28
10 0
0 2013
11 10
5 33
30 10
22.5 0
2013 11
10 6
33 31
10 0
0 2013
11 10
7 24
62 5
67.5 0
2013 11
10 8
23 61
5 67.5
0 2013
11 10
9 23
64 3
3 0
2013 11
10 10
23 64
3 0
0 2013
11 10
11 22
68 3
315 0
2013 11
10 12
22 59
8 45
0 2013
11 10
13 22
61 6
22.5 0
2013 11
10 14
21 63
6 0
0 2013
11 10
15 21
63 6
0 0
2013 11
10 16
21 65
6 0
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
8
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
10 17
20 68
5 22.5
0 2013
11 10
18 20
68 5
45 0
2013 11
10 19
19 68
5 45
0 2013
11 10
20 20
65 5
45 0
2013 11
10 21
21 59
5 45
0 2013
11 10
22 24
50 5
45 0
2013 11
10 23
26 43
6 45
0 2013
11 10
24 29
37 8
22.5 0
2013 11
11 1
30 33
8 22.5
0 2013
11 11
2 31
31 8
22.5 0
2013 11
11 3
31 31
8 0
0 2013
11 11
4 31
30 10
0 0
2013 11
11 5
31 30
10 0
0 2013
11 11
6 29
33 11
0 0
2013 11
11 7
28 37
10 0
0 2013
11 11
8 26
43 6
0 0
2013 11
11 9
24 48
6 0
0 2013
11 11
10 23
51 6
22.5 0
2013 11
11 11
23 53
7 22.5
0 2013
11 11
12 22
57 7
45 0
2013 11
11 13
22 57
5 45
0 2013
11 11
14 22
59 5
45 0
2013 11
11 15
21 61
6 45
0 2013
11 11
16 21
59 6
45 0
2013 11
11 17
30 33
11 22.5
0 2013
11 11
18 28
38 11
0 0
2013 11
11 19
26 45
10 0
0 2013
11 11
20 24
52 8
0 0
2013 11
11 21
23 55
8 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
9
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
11 22
23 57
8 22.5
0 2013
11 11
23 22
59 8
45 0
2013 11
11 24
22 61
6 22.5
0 2013
11 12
1 21
63 6
0 0
2013 11
12 2
21 63
6 0
0 2013
11 12
3 21
65 6
0 0
2013 11
12 4
20 68
5 22.5
0 2013
11 12
5 20
68 5
45 0
2013 11
12 6
19 68
5 45
0 2013
11 12
7 20
65 5
45 0
2013 11
12 8
21 59
5 45
0 2013
11 12
9 24
50 5
45 0
2013 11
12 10
26 43
6 45
0 2013
11 12
11 29
37 8
22.5 0
2013 11
12 12
30 33
8 22.5
0 2013
11 12
13 31
31 8
22.5 0
2013 11
12 14
31 31
8 0
0 2013
11 12
15 31
30 10
0 0
2013 11
12 16
31 30
10 0
0 2013
11 12
17 29
33 11
0 0
2013 11
12 18
28 37
10 0
0 2013
11 12
19 26
43 6
0 0
2013 11
12 20
24 48
6 0
0 2013
11 12
21 23
51 6
22.5 0
2013 11
12 22
23 53
7 22.5
0 2013
11 12
23 22
57 7
45 0
2013 11
12 24
22 57
5 45
0 2013
11 13
1 22
59 5
45 0
2013 11
13 2
21 61
6 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
10
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
13 3
21 59
6 45
0 2013
11 13
4 20
63 5
67.5 0
2013 11
13 5
19 63
5 67.5
0 2013
11 13
6 20
61 5
67.5 0
2013 11
13 7
21 59
5 90
0 2013
11 13
8 22
55 5
90 0
2013 11
13 9
24 48
6 67.5
0 2013
11 13
10 27
42 8
67.5 0
2013 11
13 11
29 37
8 45
0 2013
11 13
12 33
30 10
22.5 0
2013 11
13 13
33 31
10 0
0 2013
11 13
14 33
33 10
337.5 0
2013 11
13 15
32 35
11 315
0 2013
11 13
16 31
39 10
337.5 0
2013 11
13 17
29 43
8 0
0 2013
11 13
18 27
47 8
0 0
2013 11
13 19
26 52
6 22.5
0 2013
11 13
20 26
54 6
45 0
2013 11
13 21
25 58
6 67.5
0 2013
11 13
22 24
60 6
67.5 0
2013 11
13 23
25 58
6 67.5
0 2013
11 13
24 24
60 6
67.5 0
2013 11
14 1
24 62
5 67.5
0 2013
11 14
2 23
61 5
67.5 0
2013 11
14 3
23 64
3 3
0 2013
11 14
4 23
64 3
0 0
2013 11
14 5
22 68
3 315
0 2013
11 14
6 21
73 3
315 0
2013 11
14 7
21 73
3 315
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
11
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
14 8
22 68
3 315
0 2013
11 14
9 25
56 5
0 0
2013 11
14 10
29 43
8 45
0 2013
11 14
11 32
34 10
67.5 0
2013 11
14 12
23 73
2 315
0 2013
11 14
13 22
79 2
292.5 0
2013 11
14 14
22 81
2 270
0 2013
11 14
15 22
81 2
292.5 0
2013 11
14 16
23 79
2 22.5
0 2013
11 14
17 24
71 3
45 0
2013 11
14 18
26 62
3 45
0 2013
11 14
19 29
51 5
67.5 0
2013 11
14 20
30 48
5 67.5
0 2013
11 14
21 30
46 6
45 0
2013 11
14 22
32 45
7 0
0 2013
11 14
23 33
38 8
22.5 0
2013 11
14 24
33 32
8 0
0 2013
11 15
1 33
34 8
337.5 0
2013 11
15 2
32 35
10 337.5
0 2013
11 15
3 31
40 8
337.5 0
2013 11
15 4
29 44
8 0
0 2013
11 15
5 27
49 8
22.5 0
2013 11
15 6
29 52
6 45
0 2013
11 15
7 29
56 6
67.5 0
2013 11
15 8
25 60
6 90
0 2013
11 15
9 24
62 5
90 0
2013 11
15 10
24 62
5 90
0 2013
11 15
11 23
64 3
90 0
2013 11
15 12
23 66
3 90
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
12
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
15 13
22 68
2 67.5
0 2013
11 15
14 22
71 2
67.5 0
2013 11
15 15
22 71
2 45
0 2013
11 15
16 23
71 2
45 0
2013 11
15 17
24 64
2 45
0 2013
11 15
18 27
54 3
22.5 0
2013 11
15 19
29 43
6 0
0 2013
11 15
20 31
35 8
0 0
2013 11
15 21
32 31
8 0
0 2013
11 15
22 33
28 10
0 0
2013 11
15 23
33 30
10 22.5
0 2013
11 15
24 33
31 10
0 0
2013 11
16 1
33 33
10 337.5
0 2013
11 16
2 32
35 11
315 0
2013 11
16 3
31 39
10 337.5
0 2013
11 16
4 29
43 8
0 0
2013 11
16 5
27 47
8 0
0 2013
11 16
6 26
52 6
22.5 0
2013 11
16 7
26 54
6 45
0 2013
11 16
8 25
58 6
67.5 0
2013 11
16 9
24 60
6 67.5
0 2013
11 16
10 23
64 3
90 0
2013 11
16 11
23 66
3 90
0 2013
11 16
12 22
68 2
67.5 0
2013 11
16 13
22 71
2 67.5
0 2013
11 16
14 22
71 2
45 0
2013 11
16 15
23 71
2 45
0 2013
11 16
16 24
64 2
45 0
2013 11
16 17
27 54
3 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
13
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
16 18
29 43
6 0
0 2013
11 16
19 31
35 8
0 0
2013 11
16 20
32 31
8 0
0 2013
11 16
21 33
28 10
0 0
2013 11
16 22
33 30
10 22.5
0 2013
11 16
23 33
31 10
0 0
2013 11
16 24
33 33
10 337.5
0 2013
11 17
1 32
35 11
315 0
2013 11
17 2
31 39
10 337.5
0 2013
11 17
3 29
43 8
0 0
2013 11
17 4
27 47
8 0
0 2013
11 17
5 26
52 6
22.5 0
2013 11
17 6
26 54
6 45
0 2013
11 17
7 25
58 6
67.5 0
2013 11
17 8
24 60
6 67.5
0 2013
11 17
9 24
62 5
67.5 0
2013 11
17 10
23 61
5 67.5
0 2013
11 17
11 23
64 3
3 0
2013 11
17 12
23 64
3 0
0 2013
11 17
13 22
68 3
315 0
2013 11
17 14
21 73
3 315
0 2013
11 17
15 21
73 3
315 0
2013 11
17 16
22 68
3 315
0 2013
11 17
17 25
56 5
0 0
2013 11
17 18
29 43
8 45
0 2013
11 17
19 32
34 10
67.5 0
2013 11
17 20
23 73
2 315
0 2013
11 17
21 22
79 2
292.5 0
2013 11
17 22
22 81
2 270
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
14
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
17 23
22 81
2 292.5
0 2013
11 17
24 23
79 2
22.5 0
2013 11
18 1
24 71
3 45
0 2013
11 18
2 26
62 3
45 0
2013 11
18 3
29 51
5 67.5
0 2013
11 18
4 30
48 5
67.5 0
2013 11
18 5
30 46
6 45
0 2013
11 18
6 32
45 7
0 0
2013 11
18 7
33 38
8 22.5
0 2013
11 18
8 33
32 8
0 0
2013 11
18 9
33 34
8 337.5
0 2013
11 18
10 32
35 10
337.5 0
2013 11
18 11
31 40
8 337.5
0 2013
11 18
12 29
44 8
0 0
2013 11
18 13
26 54
6 45
0 2013
11 18
14 25
58 6
67.5 0
2013 11
18 15
24 60
6 67.5
0 2013
11 18
16 24
62 5
67.5 0
2013 11
18 17
23 61
5 67.5
0 2013
11 18
18 23
64 3
3 0
2013 11
18 19
23 64
3 0
0 2013
11 18
20 22
68 3
315 0
2013 11
18 21
21 73
3 315
0 2013
11 18
22 21
73 3
315 0
2013 11
18 23
22 68
3 315
0 2013
11 18
24 25
56 5
0 0
2013 11
19 1
29 43
8 45
0 2013
11 19
2 32
34 10
67.5 0
2013 11
19 3
23 73
2 315
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
15
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
19 4
22 79
2 292.5
0 2013
11 19
5 22
81 2
270 0
2013 11
19 6
22 81
2 292.5
0 2013
11 19
7 23
79 2
22.5 0
2013 11
19 8
24 71
3 45
0 2013
11 19
9 26
62 3
45 0
2013 11
19 10
29 51
5 67.5
0 2013
11 19
11 30
48 5
67.5 0
2013 11
19 12
30 46
6 45
0 2013
11 19
13 32
45 7
0 0
2013 11
19 14
33 38
8 22.5
0 2013
11 19
15 33
32 8
0 0
2013 11
19 16
33 34
8 337.5
0 2013
11 19
17 32
35 10
337.5 0
2013 11
19 18
31 40
8 337.5
0 2013
11 19
19 29
44 8
0 0
2013 11
19 20
27 49
8 22.5
0 2013
11 19
21 29
52 6
45 0
2013 11
19 22
29 56
6 67.5
0 2013
11 19
23 25
60 6
90 0
2013 11
19 24
24 62
5 90
0 2013
11 20
1 24
62 5
90 0
2013 11
20 2
23 64
3 90
0 2013
11 20
3 23
66 3
90 0
2013 11
20 4
22 68
2 67.5
0 2013
11 20
5 22
71 2
67.5 0
2013 11
20 6
22 71
2 45
0 2013
11 20
7 23
71 2
45 0
2013 11
20 8
24 64
2 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
16
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
20 9
27 54
3 22.5
0 2013
11 20
10 29
43 6
0 0
2013 11
20 11
31 35
8 0
0 2013
11 20
12 32
31 8
0 0
2013 11
20 13
33 28
10 0
0 2013
11 20
14 33
30 10
22.5 0
2013 11
20 15
33 31
10 0
0 2013
11 20
16 33
33 10
337.5 0
2013 11
20 17
32 35
11 315
0 2013
11 20
18 31
39 10
337.5 0
2013 11
20 19
29 43
8 0
0 2013
11 20
20 27
47 8
0 0
2013 11
20 21
26 52
6 22.5
0 2013
11 20
22 26
54 6
45 0
2013 11
20 23
25 58
6 67.5
0 2013
11 20
24 24
60 6
67.5 0
2013 11
21 1
24 62
5 67.5
0 2013
11 21
2 23
61 5
67.5 0
2013 11
21 3
23 64
3 3
0 2013
11 21
4 23
64 3
0 0
2013 11
21 5
22 68
3 315
0 2013
11 21
6 21
73 3
315 0
2013 11
21 7
21 73
3 315
0 2013
11 21
8 22
68 3
315 0
2013 11
21 9
25 56
5 0
0 2013
11 21
10 29
43 8
45 0
2013 11
21 11
32 34
10 67.5
0 2013
11 21
12 33
32 10
67.5 0
2013 11
21 13
33 33
10 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
17
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
21 14
32 34
10 67.5
0 2013
11 21
15 31
31 10
45 0
2013 11
21 16
31 31
10 45
0 2013
11 21
17 31
30 11
45 0
2013 11
21 18
31 31
11 22.5
0 2013
11 21
19 30
33 11
22.5 0
2013 11
21 20
28 38
11 0
0 2013
11 21
21 26
45 10
0 0
2013 11
21 22
24 52
8 0
0 2013
11 21
23 23
55 8
22.5 0
2013 11
21 24
23 57
8 22.5
0 2013
11 22
1 22
59 8
45 0
2013 11
22 2
22 61
6 22.5
0 2013
11 22
3 21
63 6
0 0
2013 11
22 4
21 63
6 0
0 2013
11 22
5 21
65 6
0 0
2013 11
22 6
20 68
5 22.5
0 2013
11 22
7 20
68 5
45 0
2013 11
22 8
19 68
5 45
0 2013
11 22
9 20
65 5
45 0
2013 11
22 10
21 59
5 45
0 2013
11 22
11 24
50 5
45 0
2013 11
22 12
26 43
6 45
0 2013
11 22
13 29
37 8
22.5 0
2013 11
22 14
30 33
8 22.5
0 2013
11 22
15 31
31 8
22.5 0
2013 11
22 16
31 31
8 0
0 2013
11 22
17 31
30 10
0 0
2013 11
22 18
31 30
10 0
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
18
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
22 19
29 33
11 0
0 2013
11 22
20 28
37 10
0 0
2013 11
22 21
26 43
6 0
0 2013
11 22
22 24
48 6
0 0
2013 11
22 23
23 51
6 22.5
0 2013
11 22
24 23
53 7
22.5 0
2013 11
23 1
22 57
7 45
0 2013
11 23
2 22
57 5
45 0
2013 11
23 3
22 59
5 45
0 2013
11 23
4 21
61 6
45 0
2013 11
23 5
21 59
6 45
0 2013
11 23
6 20
63 5
67.5 0
2013 11
23 7
19 63
5 67.5
0 2013
11 23
8 20
61 5
67.5 0
2013 11
23 9
21 59
5 90
0 2013
11 23
10 22
55 5
90 0
2013 11
23 11
24 48
6 67.5
0 2013
11 23
12 27
42 8
67.5 0
2013 11
23 13
29 37
8 45
0 2013
11 23
14 26
54 6
45 0
2013 11
23 15
25 58
6 67.5
0 2013
11 23
16 24
60 6
67.5 0
2013 11
23 17
24 62
5 67.5
0 2013
11 23
18 23
61 5
67.5 0
2013 11
23 19
23 64
3 3
0 2013
11 23
20 23
64 3
0 0
2013 11
23 21
22 68
3 315
0 2013
11 23
22 21
73 3
315 0
2013 11
23 23
21 73
3 315
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
19
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
23 24
22 68
3 315
0 2013
11 24
1 25
56 5
0 0
2013 11
24 2
29 43
8 45
0 2013
11 24
3 32
34 10
67.5 0
2013 11
24 4
33 32
10 67.5
0 2013
11 24
5 33
33 10
67.5 0
2013 11
24 6
32 34
10 67.5
0 2013
11 24
7 31
31 10
45 0
2013 11
24 8
31 31
10 45
0 2013
11 24
9 31
30 11
45 0
2013 11
24 10
31 31
11 22.5
0 2013
11 24
11 33
32 8
0 0
2013 11
24 12
33 34
8 337.5
0 2013
11 24
13 32
35 10
337.5 0
2013 11
24 14
31 40
8 337.5
0 2013
11 24
15 29
44 8
0 0
2013 11
24 16
27 49
8 22.5
0 2013
11 24
17 29
52 6
45 0
2013 11
24 18
29 56
6 67.5
0 2013
11 24
19 25
60 6
90 0
2013 11
24 20
24 62
5 90
0 2013
11 24
21 24
62 5
90 0
2013 11
24 22
23 64
3 90
0 2013
11 24
23 23
66 3
90 0
2013 11
24 24
22 68
2 67.5
0 2013
11 25
1 22
71 2
67.5 0
2013 11
25 2
22 71
2 45
0 2013
11 25
3 23
71 2
45 0
2013 11
25 4
24 64
2 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
20
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
25 5
27 54
3 22.5
0 2013
11 25
6 29
43 6
0 0
2013 11
25 7
31 35
8 0
0 2013
11 25
8 32
31 8
0 0
2013 11
25 9
33 28
10 0
0 2013
11 25
10 33
30 10
22.5 0
2013 11
25 11
33 31
10 0
0 2013
11 25
12 24
62 5
67.5 0
2013 11
25 13
23 61
5 67.5
0 2013
11 25
14 23
64 3
3 0
2013 11
25 15
23 64
3 0
0 2013
11 25
16 22
68 3
315 0
2013 11
25 17
21 73
3 315
0 2013
11 25
18 21
73 3
315 0
2013 11
25 19
22 68
3 315
0 2013
11 25
20 25
56 5
0 0
2013 11
25 21
29 43
8 45
0 2013
11 25
22 32
34 10
67.5 0
2013 11
25 23
33 32
10 67.5
0 2013
11 25
24 33
33 10
67.5 0
2013 11
26 1
32 34
10 67.5
0 2013
11 26
2 31
31 10
45 0
2013 11
26 3
31 31
10 45
0 2013
11 26
4 31
30 11
45 0
2013 11
26 5
31 31
11 22.5
0 2013
11 26
6 23
71 2
45 0
2013 11
26 7
24 64
2 45
0 2013
11 26
8 27
54 3
22.5 0
2013 11
26 9
29 43
6 0
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
21
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
26 10
31 35
8 0
0 2013
11 26
11 32
31 8
0 0
2013 11
26 12
33 28
10 0
0 2013
11 26
13 33
30 10
22.5 0
2013 11
26 14
33 31
10 0
0 2013
11 26
15 24
62 5
67.5 0
2013 11
26 16
23 61
5 67.5
0 2013
11 26
17 23
64 3
3 0
2013 11
26 18
23 64
3 0
0 2013
11 26
19 22
68 3
315 0
2013 11
26 20
21 73
3 315
0 2013
11 26
21 21
73 3
315 0
2013 11
26 22
22 68
3 315
0 2013
11 26
23 25
56 5
0 0
2013 11
26 24
29 43
8 45
0 2013
11 27
1 33
28 10
0 0
2013 11
27 2
33 30
10 22.5
0 2013
11 27
3 33
31 10
0 0
2013 11
27 4
24 62
5 67.5
0 2013
11 27
5 23
61 5
67.5 0
2013 11
27 6
23 64
3 3
0 2013
11 27
7 23
64 3
0 0
2013 11
27 8
22 68
3 315
0 2013
11 27
9 21
73 3
315 0
2013 11
27 10
21 73
3 315
0 2013
11 27
11 22
68 3
315 0
2013 11
27 12
25 56
5 0
0 2013
11 27
13 29
43 8
45 0
2013 11
27 14
32 34
10 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
22
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
27 15
33 32
10 67.5
0 2013
11 27
16 33
33 10
67.5 0
2013 11
27 17
32 34
10 67.5
0 2013
11 27
18 31
31 10
45 0
2013 11
27 19
31 31
10 45
0 2013
11 27
20 31
30 11
45 0
2013 11
27 21
31 31
11 22.5
0 2013
11 27
22 23
71 2
45 0
2013 11
27 23
24 64
2 45
0 2013
11 27
24 27
54 3
22.5 0
2013 11
28 1
29 43
6 0
0 2013
11 28
2 31
35 8
0 0
2013 11
28 3
32 31
8 0
0 2013
11 28
4 33
28 10
0 0
2013 11
28 5
33 30
10 22.5
0 2013
11 28
6 31
31 8
22.5 0
2013 11
28 7
31 31
8 0
0 2013
11 28
8 31
30 10
0 0
2013 11
28 9
31 30
10 0
0 2013
11 28
10 29
33 11
0 0
2013 11
28 11
28 37
10 0
0 2013
11 28
12 26
43 6
0 0
2013 11
28 13
24 48
6 0
0 2013
11 28
14 23
51 6
22.5 0
2013 11
28 15
23 53
7 22.5
0 2013
11 28
16 22
57 7
45 0
2013 11
28 17
22 57
5 45
0 2013
11 28
18 22
59 5
45 0
2013 11
28 19
21 61
6 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
23
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
28 20
21 59
6 45
0 2013
11 28
21 20
63 5
67.5 0
2013 11
28 22
19 63
5 67.5
0 2013
11 28
23 20
61 5
67.5 0
2013 11
28 24
21 59
5 90
0 2013
11 29
1 22
55 5
90 0
2013 11
29 2
24 48
6 67.5
0 2013
11 29
3 27
42 8
67.5 0
2013 11
29 4
29 37
8 45
0 2013
11 29
5 26
54 6
45 0
2013 11
29 6
25 58
6 67.5
0 2013
11 29
7 24
60 6
67.5 0
2013 11
29 8
24 62
5 67.5
0 2013
11 29
9 23
61 5
67.5 0
2013 11
29 10
23 64
3 3
0 2013
11 29
11 23
64 3
0 0
2013 11
29 12
22 68
3 315
0 2013
11 29
13 21
73 3
315 0
2013 11
29 14
21 73
3 315
0 2013
11 29
15 22
68 3
315 0
2013 11
29 16
25 56
5 0
0 2013
11 29
17 29
43 8
45 0
2013 11
29 18
32 34
10 67.5
0 2013
11 29
19 33
32 10
67.5 0
2013 11
29 20
33 33
10 67.5
0 2013
11 29
21 32
34 10
67.5 0
2013 11
29 22
31 31
10 45
0 2013
11 29
23 31
31 10
45 0
2013 11
29 24
31 30
11 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
24
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 11
30 1
31 31
11 22.5
0 2013
11 30
2 33
32 8
0 0
2013 11
30 3
33 34
8 337.5
0 2013
11 30
4 32
35 10
337.5 0
2013 11
30 5
31 40
8 337.5
0 2013
11 30
6 29
44 8
0 0
2013 11
30 7
27 49
8 22.5
0 2013
11 30
8 29
52 6
45 0
2013 11
30 9
29 56
6 67.5
0 2013
11 30
10 25
60 6
90 0
2013 11
30 11
24 62
5 90
0 2013
11 30
12 24
62 5
90 0
2013 11
30 13
23 64
3 90
0 2013
11 30
14 23
66 3
90 0
2013 11
30 15
22 68
2 67.5
0 2013
11 30
16 22
71 2
67.5 0
2013 11
30 17
22 71
2 45
0 2013
11 30
18 23
71 2
45 0
2013 11
30 19
24 64
2 45
0 2013
11 30
20 27
54 3
22.5 0
2013 11
30 21
29 43
6 0
0 2013
11 30
22 31
35 8
0 0
2013 11
30 23
32 31
8 0
0 2013
11 30
24 33
28 10
0 0
2013 12
1 1
33 30
10 22.5
0 2013
12 1
2 33
31 10
0 0
2013 12
1 3
24 62
5 67.5
0 2013
12 1
4 23
61 5
67.5 0
2013 12
1 5
23 64
3 3
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
25
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
1 6
23 64
3 0
0 2013
12 1
7 22
68 3
315 0
2013 12
1 8
21 73
3 315
0 2013
12 1
9 21
73 3
315 0
2013 12
1 10
22 68
3 315
0 2013
12 1
11 25
56 5
0 0
2013 12
1 12
29 43
8 45
0 2013
12 1
13 32
34 10
67.5 0
2013 12
1 14
33 32
10 67.5
0 2013
12 1
15 33
33 10
67.5 0
2013 12
1 16
32 34
10 67.5
0 2013
12 1
17 31
31 10
45 0
2013 12
1 18
31 31
10 45
0 2013
12 1
19 31
30 11
45 0
2013 12
1 20
31 31
11 22.5
0 2013
12 1
21 23
71 2
45 0
2013 12
1 22
24 64
2 45
0 2013
12 1
23 27
54 3
22.5 0
2013 12
1 24
29 43
6 0
0 2013
12 2
1 31
35 8
0 0
2013 12
2 2
32 31
8 0
0 2013
12 2
3 33
28 10
0 0
2013 12
2 4
33 30
10 22.5
0 2013
12 2
5 33
31 10
0 0
2013 12
2 6
24 62
5 67.5
0 2013
12 2
7 23
61 5
67.5 0
2013 12
2 8
23 64
3 3
0 2013
12 2
9 23
64 3
0 0
2013 12
2 10
22 68
3 315
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
26
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
2 11
21 73
3 315
0 2013
12 2
12 21
73 3
315 0
2013 12
2 13
22 68
3 315
0 2013
12 2
14 25
56 5
0 0
2013 12
2 15
29 43
8 45
0 2013
12 2
16 33
28 10
0 0
2013 12
2 17
33 30
10 22.5
0 2013
12 2
18 33
31 10
0 0
2013 12
2 19
24 62
5 67.5
0 2013
12 2
20 23
61 5
67.5 0
2013 12
2 21
23 64
3 3
0 2013
12 2
22 23
64 3
0 0
2013 12
2 23
22 68
3 315
0 2013
12 2
24 21
73 3
315 0
2013 12
3 1
21 73
3 315
0 2013
12 3
2 22
68 3
315 0
2013 12
3 3
25 56
5 0
0 2013
12 3
4 29
43 8
45 0
2013 12
3 5
32 34
10 67.5
0 2013
12 3
6 33
32 10
67.5 0
2013 12
3 7
33 33
10 67.5
0 2013
12 3
8 29
43 8
45 0
2013 12
3 9
32 34
10 67.5
0 2013
12 3
10 33
32 10
67.5 0
2013 12
3 11
33 33
10 67.5
0 2013
12 3
12 32
34 10
67.5 0
2013 12
3 13
31 31
10 45
0 2013
12 3
14 31
31 10
45 0
2013 12
3 15
31 30
11 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
27
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
3 16
31 31
11 22.5
0 2013
12 3
17 23
71 2
45 0
2013 12
3 18
24 64
2 45
0 2013
12 3
19 27
54 3
22.5 0
2013 12
3 20
29 43
6 0
0 2013
12 3
21 31
35 8
0 0
2013 12
3 22
32 31
8 0
0 2013
12 3
23 33
28 10
0 0
2013 12
3 24
33 30
10 22.5
0 2013
12 4
1 31
31 8
22.5 0
2013 12
4 2
31 31
8 0
0 2013
12 4
3 31
30 10
0 0
2013 12
4 4
31 30
10 0
0 2013
12 4
5 29
33 11
0 0
2013 12
4 6
28 37
10 0
0 2013
12 4
7 26
43 6
0 0
2013 12
4 8
24 48
6 0
0 2013
12 4
9 23
51 6
22.5 0
2013 12
4 10
23 53
7 22.5
0 2013
12 4
11 22
57 7
45 0
2013 12
4 12
22 57
5 45
0 2013
12 4
13 22
59 5
45 0
2013 12
4 14
21 61
6 45
0 2013
12 4
15 21
59 6
45 0
2013 12
4 16
20 63
5 67.5
0 2013
12 4
17 19
63 5
67.5 0
2013 12
4 18
20 61
5 67.5
0 2013
12 4
19 21
59 5
90 0
2013 12
4 20
22 55
5 90
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
28
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
4 21
24 48
6 67.5
0 2013
12 4
22 27
42 8
67.5 0
2013 12
4 23
29 37
8 45
0 2013
12 4
24 26
54 6
45 0
2013 12
5 1
25 58
6 67.5
0 2013
12 5
2 24
60 6
67.5 0
2013 12
5 3
24 62
5 67.5
0 2013
12 5
4 23
61 5
67.5 0
2013 12
5 5
23 64
3 3
0 2013
12 5
6 23
64 3
0 0
2013 12
5 7
22 68
3 315
0 2013
12 5
8 21
73 3
315 0
2013 12
5 9
21 73
3 315
0 2013
12 5
10 22
68 3
315 0
2013 12
5 11
25 56
5 0
0 2013
12 5
12 29
43 8
45 0
2013 12
5 13
33 28
10 0
0 2013
12 5
14 33
30 10
22.5 0
2013 12
5 15
33 31
10 0
0 2013
12 5
16 24
62 5
67.5 0
2013 12
5 17
23 61
5 67.5
0 2013
12 5
18 23
64 3
3 0
2013 12
5 19
23 64
3 0
0 2013
12 5
20 22
68 3
315 0
2013 12
5 21
21 73
3 315
0 2013
12 5
22 21
73 3
315 0
2013 12
5 23
22 68
3 315
0 2013
12 5
24 25
56 5
0 0
2013 12
6 1
29 43
8 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
29
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
6 2
32 34
10 67.5
0 2013
12 6
3 33
32 10
67.5 0
2013 12
6 4
33 33
10 67.5
0 2013
12 6
5 29
43 8
45 0
2013 12
6 6
32 34
10 67.5
0 2013
12 6
7 33
32 10
67.5 0
2013 12
6 8
33 33
10 67.5
0 2013
12 6
9 32
34 10
67.5 0
2013 12
6 10
31 31
10 45
0 2013
12 6
11 31
31 10
45 0
2013 12
6 12
31 30
11 45
0 2013
12 6
13 31
31 11
22.5 0
2013 12
6 14
23 71
2 45
0 2013
12 6
15 24
64 2
45 0
2013 12
6 16
27 54
3 22.5
0 2013
12 6
17 29
43 6
0 0
2013 12
6 18
31 35
8 0
0 2013
12 6
19 32
31 8
0 0
2013 12
6 20
33 28
10 0
0 2013
12 6
21 33
30 10
22.5 0
2013 12
6 22
31 31
8 22.5
0 2013
12 6
23 31
31 8
0 0
2013 12
6 24
31 30
10 0
0 2013
12 7
1 31
30 10
0 0
2013 12
7 2
29 33
11 0
0 2013
12 7
3 28
37 10
0 0
2013 12
7 4
26 43
6 0
0 2013
12 7
5 24
48 6
0 0
2013 12
7 6
23 51
6 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
30
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
7 7
23 53
7 22.5
0 2013
12 7
8 22
57 7
45 0
2013 12
7 9
22 57
5 45
0 2013
12 7
10 22
59 5
45 0
2013 12
7 11
21 61
6 45
0 2013
12 7
12 21
59 6
45 0
2013 12
7 13
20 63
5 67.5
0 2013
12 7
14 19
63 5
67.5 0
2013 12
7 15
20 61
5 67.5
0 2013
12 7
16 21
59 5
90 0
2013 12
7 17
22 55
5 90
0 2013
12 7
18 32
34 10
67.5 0
2013 12
7 19
31 31
10 45
0 2013
12 7
20 31
31 10
45 0
2013 12
7 21
31 30
11 45
0 2013
12 7
22 31
31 11
22.5 0
2013 12
7 23
23 71
2 45
0 2013
12 7
24 24
64 2
45 0
2013 12
8 1
27 54
3 22.5
0 2013
12 8
2 29
43 6
0 0
2013 12
8 3
31 35
8 0
0 2013
12 8
4 32
31 8
0 0
2013 12
8 5
33 28
10 0
0 2013
12 8
6 33
30 10
22.5 0
2013 12
8 7
33 31
10 0
0 2013
12 8
8 24
62 5
67.5 0
2013 12
8 9
23 61
5 67.5
0 2013
12 8
10 23
64 3
3 0
2013 12
8 11
23 64
3 0
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
31
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
8 12
22 68
3 315
0 2013
12 8
13 21
73 3
315 0
2013 12
8 14
21 73
3 315
0 2013
12 8
15 22
68 3
315 0
2013 12
8 16
25 56
5 0
0 2013
12 8
17 29
43 8
45 0
2013 12
8 18
33 28
10 0
0 2013
12 8
19 33
30 10
22.5 0
2013 12
8 20
33 31
10 0
0 2013
12 8
21 24
62 5
67.5 0
2013 12
8 22
23 61
5 67.5
0 2013
12 8
23 23
64 3
3 0
2013 12
8 24
23 64
3 0
0 2013
12 9
1 22
68 3
315 0
2013 12
9 2
21 73
3 315
0 2013
12 9
3 21
73 3
315 0
2013 12
9 4
22 68
3 315
0 2013
12 9
5 25
56 5
0 0
2013 12
9 6
29 43
8 45
0 2013
12 9
7 32
34 10
67.5 0
2013 12
9 8
33 32
10 67.5
0 2013
12 9
9 33
33 10
67.5 0
2013 12
9 10
29 43
8 45
0 2013
12 9
11 32
34 10
67.5 0
2013 12
9 12
33 32
10 67.5
0 2013
12 9
13 33
33 10
67.5 0
2013 12
9 14
32 34
10 67.5
0 2013
12 9
15 31
31 10
45 0
2013 12
9 16
31 31
10 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
32
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
9 17
31 30
11 45
0 2013
12 9
18 31
31 11
22.5 0
2013 12
9 19
23 71
2 45
0 2013
12 9
20 24
64 2
45 0
2013 12
9 21
27 54
3 22.5
0 2013
12 9
22 29
43 6
0 0
2013 12
9 23
31 35
8 0
0 2013
12 9
24 32
31 8
0 0
2013 12
10 1
33 28
10 0
0 2013
12 10
2 33
30 10
22.5 0
2013 12
10 3
31 31
8 22.5
0 2013
12 10
4 31
31 8
0 0
2013 12
10 5
31 30
10 0
0 2013
12 10
6 31
30 10
0 0
2013 12
10 7
29 33
11 0
0 2013
12 10
8 28
37 10
0 0
2013 12
10 9
26 43
6 0
0 2013
12 10
10 24
48 6
0 0
2013 12
10 11
23 51
6 22.5
0 2013
12 10
12 23
53 7
22.5 0
2013 12
10 13
22 57
7 45
0 2013
12 10
14 22
57 5
45 0
2013 12
10 15
22 59
5 45
0 2013
12 10
16 21
61 6
45 0
2013 12
10 17
21 59
6 45
0 2013
12 10
18 20
63 5
67.5 0
2013 12
10 19
19 63
5 67.5
0 2013
12 10
20 20
61 5
67.5 0
2013 12
10 21
21 59
5 90
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
33
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
10 22
22 55
5 90
0 2013
12 10
23 24
48 6
67.5 0
2013 12
10 24
27 42
8 67.5
0 2013
12 11
1 29
37 8
45 0
2013 12
11 2
26 54
6 45
0 2013
12 11
3 25
58 6
67.5 0
2013 12
11 4
24 60
6 67.5
0 2013
12 11
5 24
62 5
67.5 0
2013 12
11 6
23 61
5 67.5
0 2013
12 11
7 23
64 3
3 0
2013 12
11 8
23 64
3 0
0 2013
12 11
9 22
68 3
315 0
2013 12
11 10
21 73
3 315
0 2013
12 11
11 21
73 3
315 0
2013 12
11 12
22 68
3 315
0 2013
12 11
13 25
56 5
0 0
2013 12
11 14
29 43
8 45
0 2013
12 11
15 33
28 10
0 0
2013 12
11 16
33 30
10 22.5
0 2013
12 11
17 33
31 10
0 0
2013 12
11 18
24 62
5 67.5
0 2013
12 11
19 23
61 5
67.5 0
2013 12
11 20
23 64
3 3
0 2013
12 11
21 23
64 3
0 0
2013 12
11 22
22 68
3 315
0 2013
12 11
23 21
73 3
315 0
2013 12
11 24
21 73
3 315
0 2013
12 12
1 22
68 3
315 0
2013 12
12 2
25 56
5 0
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
34
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
12 3
29 43
8 45
0 2013
12 12
4 32
34 10
67.5 0
2013 12
12 5
33 32
10 67.5
0 2013
12 12
6 33
33 10
67.5 0
2013 12
12 7
29 43
8 45
0 2013
12 12
8 32
34 10
67.5 0
2013 12
12 9
33 32
10 67.5
0 2013
12 12
10 33
33 10
67.5 0
2013 12
12 11
32 34
10 67.5
0 2013
12 12
12 31
31 10
45 0
2013 12
12 13
31 31
10 45
0 2013
12 12
14 31
30 11
45 0
2013 12
12 15
31 31
11 22.5
0 2013
12 12
16 23
71 2
45 0
2013 12
12 17
24 64
2 45
0 2013
12 12
18 27
54 3
22.5 0
2013 12
12 19
29 43
6 0
0 2013
12 12
20 31
35 8
0 0
2013 12
12 21
32 31
8 0
0 2013
12 12
22 33
28 10
0 0
2013 12
12 23
33 30
10 22.5
0 2013
12 12
24 31
31 8
22.5 0
2013 12
13 1
31 31
8 0
0 2013
12 13
2 31
30 10
0 0
2013 12
13 3
31 30
10 0
0 2013
12 13
4 29
33 11
0 0
2013 12
13 5
28 37
10 0
0 2013
12 13
6 26
43 6
0 0
2013 12
13 7
28 34
10 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
35
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
13 8
33 32
10 67.5
0 2013
12 13
9 33
33 10
67.5 0
2013 12
13 10
29 43
8 45
0 2013
12 13
11 32
34 10
67.5 0
2013 12
13 12
33 32
10 67.5
0 2013
12 13
13 33
33 10
67.5 0
2013 12
13 14
32 34
10 67.5
0 2013
12 13
15 31
31 10
45 0
2013 12
13 16
31 31
10 45
0 2013
12 13
17 31
30 11
45 0
2013 12
13 18
31 31
11 22.5
0 2013
12 13
19 23
71 2
45 0
2013 12
13 20
24 64
2 45
0 2013
12 13
21 27
54 3
22.5 0
2013 12
13 22
29 43
6 0
0 2013
12 13
23 31
35 8
0 0
2013 12
13 24
32 31
8 0
0 2013
12 14
1 33
28 10
0 0
2013 12
14 2
33 30
10 22.5
0 2013
12 14
3 31
31 8
22.5 0
2013 12
14 4
31 31
8 0
0 2013
12 14
5 31
30 10
0 0
2013 12
14 6
31 30
10 0
0 2013
12 14
7 29
33 11
0 0
2013 12
14 8
28 37
10 0
0 2013
12 14
9 26
43 6
0 0
2013 12
14 10
24 48
6 0
0 2013
12 14
11 23
51 6
22.5 0
2013 12
14 12
23 53
7 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
36
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
14 13
22 57
7 45
0 2013
12 14
14 22
57 5
45 0
2013 12
14 15
22 59
5 45
0 2013
12 14
16 21
61 6
45 0
2013 12
14 17
21 59
6 45
0 2013
12 14
18 20
63 5
67.5 0
2013 12
14 19
19 63
5 67.5
0 2013
12 14
20 20
61 5
67.5 0
2013 12
14 21
21 59
5 90
0 2013
12 14
22 22
55 5
90 0
2013 12
14 23
24 48
6 67.5
0 2013
12 14
24 27
42 8
67.5 0
2013 12
15 1
29 37
8 45
0 2013
12 15
2 26
54 6
45 0
2013 12
15 3
25 58
6 67.5
0 2013
12 15
4 24
60 6
67.5 0
2013 12
15 5
24 62
5 67.5
0 2013
12 15
6 23
61 5
67.5 0
2013 12
15 7
23 64
3 3
0 2013
12 15
8 23
64 3
0 0
2013 12
15 9
22 68
3 315
0 2013
12 15
10 21
73 3
315 0
2013 12
15 11
21 73
3 315
0 2013
12 15
12 22
68 3
315 0
2013 12
15 13
25 56
5 0
0 2013
12 15
14 29
43 8
45 0
2013 12
15 15
33 28
10 0
0 2013
12 15
16 33
30 10
22.5 0
2013 12
15 17
33 31
10 0
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
37
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
15 18
24 62
5 67.5
0 2013
12 15
19 23
61 5
67.5 0
2013 12
15 20
23 64
3 3
0 2013
12 15
21 23
64 3
0 0
2013 12
15 22
22 68
3 315
0 2013
12 15
23 21
73 3
315 0
2013 12
15 24
21 73
3 315
0 2013
12 16
1 22
68 3
315 0
2013 12
16 2
25 56
5 0
0 2013
12 16
3 29
43 8
45 0
2013 12
16 4
32 34
10 67.5
0 2013
12 16
5 33
32 10
67.5 0
2013 12
16 6
33 33
10 67.5
0 2013
12 16
7 29
43 8
45 0
2013 12
16 8
32 34
10 67.5
0 2013
12 16
9 33
32 10
67.5 0
2013 12
16 10
33 33
10 67.5
0 2013
12 16
11 32
34 10
67.5 0
2013 12
16 12
31 31
10 45
0 2013
12 16
13 31
31 10
45 0
2013 12
16 14
31 30
11 45
0 2013
12 16
15 31
31 11
22.5 0
2013 12
16 16
23 71
2 45
0 2013
12 16
17 24
64 2
45 0
2013 12
16 18
27 54
3 22.5
0 2013
12 16
19 29
43 6
0 0
2013 12
16 20
31 35
8 0
0 2013
12 16
21 32
31 8
0 0
2013 12
16 22
33 28
10 0
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
38
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
16 23
33 30
10 22.5
0 2013
12 16
24 31
31 8
22.5 0
2013 12
17 1
33 28
10 0
0 2013
12 17
2 33
30 10
22.5 0
2013 12
17 3
31 31
8 22.5
0 2013
12 17
4 31
31 8
0 0
2013 12
17 5
31 30
10 0
0 2013
12 17
6 31
30 10
0 0
2013 12
17 7
29 33
11 0
0 2013
12 17
8 28
37 10
0 0
2013 12
17 9
26 43
6 0
0 2013
12 17
10 24
48 6
0 0
2013 12
17 11
23 51
6 22.5
0 2013
12 17
12 23
53 7
22.5 0
2013 12
17 13
22 57
7 45
0 2013
12 17
14 22
57 5
45 0
2013 12
17 15
22 59
5 45
0 2013
12 17
16 21
61 6
45 0
2013 12
17 17
21 59
6 45
0 2013
12 17
18 20
63 5
67.5 0
2013 12
17 19
19 63
5 67.5
0 2013
12 17
20 20
61 5
67.5 0
2013 12
17 21
21 59
5 90
0 2013
12 17
22 22
55 5
90 0
2013 12
17 23
24 48
6 67.5
0 2013
12 17
24 27
42 8
67.5 0
2013 12
18 1
29 37
8 45
0 2013
12 18
2 26
54 6
45 0
2013 12
18 3
25 58
6 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
39
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
18 4
24 60
6 67.5
0 2013
12 18
5 24
62 5
67.5 0
2013 12
18 6
23 61
5 67.5
0 2013
12 18
7 23
64 3
3 0
2013 12
18 8
23 64
3 0
0 2013
12 18
9 22
68 3
315 0
2013 12
18 10
21 73
3 315
0 2013
12 18
11 21
73 3
315 0
2013 12
18 12
22 68
3 315
0 2013
12 18
13 25
56 5
0 0
2013 12
18 14
29 43
8 45
0 2013
12 18
15 33
28 10
0 0
2013 12
18 16
33 30
10 22.5
0 2013
12 18
17 33
31 10
0 0
2013 12
18 18
24 62
5 67.5
0 2013
12 18
19 23
61 5
67.5 0
2013 12
18 20
23 64
3 3
0 2013
12 18
21 23
64 3
0 0
2013 12
18 22
22 68
3 315
0 2013
12 18
23 21
73 3
315 0
2013 12
18 24
21 73
3 315
0 2013
12 19
1 22
68 3
315 0
2013 12
19 2
25 56
5 0
0 2013
12 19
3 29
43 8
45 0
2013 12
19 4
32 34
10 67.5
0 2013
12 19
5 33
32 10
67.5 0
2013 12
19 6
33 33
10 67.5
0 2013
12 19
7 29
43 8
45 0
2013 12
19 8
32 34
10 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
40
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
19 9
33 32
10 67.5
0 2013
12 19
10 33
33 10
67.5 0
2013 12
19 11
32 34
10 67.5
0 2013
12 19
12 31
31 10
45 0
2013 12
19 13
31 31
10 45
0 2013
12 19
14 31
30 11
45 0
2013 12
19 15
31 31
11 22.5
0 2013
12 19
16 23
71 2
45 0
2013 12
19 17
24 64
2 45
0 2013
12 19
18 27
54 3
22.5 0
2013 12
19 19
29 43
6 0
0 2013
12 19
20 31
35 8
0 0
2013 12
19 21
32 31
8 0
0 2013
12 19
22 33
28 10
0 0
2013 12
19 23
33 30
10 22.5
0 2013
12 19
24 31
31 8
22.5 0
2013 12
20 1
33 28
10 0
0 2013
12 20
2 33
30 10
22.5 0
2013 12
20 3
31 31
8 22.5
0 2013
12 20
4 31
31 8
0 0
2013 12
20 5
31 30
10 0
0 2013
12 20
6 31
30 10
0 0
2013 12
20 7
29 33
11 0
0 2013
12 20
8 28
37 10
0 0
2013 12
20 9
26 43
6 0
0 2013
12 20
10 24
48 6
0 0
2013 12
20 11
23 51
6 22.5
0 2013
12 20
12 23
53 7
22.5 0
2013 12
20 13
22 57
7 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
41
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
20 14
22 57
5 45
0 2013
12 20
15 22
59 5
45 0
2013 12
20 16
21 61
6 45
0 2013
12 20
17 21
59 6
45 0
2013 12
20 18
20 63
5 67.5
0 2013
12 20
19 19
63 5
67.5 0
2013 12
20 20
20 61
5 67.5
0 2013
12 20
21 21
59 5
90 0
2013 12
20 22
22 55
5 90
0 2013
12 20
23 24
48 6
67.5 0
2013 12
20 24
27 42
8 67.5
0 2013
12 21
1 29
37 8
45 0
2013 12
21 2
26 54
6 45
0 2013
12 21
3 25
58 6
67.5 0
2013 12
21 4
24 60
6 67.5
0 2013
12 21
5 24
62 5
67.5 0
2013 12
21 6
23 61
5 67.5
0 2013
12 21
7 23
64 3
3 0
2013 12
21 8
23 64
3 0
0 2013
12 21
9 22
68 3
315 0
2013 12
21 10
21 73
3 315
0 2013
12 21
11 21
73 3
315 0
2013 12
21 12
22 68
3 315
0 2013
12 21
13 25
56 5
0 0
2013 12
21 14
29 43
8 45
0 2013
12 21
15 33
28 10
0 0
2013 12
21 16
33 30
10 22.5
0 2013
12 21
17 33
31 10
0 0
2013 12
21 18
24 62
5 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
42
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
21 19
23 61
5 67.5
0 2013
12 21
20 23
64 3
3 0
2013 12
21 21
23 64
3 0
0 2013
12 21
22 22
68 3
315 0
2013 12
21 23
21 73
3 315
0 2013
12 21
24 21
73 3
315 0
2013 12
22 1
22 68
3 315
0 2013
12 22
2 25
56 5
0 0
2013 12
22 3
29 43
8 45
0 2013
12 22
4 32
34 10
67.5 0
2013 12
22 5
33 32
10 67.5
0 2013
12 22
6 33
33 10
67.5 0
2013 12
22 7
29 43
8 45
0 2013
12 22
8 32
34 10
67.5 0
2013 12
22 9
33 32
10 67.5
0 2013
12 22
10 33
33 10
67.5 0
2013 12
22 11
32 34
10 67.5
0 2013
12 22
12 31
31 10
45 0
2013 12
22 13
31 31
10 45
0 2013
12 22
14 31
30 11
45 0
2013 12
22 15
31 31
11 22.5
0 2013
12 22
16 23
71 2
45 0
2013 12
22 17
24 64
2 45
0 2013
12 22
18 27
54 3
22.5 0
2013 12
22 19
29 43
6 0
0 2013
12 22
20 31
35 8
0 0
2013 12
22 21
32 31
8 0
0 2013
12 22
22 33
28 10
0 0
2013 12
22 23
33 30
10 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
43
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
22 24
31 31
8 22.5
0 2013
12 23
1 33
28 10
0 0
2013 12
23 2
33 30
10 22.5
0 2013
12 23
3 31
31 8
22.5 0
2013 12
23 4
31 31
8 0
0 2013
12 23
5 31
30 10
0 0
2013 12
23 6
31 30
10 0
0 2013
12 23
7 29
33 11
0 0
2013 12
23 8
28 37
10 0
0 2013
12 23
9 26
43 6
0 0
2013 12
23 10
24 48
6 0
0 2013
12 23
11 23
51 6
22.5 0
2013 12
23 12
23 53
7 22.5
0 2013
12 23
13 22
57 7
45 0
2013 12
23 14
22 57
5 45
0 2013
12 23
15 22
59 5
45 0
2013 12
23 16
21 61
6 45
0 2013
12 23
17 21
59 6
45 0
2013 12
23 18
20 63
5 67.5
0 2013
12 23
19 19
63 5
67.5 0
2013 12
23 20
20 61
5 67.5
0 2013
12 23
21 21
59 5
90 0
2013 12
23 22
22 55
5 90
0 2013
12 23
23 24
48 6
67.5 0
2013 12
23 24
27 42
8 67.5
0 2013
12 24
1 29
37 8
45 0
2013 12
24 2
26 54
6 45
0 2013
12 24
3 25
58 6
67.5 0
2013 12
24 4
24 60
6 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
44
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
24 5
24 62
5 67.5
0 2013
12 24
6 23
61 5
67.5 0
2013 12
24 7
23 64
3 3
0 2013
12 24
8 23
64 3
0 0
2013 12
24 9
22 68
3 315
0 2013
12 24
10 21
73 3
315 0
2013 12
24 11
21 73
3 315
0 2013
12 24
12 22
68 3
315 0
2013 12
24 13
25 56
5 0
0 2013
12 24
14 29
43 8
45 0
2013 12
24 15
33 28
10 0
0 2013
12 24
16 33
30 10
22.5 0
2013 12
24 17
33 31
10 0
0 2013
12 24
18 24
62 5
67.5 0
2013 12
24 19
23 61
5 67.5
0 2013
12 24
20 23
64 3
3 0
2013 12
24 21
23 64
3 0
0 2013
12 24
22 22
68 3
315 0
2013 12
24 23
21 73
3 315
0 2013
12 24
24 21
73 3
315 0
2013 12
25 1
22 68
3 315
0 2013
12 25
2 25
56 5
0 0
2013 12
25 3
29 43
8 45
0 2013
12 25
4 32
34 10
67.5 0
2013 12
25 5
33 32
10 67.5
0 2013
12 25
6 33
33 10
67.5 0
2013 12
25 7
29 43
8 45
0 2013
12 25
8 32
34 10
67.5 0
2013 12
25 9
33 32
10 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
45
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
25 10
33 33
10 67.5
0 2013
12 25
11 32
34 10
67.5 0
2013 12
25 12
31 31
10 45
0 2013
12 25
13 31
31 10
45 0
2013 12
25 14
31 30
11 45
0 2013
12 25
15 31
31 11
22.5 0
2013 12
25 16
23 71
2 45
0 2013
12 25
17 24
64 2
45 0
2013 12
25 18
27 54
3 22.5
0 2013
12 25
19 29
43 6
0 0
2013 12
25 20
31 35
8 0
0 2013
12 25
21 32
31 8
0 0
2013 12
25 22
33 28
10 0
0 2013
12 25
23 33
30 10
22.5 0
2013 12
25 24
31 31
8 22.5
0 2013
12 26
1 33
28 10
0 0
2013 12
26 2
33 30
10 22.5
0 2013
12 26
3 31
31 8
22.5 0
2013 12
26 4
31 31
8 0
0 2013
12 26
5 31
30 10
0 0
2013 12
26 6
31 30
10 0
0 2013
12 26
7 29
33 11
0 0
2013 12
26 8
28 37
10 0
0 2013
12 26
9 26
43 6
0 0
2013 12
26 10
24 48
6 0
0 2013
12 26
11 23
51 6
22.5 0
2013 12
26 12
23 53
7 22.5
0 2013
12 26
13 22
57 7
45 0
2013 12
26 14
22 57
5 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
46
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
26 15
22 59
5 45
0 2013
12 26
16 21
61 6
45 0
2013 12
26 17
21 59
6 45
0 2013
12 26
18 20
63 5
67.5 0
2013 12
26 19
19 63
5 67.5
0 2013
12 26
20 20
61 5
67.5 0
2013 12
26 21
21 59
5 90
0 2013
12 26
22 22
55 5
90 0
2013 12
26 23
24 48
6 67.5
0 2013
12 26
24 27
42 8
67.5 0
2013 12
27 1
29 37
8 45
0 2013
12 27
2 26
54 6
45 0
2013 12
27 3
25 58
6 67.5
0 2013
12 27
4 24
60 6
67.5 0
2013 12
27 5
24 62
5 67.5
0 2013
12 27
6 23
61 5
67.5 0
2013 12
27 7
23 64
3 3
0 2013
12 27
8 23
64 3
0 0
2013 12
27 9
22 68
3 315
0 2013
12 27
10 21
73 3
315 0
2013 12
27 11
21 73
3 315
0 2013
12 27
12 22
68 3
315 0
2013 12
27 13
25 56
5 0
0 2013
12 27
14 29
43 8
45 0
2013 12
27 15
33 28
10 0
0 2013
12 27
16 33
30 10
22.5 0
2013 12
27 17
33 31
10 0
0 2013
12 27
18 24
62 5
67.5 0
2013 12
27 19
23 61
5 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
47
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
27 20
23 64
3 3
0 2013
12 27
21 23
64 3
0 0
2013 12
27 22
22 68
3 315
0 2013
12 27
23 21
73 3
315 0
2013 12
27 24
21 73
3 315
0 2013
12 28
1 22
68 3
315 0
2013 12
28 2
25 56
5 0
0 2013
12 28
3 29
43 8
45 0
2013 12
28 4
32 34
10 67.5
0 2013
12 28
5 33
32 10
67.5 0
2013 12
28 6
33 33
10 67.5
0 2013
12 28
7 29
43 8
45 0
2013 12
28 8
32 34
10 67.5
0 2013
12 28
9 33
32 10
67.5 0
2013 12
28 10
33 33
10 67.5
0 2013
12 28
11 32
34 10
67.5 0
2013 12
28 12
31 31
10 45
0 2013
12 28
13 31
31 10
45 0
2013 12
28 14
31 30
11 45
0 2013
12 28
15 31
31 11
22.5 0
2013 12
28 16
23 71
2 45
0 2013
12 28
17 24
64 2
45 0
2013 12
28 18
27 54
3 22.5
0 2013
12 28
19 29
43 6
0 0
2013 12
28 20
31 35
8 0
0 2013
12 28
21 32
31 8
0 0
2013 12
28 22
33 28
10 0
0 2013
12 28
23 33
30 10
22.5 0
2013 12
28 24
31 31
8 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
48
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
29 1
33 28
10 0
0 2013
12 29
2 33
30 10
22.5 0
2013 12
29 3
31 31
8 22.5
0 2013
12 29
4 31
31 8
0 0
2013 12
29 5
31 30
10 0
0 2013
12 29
6 31
30 10
0 0
2013 12
29 7
29 33
11 0
0 2013
12 29
8 28
37 10
0 0
2013 12
29 9
26 43
6 0
0 2013
12 29
10 24
48 6
0 0
2013 12
29 11
23 51
6 22.5
0 2013
12 29
12 23
53 7
22.5 0
2013 12
29 13
22 57
7 45
0 2013
12 29
14 22
57 5
45 0
2013 12
29 15
22 59
5 45
0 2013
12 29
16 21
61 6
45 0
2013 12
29 17
21 59
6 45
0 2013
12 29
18 20
63 5
67.5 0
2013 12
29 19
19 63
5 67.5
0 2013
12 29
20 20
61 5
67.5 0
2013 12
29 21
21 59
5 90
0 2013
12 29
22 22
55 5
90 0
2013 12
29 23
24 48
6 67.5
0 2013
12 29
24 27
42 8
67.5 0
2013 12
30 1
29 37
8 45
0 2013
12 30
2 26
54 6
45 0
2013 12
30 3
25 58
6 67.5
0 2013
12 30
4 24
60 6
67.5 0
2013 12
30 5
24 62
5 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
49
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
30 6
23 61
5 67.5
0 2013
12 30
7 23
64 3
3 0
2013 12
30 8
23 64
3 0
0 2013
12 30
9 22
68 3
315 0
2013 12
30 10
21 73
3 315
0 2013
12 30
11 21
73 3
315 0
2013 12
30 12
22 68
3 315
0 2013
12 30
13 25
56 5
0 0
2013 12
30 14
29 43
8 45
0 2013
12 30
15 33
28 10
0 0
2013 12
30 16
33 30
10 22.5
0 2013
12 30
17 33
31 10
0 0
2013 12
30 18
24 62
5 67.5
0 2013
12 30
19 23
61 5
67.5 0
2013 12
30 20
23 64
3 3
0 2013
12 30
21 23
64 3
0 0
2013 12
30 22
22 68
3 315
0 2013
12 30
23 21
73 3
315 0
2013 12
30 24
21 73
3 315
0 2013
12 31
1 22
68 3
315 0
2013 12
31 2
25 56
5 0
0 2013
12 31
3 29
43 8
45 0
2013 12
31 4
32 34
10 67.5
0 2013
12 31
5 33
32 10
67.5 0
2013 12
31 6
33 33
10 67.5
0 2013
12 31
7 29
43 8
45 0
2013 12
31 8
32 34
10 67.5
0 2013
12 31
9 33
32 10
67.5 0
2013 12
31 10
33 33
10 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
50
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2013 12
31 11
32 34
10 67.5
0 2013
12 31
12 31
31 10
45 0
2013 12
31 13
31 31
10 45
0 2013
12 31
14 31
30 11
45 0
2013 12
31 15
31 31
11 22.5
0 2013
12 31
16 23
71 2
45 0
2013 12
31 17
24 64
2 45
0 2013
12 31
18 27
54 3
22.5 0
2013 12
31 19
29 43
6 0
0 2013
12 31
20 31
35 8
0 0
2013 12
31 21
32 31
8 0
0 2013
12 31
22 33
28 10
0 0
2013 12
31 23
33 30
10 22.5
0 2013
12 31
24 31
31 8
45 0
2014 1
1 1
20 70
8 45
0 2014
1 1
2 19
68 8
67.5 0
2014 1
1 3
18 67
8 90
0 2014
1 1
4 17
67 6
90 0
2014 1
1 5
15 67
6 90
0 2014
1 1
6 16
65 6
112.5 0
2014 1
1 7
16 63
6 112.5
0 2014
1 1
8 17
60 6
90 0
2014 1
1 9
18 58
6 67.5
0 2014
1 1
10 20
52 6
67.5 0
2014 1
1 11
21 28
13 67.5
0 2014
1 1
12 22
25 13
67.5 0
2014 1
1 13
22 27
13 67.5
0 2014
1 1
14 21
28 13
67.5 0
2014 1
1 15
21 30
12 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
51
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
1 16
20 33
12 45
0 2014
1 1
17 20
34 10
45 0
2014 1
1 18
19 35
10 22.5
0 2014
1 1
19 19
36 10
22.5 0
2014 1
1 20
17 41
10 22.5
0 2014
1 1
21 16
46 10
22.5 0
2014 1
1 22
15 46
8 45
0 2014
1 1
23 14
45 8
45 0
2014 1
1 24
14 45
8 45
0 2014
1 2
1 14
59 5
67.5 0
2014 1
2 2
13 57
5 67.5
0 2014
1 2
3 13
57 5
90 0
2014 1
2 4
13 62
5 90
0 2014
1 2
5 12
66 5
90 0
2014 1
2 6
11 74
5 112.5
0 2014
1 2
7 11
77 5
112.5 0
2014 1
2 8
12 66
5 90
0 2014
1 2
9 15
51 8
67.5 0
2014 1
2 10
19 70
11 67.5
0 2014
1 2
11 22
61 13
67.5 0
2014 1
2 12
24 53
13 67.5
0 2014
1 2
13 26
50 13
45 0
2014 1
2 14
27 45
13 45
0 2014
1 2
15 27
45 13
22.5 0
2014 1
2 16
26 50
13 22.5
0 2014
1 2
17 26
52 13
45 0
2014 1
2 18
24 57
13 22.5
0 2014
1 2
19 22
63 11
22.5 0
2014 1
2 20
20 73
11 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
52
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
2 21
19 78
10 22.5
0 2014
1 2
22 18
81 10
22.5 0
2014 1
2 23
17 81
8 45
0 2014
1 2
24 17
81 8
45 0
2014 1
3 1
16 78
8 45
0 2014
1 3
2 16
72 8
45 0
2014 1
3 3
16 75
8 45
0 2014
1 3
4 15
78 6
45 0
2014 1
3 5
14 77
6 67.5
0 2014
1 3
6 14
75 6
45 0
2014 1
3 7
14 72
6 45
0 2014
1 3
8 16
67 6
45 0
2014 1
3 9
18 63
6 45
0 2014
1 3
10 21
61 6
67.5 0
2014 1
3 11
23 55
6 67.5
0 2014
1 3
12 25
52 8
45 0
2014 1
3 13
27 45
10 22.5
0 2014
1 3
14 27
44 11
0 0
2014 1
3 15
28 42
13 337.5
0 2014
1 3
16 27
45 13
337.5 0
2014 1
3 17
26 50
13 337.5
0 2014
1 3
18 24
53 13
337.5 0
2014 1
3 19
22 59
11 0
0 2014
1 3
20 20
68 11
0 0
2014 1
3 21
19 73
10 0
0 2014
1 3
22 18
78 8
0 0
2014 1
3 23
17 78
6 337.5
0 2014
1 3
24 17
75 6
337.5 0
2014 1
4 1
16 72
6 315
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
53
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
4 2
16 69
6 292.5
0 2014
1 4
3 15
67 6
270 0
2014 1
4 4
14 67
5 270
0 2014
1 4
5 14
67 5
270 0
2014 1
4 6
13 67
5 292.5
0 2014
1 4
7 13
64 5
292.5 0
2014 1
4 8
14 62
5 315
0 2014
1 4
9 17
58 6
337.5 0
2014 1
4 10
19 52
8 22.5
0 2014
1 4
11 22
46 10
45 0
2014 1
4 12
24 40
11 22.5
0 2014
1 4
13 25
36 13
0 0
2014 1
4 14
26 31
13 337.5
0 2014
1 4
15 26
33 10
337.5 0
2014 1
4 16
26 32
10 337.5
0 2014
1 4
17 25
34 10
337.5 0
2014 1
4 18
24 35
8 337.5
0 2014
1 4
19 20
36 8
315 0
2014 1
4 20
18 41
8 315
0 2014
1 4
21 16
48 6
315 0
2014 1
4 22
16 53
6 315
0 2014
1 4
23 14
62 5
292.5 0
2014 1
4 24
14 62
5 270
0 2014
1 5
1 14
64 5
225 0
2014 1
5 2
13 67
3 247.5
0 2014
1 5
3 13
74 3
202.5 0
2014 1
5 4
13 80
3 202.5
0 2014
1 5
5 12
90 3
225 0
2014 1
5 6
12 96
3 247.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
54
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
5 7
12 96
3 247.5
0 2014
1 5
8 13
90 2
270 0
2014 1
5 9
16 75
2 292.5
0 2014
1 5
10 18
60 6
337.5 0
2014 1
5 11
21 49
8 22.5
0 2014
1 5
12 23
40 10
22.5 0
2014 1
5 13
24 34
11 22.5
0 2014
1 5
14 25
31 13
0 0
2014 1
5 15
26 30
11 0
0 2014
1 5
16 25
32 11
0 0
2014 1
5 17
24 34
11 0
0 2014
1 5
18 22
39 10
0 0
2014 1
5 19
20 45
8 22.5
0 2014
1 5
20 18
54 8
22.5 0
2014 1
5 21
17 60
6 45
0 2014
1 5
22 16
67 6
67.5 0
2014 1
5 23
15 67
5 67.5
0 2014
1 5
24 14
64 5
67.5 0
2014 1
6 1
14 59
5 67.5
0 2014
1 6
2 13
57 5
67.5 0
2014 1
6 3
13 57
5 90
0 2014
1 6
4 13
62 5
90 0
2014 1
6 5
12 66
5 90
0 2014
1 6
6 11
74 5
112.5 0
2014 1
6 7
11 77
5 112.5
0 2014
1 6
8 12
66 5
90 0
2014 1
6 9
15 51
8 67.5
0 2014
1 6
10 18
37 11
67.5 0
2014 1
6 11
21 28
13 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
55
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
6 12
22 25
13 67.5
0 2014
1 6
13 22
27 13
67.5 0
2014 1
6 14
21 28
13 67.5
0 2014
1 6
15 21
30 12
45 0
2014 1
6 16
20 33
12 45
0 2014
1 6
17 20
34 10
45 0
2014 1
6 18
19 35
10 22.5
0 2014
1 6
19 19
36 10
22.5 0
2014 1
6 20
17 41
10 22.5
0 2014
1 6
21 16
46 10
22.5 0
2014 1
6 22
15 46
8 45
0 2014
1 6
23 14
45 8
45 0
2014 1
6 24
14 45
8 45
0 2014
1 7
1 13
43 8
45 0
2014 1
7 2
13 43
8 67.5
0 2014
1 7
3 13
43 6
67.5 0
2014 1
7 4
12 47
6 67.5
0 2014
1 7
5 12
50 6
67.5 0
2014 1
7 6
11 52
6 90
0 2014
1 7
7 11
54 6
90 0
2014 1
7 8
12 55
6 90
0 2014
1 7
9 15
53 10
90 0
2014 1
7 10
18 50
11 90
0 2014
1 7
11 22
42 13
90 0
2014 1
7 12
24 37
13 90
0 2014
1 7
13 26
32 13
90 0
2014 1
7 14
27 30
11 90
0 2014
1 7
15 27
29 10
90 0
2014 1
7 16
27 31
10 90
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
56
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
7 17
26 35
8 67.5
0 2014
1 7
18 24
40 8
67.5 0
2014 1
7 19
22 46
8 67.5
0 2014
1 7
20 19
50 8
67.5 0
2014 1
7 21
18 50
8 67.5
0 2014
1 7
22 17
62 8
90 0
2014 1
7 23
16 67
8 90
0 2014
1 7
24 16
69 6
90 0
2014 1
8 1
16 69
6 90
0 2014
1 8
2 15
69 6
90 0
2014 1
8 3
14 75
6 90
0 2014
1 8
4 14
80 5
112.5 0
2014 1
8 5
13 86
5 112.5
0 2014
1 8
6 13
83 5
112.5 0
2014 1
8 7
13 83
5 112.5
0 2014
1 8
8 14
77 5
112.5 0
2014 1
8 9
17 70
5 112.5
0 2014
1 8
10 20
61 5
112.5 0
2014 1
8 11
23 51
5 90
0 2014
1 8
12 26
42 6
67.5 0
2014 1
8 13
27 36
8 45
0 2014
1 8
14 28
32 11
45 0
2014 1
8 15
28 30
12 22.5
0 2014
1 8
16 28
28 13
22.5 0
2014 1
8 17
27 31
13 0
0 2014
1 8
18 24
37 11
0 0
2014 1
8 19
22 44
10 337.5
0 2014
1 8
20 19
54 8
292.5 0
2014 1
8 21
17 67
8 315
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
57
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
8 22
16 81
8 315
0 2014
1 8
23 16
84 8
315 0
2014 1
8 24
15 83
6 337.5
0 2014
1 9
1 15
75 6
0 0
2014 1
9 2
14 72
5 22.5
0 2014
1 9
3 14
77 5
22.5 0
2014 1
9 4
13 90
5 22.5
0 2014
1 9
5 13
96 5
22.5 0
2014 1
9 6
13 93
5 0
0 2014
1 9
7 13
83 5
0 0
2014 1
9 8
13 72
5 0
0 2014
1 9
9 16
58 8
0 0
2014 1
9 10
18 46
11 22.5
0 2014
1 9
11 21
39 14
22.5 0
2014 1
9 12
23 35
14 0
0 2014
1 9
13 24
34 14
0 0
2014 1
9 14
25 33
16 0
0 2014
1 9
15 25
33 16
0 0
2014 1
9 16
25 33
14 0
0 2014
1 9
17 24
36 14
0 0
2014 1
9 18
22 41
13 0
0 2014
1 9
19 19
49 11
0 0
2014 1
9 20
17 58
10 0
0 2014
1 9
21 16
65 10
0 0
2014 1
9 22
15 69
10 0
0 2014
1 9
23 14
69 10
0 0
2014 1
9 24
14 69
8 0
0 2014
1 10
1 13
72 8
22.5 0
2014 1
10 2
13 72
6 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
58
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
10 3
12 74
6 22.5
0 2014
1 10
4 12
77 6
22.5 0
2014 1
10 5
11 83
6 22.5
0 2014
1 10
6 10
86 6
22.5 0
2014 1
10 7
10 86
6 22.5
0 2014
1 10
8 11
80 6
22.5 0
2014 1
10 9
13 67
8 22.5
0 2014
1 10
10 16
57 11
22.5 0
2014 1
10 11
19 40
13 22.5
0 2014
1 10
12 21
34 14
22.5 0
2014 1
10 13
23 28
14 22.5
0 2014
1 10
14 23
26 16
0 0
2014 1
10 15
26 30
11 0
0 2014
1 10
16 25
32 11
0 0
2014 1
10 17
24 34
11 0
0 2014
1 10
18 22
39 10
0 0
2014 1
10 19
20 45
8 22.5
0 2014
1 10
20 18
54 8
22.5 0
2014 1
10 21
17 60
6 45
0 2014
1 10
22 16
67 6
67.5 0
2014 1
10 23
15 67
5 67.5
0 2014
1 10
24 14
64 5
67.5 0
2014 1
11 1
14 59
5 67.5
0 2014
1 11
2 13
57 5
67.5 0
2014 1
11 3
13 57
5 90
0 2014
1 11
4 13
62 5
90 0
2014 1
11 5
12 66
5 90
0 2014
1 11
6 11
74 5
112.5 0
2014 1
11 7
11 77
5 112.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
59
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
11 8
12 66
5 90
0 2014
1 11
9 15
51 8
67.5 0
2014 1
11 10
18 37
11 67.5
0 2014
1 11
11 21
28 13
67.5 0
2014 1
11 12
22 25
13 67.5
0 2014
1 11
13 22
27 13
67.5 0
2014 1
11 14
21 28
13 67.5
0 2014
1 11
15 21
30 12
45 0
2014 1
11 16
20 33
12 45
0 2014
1 11
17 20
34 10
45 0
2014 1
11 18
19 35
10 22.5
0 2014
1 11
19 19
36 10
22.5 0
2014 1
11 20
17 41
10 22.5
0 2014
1 11
21 16
64 11
45 0
2014 1
11 22
15 67
11 45
0 2014
1 11
23 14
69 11
45 0
2014 1
11 24
14 69
11 45
0 2014
1 12
1 12
69 10
45 0
2014 1
12 2
11 69
10 45
0 2014
1 12
3 11
71 10
67.5 0
2014 1
12 4
11 74
10 67.5
0 2014
1 12
5 10
74 10
67.5 0
2014 1
12 6
10 77
10 90
0 2014
1 12
7 11
71 10
90 0
2014 1
12 8
14 64
11 67.5
0 2014
1 12
9 17
57 13
67.5 0
2014 1
12 10
20 50
16 67.5
0 2014
1 12
11 20
43 19
67.5 0
2014 1
12 12
22 39
18 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
60
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
12 13
24 34
16 67.5
0 2014
1 12
14 24
32 16
67.5 0
2014 1
12 15
25 30
16 45
0 2014
1 12
16 25
30 14
22.5 0
2014 1
12 17
24 32
14 22.5
0 2014
1 12
18 22
36 14
0 0
2014 1
12 19
19 45
14 22.5
0 2014
1 12
20 17
52 13
22.5 0
2014 1
12 21
16 52
13 45
0 2014
1 12
22 15
58 11
45 0
2014 1
12 23
14 64
10 45
0 2014
1 12
24 14
67 10
45 0
2014 1
13 1
13 69
8 67.5
0 2014
1 13
2 13
69 6
67.5 0
2014 1
13 3
12 69
8 67.5
0 2014
1 13
4 12
64 8
90 0
2014 1
13 5
11 66
8 90
0 2014
1 13
6 11
66 8
90 0
2014 1
13 7
10 66
8 90
0 2014
1 13
8 11
66 8
90 0
2014 1
13 9
14 57
10 90
0 2014
1 13
10 18
48 11
67.5 0
2014 1
13 11
21 44
13 67.5
0 2014
1 13
12 22
44 13
67.5 0
2014 1
13 13
21 44
13 67.5
0 2014
1 13
14 21
44 13
67.5 0
2014 1
13 15
21 45
12 67.5
0 2014
1 13
16 20
45 12
0 0
2014 1
13 17
20 46
12 0
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
61
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
13 18
20 47
11 0
0 2014
1 13
19 20
47 11
0 0
2014 1
13 20
19 52
10 0
0 2014
1 13
21 17
56 10
22.5 0
2014 1
13 22
17 58
8 22.5
0 2014
1 13
23 16
60 8
22.5 0
2014 1
13 24
16 58
6 22.5
0 2014
1 14
1 15
57 6
0 0
2014 1
14 2
14 57
5 0
0 2014
1 14
3 14
59 5
0 0
2014 1
14 4
13 64
5 0
0 2014
1 14
5 13
66 6
0 0
2014 1
14 6
13 66
8 0
0 2014
1 14
7 13
62 10
0 0
2014 1
14 8
14 60
10 0
0 2014
1 14
9 16
52 10
0 0
2014 1
14 10
19 47
11 22.5
0 2014
1 14
11 22
47 11
22.5 0
2014 1
14 12
24 41
11 22.5
0 2014
1 14
13 26
39 14
0 0
2014 1
14 14
27 34
14 337.5
0 2014
1 14
15 27
34 14
337.5 0
2014 1
14 16
27 34
11 337.5
0 2014
1 14
17 26
35 10
337.5 0
2014 1
14 18
23 35
10 337.5
0 2014
1 14
19 21
37 8
337.5 0
2014 1
14 20
19 41
8 337.5
0 2014
1 14
21 17
45 8
315 0
2014 1
14 22
16 52
8 315
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
62
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
14 23
16 53
8 337.5
0 2014
1 14
24 15
69 8
337.5 0
2014 1
15 1
13 72
5 22.5
0 2014
1 15
2 13
73 5
22.5 0
2014 1
15 3
12 74
5 22.5
0 2014
1 15
4 12
77 5
22.5 0
2014 1
15 5
11 83
5 22.5
0 2014
1 15
6 10
86 5
22.5 0
2014 1
15 7
10 86
5 22.5
0 2014
1 15
8 11
80 5
45 0
2014 1
15 9
13 67
8 45
0 2014
1 15
10 16
57 11
45 0
2014 1
15 11
19 40
13 45
0 2014
1 15
12 21
34 13
67.5 0
2014 1
15 13
23 28
13 67.5
0 2014
1 15
14 23
26 13
45 0
2014 1
15 15
26 30
12 45
0 2014
1 15
16 25
32 12
67.5 0
2014 1
15 17
24 34
10 67.5
0 2014
1 15
18 22
39 10
67.5 0
2014 1
15 19
20 45
10 67.5
0 2014
1 15
20 18
54 10
67.5 0
2014 1
15 21
17 60
11 90
0 2014
1 15
22 16
67 11
90 0
2014 1
15 23
15 67
11 90
0 2014
1 15
24 14
64 10
67.5 0
2014 1
16 1
14 59
6 22.5
0 2014
1 16
2 13
57 5
22.5 0
2014 1
16 3
13 57
5 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
63
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
16 4
13 62
5 67.5
0 2014
1 16
5 12
66 5
67.5 0
2014 1
16 6
11 74
5 67.5
0 2014
1 16
7 11
77 5
67.5 0
2014 1
16 8
12 66
5 67.5
0 2014
1 16
9 15
51 8
45 0
2014 1
16 10
18 37
11 45
0 2014
1 16
11 21
28 14
22.5 0
2014 1
16 12
22 25
14 22.5
0 2014
1 16
13 22
32 14
0 0
2014 1
16 14
21 34
16 0
0 2014
1 16
15 21
39 16
45 0
2014 1
16 16
20 45
14 45
0 2014
1 16
17 20
48 14
45 0
2014 1
16 18
19 49
13 22.5
0 2014
1 16
19 19
53 11
22.5 0
2014 1
16 20
19 61
10 22.5
0 2014
1 16
21 17
70 8
22.5 0
2014 1
16 22
16 75
8 45
0 2014
1 16
23 16
75 8
45 0
2014 1
16 24
15 75
6 45
0 2014
1 17
1 14
75 5
45 0
2014 1
17 2
14 72
5 45
0 2014
1 17
3 13
74 5
45 0
2014 1
17 4
13 74
5 45
0 2014
1 17
5 13
77 6
45 0
2014 1
17 6
13 80
6 67.5
0 2014
1 17
7 12
77 5
90 0
2014 1
17 8
13 72
3 90
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
64
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
17 9
16 64
5 67.5
0 2014
1 17
10 18
56 6
45 0
2014 1
17 11
22 46
8 22.5
0 2014
1 17
12 23
38 10
0 0
2014 1
17 13
24 32
13 337.5
0 2014
1 17
14 25
27 14
337.5 0
2014 1
17 15
26 25
14 315
0 2014
1 17
16 25
24 14
315 0
2014 1
17 17
24 26
16 315
0 2014
1 17
18 22
29 13
337.5 0
2014 1
17 19
19 34
11 337.5
0 2014
1 17
20 18
40 8
337.5 0
2014 1
17 21
16 48
8 337.5
0 2014
1 17
22 16
53 6
315 0
2014 1
17 23
14 60
5 315
0 2014
1 17
24 14
64 5
315 0
2014 1
18 1
13 67
6 315
0 2014
1 18
2 13
69 6
337.5 0
2014 1
18 3
13 72
6 0
0 2014
1 18
4 12
77 8
45 0
2014 1
18 5
12 79
8 67.5
0 2014
1 18
6 11
80 8
67.5 0
2014 1
18 7
11 80
8 67.5
0 2014
1 18
8 12
69 5
45 0
2014 1
18 9
14 60
8 45
0 2014
1 18
10 18
50 13
45 0
2014 1
18 11
21 42
16 45
0 2014
1 18
12 23
35 16
45 0
2014 1
18 13
24 31
18 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
65
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
18 14
25 27
18 45
0 2014
1 18
15 21
30 12
45 0
2014 1
18 16
20 33
12 45
0 2014
1 18
17 20
34 10
45 0
2014 1
18 18
19 35
10 22.5
0 2014
1 18
19 19
36 10
22.5 0
2014 1
18 20
17 41
10 22.5
0 2014
1 18
21 16
46 10
22.5 0
2014 1
18 22
15 46
8 45
0 2014
1 18
23 14
45 8
45 0
2014 1
18 24
14 45
8 45
0 2014
1 19
1 13
43 8
45 0
2014 1
19 2
13 43
8 67.5
0 2014
1 19
3 13
43 6
67.5 0
2014 1
19 4
12 47
6 67.5
0 2014
1 19
5 12
50 6
67.5 0
2014 1
19 6
11 52
6 90
0 2014
1 19
7 11
54 6
90 0
2014 1
19 8
12 55
6 90
0 2014
1 19
9 15
53 10
90 0
2014 1
19 10
18 50
11 90
0 2014
1 19
11 20
42 13
90 0
2014 1
19 12
23 37
19 90
0 2014
1 19
13 25
30 21
67.5 0
2014 1
19 14
26 27
21 67.5
0 2014
1 19
15 26
26 19
67.5 0
2014 1
19 16
26 26
18 67.5
0 2014
1 19
17 25
29 18
67.5 0
2014 1
19 18
23 34
14 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
66
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
19 19
21 40
13 45
0 2014
1 19
20 18
48 11
45 0
2014 1
19 21
17 54
11 45
0 2014
1 19
22 16
62 10
67.5 0
2014 1
19 23
16 64
10 67.5
0 2014
1 19
24 15
64 10
67.5 0
2014 1
20 1
14 64
8 67.5
0 2014
1 20
2 14
64 8
67.5 0
2014 1
20 3
14 67
8 67.5
0 2014
1 20
4 13
72 8
67.5 0
2014 1
20 5
13 77
10 90
0 2014
1 20
6 12
77 10
67.5 0
2014 1
20 7
12 74
8 67.5
0 2014
1 20
8 13
69 8
67.5 0
2014 1
20 9
16 64
8 67.5
0 2014
1 20
10 19
58 8
90 0
2014 1
20 11
22 53
10 67.5
0 2014
1 20
12 24
50 10
67.5 0
2014 1
20 13
26 43
8 90
0 2014
1 20
14 27
40 8
112.5 0
2014 1
20 15
27 38
8 112.5
0 2014
1 20
16 27
38 8
67.5 0
2014 1
20 17
26 40
8 67.5
0 2014
1 20
18 24
45 6
22.5 0
2014 1
20 19
22 51
5 0
0 2014
1 20
20 21
59 5
337.5 0
2014 1
20 21
19 65
5 315
0 2014
1 20
22 18
73 5
315 0
2014 1
20 23
18 75
5 292.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
67
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
20 24
17 75
5 292.5
0 2014
1 21
1 17
72 3
247.5 0
2014 1
21 2
17 70
2 247.5
0 2014
1 21
3 16
75 2
225 0
2014 1
21 4
16 81
3 202.5
0 2014
1 21
5 15
87 3
202.5 0
2014 1
21 6
14 93
3 180
0 2014
1 21
7 14
93 3
180 0
2014 1
21 8
15 87
3 180
0 2014
1 21
9 17
72 5
157.5 0
2014 1
21 10
19 58
6 112.5
0 2014
1 21
11 21
51 8
90 0
2014 1
21 12
21 57
10 67.5
0 2014
1 21
13 23
51 10
67.5 0
2014 1
21 14
24 46
10 67.5
0 2014
1 21
15 25
45 10
67.5 0
2014 1
21 16
26 45
8 67.5
0 2014
1 21
17 24
52 6
90 0
2014 1
21 18
23 57
5 90
0 2014
1 21
19 21
66 5
112.5 0
2014 1
21 20
19 73
3 112.5
0 2014
1 21
21 18
81 3
112.5 0
2014 1
21 22
18 87
5 135
0 2014
1 21
23 17
93 3
157.5 0
2014 1
21 24
17 93
3 180
0 2014
1 22
1 17
90 3
180 0
2014 1
22 2
16 87
2 202.5
0 2014
1 22
3 16
90 3
225 0
2014 1
22 4
15 93
3 270
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
68
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
22 5
14 100
3 292.5
0 2014
1 22
6 14
100 3
315 0
2014 1
22 7
14 100
3 315
0 2014
1 22
8 14
96 2
315 0
2014 1
22 9
17 81
5 315
0 2014
1 22
10 19
65 8
0 0
2014 1
22 11
22 51
10 22.5
0 2014
1 22
12 24
44 11
22.5 0
2014 1
22 13
25 39
13 22.5
0 2014
1 22
14 26
35 14
0 0
2014 1
22 15
26 32
14 0
0 2014
1 22
16 26
30 14
0 0
2014 1
22 17
25 32
14 22.5
0 2014
1 22
18 23
38 13
22.5 0
2014 1
22 19
21 45
11 22.5
0 2014
1 22
20 19
56 10
22.5 0
2014 1
22 21
18 63
8 22.5
0 2014
1 22
22 17
67 8
22.5 0
2014 1
22 23
16 67
8 22.5
0 2014
1 22
24 16
67 8
22.5 0
2014 1
23 1
15 69
6 0
0 2014
1 23
2 14
72 6
0 0
2014 1
23 3
14 75
6 0
0 2014
1 23
4 13
80 6
0 0
2014 1
23 5
12 83
8 0
0 2014
1 23
6 12
86 6
22.5 0
2014 1
23 7
12 83
6 22.5
0 2014
1 23
8 13
77 5
45 0
2014 1
23 9
16 69
8 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
69
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
23 10
16 57
11 22.5
0 2014
1 23
11 19
40 13
22.5 0
2014 1
23 12
21 34
14 22.5
0 2014
1 23
13 23
28 14
22.5 0
2014 1
23 14
23 26
16 0
0 2014
1 23
15 26
30 11
0 0
2014 1
23 16
25 32
11 0
0 2014
1 23
17 24
34 11
0 0
2014 1
23 18
22 39
10 0
0 2014
1 23
19 21
44 10
0 0
2014 1
23 20
19 50
8 0
0 2014
1 23
21 18
55 8
22.5 0
2014 1
23 22
17 60
6 22.5
0 2014
1 23
23 16
60 6
45 0
2014 1
23 24
16 60
6 45
0 2014
1 24
1 15
62 6
45 0
2014 1
24 2
14 67
6 22.5
0 2014
1 24
3 14
72 6
22.5 0
2014 1
24 4
13 77
6 22.5
0 2014
1 24
5 13
80 6
22.5 0
2014 1
24 6
12 80
6 22.5
0 2014
1 24
7 13
77 6
22.5 0
2014 1
24 8
14 72
6 45
0 2014
1 24
9 16
65 5
67.5 0
2014 1
24 10
19 56
8 45
0 2014
1 24
11 22
46 11
45 0
2014 1
24 12
24 37
13 22.5
0 2014
1 24
13 26
31 14
22.5 0
2014 1
24 14
26 28
14 0
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
70
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
24 15
27 27
14 0
0 2014
1 24
16 26
29 14
0 0
2014 1
24 17
26 32
14 0
0 2014
1 24
18 23
38 13
0 0
2014 1
24 19
22 44
11 0
0 2014
1 24
20 19
50 10
0 0
2014 1
24 21
18 56
10 0
0 2014
1 24
22 17
60 8
0 0
2014 1
24 23
16 62
8 0
0 2014
1 24
24 16
64 8
0 0
2014 1
25 1
15 67
8 22.5
0 2014
1 25
2 14
69 8
22.5 0
2014 1
25 3
14 72
6 22.5
0 2014
1 25
4 13
74 6
22.5 0
2014 1
25 5
13 80
6 0
0 2014
1 25
6 12
83 6
22.5 0
2014 1
25 7
12 83
5 22.5
0 2014
1 25
8 13
80 5
22.5 0
2014 1
25 9
16 75
8 45
0 2014
1 25
10 19
68 10
45 0
2014 1
25 11
22 57
13 67.5
0 2014
1 25
12 24
48 14
45 0
2014 1
25 13
26 39
14 45
0 2014
1 25
14 26
34 16
45 0
2014 1
25 15
27 32
14 0
0 2014
1 25
16 27
32 14
0 0
2014 1
25 17
26 37
14 22.5
0 2014
1 25
18 24
43 13
22.5 0
2014 1
25 19
22 51
10 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
71
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
25 20
20 56
8 22.5
0 2014
1 25
21 18
63 8
22.5 0
2014 1
25 22
18 65
8 22.5
0 2014
1 25
23 17
65 8
22.5 0
2014 1
25 24
17 65
6 45
0 2014
1 26
1 16
62 6
45 0
2014 1
26 2
16 64
6 45
0 2014
1 26
3 15
67 6
45 0
2014 1
26 4
14 75
6 45
0 2014
1 26
5 13
77 6
45 0
2014 1
26 6
13 80
6 45
0 2014
1 26
7 13
80 6
67.5 0
2014 1
26 8
14 77
6 90
0 2014
1 26
9 15
51 8
45 0
2014 1
26 10
18 37
11 45
0 2014
1 26
11 21
28 14
22.5 0
2014 1
26 12
22 25
14 22.5
0 2014
1 26
13 22
32 14
0 0
2014 1
26 14
21 34
16 0
0 2014
1 26
15 21
39 16
45 0
2014 1
26 16
20 45
14 45
0 2014
1 26
17 20
48 14
45 0
2014 1
26 18
19 49
13 22.5
0 2014
1 26
19 19
53 11
22.5 0
2014 1
26 20
19 61
10 22.5
0 2014
1 26
21 17
70 8
22.5 0
2014 1
26 22
16 75
8 45
0 2014
1 26
23 16
75 8
45 0
2014 1
26 24
15 75
6 45
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
72
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
27 1
12 69
10 45
0 2014
1 27
2 11
69 10
45 0
2014 1
27 3
11 71
10 67.5
0 2014
1 27
4 11
74 10
67.5 0
2014 1
27 5
10 74
10 67.5
0 2014
1 27
6 10
77 10
90 0
2014 1
27 7
11 71
10 90
0 2014
1 27
8 14
64 11
67.5 0
2014 1
27 9
17 57
13 67.5
0 2014
1 27
10 20
50 16
67.5 0
2014 1
27 11
20 43
19 67.5
0 2014
1 27
12 22
39 18
67.5 0
2014 1
27 13
24 34
16 67.5
0 2014
1 27
14 24
32 16
67.5 0
2014 1
27 15
25 30
16 45
0 2014
1 27
16 25
30 14
22.5 0
2014 1
27 17
24 32
14 22.5
0 2014
1 27
18 22
36 14
0 0
2014 1
27 19
19 45
14 22.5
0 2014
1 27
20 22
38 8
67.5 0
2014 1
27 21
21 44
8 67.5
0 2014
1 27
22 19
50 8
67.5 0
2014 1
27 23
18 54
6 67.5
0 2014
1 27
24 17
56 6
90 0
2014 1
28 1
17 54
6 135
0 2014
1 28
2 17
56 5
135 0
2014 1
28 3
16 60
5 112.5
0 2014
1 28
4 16
62 5
112.5 0
2014 1
28 5
15 67
5 112.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
73
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
28 6
15 67
5 90
0 2014
1 28
7 15
67 5
90 0
2014 1
28 8
17 60
5 112.5
0 2014
1 28
9 19
52 5
112.5 0
2014 1
28 10
22 41
6 90
0 2014
1 28
11 25
33 6
90 0
2014 1
28 12
27 27
11 67.5
0 2014
1 28
13 28
27 11
45 0
2014 1
28 14
29 27
13 22.5
0 2014
1 28
15 29
28 13
22.5 0
2014 1
28 16
29 27
11 22.5
0 2014
1 28
17 28
23 10
22.5 0
2014 1
28 18
26 27
8 22.5
0 2014
1 28
19 24
31 8
22.5 0
2014 1
28 20
22 36
8 22.5
0 2014
1 28
21 20
42 8
45 0
2014 1
28 22
19 48
8 45
0 2014
1 28
23 18
52 8
45 0
2014 1
28 24
18 50
6 45
0 2014
1 29
1 17
48 6
90 0
2014 1
29 2
17 50
5 90
0 2014
1 29
3 17
50 5
90 0
2014 1
29 4
16 55
5 67.5
0 2014
1 29
5 15
60 5
67.5 0
2014 1
29 6
15 60
5 67.5
0 2014
1 29
7 15
55 5
90 0
2014 1
29 8
17 50
5 90
0 2014
1 29
9 19
43 8
90 0
2014 1
29 10
22 35
10 90
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
74
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
29 11
25 30
13 90
0 2014
1 29
12 27
25 14
67.5 0
2014 1
29 13
28 23
14 67.5
0 2014
1 29
14 29
20 16
67.5 0
2014 1
29 15
21 30
12 45
0 2014
1 29
16 20
33 12
45 0
2014 1
29 17
20 34
10 45
0 2014
1 29
18 19
35 10
22.5 0
2014 1
29 19
19 36
10 22.5
0 2014
1 29
20 17
41 10
22.5 0
2014 1
29 21
16 46
10 22.5
0 2014
1 29
22 15
46 8
45 0
2014 1
29 23
14 45
8 45
0 2014
1 29
24 14
45 8
45 0
2014 1
30 1
13 43
8 45
0 2014
1 30
2 13
43 8
67.5 0
2014 1
30 3
13 43
6 67.5
0 2014
1 30
4 12
47 6
67.5 0
2014 1
30 5
12 50
6 67.5
0 2014
1 30
6 11
52 6
90 0
2014 1
30 7
11 54
6 90
0 2014
1 30
8 12
55 6
90 0
2014 1
30 9
15 53
10 90
0 2014
1 30
10 18
50 11
90 0
2014 1
30 11
22 42
13 90
0 2014
1 30
12 24
37 13
90 0
2014 1
30 13
26 32
13 90
0 2014
1 30
14 27
30 11
90 0
2014 1
30 15
28 30
12 22.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
75
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
30 16
28 28
13 22.5
0 2014
1 30
17 27
31 13
0 0
2014 1
30 18
24 37
11 0
0 2014
1 30
19 22
44 10
337.5 0
2014 1
30 20
19 54
8 292.5
0 2014
1 30
21 17
67 8
315 0
2014 1
30 22
16 81
8 315
0 2014
1 30
23 16
84 8
315 0
2014 1
30 24
15 83
6 337.5
0 2014
1 31
1 15
75 6
0 0
2014 1
31 2
14 72
5 22.5
0 2014
1 31
3 14
77 5
22.5 0
2014 1
31 4
13 90
5 22.5
0 2014
1 31
5 13
96 5
22.5 0
2014 1
31 6
13 93
5 0
0 2014
1 31
7 13
83 5
0 0
2014 1
31 8
13 72
5 0
0 2014
1 31
9 16
58 8
0 0
2014 1
31 10
18 46
11 22.5
0 2014
1 31
11 21
39 14
22.5 0
2014 1
31 12
23 35
14 22.5
0 2014
1 31
13 24
34 14
0 0
2014 1
31 14
25 33
16 0
0 2014
1 31
15 25
33 16
0 0
2014 1
31 16
25 33
14 45
0 2014
1 31
17 24
36 14
45 0
2014 1
31 18
22 41
13 45
0 2014
1 31
19 25
31 10
67.5 0
2014 1
31 20
23 37
8 67.5
0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
76
Year
M
onth
D
ay
Hou
r Te
mpe
ratu
re
Rel
ativ
e hu
mid
ity
Win
d Sp
eed
Win
d D
irec
tion
Pr
ecip
itat
ion
2014 1
31 21
21 42
8 90
0 2014
1 31
22 20
47 8
90 0
2014 1
31 23
19 49
6 90
0 2014
1 31
24 19
50 6
90 0
ANN
EXU
RE
APR
IMAR
Y M
ETER
OLO
GICA
L D
ATA
77
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd 78
ANN
EXU
RE
– B
GOO
GLE
IMAG
E SH
OW
ING
NEA
RBY
GID
C RA
FLES
HW
AR
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd 79
GOO
GLE
IMAG
E SH
OW
ING
SUR
FACE
WAT
ER B
OD
Y M
ON
ITO
RIN
G LO
CATI
ON
S,
EIA
Pre
par
atio
n f
or t
he
Pro
pos
ed P
lan
t fo
r Fo
rmal
deh
yde,
Hex
amin
e &
Res
in M
anu
fact
uri
ng
of
M/
s P
awan
For
mal
in P
vt.
Ltd 80
GOO
GLE
IMAG
E SH
OW
ING
NEA
RBY
RES
ERVE
D F
ORE
ST
Annexure C Land Possession Documents
81
Annexure C Land Possession Documents
82
Annexure C Land Possession Documents
83
Annexure C Land Possession Documents
84
Annexure C Land Possession Documents
85
Annexure C Land Possession Documents
86
Annexure C Land Possession Documents
87
ANNEXURE – D
PUBLIC HEARING MINUTES
DATE : 11-2-2015
PAGE NO. 88 - 111
ANNEXURE - D PUBLIC HEAIRNG MINUTES 88
ANNEXURE - D PUBLIC HEAIRNG MINUTES 89
ANNEXURE - D PUBLIC HEAIRNG MINUTES 90
ANNEXURE - D PUBLIC HEAIRNG MINUTES 91
ANNEXURE - D PUBLIC HEAIRNG MINUTES 92
ANNEXURE - D PUBLIC HEAIRNG MINUTES 93
ANNEXURE - D PUBLIC HEAIRNG MINUTES 94
ANNEXURE - D PUBLIC HEAIRNG MINUTES 95
ANNEXURE - D PUBLIC HEAIRNG MINUTES 96
ANNEXURE - D PUBLIC HEAIRNG MINUTES 97
ANNEXURE - D PUBLIC HEAIRNG MINUTES 98
ANNEXURE - D PUBLIC HEAIRNG MINUTES 99
ANNEXURE - D PUBLIC HEAIRNG MINUTES 100
ANNEXURE - D PUBLIC HEAIRNG MINUTES 101
ANNEXURE - D PUBLIC HEAIRNG MINUTES 102
ANNEXURE - D PUBLIC HEAIRNG MINUTES 103
ANNEXURE - D PUBLIC HEAIRNG MINUTES 104
ANNEXURE - D PUBLIC HEAIRNG MINUTES 105
ANNEXURE - D PUBLIC HEAIRNG MINUTES 106
ANNEXURE - D PUBLIC HEAIRNG MINUTES 107
ANNEXURE - D PUBLIC HEAIRNG MINUTES 108
ANNEXURE - D PUBLIC HEAIRNG MINUTES 109
ANNEXURE - D PUBLIC HEAIRNG MINUTES 110
ANNEXURE - D PUBLIC HEAIRNG MINUTES 111