MODULE VI IFI PROCUREMENT DAY 2 -...
Transcript of MODULE VI IFI PROCUREMENT DAY 2 -...
04/05/2014
1
University of Rome Tor Vergata
International Master in Public Procurement Management
May 2014
© European Bank for Reconstruction and Development 2010 | www.ebrd.com
MODULE VI – IFI PROCUREMENT
DAY 2
Veljko Sikirica, professor
Senior Procurement Specialist, EBRD
University of Rome Tor Vergata
International Master in Public Procurement Management
May 2014
© European Bank for Reconstruction and Development 2010 | www.ebrd.com
Part 5
THE PROCUREMENT CYCLE
Veljko Sikirica, professor
Senior Procurement Specialist, EBRD
04/05/2014
2
3
OBJECTIVES
By the end of this module, you will be able to:
identify the various stages in a typical procurement cycle;
understand the activities required at each stage of the process;
appreciate the need for proper planning before undertaking procurement.
4
Procurement process
Works and goods
Preparation • Identification of needs
Prequalification • Advertisement
Tendering • Invitation to tender
Execution • Signing of contract
Warranty period • Last day
04/05/2014
3
5
Ad
ve
rtis
ing
Te
nd
er
do
cu
me
nts
Cla
rifi
ca
tio
ns
Te
nd
er
Su
bm
iss
ion
Pa
ym
en
t fo
r d
oc
um
en
ts
Te
nd
er
ev
alu
ati
on
Pu
bli
c t
en
de
r o
pe
nin
g
Ev
alu
ati
on
re
su
lts
&n
oti
fic
ati
on
Pu
bli
c A
cc
es
s t
o D
ata
ba
se
Co
ntr
act
Sig
nin
g
Pro
cu
rem
en
t P
lan
Public tender process
6
A Typical Procurement Cycle
04/05/2014
4
7
1. Procurement Planning and 2. Notification
Good procurement planning is essential to determine:
– what goods, works and services are needed for the project;
– when they are needed;
– estimated costs;
– which procurement and contracting procedure is most suitable;
– the key dates and milestones which need to be met;
Planning allows for better monitoring, greater transparency and more predictability;
The Client completes the overall project procurement plan and obtain ‘no objection’ from the Bank before commencing any procurement activity;
It is needed for the Notification phase. Notification is made through a GPN to inform potential suppliers and the general community of the project and its components.
8
3. Sourcing
There are two aspects – prequalification (PQ) and shortlisting.
PQ is separate from the tender exercise and is generally an open invitation to qualified suppliers/contractors who would be able to undertake a particular contract
PQ is used when undertaking procurement through the following methods where either very specialised or complex procurement is involved or where competition is limited by the market:
– Open tendering (complex procurement)
– selective tendering;
Shortlisting requires a combination of research and existing market knowledge and is used to identify candidates for
– Direct Contracting and selection of consultants
04/05/2014
5
9
4. Tendering
This phase includes:
Drafting the appropriate tender document, including the evaluation criteria;
Launching the tender;
Appointing the evaluation committee;
Responding to tender clarifications;
Issuing any necessary tender amendments;
The tender opening process;
10
5. Evaluation and Award
Often the most contentious and time consuming and difficult part of the process which attracts the most complaints;
Evaluation consists of technical issues and price/commercial aspects;
The Client shall prepare a tender evaluation report and recommendation for contract award to the Bank for ‘no objection’ .
Client will sign the contract with the selected supplier;
04/05/2014
6
11
6. Contract Management
The contract management process includes:
– monitoring or supervision of performance;
– ensuring Client and contractor responsibilities are undertaken;
– approving payments;
– providing reports to the Bank;
– handling variations;
– Acceptance and completion
12
RECAP
In this module we have discussed:
the various stages in a typical procurement cycle;
the activities required at each stage of the process;
why planning is so critical to the procurement cycle;
04/05/2014
7
University of Rome Tor Vergata
International Masters in Public Procurement Management
Rome – May 2014
© European Bank for Reconstruction and Development 2010 | www.ebrd.com
Part 6
PROCUREMENT METHODS (GOODS & WORKS)
Veljko Sikirica, Professor
Senior Procurement Specialist, EBRD
14
MODULE OBJECTIVES
By the end of the presentation, the participants should be able to:
1. Explain the different procurement methods available and when to use each one
2. Understand the procurement methods and associated project thresholds
3. Apply a decision process to selecting the appropriate method
04/05/2014
8
15
IFI PROCUREMENT METHODS
Open Tendering (may be a two-stage tendering process)/ICB
Selective Tendering
Direct Contracting
Shopping
Local Competitive Tendering/NCB
Force account
5/4/2014 IFI Procurement Methods 16
Procurement Methods
Estimated Contract Cost
Level of competition desired/expected
•NCT
• ICT
Threshold
•LIT
•Shopping
•Direct Contracting
•Force Account
04/05/2014
9
IFI PROCUREMENT METHODS
Open Tendering / ICT
Selective Tendering
Direct Contracting
Shopping
Local Competitive Tendering/NCT
Force account
18
CHOICE OF PROCUREMENT METHOD
The choice of procurement method will be driven by:
– Financial thresholds (EBRD ≥ € 250,000 for goods & ≥ € 7.5 million for works).
– Special circumstances
Special circumstances will be determined by nature and value of the goods/works, required completion time or other considerations;
All procurement methods, other than open tendering shall be clearly justified and agreed by the Board of the Bank prior to project legal documentation.
04/05/2014
10
19
METHODS
Open Tendering
• Open to all eligible firms irrespective of nationality (EBRD – other IFIs may have restrictions)
• Adequate notification of opportunity
• It may single or two-stage tendering procedure
• Can be used with or without prequalification
Selective Tendering
• Tenders are invited from qualified firms selected in a non-discriminatory manner
• N.B. This is not as a result of prequalification – prequalification is used with open tendering only
Direct Contracting
• Extension of an existing contract / standardisation with existing equipment
• Failure of an open / selective process
• Requirement only available from a single source
• Extreme urgency
Shopping
• Low-value, off-the-shelf item
• A competitive procedure with at least three quotations
• Foreign firms to be included, if possible
Local Competitive Tendering
• Use of national procedure
• Requirement available locally at competitive prices
• Requirement unlikely to attract international competition
• National procedures are acceptable to Bank
BA
NK
AP
PR
OV
AL
RE
QU
IRE
D
20
EXERCISE
To consider the appropriate procurement method for the attached list of requirements. If Open Tendering is not recommended, what is the justification?
Working in groups – 20 minutes
Nominate one member to give feedback
04/05/2014
11
21
RECAP
In this module we have discussed:
the different procurement methods available;
when to use each one;
how to apply a decision process to selecting the most appropriate method;
University of Rome Tor Vergata
International Masters in Public Procurement Management
Rome – May 2014
© European Bank for Reconstruction and Development 2010 | www.ebrd.com
Part 7
SELECTION OF CONSULTANTS
Veljko Sikirica, Professor
Senior Procurement Specialist, EBRD
04/05/2014
12
PART 7: SELECTION OF
CONSULTANTS
Selection and Contracting of Consultants by the Client
CONSULTING SERVICES
Req
ue
st
for
Pro
po
sa
ls
Cla
rifi
ca
tio
ns
Pro
po
sa
l S
ub
mis
sio
n
Pro
po
sa
l e
va
lua
tio
n
Co
ntr
ac
t A
wa
rd
Pu
bli
c A
cc
es
s t
o D
ata
ba
se
Co
ntr
ac
t S
ign
ing
Pro
cu
rem
en
t P
lan
Sh
ort
Lis
t
Req
ue
st
of
ex
pre
sio
ns
of
inte
res
t
Selection Process - Consulting Services
04/05/2014
13
Consulting Services
The Participant with the best evaluated proposal in accordance with the selection method used.
Six selection methods:
• Quality and Cost Based Selection (QCBS)
• Quality Based Selection (QBS)
• Least Cost Based Selection (LCBS)
• Fixed Budget Selection (FBS)
• Consultants Qualifications Selection (QCS)
• Single Source Selection (SSS)
Who is Awarded the Contract
Tenderers may participate as
Independent Firm
Voluntarily constituted JVCA
Mandatory Association is not acceptable
04/05/2014
14
Consulting firm that prepares / implement project is disqualified for:
Supplying Goods
Constructing Works
Supplying Services (does not apply to turn-key contracts)
Eligibility - Conflict of Interest
The importance and necessity of the
Consultancy Services
Assist the Bank’s client with:
• Project Preparation e.g. feasibility studies, design, environmental impact assessment
Project Implementation:
• capacity building, institutional development, eg. project implementation units – role of a partner
• project supervision: Independent Engineer – very clearly defined contractual role
04/05/2014
15
The importance and necessity of the
Consultancy Services CONTINUATION
Assist the Bank with:
• due diligence
• project monitoring, lenders technical supervisor
Overview of Procedures for Consultant
Selection
Direct Selection (below EUR 75,000)
Selection from
Shortlist (EUR 75,000 – EUR 300,000)
Proposals
(EUR 300,000 and over)
Select consultant
Negotiations
Contract
Calls for expressions of
interest (not obligatory)
Long list
Shortlist
Select consultant
Negotiations
Contract
Calls for expressions of
interest
Long list
Shortlist
Proposal
Select consultant
Negotiations
Contract
04/05/2014
16
Consultant Selection Methods
Quality Based Selection (QBS)
• Most important criteria technical qualification / relevant experience
Price as a factor:
Quality Cost Based Selection (QCBS)
• 2 Envelope System. The norms are:
• Technical proposals: weight of 80% and only when technical thresholds are met
• Financial proposal: weight 20% (similar to the EU)
Quality-and-Cost Based Selection
(QCBS)
Main Features
• Competition among short-listed firms only
• Combined quality and cost evaluation
• Relative weighs of quality and cost depend on nature of assignment
• Cost as evaluation factor used judiciously
04/05/2014
17
QCBS Steps
Preparation of TOR
Preparation of cost estimate and budget
Advertising
Preparation of short list
Preparation-Issuing RFP
Receipt of Proposals
Technical Proposal evaluation
Price Proposal public opening
Price Proposal evaluation
Combined Quality-Cost evaluation
Contract Negotiation and award
QCBS
TOR
• Responsibility: Client
• Preparation: Specialist in area of assignment
• - Contents: not too detailed
• - Specify Objectives
• Compatible with budget
• List of surveys and services
• List and chronogram of Outputs
• Specify Training and Knowledge Transfer
04/05/2014
18
QCBS
Cost Estimate and Budget
• Client’s reliable assessment is essential
• Staff time
• Logistical support
• Physical inputs
• Categories:
• Fees (remuneration)
• Reimbursable expenses
• Components
• local - foreign
QCBS
Advertising
• General Procurement Notice (GPN)
• - Lists expected procurements and EA’s contact information
• - Client prepares and sends to Bank
Bank arranges publication
• Bank’s Internet website (www.ebrd.com) Specific Procurement Notice (SPN)
04/05/2014
19
Request for Proposals (RFP)
Contents
• All necessary information for proposal preparation
Clarity
• Complete, clear, precise description
• preparation/opening/evaluation/award procedures
• Scope of Consulting Services
• Completion schedules
• Clear sound evaluation criteria
Letter of Invitation
Instructions to Consultants
Data Sheet
Technical Proposal-Standard Forms
Price Proposal- Standard Forms
Terms of Reference
Standard Contract
General Conditions of Contract
Special Conditions of Contract
Eligible Countries
Appendices
RFP Typical structure
04/05/2014
20
Proposal Procedures
Only One Proposal
• Short-listed Consultants may submit only one Proposal
• A Sub-consultant or individual expert may participate in more than one Proposal
Proposal Validity
• Specified in RFP
• Sufficient to
• Evaluate Proposals
• Negotiate Contract
• Obtain all no objections and approvals
• Award contract
Pricing
• Remuneration Adjustment
Provision needed if contract duration exceeds 18 months
Provision may be included for contract duration shorter than 18 months, if local or foreign inflation expected to exceed 5% per annum
Proposal Procedures
04/05/2014
21
Currency Provisions
• Currency of Price Proposal
Consultants may express price in • Any single, fully convertible currency, or
• No more than three freely convertible foreign currencies
Client may require
• Consultants to quote local portion of price in local currency
Proposal Procedures
Proposal Preparation
• Time allowed depends on assignment circumstances and complexity
Generally, at least 4 weeks
For large complex assignments:
• no more than 3 months
Proposal Procedures
04/05/2014
22
Proposal Submission
• Place/deadline clearly specified in RFP
• By mail, by hand or electronically if Bank satisfied that system is secure
• Technical & Price proposals
• in separate envelopes
• submitted at same time (except in case of QBS where there is an option to request a Price Proposal only from the firm who submitted the best Technical Proposal).
Proposal Procedures
Proposal Opening
• Technical Proposal envelopes opened immediately by ad-hoc committee
• Evaluation of Quality takes place
• Price Proposal envelopes remain sealed
• under custody of reputable Public Auditor / Authority
• until publicly opened on completion of Evaluation of Quality
• Late proposals returned unopened
Proposal Procedures
04/05/2014
23
Price Proposal Opening CONTINUATION
• Client reads aloud and records
• Name of Consultant
• Technical score
• Proposal price
• Copy of record promptly sent to Bank and all who submitted proposals
• Client prepares minutes of public opening and sends it to all who submitted proposals and to the Bank
Proposal Procedures
Confidentiality
• From proposals opening, until publication of contract award:
Information on examination, clarification and evaluation of proposals and award recommendations shall not to be disclosed to consultants who submitted proposals or to any person not officially concerned, except as specified in RFP
Proposal Procedures
04/05/2014
24
Proposal Evaluation
• Purpose
Determine highest-ranked proposal based on combined evaluation of cost and quality and select it for negotiations and award
• Procedure
Evaluation of Quality
Evaluation of Cost
Combined evaluation of Quality and Cost
Proposal Procedures
Proposal Evaluation CONTINUATION
• Evaluation Committee evaluates Technical Proposal
• Rejects Proposals Not responsive to TOR
• Determines Technical score using evaluation criteria, subcriteria and weight specified in RFP
• Rejects proposal if
• Fails to achieve minimum Technical Score specified in RFP
• Prepares Technical Evaluation Report
• Obtains Bank’s no objection
Proposal Procedures
04/05/2014
25
Evaluation of Quality CONTINUATION
• Client
• Informs those who submitted proposals the Technical score obtained
• Notifies those whose Proposals did not meet minimum marks or were found nonresponsive that their Price Proposals are being returned unopened
• Notifies those whose proposals met minimum qualifying marks the date, time and place of public opening of Price Proposal
Proposal Procedures
Proposal Procedures
Evaluation of Quality Example
Quality evaluation criteria Weight %
Mark* Score
– Relevant experience 5 80 4
– Quality of methodology 30 100 30
– Staff qualifications 50 80 40
– Knowledge transfer 5 100 5
– Participation of nationals 10 50 5
– Totals for Evaluator #1 100 84
04/05/2014
26
Evaluation of Cost
• Price Evaluation
• Correction of arithmetical errors
• For Evaluation, cost excludes
• Local indirect taxes
• Income tax payable in Client’s country on remuneration for services by non resident staff in Client’s country
• For Evaluation, cost includes
• Remuneration
• Reimbursable expenses e.g. travel, communications
Proposal Procedures
Evaluation of Cost CONTINUATION
• Cost score
• Lowest-cost proposal gets score of 100 points
• Other proposals get score inversely proportional to their cost
• Other methodology may be used (describe in RFP)
Proposal Procedures
04/05/2014
27
Evaluation of Cost CONTINUATION
– Example
– Proposal Evaluated Cost Price Score
– A 4500 100
– B 5000 90
– C 6000 75
Proposal Procedures
Combined Quality and Cost Evaluation CONTINUATION
– Example:
– Proposal Technical Price
score* weight QWS score weight PWS Total
– A 84 80 67.2 100 20 20.0 87.2
– B 87 80 69.6 90 20 18.0 87.6
– C 90 80 72.0 75 20 15.0 87.0
– Proposal B gets highest score and is invited to negotiate contract
– ------------------------------------------
– * Average of scores of Evaluators or similar procedure
Proposal Procedures
04/05/2014
28
Contract Negotiation
• Technical Negotiation
• Should cover
• TOR
• Methodology
• Staffing – Key staff changes not allowed unless required to meet objectives and new staff should have equivalent/better qualifications
• Client’s input
Proposal Procedures
Contract Negotiation
• Technical Negotiation (cont)
• Should not substantially alter
• TOR
• Contract Terms
• Quality of final product
• Relevance of initial evaluation
• Should not substantially reduce
• Scope of assignment to meet budget
Proposal Procedures
04/05/2014
29
Contract Negotiation (cont)
• Price Negotiation
• In all contracts
• Should not cover reimbursables
• When price is evaluation factor
• In Lump-sum contracts
• should not cover Contract Price
• In Time-based contracts
• Should not cover staff-rates, except if
• Rates offered are much higher than for similar assignments
Proposal Procedures
Contract Negotiation
• Outcome of Negotiation (cont)
• If negotiations fail, Client
• Terminates negotiations
• Informs firm of reasons for termination
• Invites next highest-ranked firm, only after consultation with the Bank
Proposal Procedures
04/05/2014
30
Contract Negotiation (cont)
• Outcome of Negotiation
• On completion
• All agreements to be reflected in negotiated Contract
• Negotiated Contract subject to Bank’s no objection
• Award Contract after Bank’s no objection
• Notify all other consultants
Proposal Procedures
Debriefing
• Contract Award
• Consultant has the right to request that Client explain why its proposal was not selected
• At Client’s option, debriefing
• At meeting (Consultant bears costs to attend), or
• In writing
Proposal Procedures
04/05/2014
31
Rejection of all Proposals
• By the Client w/Bank prior approval
• No substantially-responsive proposals
• Prices substantially higher than original estimate
• After investigating in consultation with the Bank feasibility of increasing budget or reducing scope
• Reinvitation
• To obtain lower prices
• Before inviting, Client to review and consider revising
• Short list
• RFP Document/Conditions of Contract
• Design/specification/scope of assignment
Proposal Procedures
Types of
contracts
Consulting Services
04/05/2014
32
Main types
• Lump-sum
• Time-based
• Retainer and / or Success Fee
• Percentage of construction or goods cost
• Indefinite Delivery (Price agreement)
Type of contracts
Description
• Contents, duration and output can be clearly defined
• Easy to administer
• Widely used, i.e.:
• Simple planning and feasibility studies
• Environmental Studies
• Detailed design of standard/common structures
• Software design for data processing system, etc
Lump sum contract
04/05/2014
33
Procedures
• Payments due, linked to specified output, i.e.:
• Reports,
• Drawings
• Bill of quantities
• Tender documents
• Software programs, etc.
Lump sum contract
Description
• Contents, duration and output cannot be to precisely defined
• Services depend on activities by others
• Consultants input to attain objectives cannot be assessed in detail
• Widely used, i.e.:
• Complex studies
• Supervision of construction
• Advisory services
• Training assignments, etc.
Time based contract
04/05/2014
34
Procedures
• Payments due base on:
• Staff time spent in specific activities
• Agreed hourly, daily, weekly, monthly rates
• Rates comprise salary, social costs, overhead, fee (profit)
• Reimbursement of expenses on agreed categories
• Total price not to exceed ceiling that includes contingency allowance
• Requires close monitoring by Client
Time based contract
Consulting Services
Important
considerations
04/05/2014
35
Purpose / Contents
• Balanced allocation of risks and liabilities
• Rights and obligations of Parties
• Functions and authority in contract execution, supervision and administration
• Clear definition of scope of works, supply and services
• Definition/specification of project/sites locations, particular conditions
Contract
Important Provisions
• Currency Provisions
• Price Adjustment*
• Payment Terms and Methods
• Tender and Performance Securities
• Client contribution
• Conflict of interest*
• Professional Liability
• Applicable law. Settlement of disputes
• Force Majeure
Contract provisions
04/05/2014
36
Payment Terms and Methods
• Agreed at negotiations, specified in Contract
• Amounts, Schedule, procedures
• Depending on kind of Contract
• Regular intervals, or
• Based on output
• Advance payment against Bank guarantee if higher than 10% of contract price
Contract provisions
Payment Terms and Methods (cont)
• Payment Procedures
• By the Client against invoices, or
• Directly by the Bank, at Client’s request, or
• Exceptionally through letter of credit
• Only disputed amounts withheld
• Finance charges apply for delayed payments as specified in contract
Contract provisions
04/05/2014
37
Staff substitution
• May be needed due to
• Health reasons or death
• Staff not suitable
• Requires consultant to:
• Provide substitute staff of at least same qualifications
• Obtain Client’s approval to proposed staff
Contract provisions
Description
• Hired when
• No team is required for assignment
• No home office support required
• Experience and qualifications of individual are paramount to achieve objectives
• A firm is preferable to large number of individuals if
• Coordination, administration, collective responsibility become difficult
Individual consultants
04/05/2014
38
Procedures
• Selection:based on qualifications
• Advertisement: not required
• Submission of proposals: not needed
• Single source selection acceptable exceptionally if:
• Continuation of tasks
• Initial assignment awarded competitively
• Emergency situations from natural disasters
• Individual is only qualified candidate for assignment
Individual consultants
Procedures (cont)
• Evaluation
• At least three CVs from
• Those who expressed interest, or
• Were approached by Client
• Select best qualified individual based on:
• Academic background
• Experience
• Knowledge of local conditions, i.e. language, culture, etc
• If candidate is permanent staff or associate of consulting company
• Verify conflict of interest
Individual consultants
04/05/2014
39
Grazie