Minutes of Coordination Meeting Records NJH

194
Alawi Tunsi Establishment 500 Beds North Jeddah Hospital Project (9/2010 to 11/2010) Forward Note Dear All, In addition to weekly meetings, on remaining week days, daily Technical Coordination & Output Review Meetings were also conducted. Only verbal records were noted for next day reviews. About 120 sittings were conducted on an average one hour a day. Communication Records: Minutes of Weekly Progress Review & Coordinati on Meetings This ‘Minutes of Meetings or formal communications’ with Team members & Management included within this document, give a factual history for a small period of a project whereon, I 1 of 194 6/16/2022 P Eng Suraj Singh PM

Transcript of Minutes of Coordination Meeting Records NJH

Page 1: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Forward NoteDear All,In addition to weekly meetings, on remaining week days, daily Technical Coordination & Output Review Meetings were also conducted. Only verbal records were noted for next day reviews. About 120 sittings were conducted on an average one hour a day.

Communication Records:

Minutes of Weekly Progress Review &

Coordination Meetings

This ‘Minutes of Meetings or formal communications’ with Team members & Management included within this document, give a factual history for a small period of a project whereon, I worked as Project Manager. Simple Communication English language has been used.

Objective is to educate fresher & budding engineers to apprise about practicalities on job communications for virtual interactions.

Separate document shall be published covering Circulars.

Eng Suraj SinghProfessional Engineer [email protected]

1 of 128 4/11/2023 P Eng Suraj Singh PM

Page 2: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Minutes of Coordination Meeting dated 26.8.2010 held in meeting room @ 10.30 amAgenda1 Introduction by new Project Manger & New incoming Engineers2 Introduction by the Engineers & Managers on site3 Areas of responsibilities shared & staff with them4 Management plan to be introduced5 Areas organization to be reviewed6 Invitation of comments about organizational improvement7 Information about balance works List making8 Site supervision improvement / rework avoidance9 Arabic translation of notes/documents. Responsibility?10 Any other issues to discuss.

Balance WorksPlease identify all balance works to go room wise / area wise in coordination with Quantity Surveyors. QS should be clear about all such works to quantify all requirements.This requirement is very significant to understand future materials procurement & manpower requirement.This information must be treated on top priority.Please, identify all missing information that are urgently required both from client as well as from Head office.The following Engineers were Present

Present in the meeting are:1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning3. Eng Mohammed Saed 4. Eng Morsi Usman Civil Planning5. Eng Abdul Rahim Ambrosio Civil Engineer6. Eng Abdur Rahman Civil Engineer7. Eng Hafiz Shakeel Ahmad Siddiqi Quantity Surveyor8. Eng Syed Atif Zia Quantity Surveyor9. Architect Jamel Tomawis10. QA/QC Zaheer Ahmad Ansari11. Architect Osman Abdel Aleem12. Eng Benny Escobar Jr13. Eng Nathaniel Tolebo14. Eng Sahadevan Nair Electrical Engineer15. Eng Rashid Khurshid Electrical Engineer16. Eng Md Aijaz Hussain Mechanical Engineer17. Eng M Rajab Mechanical Engineer

2 of 128 4/11/2023 P Eng Suraj Singh PM

Page 3: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Proceedings:IntroductionNew PM, Head of Planning, Mechanical/Quality/ QS Engineers introduced.All existing personnel on project introduced also.

1. Safety issue was raised with request that staff was seen working without Personal Protection Equipment PPE. Protection should be respected.

2. Many areas at high levels were left without safeguard rails to allow fall of any worker. Such areas should be provided with temporary rails using old scrap materials.

3. Any person from site can be trained to look after safety affairs in general.4. Quality System does not appear to be in force on site. Quality plans such as safety

QC, Documents controls are being worked out that shall be implemented soon.5. Implementation of this system shall help run project smoothly avoiding rework

maintaining quality.

Site OrganizationProposed organization chart was circulated for comments to be suggested to head of planning.

DCC Hamid looking after work oc documents control shall control all technical & engineering transmittals & co ordinations.

Supervision issuesHas been observed that certain workers on site use mobile phones for watching video & sit on site wasting time. This practice has to be avoided by the site staff. Close watch is required. Material wastage is also to be avoided as seen that cement bags were left open.

Out putNoted that workers did not give adequate standard out put on excuse of delayed salaries release which practice is not acceptable. Management is informed to look into the matter.

Dry wallsIssue taken up due to quantities quantification requiring assistance from Survey section. Survey section is requested to coordinate & support as decision was taken.

ScheduleSince responsible dedicated planner has joined the team, all feed back respecting balance works & other information be handed to him. Decided period to complete the project is 7 months only. More foremen were demanded to be mobilized, head of planning to look into the issue.

3 of 128 4/11/2023 P Eng Suraj Singh PM

Page 4: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Site coordinationAgreed that weekly meeting should be held on Tuesday to cover all issues on site requiring coordination in addition to act on the minutes of the meeting with consultant.

Approved/Unapproved drawingsEng Gemil would issue the lists for reference.

Meeting conducted by HO Buildings Projects Manager & Coordinator 25.8.2010 @ 1300 hours

Landscape1. Complete coordination must be carried out to attack on the entire landscape.2. All required sections should be looked into.3. All services issues be charted out.4. Zonal wise plan should be charted out by the Head of planning with support from

all related engineers.

Out put1. In case of extra than specified or fixed quantities, relevant worker shall be

awarded bonus on extra quantities done.

2. Items such as helmets etc can be procured & voucher submitted for reimbursement of payments.

Scope:1. Mosque is not in the scope of work for the time being.2. STP is also not in the scope.3. Certain issues on OP & KC are to be investigated

All personnel to work as a member of team without any nationality consideration.Transportation to new engineers about purchasing food etc would be effected which Eng Mohd Saed would manage.

All materials arriving on site should be inspected directed from quality criteria & if not to mark, can be returned while after receipt, inspection by the consultant must be managed immediately for clearing payment issues.

Eng Usman shall refine new office for Adhoc PM Eng Suraj Singh for smooth use.

New Computers have been ordered.

Meeting with Curtain wall Sub Contractor dated 26.8.2010Present ATE Eng Osama, Eng Suraj, Eng Vishram Dev, Eng Gemil, Eng Walid(sub contractor)

4 of 128 4/11/2023 P Eng Suraj Singh PM

Page 5: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Automatic sliding doors cannot be provided by him.Structural steel supporting system for the curtain walls cannot be designed & provided by him.

Eng Jamael to deliver him certain details on Saturday.

Recorded by Eng Suraj Singh PM

Distribution to all Engineers & Managers working on site Copied to Head Office/ Buildings Project Manager & Coordinator/ Dr Tunsi

Minutes of Coordination Meeting dated 28.8.2010 held in meeting room @ 10.00 am regarding coordination of Landscaping & external works

Present in the meeting are:1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning3. Eng Mohd Saed CM Not available 4. Architect Jamel Tomawis5. Eng Ibrahim6. Eng Mohd Jamil7. Eng Abdur Abdul Rahim Ambrosio8. Eng Islam Surveyor9. Eng Sahadevan Nair Electrical Engineer10. Eng Rashid Khurshid Electrical Engineer

Proceedings:

Landscape & external services works are required on top priority basis.

Coordination Issues:1. Layout drawing giving levels is approved.

2. Services routes are approved according to Eng Jameal

3. Details of services in standard section forms are not available.

4. Details of services in particular Fire |Fighting, Water supply & Irrigation are required & can be requested to be provided by Head Office.

5. Civil section to provide various sections relating kerb stones etc for incorporation.

5 of 128 4/11/2023 P Eng Suraj Singh PM

Page 6: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

6. All these sectional details require consultant’s approvals.

Following activities can be taken up for time being:1. Marking of lines respecting

2. Electrical in zone 2 partly

3. Marking of manholes for mock up & others

4. Marking of street light poles.

5. Marking of sewer lines

6. Matter to be discussed with Eng Taha & Eng Mohd Saed CM

Planning to chart out directing programme to the construction team so that it can be smoothly enforced on site.

1. All zones were discussed for cause of fill.

2. All site entry gates are to be checked whether or not, entries for heavy trucks can be permitted.

3. Filling has to continue & deliveries of fill material should continue without break.

4. Laboratory for field density test is expected probably on 29.8.2010.5. Work request to be submitted for relevant areas.

Recorded by Eng Suraj Singh PM

Distribution to all present Engineers & Managers.

Copied to Head Office/ Buildings Project Manager & Coordinator/ Dr Tunsi

Next meeting depending on the progress of activities.

Weekly Project Progress Review Meeting

Present in the meeting are:1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning

6 of 128 4/11/2023 P Eng Suraj Singh PM

Page 7: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

3. Eng Mohammed Saeed CM Not Present4. Architect Jamel Tomawis5. Architect Osman Abdel Aleem Not Present6. Eng Morsi Usman Civil Planning Not Present7. QA/QC Zaheer Ahmad Ansari8. Eng Benny Escobar Jr9. Eng Nathaniel Tolebo10. Eng Abdul Rahim Ambrosio Civil Engineer11. Eng Abdur Rahman Civil Engineer12. Eng Hafiz Shakeel Ahmad Siddiqi Quantity Surveyor13. Eng Syed Atif Zia Quantity Surveyor14. Eng Sahadevan Nair Electrical Engineer15. Eng Rashid Khurshid Electrical Engineer Not Present16. Eng Md Aijaz Hussain Mechanical Engineer17. Eng M Rajab Mechanical Engineer Not Present18. Eng Mujeeb Mechanical Engineer19. Eng Waleed Mohammad Surveyor

S #

Minutes Description Action By

1 Labour Working Issues/Output/Time Keeper – Checking on site. Warning to painters

Due to not finding all reported workers available on site during visits, all workers to be checked at site shift joining time in morning on 1.9.2010. Time keeper to support checking.

On complaint by Foreman Gulzar, paint foreman, 8 painters were warned verbally to produce required output or action would be taken against them.

All foreman have to check & report all outputs by quantities daily which engineers have to enforce strictly.

Balance quantities are to be resolved for estimation for procurement & assessment of additional workforce required.

Time keeper

Foremen/Engineers

Engineers2 Night Work During Ramadan period

As attempted by the site team, night working has not been too successful except by subcontractors. Strength available at night is not considerable. Presence of engineers at site is not well returned

CM/Management

3 Bus trip & time controlsOnly one micro bus is available that makes 2 or 3 trips for all shifts. It is not practically feasible by engineers to be present ahead of workers to check them in morning shift.Moreover, condition of bus us worse to show a glimpse of any reputed construction company. It packs staff. Engineers should be provided a separate transport to maintain dignity. Joining shift late too is not a preferred option.

CM/Management

4 Stores issues-Material checks All

7 of 128 4/11/2023 P Eng Suraj Singh PM

Page 8: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

While making procurement requisitions, the originator should refer to stores incharge to make sure that the requested item is not available. Duplicate procurement should be avoided as it blocks cash flow.While materials arrive at site stores, store keeper must refer to the originator for inspections by engineer & then engineer to arrange inspection by consultant if so required. Item should then be delivered to originator.Quantities & qualities must be checked. Also noted that it takes weeks for procurement which impacts the works progress. Work is hampered even by smaller items.

5 Equipment maintenance & avoidance of idlingNoted that due to delayed delivery of fill materials, some idling of shovel happened that requires avoidance.Requisition for required equipment must be made quiet in advance to facilitate timely delivery.

All

6 Engineering Submittal IssuesMany submitted items of Electromechanical require follow up such as BMS/FM 200 etc.Submissions are delayed due to delayed processing.Certain submission for example Ramps were made in 8/2010 but not tractable which requires resubmission.But due to non availability of printing ink, hard copies cannot be taken. It is ill state of affairs.Submissions have to be expedited

All

7 Issues on meeting with consultantsAll records with secretariat to be checked for status for follow up. Many items require attention.Many documents require translation.

PM/CM

8 Quality System Issues / Organisation Chart etc.It is under home work preparationPlanning is being schedule by head of planningOrganisation chart imported comments from Site QS who have been working on materials take off from drawings & site. Comments are that on c hart, Quantity Section is not indicated. QS & Project Coordinator/designers have to coordinate for technicalities. Contractual matters & priorities of valuations to be dealt on management decided priority basis

PM/ Head of Planning

PC/QS

9 Quality Control Issues/rework/water/remedial actionsQC Engineer has bee authorized to control all areas where quality lapse is reported or discovered & issue report to PMSite requires certain plastic drum containers for site water storage for works.All items of finishing & structures require quality checks to avoid complication while handing over project.Main building repairs, Service building repairs etc all require

QC/Engineers/PM/CM

8 of 128 4/11/2023 P Eng Suraj Singh PM

Page 9: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

attention.QC has to notify to all engineers/foreman about remedial actions. This point has already been recorded by consultant.Fill material test FDD conducted on site on 30.8.2010 are reported approved for part areas. Many ac ducts on roof are seen supported on wooden frames /props that require action.At many areas insulation items require remedials

10 Quantity Surveyors Issues-Land Surveyors assistanceSince QS are overloaded currently to compute finishing items for procurement purpose, it is suggested that engineers could help them provided their site job is not effected adversely. In addition to that available 2 land surveyors on site are not dedicatedly occupied. They are asked to assist QS in producing required quantities both from site as well as from drawings. Meeting to be conducted

PM/CM/QS/Surveyors

11 Schedule for 7 months & landscape schedule planNew schedule for 7 months & landscape schedule are being processed.Reported system to base on quantities & not on % .All reporting of output should base on quantities of work.

HOP/PM/Engineers

12 Landscape & demobilization of site establishmentA meeting conducted by HOP on 30.8.2010 to finalise landscape schedule.Ramps around buildings where damaged concrete protection/waterproofing needs repairs, coordination be done with subcontractor.Offices require relocation to Single Female areas being an urgent issue-to be planned.Deliberation is required for other areas clashing with landscape such as stores etc. Scrap steel |& form materials.Otherwise, full scale attack on landscape is not feasible.

HOP/PM/CM

13 Buildings Services issuesServices require complete input. Details not on table. Work out.Electrical FM informed that 40 electricians are available on site. To be verified 10 to 12 duct workers are available. Manpower requisition requires attention to speed up activities.

PM/Electromech

14 Safety issues-Site cleaning-PPENo site person has been identified to check fall prone areas. Temporary rails guards are required there. We cannot risk lives.

All

15 Previous meeting minutes discussionsBalance works requires urgent attention to check available workforce & new requirement. Must be submitted in details.Supervision on site is not to mark. FM /Engineers have to improve supervision. Engineers have to control FM & FM their workers. Time

9 of 128 4/11/2023 P Eng Suraj Singh PM

Page 10: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

wastage practice has to stop.Work allocation should be given regularly in advance.Materials be made available in time.Material wastage is not allowed.Document control is still poor. New experience person should be posted to avoid record messing up.Remedial works on dry walls have to be taken up & other measures with subcontractor are required.Appears that sites require more civil foreman to control works. Some reshuffling is also required.Landscape is in process of moving. Drawings are to be submitted for details approvals.Manhole mock up sample is required.

16 Any other businessNew staff do not have any transport for going to any place.Staff joining attendance should be signed at secretariat office & not at gate.Some transport should be available for staff on Fridays.Eng Usman conducted meeting with vendor for Automatic doors on 30.8.2010

17 Next Meeting7.9.2010 @ 10.30 am

Recorded by Eng Suraj Singh PM

To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME/Buildings Project Manager & Coordinator/ Dr Tunsi

Weekly Project Progress Review Meeting

Present in the meeting are:1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning3. Eng Mohammed Saeed CM Not Present4. Architect Osman Abdel Aleem 5. Architect Jamel Tomawis6. Eng Morsi Usman Civil Planning Not Present7. QA/QC Zaheer Ahmad Ansari8. Eng Benny Escobar Jr Not Present (apology)9. Eng Nathaniel Tolebo Not Present10. Eng Abdul Rahim Ambrosio Civil Engineer11. Eng Abdur Rahman Civil Engineer

10 of 128 4/11/2023 P Eng Suraj Singh PM

Page 11: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

12. Eng Hafiz Shakeel Ahmad Siddiqi Quantity Surveyor13. Eng Syed Atif Zia Quantity Surveyor Not Present14. Eng Sahadevan Nair Electrical Engineer15. Eng Rashid Khurshid Electrical Engineer Not Present

(Vacation)16. Eng Md Aijaz Hussain Mechanical Engineer17. Eng M Rajab Mechanical Engineer Not Present

(Transferred)18. Eng Mujeeb Mechanical Engineer Not Present19. Eng Waleed Mohammad Surveyor Not Present

Observation Note: Non attending progress review meeting is a matter of serious concern. Noticed that many responsinle engineers & certain manager do not attend this important meeting meant for making site & work decisions promptly. It is advised to all concerned that they schedule out in accordance to comply with requirement of this meeting.

S #

Minutes Description Action By

1 Labour Working Issues/Output/Time Keeper – Checking on site. Warning to painters

Planned attempt to check workers’ head count failed for the reason that I could not reach to site in time in morning on 1.9.2010 due to transport non availability in time. Shall be checked after Id.

On complaint by Foreman Gulzar, paint foreman, 8 painters were warned verbally to produce required output or action would be taken against them. It has been noted that these workers are spoiling site environment & others too are not doing to required production mark. Even, Eng Usman senior architect intends these to be removed from site. Action to be initiated immediately. These were also given an opportunity in past but, no improvement has been reported.

It is not feasible for engineers to report daily output but they may produce weekly. Daily activity based report can be provided.

Balance quantities are to be used from planning department that is available on reporting.

Time keeper

PM/CM

2 Night Work During Ramadan periodAs attempted by the site team, night working has not been too successful except by subcontractors. Strength available at night is not considerable. Presence of engineers at site is not well returned. Night work may be adopted after Id by reorganizing work for 12 hours shift for which a proposal advisory has been sent to head office for approval.Schedule of staff regarding their contract working time is available with Mr Noor.

PM/CM/Management

11 of 128 4/11/2023 P Eng Suraj Singh PM

Page 12: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

3 Bus trip & time controlsOnly one micro bus is available that makes 2 or 3 trips for all shifts. It is not practically feasible by engineers to be present ahead of workers to check them in morning shift.Moreover, condition of bus is worse to show a glimpse of any reputed construction company. It packs staff. Engineers should be provided a separate transport to maintain dignity. Joining shift late too is not a preferred option.Site should demand a coaster in addition to current bus so that all site staff reach in time. Procurement process may be initiated.

PM/CM/Management

4 Stores issues-Material checksSite has witnessed acute shortage of cash not allowing to make local purchases. Eng Usman suggested an availability of site imprest fund of at least one hundred fifty thousand monthly so that materials urgently required & hire of machines as well as water payment could be cleared.

Many vendors are not delivering materials due to non payments. Site store computer was sent for repairs long back yet, not returned. No details of updated stock are available.

Technical office should be established to resolve store materials issues. From head office certain relevant staff should be mobilized to check the required & unrequired materials issue out of available materials & unrequired materials be returned to other locations.

PM/CM/Management

5 Equipment maintenance & avoidance of idlingAll equipment working on site should not be allowed any idling as it costs a lot. All logs of equipment working should be filled by responsible engineer & not by any helper as is being effected.

PM/CM

6 Engineering Submittal IssuesSince 31.8.2010, status of submission is as followsDetails of Submittals effective 1.9.2010Submitted to ConsultantFF Fire Fighting Layout- Kidney Centre Building

31.8.2010Sample approval request of Telecom Distribution Box TAC

31.8.2010Generator Room FM200 Fire Extinguishing System GF Service building 08 31.8.2010BMS Layout Pump room

1.9.2010Main building roof floor BMS Layout HVAC routing

1.9.2010Typical details of Manhole Sump pit

1.9.2010Main building Roof deck floor BMS Layout HVAC routing

All

12 of 128 4/11/2023 P Eng Suraj Singh PM

Page 13: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

1.9.2010BMS layout GF @ Service building

1.9.2010

Prepared only-\to be submitted after holidaysPump room details layout @ soft & treated water tank Service buildingRamp & shop details Main Building 01Main building GF expansion joint detailMain building Details of proposed CMU walling in front entranceMain building01 Anesthesia pump room (part 78)Ramps & steps submitted on 24.8.2010 missed.Design prepared on 2.9.2010 but, could not be checked by construction that delayed its submission. After Id.FM 200 reported approval.

Remarks:Main Building Main Entrance above canopy steel work pending. Material is not available. Procurement to be expedited. Aluminum cladding cannot proceed on main entrance without finishing steel work.(Talab Sera orders)

Main Entrance Structural Computation.Consultant requires design calculations from subcontractor of curtain wall.Technical requirements:Design of loading for rafters.Design of steel beam for long span.Web members/thickness of steel/welding connection.Foregoing being consultants’ comments on submittal.Elevators;Mechanical section conducted a meeting with consultants on 5.9.2010 regarding various comments on subcontractor submittal about fixing arrangements, details with structural core walls fixing, protection of rails from corrosion & hoist check after installation. Comly with comments.

7 Issues on meeting with consultantsAll records with secretariat to be checked for status for follow up. Many items require attention.Many documents require translation.

PM/CM

8 Quality System Issues / Organisation Chart etc.Project Coordinators are required for Architectural as well as allied services.

Eng Jameil & Eng Usman have been coordinating jointly for architectural & structurals all.

PM/ Head of Planning

13 of 128 4/11/2023 P Eng Suraj Singh PM

Page 14: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Electromechanical sections are requested to explore possibility who can competently serve for allied services coordination that is an urgent requirement.Issue is to be raised to management.

All copies of approved documents in complete should be made available on site for ready references by the site electromechanical team. This is also an urgent requirement.

Electromechanical

9 Quality Control Issues/rework/water/remedial actionsQC report regarding issue of lintels installation for raising door height on tower was taken up while Eng Jameil informed that it shall be remedied only at later stage. Currently only finishing is going on just to make look good.

Curing:Foreman have to arrange for the curing water to be filled into site drums. Water drums are now available on site.

Drainage system: According to CM Eng Mohd El Saed, DGIP & GC Eng Sayeed decided to lower the invert levels of manholes by 400 mm. Excavations for lines have been started. It is also recommended that in case, the final line is to be connected to the external manholes drainage, IL of that Manholes should also be investigated at this stage so that any incompatibility could be resolved.

Compaction:On 7.9.2010, road roller was noticed working for compaction immediately after spraying water. It spoiled some surface that was already tested. Water should be allowed to percolate first. Consultants QS commented on site.

PM/CM/Engineers

10 Quantity Surveyors Issues-Land Surveyors assistanceNew QS is unable to perform work efficiently due to non availability of computer as he has to share only.Wall guards & corner guards quantification finished.Expansion joint quantification finished but basement area to be resolved. Coordination with consultants.Bathrooms partitions quantification going on- After Id.Staircase Granite Eng Jamael & Attif to coordinate.Border for buildings quantification finish but, main entry & elevator.Shop drawing Signage coordination with Eng Ali Saeed TABA- After IdBorder Marble delivery-Mulhen Co Fady delayed- could be on shipment.Shop drawings entrance, staircase, ramp under submission.

PM/CM/QS/Surveyors

14 of 128 4/11/2023 P Eng Suraj Singh PM

Page 15: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Sample colour all buildings effected- Inspection / RFI Eng Usman to coordinateCurtain wall OPD Tower Eng Ealeed Matbouli –No responseCladding: Intec Mohd Aslam Aleem for raising workforce- OngoingDrywalls quantities for payment certificate-progressing. Site measurements ongoing. (urgent)Cost to complete the remaining works are required for budget requirement. This is for all disciplines.Materials delivered to site are being processed for consultants approvals.Skylights coordination issue being done by DG &b IC & GC.Metalco- Letter sent by Eng Usman-No response. Material on site.Weekly report submitted by planner Eng Morshid but after review, asked to resubmit incorporating many issues. Revised report received on 7.9.2010.

11 Schedule for 7 months & landscape schedule planNew schedule for 7 months & landscape schedule are being processed. Landscape schedule to be finalized after the main schedule is completed. Slow speed is due to non availability of computer with head of planning.Reported system to base on quantities & not on % .All reporting of output should base on quantities of work.

HOP/PM/Engineers

12 Landscape & demobilization of site establishmentA meeting conducted by HOP on 30.8.2010 to finalise landscape schedule.Most minutes recorded on meeting dated 31.8.2010 are still in action stage & to be taken up after Id.Kerb Stones & Interlock blocks to be submitted after Id only.Road work subcontractor not decided yet.Landscape design work progressing.Drainage work is in progress.Detailed discussion in next meeting. Meetings clubbed.Waterproofing subcontractor was asked to repair damaged areas of protection membrane at adjacent proposed ramps.Relocation of offices to Single Females requires main electric cables procurement. Plumbing ongoing. Cheap carpets may be required for flooring. Relocation next two weeks possibly.Removal of scrap reinforcing steel & shuttering materials from rear part of site for landscape clearance areas.

HOP/PM/CM

13 Buildings Services issuesServices require complete input. Details not on table. Work out. EME should table all requirements of site..

PM/Electromech

14 Safety issues-Site cleaning-PPENo site person has been identified to check fall prone areas. Temporary All

15 of 128 4/11/2023 P Eng Suraj Singh PM

Page 16: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

rails guards are required there. We cannot risk lives. Safety on site is still not intact.Cleaning not moving fast.

15 Previous meeting minutes discussionsBalance works from planning.Supervision on site is not to mark. FM /Engineers have to improve supervision. Engineers have to control FM & FM their workers. Time wastage practice has to stop.Work allocation should be given regularly in advance.Materials be made available in time.Material wastage is not allowed.Document control is still poor. New experience person should be posted to avoid record messing up.Remedial works on dry walls have to be taken up & other measures with subcontractor are required.Manhole mock up sample is required.

All

16 Any other businessAccommodation:Noticed that certain workers join the site for many days but, are not allotted their accommodation. They have to wander here & there. This practice has to stop.

Insurance company representative visited site & collected relevant project information on 4.9.2010.

Certified welder Parvez Ahmad test procedure certificate has expired on 2.9.2010. Revalidation is required.

Eng Abdul Rehman looking Single Female can be utilized for other areas as he is not 100 % dedicated to that building.Eng Jamael reported that he received one CD on 6.9.2010 that could be released by head office one year back that could help design section to clear backlog.One CD for tender drawings was provided to PM but no computer is available. Cannot be used.New staff do not have any transport for going to any place.Staff joining attendance should not be signed at gate.Announcement was made for Id holidays 9.9.2010 to 12.9.2010.Announcement was made for a lost time recovery proposal forwarded to head office for 12 hours working on site for the remaining period of contract duration.Some transport should be available for staff on Fridays.ID GreetingsWished a happy Mabarak Id festival to all.

17 Next Meeting21.9.2010 @ 10.30 am

16 of 128 4/11/2023 P Eng Suraj Singh PM

Page 17: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Recorded by Eng Suraj Singh PM

To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME/Director General For Implementation of Projects & General Coordinator

Chairman Dr Tunsi

Electrical Mechanical Engineers Meeting

Present in the meeting are:1. Sheikh Al Sayed Alawi Tunsi ATE Chairman 2. Eng Suraj Singh Project Manager3. Eng Vishram Deo Head of Planning4. Eng Mohammed Saeed CM5. Architect Jamel Tomawis Partly6. Eng Benny Escobar Jr Partly7. Eng Mujeeb Mechanical Engineer Services Coordinator8. Eng Md Aijaz Hussain Mechanical Engineer9. Eng Mohd Rajab Mechanical Engineer Transferred10. Eng Mohd Gamel Mechanical Engineer11. Eng Sahadevan Nair Electrical Engineer12. Eng Ahmad Ibrahim Electrical Engineer

Chairman ATE chaired this meeting objective of which was to introduce the electromechanical departments to the New PM & The Head of Planning or project the updated status of documents on project.S #

Minutes Description Action By

1 Services CoordinatorOut of all 6 engineer, 2 from Electrical section & 4 from

mechanical section, competent engineer to look after the coordination of all services disciplines was to be identified.

Eng Mujeeb Mechanical engineer Agreed to share services coordination responsibility.

He is looking after HVAC as well. He has to coordinate with all engineers in both section &

update the PM on status of all documents. He has to further coordinate with the architectural coordinator

Eng Jamiel.

PM/CMServices coordinator

2 Landscape & External works:An emphasis was given on the external work coordination & in

17 of 128 4/11/2023 P Eng Suraj Singh PM

Page 18: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

conjunction with Eng Jamiel senior architect, complete details are to be decided very fast.Mechanical section to provide information about the mechanical requirement for the sump pits on 15.9.2010

3 Documents:Electrical Informed that all shop drawings are approved.As built drawings have to be submitted but comments from electrical section that these were not received by consultants being the work not completed. Mechanical Informed that fire fighting drawings were submitted for 3 buildings Single female/OPD/KCA list of all drawings & materials approved & updated are required for planning & follow up. Noor has dealt with update work of all such records. Noor update pending for a couple of months. Required urgent upgradation using Bilal & Eng Beny.

PMCM/Services coordinator

4 Miscellaneous:Planning demanded list of balance works, variation of works, list of rework areas. All details to be provided in laision with Noor & Electromechanical engineers.

Coordinator/PM/HOP

5 Area of Responsibilities:Eng Mujeeb to look after Coordination & HVACEng Aijaj Hussain to look after Fire Fighting, Elevators, Sump valves, electrical pump room etc & general QCEng Gamel FF & plumbingEng Nair to look after load calculation, general supervision & site supervision.Eng Ahmad Ibrahim looking after site supervision..

Named Engineers

6 Next Meeting to club with Progress review meeting 21.9.2010 @ 10.30 am

Recorded by Eng Suraj Singh PM

To all Presents/ CM/ Planning Head/Copied to Head Office/ Electrical/Mechanical/Eng Sayeed Behairi

Chairman Dr Tunsi

Architectural Civil Engineers Meeting

Present in the meeting are:1. Sheikh Al Sayed Alawi Tunsi ATE Chairman & Dr Tunsi2. Eng Suraj Singh Project Manager3. Eng Vishram Deo Head of Planning

18 of 128 4/11/2023 P Eng Suraj Singh PM

Page 19: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

4. Eng Mohammed Saeed CM5. All Architectural & Civil Engineers6. All Quantity Surveyors

Chairman ATE chaired this meeting objective of which was to introduce the All present Engineers to the New PM & The Head of Planning & project the updated status of documents & material on project.S #

Minutes Description Action By

1 IntroductionFormal introduction made by the Chairman about the new administration for the project & all were advised to fully extend their supports to the new officials.

All

2 Documents & Materials All buildings:All engineers were requested to provide all details about the materials, drawings status & all other pending requirements for balance of works.

Most drawings approved. Various materials to be followed. Ceiling, Vinyl, Marble border, strip ceiling, cubicles, sign boards, kerb stones, interlocks & many other to be followed.

Particularly, roofing access details are required on an urgent basis. Surveyors shall prepare as builts of plinths on roof.

All Engineers

3 General:All have to note that project duration is left only for 6 to 7 months. All pending operations are to be completed in this duration.

All materials & other resources have to be completed with full follow up.

There should be no lack on dealings with all issues. All updates of documents are required.

Translation of BOQ is under preparation by Mr Noor.

Remaining documents shall be tried for translation from Market.Offices are required to be shifted to Single Female soon.

All Engineers

4 Valuation:QS from head office dealing with valuation has to attend a meeting on site with PM & QS for site involvement with valuation. Pending valuations must be processed with efficiently.Procedures for all valuation have to be formalized immediately.

PM/QS

5 Quality Control: InternalQC is required to be involved for inspections on site.QC should prepare procedures for engineers references.

PM/QC

19 of 128 4/11/2023 P Eng Suraj Singh PM

Page 20: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Rework is not appreciated in future.6 Local Purchases

All bills are to be also signed by PM.Adequate cash has to be maintained on site.Bills are to be submitted when expenses reach 50000 Riyals.All immediate purchases to be effected on site.

All

7 Additional ManpowerTo meet shortage of site workforce, additional workforce to be arranged from market.

PM/CM

8 Next Meeting to club with Progress review meeting 21.9.2010 @ 10.30 am

Recorded by Eng Suraj Singh PM

To all Presents/ CM/ Planning Head/Copied to Head Office/ Eng Sayeed Behairi

Foreman Meeting

Present in the meeting are:1. Sheikh Al Sayed Alawi Tunsi ATE Chairman & Dr Tunsi2. Eng Suraj Singh Project Manager3. Eng Vishram Deo Head of Planning4. Eng Mohammed Saeed CM5. All Foreman

Chairman ATE chaired this meeting objective of which was to introduce the All present Engineers to the New PM & The Head of Planning S #

Minutes Description Action By

1 IntroductionFormal introduction made by the Chairman about the new administration for the project & all were advised to fully extend their supports to the new officials.

All

2 PM instructed all foreman to check that no worker on site below foreman level should use mobile.

No Cement & other material should be allowed to be wasted.

All works should be done with quality.

All work out put should be recorded & signed by the concerned engineers.

Those who get extra work in 8 hours more than standard, those workers shall be paid extra amount as bonus.

20 of 128 4/11/2023 P Eng Suraj Singh PM

Page 21: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Those who do not fulfill the standards shall be punished.

3 General: All have to use safety helmets etc. Procedure to procure is in progress.

All Foremen

4 Additional ManpowerIt shall be arranged from market & foremen general shall be involved for support. Trial shall be made on site & if approved for quality, further contract shall be discussed with Eng Sayeed Behairi.

PM/CM

Recorded by Eng Suraj Singh PMCopy to all engineers & those officials presentPost on siteCopied to Head Office/ Eng Sayeed Behairi

Weekly Project Progress Review MeetingCC Head Office / Eng Sayeed Behairi بحيري / السيد المهندس السيدCC Chairman / أسعد علوى السيد تونسيPresents in the meeting are:

1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning3. Eng Mohammed Saeed CM Partly4. Architect Osman Abdel Aleem 5. Architect Jamel Tomawis6. QA/QC Zaheer Ahmad Ansari7. Eng Benny Escobar Jr Leaving8. Eng Nathaniel Tolebo Sick9. Eng Abdul Rahim Ambrosio Civil Engineer10.Eng Abdur Rahman Civil Engineer11.Eng Hafiz Shakeel Ahmad Siddiqi Quantity Surveyor Busy on valuation12.Eng Sahadevan Nair Electrical Engineer13.Eng Syed Atif Zia Quantity Surveyor Busy on valuation

Eng Rashid Khurshid Electrical Engineer Vacation14.Eng Md Aijaz Hussain Mechanical Engineer15.Eng Mujeeb Mechanical Engineer 16.Eng Yasser Head Office, Guest Presence

Information: Meeting with consultants scheduled for 22.9.2010 @ 10 am.

S # Minutes Description Action By

1 Labour Working Issues/Output/Time Keeper – Checking on site.

21 of 128 4/11/2023 P Eng Suraj Singh PM

Page 22: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

All have to joining shift in time & keeping in view transport problem, 7.30 am, time sheet to be closed. 2.30 pm, time sheet to be closed.

All directed to check output in line with salaries paid. Higher wages mean higher production.

Balance quantities are to be produced by engineers of all disciplines. Responsibility goes to relevant engineers. Cost to complete the remaining project is very urgently required to allot budget.

Daily meetings conducted effective 16.9.2010.

Improvement on production is required urgently.

Gradually production increases but, in certain cases not to higher standards.

All engineers & foremen have been directed to contact their known resources to mobilize workers to site for tiles, marble & other items like screed.

All

EngineersPM/CM

2 Night Work 12 hours shift was not accepted by management but, additional work after daily output shall be considered in place of overtime depending on the wage rates. Circular was already on record in that direction.

All/Management

3 Bus trip & time controlsManagement has agreed to provide one coaster bus for this site to resolve staff transportation problem..

PM/CM/Management

4 Stores issues-Material checksProcedure for materials demands & delivery has been circulated to all concerned.

Procedure about materials issue shall be circulated soon.

PM/CM/Management

5 Equipment maintenance & avoidance of idlingAll equipment working on site should not be allowed any idling as it costs a lot.

All logs of equipment working should be filled.

Relevant engineer instructed to check all equipment working & in case of break down, immediate action is required.

PM/CM

22 of 128 4/11/2023 P Eng Suraj Singh PM

Page 23: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

6 Engineering Submittal IssuesSince 31.8.2010, status of submission is as follows

Details of Submittals effective 1.9.2010Submitted to Consultant

Drawings StatusService BuildingPump room Details Layout @ soft & treated water tank: Approved as noted

Main BuildingRoof Deck Floor BMS Layout HVAC routingRevise & resubmit

Roof floors BMS layout HVAC routingRevise & resubmit

Pump RoomBMS layout: Revise & resubmit

Service BuildingBMS layout GF: Revise & resubmit

Submittals MadeDiesel tank of boiler near soft water tank 14.9.2010Treated water pump Head calculation for Fuel Oil pump generator/boiler 14.9.2010

Main buildingPressure tank calculation for pump room 14.9.2010Filter tank sizing : 14.9.2010

DrawingsRamp & Step details 14.9.2010Main building GF expansion joint layout plan14.9.2010 Details of proposed CMU walling in front of Main entrance: Anethesia pump room

Service buildingPump room detailed layout @ soft & treated water

All

23 of 128 4/11/2023 P Eng Suraj Singh PM

Page 24: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

14.9.2010SamplesRequest for sample approval of granite cladding 19.9.2010As Built StatusKidney CentreFire fighting layout GF/FFRevise & resubmit

OPDFire fighting layout GF/Supervision Floor/FFRevise & resubmitFF Fire Fighting Layout- Kidney Centre Building

31.8.2010Sample approval request of Telecom Distribution Box TAC

31.8.2010Generator Room FM200 Fire Extinguishing System GF

Service building BMS Layout Pump room

1.9.2010Main building roof floor BMS Layout HVAC routing

1.9.2010Typical details of Manhole Sump pit

1.9.2010Main building Roof deck floor BMS Layout HVAC routing

1.9.2010BMS layout GF @ Service building

1.9.2010

Remarks:

Main Building Main Entrance above canopy steel work pending. Material is not available. Procurement to be expedited. Aluminum cladding cannot proceed on main entrance without finishing steel work.(Talab Sera orders)

Main Entrance Structural Computation.Consultant requires design calculations from subcontractor of curtain wall.

Technical requirements:Design of loading for rafters.Design of steel beam for long span.

24 of 128 4/11/2023 P Eng Suraj Singh PM

Page 25: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Web members/thickness of steel/welding connection.Foregoing being consultants’ comments on submittal.

Elevators;Mechanical section conducted a meeting with consultants on 5.9.2010 regarding various comments on subcontractor submittal about fixing arrangements, details with structural core walls fixing, protection of rails from corrosion & hoist check after installation. Vendor to resort action. Meeting scheduled.

7 Issues on meeting with consultantsAttachments to material submittal documents are not available.Consultants to be requested to provide all attachment copies for our record & use.

PM

8 Quality System Issues / Organisation Chart etc.Project Coordinators Eng Jameil & Eng Usman have been coordinating jointly for architectural & structurals all.

Electromechanical Eng Mujeeb has started working as services coordinator.

All copies of approved documents have to be provided.

PM/ Head of Planning

Electromechanical

9 Quality Control Issues/rework/water/remedial actionsQC engineers have been regularly working & reporting to management about lapses.

Everyday, day to day work meetings are conducted for all disciplines.

Curing:Foremen have to arrange for the curing water to be filled into site drums. Any lapse not be be tolerated.

Drainage system: According to CM Eng Mohd El Saed, DGIP & GC Eng Sayeed decided to lower the invert levels of manholes by 400 mm. Excavations for lines have been started. It is also recommended that in case, the final line is to be connected to the external manholes drainage, IL of that Manholes should also be investigated at this stage so that any incompatibility could be resolved.

Follow up:

All

Engineers

25 of 128 4/11/2023 P Eng Suraj Singh PM

Page 26: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Dropped levels were not coordinated for the mechanical requirement & therefore, again, backfill is being done in the incorrect excavation line. Drawings for the invert levels are yet not approed. Drawings for manholes & sump pits are not approved.

EME/CM/PM

10 Quantity Surveyors Issues-Land Surveyors assistanceDiscussions could not be held due to their being busy with valuation. To be discussed later.

Previous records reproduced:Wall guards & corner guards quantification finished.

Expansion joint quantification finished but basement area to be resolved. Coordination with consultants.

Bathrooms partitions quantification going on- After Id.Staircase Granite Eng Jamael & Attif to coordinate.

Border for buildings quantification finish but, main entry & elevator.

Shop drawing Signage coordination with Eng Ali Saeed TABA- After Id

Border Marble delivery-Mulhen Co Fady delayed- could be on shipment.

Shop drawings entrance, staircase, ramp under submission.

Sample colour all buildings effected- Inspection / RFI Eng Usman to coordinate

Curtain wall OPD Tower Eng Ealeed Matbouli –No response

Cladding: Intec Mohd Aslam Aleem for raising workforce- Ongoing

Drywalls quantities for payment certificate-progressing. Site measurements ongoing. (urgent)

Cost to complete the remaining works are required for budget requirement. This is for all disciplines.

Materials delivered to site are being processed for consultants

PM/CM/QS/Surveyors

26 of 128 4/11/2023 P Eng Suraj Singh PM

Page 27: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

approvals.

Skylights coordination issue being done by DG &b IC & GC.

Metalco- Letter sent by Eng Usman-No response. Material on site.

11 Schedule for 7 months & landscape schedule planNew schedule is being prepared by the Head of Planning after deliberation with the consultants 7 shall be completed in 7 to 10 days.

HOP/PM/

12 Landscape & demobilization of site establishment

Kerb Stones & Interlock blocks to be submitted..Road work subcontractor not decided yet.

Landscape soft landscape excluded from scope according to Eng Yasser Head office.

Drainage work is in progress. All relevant drawings are required. Coordination between civil & electro mechanical is required on top profile.

Waterproofing subcontractor was asked to repair damaged areas of protection membrane at adjacent proposed ramps.No action-sub contractor to be forced to resume work

Relocation of offices New area opposite right compound wall under Ministry of Health is to be used as directed by Eng Sayeed Behairi.Proposal to be sent to Head Office.

CM

13 Buildings Services issuesAll issues are to be taken up in this meeting as wel as during daily production meeting that must give detailed outputs from site for scrutiny. Reports should cover all items of services & relevant coordination issue among them.

PM/Electromech

14 Safety issues-Site cleaning-PPESafety officer is not available on site. It is a must now. Chairman shall be contacted for this issue.

All

15 Previous meeting minutes discussionsBalance works from planning.

27 of 128 4/11/2023 P Eng Suraj Singh PM

Page 28: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Balance work is an issue. Eng Usman is not ready to work out quantities of this requirement. All were directed to work out quantities. QS are over occupied for valuation purpose. Remaining works are well known to Project site engineers. Assistance of Eng Abdul Rehman & Eng Imad could be deployed for this purpose.

Supervision on site is not to mark. FM /Engineers have to improve supervision. Engineers have to control FM & FM their workers. Time wastage practice has to stop. No lack of controls are acceptable.

Work allocation should be given regularly in advance.Materials to be made available in time.Material wastage is not allowed. Cement bags are seen open. It must stop.

Document control is still poor Procedures are to be established. Already started.

Remedial works on dry walls have to be taken up & other measures with subcontractor are required. Sub contractors are to be coordinated.

Manhole mock up sample is required. Designs not approved.

All

Relevant engineers

16 Any other businessJob descriptions:Foreman & engineers job descriptions issued from site constitution part of QA system.Other positions shall be issued soon.Meeting to be held to explain to relevant persons about their responsibilities.

Scrap materials: to be removed from site. About steel discussion to be made with owner.

Accommodation: New comers should immediately be accommodated.

Insurance company representative visited site & collected relevant project information on 4.9.2010. Management did not provide any feed back after his visit.

PM/CM

PM/CM

Management

PM

28 of 128 4/11/2023 P Eng Suraj Singh PM

Page 29: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Certified welder Revalidation & validation of welders are required.

17 Next Meeting28.9.2010 @ 10.30 am

All

Recorded by Eng Suraj Singh PM September 21, 2010To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME

Weekly Project Progress Review MeetingCC Head Office / Eng Sayeed Behairi بحيري / السيد المهندس السيدCC Chairman / أسعد علوى السيد تونسيPresents in the meeting are:

1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning3. Eng Mohammed Saeed CM4. Architect Osman Abdel Aleem 5. Architect Jamel Tomawis Sick6. QA/QC Zaheer Ahmad Ansari Partly7. Eng Nathaniel Tolebo 8. Eng Abdul Rahim Ambrosio Civil Engineer9. Eng Abdur Rahman Civil Engineer10.Eng Hafiz Shakeel Ahmad Siddiqi Quantity Surveyor Busy on valuation11.Eng Sahadevan Nair Electrical Engineer12.Eng Syed Atif Zia Quantity Surveyor Busy on valuation

Eng Rashid Khurshid Electrical Engineer Vacation13.Eng Md Aijaz Hussain Mechanical Engineer14.Eng Mujeeb Mechanical Engineer Sick

S # Minutes Description Action By

1 Labour Working Issues/Output/Time Keeper – Checking on site.

Productivity is not resulting to project requirements. Methods are to be adopted for pushing project.

Incentives required to be planned for the best workers depending on the total conduct of performances..

List of workforce wages is required for information to engineers & foreman to evaluate outputs. Standard data of output to be decided.

Meeting to boost foremen is required one biweekly to induce their motto for work.

All

EngineersPM/CM

29 of 128 4/11/2023 P Eng Suraj Singh PM

Page 30: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Balance quantities provided to Planner by Eng Usman/Abdul Rehman. Others to follow urgently as Cost to Complete is an urgent issue.

No response from any engineer or foreman for hiring finishers from market. Abbas was contacted who complained about nonpayment from head office. All previous payment demand documents to be perused.

Engineers

2 Night Work No night work going on.

3 Bus trip & time controlsManagement has agreed to provide one coaster bus for this site to resolve staff transportation problem. Till now no bus has reached site. Management has to resolve. It is an issue. Staff cannot reach site with punctuality..

PM/CM/Management

4 Stores issues-Material checksProcedure for materials demands & delivery has been circulated to all concerned.

Procedure about materials issue shall be circulated soon.Stores have to be supported to allow store keeper to compose list of material available on site discipline wise..

PM/CM/Management

5 Equipment maintenance & avoidance of idlingAll equipment working on site should not be allowed any idling as it costs a lot.

All logs of equipment working should be filled. No logs have been maintained till now.

PM/CM

6 Engineering Submittal IssuesSince 31.8.2010, status of submission is as followsDetails of Submittals effective 1.9.2010SubmittalsMain buildingPressure tank calculationTreated water pump service buildingApproved as noted

Main buildingFilter tank sizing pump roomApproved as noted revise & resubmit

All

30 of 128 4/11/2023 P Eng Suraj Singh PM

Page 31: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Work requestSingle female Installation of marbleDisapprovedSingle KC Installation of marbleDisapprovedOPD Installation of marbleDisapproved

RFIDC Fire pump, Fire water line, PRV line, for full weldNot readySingle female GF roomsPainting mock up sampleAccepted as noted

Single female GF CorridorPainting mock up sampleRevise & resubmit

Visual inspection for boilerRejected

TestingPressure testing for chilled water piping basement tunnel area including risers & services buildingSatisfactory

SubmittalsService building GF. Transformer roomFM 200Approved as noted 27/9/2010(to be used as approved earlier)Generator room Fire extinguishing system GFNot required for Generator room 27/9/2010

RFIMain buildingInstallation of ceramic walls 3rd floor toilet shifting door area part 1

31 of 128 4/11/2023 P Eng Suraj Singh PM

Page 32: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Revise & resubmit 27/9/2010

Installation of ceramic walls 3rd floor toilet shifting door area part 3Revise & resubmit 27/9/2010

Delivery NotesHydrantsSFFECO stamp not availableAccepted subject to compliance 27/9/2010

Grease interceptor (zurn LC)Accepted subject to comments+ for payment 27/9/2010

Grills & diffusersLocation as agreed+ for payment 27/9/2010Drawings StatusService BuildingPump room Details Layout @ soft & treated water tank: Approved as noted

Main BuildingRoof Deck Floor BMS Layout HVAC routingRevise & resubmit

Roof floors BMS layout HVAC routingRevise & resubmit

Pump RoomBMS layout: Revise & resubmit

Service BuildingBMS layout GF: Revise & resubmit

Submittals MadeDiesel tank of boiler near soft water tank 14.9.2010Treated water pump Head calculation for Fuel Oil pump generator/boiler 14.9.2010

32 of 128 4/11/2023 P Eng Suraj Singh PM

Page 33: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Main buildingPressure tank calculation for pump room 14.9.2010Filter tank sizing : 14.9.2010

DrawingsRamp & Step details 14.9.2010Main building GF expansion joint layout plan14.9.2010 Details of proposed CMU walling in front of Main entrance: Anethesia pump room

Service buildingPump room detailed layout @ soft & treated water 14.9.2010SamplesRequest for sample approval of granite cladding 19.9.2010As Built StatusKidney CentreFire fighting layout GF/FFRevise & resubmit

OPDFire fighting layout GF/Supervision Floor/FFRevise & resubmitFF Fire Fighting Layout- Kidney Centre Building

31.8.2010Sample approval request of Telecom Distribution Box TAC

31.8.2010Generator Room FM200 Fire Extinguishing System GF

Service building BMS Layout Pump room

1.9.2010Main building roof floor BMS Layout HVAC routing

1.9.2010Typical details of Manhole Sump pit

1.9.2010Main building Roof deck floor BMS Layout HVAC routing

1.9.2010BMS layout GF @ Service building

1.9.2010

33 of 128 4/11/2023 P Eng Suraj Singh PM

Page 34: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Remarks:Main Building Main Entrance above canopy steel work pending. Material is not available. Procurement to be expedited. Aluminum cladding cannot proceed on main entrance without finishing steel work.(Talab Sera orders)

Main Entrance Structural Computation.Consultant requires design calculations from subcontractor of curtain wall.

No action. HO to decide about any consultant for calculations.

Technical requirements:Design of loading for rafters.Design of steel beam for long span.Web members/thickness of steel/welding connection.Foregoing being consultants’ comments on submittal.

Elevators;Mechanical section conducted a meeting with consultants on 5.9.2010 regarding various comments on subcontractor submittal about fixing arrangements, details with structural core walls fixing, protection of rails from corrosion & hoist check after installation. Vendor to resort action. Meeting scheduled.

Eng Sami from Saudi elevators was invited in meeting. Guard rails & doors approved. Motors & cabinet not delivered due to non approval.

Vendor to submit all documents including schedule by Monday. Confirm by letter.

Lifts pits are not ready for installation of lift.1.3 m required. Available 3.8 m. Floor in pit area to be raised. Certain lift well dimensions to be checked for coordinations.

7 Issues on meeting with consultantsAttachments to material submittal documents are not available. Consultants were requested to provide all attachment. Engineers could borrow consultants record files one by one for photo copies.

PM

8 Quality System Issues / Organisation Chart etc.Project Coordinators Eng Jameil & Eng Usman have been coordinating jointly for PM/ Head

34 of 128 4/11/2023 P Eng Suraj Singh PM

Page 35: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

architectural & structurals all.

Organisation chart is in preparation stage.

Electromechanical Eng Mujeeb has started working as services coordinator.

All copies of approved documents have to be provided from consultants records.

of Planning

Electromechanical

9 Quality Control Issues/rework/water/remedial actionsQC engineers have been regularly working & reporting to management about lapses.

Everyday, day to day work meetings are conducted for all disciplines. Quantity production is not satisfactory.

Curing:Foremen have to arrange for the curing water to be filled into site drums. Any lapse not be be tolerated.

Drainage system: According to Eng Gamel, Head of Construction decided that lift station shall coordinated to the last disposal point of sewerage system. Drawing in process of approval.Form of 3 # pits being ready to new requirement.

All

Engineers

EME/CM/PM

10 Quantity Surveyors Issues-Land Surveyors assistanceDiscussions could not be held due to their being busy with valuation. To be discussed later.

Wall guards & corner guards ordered.

Expansion joint quantification finished but basement area to be resolved. Coordination with consultants.

Bathrooms partitions quantification finished.datasheet to be provided by Enj Jamiel

Staircase Granite Eng Jamael & Attif to coordinate.

Border for buildings marble substitution issue to be resolved.

Shop drawing Signage coordination with Eng Ali Saeed TABA- After 10 days

PM/CM/QS/Surveyors

35 of 128 4/11/2023 P Eng Suraj Singh PM

Page 36: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Border Marble delivery-Mulhen Co material under process of alternative submission as materials delivered 12 mm for 20 mm. Test report with comparison statement submitted.

Shop drawings entrance, staircase, ramp under submission. Requires follow up by Eng Jamiel

Sample colour all buildings effected- one approved. One rejected. Anti bacterial paint area require to be located on drawings Eng Usman to coordinate

Curtain wall OPD Tower Eng Ealeed Matbouli –Expected toad discussion.

Cladding: Intec Mohd Aslam Aleem for raising workforce- Ongoing- payment demanded by vendor-Head of Construction to follow payments

Drywalls quantities for payment certificate-progressing. Site measurements ongoing. (urgent)-Also method of measurement to be finalized- Fire zoning based or RFI based. Discussion with ZFP engineer.

Cost to complete the remaining works are required for budget requirement. This is for all disciplines. To be expedited.

Materials delivered to site are being processed for consultants approvals.

Skylights coordination issue being done by DG &b IC & GC. Quotations received by HOC.

Metalco- Letter sent by Eng Usman-Action-. Material on site soon.

11 Schedule for 7 months & landscape schedule planBalance quantities are required for final schedule composition HOP/

PM/

12 Landscape & demobilization of site establishment

Kerb Stones & Interlock blocks to be submitted.. CM

36 of 128 4/11/2023 P Eng Suraj Singh PM

Page 37: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Road work subcontractor not decided yet. Two vendors submitted quotation to HO.

Drainage work is in progress. All relevant drawings are required. Coordination between civil & electro mechanical is required on top profile.

Waterproofing subcontractor was asked to repair damaged areas of protection membrane at adjacent proposed ramps.sub contractor contacted by Eng Usman by phone. To start back area in 3 days.

Relocation of offices New area opposite right compound wall under Ministry of Health is to be used as directed by Eng Sayeed Behairi.Proposal to be sent to Head Office.No further action till now.

13 Buildings Services issuesVarious issues are being taken up.

1. Electrical section required electrical load input n HP or KW units input from Mechanical section about:

2. All water pumps, Lifts, Medical gas equipment, Fuel pumps, All hvac equipment, Boiler room equipment, Kidney centre, water treatment plant, hydrotherapy equipment.

3. Information to be provided by Mechanical section at an earliest.

4. Issue of 60 m x 70 m SEC room to be taken up for resolution by MOH. SW room does no exist. As built SEC room is too small for revised requirement.

5. Ancilliary building SW room ne door is mandatory for access. Other can be reduced or removed also. For emergency purpose, smaller may be provided.

PM/Electromech

14 Safety issues-Site cleaning-PPESafety officer is not available on site. It is a must now. Chairman shall be contacted for this issue.

All

15 Previous meeting minutes discussionsBalance works from planning.

Balance work is an issue. Information starts coming in slowly. All

37 of 128 4/11/2023 P Eng Suraj Singh PM

Page 38: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

To be expedited.

1. Supervision on site is not to mark. 2. FM /Engineers have to improve supervision. 3. Engineers have to control FM & FM their workers. 4. Time wastage practice has to stop. 5. No lack of controls are acceptable.

Work allocation should be given regularly in advance.Materials to be made available in time.Material wastage is not allowed. Cement bags are seen open. It must stop.

Remedial works on dry walls have to be taken up & other measures with subcontractor are required. Sub contractors are to be coordinated.

Manhole mock up sample is required. Designs not approved. Design not approved. To be followed.

Relevant engineers

16 Any other businessJob descriptions:Meeting to be held to explain to relevant persons about their responsibilities.

Scrap materials: to be removed from site. About steel discussion to be made with owner.

Insurance company representative visited site & collected relevant project information on 4.9.2010. Management did not provide any feed back after his visit.Letter written to Head Office.

Certified welder Revalidation & validation of welders are required.

PM/CM

PM/CM

Management

PM

17 Next Meeting5.10.2010 @ 10.30 am

All

Recorded by Eng Suraj Singh PM September 28, 2010To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME

Foreman MeetingPresent in the meeting are:

38 of 128 4/11/2023 P Eng Suraj Singh PM

Page 39: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Eng Suraj Singh Project Manager /Eng Usman/Eng Vishram Deo Head of PlanningSite Engineers/ All Foreman from all disciplinesS #

Minutes Description Action By

1 Explanation Respecting Foreman Job DescriptionExplanation was given to all foremen about the Job Description that was issued to them. Eng Usman translated description & explained meaning of the points on the description.It was also agreed that these points would be noted in Arabic as well in future for a better understanding by Arabic foremen.

All

2 Production related bonusAn explanation was also given that those workers who produce more than standard requirement that has to be agreed based on their salaries, shall be paid bonus amount.Foremen complained about the previous works that were done, no bonus was paid. They were asked about the repairs that were being carried out, who were responsible for those?

3 General: All were instructed to get workers from market so that further subcontracts for finishing items would be awarded by head office. Previous payment issues to subcontractors shall be looked into.

All Foremen

4 Site drinking waterNo worker is allowed to leave the site area for bringing water as it is being arranged within site area.No material wastage is allowed. Foremen are responsible.Foremen are responsible in case, workers are absent after joining.Anytime, surprise check shall be made.Foremen meeting would be conducted 2 to 3 weeks interval.

PM/CM

Recorded by Eng Suraj Singh PMCopy to all engineers & those officials presentPost on siteCC Head Office / Eng Sayeed Behairi بحيري / السيد المهندس السيدCC Chairman / أسعد علوى السيد تونسي

39 of 128 4/11/2023 P Eng Suraj Singh PM

Page 40: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Weekly Project Progress Review MeetingCC Head Office / Eng Sayeed Behairi بحيري / السيد المهندس السيدCC Chairman / أسعد علوى السيد تونسيPresents in the meeting are:

1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning3. Eng Mohammed Saeed CM4. Architect Osman Abdel Aleem 5. Architect Jamel Tomawis6. QA/QC Zaheer Ahmad Ansari7. Eng Nathaniel Tolebo 8. Eng Abdul Rahim Ambrosio Civil Engineer9. Eng Abdur Rahman Civil Engineer10.Eng Sahadevan Nair Electrical Engineer11.Rashid Khurshid Electrical Engineer 12.Eng Mohd Al Gamel Mechanical Engineer13.Eng Md Aijaz Hussain Mechanical Engineer14.Eng Mujeeb Mechanical Engineer

S # Minutes Description Action By

1 Labour Working Issues/Output/Time Keeper – Checking on site.

1. Productivity is gradually improving.2. Tiling work is very slow.3. Methods are to be adopted for pushing project further

by initiatives & bonus etc.4. List of workforce provided is not updated.5. Meeting to boost foremen is still required one biweekly

to induce their motto for work.6. One meeting already held for explaning job description.

Balance quantities 1. provided to Planner by Eng Usman / Abdul Rehman

/Abdul Rahim / Nathnel etc.. Others to follow urgently as Cost to Complete is an urgent issue.

2. No response from any engineer or foreman for hiring finishers from market. Foreman Abbas brought some contractor who has quoted certain rates. Also, one person sent by management has quoted.

All

EngineersPM/CM

Engineers

2 Night Work

40 of 128 4/11/2023 P Eng Suraj Singh PM

Page 41: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

No night work going on. Only bonus works are arranged sometimes..

3 Bus trip & time controlsNew staff bus mobilised to site. Now only one trip is made to transport staff in morning & afternoon. .

4 Stores issues-Material checksNew list of available materials are being worked out by stores. All engineers are required to support for identification of discipline materials.

PM/HOP

5 Equipment maintenance & avoidance of idlingPunctures to tyres require immediate attention for repairs. PM

6 Engineering Submittal IssuesFor 12.10.2010 MeetingStatus up to 12/10/2010 forenoonShop Drawing

1. Main Building 01-Anesthesia Pump room (Part 78) - Approved with comments (dowels in columns to approved method)

2. MB Anesthesia pump room approved as commented

3. Chilled water pump room expansion tank, air separator section details- Approved as noted.

4. External- Typical details for Manhole sump pit 1080- Revise & resubmit.

5. SB- Expansion Joint Layout plan GF -1091- Approved as noted.

6. Manhole - Typical layout details & sections -1109 - Revise & resubmit

7. MB- Aluminum Cladding & Plaster FF- 1107- Approved as noted

8. KC 03 - Main entrance details -1308 - Approved as noted

9. MB 01 - Main entrance details Plan - 053 - Approved as noted

10. Power distribution layout -1070-Approved as noted

Deliveries1. Marble, hollow metal doors, leaf / frame,

mechanical & electrical goods, 2. Glass with black screen film curtain wall 6 mm

All

41 of 128 4/11/2023 P Eng Suraj Singh PM

Page 42: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

double3. Windows ac 192 #4. Porcelain tile 400 x 400 MB5. Bath room accessories6. External pipes uPVC7. Windows for services building 41 #, 2/10/2010 8. Door leaf & frame, 9. Marble for window10. Warning tape 19.9.201011. Door leafs & frames Note #

1474/1480/1483-rejected

RFI1. External Mechanical Drainage Ist fix test

drainage2. Tower basement preparation for putty in part 1,

2, 33. MB Wall tiles 29.9.20104. External Mechanical inspection Pressure test

for drainage 29.9.20105. MB Marble window 29.9.20106. MB Marble FF 6A & 6B Revise & resubmit.7. MB Ceramic walls FF 6A8. MB Marble FF 5A Revise & resubmit.9. MB Putty FF Corridor10. MB Putty GF, FF 7A11. Anesthesia Pre concrete 2 # columns @

pump room 7B Approved.12. External Fill - subgrade preparation – car

parking, roadways ready for FDD. Accepted.13. OPB- Rectification of ceramic tiles GF.14. MB- marble window FF part 6b - not

accepted.15. MB- ceramic tiles GF 4b - revise +

resubmit16. MB- ceramic walls 6a- accepted.17. MB- ceramic SF, toilet part 1- not ready.

Part 3 not ready, part 3 not ready.18. MB- Ist coat putty FF 4A, 894 rear area-

42 of 128 4/11/2023 P Eng Suraj Singh PM

Page 43: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Not accepted19. MB- Above ceiling holes openings pent

house- 1007 arch-Revise +resubmit.20.

3-970 arch21. MB- Marble windows sill 2nd floor 1009

arch22. MB- Marble window sill 4th floor- 1008

arch23. MB- Gypsum board Ist layer R65524. MB- Gypsum board FF R99225. MB- Gypsum board FF R99126. MB-ceramic wall toilet area part 2-964-

accepted27. MB-ceramic wall toilet area part 3-965-

accepted

Work Request1. External Backfill of sub grade at zone 4 & 5

landscape for road way & car parking Approved 5.10.2010

2. Transformer foundation pad 1, 2, 5 approved, other 2 not approved.

3. MB SF back area Start work waterproofing 4. MB Start work for chilled water return piping

insulation @ tunnel area including riser & services building- disapproved.

5. Soft & Treated Water Tank Concrete pour found pad in - approved.

6. MB Marble 12 mm sample approved.7. MB Start fixing marble tile – corridor part 1, 4th

floor. Approved.8. SB- start Ist coat putty FF. Approved9. MB- marble tile corridor part 3 4th floor.

Approved.10. OPB-marble floor tile corridor GF, SF.

Approved.11. SFB- marble floor tiles GF, SF. Approved.12. KC- marble floor tiles GF, SF. Approved.

43 of 128 4/11/2023 P Eng Suraj Singh PM

Page 44: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

13. External- star work b/fill sub grade zone 4 & 5- approved.

14. Transformer foundation Star work SS 1.2 5 approved.

15. MB- plastering basement, GF, FF, 6a approved.

16. MB Plaster @ stair, BM/GF/FF 6A approved to compliance (EJ)

17. MB GF Part 3 29.9.201018. OPB Floor screed GF 60219. MB- Waterproofing Basement Part 1- 604

arch20. MB- Waterproofing Basement Part 2- 605

arch

Submittal 1. Letter to ZFP for Marble material 12 mm

approval with test report 28.9.20102. Boiler piping (steam piping material) approved

as noted-alternative brand/supplier for steam pipe is approved subject to certification.

3. MB - GF expansion joint layout plan 01 approved as noted.

4. OPB 03 Main entrance structural details5. KC 03 - Main entrance structural details.6. MB-Main stair plan & section7. MB01 - Ramp & plan.8. External piping system, details & section.9. MB 01- ramps & stair details - approved as

noted.10. MB main entrance- proposed CMU wall in

front rejected.11. Request for prequalification sample

approved of Children Gymnasium Flooring & skirting accessories – Tarkett- Rejected.

Remarks:Main Building Main Entrance above canopy steel work pending. Material is not available. Procurement to be expedited. Aluminum cladding cannot proceed on main entrance without finishing steel work.(Talab Sera orders).

44 of 128 4/11/2023 P Eng Suraj Singh PM

Page 45: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Material to arrive by 15.10.2010.

Main Entrance Structural Computation.Meeting with Matbouli held on 12.10.2010. To submit all required technical details & drawings revisions.Structurally integrated section informally discussed swith ZFP, to be formally approved.

Elevators;Eng Sami from Saudi elevators has to provide pending details & to procure to site required balance materials.

Still some lift pits are to be made ready for installation of lift.1.3 m required. Available 3.8 m. Floor in pit area to be raised. Certain lift well dimensions to be checked for coordination.

7 Issues on meeting with consultantsAttachments to material submittal documents are being copied from ZFP files as & when required by Electro Mechanical engineers.

8 Quality System Issues / Organisation Chart etc.Organisation chart prepared & tabled..

Electromechanical Many electromechanical coordination issues are to be resolved & continuous coordination is required.

All

Electromechanical

9 Quality Control Issues/rework/water/remedial actionsQC engineers have been regularly working & reporting to management about lapses.

Every day, day to day work meetings are conducted for all disciplines. Quantity production is not satisfactory. Improvement is required. Detailed discussion about productivity are made.

Curing:Needs continuous improvement.

Drainage system: Eng Gamel has to coordinate with Eng Mohd Saed & surveyor for non stop drainage activities.Form of 3 # pits being ready to new requirement.

Chillers Pads:Pads are not constructed to levels. Unevenness does not

All

Engineers

EME/CM/PM

45 of 128 4/11/2023 P Eng Suraj Singh PM

Page 46: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

allow installation of chillers.ZFP raised non compliance that requires urgent attention. Issue pending for more than 4 to 5 months. Eng Saed has to look into urgently & resolve with EME engineers, ZFP & chip out to required levels & stabilize by chemicals.

10 Quantity Surveyors Issues-Land Surveyors assistanceDiscussions could not be held due to their being busy with valuation. To be discussed later.

Wall guards & corner guards ordered.

Expansion joint quantification finished but basement area to be resolved. Coordination with consultants, to be resolved.

Bathrooms partitions quantification finished.datasheet to be provided by Enj Jamiel - action in 1 week

Staircase Granite Eng Jamael & Attif to coordinate. Drg to be resubmitted.

Border for buildings marble substitution issue resolved.

Shop drawing Signage coordination with Eng Ali Saeed TABA- After 10 days

Border Marble delivery-Mulhen Co material under process of alternative submission as materials delivered 12 mm for 20 mm. 12 mm now approved..

Shop drawings entrance, staircase, ramp under submission. Requires follow up by Eng Jamiel- 6 drawings approved.

Sample colour all buildings effected- one approved. One rejected. Anti bacterial paint area require to be located on drawings Eng Usman to coordinate- Location to be decided by ZFP.

Curtain wall OPD Tower Eng Ealeed Matbouli –Meeting conducted on 12.10.2010. Details to be received .

Cladding: Intec Mohd Aslam Aleem for raising workforce- only 7 workers on site- material to be delivered on 15.10.2010.

Drywalls quantities for payment certificate--Also method of

PM/CM/QS/Surveyors

46 of 128 4/11/2023 P Eng Suraj Singh PM

Page 47: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

measurement to be scrutinized based on fire zoning.

Cost to complete the remaining works are required for budget requirement. This is for all disciplines. To be expedited. Did not progress well.

Materials delivered to site are being processed for consultants approvals. Wooden doors rejected by consultants for colour non approval & quality lapses.

Skylights sample to be produced by Matbouli..

11 Schedule for 7 months & landscape schedule planTo be issued in 2 days after final touch up. HOP/

PM/

12 Landscape & demobilization of site establishment

Kerb Stones & Interlock blocks to be submitted..

Road work subcontractor not decided yet. Two vendors submitted quotation to HO.

Drainage work is in progress. Manhole drawings are to be resubmitted. Coordination between civil & electro mechanical is required on top profile.

Waterproofing subcontractor working for repairs.

Relocation of offices MOH allowed but Municipality to be coordinated by HO for final approval.

CM

13 Buildings Services issuesVarious issues are being taken up.

6. Electrical section required electrical load input n HP or KW units input from Mechanical section about:

7. All water pumps, Lifts, Medical gas equipment, Fuel pumps, All hvac equipment, Boiler room equipment, Kidney centre, water treatment plant, hydrotherapy equipment.

8. Pending Information to be provided by Mechanical section at an earliest. Information should be official.

9. Issue of 60 m x 70 m SEC room to be taken up for resolution by MOH. SW room does exist. As built SEC room is too small for revised requirement. Drawing

PM/Electromech

47 of 128 4/11/2023 P Eng Suraj Singh PM

Page 48: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

provided to Electrical engineer. Required SG room details with Designs.

10.Ancilliary building SW room door is mandatory for access. Other can be reduced or removed also. For emergency purpose, smaller may be provided. Coordination with ZFP required.

11.All electrical loads details were mailed to Eng Khaed Ashuri for final resolution for submission.

14 Safety issues-Site cleaning-PPESafety officer is not available on site.

1. Certain minor accident occurred. All engineers & foreman have to deliver Toolbox talks to their workers to let them understand safe use of tools. Even minor accidents costs considerable amount to company. Safe working is directed to all concerned.

2. PPE are being arranged for all.3. Those who have returned their safety helmets to stores

are instructed to use helmets. These were not purchased for store. Non use shall import action.

All

15 Previous meeting minutes discussionsBalance work is an issue. Information starts coming in slowly. To be expedited from those who did not furnish information..Comments:

6. Supervision on site is not to mark. 7. FM /Engineers have to improve supervision. 8. Engineers have to control FM & FM their workers. 9. Time wastage practice has to stop. 10.No lack of controls are acceptable.11.Skipping of workers & staff is to be checked.12.Water arrangements have been made on site.13.Work allocation should be given regularly in advance.14.Materials to be made available in time.15.Material wastage is not allowed. Cement bags are seen

open. It must stop.

Remedial works on dry walls have to be taken up & other measures with subcontractor are required. Sub contractors are to be coordinated. Meeting is planned with subcontractors.

Manhole mock up sample is required. Design under revision. To be followed.

All

Relevant engineers

16 Any other businessJob descriptions:Meeting was held to explain to foremen about their duties.Others if require, explanations shall be made.

PM

48 of 128 4/11/2023 P Eng Suraj Singh PM

Page 49: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Scrap materials: to be removed from site. About steel discussion to be made with owner.

Insurance company representative visited site & collected relevant project information on 4.9.2010. Management did not provide any feed back after his visit.Letter written to Head Office. Mail sent to head office.

Certified welder Revalidation & validation of welders are required. Mechanical engineers to advise the names of the best welders who could qualify procedures.

Drawing:Shop drawing for corridors GF between Tower & Back area according to sketch with ZFP Eng Abu Tahir- Submitted to ZFP

Roofing WalkwaysDetails are being received from Surveyors- in one week some drawings to be released for approval.

PM

Management

PM

Designs

Designs

17 Next Meeting19.10.2010 @ 16.30 am

All

Recorded by Eng Suraj Singh PM October 13, 2010To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME

Weekly Project Progress Review MeetingCC Head Office / Eng Sayed Behairi بحيري / السيد المهندس السيدCC Chairman / أسعد علوى السيد تونسيPresents in the meeting are:

1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning3. Eng Mohammed Saeed CM Not Present No Apology4. Architect Osman Abdel Aleem 5. Architect Jamel Tomawis6. QA/QC Zaheer Ahmad Ansari7. Eng Nathaniel Tolebo 8. Eng Abdul Rahim Ambrosio Civil Engineer9. Eng Abdur Rahman Civil Engineer10.Eng Sahadevan Nair Electrical Engineer

49 of 128 4/11/2023 P Eng Suraj Singh PM

Page 50: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

11.Rashid Khurshid Electrical Engineer 12.Eng Mohd Al Gamel Mechanical Engineer13.Eng Md Aijaz Hussain Mechanical Engineer14.Eng Mujeeb Mechanical Engineer

15.Eng Hafiz Shakeel Ahmad Siddiqi Quantity Surveyor16.Eng Syed Atif Zia Quantity Surveyor

S # Minutes Description Action By

1 Labour Working Issues/Output– Checking on site. 7. Productivity is gradually improving with positive signs.8. Tiling work is very slow. Petty contractors are required

urgently to avoid suffering on delay account.9. Methods are to be adopted for pushing project further

by initiatives & bonus etc. Work of shifting materials to tower & SB floors being done on bonus measurements.

10.List of workforce provided is not updated. To be used only for guidance.

11.Meeting to boost foremen is still required one biweekly to induce their motto for work. Still necessary for encouragement.

12.One meeting already held for explaining job description. Next meeting to be scheduled.

Balance quantities 3. All balance quantities must be provided to Head of

Planning urgently by whom, not provided..

4. Response from engineer or foreman for hiring finishers from market. Foreman Abbas brought some contractor who has quoted certain rates. Also, one person sent by management has quoted. Both quotations were rejected by Eng Sayed Behairi on account of high rates but, market is not allowing low rates. This is urgent requirement to be resolved by management. Also, Eng Jamiel successfully brought one party who has to submit final quotation to be sent to head office. Management should realize the market status.

All

EngineersPM/CM

Engineers

2 Night Work Going on for bonus activities.

3 Bus trip & time controlsWorkers bus is an issue as one bus is not in operation due to mechanical faults & its legal documents requirement. Other bus too posing faults. Mechanic is urgently required on site.Urgent solution is required.

4 Stores issues-Material checks

50 of 128 4/11/2023 P Eng Suraj Singh PM

Page 51: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

New list of available materials are being worked out by stores. All engineers are required to support for identification of discipline materials. Also, stock quantity availability as reserve must be checked by all.

All Enginers/PM/HOP

5 Equipment maintenance & avoidance of idlingIdling dropped to 5 % only. Certain punctures were reported.. PM

6 Engineering Submittal IssuesFor 19.10.2010 MeetingProgress Coordination Meeting Submission StatusWork RequestMB-Marble floor-FF-6A & 6 B-992 R1 arch. Code AMB-Marble floor-FF-5A -991 R1 arch. Code AMB- Ceramic tiles - 4th floor centre- 606 arch - ApprovedMB- waterproofing basement part 1- 604 arch - ApprovedMB-Waterproofing 2nd floor 613 archMB-Ceramic Floor FF Centre Area-609 Arch - Approved.MB-Ceramic Floor TF Centre Area-607 Arch - Approved.MB-Ceramic Floor SF Centre Area-608 Arch - Approved.MB-UPS panel installation basement part 03 -120 Elect - Approved.MB-Cable tray panel installation & wire pulling works in pump room-121 Elect - Approved.MB- Roof area-Form concrete waterproofing-616 arch.

External-SECO room - Plastering-612 Arch- Disapproved.External-Guard room 2/3/4 – 614 arch- Approved.External- Driver room - 615 Arch- Approved.

RFI Request For InspectionMB- Rectification above ceiling Gypsum board 7A - 1005-Revise & resubmit.MB- Rectification above ceiling Gypsum board part 7B - 1004-Revise & resubmit.- Not accepted-Do not

All

51 of 128 4/11/2023 P Eng Suraj Singh PM

Page 52: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

submit without checking.MB- Rectification above ceiling Gypsum board gf 4B- 1003-AcceptedMB- Rectification above ceiling Gypsum board gf 4A- 1002-AcceptedMB- Install ceramic floor tiles 4th floor toilet part 3-970 arch-Revise & ResubmitMB- 2nd floor- RCC pour-Anesthesia pump room top slab part 7B- 637-Proceed.MB-Ceramic walls tiles FF 5BMB- First Putty Coat GF Corridor- 1013-ArchMB part 68- Cement board first layer GF – Accepted MB- First coat putty GF- 1013 Arch- Accepted.MB-GF 6A- First Layer Gypsum- R955- Accepted.MB- Block work Second Floor Back Area- LC Room 1 & LC Room 2-1012 Arch- Not ReadyMB-GF part 1 above dry wall partition-1020 ArchMB-Pent House above ceiling closing holes-1018 ArchMB- Ceramic walls tiles FF part 5B-1014-Accepted.MB- Marble Flooring GF 4A- 996 Arch- Revise & resubmit.MB- Waterproofing SF Back Area- 613 arch- Disapproved.MB-GF Part B – Putty - 988 Arch - Accepted. MB- GF Part 5A – Putty - 987 Arch - Accepted.MB-Marble window sill-FF-6B-971-R1-ArchMB-BA-Waterproof-FF 6A-6B-1016-ArchMB-Marble floor FF-7A-1017-Arch.

SFB - RCC pour- Transformer foundation-dist system-2 #- 638- Proceed.

KC - RCC pour - Transformer foundation - distribution system -1 # - 639- Proceed.

SB-Soft water tank-Surface repair work of ceiling & walls such as 1-canstrip, 2- filing water plug at hole 3, 3- honey comb repair-481-Accepted.

52 of 128 4/11/2023 P Eng Suraj Singh PM

Page 53: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

SB- Soft water tank- Thermo coat on ceiling- 480- Accepted

OPB - Marble skirting-959 R1 Arch1006 Arch - Revise & Resubmit.OPB-Rectification Ceramic floor tiles-842-R4-ArchOPB-GF-Repair Gypsum Board Drywall Partition above ceiling-831-R7 Arch- Accepted.

External-Sub grade car park, road FDD besides KC-523-R1CN- Accepted.External Drainage- Pressure testing for drainage & pipe level-1036SubmittalMB 01-Relocation of wall-Therapy Room- Sk 3186-Approved.MB 01-Relocation of wall-Recovery Room- Sk 3187-Approved as noted.MB 01- West Side Ramp & Step Details- 01-A-R & S-03MB-Main stair plan & section 01-A-CMU-01-Revise & ResubmitMB- Prequalification Approval of disconnect switch GF-M-0286-ElecMB-01-Ramp & Plan- 01-Ramp-001-Revise & resubmit.MB- 02- Main Stair Plan & Section-01-SD-Stair-02

Sound attenuators selection data for FAHU, AHU, IAHU-M-0278-HVAC-SOUND ATTENUATOR-R1- Revise & Resubmit.

OPB-Layout & Builder Work-Passenger / Bed Lift Two 2 units-02-ELE-01-R03

All Buildings- Sample approval- Aluminum Tiles + Perforated Tiles- 600 x 600 mm Ceiling. M-0284-Arch-RGA- Revise & Resubmit.

53 of 128 4/11/2023 P Eng Suraj Singh PM

Page 54: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

SB-08-Medical Gas Plant Room Equipment Details- 08- MGR-SD-001SB- 08-Hot water pumps & piping layout boiler room-08-SD-BOI-003

KC- 03- Medical Gas Plant Room Equipment Details-03-MGR-SD-04

Materials DeliveriesAncillary Building- Windows 67 # - 2518

Up to 19/10.2010 Noon.Remarks:Main Building Main Entrance above canopy steel work pending. Material is not available. Procurement to be expedited. Aluminum cladding cannot proceed on main entrance without finishing steel work. (Talab Sera orders). Material to arrive by 15.10.2010. Not delivered. Possible payment problems.

Main Entrance Structural Computation.Meeting with Matbouli held on 12.10.2010. To submit all required technical details & drawings revisions.Structurally, integrated section informally discussed with ZFP, to be formally approved. No action till now. Walid Mutawali’s action awaited

Elevators;Eng Sami from Saudi elevators has to provide pending details & to procure to site required balance materials.

Still some lift pits are to be made ready for installation of lift.1.3 m required. Available 3.8 m. Floor in pit area to be raised. Certain lift well dimensions to be checked for coordination.Meeting with Eng Sami scheduled on 20.10.2010

7 Issues on meeting with consultantsAttachments to material submittal documents are being copied from ZFP files as & when required by Electro Mechanical engineers. Ongoing.

8 Quality System Issues / Organisation Chart etc.Organisation chart prepared. To be officially submitted. All

54 of 128 4/11/2023 P Eng Suraj Singh PM

Page 55: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Electromechanical BMS rooms coordination not resolved, has to be resolved. Had been pending for about 2 months. Continuously, coordination is essential at this stage. ZFP complained work done on site without approvals. To be resolved.

Electromechanical

9 Quality Control Issues/rework/water/remedial actionsQC engineers have been regularly working & reporting to management about lapses.

Certain foreman are lazy, have to be trained to bring them to required level.

Corridor areas require better quality.

Curing:Needs continuous improvement.

Drainage system: Coordination ongoing. Work to be in progress. Manhole drawings not resubmitted yet. Eng Taha not attending meeting & drawings are delayed.

Chillers Pads:Pads are not constructed to levels. Unevenness does not allow installation of chillers.ZFP raised non compliance that requires urgent attention. Issue pending for more than 4 to 5 months. Eng Saed Taha has to look into this issue urgently & resolve with EME engineers, ZFP & chip out to required levels & stabilize by chemical grouting.Eng Saed Taha not available in meeting to respond status.

All

Engineers

EME/CM/PM

10 Quantity Surveyors Issues-QS are available in this meeting..RFI are being issued to them regularly for including with Payment Certificate.Highlighted drawings are required from Engineers for next payment certificates. Dead line is 28.10.2010.Drawings showing types of Metalco doors are not available to help QS about type quantifications.Eng Jamiel, Eng Usman & Hamada to coordinate with QS for complete information for PC purpose.

Wall guards & corner guards ordered. No deliveries- Vendor’s Contract status is not known.

Expansion joint quantification finished but basement area to

PM/CM/QS/Surveyors

55 of 128 4/11/2023 P Eng Suraj Singh PM

Page 56: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

be resolved. Coordination with consultants, to be resolved. Response from ZFP to be coordinated. Eng Jamiel to contact the vendor tomorrow. QS should get approved drawings for quantification. Schematic line plan shall not help for procurable quantities. Location is approved.

For Kitchen SS expansion joint is not available. To be discussed with ZFP.

Bathrooms partitions quantification finished.datasheet to be provided by Eng Jamiel - action in 1 week

Staircase Granite Drg resubmitted.

Border for buildings marble substitution issue resolved.

Shop drawing Signage coordination with Eng Ali Saeed TABA- After 10 days did not work. Eng Usman to coordinate with vendor urgently.

Border Marble delivery-Mulhen Co material under process of alternative submission as materials delivered 12 mm for 20 mm. 12 mm now approved..Border for buildings marble substitution issue resolvedLaboratory test results to be revised & submitted to ZFP for records.

Shop drawings entrance, staircase, ramp under submission. Requires follow up by Eng Jamiel Ongoing.

Sample colour Anti bacterial paint area require to be located on drawings Eng Usman to coordinate with ZFP

Curtain wall OPD Tower Eng Ealeed Matbouli –Meeting conducted on 12.10.2010. Details not submitted by Walid Matbouli. .

Cladding: Intec Mohd Aslam Aleem for raising workforce- only 7 workers on site- material was to be delivered on 15.10.2010. Not delivered from UAE.

Drywalls quantities for payment certificate--Also method of measurement being chalked out. Appears to be conflicting quantities causing a considerable amount difference.Eng Usman to coordinate with QS for final status.

56 of 128 4/11/2023 P Eng Suraj Singh PM

Page 57: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Cost to complete the remaining works are required for budget requirement. This is for all disciplines. No major results.

Materials delivered to site are being processed for consultants approvals. Wooden doors rejected by consultants for colour non approval & quality lapses. Meeting was conducted with vendor on 18.10.2010. Information about approvals to be formally provided to ZFP.

Skylights sample to be produced by Matbouli. No action so far.

11 Schedule for 7 months & landscape schedule planIssue by Planning. Hard copies in process of circulation.Two weeks look ahead shall be produced for circulation.

HOP/PM/

12 Landscape & demobilization of site establishment

Kerb Stones & Interlock blocks to be submitted. Samples procured to site.

Road work subcontractor not decided yet. Two vendors submitted quotation to HO. No further news.

Drainage work is in progress. Manhole drawings are to be resubmitted. Coordination between civil & electro mechanical is ongoing.

Waterproofing subcontractor work ongoing for repairs.

Relocation of offices MOH allowed but Municipality representative visited site location for approval. Given Google Earth Print out.

OPB 20 # windows not fixed @ GF & FF. Material is available.

CM

13 Buildings Services issuesVarious issues are being taken up.

12.Electrical section required electrical load input in HP or KW units input from Mechanical section about for all water pumps, Lifts, Medical gas equipment, Fuel pumps, All HVAC equipment, Boiler room equipment, Kidney centre, water treatment plant, hydrotherapy equipment.

PM/Electromech

57 of 128 4/11/2023 P Eng Suraj Singh PM

Page 58: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

13.Pending Information to be provided by Mechanical section at an earliest. Information should be official.

14. Issue of 60 m x 70 m SEC room to be taken up for resolution by MOH. SW room does exist. As built SEC room is too small for revised requirement. Drawing provided to Electrical engineer. Given SG room electrical requirement details to Designs.

15.Ancilliary building SW room door is mandatory for access. Other can be reduced or removed also. For emergency purpose, smaller may be provided. Coordination with ZFP required.

16.All electrical loads details were sub mitted to ZFP.14 Safety issues-Site cleaning-PPE

Safety officer is not available on site. 4. PPE to be provided to all workers & staff..5. Many Staff members are not using hard hats. It is non

disciplinary issue. All were instructed to use & instruct their foremen to use.

6. Those workers who have returned their safety helmets to stores are instructed to use helmets. These were not purchased for store. Non use shall import action.

All

15 Previous meeting minutes discussionsBalance work is an issue. Information starts coming in slowly. To be expedited from those who did not furnish information..Comments:

16.Supervision on site is gradually improving. 17.Engineers have to control FM & FM their workers. 18.Time wastage practice has to stop. 19.Skipping of workers & staff is to be checked.20.Water arrangements have been made on site.21.Work allocation should be given regularly in advance.22.Materials to be made available in time.23.Material wastage is not allowed. Cement bags are seen

open. It must stop. Otherwise, cost shall be charged to concerned foremen.

Remedial works on dry walls have to be taken up & other measures with subcontractor are required. Sub contractors are to be coordinated. Meeting is planned with subcontractors.

Manhole mock up sample is required. Design under revision. To be followed. Design not approved yet. Under resubmission.

All

Relevant engineers

16 Any other businessJob descriptions:DCC job description has been issued. Drawings submission & PM

58 of 128 4/11/2023 P Eng Suraj Singh PM

Page 59: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

approval procedure has been issued.

Scrap materials: vendor to buy scrap steel to be searched..

Insurance policy non availability stopped payment certification by the ZFP.

Certified welder Recommended welder for procedure test shall be tested in due course..

Drawing:Shop drawing for corridors GF between Tower & Back area according to sketch with ZFP Eng Abu Tahir- Submitted to ZFP

Roofing WalkwaysDetails received from Surveyors- EME coordination required. In one week some drawings to be released for approval.

PM

Management

PM

Designs

Designs17 Next Meeting

19.10.2010 @ 16.30 amAll

Recorded by Eng Suraj Singh PM October 20, 2010To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME

Weekly Project Progress Review MeetingCC Head Office / Eng Sayed Behairi بحيري / السيد المهندس السيدCC Chairman / أسعد علوى السيد تونسيPresents in the meeting are:

1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning3. Eng Mohammed Saeed CM4. Architect Osman Abdel Aleem 5. Architect Jamel Tomawis6. QA/QC Zaheer Ahmad Ansari In Makkah

7. Eng Nathaniel Tolebo 8. Eng Abdul Rahim Ambrosio Civil Engineer9. Eng Abdur Rahman Civil Engineer10.Eng Sahadevan Nair Electrical Engineer11.Rashid Khurshid Electrical Engineer

59 of 128 4/11/2023 P Eng Suraj Singh PM

Page 60: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

12.Eng Mohd Al Gamel Mechanical Engineer13.Eng Md Aijaz Hussain Mechanical Engineer14.Eng Mujeeb Mechanical Engineer

15.Eng Hafiz Shakeel Ahmad Siddiqi Quantity Surveyor16.Eng Syed Atif Zia Quantity Surveyor

S # Minutes Description Action By

1 Labour Working Issues/Output– Checking on site. 13.Productivity was gradually improving with positive

signs. But, there is seen drop again. Week started for pushing works but, subcontractor did not mobilize. To be pushed or to select more.

14.Tiling work is very slow. Petty contractors were contracted but, no mobilization. Required urgently to avoid suffering on delay account.

15.Methods are to be adopted for pushing project further by initiatives & bonus etc. Engineers showing resistance for standard output 10 sqm. Punishment criteria not acceptable by engineers. Bonus payable when extra work done. They were instructed to follow punishment. There is no other way out. Work of shifting materials to tower & SB floors being done on bonus measurements.

16.Meeting to boost foremen is still required biweekly to induce their motto for work. Still necessary for encouragement, after salary is disbursed for July.

Balance quantities 5. Electrical & Landscape balance quantities must be

provided to Head of Planning urgently. By Thursday.

6. Philipino subcontractor did not respond. Rate reduction not acceptable. Pakistani for screed too did not mobilize. Turky awaited for screed.

All

EngineersPM/CM

PM/Engineers

2 Night Work Going on for bonus activities. To continue.

3 Bus trip & time controlsBoth buses are in operation. Mechanic is urgently required on site.

4 Stores issues-Material checksNew list of available materials are being worked out by stores. Stores to be notified. Stores procedures to be followed for outdoor materials issues. Must be issued on records whatever items are available outdoors.

All Enginers/PM/HOP

5 Equipment maintenance & avoidance of idling

60 of 128 4/11/2023 P Eng Suraj Singh PM

Page 61: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Excavator remained idle for 16 hours due to tyre bursting & hydraulic problem. Certain punctures were also reported..

PM

6 Engineering Submittal IssuesFor 26.10.2010 Progress Coordination Meeting Submission StatusWork RequestMB-Marble floor-FF-6A & 6 B-992 R1 arch.

Code AMB-Marble floor-FF-5A -991 R1 arch.

Code AMB- Ceramic tiles - 4th floor centre- 606 arch -

ApprovedMB- waterproofing basement part 1- 604 arch - ApprovedMB-Waterproofing 2nd floor 613 archMB-Ceramic Floor FF Centre Area-609 Arch -

Approved.MB-Ceramic Floor TF Centre Area-607 Arch -

Approved.MB-Ceramic Floor SF Centre Area-608 Arch -

Approved.MB-UPS panel installation basement part 03 -120 Elec - Approved.MB-Cable tray panel installation & wire pulling works in pump room-121 Elec - Approved.MB- Roof area-Form concrete waterproofing-616 arch.- Approved on ATE responsibilityMB- Marble FF Part 6- 618 ArchMB-Putty @ Marble FF Part 6- 620 Arch.-

ApprovedMB-Putty FF Part 5-619 Arch.-

ApprovedMB-Marble Skirting FF Part 5- 617 Arch.-

ApprovedMB- Marble Floor Corridor 5A-621 A Arch-

ApprovedMB- Ceiling Hangers + Framing FF part 5- 624 Arch- Disapproved

All

61 of 128 4/11/2023 P Eng Suraj Singh PM

Page 62: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB- Ceiling Hangers + Framing FF part 6- 623 Arch- DisapprovedMB- Screed concrete for Vinyl floor FF part 5 & 6 – 625 ArchOPB- False ceiling main runner corridor FF & SF 625 Arch-DisapprovedKC- False ceiling corridor GF & FF 626 Arch.- ApprovedExternal-SECO room - Plastering-612 Arch-

Disapproved.External-Guard room 2/3/4 – 614 arch-

Approved.External- Driver room - 615 Arch-

Approved.

RFI Request For InspectionMB-Pent House above ceiling closing holes-1018 Arch-AcceptedMB- Rectification above ceiling Gypsum board 7A - 1005-Revise & resubmit. -Not AcceptedMB- Rectification above ceiling Gypsum board part 7B - 1004-Revise & resubmit.- Not accepted-Do not submit without checking.MB- Rectification above ceiling Gypsum board gf 4B- 1003-AcceptedMB- Rectification above ceiling Gypsum board gf 4A- 1002-AcceptedMB- Install ceramic floor tiles 4th floor toilet part 3-970 arch-Revise & ResubmitMB- 2nd floor- RCC pour-Anesthesia pump room top slab part 7B- 637-Proceed.MB-Ceramic walls tiles FF 5BMB- First Putty Coat GF Corridor- 1013-ArchMB part 68- Cement board first layer GF –

Accepted MB- First coat putty GF- 1013 Arch-

Accepted.MB-GF 6A- First Layer Gypsum- R955-

Accepted.

62 of 128 4/11/2023 P Eng Suraj Singh PM

Page 63: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB- Block work Second Floor Back Area- LC Room 1 & LC Room 2-1012 Arch- Not ReadyMB-GF part 1 above dry wall partition-1020 Arch- Not accepted, Rework, adjust & resubmit.MB- Ceramic walls tiles FF part 5B-1014-

Accepted.MB- Marble Flooring GF 4A- 996 Arch- Revise & resubmit.MB- Waterproofing SF Back Area- 613 arch- Disapproved.MB-GF Part B – Putty - 988 Arch -

Accepted. MB- GF Part 5A – Putty - 987 Arch -

Accepted.MB-Marble window sill-FF-6B-971-R1-Arch-

AcceptedMB-BA-Waterproof-FF 6A-6B-1016-Arch-

Accepted.MB-Marble floor FF-7A-1017-Arch.-Work May Proceed.MB- GF Part 7 & part 8- Pressure testing for FCU Drainage-Work proceed-satisfactoryMB- GF Part 1 & part 2- Pressure testing for FCU Drainage-Work proceed-satisfactoryMB- Above Ceiling GF 7A, 7B – 1029 ArchMB- Above Ceiling GF 5A, 5B – 1030 ArchMB- Marble Window sill 4th floor 1008 Arch- Revise & resubmitMB- Marble Window sill 2nd floor 1009 Arch- Revise & resubmitMB-BM part 1-1st coat putty. 1031-Arch-Not Accepted-Do not submit RFI without checking on site.MB-BM part 2-1st coat putty. 1032-Arch-

Not AcceptedMB-BM part 3-1st coat putty. 1033-Arch-

Not AcceptedMB-GF 4 A Marble Flooring 996 R1MB-FF part 2, FCU Valve assembly 169 HVAC Mech

63 of 128 4/11/2023 P Eng Suraj Singh PM

Page 64: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB- GF, FF 7A-1001 R1 archMB- Marble floor corridor lift floor part 3, 3-2, 1037 archMB- Marble floor corridor lift floor part 3, 3-20, 1038 archMB- Marble floor ceramic wall tiles first floor part 1, 1039 archExternal- Surface repair ceiling & walls- soft treated water tank 1- canstrip, 2- filling water plug at hole 3- honeycomb 483 civilExternal- thoroseal coat ceiling- soft treated water tank1- 482 civil

SFB - RCC pour- Transformer foundation-dist system-2 #- 638- Proceed.SFB- Part A-Marble Floor-1015SFB- part B-Marble tiles corridor-1023Ext-SFB/SB-plate load test-525 civil- AcceptedKC - RCC pour - Transformer foundation - distribution system -1 # - 639- Proceed.

SB-Soft water tank-Surface repair work of ceiling & walls such as 1-canstrip, 2- filing water plug at hole 3, 3- honey comb repair-481-Accepted.SB- Soft water tank- Thermo coat on ceiling- 480- AcceptedSB- Chiller foundation pad -525-civilOPB - Marble skirting-959 R1 Arch-Accepted1006 Arch - Revise & Resubmit.OPB-Rectification Ceramic floor tiles-842-R4-Arch-Not accepted, rework, adjust & resubmit.OPB-GF-Repair Gypsum Board Drywall Partition above ceiling-831-R7 Arch- Accepted. MB-OPB- FF-Honeycombing rectification. 525-CivilOPB- SF-Honeycombing rectification. 526-CivilExternal-Sub grade car park, road FDD besides KC-523-R1CN- Accepted.External Drainage- Pressure testing for drainage & pipe level-1036-Proceed-Satisfactory

64 of 128 4/11/2023 P Eng Suraj Singh PM

Page 65: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

External Water - Pressure testing for water line-1034-Work may proceed-satisfactory.

SubmittalMB 01-Relocation of wall-Therapy Room- Sk 3186-Approved.MB 01-Relocation of wall-Recovery Room- Sk 3187-Approved as noted.MB 01- West Side Ramp & Step Details- 01-A-R & S-03-Approved as noted.MB-Main stair plan & section 01-A-CMU-01-Revise & ResubmitMB- Prequalification Approval of disconnect switch GF-M-0286-Elec, Approved as noted.MB-01-Ramp & Plan- 01-Ramp-001-Revise & resubmit.MB- 02- Main Stair Plan & Section-01-SD-Stair-02, Approved as notedMB-Upper Roof Floor Aluminum Cladding Layout- Lay-SD-A-1108- Approved as noted.MB-01-Low current room @SF rear. 01-A-LC-01-R01. Revise & resubmit.MB-01-TF-BMS-Lay out-Part 2. 01-BMS-SD-3rd-834 R1-Revise & ResubmitMB-01-TF-BMS-Lay out-Part 3. 01-BMS-SD-3rd-835 R1-Revise & ResubmitMB-01-SF-BMS-Lay out-Part 5. 01-BMS-SD-2nd-832 R1-Revise & ResubmitMB-01-SF-BMS-Lay out-Part 4. 01-BMS-SD-2nd-831 R1-Revise & ResubmitMB-01-RF-BMS-Lay out-Part 3. 01-BMS-SD-RF-841 R1-Revise & ResubmitMB-01-RF-BMS-Lay out-Part 2. 01-BMS-SD-RF-840 R1-Revise & ResubmitMB-01-RF-BMS-Lay out-Part 1. 01-BMS-SD-RF-839 R1-Revise & ResubmitMB-01-RF-BMS-Lay out-Part 3. 01-BMS-SD-RF-841 R1MB-01-4th F-BMS-Lay out-Part 2. 01-BMS-SD-4th-

65 of 128 4/11/2023 P Eng Suraj Singh PM

Page 66: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

837 R1-Revise & ResubmitMB-01-4th F-BMS-Lay out-Part 1. 01-BMS-SD-4th-836 R1-Revise & ResubmitMB-01-FF-BMS-Lay out-Part 4. 01-BMS-SD-FF-825 R1-Revise & ResubmitMB-01-FF-BMS-Lay out-Part 3. 01-BMS-SD-FF-824 R1-Revise & ResubmitMB-01-FF-BMS-Lay out-Part 2. 01-BMS-SD-FF-823 R1-Revise & Resubmit

MB-01-FF-BMS-Lay out-Part 1. 01-BMS-SD-FF-822 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 8. 01-BMS-SD-GF-820 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 7. 01-BMS-SD-GF-819 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 6. 01-BMS-SD-GF-818 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 5. 01-BMS-SD-GF-817 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 4. 01-BMS-SD-GF-816 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 1. 01-BMS-SD-GF-810 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 2. 01-BMS-SD-BF-812 R1-Revise & ResubmitMB-01-BM-BMS-Lay out-Part 3. 01-BMS-SD-GF-811 R1-Revise & ResubmitMB-01-BM-BMS-Lay out-Part3 . 01-BMS-SD-GF-812 R1MB-01-GF-BMS-Lay out-Part1 . 01-BMS-SD-GF-813 R1-Revise & ResubmitMB-01-Low Current room at Second Floor rear area- 01-A-LC-01-R01, Revise & resubmitMB- Granite 400 x 400 exterior corridor @ FF 01-A-Corridor 01. Approved as notedMB- Proposed corridor architecture GF- Lay-SD-1090- Revise & resubmitSound attenuators selection data for FAHU, AHU,

66 of 128 4/11/2023 P Eng Suraj Singh PM

Page 67: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

IAHU-M-0278-HVAC-SOUND ATTENUATOR-R1- Revise & Resubmit.

OPB-Layout & Builder Work-Passenger / Bed Lift Two 2 units-02-ELE-01-R03OPB- Porcelain Sample- For Floor Junction Box- M-0288-Arch-Porcelain

All Buildings- Sample approval- Aluminum Tiles + Perforated Tiles- 600 x 600 mm Ceiling. M-0284-Arch-RGA- Revise & Resubmit.

External Panel Board- M-0285-Elec

SB-08-Medical Gas Plant Room Equipment Details- 08- MGR-SD-001, Revise & resubmitSB- 08-Hot water pumps & piping layout boiler room-08-SD-BOI-003-Revise & resubmit.- Revise & resubmit.

KC- 03- Medical Gas Plant Room Equipment Details-03-MGR-SD-04-Revise & ResubmitKC-Main entrance structural details-3184 ME-Revise & resubmitOPB- Main entrance structural details-3185 ME-Revise & resubmitExternal- Manhole layout 900 x 900 & sections Lay-SD-ST-1109-R01External- Manhole layout 700 x 700 & sections Lay-SD-ST-1110-R01Lift-Layout & Builders Work Passenger / Bed Lifts (2) Units 02-ELE-01-R03, Revise & resubmit

Materials Deliveries25158-Ancillary Building- Windows 67 58954-Ceramic Tiles white2520-Curtain Walls Frame - AcceptedValve, actuators, 3 way valves 15768 Fire alarm material

67 of 128 4/11/2023 P Eng Suraj Singh PM

Page 68: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Up to 26/10.2010 Noon.Up to 19/10.2010 Noon.Remarks:Main Building Main Entrance above canopy steel work pending. Material is not available. Procurement to be expedited. Aluminum cladding cannot proceed on main entrance without finishing steel work. (Talab Sera orders). Material to arrive by 15.10.2010. Not delivered. Possible payment problems.

Main Entrance Structural Computation.Meeting with Matbouli held on 12.10.2010. To submit all required technical details & drawings revisions.Structurally, integrated section informally discussed with ZFP, to be formally approved. No action till now. Walid Mutawali’s action awaited

Elevators;Eng Sami from Saudi elevators has to provide pending details & to procure to site required balance materials.

1/2/9/10/11/12 are ready for work but subcontractor did not start installation. To write to vendor for work.

Still some lift pits are to be made ready for installation of lift.1.3 m required. Available 3.8 m. Floor in pit area to be raised..Meeting with Eng Sami scheduled on 26.10.2010. Did not come to meet.

7 Issues on meeting with consultantsPorcelain sample issue for electric box to be resolved.Many other issues to be discussed for approvals.

8 Quality System Issues / Organisation Chart etc.Organisation chart prepared. To be officially submitted.

Electromechanical BMS issue has been dealt thoroughly as all 25 drawings were rejected. Meeting with vendor Honey Well conducted &outcome notified. Drawings are to be urgently resubmitted. Interface issues have to be resolved.Gen room minor works pending.

All

Electromechanical/HO

9 Quality Control Issues/rework/water/remedial actionsQC engineers has been transferred temporarily to Makkah in absence of whom, engineers have to take full self care till he resumes duty here.

All

68 of 128 4/11/2023 P Eng Suraj Singh PM

Page 69: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Corridor areas require better quality.

Drainage system: Now drainage work is in progress. Excavation & pipe laying moving. Manhole drawings are not yet finally approved.

Chillers Pads:RFI for pad modifications has to be sub mitted by Mechanical section. 4 of 6 pads are ready.

Chillers Pump Pads:Chiller pumps foundation pads to be submitted for approval. Submittal was received but it did not comply for floor mounting purpose. Arabian Pumps to be coordinated by HO.

Engineers

EME/CM/PM

10 Quantity Surveyors Issues-Work for modification area on MB rear, moving. Civil part is nearly complete except windows. Electro Mechanical not completed. Urgent attention needed.

Indicative Drawings were issued to various engineers by the QS. Dead line is 28.10.2010.

Eng Jamiel, Eng Usman & Hamada to coordinate with QS for complete information for PC purpose.

Wall guards & corner guards ordered. No deliveries- Vendor’s Contract status is not known.

Expansion joint quantification finished but basement area to be resolved. Coordination with consultants, to be resolved. Response from ZFP to be coordinated. Eng Jamiel to contact the vendor tomorrow. QS should get approved drawings for quantification. Schematic line plan shall not help for procurable quantities. Location is approved.

For Kitchen SS expansion joint is not available. To be discussed with ZFP.

Bathrooms partitions quantification finished.datasheet to be provided by Eng Jamiel – Drawings expected next day. Quotation received.

Staircase Granite Drg approved. Other types steps to be resolved such as Epoxy coated & chequered plated.

PM/CM/QS/Surveyors

69 of 128 4/11/2023 P Eng Suraj Singh PM

Page 70: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Border for buildings to be checked for design issue .

Shop drawing Signage coordination with Eng Ali Saeed TABA- After 10 days did not work. Eng Usman to coordinate with vendor urgently. No action till now.

Border Marble delivery-Mulhen Co to deliver more material as material finished. Laboratory report for 12 & 20 mm resubmission not receilved. Usman to urgently follow up this issue.Laboratory test results to be revised & submitted to ZFP for records.

Shop drawings entrance, staircase, ramp under submission. Requires follow up by Eng Jamiel Ongoing. Hand rail for SS approved. For GS not submitted.

Sample colour Anti bacterial paint area require to be located on drawings Eng Usman to coordinate with ZFP. Urgent.

Curtain wall OPD Tower Eng Ealeed Matbouli –Meeting conducted on 12.10.2010. Details not submitted by Walid Matbouli. Yest, no action.

Cladding: No work on site- material was to be delivered on 15.10.2010. Not delivered from UAE.

Drywalls 95% finalised.

Materials delivered to site are being processed for consultants approvals.

Skylights sample to be produced by Matbouli. No action so far. No other sample produced. Issue ongoing.

11 Schedule for 7 months & landscape schedule planCirculated to all. To be commented by all. Some comments given verbally. Weekly progress report issued.

HOP/PM/

12 Landscape & demobilization of site establishment

Kerb Stones & Interlock blocks to be submitted. Samples procured to site.To be submitted.

Road work subcontractor not decided yet. Two vendors

CM

70 of 128 4/11/2023 P Eng Suraj Singh PM

Page 71: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

submitted quotation to HO. No further news.

Drainage work is in progress. Manhole drawings are to be approved. Coordination between civil & electro mechanical is ongoing.

Waterproofing subcontractor work ongoing for repairs. Foam concrete moving on rear area roof.

Relocation of offices Preparation in planning for relocation to outside road side.

13 Buildings Services issuesVarious issues are being taken up.

17.Electrical Loads requirement approved with comments.18. Issue of 60 m x 70 m SEC room to be taken up for

resolution by MOH.

PM/Electromech

14 Safety issues-Site cleaning-PPESafety officer is not available on site.

7. PPE to be provided to all workers & staff..8. Many Staff members are not using hard hats. It is non

disciplinary issue. All were instructed to use & instruct their foremen to use.

9. Those workers who have returned their safety helmets to stores are instructed to use helmets. These were not purchased for store. Non use shall import action.

All

15 Previous meeting minutes discussionsBalance work is an issue. Information starts coming in slowly. To be expedited from those who did not furnish information..Comments:

24.Supervision on site is gradually improving. 25.Engineers have to control FM & FM their workers. 26.Time wastage practice has to stop. 27.Skipping of workers & staff is to be checked.28.Water arrangements have been made on site.29.Work allocation should be given regularly in advance.30.Materials to be made available in time.31.Material wastage is not allowed. Cement bags are seen

open. It must stop. Otherwise, cost shall be charged to concerned foremen.

Remedial works on dry walls have to be taken up & other measures with subcontractor are required. Sub contractors are to be coordinated. Meeting is planned with subcontractors.

Manhole mock up sample is required. Design under revision.

All

Relevant engineers

71 of 128 4/11/2023 P Eng Suraj Singh PM

Page 72: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

To be followed. Design not approved yet. Under resubmission.

16 Any other businessJob descriptions:DCC job description has been issued. Documents submission & approval procedure has been issued.

Scrap materials: vendor to buy scrap steel to be searched..

Insurance policy non availability stopped payment certification by the ZFP.

Certified welder Recommended welder for procedure test shall be tested in due course..

Drawing:Shop drawing for corridors GF between Tower & Back area according to sketch with ZFP Eng Abu Tahir- Submitted to ZFP

Roofing WalkwaysDetails received from Surveyors- EME coordination required. In one week some drawings to be released for approval.

PM

PM

Management

PM

Designs

17 Next Meeting2.11.2010 @ 16.30 am

All

Recorded by Eng Suraj Singh PM October 27, 2010To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME

Weekly Project Progress Review MeetingCC Head Office / Eng Sayed Behairi بحيري / السيد المهندس السيدCC Chairman / أسعد علوى السيد تونسيCC Eng Jafar

Presents in the meeting are:1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning3. Eng Mohammed Saeed CM4. Architect Osman Abdel Aleem 5. Architect Jamel Tomawis

72 of 128 4/11/2023 P Eng Suraj Singh PM

Page 73: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

6. QA/QC Zaheer Ahmad Ansari In Makkah

7. Eng Nathaniel Tolebo 8. Eng Abdul Rahim Ambrosio Civil Engineer9. Eng Abdur Rahman Civil Engineer10.Eng Sahadevan Nair Electrical Engineer11.Rashid Khurshid Electrical Engineer Apology-Sick

12.Eng Mohd Al Gamel Mechanical Engineer Absent13.Eng Md Aijaz Hussain Mechanical Engineer14.Eng Mujeeb Mechanical Engineer Absent

15.Eng Hafiz Shakeel Ahmad Siddiqi Quantity Surveyor

S # Minutes Description Action By

1 Labour Working Issues/Output– Checking on site. 17.Productivity was gradually improving with positive

signs. But, there is seen drop again. Week started for pushing works but, subcontractor did not mobilize immediately. Turkish quality not good. Philipino joined Tower. Malik to join. Tuesday some positive signs of subcontractors.

18.Tiling work is very slow. Only Pakistan & Egyptian on tiling. Sudanese on grouting.

19.Meeting of Foremen on Thursday afternoon. Time to be announced. Best foreman to be announced for gift.

Balance quantities 7. Electrical quantities to be provided. Ready but some

more details required. By Wednesday.8. Mechanical engineer Mohd Gamel not submitting

weekly report details. It is a question mark on his efficiency. Only once he submitted.

9.

All

Nair

Gamel

2 Night Work Going on for bonus activities. To continue. Materials are being lifted upwards.

All

3 Bus trip & time controls Mechanic is urgently required on site. PM/CM/

Noor4 Stores issues-Material checks

New lists of available materials have been circulated.Feed back to be provided to planning by all engineers. Required columns are to be filled.

All Engineers

73 of 128 4/11/2023 P Eng Suraj Singh PM

Page 74: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

5 Equipment maintenance & avoidance of idlingNo breakdown this week. To keep close watch on idling.

6 Engineering Submittal Issues

For 2.11.2010 MeetingRFIMB – Mechanical- Pressure test Fire Fight FF- 1037- AcceptedMB- FF-5A Ceramic wall tiles 1034 Arch-Accepted.MB- FF-7A Marble floor 1035 Arch-Accepted.MB- Marble floor corridor lift floor part 3, 3-20, 1038 arch-Revise & resubmitMB- GF, FF 7A-1001 R1 arch-Not ready- ATE Engineer not respondingMB-GF-FF 7A-1001 R2 Arch- ApprovedMB-GF 4 A Marble Flooring 996 R1-Revise & resubmit/work mar proceed to comments incorporation.MB- Putty Ist coat basement-1031 R1 ArchMB- Waterproofing basement1/1-2 1043-archMB-FF 4A-Ist coat putty-894 R4MB- GF 5B- Ceramic- 928 R2-archMB- GF 5A- 1041 ArchMB- FF 4A- 894 R4MB- Marble floor ceramic wall tiles first floor part 1, 1039 arch- Revise & resubmit/work mar proceed to comments incorporation.SB-Pressure Test Fire Fighting Pipe Line FF- 1036- AcceptedSB- GF-Honeycomb rectification- 497 R1 CivilSB- FF-Honeycomb rectification- 498 R1 CivilSFB- Part A-Marble Floor-1015-Not ReadySFB- back Area –Pour RCC Package Sub Station-Transformer pad- (PSS1) Lean concrete-640-AcceptedOPB- SF-Honey combing rectification. 526-Civil-AcceptedOPB-SF Honeycombing rectification- Accepted

All

74 of 128 4/11/2023 P Eng Suraj Singh PM

Page 75: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

OPB- GF-Honeycombing rectification. 524-Civil-AcceptedExternal b/wall Mock up sample paint 1036 ArchChiller Foundation Pads Locations- 3/4/5/6- 170-HVAC-MECH-No Need for this RFIExternal- thoroseal coat ceiling- soft treated water tank1- 482 civil-Accepted.External- Surface repair ceiling & walls- soft treated water tank 1- canstrip, 2- filling water plug at hole 3- honeycomb 483 civil-AcceptedExternal- Besides OPB- Pour Concrete for distribution pad PSS4-J05-00300

SubmittalsAll Buildings- Electrical Loads Calculations for NJH. Sketch-3188-E Loads- Approved with comments

SF back area & besides OPB- Transformer foundation Part 1 blind- 640 struct.

SEC- SG room- Struct details- 11-ST-SG-001

MB- 01- Ramp & Plan- 01-Ramp-001-R01MB-01- BM Floor BMS Layout 01-BMS-BM-810-R02- Approved as notedMB-01- G Floor BMS Layout 01-BMS-GF-820-R02- Approved as notedMB-01- F Floor BMS Layout 01-BMS-FF-822-R02- Approved as notedMB-01- S Floor BMS Layout 01-BMS-SF-350-R02- Approved as notedMB-01- T Floor BMS Layout 01-BMS-TF--R02- Approved as notedMB-01- Forth Floor BMS Layout 01-BMS-4th-836-R02- Approved as notedMB-01- Roof Floor BMS Layout 01-BMS-RF-839-R02- Approved as notedMB-01- Roof Deck BMS Layout 01-BMS-RD-842-R02- Approved as noted

75 of 128 4/11/2023 P Eng Suraj Singh PM

Page 76: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB-01-Installation details for internal windows-SD-01-A-13-21, Approved as notedMB- Emergency Stair Typical Plan & Section- 01-A-Stair-03, Approved as notedMB- Prequalification & sample approval Children gymnasium & skirting accessories M-0264-Arch-Vinyl tiles-R03. Revise & resubmit

External- Manhole layout 900 x 900 & sections Lay-SD-ST-1109-R01-Revise & resubmitExternal-Sample kerb stone & interlock-M-0290-Arch-C & I. Revise & resubmitExternal- Manhole layout 700 x 700 & sections Lay-SD-ST-1110-R01-Revise & resubmitExternal-Typical details of manhole sump pit Lay-SD-1089-R02 Revise & resubmit

OPB- Porcelain Sample- For Floor Junction Box- M-0288-Arch-Porcelain-Revise & resubmitPassenger Bed Lifts-Shaft & Car Drawing- 01-ELE-03-R01?Passenger Bed Lifts 2 units Lay out & builder work Drawing- 02-ELE-01-R03KC- Passenger / bed lift 2 units- 03-ELE-01-R02Passenger/ bed lift 6 units- shaft + car drawing 01-ELE-03-R01

SB- Bed lift 1 unit Lay out & Builder work 08-ELE-01-R01SB-08- Hot water pump & piping Lay out 08-SD-B01-003-R1SB-Generator Room- Pump pad- Sketch-3191-Generator- Revise & resubmitSB-Generator Room- Silencer pad- Sketch-3190-Generator- Revise & resubmitSwitch gear room structural details- 11-ST-SG-001 Revise & resubmit

MCC-BMS-Motor Control Centre- Technical

76 of 128 4/11/2023 P Eng Suraj Singh PM

Page 77: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Catalogue-Honeywell-M-0289-BMSMCC-BMS- Drawings-Honeywell-Doc-3189-BMS

Approval for AMICO-Al Dawleiah For bed head units-M-0293-BHURAL colour sample approval for Metal doors- Hempel-M-0291-Hempel. Revise & resubmit

Buildings-Test Report Marble stone panel Royal Grey JD-5232.1Epoxy sealer Hempadur for staircase & flooring, electric room-Hempadur-M-0292 Hempadur

Storage tank approval request-WADAD- MG-0011-Tank-R1

All Buildings-External panel boards-Jeddah Panel board factory- M-0285-Elect – R01

Work RequestSB- Ceramic tiles GF Cent area 810 archSB- Ceramic tiles FF Cent area 811 archSB-GF Ceramic wall tiles, centre area- 610 arc - DisapprovedSB-FF Ceramic wall tiles, centre area- 611 arc - DisapprovedMB- BM-Floor screed-Elec. Room + Kids play Area – 629 Arch.-ApprovedMB- FF-Floor 5/6 – 626 Arch.-ApprovedMB- 4th Floor Elec room – 632 Arch.MB- 3rd Floor Elec room – 631 Arch. .-ApprovedMB- 2nd Floor Elec room – 630 Arch.-ApprovedMB- Ceiling grid runner patient room FF part 1-633 arch. ApprovedMB- Ceiling grid runner patient room FF part 2-634 arch. ApprovedMB- Ceiling grid runner patient room FF part 3-635 arch. ApprovedMB-Dry wall GF 6A, 6B-638 arch. Disapproved

77 of 128 4/11/2023 P Eng Suraj Singh PM

Page 78: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Delivery Notes80049204 External- Armoured Cable for lighting- AcceptedJ 0966/959/949/953 Hydrotheraphy + Theraphy poolSDS/2010/DN/506 Clock & Accessories- AcceptedA019331 NCS Cables-Accepted15768-Fire Alarm System- Accepted80050351-Cables - Accepted2204- Marble tiles2525 & 188898- Curtain walls frame chemicals for tiles.Cables- 80050351

Remarks:INTEC Meeting was conducted to resolve stoppage of works due to non delivery of materials. All materials & works to be finished at the most after one month of Haj. Otherwise damages to be recovered.

Main Entrance Structural Computation.Walid Matbouli did not take actions on required submissions.

Elevators;Eng Sami from Saudi elevators could not respond to ZFP question on drawings during meeting. Urgent action is required on this account.Lift materials delivered 2 days back. No delivery details provided.For lifts 1/2/9/10/11/12 are ready for work but, subcontractor did not start installation. CM to follow urgently.

7 Issues on meeting with consultantsPorcelain sample issue for electric box to be resolved.Many other issues as discussed during meeting to be discussed for approvals.

8 Quality System Issues / Organisation Chart etc.Organisation chart officially submitted to ZFP. To be updated at regular intervals

Der grave did not perform well on Paints in certain areas. To be looked into. There are already many complaingt of dry wall

All

78 of 128 4/11/2023 P Eng Suraj Singh PM

Page 79: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

quality standards. Electromechanical Some BMS have been approved with comments. EME

9 Quality Control Issues/rework/water/remedial actionsQC engineers had been transferred temporarily to Makkah. One week is over. Must come back to site.Corridor areas require better quality.fixing for marble. Turkish marble work not to mark.

Drainage system: Now drainage work is not in good progress. To be expedited.

Chillers Pads:4 Pads are ready. 2 not ready. Requires lifting for remedial actions.

Chillers Pump Pads:Arabian Foundation did not respond on technical issues. Could not be submitted for approval.

HO

CM

EME/CM

Mujeib

10 Quantity Surveyors Issues-Work for modification area on MB rear, moving. Civil part is nearly complete except windows. Electro Mechanical not completed. Urgent attention needed.

Indicative Drawings were issued to various engineers by the QS. Dead line is 28.10.2010. Not provided yet.

Eng Jamiel, Eng Usman & Hamada to coordinate with QS for complete information for Payment Certificate purpose regularly.

Wall guards & corner guards ordered. No deliveries- Vendor’s Contract status is not known.

Expansion joint quantification finished but, basement area to be resolved. Coordination with consultants, to be resolved. Response from ZFP to be coordinated. Eng Jamiel to contact the vendor tomorrow. QS should get approved drawings for quantification. Schematic line plan shall not help for procurable quantities. Location is approved.

For Kitchen SS expansion joint is not available. To be

PM/QS/

Civil/ArchtEngineers

79 of 128 4/11/2023 P Eng Suraj Singh PM

Page 80: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

discussed with ZFP.

Bathrooms partitions Quotation received. Catalogues with Designs Eng Jamiel – Ongoing.

Staircase Granite Drg approved. To be provided to Eng Usman. All buildings detailing are to be resolved. Handrail to be resolved by sample. Quotation not finalized.

Border for buildings to be checked for design issue.

Shop drawing Signage coordination with Eng Ali Saeed TABA- After 10 days did not work. Eng Usman to coordinate with vendor urgently. No action till now. Letter written.Signage for mechanical section also required. Piping signs.

Border Marble delivery-Mulhen Co to deliver more material as material finished. Laboratory report submitted. Usman to urgently follow up this issue. Requested 5000 sqm Nicrado. 320 sqm Kenya.

Shop drawings entrance, staircase, ramp under submission. Requires follow up by Eng Jamiel Ongoing. Hand rail for SS approved. For GS not submitted. Sample not approved.

Sample colour Anti bacterial paint area required to be located on drawings Eng Usman coordinate with ZFP. Indicative details with QS for quantification.

Curtain wall OPD Tower Eng Waleed Matbouli –Meeting conducted on 12.10.2010. Details not submitted by Walid Matbouli. Yet, no action. To be pursued by Eng Usman.

Skylights sample to be produced by Matbouli. No action so far. No other sample produced. Issue ongoing. Quotations are being invited from 3 vendors.

11 Schedule for 7 months Circulated to all. To be commented by all. All to comment by Saturday positively. Foreman performance report to be submitted by all on Wednesday before Thursday Foreman meeting.

HOP/PM/All

12 Landscape & demobilization of site establishment

80 of 128 4/11/2023 P Eng Suraj Singh PM

Page 81: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Kerb Stones & Interlock rejected due to lack of technical information. Provide all technical details.

Road work subcontractor not decided yet. Two vendors submitted quotation to HO. No further news.

Drainage work is in slow progress. Manhole drawings not approved yet due to technicalities. CM to follow ZFP.

Waterproofing subcontractor work ongoing on right side of rear area. Foam concrete moving on rear area roof. Roofing slopes to be made sure by surveyor by producing as built levels.

Relocation of offices No permission from municipality yet. To be expedited.

CM

HO

CM

Eng Usman

HO

13 Buildings Services issuesVarious issues are being taken up.

19.Electrical Loads requirement approved with comments.20. Issue of 60 m x 70 m SG room with SEC room..

Drawing rejected by ZFP.21.

Electromech

14 Safety issues-Site cleaning-PPESafety officer is not available on site.

10.PPE to be provided to all workers & staff on a priority basis.

11.Many Staff members are not using hard hats. It is non disciplinary issue. All were instructed to use & instruct their foremen to use.

12.Those workers who have returned their safety helmets to stores are instructed to use helmets. These were not purchased for store. Non use shall import action.

13.

All/ Noor/Ahmad

15 Previous meeting minutes discussions32.Supervision on site is gradually improving. 33.Engineers have to control FM & FM their workers. 34.Water arrangements have been made on site. To be

improved to meet requirement of all workers.35.Work allocation should be given regularly in advance.36.Materials to be made available in time.37.Material wastage is not allowed. Cement bags are seen

open. It must stop. Otherwise, cost shall be charged to concerned foremen.

Remedial works on dry walls ongoing wherever, necessary.

All

Relevant

81 of 128 4/11/2023 P Eng Suraj Singh PM

Page 82: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

This involves considerable workforce. engineers

16 Any other business

Scrap materials: Scrap steel bars. Removed from site. Sent to Makkah stores.

Insurance policy still not available.

Drawing:All drawings to be produced by Eng Jamel before proceeding on vacation.

Roofing WalkwaysTo be produced urgently by Eng Jamel. One drawing to be released tomorrow.

HO

Designs

17 Next Meeting9.11.2010 @ 16.30 am

All

Recorded by Eng Suraj Singh PM November 3, 2010To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME

Foreman Meeting:Present in the meeting are:Eng Suraj Singh Project Manager /Eng Usman/Eng Vishram Deo Head of PlanningSome Engineers / All Foreman from all disciplines

S #

Minutes Description Action By

1 Explanation Regarding Tool Box TalksExplanation was given to all foremen about giving the Tool Box Talks to workers on regular basis as a part of preventing serious injuries that augment to loss of man hours.

All were informed necessity of safe use of all tools & equipment that could cause mishaps on site. All foremen are responsible to deliver their workers about how to control tools use activities. PPEs are being arranged for all. In case, someone found not using PPE after being issued, disciplinary action shall be taken.

List of certain tools or equipment in common use on site were announced. Brief procedures shall be explained by engineers to foremen so that, they could explain to workers Tool Box Talks

All

82 of 128 4/11/2023 P Eng Suraj Singh PM

Page 83: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

at least twice a week. It shall be a must activity on site.2 Foremen Incentives

It was also announced that Foreman appraisal system was being brought into force immediately & relevant format has been developed by planning, to be filled by engineers after evaluating foreman skills. These include all aspects of foreman performance. Based on engineer’s report & site management review, foreman shall be selected to grades for being awarded incentives for motivation.

Engineers /HOP/PM

3 General: All foremen were directed to evaluate their workers as well, for appraisal leading to motivation award. Foremen should not worry about their bonus but, how to create working environment for workers so that workers work by pro action rather than being forced. The same formula applies to foreman as well. Engineers have to check all such issues on site in project interest.

Engineeers / All Foremen

Recorded by Eng Suraj Singh PMCopy to all engineers & those officials presentPost on siteCC Chairman / أسعد علوى السيد تونسيCC Head Office / Eng Sayed Behairi / السيد المهندس السيدCC Eng Jafar بحيري

Weekly Project Progress Review MeetingCC Head Office / Eng Sayed Behairi بحيري / السيد المهندس السيدCC Chairman / أسعد علوى السيد تونسيCC Eng Jafar

Presents in the meeting are:1. Eng Suraj Singh Project Manager2. Eng Vishram Deo Head of Planning3. Eng Mohammed Saeed CM4. Architect Osman Abdel Aleem 5. Architect Jamel Tomawis6. QA/QC Zaheer Ahmad Ansari 7. Eng Nathaniel Tolebo 8. Eng Abdul Rahim Ambrosio Civil Engineer9. Eng Abdur Rahman Civil Engineer

83 of 128 4/11/2023 P Eng Suraj Singh PM

Page 84: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

10.Eng Sahadevan Nair Electrical Engineer11.Rashid Khurshid Electrical Engineer 12.Eng Mohd Al Gamel Mechanical Engineer13.Eng Md Aijaz Hussain Mechanical Engineer14.Eng Mujeeb Mechanical Engineer

S # Minutes Description Action By

1 Labour Working Issues/Output– Checking on site. 20.Turky workers left site due to bad quality. Pakistani dis

not start yet. Marble delivery problem. Only 2 philipinos on site. It is really critical stage for lack of subcontractors. Screed has not started yet.

21.Tiling work is very slow. Only Pakistan & Egyptian on tiling. Sudanese on grouting. Salraies to be reduced.

22.Meeting of Foremen conducted on Thursday afternoon. Toolbos talks & other issues were discussed.

Balance quantities 10.Quantities provided to head of planning11.Eng Mohd Gamel is still not providing required weekly

reports even after reminders in all meetings. This is not professional approach.

All

HOP/Gamel

2 Night Work Going on for bonus activities. Materials are being lifted upwards.

All

3 Bus trip & time controls Mechanic is urgently required on site. No action by HO HO

4 Stores issues-Material checksNew comprehensive lists of available materials have been circulated. Feed back to be provided to planning by all engineers. Required columns are to be filled. Reserve stock shall be available based on this list for controls. Approximate quantities could be indicated by engineers for stock reservation.

All Engineers

5 Equipment maintenance & avoidance of idlingExcavator broke between 3 pm on 8.11. 2010 to 9 am 9.11.2010 because of puncture. Neither CM, nor Engineer informed. During site visit in morning, it was noticed by PM & HOP. CM & Engineer has to be careful. Did not check at 7 am about machine breakdown.

6 Engineering Submittal Issues

For 9.11.2010 Meeting

84 of 128 4/11/2023 P Eng Suraj Singh PM

Page 85: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

RFIMB- Putty Ist coat basement-1031 R1 Arch. - Revise & resubmitMB- Waterproofing basement1/1-2 1043-arch-

AcceptedMB-FF 4A-Ist coat putty-894 R4.

Accepted.MB- GF 5B- Ceramic- 928 R2-arch. - Revise & resubmit.MB- GF 5A- 1041 Arch.- Revise & resubmit.MB-BM- Tunnel area including riser & to service building. 171-CHW-MechMB-01-HVAC ducting, FAHU & (shaft) 179-HVAC-MechMB- TA- FF corridor, 3, 3-2. Marble floor 1047 Arch. Accepted. MB- TA- TF corridor, 3, 3-2. Marble floor 1048 Arch. Not ready.MB-FF 4A. First Coat Putty. 894-R4 ArchMB-01- FF part 7-Measurement Fire Fighting Pipes. 216-FF-MechMB-01- FF part 8-Measurement Fire Fighting Pipes. 217-FF-MechMB-01- FF part 9-Measurement Fire Fighting Pipes. 218-FF-MechMB-01- FF part 3-Measurement Fire Fighting Pipes. 215-FF-MechMB-01- BM part 1-Measurement Fire Fighting Pipes. 213-FF-MechMB-01- Shaft 03 part 3-Measurement Fire Fighting Pipes. 219-FF-MechMB-01- BM part 2-Measurement Fire Fighting Pipes. 213-FF-MechMB- Corridor 4th floor Marble flooring-3, 3-2. 1037-Arch. Revise & resubmit.MB-FF1/1-2-Corridor-Marble Floor Tiles. 1051 Arch

OPB- External Aluminum Windows ready for

All

85 of 128 4/11/2023 P Eng Suraj Singh PM

Page 86: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

inspection-1044 Arch

SB- GF-Honeycomb rectification- 497 R1 Civil. Approved

SB- FF-Honeycomb rectification- 498 R1 Civil. Approved

SB- Exterior surface paint. 1046 Arch

External b/wall Mock up sample paint 1036 ArchExternal- Besides OPB- Pour Concrete for distribution pad PSS4-J05-00300.

Work to proceed

SubmittalsSF back area & besides OPB- Transformer foundation Part 1 blind- 640 struct.SEC- SG room- Struct details- 11-ST-SG-001

MB- 01- Ramp & Plan- 01-Ramp-001-R01. Revise & resubmitMB-01-Details of cubicle partition @ all wet area. 01-A-11-35. Approved as notedMB- GF False column details.-Sketch-A-3192 PCMB- FF False column details.-Sketch-A-3193 PC

Passenger Bed Lifts-Shaft & Car Drawing- 01-ELE-03-R01?

Passenger Bed Lifts 2 units Lay out & builder work Drawing- 02-ELE-01-R03KC- Passenger / bed lift 2 units- 03-ELE-01-R02. Approved as noted. Approved as notedPassenger/ bed lift 6 units- shaft + car drawing 01-ELE-03-R01. Rejected

SB- Bed lift 1 unit Lay out & Builder work 08-ELE-01-R01. RejectedSB-08- Hot water pump & piping Lay out 08-SD-B01-003-R1- Approved as noted. Revise & resubmit

86 of 128 4/11/2023 P Eng Suraj Singh PM

Page 87: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MCC-BMS-Motor Control Centre- Technical Catalogue-Honeywell-M-0289-BMS.- Approved as noted for 1. Revise & resubmit for 2 & 3MCC-BMS- Drawings-Honeywell-Doc-3189-BMS.-Approved as noted

Approval for AMICO-Al Dawleiah For bed head units-M-0293-BHU. Revise & resubmit

Buildings-Test Report Marble stone panel Royal Grey JD-5232.1Epoxy sealer Hempadur for staircase & flooring, electric room-Hempadur-M-0292 Hempadur.

Revise & resubmit.

Storage tank approval request-WADAD- MG-0011-Tank-R1

All Buildings-External panel boards-Jeddah Panel board factory- M-0285-Elect – R01. Approved as notedAll Buildings – Duct Access Doors M-0294-Mech. Approved as noted.Granite cladding sample approval under aluminum cladding - M-0280-Arch-Mulhem-R01. Revise & resubmit.

Plan Switch Gear Room 11-A-SD-SG-02, 11-A-SG-02 External- Typical Layout Manhole 700 x 700 Details + sections Lay-SD-ST-1110-R02.

Work RequestMB- 4th Floor Elec room – 632 Arch.MB- GF 4, 7 Marble skirting. 645 Arch.

Approved.MB- GF 4, 7 Putty 2nd Coat. 644 Arch.

87 of 128 4/11/2023 P Eng Suraj Singh PM

Page 88: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Approved.MB- GF 7 Floor Screed. 647 Arch.

Approved.MB- Back Area- Waterproofing (foam concrete). 642 Arch. Approved.MB-GF Waterproofing Wet Area 4, 7- 648-ArchMB- TF Corridor Marble Floor Tiles-650-ArchMB- SF Corridor Marble Floor Tiles-651-ArchMB- FF Corridor Marble Floor Tiles-652-Arch

All Buildings-EMT for BMS System @ FF Tower- 123 Elect. Approved

SB- Ceiling grid angles & hangers FF. 639 Arch.- Approved.

SB- Ceramic tiles GF Cent area 810 archSB- Ceramic tiles FF Cent area 811 arch

OPB- GF, SF False ceiling. 640 Arch. Approved.

065490- Air diffuser & external Air grillSA 0960010- 3 way valve & control switches

Delivery NotesJ 0966/959/949/953 Hydrotheraphy + Theraphy pool resubmitted on 6.11.2010 due to it was lost in ZFP office.2204 - Marble tiles.

Accepted.2525 & 188898- Curtain walls frame chemicals for tiles.Cables- 80050351.

Accepted. 0003555 MB- Glass for curtain wall & windows.

Accepted. 2527 & 2519- MB & OPB.

Accepted.

Remarks:

88 of 128 4/11/2023 P Eng Suraj Singh PM

Page 89: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

INTEC Meeting was conducted to resolve stoppage of works due to non delivery of materials. All materials & works to be finished at the most after one month of Haj. Otherwise damages to be recovered. No delivery reported yet.

Main Entrance Structural Computation.Walid Matbouli did not take actions on required submissions. No submission yet.

Elevators;Saudi elevators did not resubmit drawings yet. No delivery notes provided. Urgent. In case, no delivery notes are provided, site PM shall write to Top management to stop LC payment.

One lift well in Service Building available but, no work started.

Some component parts of scaffolding not available.

For lifts 1/2/9/10/11/12 are ready for work but, subcontractor did not start installation. CM to follow urgently.

7 Issues on meeting with consultants1. Porcelain sample issue for electric box to be resolved.

No progress on this issue.2. Landscaping around below water tank issue to be

submitted to ZFP as discussed by Eng Jamel.3. Arcade corridor granite issue to be resolved.4. Expansion joint issue to be resolved.5. For Dedicated BMS room, scrutiny is required. BMS

vendor to meet ZFP with ATE, 8 Quality System Issues / Organisation Chart etc.

Organisation chart officially submitted to ZFP. To be updated at regular intervals. One foreman who was on vacation resumed work on meeting day.

Der grave did not perform well on Paints in certain areas. No progress. To be issued letter & hold meeting for agreeing new schedule.

Electromechanical 1. Some BMS drawings have been approved with

comments.2. Service Building drawings still pending.3. Dedicated BMS room is still a question mark. To be

scrutinized.

All

EME

89 of 128 4/11/2023 P Eng Suraj Singh PM

Page 90: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

4. Chilled water pump vendor did not come to site as scheduled to see PM on 9.11.2010 @ 3 pm.

5. Service building has only one Weekly tank & Boiler room has 2 Weekly Tanks.

6. Drawings to be provided to CM for builder’s works.7. Materials were approved with comments long back but,

not resubmitted.8. All builders work drawings to be resubmitted for

execution.9 Quality Control Issues/rework/water/remedial actions

QC engineers had resumed his duty.

Drainage system: CM has to confer wit ZFP engineer for starting blinding & structural preparation works for manholes.

Chillers Pads:4 Pads agreed by ZFP. 2 not ready. Requires lifting for remedial actions. Contact Ashraf vendor.

Package units still not mounted on pads.

Chillers Pump Pads:Arabian Foundation did not respond on technical issues. Could not be submitted for approval. It is a serious issues that requires design of machine foundations. Frequencies information & amplitude to be provided by vendor.

CM

CM

EME/CM

Mujeib

10 Quantity Surveyors Issues-Work for modification area on MB rear, moving. Civil part is nearly complete except windows. Details of Mechanical provided to QS. Urgent attention needed.

Indicative Drawings were issued to various engineers by the QS. Dead line is 28.10.2010. Not provided yet.

Wall guards & corner guards ordered. No deliveries- Vendor’s Contract status is not known. Eng Usman to coordinate.

Expansion joint quantification finished but, basement area to be resolved. Coordination with consultants, to be resolved. For Kitchen SS expansion joint is not available. To be discussed with ZFP.

Bathrooms partitions Quotation received. Catalogues to be

QS

Civil/ArchtEngineers

90 of 128 4/11/2023 P Eng Suraj Singh PM

Page 91: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

received by Designs Eng Jamiel – Ongoing.

Staircase Granite Drg approved. To be provided to Eng Usman. All buildings detailing are to be resolved. Handrail to be resolved by sample. Quotation not finalized.

Border for buildings to be checked for design issue.

Shop drawing Signage coordination with Eng Ali Saeed TABA- After 10 days did not work. Eng Usman to coordinate with vendor urgently. No action till now. Letter written. PM talked to vendor. In 2 days documents to be received.Signage for mechanical section also required. Piping signs.

Border Marble delivery-Mulhen Co to deliver more material as material finished. Laboratory report submitted. Usman to urgently follow up this issue. Requested 5000 sqm Nicrado. 320 sqm Kenya.

Shop drawings entrance, staircase, ramp under submission. Requires follow up by Eng Jamiel Ongoing. Hand rail for SS approved. For GS not submitted. Sample not approved.

Sample colour Anti bacterial paint area required to be located on drawings Eng Usman coordinate with ZFP. Indicative details with QS for quantification. Not completed yet by QS for pursual.

Curtain wall OPD Tower Eng Waleed Matbouli –Meeting conducted on 12.10.2010. Details not submitted by Walid Matbouli. Yet, no action. To be pursued by Eng Usman.

Skylights sample to be produced by Matbouli. No action so far. No other sample produced. Issue ongoing. Quotations are being invited from 3 vendors.

11 Schedule for 7 months Comments received from all.

Foreman performance report submitted by engineers not consistent adequately for reappraisal. Engineers have to project factual report. Indicated no material wastage on report is not correct. So many accidents clearly indicate lack on foremen performance. Foremen have to work efficiently & Engineers have to check efficiently.

HOP/PM/All

91 of 128 4/11/2023 P Eng Suraj Singh PM

Page 92: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

12 Landscape & demobilization of site establishment

Kerb Stones & Interlock rejected due to lack of technical information. Provide all technical details. Back up details not received yet from ATE factory. CM & Eng Usman to expedite.

Road work subcontractor not decided yet. Two vendors submitted quotation to HO. No further news. Requires immediate attention.

Drainage work is in slow progress. Manhole drawings not approved yet due to technicalities. CM to follow ZFP.

Canopies in various buildings have not been provided with drainage pipes. To be checked by Eng Gamel.

Waterproofing subcontractor work ongoing on right side of rear area. Foam concrete moving on rear area roof. Roofing slopes to be made sure by surveyor by producing as built levels. Some issue exists about additional payment by contractor. To be resolved by HO. Eng Usman to coordinate for resolution of contractual issues..

Relocation of offices No permission from municipality yet. To be expedited. HO to resolve Baladia / municipality approval issue.

CM

HO

CM

Eng Usman

HO

13 Buildings Services issuesVarious issues are being taken up.

22.Electrical resolved..23. Issue of 60 m x 70 m SG room with SEC room..

Drawing rejected by ZFP. Resubmitted.24.Low current room to be expedited by Mechanical

section.

ElectromechEng Jamiel

Eng Mujeib

14 Safety issues-Site cleaning-PPESafety officer is not available on site.

14.PPE are being provided to all workers & staff on a priority basis.

15.All have to use hard hats & safety shoes. 16.Foremen have to ensure safety at work.

All/ Noor/Ahmad

15 Previous meeting minutes discussions38.Supervision on site is gradually improving. 39.Engineers have to control FM & FM their workers.

All

92 of 128 4/11/2023 P Eng Suraj Singh PM

Page 93: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

40.Drinking Water arrangements have been made on site41.No worker should leave site for bringing water.42.Materials to be made available in time.43.Material wastage is not allowed. 44.Remedial works in many areas ongoing wherever,

necessary. This involves considerable workforce. All are required to coordinate to avoid rewprk.

Relevant engineers

16 Any other business

Insurance policy still not available. Many accidents happening daily. Money for medical treatment being paid.

Drawing:All drawings to be produced by Eng Jamel before proceeding on vacation. It is an urgent issue.

Roofing WalkwaysOnly one drawing done. Others to be produced urgently by Eng Jamel.

Walkthrough efforts did not result in planned performance due to inaction by civil & architectural engineers. There are various other reasons as well. Review shall be made.

HO

Designs

17 Next Meeting30.11.2010 @ 16.30 am

All

Recorded by Eng Suraj Singh PM November 10, 2010To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME

Regular Records were maintained for meeting purpose.

For Meeting dated 28.9.2010SubmittalsMain buildingPressure tank calculationTreated water pump service buildingApproved as noted

93 of 128 4/11/2023 P Eng Suraj Singh PM

Page 94: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Main buildingFilter tank sizing pump roomApproved as noted revise & resubmit

Work requestSingle female Installation of marbleDisapprovedSingle KC Installation of marbleDisapprovedOPD Installation of marbleDisapproved

RFIDC Fire pump, Fire water line, PRV line, for full weldNot readySingle female GF roomsPainting mock up sampleAccepted as noted

Single female GF CorridorPainting mock up sampleRevise & resubmit

Visual inspection for boilerRejected

TestingPressure testing for chilled water piping basement tunnel area including risers & services buildingSatisfactory

SubmittalsService building GF. Transformer roomFM 200Approved as noted 27/9/2010(to be used as approved earlier)

94 of 128 4/11/2023 P Eng Suraj Singh PM

Page 95: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Generator room Fire extinguishing system GFNot required for Generator room 27/9/2010

RFIMain buildingInstallation of ceramic walls 3rd floor toilet shifting door area part 1Revise & resubmit 27/9/2010

Installation of ceramic walls 3rd floor toilet shifting door area part 3Revise & resubmit 27/9/2010

Delivery NotesHydrantsSFFECO stamp not availableAccepted subject to compliance 27/9/2010

Grease interceptor (zurn LC)Accepted subject to comments+ for payment 27/9/2010

Grills & diffusersLocation as agreed+ for payment 27/9/2010

For 12.10.2010 Meeting

Shop DrawingMain Building 01-Anesthesia Pump room (Part 78) - Approved with comments (dowels in columns to approved method)MB Anesthesia pump room approved as commentedChilled water pump room expansion tank, air separator section details- Approved as noted.External- Typical details for Manhole sump pit 1080- Revise & resubmit.SB- Expansion Joint Layout plan GF -1091- Approved as noted.Manhole - Typical layout details & sections -1109 - Revise & resubmitMB- Aluminum Cladding & Plaster FF- 1107- Approved as notedKC 03 - Main entrance details -1308 - Approved as noted MB 01 - Main entrance details Plan - 053 - Approved as noted

95 of 128 4/11/2023 P Eng Suraj Singh PM

Page 96: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Power distribution layout -1070-Approved as noted

DeliveriesMarble, hollow metal doors, leaf / frame, mechanical & electrical goods, Glass with black screen film curtain wall 6 mm doubleWindows ac 192 #Porcelain tile 400 x 400 MBBath room accessoriesExternal pipes uPVCWindows for services building 41 #, 2/10/2010 Door leaf & frame, Marble for windowWarning tape 19.9.2010Door leafs & frames Note # 1474/1480/1483-rejected

RFIExternal Mechanical Drainage Ist fix test drainageTower basement preparation for putty in part 1, 2, 3MB Wall tiles 29.9.2010External Mechanical inspection Pressure test for drainage 29.9.2010MB Marble window 29.9.2010MB Marble FF 6A & 6B Revise & resubmit.MB Ceramic walls FF 6AMB Marble FF 5A Revise & resubmit.MB Putty FF CorridorMB Putty GF, FF 7AAnesthesia Pre concrete 2 # columns @ pump room 7B Approved.External Fill - subgrade preparation – car parking, roadways ready for FDD. Accepted.OPB- Rectification of ceramic tiles GF.MB- marble window FF part 6b - not accepted.MB- ceramic tiles GF 4b - revise + resubmitMB- ceramic walls 6a- accepted.MB- ceramic SF, toilet part 1- not ready. Part 3 not ready, part 3 not ready.MB- Ist coat putty FF 4A, 894 rear area-Not acceptedMB- Above ceiling holes openings pent house- 1007 arch-Revise +resubmit.

96 of 128 4/11/2023 P Eng Suraj Singh PM

Page 97: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB- Install ceramic floor tiles 4th floor toilet part 3-970 archMB- Marble windows sill 2nd floor 1009 archMB- Marble window sill 4th floor- 1008 archMB- Gypsum board Ist layer R655MB- Gypsum board FF R992MB- Gypsum board FF R991MB-ceramic wall toilet area part 2-964-acceptedMB-ceramic wall toilet area part 3-965-accepted

Work RequestExternal Backfill of sub grade at zone 4 & 5 landscape for road way & car parking Approved 5.10.2010Transformer foundation pad 1, 2, 5 approved, other 2 not approved.MB SF back area Start work waterproofing MB Start work for chilled water return piping insulation @ tunnel area including riser & services building- disapproved.Soft & Treated Water Tank Concrete pour found pad in - approved.MB Marble 12 mm sample approved.MB Start fixing marble tile – corridor part 1, 4th floor. Approved.SB- start Ist coat putty FF. ApprovedMB- marble tile corridor part 3 4th floor. Approved.OPB-marble floor tile corridor GF, SF. Approved.SFB- marble floor tiles GF, SF. Approved.KC- marble floor tiles GF, SF. Approved.External- star work b/fill sub grade zone 4 & 5- approved.Transformer foundation Star work SS 1.2 5 approved.MB- plastering basement, GF, FF, 6a approved.MB Plaster @ stair, BM/GF/FF 6A approved to compliance (EJ)MB GF Part 3 29.9.2010OPB Floor screed GF 602MB- Waterproofing Basement Part 1- 604 archMB- Waterproofing Basement Part 2- 605 arch

Submittal Letter to ZFP for Marble material 12 mm approval with test report 28.9.2010Boiler piping (steam piping material) approved as noted-alternative brand/supplier for steam pipe is approved subject to certification.MB - GF expansion joint layout plan 01 approved as noted.

97 of 128 4/11/2023 P Eng Suraj Singh PM

Page 98: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

OPB 03 Main entrance structural detailsKC 03 - Main entrance structural details.MB-Main stair plan & sectionMB01 - Ramp & plan.External piping system, details & section.MB 01- ramps & stair details - approved as noted.MB main entrance- proposed CMU wall in front rejected.Request for prequalification sample approved of Children Gymnasium Flooring & skirting accessories – Tarkett- Rejected.

Status up to 12/10/2010 forenoon

For 19.10.2010 Progress Coordination Meeting Submission Status

Work RequestMB-Marble floor-FF-6A & 6 B-992 R1 arch. Code AMB-Marble floor-FF-5A -991 R1 arch. Code AMB- Ceramic tiles - 4th floor centre- 606 arch - ApprovedMB- waterproofing basement part 1- 604 arch - ApprovedMB-Waterproofing 2nd floor 613 arch

MB-Ceramic Floor FF Centre Area-609 Arch - Approved.MB-Ceramic Floor TF Centre Area-607 Arch - Approved.MB-Ceramic Floor SF Centre Area-608 Arch - Approved.MB-UPS panel installation basement part 03 -120 Elec - Approved.MB-Cable tray panel installation & wire pulling works in pump room-121 Elec - Approved.MB- Roof area-Form concrete waterproofing-616 arch.

External-SECO room - Plastering-612 Arch- Disapproved.External-Guard room 2/3/4 – 614 arch- Approved.External- Driver room - 615 Arch- Approved.

RFI Request For InspectionMB- Rectification above ceiling Gypsum board 7A - 1005-Revise & resubmit.

98 of 128 4/11/2023 P Eng Suraj Singh PM

Page 99: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB- Rectification above ceiling Gypsum board part 7B - 1004-Revise & resubmit.- Not accepted-Do not submit without checking.MB- Rectification above ceiling Gypsum board gf 4B- 1003-AcceptedMB- Rectification above ceiling Gypsum board gf 4A- 1002-AcceptedMB- Install ceramic floor tiles 4th floor toilet part 3-970 arch-Revise & ResubmitMB- 2nd floor- RCC pour-Anesthesia pump room top slab part 7B- 637-Proceed.MB-Ceramic walls tiles FF 5BMB- First Putty Coat GF Corridor- 1013-ArchMB part 68- Cement board first layer GF – Accepted MB- First coat putty GF- 1013 Arch- Accepted.MB-GF 6A- First Layer Gypsum- R955- Accepted.MB- Block work Second Floor Back Area- LC Room 1 & LC Room 2-1012 Arch- Not ReadyMB-GF part 1 above dry wall partition-1020 ArchMB-Pent House above ceiling closing holes-1018 ArchMB- Ceramic walls tiles FF part 5B-1014-Accepted.MB- Marble Flooring GF 4A- 996 Arch- Revise & resubmit.MB- Waterproofing SF Back Area- 613 arch- Disapproved.MB-GF Part B – Putty - 988 Arch - Accepted. MB- GF Part 5A – Putty - 987 Arch - Accepted.MB-Marble window sill-FF-6B-971-R1-ArchMB-BA-Waterproof-FF 6A-6B-1016-ArchMB-Marble floor FF-7A-1017-Arch.

SFB - RCC pour- Transformer foundation-dist system-2 #- 638- Proceed.

KC - RCC pour - Transformer foundation - distribution system -1 # - 639- Proceed.

SB-Soft water tank-Surface repair work of ceiling & walls such as 1-canstrip, 2- filing water plug at hole 3, 3- honey comb repair-481-Accepted.SB- Soft water tank- Thermo coat on ceiling- 480- Accepted

OPB - Marble skirting-959 R1 Arch1006 Arch - Revise & Resubmit.

99 of 128 4/11/2023 P Eng Suraj Singh PM

Page 100: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

OPB-Rectification Ceramic floor tiles-842-R4-ArchOPB-GF-Repair Gypsum Board Drywall Partition above ceiling-831-R7 Arch- Accepted.MB-

External-Sub grade car park, road FDD besides KC-523-R1CN- Accepted.External Drainage- Pressure testing for drainage & pipe level-1036

SubmittalMB 01-Relocation of wall-Therapy Room- Sk 3186-Approved.MB 01-Relocation of wall-Recovery Room- Sk 3187-Approved as noted.MB 01- West Side Ramp & Step Details- 01-A-R & S-03MB-Main stair plan & section 01-A-CMU-01-Revise & ResubmitMB- Prequalification Approval of disconnect switch GF-M-0286-ElecMB-01-Ramp & Plan- 01-Ramp-001-Revise & resubmit.MB- 02- Main Stair Plan & Section-01-SD-Stair-02

Sound attenuators selection data for FAHU, AHU, IAHU-M-0278-HVAC-SOUND ATTENUATOR-R1- Revise & Resubmit.

OPB-Layout & Builder Work-Passenger / Bed Lift Two 2 units-02-ELE-01-R03

All Buildings- Sample approval- Aluminum Tiles + Perforated Tiles- 600 x 600 mm Ceiling. M-0284-Arch-RGA- Revise & Resubmit.

SB-08-Medical Gas Plant Room Equipment Details- 08- MGR-SD-001SB- 08-Hot water pumps & piping layout boiler room-08-SD-BOI-003

KC- 03- Medical Gas Plant Room Equipment Details-03-MGR-SD-04

Materials DeliveriesAncillary Building- Windows 67 # - 2518

Up to 19/10.2010 Noon.

For 26.10.2010

100 of 128 4/11/2023 P Eng Suraj Singh PM

Page 101: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Progress Coordination Meeting Submission Status

Work RequestMB-Marble floor-FF-6A & 6 B-992 R1 arch. Code AMB-Marble floor-FF-5A -991 R1 arch. Code AMB- Ceramic tiles - 4th floor centre- 606 arch - ApprovedMB- waterproofing basement part 1- 604 arch - ApprovedMB-Waterproofing 2nd floor 613 archMB-Ceramic Floor FF Centre Area-609 Arch - Approved.MB-Ceramic Floor TF Centre Area-607 Arch - Approved.MB-Ceramic Floor SF Centre Area-608 Arch - Approved.MB-UPS panel installation basement part 03 -120 Elec - Approved.MB-Cable tray panel installation & wire pulling works in pump room-121 Elec - Approved.MB- Roof area-Form concrete waterproofing-616 arch.- Approved on ATE responsibilityMB- Marble FF Part 6- 618 ArchMB-Putty @ Marble FF Part 6- 620 Arch.- ApprovedMB-Putty FF Part 5-619 Arch.- ApprovedMB-Marble Skirting FF Part 5- 617 Arch.- ApprovedMB- Marble Floor Corridor 5A-621 A Arch- ApprovedMB- Ceiling Hangers + Framing FF part 5- 624 Arch- DisapprovedMB- Ceiling Hangers + Framing FF part 6- 623 Arch- DisapprovedMB- Screed concrete for Vinyl floor FF part 5 & 6 – 625 ArchOPB- False ceiling main runner corridor FF & SF 625 Arch-DisapprovedKC- False ceiling corridor GF & FF 626 Arch.- ApprovedExternal-SECO room - Plastering-612 Arch- Disapproved.External-Guard room 2/3/4 – 614 arch- Approved.External- Driver room - 615 Arch- Approved.

RFI Request For InspectionMB-Pent House above ceiling closing holes-1018 Arch-AcceptedMB- Rectification above ceiling Gypsum board 7A - 1005-Revise & resubmit. -Not AcceptedMB- Rectification above ceiling Gypsum board part 7B - 1004-Revise & resubmit.- Not accepted-Do not submit without checking.MB- Rectification above ceiling Gypsum board gf 4B- 1003-AcceptedMB- Rectification above ceiling Gypsum board gf 4A- 1002-Accepted

101 of 128 4/11/2023 P Eng Suraj Singh PM

Page 102: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB- Install ceramic floor tiles 4th floor toilet part 3-970 arch-Revise & ResubmitMB- 2nd floor- RCC pour-Anesthesia pump room top slab part 7B- 637-Proceed.MB-Ceramic walls tiles FF 5BMB- First Putty Coat GF Corridor- 1013-ArchMB part 68- Cement board first layer GF – Accepted MB- First coat putty GF- 1013 Arch- Accepted.MB-GF 6A- First Layer Gypsum- R955- Accepted.MB- Block work Second Floor Back Area- LC Room 1 & LC Room 2-1012 Arch- Not ReadyMB-GF part 1 above dry wall partition-1020 Arch- Not accepted, Rework, adjust & resubmit.MB- Ceramic walls tiles FF part 5B-1014- Accepted.MB- Marble Flooring GF 4A- 996 Arch- Revise & resubmit.MB- Waterproofing SF Back Area- 613 arch- Disapproved.MB-GF Part B – Putty - 988 Arch - Accepted. MB- GF Part 5A – Putty - 987 Arch - Accepted.MB-Marble window sill-FF-6B-971-R1-Arch- AcceptedMB-BA-Waterproof-FF 6A-6B-1016-Arch- Accepted.MB-Marble floor FF-7A-1017-Arch.-Work May Proceed.MB- GF Part 7 & part 8- Pressure testing for FCU Drainage-Work proceed-satisfactoryMB- GF Part 1 & part 2- Pressure testing for FCU Drainage-Work proceed-satisfactoryMB- Above Ceiling GF 7A, 7B – 1029 ArchMB- Above Ceiling GF 5A, 5B – 1030 ArchMB- Marble Window sill 4th floor 1008 Arch- Revise & resubmitMB- Marble Window sill 2nd floor 1009 Arch- Revise & resubmitMB-BM part 1-1st coat putty. 1031-Arch-Not Accepted-Do not submit RFI without checking on site.MB-BM part 2-1st coat putty. 1032-Arch- Not AcceptedMB-BM part 3-1st coat putty. 1033-Arch- Not AcceptedMB-GF 4 A Marble Flooring 996 R1MB-FF part 2, FCU Valve assembly 169 HVAC MechMB- GF, FF 7A-1001 R1 archMB- Marble floor corridor lift floor part 3, 3-2, 1037 archMB- Marble floor corridor lift floor part 3, 3-20, 1038 archMB- Marble floor ceramic wall tiles first floor part 1, 1039 arch

102 of 128 4/11/2023 P Eng Suraj Singh PM

Page 103: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

External- Surface repair ceiling & walls- soft treated water tank 1- canstrip, 2- filling water plug at hole 3- honeycomb 483 civilExternal- thoroseal coat ceiling- soft treated water tank1- 482 civil

SFB - RCC pour- Transformer foundation-dist system-2 #- 638- Proceed.SFB- Part A-Marble Floor-1015SFB- part B-Marble tiles corridor-1023Ext-SFB/SB-plate load test-525 civil- AcceptedKC - RCC pour - Transformer foundation - distribution system -1 # - 639- Proceed.

SB-Soft water tank-Surface repair work of ceiling & walls such as 1-canstrip, 2- filing water plug at hole 3, 3- honey comb repair-481-Accepted.SB- Soft water tank- Thermo coat on ceiling- 480- AcceptedSB- Chiller foundation pad -525-civilOPB - Marble skirting-959 R1 Arch-Accepted1006 Arch - Revise & Resubmit.OPB-Rectification Ceramic floor tiles-842-R4-Arch-Not accepted, rework, adjust & resubmit.OPB-GF-Repair Gypsum Board Drywall Partition above ceiling-831-R7 Arch- Accepted. MB-OPB- FF-Honeycombing rectification. 525-CivilOPB- GF-Honeycombing rectification. 524-CivilOPB- SF-Honeycombing rectification. 526-CivilExternal-Sub grade car park, road FDD besides KC-523-R1CN- Accepted.External Drainage- Pressure testing for drainage & pipe level-1036-Proceed-SatisfactoryExternal Water - Pressure testing for water line-1034-Work may proceed-satisfactory.

SubmittalMB 01-Relocation of wall-Therapy Room- Sk 3186-Approved.MB 01-Relocation of wall-Recovery Room- Sk 3187-Approved as noted.MB 01- West Side Ramp & Step Details- 01-A-R & S-03-Approved as noted.

103 of 128 4/11/2023 P Eng Suraj Singh PM

Page 104: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB-Main stair plan & section 01-A-CMU-01-Revise & ResubmitMB- Prequalification Approval of disconnect switch GF-M-0286-Elec, Approved as noted.MB-01-Ramp & Plan- 01-Ramp-001-Revise & resubmit.MB- 02- Main Stair Plan & Section-01-SD-Stair-02, Approved as notedMB-Upper Roof Floor Aluminum Cladding Layout- Lay-SD-A-1108- Approved as noted.MB-01-Low current room @SF rear. 01-A-LC-01-R01. Revise & resubmit.MB-01-TF-BMS-Lay out-Part 2. 01-BMS-SD-3rd-834 R1-Revise & ResubmitMB-01-TF-BMS-Lay out-Part 3. 01-BMS-SD-3rd-835 R1-Revise & ResubmitMB-01-SF-BMS-Lay out-Part 5. 01-BMS-SD-2nd-832 R1-Revise & ResubmitMB-01-SF-BMS-Lay out-Part 4. 01-BMS-SD-2nd-831 R1-Revise & ResubmitMB-01-RF-BMS-Lay out-Part 3. 01-BMS-SD-RF-841 R1-Revise & ResubmitMB-01-RF-BMS-Lay out-Part 2. 01-BMS-SD-RF-840 R1-Revise & ResubmitMB-01-RF-BMS-Lay out-Part 1. 01-BMS-SD-RF-839 R1-Revise & ResubmitMB-01-RF-BMS-Lay out-Part 3. 01-BMS-SD-RF-841 R1MB-01-4th F-BMS-Lay out-Part 2. 01-BMS-SD-4th-837 R1-Revise & ResubmitMB-01-4th F-BMS-Lay out-Part 1. 01-BMS-SD-4th-836 R1-Revise & ResubmitMB-01-FF-BMS-Lay out-Part 4. 01-BMS-SD-FF-825 R1-Revise & ResubmitMB-01-FF-BMS-Lay out-Part 3. 01-BMS-SD-FF-824 R1-Revise & ResubmitMB-01-FF-BMS-Lay out-Part 2. 01-BMS-SD-FF-823 R1-Revise & Resubmit

MB-01-FF-BMS-Lay out-Part 1. 01-BMS-SD-FF-822 R1-Revise & Resubmit

104 of 128 4/11/2023 P Eng Suraj Singh PM

Page 105: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB-01-GF-BMS-Lay out-Part 8. 01-BMS-SD-GF-820 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 7. 01-BMS-SD-GF-819 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 6. 01-BMS-SD-GF-818 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 5. 01-BMS-SD-GF-817 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 4. 01-BMS-SD-GF-816 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 1. 01-BMS-SD-GF-810 R1-Revise & ResubmitMB-01-GF-BMS-Lay out-Part 2. 01-BMS-SD-BF-812 R1-Revise & ResubmitMB-01-BM-BMS-Lay out-Part 3. 01-BMS-SD-GF-811 R1-Revise & ResubmitMB-01-BM-BMS-Lay out-Part3 . 01-BMS-SD-GF-812 R1MB-01-GF-BMS-Lay out-Part1 . 01-BMS-SD-GF-813 R1-Revise & ResubmitMB-01-Low Current room at Second Floor rear area- 01-A-LC-01-R01, Revise & resubmitMB- Granite 400 x 400 exterior corridor @ FF 01-A-Corridor 01. Approved as notedMB- Proposed corridor architecture GF- Lay-SD-1090- Revise & resubmitSound attenuators selection data for FAHU, AHU, IAHU-M-0278-HVAC-SOUND ATTENUATOR-R1- Revise & Resubmit.

OPB-Layout & Builder Work-Passenger / Bed Lift Two 2 units-02-ELE-01-R03OPB- Porcelain Sample- For Floor Junction Box- M-0288-Arch-Porcelain

All Buildings- Sample approval- Aluminum Tiles + Perforated Tiles- 600 x 600 mm Ceiling. M-0284-Arch-RGA- Revise & Resubmit.

All Buildings- Electrical Loads Calculations for NJH. Sketch-3188-E Loads

105 of 128 4/11/2023 P Eng Suraj Singh PM

Page 106: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

External Panel Board- M-0285-Elec

SB-08-Medical Gas Plant Room Equipment Details- 08- MGR-SD-001, Revise & resubmitSB- 08-Hot water pumps & piping layout boiler room-08-SD-BOI-003-Revise & resubmit.- Revise & resubmit.

KC- 03- Medical Gas Plant Room Equipment Details-03-MGR-SD-04-Revise & ResubmitKC-Main entrance structural details-3184 ME-Revise & resubmitOPB- Main entrance structural details-3185 ME-Revise & resubmitExternal- Manhole layout 900 x 900 & sections Lay-SD-ST-1109-R01External- Manhole layout 700 x 700 & sections Lay-SD-ST-1110-R01Lift-Layout & Builders Work Passenger / Bed Lifts (2) Units 02-ELE-01-R03, Revise & resubmit

Materials Deliveries25158-Ancillary Building- Windows 67 58954-Ceramic Tiles white2520-Curtain Walls Frame - AcceptedValve, actuators, 3 way valves 15768 Fire alarm material Up to 26/10.2010 Noon.

For 2.11.2010 MeetingRFIMB – Mechanical- Pressure test Fire Fight FF- 1037- AcceptedMB- FF-5A Ceramic wall tiles 1034 Arch-Accepted.MB- FF-7A Marble floor 1035 Arch-Accepted.MB- Marble floor corridor lift floor part 3, 3-20, 1038 arch-Revise & resubmitMB- GF, FF 7A-1001 R1 arch-Not ready- ATE Engineer not respondingMB-GF-FF 7A-1001 R2 Arch- ApprovedMB-GF 4 A Marble Flooring 996 R1-Revise & resubmit/work mar proceed to comments incorporation.MB- Putty Ist coat basement-1031 R1 ArchMB- Waterproofing basement1/1-2 1043-archMB-FF 4A-Ist coat putty-894 R4

106 of 128 4/11/2023 P Eng Suraj Singh PM

Page 107: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB- GF 5B- Ceramic- 928 R2-archMB- GF 5A- 1041 ArchMB- FF 4A- 894 R4MB- Marble floor ceramic wall tiles first floor part 1, 1039 arch- Revise & resubmit/work mar proceed to comments incorporation.

SB-Pressure Test Fire Fighting Pipe Line FF- 1036- AcceptedSB- GF-Honeycomb rectification- 497 R1 CivilSB- FF-Honeycomb rectification- 498 R1 CivilSFB- Part A-Marble Floor-1015-Not ReadySFB- back Area –Pour RCC Package Sub Station-Transformer pad- (PSS1) Lean concrete-640-Accepted

OPB- SF-Honey combing rectification. 526-Civil-AcceptedOPB-SF Honeycombing rectification- AcceptedOPB- GF-Honeycombing rectification. 524-Civil-Accepted

External b/wall Mock up sample paint 1036 ArchChiller Foundation Pads Locations- 3/4/5/6- 170-HVAC-MECH-No Need for this RFIExternal- thoroseal coat ceiling- soft treated water tank1- 482 civil-Accepted.External- Surface repair ceiling & walls- soft treated water tank 1- canstrip, 2- filling water plug at hole 3- honeycomb 483 civil-AcceptedExternal- Besides OPB- Pour Concrete for distribution pad PSS4-J05-00300

SubmittalsAll Buildings- Electrical Loads Calculations for NJH. Sketch-3188-E Loads- Approved with comments

SF back area & besides OPB- Transformer foundation Part 1 blind- 640 struct.

SEC- SG room- Struct details- 11-ST-SG-001

MB- 01- Ramp & Plan- 01-Ramp-001-R01

107 of 128 4/11/2023 P Eng Suraj Singh PM

Page 108: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB-01- BM Floor BMS Layout 01-BMS-BM-810-R02- Approved as notedMB-01- G Floor BMS Layout 01-BMS-GF-820-R02- Approved as notedMB-01- F Floor BMS Layout 01-BMS-FF-822-R02- Approved as notedMB-01- S Floor BMS Layout 01-BMS-SF-350-R02- Approved as notedMB-01- T Floor BMS Layout 01-BMS-TF--R02- Approved as notedMB-01- Forth Floor BMS Layout 01-BMS-4th-836-R02- Approved as notedMB-01- Roof Floor BMS Layout 01-BMS-RF-839-R02- Approved as notedMB-01- Roof Deck BMS Layout 01-BMS-RD-842-R02- Approved as notedMB-01-Installation details for internal windows-SD-01-A-13-21, Approved as notedMB- Emergency Stair Typical Plan & Section- 01-A-Stair-03, Approved as notedMB- Prequalification & sample approval Children gymnasium & skirting accessories M-0264-Arch-Vinyl tiles-R03. Revise & resubmit

External- Manhole layout 900 x 900 & sections Lay-SD-ST-1109-R01-Revise & resubmitExternal-Sample kerb stone & interlock-M-0290-Arch-C & I. Revise & resubmitExternal- Manhole layout 700 x 700 & sections Lay-SD-ST-1110-R01-Revise & resubmitExternal-Typical details of manhole sump pit Lay-SD-1089-R02 Revise & resubmit

OPB- Porcelain Sample- For Floor Junction Box- M-0288-Arch-Porcelain-Revise & resubmitPassenger Bed Lifts-Shaft & Car Drawing- 01-ELE-03-R01?Passenger Bed Lifts 2 units Lay out & builder work Drawing- 02-ELE-01-R03KC- Passenger / bed lift 2 units- 03-ELE-01-R02Passenger/ bed lift 6 units- shaft + car drawing 01-ELE-03-R01

108 of 128 4/11/2023 P Eng Suraj Singh PM

Page 109: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

SB- Bed lift 1 unit Lay out & Builder work 08-ELE-01-R01SB-08- Hot water pump & piping Lay out 08-SD-B01-003-R1SB-Generator Room- Pump pad- Sketch-3191-Generator- Revise & resubmitSB-Generator Room- Silencer pad- Sketch-3190-Generator- Revise & resubmitSwitch gear room structural details- 11-ST-SG-001 Revise & resubmit

MCC-BMS-Motor Control Centre- Technical Catalogue-Honeywell-M-0289-BMSMCC-BMS- Drawings-Honeywell-Doc-3189-BMS

Approval for AMICO-Al Dawleiah For bed head units-M-0293-BHURAL colour sample approval for Metal doors- Hempel-M-0291-Hempel. Revise & resubmit

Buildings-Test Report Marble stone panel Royal Grey JD-5232.1Epoxy sealer Hempadur for staircase & flooring, electric room-Hempadur-M-0292 Hempadur

Storage tank approval request-WADAD- MG-0011-Tank-R1

All Buildings-External panel boards-Jeddah Panel board factory- M-0285-Elect – R01

Work RequestSB- Ceramic tiles GF Cent area 810 archSB- Ceramic tiles FF Cent area 811 archSB-GF Ceramic wall tiles, centre area- 610 arc - DisapprovedSB-FF Ceramic wall tiles, centre area- 611 arc - DisapprovedMB- BM-Floor screed-Elec. Room + Kids play Area – 629 Arch.-ApprovedMB- FF-Floor 5/6 – 626 Arch.-ApprovedMB- 4th Floor Elec room – 632 Arch.MB- 3rd Floor Elec room – 631 Arch. .-ApprovedMB- 2nd Floor Elec room – 630 Arch.-ApprovedMB- Ceiling grid runner patient room FF part 1-633 arch. ApprovedMB- Ceiling grid runner patient room FF part 2-634 arch. ApprovedMB- Ceiling grid runner patient room FF part 3-635 arch. Approved

109 of 128 4/11/2023 P Eng Suraj Singh PM

Page 110: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB-Dry wall GF 6A, 6B-638 arch. Disapproved

Delivery Notes80049204 External- Armoured Cable for lighting- AcceptedJ 0966/959/949/953 Hydrotheraphy + Theraphy poolSDS/2010/DN/506 Clock & Accessories- AcceptedA019331 NCS Cables-Accepted15768-Fire Alarm System- Accepted80050351-Cables - Accepted2204- Marble tiles2525 & 188898- Curtain walls frame chemicals for tiles.Cables- 80050351

For 9.11.2010 MeetingRFIMB- Putty Ist coat basement-1031 R1 Arch. - Revise & resubmitMB- Waterproofing basement1/1-2 1043-arch- AcceptedMB-FF 4A-Ist coat putty-894 R4. Accepted.MB- GF 5B- Ceramic- 928 R2-arch. - Revise & resubmit.MB- GF 5A- 1041 Arch.- Revise & resubmit.MB-BM- Tunnel area including riser & to service building. 171-CHW-MechMB-01-HVAC ducting, FAHU & (shaft) 179-HVAC-MechMB- TA- FF corridor, 3, 3-2. Marble floor 1047 Arch. Accepted. MB- TA- TF corridor, 3, 3-2. Marble floor 1048 Arch. Not ready.MB-FF 4A. First Coat Putty. 894-R4 ArchMB-01- FF part 7-Measurement Fire Fighting Pipes. 216-FF-MechMB-01- FF part 8-Measurement Fire Fighting Pipes. 217-FF-MechMB-01- FF part 9-Measurement Fire Fighting Pipes. 218-FF-MechMB-01- FF part 3-Measurement Fire Fighting Pipes. 215-FF-MechMB-01- BM part 1-Measurement Fire Fighting Pipes. 213-FF-MechMB-01- Shaft 03 part 3-Measurement Fire Fighting Pipes. 219-FF-MechMB-01- BM part 2-Measurement Fire Fighting Pipes. 213-FF-MechMB- Corridor 4th floor Marble flooring-3, 3-2. 1037-Arch. Revise & resubmit.MB-FF1/1-2-Corridor-Marble Floor Tiles. 1051 Arch

110 of 128 4/11/2023 P Eng Suraj Singh PM

Page 111: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

OPB- External Aluminum Windows ready for inspection-1044 Arch

SB- GF-Honeycomb rectification- 497 R1 Civil. ApprovedSB- FF-Honeycomb rectification- 498 R1 Civil. ApprovedSB- Exterior surface paint. 1046 Arch

External b/wall Mock up sample paint 1036 ArchExternal- Besides OPB- Pour Concrete for distribution pad PSS4-J05-00300. Work to proceed

SubmittalsSF back area & besides OPB- Transformer foundation Part 1 blind- 640 struct.SEC- SG room- Struct details- 11-ST-SG-001

MB- 01- Ramp & Plan- 01-Ramp-001-R01. Revise & resubmitMB-01-Details of cubicle partition @ all wet area. 01-A-11-35. Approved as notedMB- GF False column details.-Sketch-A-3192 PCMB- FF False column details.-Sketch-A-3193 PC

Passenger Bed Lifts-Shaft & Car Drawing- 01-ELE-03-R01?

Passenger Bed Lifts 2 units Lay out & builder work Drawing- 02-ELE-01-R03KC- Passenger / bed lift 2 units- 03-ELE-01-R02. Approved as noted. Approved as notedPassenger/ bed lift 6 units- shaft + car drawing 01-ELE-03-R01. Rejected

SB- Bed lift 1 unit Lay out & Builder work 08-ELE-01-R01. RejectedSB-08- Hot water pump & piping Lay out 08-SD-B01-003-R1- Approved as noted. Revise & resubmit

MCC-BMS-Motor Control Centre- Technical Catalogue-Honeywell-M-0289-BMS.- Approved as noted for 1. Revise & resubmit for 2 & 3MCC-BMS- Drawings-Honeywell-Doc-3189-BMS.-Approved as noted

111 of 128 4/11/2023 P Eng Suraj Singh PM

Page 112: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Approval for AMICO-Al Dawleiah For bed head units-M-0293-BHU. Revise & resubmit

Buildings-Test Report Marble stone panel Royal Grey JD-5232.1Epoxy sealer Hempadur for staircase & flooring, electric room-Hempadur-M-0292 Hempadur. Revise & resubmit.

Storage tank approval request-WADAD- MG-0011-Tank-R1

All Buildings-External panel boards-Jeddah Panel board factory- M-0285-Elect – R01. Approved as notedAll Buildings – Duct Access Doors M-0294-Mech. Approved as noted.Granite cladding sample approval under aluminum cladding - M-0280-Arch-Mulhem-R01. Revise & resubmit.

Plan Switch Gear Room 11-A-SD-SG-02, 11-A-SG-02 External- Typical Layout Manhole 700 x 700 Details + sections Lay-SD-ST-1110-R02.

Work RequestMB- 4th Floor Elec room – 632 Arch.MB- GF 4, 7 Marble skirting. 645 Arch. Approved.MB- GF 4, 7 Putty 2nd Coat. 644 Arch. Approved.MB- GF 7 Floor Screed. 647 Arch. Approved.MB- Back Area- Waterproofing (foam concrete). 642 Arch. Approved.MB-GF Waterproofing Wet Area 4, 7- 648-ArchMB- TF Corridor Marble Floor Tiles-650-ArchMB- SF Corridor Marble Floor Tiles-651-ArchMB- FF Corridor Marble Floor Tiles-652-Arch

All Buildings-EMT for BMS System @ FF Tower- 123 Elect. Approved

SB- Ceiling grid angles & hangers FF. 639 Arch.- Approved.SB- Ceramic tiles GF Cent area 810 archSB- Ceramic tiles FF Cent area 811 arch

OPB- GF, SF False ceiling. 640 Arch. Approved.065490- Air diffuser & external Air grillSA 0960010- 3 way valve & control switches

112 of 128 4/11/2023 P Eng Suraj Singh PM

Page 113: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Delivery NotesJ 0966/959/949/953 Hydrotheraphy + Theraphy pool resubmitted on 6.11.2010 due to it was lost in ZFP office.2204 - Marble tiles. Accepted.2525 & 188898- Curtain walls frame chemicals for tiles.Cables- 80050351. Accepted. 0003555 MB- Glass for curtain wall & windows. Accepted. 2527 & 2519- MB & OPB. Accepted.

For 9.11.2010 MeetingRFIMB- Putty Ist coat basement-1031 R1 Arch. - Revise & resubmitMB- Waterproofing basement1/1-2 1043-arch- AcceptedMB-FF 4A-Ist coat putty-894 R4. Accepted.MB- GF 5B- Ceramic- 928 R2-arch. - Revise & resubmit.MB- GF 5A- 1041 Arch.- Revise & resubmit.MB-BM- Tunnel area including riser & to service building. 171-CHW-MechMB-01-HVAC ducting, FAHU & (shaft) 179-HVAC-MechMB- TA- FF corridor, 3, 3-2. Marble floor 1047 Arch. Accepted. MB- TA- TF corridor, 3, 3-2. Marble floor 1048 Arch. Not ready.MB-FF 4A. First Coat Putty. 894-R4 ArchMB-01- FF part 7-Measurement Fire Fighting Pipes. 216-FF-MechMB-01- FF part 8-Measurement Fire Fighting Pipes. 217-FF-MechMB-01- FF part 9-Measurement Fire Fighting Pipes. 218-FF-MechMB-01- FF part 3-Measurement Fire Fighting Pipes. 215-FF-MechMB-01- BM part 1-Measurement Fire Fighting Pipes. 213-FF-MechMB-01- Shaft 03 part 3-Measurement Fire Fighting Pipes. 219-FF-MechMB-01- BM part 2-Measurement Fire Fighting Pipes. 213-FF-MechMB- Corridor 4th floor Marble flooring-3, 3-2. 1037-Arch. Revise & resubmit.

SB- GF-Honeycomb rectification- 497 R1 Civil. ApprovedSB- FF-Honeycomb rectification- 498 R1 Civil. Approved

113 of 128 4/11/2023 P Eng Suraj Singh PM

Page 114: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

External- Besides OPB- Pour Concrete for distribution pad PSS4-J05-00300. Work to proceed

SubmittalsSF back area & besides OPB- Transformer foundation Part 1 blind- 640 struct.SEC- SG room- Struct details- 11-ST-SG-001

MB- 01- Ramp & Plan- 01-Ramp-001-R01. Revise & resubmitMB-01-Details of cubicle partition @ all wet area. 01-A-11-35. Approved as noted

Passenger Bed Lifts-Shaft & Car Drawing- 01-ELE-03-R01?

Passenger Bed Lifts 2 units Lay out & builder work Drawing- 02-ELE-01-R03KC- Passenger / bed lift 2 units- 03-ELE-01-R02. Approved as noted. Approved as notedPassenger/ bed lift 6 units- shaft + car drawing 01-ELE-03-R01. Rejected

SB- Bed lift 1 unit Lay out & Builder work 08-ELE-01-R01. RejectedSB-08- Hot water pump & piping Lay out 08-SD-B01-003-R1- Approved as noted. Revise & resubmit

MCC-BMS-Motor Control Centre- Technical Catalogue-Honeywell-M-0289-BMS.- Approved as noted for 1. Revise & resubmit for 2 & 3MCC-BMS- Drawings-Honeywell-Doc-3189-BMS.-Approved as noted

Approval for AMICO-Al Dawleiah For bed head units-M-0293-BHU. Revise & resubmit

Buildings-Test Report Marble stone panel Royal Grey JD-5232.1Epoxy sealer Hempadur for staircase & flooring, electric room-Hempadur-M-0292 Hempadur. Revise & resubmit.

Storage tank approval request-WADAD- MG-0011-Tank-R1

114 of 128 4/11/2023 P Eng Suraj Singh PM

Page 115: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

All Buildings-External panel boards-Jeddah Panel board factory- M-0285-Elect – R01. Approved as notedAll Buildings – Duct Access Doors M-0294-Mech. Approved as noted.Granite cladding sample approval under aluminum cladding - M-0280-Arch-Mulhem-R01. Revise & resubmit.

Work RequestMB- 4th Floor Elec room – 632 Arch.MB- GF 4, 7 Marble skirting. 645 Arch. Approved.MB- GF 4, 7 Putty 2nd Coat. 644 Arch. Approved.MB- GF 7 Floor Screed. 647 Arch. Approved.MB- Back Area- Waterproofing (foam concrete). 642 Arch. Approved.

All Buildings-EMT for BMS System @ FF Tower- 123 Elect. Approved

SB- Ceiling grid angles & hangers FF. 639 Arch.- Approved.SB- Ceramic tiles GF Cent area 810 archSB- Ceramic tiles FF Cent area 811 arch

OPB- GF, SF False ceiling. 640 Arch. Approved.065490- Air diffuser & external Air grillSA 0960010- 3 way valve & control switches

Delivery NotesJ 0966/959/949/953 Hydrotheraphy + Theraphy pool resubmitted on 6.11.2010 due to it was lost in ZFP office.2204 - Marble tiles. Accepted.2525 & 188898- Curtain walls frame chemicals for tiles.Cables- 80050351. Accepted. 0003555 MB- Glass for curtain wall & windows. Accepted. 2527 & 2519- MB & OPB. Accepted.

For meeting dated 30.11.2010RFISB- Exterior surface paint. 1046 Arch-Not accepted. ReworkMB-GF-RC Slab rectification 4,7. 528 Civil. Accepted.MB- GF 5B Ceramic wall tiles- 928 R3 Arch. Revise & resubmit.MB- GF 5A Ceramic wall tiles- 1041 R1 Arch. Revise & resubmit.

115 of 128 4/11/2023 P Eng Suraj Singh PM

Page 116: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

MB- SF Waterproofing back area- 1045 Arch. AcceptedMB- FF 5A/5B Waterproofing back area- 1049 Arch. AcceptedMB- GF 7B First coat putty- 1052 Arch. Revise & resubmitMB-FF1/1-2-Corridor-Marble Floor Tiles. 1051 Arch. Accepted.MB-GF 5, 6 RC Slab rectification 529-Civil- Accepted.

OPB- External Aluminum Windows ready for inspection-1044 Arch. Rejected.External b/wall Mock up sample paint 1036 Arch- Revise & resubmit.

SubmittalMB- GF False column details.-Sketch-A-3192 PC. Approved as notedMB- FF False column details.-Sketch-A-3193 PC. Approved as notedPlan Switch Gear Room 11-A-SD-SG-02, 11-A-SG-02. Approved as noted. External- Typical Layout Manhole 700 x 700 Details + sections Lay-SD-ST-1110-R02. Approved as noted.MB-FF LPG System 01-LPG-SD-0009. Approved as noted.External- Typical Layout Manhole 900 x 900 Details + sections Lay- Lay-SD-ST-1109-R02. Approved as noted.External- Typical Layout Manhole 1200 x 1200 Details + sections Lay- Lay-SD-ST-1112-R02

Work RequestMB- FF 2/3 Ceramic floor- 653 Arch. Approved.

MB- SF Corridor Marble Floor Tiles-651-Arch. Approved.MB- TF Corridor Marble Floor Tiles-650-Arch. Approved.MB-GF Waterproofing Wet Area 4, 7- 648-Arch. Approved.MB- FF Corridor Marble Floor Tiles-652-Arch. Approved.External- Manhole structure construction drainage manholes zone 1/2/3/4/5-262 Civil. Approved.MB- 4th floor EMT for BMS-124 Electrical- Approved.

Delivery NotesSA 0960010 3 way valve & control switches- Not accepted065490 Air diffusers & exhaust air grills- Not accepted

116 of 128 4/11/2023 P Eng Suraj Singh PM

Page 117: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Weekly Contract Progress Review Meeting # 179With Consultants

To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME

CC Head Office / Eng Sayeed Behairi بحيري / السيد المهندس السيدCC Chairman / أسعد علوى السيد تونسي

Presents in the meeting are:ZFP & ATE Key Personnel

For ATE Internal information.

S # Minutes Description Action By

1 Introduction1. ATE new Engineers- introduced to ZFP Engineers2. ZFP introduced its Engineers to ATE new Engineers

None

2 Progress of workProgress report to be submitted one day in advance to the meeting day for review. During meeting, it cannot be reviewed.

ATE

3 Increased ManpowerLast minutes about increasing manpower & staff, information tabled about new key personnel.

ATE

4 CompletionProgress completion date is 24.4.2011 based on 68 months duration ATE

5 Telephones set not in original scope but, letter by ZFP sent to MOH has not been responded. ATE to peruse.

ATE/HO

6 Mechanical worksUrgent

1. Remaining shop drawings & materials- 2. schedule for submission required.- advise schedule3. 2 weeks allowed for schedule

4. VCD started fixing, transfer grill

ATE

117 of 128 4/11/2023 P Eng Suraj Singh PM

Page 118: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

5. Check all material approvals before use of silicon where ever required according to details

6. Ceilings works not progressing.due to mechanical works

7. Quantity of mechanical work is effected

8. ATE engineers retention capacity too poor

7 Architectural

1. Shop drawings 2. Curtain walls not submitted- Matboli to be coordinated before

submission- check all details whatsoever

3. New submittals4. EO doors for operation room- waiting from MOH-ATE to

peruse

5. Automatic sliding door – shop drawing received-ATE to submit price

6. Aluminum doors- no shop drawing submitted- submit before material fabrication & delivery- ZFP cautioned ATE

7. Fence- shop drawing for emergency gate required

8. Precast panels defects-cracks-damaging corners- letter for rectification from ZFP- Joint inspection with ZFP

9. Protection of finishing works- All finishing works such as Aluminum cladding, curtain walls etc. require protection as people make writing on them.

ATE/Walid Matbouli

ATE/HO

8 Electrical works1. Submittal of additional lighting fixtures in place of omitted

external street lights – these fixture not in BOQ but, a substitution for not required external lights as some lighting poles deleted

2. Many areas such as mosque, store building, STP, on hold. OHT in generator room on hold

3. RO, waste disposal, medical disposal etc may be required.

ATE

118 of 128 4/11/2023 P Eng Suraj Singh PM

Page 119: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

4. Cold storage in main building- scope not known- coordinate with supplier sufficiently.

5. ZFP not clear about its deletion- ATE has to confirm from MOH

9 Main Building auditorium interior finish – coordinate with specialist vendor in details before ZFP meeting- audio video system- Eng Usman reported next week, vendor may visit

101. Load calculation for 500 beds. Requirement 60 x 70 m size

outside project area SCECO room (new item) size calculation to be done

2. Load calculations are being worked out for all areas by Eng Nair ATE- His CVs shall be submitted.

ATE

11 1. Civil works2. RCC works exhibiting defects all over areas not finished3. This is a serious concern. Quality of all RC work was bad

during initial execution.

4. Repairs to be explored to avoid corrosion due to location of project being near to sea & as many years have elapsed, it is to be protected urgently. Some special task force is required for this purpose.

5. All repairs must be recorded by RFIs

6. New items- collection & disposal of medical waste7. ATE working on structural shop drawings

8. Lift station-control room- ATE proposed to cancel it & connect last pipe line manhole to government sewerage network but, no thorough engineering studies have been conducted.

9. Hospital shall come in operation after long time & sewerage system could be used but, detailed information should be available before carrying out external area/ internal sewerage system.

10.ATE write to MOH about capacity requirement for 500 beds.

11.Mosque & Stores on hold from MOH

ATE/HO

119 of 128 4/11/2023 P Eng Suraj Singh PM

Page 120: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

12.Schedules13.Realistic Schedule for target date 24.4.2011, schedule is

required for remaining works & remaining times14.Weekly/monthly schedules should be submitted

15.Days remaining16.Countdown board displaying number of days left for

completion to be mounted on front of main building is not done.

17.Cash flow- updated cash flow for 228 million to be submitted by ATE

12 As Built drawings schedules to be submitted & all drawings to be expedited now & not after the project is completed.

ATE

13 Organisation chart to be submitted by ATEAll positions should be exhibited with names

ATE

14 Foremen:List of all foremen on site & their working areas to be submitted. This is required for site coordination by ZFP.

ATE

15 1. Safety-2. No safety on site- no third party insurance is in force-

Insurance is very urgent- safety is very urgent- helmet & safety shoes for all working on site are required

3. Safety plan is required4. House Keeping is very poor all over

ATE

16 Photocopier:1. ZFP photocopier has been out of service for long. 2. Needs repairs or replacement urgently

ATE

17 1. Payment Certificate2. Payment certificate is a serious issue & cannot be done

haphazardly- requires all inputs- ATE engineers should provide all information to QS dealing with it.

3. Particularly, mechanical & architectural documents supports are too poor.

4. FM 200 system Service building fire suppression drawings

ATE

120 of 128 4/11/2023 P Eng Suraj Singh PM

Page 121: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

have been approved for areas also not included in scope of work. Those areas not covered in scope of contract, shall not be required to be executed though approval granted.

5. In case of execution, no extra payment shall be made.

6. Concerned discipline engineers must check scope of work before submissions.

7. Package substation shop drawing to be submitted today18 RO plant Kidney Centre – Location to be decided. ATE may for an

optional supplier who could accommodate.

19 Material submittals:- all material ATE so far, has submitted with single data or catalogues attachment only though, contractually, it should be submitted in duplicate. One copy has to be returned to ATE after signing.

ATE

20 Coordination:1. Coordination on site is too poor. No one knows about what

activities should be started. Any operation is started anywhere & then rework is done. Services are not installed & walling is completed. Then walling is removed for installing services.

2. Engineers have to check all drawings & specification prior to commencing any activity. All contract scope must be known to concerned engineers.

3. No Work request submission should be made prior to making complete coordination of relevant activity. After commencing works, the area should not be abandoned & restarted anytime without information.

4. Once activity starts, considerable areas should be completed prior to raising any RFI.

5. All smaller areas RFI should be avoided keeping in view nature of buildings, accessibility & limitation of inspectors.

6. ATE engineers should act professionally, as there is no difference between ATE & ZFP engineers. All are professionals & should conduct accordingly. What checks are required on activities, must be known to ATE engineers on site. It is not the job of ZFP to teach ATE engineers about good professional practice.

ATE

121 of 128 4/11/2023 P Eng Suraj Singh PM

Page 122: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

21 Contract language:

1. Administrative language of contract is Arabic

2. Technical communication with ZFP should be effected in English.

3. ATE should write from head office using English language for any technical issues with ZFP.

4. English letters can be issued from office of Project Manager on site.

ATE/ZFP

22 Unrequired letters:1. It has been a practice by ATE to write anything without

analyzing thoroughly for the entirety of the items as packages.

2. ATE should write only those issues that have merits.

3. ZFP does not accept ATE to contribute time wastage based on such low profile letters.

ATE

23 1. Quality System:2. ATE advised that site has already started implementing

quality system of organization by issuing job descriptions at various levels, control of stores procurement, ensuring punctuality of all workforce & all catagories of personnel.

3. ATE now believes in self regulation of all works to help ZFP invest minimum time on inspections.

4. Meetings:5. Regular weekly progress review meetings, daily output

meeting are being organized to review all works results.

6. Soon all project areas shall be covered with QA implementation to contractual requirements.

24 Next Meeting:After two weeks @ 10.00 am depending on the outcome of this meeting’s follow ups.

ATE/AFP

Recorded by Eng Suraj Singh PM September 22, 2010

122 of 128 4/11/2023 P Eng Suraj Singh PM

Page 123: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME

Weekly Contract Progress Review Meeting # 181With Consultants

To all Engineers / CM/ Planning Head/Designs/Stores/SecretariatCopied to Head Office/ EME

CC Head Office / Eng Sayeed Behairi بحيري / السيد المهندس السيدCC Chairman / أسعد علوى السيد تونسي

Presents in the meeting are:ZFP & ATE Key Personnel

For ATE Internal information.

S # Minutes Description Action By

1 Meeting Frequency3. Due to no progress as well as no follow up by ATE, in past,

Contract Meetings were scheduled between long intervals.4. Now meetings shall be held once in two weeks until more

progress takes off.

None

2 Progress of workProgress reported to be improving to some extent but, not to an acceptable speed. Mechanical discipline is far behind than required.

ATE

3 CompletionTill date Progress completion date is 24.4.2011 based on 68 months duration. Officially, no extension has been received yet.

ATE

4 Telephones set not in original scope but, letter by ZFP sent to MOH has not been responded. ATE to peruse. List of priority respecting new items to be prepared by MOH.

ATE/HO

5 Mechanical worksUrgent

123 of 128 4/11/2023 P Eng Suraj Singh PM

Page 124: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

shop drawings & materials.schedule for submission required- Next week

Check all material approvals before use of silicon where ever required according to details in fire areas. Eng Salem with ATE Mechanical engineers to assess situation on site after meeting. Then submit report.

Ceilings works not progressing. due to mechanical works

SG Room+Gen Room now requires FM 200

ATE

6 Architectural10.Shop drawings 11.Curtain walls not submitted- Matboli being coordinated

drawings & details to be submitted in one week.

12.New submittals13.EO doors for operation room- waiting from MOH - ATE to

peruse. 3 # international manufacturers’ quotation required in line with contract.

14.Automatic sliding door – shop drawing received - ATE to submit price

15.Aluminum doors- no shop drawing submitted- submit before material fabrication & delivery- ZFP cautioned ATE not to commence with fabrication prior to approval.

16.Fence- shop drawing for emergency gates required. Reminded to submit drawings & manufacturer.

17.Precast panels defects-cracks-damaging corners- letter for rectification from ZFP- Joint inspection with ZFP. To pursue on site with ZFP. Paint should not be applied on defects affected areas.

18.Protection of finishing works- All finishing works such as Aluminum cladding, curtain walls etc. require protection as people make writing on them. Lift doors required prevention & should be taken care of urgently. In case, the doors are damaged, it shall cost ATE.

ATE/Walid Matbouli

ATE/HO

7 Electrical works

124 of 128 4/11/2023 P Eng Suraj Singh PM

Page 125: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

6. Submittal of additional lighting fixtures in place of omitted external street lights – these fixture not in BOQ but, a substitution for not required external lights as some lighting poles deleted

7. Many areas such as mosque, store building, STP, on hold. OHT in generator room on hold

8. RO, waste disposal, medical disposal etc may be required.

9. Cold storage in main building- scope not known- co ordinate with supplier sufficiently.

10.ZFP not clear about its deletion- ATE has to confirm from MOH. MOH to confirm its deletion.

ATE

8 Main Building auditorium interior finish – coordinate with specialist vendor in details before ZFP meeting- audio video system- Eng Usman had to act, vendor may visit. No action taken. Rapid action is required on this issue. ZFP, ATE & vendor should meet prior to finalization pertaining to design requirement issues. It is very urgent.

9 Electrical. Load calculation for 500 beds.

1. Load calculations are being worked out for all areas by Eng Nair ATE- These shall be submitted today

ATE

10 18.Civil works19.RCC works exhibiting defects all over areas not finished20.This is a serious concern. Quality of all RC work was bad

during initial execution.

21.Repairs to be explored to avoid corrosion due to location of project being near to sea & as many years have elapsed, it is to be protected urgently. Some special task force is required for this purpose. Urgent action on site is required.

22.All repairs must be recorded by RFIs

New items- collection & disposal of medical wasteATE working on structural shop drawings

Lift station-control room- ATE proposed to cancel it & connect last pipe line manhole to government sewerage

ATE

125 of 128 4/11/2023 P Eng Suraj Singh PM

Page 126: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

network but, no thorough engineering studies have been conducted. ATE has to confirm from MOH about the status of connecting pipeline to government sewage system or to STP.

Hospital shall come in operation after long time & sewerage system could be used but, detailed information should be available before carrying out external area/ internal sewerage system.

Mechanical department has to promptly resort to MOH for a final decision. Site practical execution is suffering. Now works are moving based on connection to STP Lift station.

ATE write to MOH about capacity requirement for 500 beds.

Mosque & Stores on hold from MOH due to lack of plot space as well as budget scarcity.

23.SchedulesRealistic Schedule for target date 24.4.2011+ extension whatever it could be, schedule is required for remaining works & remaining times

Daily/Weekly/monthly schedules should be submitted

Recoveries programmes are to be included with submission of contract remaining works schedule.

24.Days remainingCountdown board displaying number of days left for completion to be mounted on front of main building is not done.

25.Cash flow- updated cash flow for 228 million to be submitted by ATE

11 As Built drawings schedules to be submitted & all drawings to be expedited now & not after the project is completed. It is an urgent requirement & to be complied by all sections / disciplines.

ATE

12 Organisation chart to be submitted by ATETabled. To be officially submitted.

ATE

13 Foremen:

126 of 128 4/11/2023 P Eng Suraj Singh PM

Page 127: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

List of all foremen on site & their working areas submitted. This is required for site coordination by ZFP. To be updated..

ATE

14 5. Safety-6. No safety on site- no third party insurance is in force-

Insurance is very urgent- safety is very urgent- helmet & safety shoes for all working on site are required

7. Safety plan is required8. House Keeping is very poor all over

ATE

15 8. Payment Certificate9. In case of non availability of Revised Insurance Policy,

Payment Certificate # 44 shall not be forwarded. Munakula # 2 has not been included, since it has not been approved by MOH.

ATE

16 Material submittals:- Remaining materials list is required from all disciplines with submission schedule dates.

ATE

17 Coordination:OPBAccoustic room details are required.

CupBoardsRFI was submitted long back for Cupboard but, sample is required.

External fountain being a part of landscape, details are required

Elevator walls GFMarble cladding details, quantities & sample are required.

Access Panel in Ceiling- Mock up sample is required. Mechanical section to provide locations.

Offices Camp ShiftingAll offices including ZFP shall be shifted to outside of side on the other side of road within the MOH area. Approval to use this land for offices obtained from MOH & Municipality. Announced by ATE.

ATE

18 Next Meeting:After two weeks @ 10.00 am depending on the outcome of this meeting’s follow ups.

ATE/AFP

Recorded by Eng Suraj Singh PM October 13, 2010To all Engineers / CM/ Planning Head/Designs/Stores/Secretariat

127 of 128 4/11/2023 P Eng Suraj Singh PM

Page 128: Minutes of Coordination Meeting Records NJH

Alawi Tunsi Establishment500 Beds North Jeddah Hospital Project (9/2010 to 11/2010)

Copied to Head Office/ EME

128 of 128 4/11/2023 P Eng Suraj Singh PM