Monitoring Report MP1 Version 6
-
Upload
naveengoyal -
Category
Documents
-
view
220 -
download
4
Transcript of Monitoring Report MP1 Version 6
-
MONITORING REPORT
Monitoring Period
02/04/2007 to 31/05/2008
(Both days included)
Version: 06
Date: 25/01/2009
Rice Husk based power project at Satia Paper Mills Limited (SPML), Punjab,
India.
UNFCCC Reference No.- 0955
Project Site:
Village- Rupana, District- Muktsar, State-Punjab
Satia Paper Mills Limited
-
2
Table of contents
Current Status of the Project.............................................................................................................3
Monitoring Period ...........................................................................................................................4
Parameters monitored.......................................................................................................................5
Recorded observations for monitored parameters ............................................................................8
Emission reduction .........................................................................................................................10
Details of Down Time at the plant .................................................................................................12
Measures to ensure the Results / uncertainty analysis....................................................................13
Roles & Responsibilities ...............................................................................................................13
Training Procedure ........................................................................................................................13
-
3
Current Status of the Project
Satia Paper Mills Limited (SPML) is a leading integrated paper manufacturing unit in Punjab
with daily production in the range 130-150 Tons per day (TPD) of paper. The paper
manufacturing process requires thermal and electrical energy for various processes of
manufacturing unit. In order to meet the power requirements of the paper unit, SPML proposed a
rice husk based power project.
This project was successfully commissioned by Satia Paper Mills Limited (SPML), Punjab and
has been operational since July 2003.
The major equipments deployed in the project activity are as follows:
Turbine details
Description Fully condensing
Make Siemens
Power (MW) 5
Boiler details
Prior to the project activity two rice husk boilers (capacity 15 TPH and 27 TPH respectively)
were operational to meet the total steam requirements (23 TPH) of the process. The boiler with
installed capacity of 27 TPH was running on lower capacity in pre project scenario. After
installation of turbine, 27 TPH boilers runs on full capacity and generates 19 TPH of extra high
pressure steam which is used to run the project turbine. The electricity produced from project
turbine shall displace equivalent amount of electricity supply from the grid which would have
otherwise happened in absence of the project activity.
The configuration details of the boilers are as follow:
Description Parameter
Steam generating capacity (tons per hour) 15
Steam pressure (kg/cm2) 14.06
Steam temperature (0 C) 200
Description Parameter
Steam generating capacity (tons per hour) 27
Steam pressure (kg/cm2) 32.9
Steam temperature (0 C) 400 10
-
4
Monitoring Period
The Monitoring Period is chosen from 02/04/2007 to 31/05/2008 (both days included).
-
5
Parameters monitored
The following parameters have been monitored:
Data / Parameter: Total Electricity generated
Data unit: kWh
Description: Total electricity generated by the project activity
Data reported in : Plant log books
Instrument used for
measurement:
Electronic energy meter
Description of
measurement
methods and
procedures to be
applied:
Energy meter at the plant location record the total electricity generated
which is then reported in the plant log books on every 8 hours shift &
daily basis.
QA/QC procedures
to be applied:
In order to ensure the highest levels of accuracy in the monitoring
procedures, the instrument used for the monitoring is calibrated annually.
As measure of quality assurance, efficient compilation and easy
accessibility of the data logged for the monitored parameter, the observed
readings are reported in the excel sheet as well. PSEB meter is installed
for cross verification
Accuracy class 1.0
Data / Parameter: Auxiliary Consumption
Data unit: kWh
Description: Electricity consumption in the plant
Data reported in : Plant log books
Instrument used for
measurement:
Electronic energy meters
Description of
measurement
methods and
procedures to be
applied:
Energy meters at different auxiliary locations shall measure the energy
consumed in auxiliaries which is then reported in the plant log books on
every 8 hours shift & daily basis.
QA/QC procedures
to be applied:
In order to ensure the highest levels of accuracy in the monitoring
procedures, the instruments used for the monitoring are calibrated
-
6
annually.
As measure of quality assurance, efficient compilation and easy
accessibility of the data logged for the monitored parameter, the observed
readings are reported in the excel sheet as well.
Accuracy class 1.0
Data / Parameter: Power supplied to the plant
Data unit: kWh
Description: Net power supply to plant
Data reported in : Plant log books
Description of
measurement
methods and
procedures to be
applied:
The net power supplied to plant is calculated by taking the difference of
the gross power generated and the auxiliary power consumption in the
plant.
QA/QC procedures
to be applied:
In order to avoid any discrepancies in the reporting of the monitoring
parameters the calculated readings would be directly reported in the excel
sheets.
Data / Parameter: Rice husk Quantity
Data unit: Tones
Description: Quantity of rice husk used
Data reported in : Plant log books
Instrument used for
measurement:
Weighto meter
Description of
measurement
methods and
procedures to be
applied:
The rice husk quantity consumed is measured by the weighto meter
installed at the plant site.
QA/QC procedures
to be applied:
In order to ensure the highest levels of accuracy in the monitoring
procedures, the instrument used for the monitoring is calibrated annually.
As measure of quality assurance, efficient compilation and easy
accessibility of the data logged for the monitored parameter, the observed
readings are reported in the excel sheet as well.
-
7
Data / Parameter: Calorific Value
Data unit: kCal/kg
Description: NCV of rice husk
Data reported in : Test Reports
Description of
measurement
methods and
procedures to be
applied:
The net calorific value of the rice husk samples sent by SPML is tested by
the third party agency.
QA/QC procedures
to be applied:
As measure of quality assurance, efficient compilation and easy
accessibility of the data, the records for the net calorific value is
maintained in the excel sheets as well.
Biomass Availability:
An independent third party has conducted biomass assessment study for the period 01/12/2007 to
31/12/2008. The biomass assessment study clearly demonstrates that the quantity of available
biomass in the region (50 km radius), is 26.9% larger than the quantity of biomass (rice husk) that
is utilized including the project activity.
The biomass assessment report concludes that the surplus rice husk available in the command
area is 72622 MTPA when the requirement of biomass is around 269958 MTPA.
-
Recorded observations for monitored parameters
Month
Total
Electricity
Generated
(kWh)
Auxiliary
Consumption
(kWh) *
Power
Supplied to
the Plant
(kWh)
Rice Husk
Quantity
(Tonnes)
Net
Calorific
Value
(kCal/Kg)
Apr-07 1639783 128800 1510983 2507 3380
May-07 1095582 94300 1001282 2343 3480
Jun-07 2755022 154500 2600522 3859 3690
Jul-07 889263 63000 826263 2704 3680
Aug-07 1846531 95400 1751131 3082 3982
Sep-07 701731 37800 663931 2232 4070
Oct-07 3168168 144700 3023468 5106 4067
Nov-07 2964822 127600 2837222 4741 3770
Dec-07 2599422 118600 2480822 4560 3548
Jan-08 2880720 129900 2750820 5072 3660
Feb-08 2953491 124200 2829291 4725 3865
Mar-08 3165180 136800 3028380 5082 4079
Apr-08 2856308 129200 2727108 4765 4260
May-08 2630030 122000 2508030 4683 4290
Total 32146053 1606800 30539253 55461
-
Auxiliary Components
Auxiliary components for the project activity (Boiler No.4 and Turbo Generator) consist of CT
FAN & CWP-3 .CWP-2 (Stand by). The technical specifications for the auxiliary components are
follows:
CT FAN
Make Paltech
Quantity 10 Nos
Capacity 12.5 HP
CWP-3
Make KSB
Quantity 1 No.
Flow 900m3/hr
Head 35m
Motor 150 HP Crompton Make
CWP-2 (Stand by)
Make KSB
Quantity 1 No.
Flow 900m3/hr
Head 35m
Motor 150 HP Crompton Make
-
10
Emission reduction
Baseline and project emissions are calculated as per the formulas mentioned in Section E of the
PDD. The same is given below:
Formulae used
The emission reduction is given by
Emission reduction = Baseline emissions Project emissions
Baseline emissions
BEY = EFY X EGY
BEY baseline emission due to displacement of electricity during the year y (t CO2)
EGY net quantity of electricity generated by the project activity during the year y (KWh)
EFY 1 CO2 baseline emission factor for the electricity displaced due to the project activity
in tons CO2/MWh (0.751 tCO2/MWh)
Project emissions
Since no fossil fuel used for the boiler operation, there is no project emission due to project
activity:
PEY = 0
1 The grid emission factor has been taken from the registered PDD.
http://cdm.unfccc.int/Projects/DB/TUEV-SUED1171633439.48/view
-
11
Emission reductions
Period
Baseline
Emission
factor
(tCO2/MWh)
(A)
Net
Power
produced
(KWh)
(B)
Project
emissions
(t CO2)
Baseline
emissions
(t CO2 )
( C =
A*B)
Emission
reductions
(t CO2)
(C-F)
02/04/2007 -31/05/2008 0.751 30539253 0 22935 22935
-
12
Details of Down Time at the plant
Major Outage Period2 Outage Period
Serial Number
Start from Up To (Days)
1 15/05/2007 25/05/2007 11
2 07/07/2007 24/07/2007 18
3 12/08/2007 14/08/2007 03
4 24/08/2007 31/08/2007 08
5 01/09/2007 22/09/2007 22
6 24/12/2007 26/12/2007 03
7 21/02/2008 21/02/2008 01
8 04/05/2008 05/05/2008 02
Total 67
2 The Downtime period is defined as the period during which the Turbine Generator (TG) was not in operation / production was stopped due to scheduled preventive maintenance or brake down maintenance /
equipment failure / modification / equipment installation etc. or any of the reason.
-
13
Measures to ensure the Results / uncertainty analysis
In order to ensure the highest levels of accuracy the monitoring instruments are calibrated
regularly as per the manufacturers specifications. The gross power generated, auxiliary power
consumption and rice husk consumption are recorded in the plant log books which are reviewed,
verified and finally approved by the Director of the company. Also as a measure of quality
assurance in the data recording, the recorded parameters are reported in the excel format as well
which ensures the efficient compilation and easy accessibility of the data.
In order to avoid any kind of discrepancy in the monitoring process and to ensure quality and
error free monitoring process, regular internal audits are planned. The audit team comprise of the
in house technical experts and the senior officials.
-
14
Roles and responsibilities
SPML would be solely responsible for the monitoring activity. Organization structure responsible
for monitoring and reporting of parameters involved in CDM project activity is as presented in
the following flow chart.
Director
Vice President (works)
Manager-Utilities
Monitoring Supervisor-electrical Monitoring Supervisor-
mechanical
Director (Tech.)
-
Training Procedure
SPML would ensure the efficient working of the RICE HUSK BASED POWER PROJECT by
conducting training programmes. Aim of the procedure is to ensure training of SPML employees
associated with Project activity. The training will be on the following aspects of activity involved
in the Project operation, maintenance, monitoring of parameters, precautions, safety instructions
etc. These trainings will be meant to address the following key requirements related to the project
activity:
1. Corrective and preventive maintenance It would include the procedures for the general
inspection to be carried out, the maintenance required to ensure the uninterrupted
operation of the project plant.
2. Proper maintenance of the log books & reporting.
3. Calibration requirements of the monitoring equipments.
4. Monitoring of Fuel Efficiency
5. To take care of the other monitoring requirements of the CDM project activity.