Metro North
Metro North
St Stephen’s Green to Estuary
• 16.5km total length – 11 km in tunnel (City centre to Ballymun and
Airport)– 5.5 km in retained cut, at-grade or elevated
• 14 stops – 9 underground stops from St. Stephen’s Green to
Ballymun and at Airport– 5 surface stops
• High quality service– Capacity – 8,000 ppdph initially, capable of
growing to 20,000– Frequency - 5 minute peak headway initially,
capable of going to 2 minute– Speed – Airport to city in 20 minutes; Swords to
city in under 30 minutes; Ballymun to city in 13 minutes
● Estuary● Swords● Fosterstown● Airport● Dardistown● Northwood● Ballymun● DCU● Griffith Avenue● Drumcondra● Mater● Parnell Square● O’Connell Bridge● St Stephen’s Green
Westmoreland Street Works
O’Connell Street – Westmoreland Street
The Aim
The aim for RPA is to design and construct the works without materially impacting on the existing businesses
• Keeping Dublin Open for Business
• Ensuring that City centre remains an attractive destination for shoppers
How we keep Dublin Open for Business? • By maintaining pedestrian access to all premises• By maintaining access for servicing and deliveries• By maintaining access to all existing car parks• Getting the message across to the Public
All of this is achieved through • Careful planning and execution of the works
How we ensure the City centre remains an attractive destination?
• Noise and dust limits strictly controlled and monitored• High quality, well maintained attractive hoarding• Good lighting will be provided between the worksites
and the shops so that a safe environment is created• Good housekeeping, plant and equipment cleaned and
fully serviced, worksites kept tidy and dust free• By RPA and its contractor working closely with you the
business community throughout the construction period
Enabling Works - Spring 2011 to Autumn 2012
What are the Enabling Works?
• Heritage works• Tree Removal• Service diversions
Extent of Enabling Works
Enabling Works Phase 1
Enabling Works Phase 2
Enabling Works Phase 3
Enabling Works Phase 4
Enabling Works Phase 5
Enabling Works Phase 6
Enabling Works Phase 7
Enabling Works Phase 8
Enabling Works Phase 9
Enabling Works Phase 10
Enabling Works Phase 11
Enabling Works Phase 12
Enabling Works Phase 13
Enabling Works Phase 14
Enabling Works Phase 15
Enabling Works Phase 16
Enabling works in Westmoreland Street
Construction of Service Tunnels
• Most surface works adjacent to buildings will happen outside business hours
• Excavations covered over during business hours• Work continues below ground during the day and is
serviced from small hoarded areas(7.5m x 3.0m)• Footpaths widened into the roads by 3 to 5m improving
pedestrian flows during the day• Works are phased• All existing traffic movements maintained
Works by day Westmoreland Street East
Works by Day Westmoreland Street East
Works by Day Westmoreland Street West
Works by Day Westmoreland Street West
Worksite by nightWorks by night Westmoreland Street East
Works by night Westmoreland Street West
Works by night Westmoreland Street West
Main Works – 2012 to 2016
Main Works
Station Construction• Main works 36 months (excavation and concrete
works) 2012 to 2016• Equipping the Station 12 months• Testing and commissioning the system 12months• Main works is carried out in 6 distinct phases to ensure
pedestrian access and traffic flow is maintained• Westmoreland Street will remain open for Public
transport and deliveries
Extent of the Works
Work Site Phase 1
Works will be split into different phases so as to minimise the impact of the works.
Main Works Phase 1 (4 months)
Main Works Phase 2 (5 months)
Main Works Phase 3 - 5 months
Phase 4 Piling Worksite Duration approx: 4 Months
Main Works Phase 4 (4 months)
Phase 5 Excavation & Concrete Worksite Duration approx 18 months
Main Works Phase 5 (18 months)
Fit out of Stop Phase 6 (12 months)
Traffic Management Measures
Public Transport Bridge
Banned Right Turns
Banned Left Turns
Single Lane
Current Situation
13ft 4inches - 4.1m
During Phase 2 – Approx 5 Months
12ft – 3.6 m
Current Situation
14ft – 4.6m min width
During Phase 3 – 5 months
12ft – 3.6m min width
Current Situation
Phase 3 – 5 months
12ft – 3.6m min width
Car Park Access
• Access is maintained to all car parks.• Information on routes will be provided to
car park users via leafleting from 3 months before the route change
• Signage to each car park will be provided
• A
Our commitment to you
• Access will be maintained to all premises fronting on to the works during business hours
• Westmoreland Street will remain the main pedestrian thoroughfare between the two main shopping districts
• Access will be maintained to all premises for servicing and deliveries
• Noise and dust limits will be strictly controlled and monitored
Our commitment to you
A public information centre will be established• Communications HQ & media centre for press briefings • Venue for open forums with local businesses and
residents • 24/7 telephone hotline for queries and complaints • up to date public information on the works• a marketing campaign to advertise the city as being
“open for business as usual”
Community Liaison Officers will be available during the works for you to communicate with
How does RPA honour its commitments to you?
RPA will • Have an ongoing role throughout the works• Review the contractor’s method of work to
ensure compliance• Ensure you have been consulted about the
works before they happen• Audit and monitor the works as they happen• Be available and answerable to you
Contractors Commitments
• Comply with conditions of contract the Railway Order & EIS
• Will plan his works in line with best practice• Will be a good neighbour• Educate and brief his workforce on an
ongoing basis• Will engage with you
Next StepsNovember 2010• Provide presentation to affected businesses
• O’Connell Street 17th November• St Stephen’s Green 24th November• Parnell Square 30th November
November 2010 – March 2011• Meet with individual businesses to discuss impacts
and agree appropriate measures