Micro Turbine Testing Program

download Micro Turbine Testing Program

of 27

Transcript of Micro Turbine Testing Program

  • 8/14/2019 Micro Turbine Testing Program

    1/27

  • 8/14/2019 Micro Turbine Testing Program

    2/27

    SCE Microturbine Generator (MTG)

    Testing ProgramGoal & Objectives:

    Goal: determine the performance, reliability, operability,availability, maintainability, and overall characteristics of commercially available MTGs.Objectives: compare MTGs actual performance toperformance specifications and industry/other standards,such as emissions.

    Accomplishments: $3.0 million program in progress since 1996 12 MTGs tested or in test Two to four more MTGs expected for testing Completed machine performance tests on 8 MTGs

    Completed initial electrical behavior testing Over 44,000 hours of testing Implemented live browser enabling technology

    DOE Program Manager: Debbie HaughtSCE Program Manager: Stephanie Hamilton

  • 8/14/2019 Micro Turbine Testing Program

    3/27

    SCEs MTG ProgramGoal & Objectives:

    Goal: determine the performance, reliability, operability, availability,maintainability, and overall characteristics of commercially available MTGs.

    Objectives: compare MTGs actual performance to performancespecifications and industry/other standards, such as emissions.

    Collaborations: DOE, CERTS, EPRI, CEC, CERA, UCI, Connected Energy,GE, SNL, ORNL, MTG mfgrs.

    Accomplishments: $3.0+ million program in progress since 1996; results have driven

    improvements to MTGs and program builds public awareness 12 MTGs tested or in test; two to four more MTGs expected for testing Over 48,000 hours of testing

    Completed machine performance tests on eight MTGs Completed initial electrical behavior testing Numerous site tours, presentations, papers

  • 8/14/2019 Micro Turbine Testing Program

    4/27

    SCE MTG Test Bed at University of California at Irvine (UCI)

    4 test bays 400 amp 480 volt service 100 psig natural gas with ability

    to blend for lower Btu testing Cogen heat dissipation ability 80 kW load banks for stand

    alone and micro grid testing Electronic data acquisition and

    instrumentation for gas & electric Veteran two-person testing crew Standardized testing procedures Ability to do specialized/custom

    testing

  • 8/14/2019 Micro Turbine Testing Program

    5/27

    Desirable Attributes vs. Test Parameters ATTRIBUTES

    Heat rate 12,000 to 16,000BTU/kWh

    Good Part Load Performance

    Emissions < 9 ppm Power Quality < IEEE 519 Noise < 70 dBa Endurance = 40,000 hours Installation = Easy & Cheap

    TEST PARAMETERS Overall unit efficiency Net Power Output Emissions Power Quality Noise Endurance

    Ease of Installation Operability Maintainability

  • 8/14/2019 Micro Turbine Testing Program

    6/27

  • 8/14/2019 Micro Turbine Testing Program

    7/27

  • 8/14/2019 Micro Turbine Testing Program

    8/27

    Capstone 30 kW DescriptionModel 330 rated output: 30 kW at ISO480 VAC, 3-phase, 60 Hz

    Recuperated single stage radial flowcompressor and turbine on a singleshaft, integrated with generator Equipped with a low NOx combustor Not equipped with a waste heatrecovery boiler Fourth generation unit

    One unit only capable of grid connectOne unit capable of stand alone andgrid connect operation

  • 8/14/2019 Micro Turbine Testing Program

    9/27

    Capstone 28 kW ResultsSeveral overspeed trips were resulting from flame control

    algorithm; Capstone remotely downloaded revised controlsystem software; no overspeed trips since software revisedReliable operation following resolution of overspeed

    Comparing manufacturers efficiency and heat rate claimswith test results converted to a common basis, resulted intesting results consistent with claims as shown below@ 70F, about sea level, and LHV:

    (tested) (claimed)

    Efficiency 23.7% 0.45% 24.5% 0.5%

    Heat rate 14,415 BTU/kWh 13,931 BTU/kWh

  • 8/14/2019 Micro Turbine Testing Program

    10/27

    Capstone 28 kW ResultsTotal Harmonic Distortion (THD) requirements specified by IEEE519 were met: Voltage THD: 1.6% measured average < 5% IEEE 519

    Current THD: 5.87% measured average < 8% IEEE 519Noise measurement taken at 2m due to site conditions, e.g.obstructions and site compressor noise. Noise measured 70 dBA @ 2m, consistent with manufacturers claim, 65 dBA, 10m.Emissions test results met SCAQMD requirements:

    M anufacturer Claim SCAQM D Standard(Rule 1303 )

    Test Resu lts

    NOx: < 9ppm

    (0.023 lb/hr)

    NOx: 0.2 lb/hr 0.0031 lb/hr

    No Claim CO: 11.0 lb/hr 0.11 lb/hr

  • 8/14/2019 Micro Turbine Testing Program

    11/27

    Grid Impact Testing

    Uncovers problems potentially hinderinggrid interconnection of DG Testing needed to determine:

    Power quality Protection/ anti-islanding issues

    Interconnection standards/rules Dynamic behavior so simulation modelscan be built

  • 8/14/2019 Micro Turbine Testing Program

    12/27

    Capstone Voltage & Current Waveforms

    Voltage Waveform Snapshot Current Waveform Snapshot

    Phase A Voltage - THD 1.6% Phase A Current - THD 7.33%Phase B Voltage - THD 1.6% Phase B Current - THD 6.98%Phase C Voltage - THD 1.6% Phase C Current - THD 5.64%

    50.0A

    0.0A

    -50.0A

    450.0V

    0.0V

    -450.0V

    833.33 us/div0sec 16.67ms

    Snapshot WaveformModel 7100

    06/22/99 01:20:51:190 PM

    Three Phase Wye

    1V

    2V

    3V

    50.0A

    0.0A

    -50.0A

    450.0V

    0.0V

    -450.0V

    833.33 us/div0sec 16.67ms

    Snapshot WaveformModel 7100

    06/22/99 01:20:51:190 PM

    Three Phase Wye

    1A

    2A

    3A

  • 8/14/2019 Micro Turbine Testing Program

    13/27

    Dynamic Testing Tests to observe the behavior of MTGs when

    interconnected with the utility grid Tests conducted at the SCE test bed Power ramping tests in both grid-connected and

    stand-alone modes (slow dynamics) SCE working with ORNL, SNL and GE to define

    additional testing to obtain data for fast dynamicmodels

    Data helps build models to simulate operation of the MTGs in a distribution system

  • 8/14/2019 Micro Turbine Testing Program

    14/27

    Capstone Grid Connect Tests

    Capstone 30 kW MTG

    0

    5000

    10000

    15000

    20000

    25000

    30000

    35000

    0 4 0

    8 0

    1 2 0

    1 6 0

    2 0 0

    2 4 0

    2 8 0

    3 2 0

    3 6 0

    4 0 0

    4 4 0

    4 8 0

    5 2 0

    5 6 0

    6 0 0

    6 4 0

    6 8 0

    7 2 0

    7 6 0

    8 0 0

    8 4 0

    8 8 0

    9 2 0

    9 6 0

    1 0 0 0

    1 0 4 0

    Seconds

    P o w e r

    ( W )

    0

    20000

    40000

    60000

    80000

    100000

    120000

    S h a f t S p e e

    d ( R P M )

    Power Demand (W)

    Output Power (W)

    Engine Speed (rpm)

  • 8/14/2019 Micro Turbine Testing Program

    15/27

  • 8/14/2019 Micro Turbine Testing Program

    16/27

    Honeywell 75 kW DescriptionParallon TM 75 kW at ISO

    275 AC with Honeywell transformer option added to boost to 480 VAC, 3-phase, 60 Hz at siteRecuperated single stage radial flowcompressor and turbine on a singleshaft, integrated with generator Not equipped with a heat recoveryboiler option is availableGrid parallel or stand-alone operationInternal gas compressor

  • 8/14/2019 Micro Turbine Testing Program

    17/27

  • 8/14/2019 Micro Turbine Testing Program

    18/27

  • 8/14/2019 Micro Turbine Testing Program

    19/27

    Summary of Testing Results: 03/07/02

    (continued) 2000 Capstone high pressure units DPC upgraded and replaced resulting

    in higher power output and increased efficiency Began testing low pressure Capstone and Honeywell

    2001 Initial results for Capstone both LP and upgraded HP

    Honeywell results Performed electrical characterization on Capstones and Honeywell Began testing Bowman Elliot returned to UCI test site and testing to resume

    2002 Begin testing of Ingersoll-Rand (I-R) Seek other MTGS, such as Capstone 60 kW, Turbec 100 kW CHP

    Test new models from Bowman & I-R Finalize results for Capstones and Bowman

  • 8/14/2019 Micro Turbine Testing Program

    20/27

    Future testing -- Elliott 80 kW

    Elliott 80 kW at ISO480 VAC, 3-phase, 60 HzRecuperated single stageradial flow compressor and

    turbine on a single shaft,integrated with generator Not equipped with a heatrecovery boiler option isavailableGrid parallel or stand-aloneoperation

  • 8/14/2019 Micro Turbine Testing Program

    21/27

    Future testing -- Ingersoll-Rand 70 kW

    Ingersoll-Rand 70 kW at ISO480 VAC, 3-phase, 60 HzA dual shaft recuperated MTG:

    A radial flow compressor andgasifier turbine on one shaftA radial flow power turbine on theother shaftThe power turbine drives thereduction gear and inductiongenerator for grid parallel-only

    operationHeat recovery boiler optionavailableInternal gas compressor

  • 8/14/2019 Micro Turbine Testing Program

    22/27

    Future Testing - Capstone 60 kWDescription

    Capstone 60 kW at ISO480 VAC, 3-phase, 60 HzRecuperated single stageradial flow compressor and

    turbine on a single shaft,integrated with generator Not equipped with a heatrecovery boiler option isavailableGrid parallel or stand-aloneoperation

  • 8/14/2019 Micro Turbine Testing Program

    23/27

  • 8/14/2019 Micro Turbine Testing Program

    24/27

  • 8/14/2019 Micro Turbine Testing Program

    25/27

    CapstoneLP

    3030CS

    BTU

    CapstoneHP Bowman

    Site installation

    Elliott(when

    available)

    Blue lines = installed Wiring

    Aggregated connectionsto MTGs. Typicallymounted inside controlpanel. Centralized dueto migration of MTG

    Equipment.

    Router to Internet. Provides VPNand local IP addresses for equipment

    2020

  • 8/14/2019 Micro Turbine Testing Program

    26/27

    3030 box at SCE MTG TestBed

    CapstoneLP

    3030CS

    BTU

    CapstoneHP Bowman

    Site installation

    Elliott(when

    available)

    Blue lines = installed Wiring

    Aggregated connectionsto MTGs. Typicallymounted inside controlpanel. Centralized dueto migration of MTGEquipment.

    Router to Internet. Provides VPNand local IP addresses for equipmen

    2020

  • 8/14/2019 Micro Turbine Testing Program

    27/27

    Questions?