MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

15
MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05

Transcript of MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

Page 1: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

MICE Phase 1

Koji YoshimuraKEK

June 22,2005 @NuFACT05

Page 2: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

“MICE Project gets the green light”

-CERN Courier-

Page 3: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

Outline

• MICE Step and Phase

• Motivation of Phase I

R&D activities for implementation of Phase I

Page 4: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

MICE Step and Phase

Phase I

Phase II

Phase is budgetary condition

Page 5: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

Motivation of Phase I• Step I

• Beam tuning• Tuning up of PID and Beam counter

• Step II• Various systematic study on tracker• Calibration of spectrometer

• Step IIISystematic calibration of emittance measurement

μ- STEP I: spring 2007

STEP II: summer 2007

STEP III: winter 2008

Reference of later step

Page 6: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

Implementation for Phase I

• Beam line & Shielding• PID

• TOF• CKOV• MUCAL

• Spectrometer• SciFi Tracker• Spectrometer Solenoid

• DAQSoftware

Page 7: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

MICE Beamline

Page 8: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

PID Detectors

Page 9: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

SciFi Tracker• Add one more station to 3

station (FNAL, IC)• Close to final design and

manufacture• Connectors• Assembling • Vacuum tight patch conncetors

• Outer cylinder made of carbon fiber (Liverpool)New wave guide system (Osaka)

Page 10: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

VLPC readout system• 2 slots VLPC cryostat has been

successfully commissioned. (Great Effort by Russ and Alan)

• Temperatures are as expected by Russ.

• Newly-developed readout board (AFEII) has been tested

Recently success in taking data

Page 11: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

KEK Test• Final check before manufacturing real

tracker• Performance check w/ B field (1 Tesla) and

beam

Various systematic study of the tracker

Page 12: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

Series of tests• Adopting staging approach?

• Feb, 2005 TOF and ACC test w/o • Performance of single counter

• May, 2005 TOF and ACC test w/Bfiled (final layout)

• Test PID and beam counters w/ magnetic field

• Performance of TOF hodoscope

Aerogel w/

Monitor beam under the condition of Step II

• VME DAQ system

Participants from UK International collaboration

• Aug, 2005 Cosmic-ray test at FNAL/KEK

Sep, 2005 SciFi tracker test

KEK Step I

KEK Step 0

KEK Step II

Page 13: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

Preliminary Results

0.425 GeV/c

π

μ

e

Page 14: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

VLP

C backplane

Linux PC

PCI-VME (SBS Bit3)

SASeq #2

SASeq #1

1553

VLSB #3

VLSB #4

AFE II (L)

AFE II (R)

VLPC Cassette #2

VLPC Cryostat

AFE II (L)

AFE II (R)

VLPC Cassette #1

VM

E B

US

DAQ System for KEK beam test

Linux PCCAMAC ADC/TDC

6U

Serialized ADC DATA

Slow Control

Trigger Control

1024 ch

1024 ch8x64 ch

8x64 ch

4

8x64 ch

8x64 ch

VLSB #1

VLSB #24

4

4

VME LVDS SERDES Buffer (VLSB)

Page 15: MICE Phase 1 Koji Yoshimura KEK June 22,2005 @NuFACT05.

Summary

• There are no show stoppers towards MICE PHase I.

• Magnet delivery date?

• MICE first data will come April, 2007

• Still lot of Task to do within limited time282 + 365 = 647 days left