Method Statement for Pipe Support Fabrication and Installation 6423dp420!00!0030000_rev01

download Method Statement for Pipe Support Fabrication and Installation 6423dp420!00!0030000_rev01

of 21

description

Method Statement for pipe support fabrication

Transcript of Method Statement for Pipe Support Fabrication and Installation 6423dp420!00!0030000_rev01

  • 1 / 20

    TABLE OF CONTENTS

    1.0 PURPOSE

    2.0 SCOPE

    3.0 REFERENCE

    4.0 ORGANIZATION AND RESPONSIBILITIES

    5.0 GENERAL

    6.0 WORK PROCEDURE

    7.0 HEALTH SAFETY ENVIRONMENT AND SECURITY

    8.0 ATTACHMENT

    Attachment 1 : Daily Fabrication Inspection Report (DFIR)

    Attachment 2 : Material Traceability Record (MTR)

    Attachment 3 : Daily Welding Inspection Report (DWIR)

    1 { Attachment 4 : Inspection Report for Embedded Plate Fabrication (IREPF)

    Attachment 5 : Release Note for Field Installation (RNF)

    Attachment 6 : Release Note for Painting (RNP)

    Attachment 7 : Job Safety Analysis (JSA)

  • 2 / 20

    1.0 PURPOSE

    This method statement is to establish the work plan and inspection instruction for the

    assembly, fabrication, inspection and documentation to be performed in order to complete the

    construction of pipe hangers and supports which shall be in compliance with applicable

    drawings and specifications.

    2.0 SCOPE

    1 { This method statement covers all pipe hangers, spring, cold shoe, clamped, supports and embedded plate to be assembled, fabricated, installed and inspected at Algeria Oman

    Fertilizer Project (AOFP).

    3.0 REFERENCE 3.1 6423MP201-00-00100 00 Basis for Piping Engineering

    3.2 6423MP202-00-00100 00 Piping Material Specification

    3.3 6423MP214-00-00100 00 Piping Standard Drawing

    3.4 6423MP214-00-00200 00 Piping Support Standard Drawing

    3.5 6423MS230-00-00100 00 Specification for Piping Work

    3.6 6423MS231-00-00100 00 Specification for Piping Fabrication By Each Service Class

    3.7 6423MS260-00-00100 00 Specification for Painting

    3.8 6423DA060-00-00700 00 Welder Qualification Procedure

    3.9 6423DJ530-00-00300 00 Material Control Procedure

    3.10 6423DA060-00-01300 00 NDE Control Procedure

    3.11 6423DP420-00-00420 00 Method Statement for Painting

    3.12 6423DP420-00-00500 00 Method Statement for PWHT

    3.13 ASME B31.1 Power Piping

    3.14 ASME B31.3 Process Piping

    3.15 ASME Sec, IX Qualification Standard for Welding and Brazing

    3.16 ASME Sec. V Nondestructive Examination

    3.17 ASME Sec. II Welding Rods, Electrodes and Filler Metals

    NOTE : In case of conf l ic t between this method statement and reference documents, fo l lowed below.

    - As a standard pract ice, method statement wi l l fol low the speci f icat ion and

    then, speci f icat ion wi l l fol low the code.

    - In case the speci f icat ion has conf l ic t wi th method statement . I t would be

    decided af ter d iscussions at the meet ing.

  • 3 / 20

    4.0 ORGANIZATION AND RESPONSIBILITIES 4.1 The Construction Manager has the responsibility to :

    (1) Plan the fabrication program and report its progress

    (2) Manage all fabrication drawings.

    (3) Preparation, revision and control of this document.

    (4) Managing of raw materials.

    (5) Managing of welding consumables.

    (6) Inspect the fabrication and installation of support and changes of its design.

    (7) Ensuring that design changes are incorporated into the work.

    (8) Requesting NDE or PWHT, if any

    (9) Requesting inspection to the QA/QC Team.

    (10) Preparation of material requisition of material for support fabrication work.

    (11) Control of welder and support welding data

    (12) Requesting and preparation for welder and welding operator qualification.

    4.2 The QA/QC Manager has the responsibility to :

    (1) Review of all request including Daily Welding Inspection Report. (2) Managing welder qualification. (3) Managing welding control system. (4) Managing of quality control. (5) Managing inspection and test with regard to support fabrication and installation.

    4.3 The Material Control Manager has the responsibility to : (1) Receiving and maintaining of material

    (2) Control of material stock status before release to construction team.

    (3) Issuance of material to Support shop and other sections.

    (4) Request the material receiving inspection to QA/QC team

    5.0 GENERAL Material to be installed will be withdrawn from the receiving area in accordance with material

    control procedure, the prefabricated sub assembly storage area, or the lay down area.

    Transferring the material from the storage area to work site will be performed in a manner

    which will not be deleterious to the material.

    When storage requirements are not defined, the type of storage and protection shall be

    determined through arrangements with project owner.

  • 4 / 20

    5.1 General Work Sequence

    (1) Make production plan considering material availability and area priority.

    (2) Issuance of Isometric drawing or support style list to support fabrication shop.

    (3) Request support material to material warehouse

    (4) Receiving support material from warehouse and perform receiving inspection.

    (5) Issue work order

    (6) Cutting and end preparation

    (7) Fit-up and tack welding

    (8) Welding

    (9) Inspection

    (10) Blasting and primer painting work at paint shop

    (11) QC documentation

    (12) Release support and store on stock yard

    (13) Support issuance to Field support team.

    5.2 Storage and handling material

    (1) Material shall be stored separately by its type and specification and it shall be marked

    according to its designated color.

    (2) Certificates verifying that materials or items used in the fabrication comply with

    Purchasers requirement. Certificates for each category of material shall be submitted.

    (3) Materials shall be maintained to comply with any warranty conditions imposed by the

    manufacturer.

    (4) Nylon slings shall be used for handling stainless steel material and straps.

    5.3 Drawing and materials

    (1) Pipe support shall be fabricated and installed in accordance with the approved drawing,

    pipes support style list.

    (2) For pipes requiring post weld heat treatment, attachments required for supporting

    purposes shall be indicated on the piping isometric drawings.

    (3) Pipe stanchions, pipe dummies and trunnions shall be made with same type of material

    as the connecting pipe. All other support material to be welded directly to the pipe shall

    be same type of material as the pipe itself.

    5.4 Inspection and test

    The inspection and test shall be notified to QA/QC team 24hours in advance prior to

    inspection and testing, and it shall be performed in accordance with the inspection and test

    plan.

  • 5 / 20

    6.0 WORK PROCEDURE 6.1 Control of pipe supports fabrication

    (1) Raw material All material of pressure retaining parts shall be identified.

    Part number, material specification and heat number shall be marked on the piece to be

    cut, and it shall be recorded on the material identification record, and it shall be inspected

    by QC inspector before cutting. (2) Cutting

    Support materials may be cut to shape and size by flame or thermal cutting.

    Stainless steel materials shall be cut by mechanical means or plasma arc cutting, but

    flame cutting shall not be allowed. Surface to be welded shall be free from slag and

    excessive notch foreign matter.

    Pipe support assemblies may be acceptable if items having greater strength are

    substituted for those indicated on the drawings.

    (3) Welding

    Welding shall be performed in accordance with the approved WPS and drawing by

    qualified welder.

    These fabricated support shall be inspected and recorded using the Daily Fabrication

    Inspection Report (Attachment 1).

    Field welding to pipes for the purpose of pipe support shall be limited as far as practical.

    Field welding for pipe support purposes shall not be performed on the following pipe

    materials.

    - Materials requiring post weld heat treatment (PWHT)

    - Non-ferrous materials

    All welding shall be done before post weld heat treatment

    Stainless material shall be segregated from normal carbon steel during fabrication and

    erection in order to avoid the contamination.

    (4) Marking and Tagging

    When welding has been completed, designate person will tag on each support body with

    stamped tags.

    The characters on such tags shall be a minimum of 3/16 inch and tags shall be securely

    attached to the assembly.

    (5) Painting and Stock

    When fabrication of pipe support is done, prepare the painting request form and transport

    to painting area. (Attachment 5)

  • 6 / 20

    Painting subcontractor shall paint and submit painting inspection report to contractor.

    Painted pipe support should be marked and properly identified and shall be stored in the

    designated area and preserved from dust and rust until issue to field erection.

    (Attachment 4)

    6.2 Control of Pipe supports installation

    (1) General

    As a general practice, appropriate adjustment / modification / addition of support shall be

    made by construction contractor according to the actual field conditions, especially for

    small bore piping.

    All pipe support must be installed as per specification and drawing.

    - Isometric drawing

    - Piping arrangement drawing

    - Pipe support standard drawing

    - Special pipe support drawing

    - Pipe support index

    Piping shall be properly anchored and guided before pressure testing.

    Support should be fabricated and installed prior to the piping installation, and use of

    temporary supports is to be minimized.

    In case the temporary supports are required, the supports arrangement shall be made

    sure so that they have sufficient bearing strength and stable supporting for the piping

    system.

    All temporary supports shall be removed before hydro test.

    Field welded supports shall be set correctly in place and adjusted to the final position

    before welding.

    For sliding supports, bearing surfaces shall be sufficiently clean to ensure unrestricted

    movement.

    Clamp bolts on clamped shoe type support should be checked as per standard pipe

    support drawing.

    Support shall not be welded to the equipment unless otherwise specified.

    In case that stainless steel piping without insulation is resting on the steel structure, pipe

    rack or piping support directory, stainless steel plate shall be installed between piping

    and structure to avoid direct contact, even if this information is not shown in support

    drawing.

    (2) Concrete expansion anchor bolts

    Installation of concrete expansion anchor bolt shall be performed in accordance with

    vendor information.

  • 7 / 20

    (3) Locking devices (Bolts / Nuts)

    The support height shall be adjusted by construction team to the actual field condition.

    All threaded connections, except high strength bolts, shall be secured by locking devices

    to prevent loosening during service.

    Wherever possible bolts/stud shall be locked in place with double nut. (Jam nut)

    A nut tack welded to the bolt/stud shaft may also serve as a locking device and may be

    used except where welding is prohibited on the bolt material.

    (4) Installation of Spring hangers

    Installation of constant and variable spring hangers shall be in accordance with the

    manufacturers instruction, the design drawing and the procedure.

    Spring hangers shall be easily accessible after installation within the limits of possible,

    and the scales shall be unobstructed and visible.

    Field engineer should be ensured that the travel stops are engaged and maintained thus

    on all spring hangers until the piping system are placed in service, except during such

    time of checking and marking adjustments on the spring hangers.

    Spring supports shall be installed with the spring locks in place and the travel shall be

    cold set position.

    These spring locking plates or pins shall not be removed until hydrostatic testing and

    insulation of the piping system has been completed, but before the line is put into service,

    as directed by commissioning group.

    If the spring force on empty line will cause possible damage to connected strain sensitive

    equipment, the spring locks shall remain in position until the line is filled with the actual

    service fluid.

    The relevant support and support drawing shall bear the warning block against empty

    position and the locks shall be attached with the spring support during operation.

    The travel stops on spring hangers shall be engaged during filling, testing and draining of

    pipe systems for hydro test.

    (5) Floor of base mounted supports

    Grouting is required between concrete surface and structural pipe support attachment

    plates.

    All grout work shall be performed in accordance with relevant work procedure.

    Non shrink grout shall be mixed and placed in according with the manufacturers written

    instruction.

    (6) Wall or ceiling mounted supports

    Pipe support base plates shall be mounted flat against the wall or ceiling.

  • 8 / 20

    Irregularities on the wall or ceiling surface that prevent flush mounting on the base plate,

    such as fins, protrusions, and excessive roughness, shall be removed by grinding.

    Grouting is not required except when depression, grooves, holes or other cavities under

    the base plate that are not amenable to removal by grinding.

    These shall be filled with grout before mounting the base plate.

    (7) Hanger rod and turn buckle installation

    Threading of hanger rods shall be performed in accordance with ASME B31.3 para

    321.1.5, thread designation UNC and, shall have a minimum of three full thread exposed

    when the nut is tightened on the hanger rod threads.

    Lubricant for threaded portion of rod is not required.

    For galvanized threads cut in the fields, the threaded portion of the rod shall have a

    touch-up coating.

    To compensate for pipe elevation discrepancies, hangers are usually provided with

    means to permit vertical adjustment during and after installation

    Threaded devices such as turnbuckles, clevises, etc. are acceptable, provided that after

    the adjustment the result is no less than full thread engagement.

    (8) Shoe or pads installation

    For shoes shall be welded to the piping with careful way avoiding any welding defects.

    Special care must be taken to the anchor points, as they are to be heavily loaded.

    Shoes pads for low alloy steel piping shall be of the same material as the pipes.

    In case of lines having shoe or saddle support, site measurement between distances of

    supports may be given and marked on the assembly.

    The supports are then welded on the spool assembly on the ground.

    In case of lines having guide or anchor the supports are to be welded in position.

    All supports / saddle welded to main pipe shall undergo the same testing requirement as

    that of main pipe.

    1 { (9) For the installation of Embedded plate shall be followed in accordance to Concrete Works

    Procedure No.6423DC420-00-0080000 6.3 Welding and welding attachment

    (1) All welding shall be in accordance with approved welding procedure specification.

    (2) The material of the attachment which is directly welded to the pipe shall be as shown on

    the pipe support detailed drawings.

    (3) Welding must be carried out by qualified welder in accordance with approved welding

    procedure specification.

  • 9 / 20

    (4) Material traceability report shall be recorded the heat-number of attachment and verified

    by QA/QC inspector and Contractors inspector for stainless steel and alloy steel.

    (Attachment 2)

    (5) Daily welding inspection report shall be signed off by QC inspector after visual

    inspection.

    (6) All weld attachment on pipe shall be identified by marking the weld and welder number.

    (7) All welds will be identified on the isometric drawing and shall be inspected by welding

    inspector and recorded in daily welding inspection report. (Attachment 3)

    6.4 Post Weld Heat Treatment (PWHT)

    (1) Performance of PWHT shall be in accordance with post weld heat treatment procedure.

    (2) The QA/QC shall review PWHT record and submit to owner for review.

    6.5 Non Destructive Examination (NDE)

    (1) The management and request of NDE shall be in accordance with NDE control

    procedure.

    (2) The QA/QC shall review NDE record and submit to owner for review.

    6.6 Paint and Touch up painting

    (1) At completion of fabrication and installation, painting subcontractor shall paint or touch

    up paint the pipe support according to painting specification and procedure.

    (2) Pipe construction manager is responsible for keeping and maintaining all related

    documents.

    6.7 Progress check

    (1) Progress of fabrication and installation in pipe support shall be measured together with

    piping progress using progress measuring program.

    (2) Every support item shall be tracked by this system.

    7.0 Health Safety Environment and Security 7.1 All workers shall wear PPE required as below.

    (1) Safety helmet

    (2) Safety glasses

    (3) Safety shoes

    (4) Gloves

    (5) Mask, if required to prevent inhalation of dust and welding gas

    (6) Ear plug, if required by conditions.

    7.2 Machinery like grinding wheel cutter shall have a protection method.

    7.3 Safety shall be requested and carried out in accordance with safety procedure.

  • 10 / 20

    8.0 Attachments Attachment 1 ; Daily Fabrication Inspection Report (DFIR)

    Attachment 2 : Material Traceability Record (MTR)

    Attachment 3 : Daily Welding Inspection Report (DWIR)

    1 { Attachment 4 : Inspection Report for Embedded Plate Fabrication (IREPF)

    Attachment 5 : Release Note for Field Installation (RNF)

    Attachment 6 : Release Note for Painting (RNP)

    Attachment 7 : Job Safety Analysis (JSA)

  • 11 / 20

    Attachment 1

    Daily Fabrication Inspection Report (DFIR) Algeria Oman Fertilizer Project Report No. : Date :

    No. Area Isometric Drawing No. Pipe Support Type Heat No. WPS No. Welder

    No. Qty Weight

    (kg) Remarks

    Prepared by : (Construction) Name Signature Date

    Inspected by : (QC Inspection) Name Signature Date

    6423DP420-003-01(0)

  • 12 / 20

    Attachment 2

    Material Traceability Record (MTR) Algeria Oman Fertilizer Report No. : Date :

    Isometric Drawing No. Rev. No. Pipe Support Type Material Size Cut Length QC Sign Contract Sign

    Line No. Spool No. Pipe Support Name Heat No. Thickness Qty Date Date

    SHOP The shop components have been verified against the fabricated piping and are complete and accurate.

    Prepared by : (Construction) Name Signature Date

    Inspected by (QC Inspector) Name Signature Date

    FIELD The field components have been verified against the erected piping and are complete and accurate.

    Prepared by : (Construction) Name Signature Date

    Inspected by (QC Inspector) Name Signature Date

    6423DP420-003-02(0)

  • 13 / 20

    Attachment 3

    Daily Welding Inspection Report (DWIR) Algeria Oman Fertilizer Project Report No. : Date :

    No. Area Isometric Drawing No. Sheet No.

    Rev. No.

    Support No.

    Joint No.

    Spool No. Material

    Piping Class Size Sch. Pipe Support Type Qty

    Weight (kg).

    Heat No.

    WPS No.

    Welder No.1

    Welder No.2

    PWHT Reqd VT Remarks

    Prepared by : Inspected by :

    Name : Name :

    Date : Date :

    (Construction) (QC Inspector)

    6423DP420-003-03(0)

  • 14 / 20

    Attachment 4

    6423DP420-003-04(0)

    INSPECTION REPORT FOR EMBEDDED PLATE FABRICATION (IREPF) Embedded Plate Anchor Bar

    S/No Reference Dwg (Standard Dwg) Type Plate No Thk (m) W W' H a b c d e f p

    Length tolerance 5mm/1m

    Dia (mm)

    Length (mm)

    No of Anchor

    Bar Tolerance Remarks

    1 Dwg Requirement Actual Deviation

    2 Dwg Requirement Actual Deviation

    3 Dwg Requirement Actual Deviation

    4 Dwg Requirement Actual Deviation

    5 Dwg Requirement Actual Deviation

    6 Dwg Requirement Actual Deviation

    7 Dwg Requirement Actual Deviation

    Prepared By: (Construction Team) Name Signature Date

    Inspected By: (QC Inspector) Name Signature Date

  • 15 / 20

    Attachment 5

    Release Note for Field Installation (RNF) Algeria Oman Fertilizer Project Report No. : Date :

    No. Area Isometric Drawing No. Sheet No. Rev. No. Pipe Support Type Qty

    Weight (kg) Remarks

    Prepared by : (Pipe Support Field Team) Name Signature Date

    Confirmed by : (Pipe Support Field Team) Name Signature Date

    Checked by : (Pipe Support Fabrication Team) Name Signature Date

    Approved by : (Pipe Support Fabrication Team) Name Signature Date

    6423DP420-003-05(0)

  • 16 / 20

    Attachment 6

    Release Note for Painting (RNP) Algeria Oman Fertilizer Project Report No. : Date :

    No. Area Isometric Drawing No. Sheet No. Rev. No. Pipe Support Type Qty

    Weight (kg)

    Paint Code Remarks

    Prepared by : (Pipe Support Fabrication Team) Name Signature Date

    Approved by : (Pipe Support Fabrication Team) Name Signature Date

    Received by : (Painting Team) Name Signature Date

    Reviewed by : (QC Inspector) Name Signature Date

    6423DP420-003-06(0)

  • 17 / 20

    Attachment 7

    JOB SAFETY ANALYSIS

    Date of Issue JSA No.

    Work Group Preparing JSA Piping Prepared by

    Job Description Pipe Support Fabrication & Installation Approved by

    Sequence of Task Potential Hazards Recommendations / Control Measures

    Worksite Housekeeping Slips Trips Falls

    Access egress and emergency routes are not to be obstructed

    All waste to be removed sorted and placed in Authorized storage

    /sort bins

    Wires and cables to be secured to avoid tripping hazard, and/or

    provide walkway clearance storage /sort bins

    All electrical system connections to be secured off ground and

    protected from rainfall

    Structure and scaffold projections to be signposted and masked

    when possible

    Holes and ground/floor openings to be barricade and signposted

    Fluid spills to be cleared as they occur

    Hoses and cables crossing roadways/paths to be protected with

    suitable covers

    Tools to be returned to store after use

    Materials to be stored in correct locations

    Flammable material are not to be left unattended at worksite

    Gas Cutting, Welding and Grinding operation

    Fire Explosion Electric shock Hot spot re-ignition Skin & eye damage

    Equipment to be operated by competent person only

    Electrical supplies to inspected and to be fit for purpose

    Welding sets and transforms to be correctly earthed

    Equipment to be inspected, labeled and in date for use

    Competent fire watcher to be appointed (two if work on bulkhead

    / floor / deck head)

    Clear area of combustible materials

    Equipment liable to spark or spatter damage to be covered

    Barriers and warning signs to be posted

    Fire extinguisher to be at worksite

    Electrical supply leads to be run so as not to provide a trip or

    fouling hazard

    Correct eye and body protection to be worn during work

    Eye line glare shields for adjacent by firewatcher 30 minutes after

    hot work ceases

  • 18 / 20

    Sequence of Task Potential Hazards Recommendations / Control Measures

    Crane operations and Lifting

    Dropped objects crushing Trapping moving machinery

    Hazard assessment to be conducted for all heavy (75% crane

    capacity) or unusual movements

    Every lift to be supervised by competent controller

    Weight of lift to be known

    Lift brief to be held on site

    Lifting equipment to be correct color code

    Lifting gear to be inspected fit for purpose each time of use

    Only authorized crane to operate crane

    Banks man to be trained and wear identifying clothing

    Enough men to control load to be at site

    Tag lines to be fitted and used at all times

    Area under lift and immediate vicinity to be vacated

    Overhead and jib swing hazards and obstructions to be noted

    and clearly marked where applicable

    Crane operating lift limits to be observe

    Gear to be inspected and stored after lift

    Vehicles on site Trapping crushing collision

    Vehicle pass to be obtained an entry to site

    Only authorized vehicles allowed on worksite

    Only qualified and authorized drivers to operate vehicles

    Vehicles to keep to directed routes

    Speeds to be appropriate to site

    Reversing warning tone to be operational

    Banks man to be present when vehicles are reversing

    Only authorized maintainers to work on vehicles whilst on site

    Seat belts where fitted are to be worn by drivers and passengers

    Passengers in vehicles only allowed in fitted seats, no riding

    Vehicles are not to be overloaded

    Wide or high loads are to be escorted whilst moving on site

    Vehicle are only to be used for designed purpose

    Vehicle and auxiliary engines are to be stopped when refueling

    Engines to be stopped and keys are to be removed when

    vehicles are left unattended

    Work on or with scaffolds Falling Dropped objects

    Only trained scaffolders are to erect, modify or dismantle scaffold

    structures

    Only authorized people to be scaffolds

    Scaffolds are not to be used unless properly inspected and

    certified with a current scaffold tag

    Scaffolds are not to be overloaded with materials or men

    Access ladders are to be secured to scaffold structure

    Toe boards and guardrails must be fitted

    Scaffolds must be tied into the parent structure to provide stability

    Intermediate stage boarding to be provided for access ladders

    Dropped object catchment netting to be provided as appropriate

    Walkways under scaffolding to be bridged by hard barriers

  • 19 / 20

    Sequence of Task Potential Hazards Recommendations / Control Measures

    Work at height Falling Dropped objects

    Only authorized people to go aloft

    Ladders scaffolds and platforms to be properly erected and

    certified

    Hard points established for fall arrester and safety line anchor

    points

    Fall arresters and harnesses inspected for defects/damage

    before each use

    Fall arrester and harness to be worn and secured prior to

    commencement of operations at height

    Barriers and signs posted to keep people out from drop zone

    Area lookout safety man appointed

    Other PPE appropriate to task to be worn

    Tools for use are attached to lanyards and secured

    Area below worksite inspected for conflicting activities

    Appropriate precautions taken for adverse wind/weather

    Open Flame Cutting, Welding and Burning

    Fire Explosion Hot spot re-ignition Skin & eye damage

    Clear area of combustible materials

    Equipment to be operated by competent person only

    Competent fire watcher to be appointed (two if work on bulkhead

    / floor / deck head)

    Equipment to be inspected and fit for purpose

    Flashback arresters to be fitted and functional

    Equipment liable to spark or spatter damage to be covered

    Fire extinguisher to be at worksite

    Gas bottles not to be placed in confined spaces

    Gas bottles to be secured upright and away from hot site

    Hoses to be clear of walkways

    Bottle key to be attached to gas bottle by chain

    Correct eye, ear and body protection to be worn during work

    Worksite to be inspected by firewatcher 30 minutes after hot work

    ceases

    Pollution control Damage to environment and water courses

    Always use hazardous substances with care, ensuring they are

    suitably stored and empty containers are property disposed of

    Oil and fuel cans, etc, should be stored and used so that

    leakages /spillages can be contained consider hard standings

    bund, spill trays, spill absorbs, etc

    Ensure all plant and equipment is well maintained to ensure it is

    running efficiently-no smoke, oil leaks etc

    Do not run plant or equipment when not in use

    Do not waste water by using leaking hoses of running taps

    unnecessarily

    Reduce dust by damping down materials, roads, truck loads

    Be aware if your site borders any watercourse.

    Do not allow dumping near banks.

  • 20 / 20

    Sequence of Task Potential Hazards Recommendations / Control Measures

    Pollution control Damage to environment and water courses

    Water can carry pollutants over significant distances, and can

    contaminate local drinking supplies

    Near pour any contaminants down storm drains or gullies

    Near use watercourses for cleaning tools, etc, and never store

    hazardous substances nearby

    Store potential contaminants in authorized stowage and do not

    take more than is required to the worksite

    Keep secure storage facilities locked with appropriate key control

    Comments 1. JSA should be used in conducting Tool Box Talks(TBT0 with all concerned workers

    2. Provide that all the necessary PPE are used, relevant PTW requirements are followed and all the control

    measures stated above are adhered to, the activity can proceed.

    PPE & Safety Equipment Required to Perform Task (tick as Appropriate)

    Safety Helmet Face Shield Goggle Barricade Harness Hand Gloves Safety Shoes

    Ear Plug Coverall Safety Glasses Work Permit Fire Extinguisher Dust Mask Others