Modeling Grid Operations in China’s Partially-Restructured Electricity Market Michael R. Davidson,...
-
Upload
melissa-wells -
Category
Documents
-
view
222 -
download
0
Transcript of Modeling Grid Operations in China’s Partially-Restructured Electricity Market Michael R. Davidson,...
Modeling Grid Operations in China’s Partially-
Restructured Electricity Market
Michael R. Davidson, Valerie J. Karplus, Ignacio Perez-Arriaga
China’s wind integration challenges
2
Curtailment = Available wind-generated electricity not accepted onto grid
2013-2014
Source: NEA
Dispatch priorities
Institutional arrangements important cause of large-scale wind integration challenges (Zhao et al 2012; Kahrl et al 2011)
Equitable dispatch (三公调度 )• Equal shares of benefits (& costs) for plants at
provincial level: generation quotas, equal curtailment allocation…
Minimum mode (最小方式 )• Sum of committed plants’ submitted minimum
outputs
Energy-efficient dispatch (节能调度 )• Post-MM: Prioritize RE high efficiency coal low
effic coal
Unit commitment and economic dispatch-like optimization is not regularly performed
3Sources: Interviews (2014, 2015) and Kahrl & Wang (2014)
4
Goals of presentation
• Demonstrate approach to optimize generator scheduling under coupling regulatory constraints, with applications to partially-restructured electricity sectors
• Quantify economic and environmental cost of deviations from ideal operation, such as “administrative congestion”
Model
5
Additional technical detail
Regulatory constraints
Optimality criteria ≤ 0.003
6
• Generation quota / Full Load Hours (FLH):Minimum capacity factor of coal generators by type based on provincial averages
Lagrangian penalty for non-served FLH faster and more reliable than hard constraint
Regulatory constraints
7
• Generation quota (FLH):Minimum capacity factor of coal generators by type based on provincial averages
• Provincial dispatch (PROV):Separate provincial reserve requirements
Similar treatment for downward reserves
Regulatory constraints
8
• Generation quota (FLH):Minimum capacity factor of coal generators by type based on provincial averages
• Provincial dispatch (PROV):Separate provincial reserve requirements
• Transmission contracts (TRANS):Historical annual imports/exports limited transmission capacity and
directions between provinces
Regulatory constraints
9
Clustering formulation
Commitment variables: binary integer
Palmintier & Webster (2014)
10
Clustering formulation
Commitment variables: binary integer
Palmintier & Webster (2014)
11
Experiments
• Week (168-hour) time horizon• Mean results for 6 winter wind profiles from 2011• Pre-solve for min of two wind scenarios: MIPSTART• System: Northeast China 2011, provincial nodes
(CEC 2010)
12
Construction of generator dataset
ClusteringCluster same-type units into single unit, integer
commitments
Minimum modeCogeneration unit commitments (default: 80%)
12-type configurationAggregate units into: (25, 50, 135, 200, 350, 600) x (Heat, Thermal)
Units databaseInside-the-fence unit capacities and type (cross-check)
Power plant database (China Electricity Council)Plant capacities (2011) Names
13
Aggregation results
14
Aggregation results (2)
15
Aggregation results (3)
16
Aggregation results (4)
17
Solution times (min)
• Implemented in GAMS using CPLEX 12.6.2• Each scenario was run using 8 parallel threads on a 64-bit
dual-socket quad core 2.7 GHz Intel nehalem machine with 12 GB RAM
Aggregation results (5)
18
Aggregation summary
Acceptable aggregation errors of multi-node 12-type homogeneous and clustering methods• objective ~ 0.3% = tolerance threshold• wind ~ ± 2%
Node-specific incidences more varied• signal of Δwind, Δobj ~ 5% difficult to attribute
19
Wind curtailment
Regulatory and transmission constraints increase objective
Interaction of PROV + TRANS increases curtailment Quota has zero or slightly negative impact on wind
curtailment
20
Cogeneration sensitivity results
Black border: 90% cogen commitment
21
Results summary
Absent regulatory design issues, there is curtailment, but still below observed levels of curtailment
Largest difference is usage of high-efficiency coal, changing among provinces based on transmission & other constraints
No congestion in reference scenarios marginals of transmission constraints show transmission is binding only in Limited TRANS case (“administrative congestion”)
Generator flexibility: Large gains from increased flexibility concentrated in small cogeneration units (~ 1% objective per MW decrease in minimum mode)
Curtailment is insensitive to minimum mode (of tested range)
22
Validation80%, 90% cogen scenarios with distribution of actual Jan-Mar 2011
daily production
Authors’ calculation based on CEC monthly and SERC daily electricity production totals
Validation (2)
23
Jan Feb Mar Apr May Jun AvgHeilongjiang
19.2% 20.2% 22.3% 15.9% 2.7% 0.8% 13.5%
Jilin30.5
% 34.8% 42.5% 30.3% 19.5% 11.0% 28.1%
Liaoning23.6
% 20.4% 19.1% 13.8% 3.5% 1.4% 13.6%E. Inn. Mong.
24.1% 27.9% 23.6% 22.3% 12.7% 6.1% 19.4%
Wind curtailment (generation) by province (2012H1)
Source: China Association of Agricultural Machine Manufacturers
24
Discussion
• Clustering method for multi-node systems have low aggregation errors for whole system, but potentially some issues with province heterogeneity
• Demonstrated methodology to measure “administrative congestion” and other regulatory impacts
• Potential for much broader suite of tests on coal unit flexibilities (need for better data on technical limits)
• Looking for further validation approaches
Thank you谢谢 !
Michael Davidson ([email protected]) This work was supported by the founding sponsors of the China Energy and Climate Project, Eni S.p.A., ICF International, Shell International Limited, and the French Development Agency (AFD). Financial support was also provided by the MIT Joint Program on the Science and Policy of Global Change through a consortium of industrial sponsors and Federal grants, including the U.S. Department of Energy. This work is also supported by U.S. DOE Integrated Assessment Grant (DE-FG02-94ER61937).
26
References
Davidson, M. R. (2014). Regulatory and Technical Barriers to Wind Energy Integration in Northeast China (M.S. Thesis). Massachusetts Institute of Technology.Hedegaard, K., Mathiesen, B. V., Lund, H., & Heiselberg, P. (2012). Wind power integration using individual heat pumps – Analysis of different heat storage options. Energy, 47(1), 284–293. http://doi.org/10.1016/j.energy.2012.09.030Kahrl, F., & Wang, X. (2014). Integrating Renewables into Power Systems in China: A Technical Primer - Power System Operations. Beijing: The Regulatory Assistance Project.Kahrl, F., Williams, J., Ding, J. H., & Hu, J. F. (2011). Challenges to China’s transition to a low carbon electricity system. Energy Policy, 39(7), 4032–4041. http://doi.org/10.1016/j.enpol.2011.01.031King, J., Kirby, B., Milligan, M., & Beuning, S. (2011). Flexibility Reserve Reductions from an Energy Imbalance Market with High Levels of Wind Energy in the Western Interconnection (No. NREL/TP-5500-52330). Golden, CO: National Renewable Energy Laboratory (NREL). Retrieved from http://www.osti.gov/scitech/biblio/1028530Palmintier, B. S., & Webster, M. D. (2014). Heterogeneous Unit Clustering for Efficient Operational Flexibility Modeling. IEEE Transactions on Power Systems, 29(3), 1089–1098. http://doi.org/10.1109/TPWRS.2013.2293127Van den Bergh, K., & Delarue, E. (2015). Cycling of conventional power plants: Technical limits and actual costs. Energy Conversion and Management, 97, 70–77. http://doi.org/10.1016/j.enconman.2015.03.026Zhao, X., Wang, F., & Wang, M. (2012). Large-scale utilization of wind power in China: Obstacles of conflict between market and planning. Energy Policy, 48, 222–232. http://doi.org/10.1016/j.enpol.2012.05.009