MINIMIZING CONFLICTS DURING CONSTRUCTION STAGE...
Transcript of MINIMIZING CONFLICTS DURING CONSTRUCTION STAGE...
MINIMIZING CONFLICTS DURING CONSTRUCTION STAGE BY USING
BUILDING INFORMATION MODELING
MOHD FAIZ BIN SHAPIAI
A capstone project report submitted in partial fulfilment of the
requirements for the award of the degree of
Master of Project Management
Faculty of Civil Engineering
Universiti Teknologi Malaysia
JANUARY 2015
iii
To Farah Azmin who stood beside her husband at every single step of the way,
to Amsyar Darwisy who sacrificed precious time, attention and love with his father,
and to people around me especially my parents who constantly encouraged,
supported and committed to me
iv
ACKNOWLEDGEMENT
Alhamdulillah, praise to Allah the Almighty God who gave me truly strength
to me for completing this thesis. Deepest and sincere appreciations to Dr. Mohamad
Syazli bin Fathi who has been an ideal capstone supervisor for his advices, criticisms
and encouragement in aiding the writing of this capstone project report in countless
ways. I also want to thank you to PWDM supervisor, Ir. Ahmad Ridzuan bin Abu
Bakar for his advices and guidance in project management field especially in
Building Information Modeling knowledge.
Thanks in advanced also to the examiners and panels for their suggestions
and constructive comments in making this thesis the same as it is presented here. I
am also indebted to Faculty of Civil Engineering, School of Graduate Studies
(Engineering) for their assistance and professionalism throughout the duration of the
course was conducted. Special thanks to Universiti Teknologi Malaysia (UTM) in
supplying and information especially for their assistance in supplying the relevant
literatures.
Gratitude is also owed to various people namely family, friends, colleagues
and students group of MAZ09 who not giving up to help and support along the way
to the successful completion of this capstone project report. Last but not least, special
thanks are expressly dedicated to Complex Project Management Branch, Public
Work of Department Malaysia (PWDM) for their substantial funding contribution
and cooperation to the completion of this capstone project report.
ABSTRACT
Public Works Department of Malaysia (PWDM) is one of the main
governments’ technical agency in Malaysia. PWDM has supervised numerous
government projects but still faces problems such as delays and variations due to
conflicts during construction. The main study is to investigate the effectiveness of
applying Building Information Modeling (BIM) in managing conflicts during
construction. The results of the analysis were established from surveys of questionnaires,
interviews and lastly from PWDM’s own database. The analysis was based on mixed
method which combines the qualitative and quantitative analysis approach and finally
comparing it with literatures that discusses conventional projects and projects using
BIM. This study which focuses on the conflicts during construction, finds that conflicts
are attributed to the lack of communication and coordination which eventually
contributes to the project delay. This study was conducted in order to find the root cause
of the problem and proposing an action plan that utilises the BIM approach in order to
properly manage conflicts during the construction stage. It has also come into attention
that although the proposed measures for conflict management through BIM is practical
and feasible, it will still encounter some resistance. This form of resistance has been
identified and appears in the form of cognitive, resources, motivational and political. The
results have also provided evidence that through BIM utilisation, conflicts during the
construction stage can be minimized. Other beneficial factors of applying BIM are
improved communication and coordination among the projects stakeholders. This
research study has also encountered some challenges due to the limitation of BIM
expertise and the small number of PWDM projects that actually utilises the concept of
BIM. It is with great hope that this research study will spur and generate greater interest
for those whom are involved in BIM and Architecture, Engineering and Construction
(AEC) industry as it provides an extension of BIM’s current knowledge base especially
in the aspect of construction stage conflict reduction.
v
ABSTRAK
Jabatan Kerja Raya (JKR) Malaysia merupakan salah sebuah agensi teknikal
kerajaan yang utama di Malaysia. JKR telah banyak menyelia projek-projek kerajaan
tetapi masih menghadapi masalah seperti projek lewat dan perubahan kerja yang
disebabkan oleh konflik semasa pembinaan. Tujuan utama kajian ini adalah untuk
mengkaji keberkesanan penggunaan Building Information Modeling (BIM) dalam
menguruskan konflik semasa pembinaan. Keputusan analisis adalah berdasarkan
kajian soal selidik, temubual dan juga daripada pangkalan data JKR iaitu berdasarkan
kaedah analisis kualitatif dan kuantitatif. Hasil keputusan analisis adalah
bersandarkan kajian literatur yang berkaitan iaitu antara projek konvesional dengan
projek yang menggunakan BIM. Hasil utama kajian keatas konflik semasa
pembinaan menunjukkan ia boleh berlaku akibat daripada komunikasi dan koordinasi
yang kurang berkesan dan menyumbang kearah kelewatan projek. Hasil dapatan
kajian digunakan untuk pelaksanaan pelan cadangan dengan menggunakan
pendekatan BIM dalam menguruskan konflik semasa pembinaan. Namun terdapat
beberapa kekangan yang telah dikenalpasti dalam melaksanakan pelan cadangan
tersebut iaitu dari aspek halangan kognitif, sumber, motivasi dan politik. Keputusan
juga menunjukkan bahawa pelaksanaan BIM dapat membantu mengurangkan konflik
semasa pembinaan. Selain faktor tersebut, penggunaan BIM juga dapat
meningkatkan komunikasi dan koordinasi antara semua pihak yang terlibat. Kajian
ini mendapati terdapat kekangan dalam melaksanakan kajian ini dimana pakar BIM
dan projek JKR yang menggunakan kaedah BIM adalah masih terhad di Malaysia.
Adalah menjadi harapan, kajian ini akan menjadi salah satu sumber rujukan dan
inspirasi bagi mereka yang terlibat dalam BIM dan industri Arkitek, Kejuruteraan
dan Pembinaan (AEC) khususnya, kerana kaedah ini merangkumi ilmu asas dalam
BIM terutama dalam mengurangkan konflik semasa pembinaan.
vi
vii
TABLE OF CONTENTS
CHAPTER TITLE
PAGE
DECLARATION
DEDICATION
ACKNOWLEDGEMENTS
ABSTRACT
ABSTRAK
TABLE OF CONTENTS
LIST OF TABLES
LIST OF FIGURES
LIST OF ABBREVIATIONS
LIST OF APPENDICES
ii
iii
iv
v
vi
vii
xii
xiv
xvi
xvii
1 INTRODUCTION 1
1.1 Introduction 1
1.2 Background of the Problem 3
1.3 Problem Statement 7
1.4 Research Questions 10
1.5 The Aim and Objectives of the Study 11
1.6 Scope of Study 11
1.7 Significance of the Study 12
1.8 Research Structure 13
viii
2 LITERATURE REVIEW 15
2.1 Introduction 15
2.2 Variation in Construction 15
2.3 Problems Due to Conflicts During
Construction Stage
18
2.4 Building Information Modeling 22
2.4.1 BIM and its Definition 22
2.4.2 The Use of BIM 24
2.4.3 Benefits of BIM 27
2.5 Previous Study 29
2.5.1 BIM Projects at Hong Kong, Macau
and Singapore Case Study
29
2.5.2 BIM Project at St. Silas CE Primary
School Case Study
30
2.5.3 BIM Projects in Hilton Aquarium,
Atlanta and One Island East, Hong
Kong Case Study
31
2.6 Relation of Stakeholder Satisfaction With
Conflict and Variation/Delay Between
Conventional Project and BIM Project
32
2.7 Implementation of BIM in PWDM 34
2.8 Summary 36
3 METHODOLOGY 37
3.1 Introduction 37
3.2 Research Design 39
3.3 Data Collection 40
3.3.1 PWDM Projects Data 40
3.3.2 Questionnaire Survey and
Distribution
41
3.3.3 Interview With Experience Panel
43
ix
3.4 Data Analysis 45
3.4.1 Reliability Test 45
3.4.2 Normality Test 46
3.4.3 Frequency Analysis 46
3.4.4 Mean Average Index 46
3.4.5 Relative Importance Index (RII) 47
3.5 Summary 48
4 DATA COLLECTION AND ANALYSIS 49
4.1 Introduction 49
4.2 Findings of PWDM Data Projects 49
4.2.1 Batu Pahat Hospital : Package B –
Upgrading of OT, Emergency Ward,
HDW, Blood Bank, Lab, CSSD &
CT Scan and Registration
50
4.2.2 Shah Alam Hospital : Package II -
Building Works
52
4.2.3 National Cancer Institute, Putrajaya 54
4.3 Interview Data and Analysis 57
4.3.1 Expert Interview Analysis 58
4.4 Questionnaire Survey and Analysis 59
4.4.1 Demographic Profile 59
4.4.2 Knowledge Level in Building
Information Modeling
65
4.4.3 Implementing BIM in Project 66
4.4.4 Questionnaire Survey Analysis 67
4.4.5 Frequency and Mean Score Analysis 70
4.4.6 Relative Importance Index (RII) 73
4.5 Summary 74
x
5 DISCUSSION AND RECOMMENDATION 76
5.1 Introduction 76
5.2 Understanding the Conflicts 76
5.2.1 Conflict in Construction 77
5.2.2 Type of Conflicts 78
5.2.3 Factor of Conflicts 80
5.2.4 Causes of Conflicts 82
5.2.5 Summary of Conflict Stage 84
5.3 Comparing the Conflicts 87
5.3.1 Conflict Consequences 87
5.3.2 Conflict Overcome 89
5.3.3 Benefit of BIM in Project 91
5.4 Recommendation 93
5.4.1 Root Cause Analysis 94
5.4.2 Benefit Matrix 96
5.4.3 Strategy in Managing Conflicts 97
5.4.4 Recommendation in Managing
Conflicts
100
5.5 Resistances 103
5.5.1 Cognitive Hurdles 104
5.5.2 Resources Hurdles 104
5.5.3 Motivational Hurdles 105
5.5.4 Political Hurdles 106
5.6 Summary 106
6 CONCLUSION 109
6.1 Introduction 109
6.2 Conclusion 109
6.2.1 Objective 1: Identifying Conflicts
During Construction
110
6.2.2 Objective 2: Comparing the
Conflicts Between Conventional
Project and BIM Project
111
xi
6.2.3 Objective 3: Making a
Recommendation of Managing
Conflicts
112
6.3 Limitation of Study 113
6.4 Recommendation for Further Study 113
6.5 Conclusion Remark 114
REFERENCES 115
Appendices A-H 121-146
LIST OF TABLES
TABLE NO. TITLE
PAGE
2.1 Table of Various Causes of Variation and Their
Categorization
17
2.2 Summary of The Literature on the Potential
Problems in Executing D&B Projects in the
Construction
20
2.3 Data and Information of Two Projects
Implementing BIM
32
2.4 PWDM Pioneer Projects Using BIM and Its
Objectives
34
3.1 Interview Questions for Conventional Projects 44
4.1 Batu Pahat Hospital Project Information 50
4.2 Shah Alam Hospital Project Information 52
4.3 National Cancer Institute Project Information 54
4.4 Basic Information of Expert Panel 58
4.5 Cronbach’s Alpha Value 68
4.6 Skewness and Kurtosis Value for Section B 69
4.7 Skewness and Kurtosis Value for Section C 69
4.8 Likert Scale – Measurement of Agree and Disagree 70
4.9 Section B – Frequency and Mean Score Analysis 71
4.10 Section C – Frequency and Mean Score Analysis 72
4.11 Section B - Relative Importance Index (RII) 73
4.12 Section C - Relative Importance Index (RII) 74
5.1 Ranking for Conflict in Construction 77
xii
xiii
5.2 Ranking for Type of Conflicts in Construction 79
5.3 Table of Various Statements Related to the Type of
Conflicts
80
5.4 Ranking for Factor of Conflict in Construction 80
5.5 Table of Various Statements Related to Type of
Conflicts
82
5.6 Ranking for Causes of Conflicts in Construction 83
5.7 Table of Various Statements Related to Types of
Conflicts
84
5.8 Ranking for Conflict Stages During Construction 84
5.9 Ranking for Conflict Consequences in
Conventional Projects
87
5.10 Ranking for Conflict Overcome in Projects 89
5.11 Ranking for Benefits of BIM in Projects 91
5.12 Benefits of BIM in the NCI Project 93
5.13 Action Plan by Using BIM 94
5.14 Possible Solution for Managing Conflicts by Using
BIM
95
5.15 Benefit Matrix – QW, TW, BO And SE 96
5.16 ERRC Grid – Elements to Minimize the Conflicts
by Using BIM in PWDM Projects During
Construction Stage
98
LIST OF FIGURES
FIGURES NO. TITLE
PAGE
1.1 BIM Cycle Phases 2
1.2 Flow Chart of Basic Work Process in
Implementing PWDM Project Delivery
6
1.3 BIM Benefits Contributing the Most Value 9
2.1 Timeline of BIM Definition by Researchers 22
2.2 Timeline of BIM Definition by Researchers 23
2.3 The components of a BIM use 25
2.4 The BIM use purposes 25
2.5 Table of BIM use Characteristic 25
2.6 BIM Uses on each project stages 26
2.7 Flowchart on how the BIM uses can be applied to
a project
27
2.8 Five Projects Utilising BIM in Hong Kong, Macau
and Singapore
30
2.9 CLD of Satisfaction of Stakeholder by using BIM
and Conventional in the Project
33
2.10 BIM projects in PWDM 34
3.1 Schematic of Research Approach 38
3.2 Research Schedule of Work Programme 39
3.3 Likert Scale 43
4.1 Financial progress for Batu Pahat hospital 51
4.2 Financial progress for Shah Alam hospital
53
xiv
xv
4.3 Financial progress for National Cancer Institute
project
56
4.4 Respondent’s Gender Profile 60
4.5 Respondent’s Age Profile 60
4.6 Respondent’s Education Profile 61
4.7 Respondent’s Profession Profile 62
4.8 Respondent’s Experience in Project/Construction
Profile
62
4.9 Respondent’s Professional Involvement Profile 63
4.10 Respondent’s JKR Staff and Non-JKR Staff
Profile
64
4.11 Respondent’s JKR Sector Profile 64
4.12 Respondent’s Grade Profile of JKR Staff 65
4.13 Level of knowledge in BIM of Respondents 66
4.14 Organization Implementing BIM by Respondents 67
4.15 Likert Scale – Level of Agree and Disagree 70
5.1 Summary of Conflict Stages 86
5.2 Four Action Framework in BOS 97
5.3 Strategic Canvas for Minimizing Conflicts by
Using BIM
99
LIST OF ABBREVIATIONS
AEC Architect, engineering and construction
BIM Building Information Modeling
BOS Blue Ocean Strategy
CLD Causal Loop Diagram
EOT Extension of time
HODT Head of Design Team
HOPT Head of Project Team
IBS Industrial Building System
ICT Information and communication technology
JKR Jabatan Kerja Raya
LAD Liquidated Ascertain Damages
M&E Mechanical and electrical
NCI National Cancer Institute
PSG Problem Solve Governance
PWDM Public Work of Department Malaysia
RII Relative importance index
RISP Registered IBS System Provider
RMK-9 Rancangan Malaysia ke-9
SKALA Sistem Kawal dan Lapor
SPSS Statistic Package for Social Science
VO Variation order
xvi
LIST OF APPENDICES
APPENDIX TITLE
PAGE
A Research Schedule 121
B Sample of Questionnaire 122
C Picture of Batu Pahat Hospital 131
D Picture of Shah Alam Hospital 132
E Picture of National Institute Cancer 133
F Picture of BIM Uses in NCI Project 134
G Summary of Interview with Expert Analysis 139
H Root Cause Analysis 146
xvii
CHAPTER 1
INTRODUCTION
1.1 Introduction
The construction industry is in need to move forward through ‗change‘; from
the traditional or conventional method to the Building Information Modelling (BIM)
method. This involves the entire project phase, from the project planning up until the
completion and handing it over to the operators. Wong et al. (2013) stated that ―Due
to low productivity levels in the construction industry, there is a continuous urge for
its improvement by using those innovative techniques and methods already adopted
by other industries‖.
Building Information Modeling (BIM) is a modern technology which was
introduced by the Architecture, Engineering and Construction (AEC) industry. In
Malaysia, BIM had formally surfaced during the early year of 2007 by the Public
Works Department (Latiffi et al., 2013). There are many definitions of BIM and
according to Penn State Department Architectural Engineering (2010), ―Building
Information Modelling (BIM) is a process focused on the development, use and
transfer of a digital information model of a building project to improve the design,
construction and operations of a project or portfolio of facilities.‖
2
Figure 1.1 shown the BIM cycle phases, based on an article linking about the
daily life of BIM (Dispenza, 2010), which can carry information downstream all the
way from the planning phase up until its operational and maintenance phases.
Figure 1.1: BIM Cycle Phases (Adopted from Buildipedia.com., 2010)
Public Works Department of Malaysia (PWDM), also known as Jabatan
Kerja Raya (JKR) started using BIM in their pilot projects, which were the National
Cancer Institute of Malaysia, followed by SMK Meru Raya (Ipoh, Perak), SK
Tanjung Minyak 2 (Melaka), SPRM Administration Building (Shah Alam, Selangor)
and Klinik Kesihatan Maran,-KK Jenis 5 (Maran, Pahang) (Latiffi et al., 2013).
Latiffi et al. (2013) also states that the intention of BIM application in these pilot
projects are to facilitate problems solving during the construction stage, as the aims
of BIM is to prevent disputes between the different construction players and parties.
According to Peter et al. (1997), disputes require quick resolutions and it is extension
from the conflicts if it is not properly managed.
As interest in the BIM workflow is growing immensely amongst industry
players (Rooney, 2014), many agencies including the public sector are looking
forward to inspire and influence designers and contractors to team up and getting
actively involved in applying the BIM method. Being a technical agency, PWDM
3
has initiated to kick-off the pilot projects in order to identify the benefits of using
BIM (JKR, 2014).
The intention of this research is to explore BIM potential in reducing
conflicts during the construction stage since that a common project environment
hugely draws in potential conflicts (Verma, 1998). These conflicts come in the form
of scope change, design variation and drawing discrepancies among disciplines due
to the lack of communication and coordination during the planning and design stage.
(Mohamud, 2014).
1.2 Background of the Problem
Generally, project faces problems during the construction stage (Verma,
1998) and this will eventually lead to cost and time overruns (So, 2004). A study by
Memon et al. (2011) on causative factors leading to construction cost overrun and
delay in time for projects in Malaysia is mainly due to these factors:
Poor design
Unrealistic contract requirements and duration
Lack of experience
Late delivery of materials and equipment
Poor relationship between the management and labour
Delay in the preparation and approval of drawings
Inadequate planning and scheduling
Poor site management and supervision resulting in errors during construction.
According to Whitfield and Blackwell (2012), the main cause of conflicts is
due to the misunderstanding from poor communication practices in the project.
4
In the PWDM organization, the Business Sector is divided into several
branches which is responsible in managing projects given by the clients (government
sector), which involves the planning stage up until handover. Projects are led by the
Head of Project Team (HOPT). The clients will award the projects with an agreed
completion time, cost, quality and scope of work. The Expert Sector will be
appointed by HOPT as the Head of Design Team (HODT) with each disciplines
(Architect, Civil & Structure, Geotechnical, Electrical, Mechanical, Quantity
Surveyor, etc.) required to fulfil the project‘s design within the agreed time, cost,
quality and scope.
When the scope is given by the client, the architect will start with the concept
design and the client is required to approve the concept design before the architect
can proceed with the preliminary design. This is provided that the ‗confirmed
proposed site‘, reasonable cost and reasonable time duration has been incorporated in
the design. But this has not been the case and HODT‘s are pressured by the HOPT‘s
to complete the design within a short period of time without beforehand properly
completing and finalizing the projects brief. Delay by the client in finalising the
architect‘s concept design has also contributed to the delay and problems of the
successive design stage efforts.
The situation above also occurs in the design and build method, which is
faced by the consultants, contractors, clients and PWDM‘s project team. The client
needs to provide the project brief to the HOPT within the agreed time, cost, quality
and scope. The appointment of HODT is to ensure that the statements of needs are
prepared and completed before appointment of any contractors. Contractors are
appointed to execute the project, starting from the design stage up until the handover
stage (including the defect and liability period). The concept design comes from the
HODT‘s architect to verify that the project is within the agreed cost given by the
client. If the project brief, especially the projects scope of work is not completed
during the planning stage; the projects concept design and need statement will not be
clearly defined.
During the design stage, it is common that the consultants and the contractors
do not put serious attention to the design coordination amongst the design
5
disciplines. It is also a fact that sometimes the HOPT is forced to pressure these
parties to complete the design works within a short period of time.
In addition, conventional projects as well as design and build projects also
experiences the same problem during the early stage of a project. Whenever the
HOPT holds a coordination/technical meeting of projects, the meeting objectives are
not agreed or met, even though in the presence of the clients. In certain occasions,
roles and responsibilities of HOPT‘s and HODT‘s with the clients are not clear
resulting in ineffective communication.
Figure 1.2 indicates a flow chart of basic work process in implementing
project delivery based on Quality Management System (JKR,2014).
6
Figure 1.2: Flow Chart of Basic Work Process in Implementing PWDM Project
Delivery
In PWDM, conflicts mainly occurs during the construction stage and this will
lead to delay in project completion. A study by Mohamud (2013) found that there are
Project given by the Client
HOPT receive Project Brief
HOPT appoint HODT‘s
Method in Implementing of project
(In-house-conventional/Consultant-conventional/Design and Build)
HODT Architect start a concept design
based on project brief and prepare
preliminary cost estimation
Procurement Stage if
using Design & Build
method
HODT‘s Preparing
Preliminary Design
HODT‘s Preparing
Detailed Design
Construction
Handing Over
Procurement Stage if
using Conventional
method
Preparing Need
Statement/Term of
Reference
7
three (3) main factors on each categories of delay that may occur in projects during
the planning and design stage. These factors are:
a. Client related
A. Slowness in decision making process
B. Change order
C. Client interference
b. Consultant/Designer
A. Poor communication and coordination
B. Poor monitoring and control of progress of work
C. Errors and discrepancies in design documents
From the study done by Mohamud (2013), it is shown that, one of the
important factors in consultant/designer category is errors and discrepancies in
design documents that will lead to delay during the construction stage.
Although PWDM has introduced new approaches such as Registered IBS
System Provider (RISP) and Problem Solve Governance (PSG), projects are still
experiencing delays due to the internal and external problems resulting in improper
implementation of the approaches. (JKR, 2014).
1.3 Problem Statement
PWDM is a technical agency that has supervised a vast number of projects
which includes the planning stage up until the projects handover. A total number of
810 building projects for RMK9 and RMK10 registered in ‗Sistem Kawal Lapor‘ in
2013 (SKALA, 2014). On Jun 1st, 2009, Utusan (2009) has reported that 80% of
PWDM projects are delayed and this hasleft a negative impression in the public‘s eye
in regards to the organization. Even though all of the projects were completed, there
is a major issue in projects completion delay. According to the SKALA report
8
(2013), an estimation of 57% of projects were delayed from the list of 216 projects
which were in the construction phase (Mohamud, 2014).
Several reasons have been identified which had contributed to the delay of
projects by researchers (Luh et al., 2006). Some of the delay factors which may be
related to this study are:
a. Delays in design works and frequent changes in orders/design (Arditi
et al., 1985)
b. Increases in the scope of the work (Semple et al., 1994)
c. Changes of design (Ogunlana et al., 1996)
d. Poor design and changes in orders/design (Al-Monami, 2000)
e. Inadequate early planning of the project (Faridi and El-Sayegh, 2006)
According to Mohamud (2014), the top five (5) most important causes of
project delay in PWDM are:
a. Poor site management and supervision
b. Financial difficulties – poor cash flow management
c. Inadequate contractor experience
d. Poor communication and coordination
e. Slow in the decision making process
The purpose of this study is to investigate the effectiveness of applying BIM
in managing conflicts during the construction stage. The study area is to focus and
locate these conflicts that can potentially contribute to the delay and variation of
PWDM projects. It will also emphasize on the lack of coordination within the
projects planning and design stages. From the results and findings, we will try to
explore BIM‘s potential in managing these conflicts in order to ensure a more
efficient coordination and communication among the project team members and
parties. Hence, minimizing conflicts during the construction stage.
9
Figure 1.3: BIM Benefits Contributing the Most Value (McGraw Hill, 2009)
Figure 1.3 shows the top benefits contributing the most value to a project,
taken from the McGraw Hill (2009). The top benefits of using BIM are:
i. Reduced conflicts during construction
ii. Improved collective understanding of design intent
iii. Improved overall project quality
iv. Reduced changes during construction
v. Reduced number of Request for Information (RFIs)
vi. Better cost control/predictability
The most immediate benefits of utilising BIM in projects is that it produces
better designs and increases efficiency and productivity (Batcheler and Preger,
2011). The design and construction documentations are closely linked, and the time
to produce these documents have been reduced significantly through the application
of BIM. This was achieved by the reduction in time required to evaluate different
alternatives thus minimizing the time to execute these design changes. This is
particularly important to the clients as it maximize the cumulative benefits of BIM
through enhancing the efficiency in project delivery, reducing risks and optimising
10
client‘s satisfaction (Batcheler and Preger, 2011). Apart from efficiency and
productivity, BIM facilitates to optimize project coordination amongst various
disciplines (Autodesk, 2011).
Findings from the study indicates that conflicts will more likely contribute to
project delay and variations to PWDM projects. This is due to the lack of efficient
and effective project communication and coordination. From the analysis results,
conflicts are likely to be reduced by applying BIM as it also helps to ensure a better
communication and coordination amongst project stakeholders. Hence, preventing
the project from further delays and variations.
1.4 Research Questions
The research questions of this study must be relevant and significant in order
to provide solutions to the common problems experienced by the AEC industries and
specifically, within PWDM. The questions relevant to this study are:
i. What is conflict in respective to project construction
ii. What are the problems that triggers conflicts during the construction?
iii. What are the factors contributing to delays and variations during
construction stage?
iv. Why conflicts occur in projects during construction stage?
v. How to overcome these conflicts which occurs during the construction
stage?
vi. What is BIM and how is BIM relevant to projects during the construction
stage?
vii. Why use BIM in to reduce conflicts during the construction stage?
viii. How is BIM able to reduce these conflicts?
ix. How to manage the conflicts by applying BIM?
x. Is there any resistance to implement BIM?
11
1.5 The Aim and Objectives of the Study
The focal objective of this study effort is to investigate the effectiveness of
applying BIM in managing conflicts during the construction stage. The study will
address the followings:
a. To identify conflicts occurring during construction stage for conventional
projects and BIM projects
b. To compare the conflicts between conventional projects and BIM projects
c. To make recommendations on managing conflicts in order to reduce the
conflicts related problems
1.6 Scope of Study
The scope of this study is limited to hospital projects that have been delivered
by PWDM only. This is due to the reason that up until the year 2014, there was only
one project that has been completed which utilises the BIM approach; that is the
National Cancer Institute, Putrajaya. The project was awarded as a design and build
contract. Therefore, only design and build hospital projects from RMK-9 are
comparable to the completed BIM-utilised project. All of the projects data will be
gathered from the PWDM database, ―Sistem Kawal & Lapor‖ (SKALA). The data
will be gathered and separated into conventional projects and BIM projects. These
two group data‘s will be compared to the variation orders that has been put forward
due to the conflicts arising during the construction stage.
12
1.7 Significance of the Study
The significance of the study is divided into three categories which is aimed
at closing the gap between problems in a project environment by minimizing
conflicts during the construction stage through the application of BIM.
i. For PWDM
The study of this capstone project is to show that by using BIM tools in
PWDM projects, there will be an improvement throughout the PWDM project
phases. This improvement will be visible especially in the communication and
coordination amongst project team parties which focuses on reducing conflicts
during the construction stage.
ii. For PWDM Staff
It is hoped that the study will provide benefits and useful information on the
implementation of BIM methodology within PWDM projects and eventually creating
greater awareness and readiness when they themselves are actively involved in future
BIM related projects.
iii. Significance to Knowledge
The findings of this study would be of interest for those whom are involved
directly in BIM and also the construction industry as it extends the current
knowledge base for BIM. This is mainly due to its capability in reducing conflicts
hence, providing greater benefits to the construction industry. It is also hoped that in
the near future, the topic of BIM can be further explored by other researchers.
13
1.8 Research Structure
This research study, also known as the capstone project will specifically
focus on PWDM. The first chapter will briefly discuss about the Introduction,
Problem Statement, Research Questions that will provide Aim and Objectives of the
research and the scope of the study. Most importantly is the significance of the study
towards providing benefits to PWDM and its staff.
Chapter 2 will be the Literature Review which will discuss scholars and
academic findings related to this study. The sub-topics for this chapter is:
Variation and conflicts during construction phase,
What is BIM?
Relationship between stakeholder satisfactions by implementing
BIM in projects.
Previous study and implementations of BIM within PWDM will also be
discussed briefly in this chapter in order to further understand BIM projects and its
benefits.
Research Methodology will be covered in Chapter 3. The focus is to provide
a step by step guideline for the researcher in order to successfully achieve the aims
and objectives of this capstone project. The methodology of this study is firstly
kicking off by collecting data and information. Then, secondly the data and
information will be analysed by using qualitative and quantitative method of research
design. Finally, the recommendations in that has been found through this research
study will be proposed in Chapter 4.
Chapter 4 mainly discusses the analysis and results of the study. The analysis
and result will be done comprehensively in regards to the conflicts through
comparison between conventional projects and BIM projects. Apart from that, the
analysis also will be considering the questionnaires taken by the stakeholders
especially their experiences in conducting conventional projects and BIM projects.
14
Furthermore, the discussion of the results and recommendations will be
covered in Chapter 5 through the proposal of a strategic canvas in order to minimize
the conflicts during construction through the application of BIM.
Last but not least, Chapter 6 will be the conclusion of this study in regards to
the initial aims and the objectives whilst also including the limitations of the study.
REFERENCES
A. Bakar A. A. (2013). JKR BIM Technical Paper, JKR Civil Engineer Committee
Meeting. 13th September. Renaissance Hotel, Kota Bharu, Kelantan.
A. Bakar A. A., (2014). Preparation of Final Draft JKR BIM Guide and Standard
Meeting, JKR BIM Committee Meeting. 13th November. Cawangan
Pengurusan Projek Kompleks, JKR Headquarters, Menara PJD, Kuala
Lumpur.
A. Karim N. (2014). Building Information Modeling Awareness and Readiness at
Jabatan Kerja Raya Malaysia, Master in Project Management, University of
Technology Malaysia, Skudai.
A. Zaki A. B., (2013). Causal Loop Diagram, System Thinking Course for Master of
Project Management. 14-15th September. Universiti Teknologi Malaysia,
Kuala Lumpur.
Latiffi A., Mohd S., Kasim N. and Fathi M. S. (2013). Building Information
Modeling (BIM) Application in Malaysian Construction Industry.
International Journal of Construction Engineering Management, 2(4A), 1-6,
viewed July 7, 2014 from http://journal.sapub.org/ijcem
Abdullah S. A., Sulaiman N. and Latiffi A. (2014). Building Information Modeling
(BIM) from the perspective of Facilities Management (FM) in Malaysia.
International Real Estate Research Symposium 2014 (IRERS), 29-30 April.
Ministry of Finance Malaysia.
Acharya N. K. and Lee Y. D. (2006). Conflicting factors in construction projects:
Korean perspective. Engineering, Construction and Architectural
Management, 13(6), 543-566.
Ali K N and et al. (2013). Building Information Modelling Awareness and Readiness.
University of Technology Malaysia, Royal Institution of Surveyors Malaysia.
116
Anderson Jr. L. L. and Polkinghorn B. (2008). Managing Conflict in Construction
Megaprojects: Leadership and Third-Party Principles. Conflict Resolution
Quarterly, 26(2), 167-198.
Arain F. M., Assaf S., and Pheng L. S. (2011). Causes of Discrepancies between
Design and Construction. Architectural Science Review, 47(3), 237-249.
Ashcraft H. W., (2008). Building Information Modeling: A Framework for
Collaboration, Construction Lawyer, 28(3).
Autodesk (2003). Building Information Modeling in Practice. Autodesk Building
Solutions, Autodesk Inc., pp. 2, viewed 4 August 2014 from
http://www.ddscad.com/BIM ___In_Practice.pdf
Autodesk (2011). Realizing the Benefits of BIM, Autodesk Building Information
Modeling, Autodesk Inc., pp. 1-12
Azhar S., Nadeem A., N Mok J. Y., and Y Leung B. H. (2008). Building Information
Modeling (BIM): A New Paradigm for Visual Interactive Modeling and
Simulation for Construction Projects. First International Conference on
Construction in Developing Countries (ICCIDC-I), 4-5 August. Karachi,
Pakistan, pp. 436-446.
Batcheler B and Preger A. (2011). The Unmistakable Benefits of BIM Enhanced
With PIM. National Institute of Building Sciences buildingSMART alliance,
Journal of Building Information Modeling, pp. 22-23.
Balfour Beatty (2012). St. Silas CE Primary School-Using BIM to deliver
Stakeholder Engagement, Balfour Beatty Construction Services UK, viewed 4
August 2014, from http://www.balfourbeattycsuk.com/capabilities/building-
information-modelling/
BIM Malaysia Steering Committee (2013). BIM Malaysia Steering Committee
Inaugural Meeting, Kuala Lumpur, 23 September.
Dada M. O. (2013). Conflicts in Construction Projects Procured Under Traditional
and Integrated Systems: A Correlation Analysis. International Journal of
Constrcution Supply Chain Management, 3(1), 1-15.
Demian P. and Walters D. (2013). The Advantages of Information Management
Through Building Information Modeling. Construction Management and
Economics, DOI:10,1080/01446193.2013.777754.
Dispenza K. (2010). The Daily Life of Building Information Modeling (BIM),
Buildipedia.com, viewed 7 July 2014, from http://buildipedia.com/aec-
117
pros/design-news/the-daily-life-of-building-information-modeling-
bim?print=1&tmpl=component
Dreu D. and Weingart L. R. (2003). Task Versus Relationship Conflict, Team
Performance, and Team MemberSatisfaction: A Meta-Analysis. Journal of
Applied Psychology, 88(4), 741-749.
Elizabeth Fanning (2005). Practical Assessment, Research & Evaluation, Practical
Assessment. Research & Evaluation, 10(2), 1-14.
Fisher M. and Tatum C. B. (1997). Characteristic of Design-relevant Constructability
Knowledge. Journal of Construction Engineering and Management,
123(123), 253-260.
Ismail A., Pourrostam T., Soleymanzadeh A., and Ghouyounchizad M. (2012).
Factors Causing Variation Orders and their Effects in Roadway Construction
Projects. Research Journal of Applied Science, Engineering and Technology,
pp. 4949-4972.
ISO Standard (2010). ISO 29481-1:2010(E). Switzerland: The International
Organization for Standardization.
Jabatan Kerja Raya Malaysia (2014). JKR BIM website, viewed 3 August 2014, from
http://172.20.1.63/bim/index.php?option=com_content&view=frontpage&Ite
mid
Kim W. Chan and Renée Mauborgne. (2005). Blue Ocean Strategy. Harvard
Business School Publishing Corporation, USA
Kreider R. G. and Messner J. I. (2013). The Uses of BIM-Classifying and Selecting
BIM Uses. (Version 0.9), The Pennsylvania University, University Park, PA,
USA: Penn State Computer Integrated Construction, pp.6 from
http://bim.psu.edu.
Lam E. W. M. and Chan A. P. C. (2013). Potential Problems of Running Design-
build Projects in Construction. HKIE Transaction, 10(3), 8-14.
Luke G. J. (2007). An Assessment of the service quality expectations and perceptions
of the patients of Awali Hospital in the Kingdom of Bahrain, Unpublished
masters dissertation, Rhodes Investec Business School.
M Azlan A. A. (2013). JKR BIM Road Map, JKR BIM Road Map Conference-
Industry Engagement. 4th April. Dewan Tan Sri Mahfuz, JKR Malaysia,
Kuala Lumpur. viewed 3 August 2014, from http://
172.20.1.63/bim/index.php?option =com_content&view=frontpage&Itemid
118
McGraw Hill (2008). SmartMarket Report: Building Information Modeling (BIM) –
Transforming Design and Construction to Achieve Greater Industry
Productivity. New York: McGraw Hill Construction, pp. 2.
McGraw Hill (2009). SmartMarket Report: The Business Value of BIM-Getting
Building Information Modeling to the Bottom Line. New York: McGraw Hill
Construction, pp. 22.
Memon A. H., A. Rahman, I. and A. Azis A. A. (2011). Preliminary Study on
Causative Factors Leading to Construction Cost Overrun. International
Journal of Sustainable Construction Engineering & Technology, 2(1), 57-71.
Messner J. I., (2013). The Uses of BIM. Penn State University, viewed 4 August
2014, from http://bim.psu.edu/Uses/
Mohamud M. Z. (2014). Method to Resolve Building Project Delay, Faculty of Civil
Engineering, Master in Project Management, University of Technology
Malaysia, Skudai.
National BIM Standard (2007), (cited in Tammy L M 2008). Building Information
Modeling and the Interactive Capability Maturity Model, University of
Oklahoma, Norman, Oklahoma, pp. 2.
National BIM Standard (2010). What is a BIM. National Institute of Building
Science buildingSMART alliance, retrieved August 4, 2014 from
http://www.nationalbimstandard.org/faq.php
Owolabi J. D., Amusan L. M., Oloke C. O., Olusanya O., Tunji O. P. (2014). Causes
and Effect of Delay on Project Construction Delivery Time. International
Journal of Education and Research, 2(4), 197-208.
Onyegiri I., Nwachukwu C. C. and Jamike O. (2011), Information and
Communication Technology in the Construction Industry. American Journal
of Scientific and Industrial Research, 2(3), 461-468.
Oxford University (2014). Oxford Learner’s Dictionary of Academic English.
Oxford University Press.
Penn State Department Architectural Engineering (2010). BIM Project Execution
Planning Guide. (Version 2.0). The Pennsylvania State University, USA.
Penttila (2006) (as cited in Succar 2009). The Five Components of BIM Performance
Measurement, University of Newcastle, NSW Australia, pp.2.
119
Per Anker Jensen and Elvar Ingi Johannesson (2013). Building information
modelling in Denmark and Iceland, Engineering. Construction and
Architectural Management, 20(1), 99-110.
Peter Fenn, David Lowe and Christopher Speck (1997). Conflict and Dispute in
Construction. Construction Management and Economics, 15(6), 513-518.
Rooney K. (2014). BIM Education–Global-Summary-2013. (Version 1.0).
Construction Information System Limited, NATSPEC, Australia
Ruben Ndihokubwayo (2008). An Analysis of the Impact of Variation Orders on
Project Performance. Cape Peninsula University of Technology.
Sekaran U. (2003). Research Method for Business: A Skill Building Approach. (4th
Edition), John Wiley & Sons.
Sikan, H. (1999). Variation Orders in Construction Contract. Department of Quantity
Surveying, Faculty of Built Environment, Universiti Teknology Malaysia,
Journal Alam Bina. 02, 48-53.
SKALA (2014). Sistem Pengurusan Projek JKR (SKALA), Jabatan Kerja Raya
Malaysia, retrieved August 3, 2014 from http://skala.jkr.gov.my/
So C. K. (2004). Conflict and Cross Effect in Fire Services Installation and Building
Constrcution in New Projects. International Journal on Engineering
Performance-Based Fire Codes. 6(4), 322-332.
Succar (2009). The Five Components of BIM Performance Measurement. University
of Newcastle, NSW Australia, pp.2.
Sunday O. A. (2010). Impact of Variation Orders on Public Construction Projects,
26th Annual ARCOM Conference. 6-8 September. Ministry of National
Development, Independence House, Victoria. In: Egbu, C. (Ed) Procs, Leeds,
UK, Association of Researchers in Construction Management, pp. 101-110.
Verma V. K. (1998). Conflict Management. Project Management Institute Project
Management Handbook, Chapter 22, 353-376.
Whitfield J. and Blackwell W. (2012). Conflict in Construction. Construction
Management and Economics, 497-503.
120
Wong Andy K. D., Wong Francis K. W. and Nadeem A. (2009). Attributes of
Building Information Modeling and Its Development in Hong Kong. The
HKIE Transactions, 16(2), 38-45.
Wong Andy K. D., Wong Francis K. W. and Nadeem A. (2013). Attributes of
Building Information Modeling Implementations in Various Countries.
Architectural Engineering and Design Management. 6(4), 288-302.
80 peratus projek JKR lewat. (2009, June 1). Utusan Online, Retrieved July 9, 2014,
from http://www.utusan.com.my/utusan/info.asp?y=2009&dt=0601&pub=
Utusan_Malaysia&sec=Terkini&pg=bt_08.htm