Mauritania - Public Investment Management Support Project ... · AFRICAN DEVELOPMENT FUND Langue:...
-
Upload
duongkhuong -
Category
Documents
-
view
214 -
download
0
Transcript of Mauritania - Public Investment Management Support Project ... · AFRICAN DEVELOPMENT FUND Langue:...
AFRICAN DEVELOPMENT FUND
Langue: Français
PROJECT : Public Investment Management Support Project (PIMSP)
COUNTRY : Islamic Republic of Mauritania
APPRAISAL REPORT
OSGE DEPARTMENT
August 2013
Translated Document
TABLE OF CONTENTS
I. STRATEGIC THRUST AND RATIONALE ......................................................... 1
1.1 Project Linkages with Country Strategy and Objectives ............................................. 1
1.2 Rationale for Bank Involvement .................................................................................. 2
1.3 Aid Coordination ......................................................................................................... 4
II. PROJECT DESCRIPTION ...................................................................................... 6
2.1 Project Components ..................................................................................................... 6
2.2 Technical Solutions Adopted and Alternative Solutions Considered .......................... 8
2.3 Project Type ................................................................................................................. 8
2.4 Project Cost and Financing Arrangements .................................................................. 8
2.5 Project Area and Beneficiaries .................................................................................. 10
2.6 Participatory Approach in Project Identification, Design and Implementation ........ 11
2.7 Bank Group Experience and Lessons Reflected in Project Design ........................... 11
2.8 Key Performance Indicators ...................................................................................... 12
III. ENVIRONMENTAL AND SOCIAL IMPACTS ................................................. 13
3.1 Environmental Impacts .............................................................................................. 13
3.2 Climate Change ......................................................................................................... 13
3.3 Gender ........................................................................................................................ 13
3.4 Social ......................................................................................................................... 14
3.5 Involuntary Resettlement ........................................................................................... 14
IV. IMPLEMENTATION ............................................................................................. 14
4.1 Implementation Arrangements .................................................................................. 14
4.2 Monitoring ................................................................................................................. 16
4.3 Governance ................................................................................................................ 17
4.4 Sustainability ............................................................................................................. 17
4.5 Risk Management ...................................................................................................... 18
4.6 Knowledge Building .................................................................................................. 18
V. LEGAL FRAMEWORK......................................................................................... 19
5.1 Legal Instrument ........................................................................................................ 19
5.2 Conditions for Bank Intervention .............................................................................. 19
5.3 Compliance with Bank Policies ................................................................................. 19
VI. RECOMMENDATION ........................................................................................... 19
i
LIST OF ANNEXES
Annex I: Comparative Socio-economic Indicators of Mauritania
Annex II: Table of AfDB Portfolio in Mauritania (June 2013)
Annex III: Key Related Projects Financed by the Bank and Other Development
Partners of Mauritania
Annex IV: Map of Project Area
LIST OF TABLES
Table 1.1: Key TFP Projects in Areas covered by the Project
Table 2.1: Project Components and Activities
Table 2.2: Alternative Solutions Explored and Reasons for Rejection
Table 2.3: Project Cost Estimate by Component (in UA million)
Table 2.4: Project Sources of Financing (in UA million)
Table 2.5: Project Cost by Expenditure Category (in UA million)
Table 2.6: Project Cost by Expenditure Category of the Grant (in UA million)
Table 2.7: Project Cost by Expenditure Category of Government’s Counterpart Contribution
(in UA million)
Table 2.8: Expenditure Schedule by Component (in UA million) Table 4.1: Monitoring Milestones and Feedback Loop
Table 4.2: Potential Risks and Mitigation Measures
Currency Equivalents
(August 2013)
Currency Unit: Mauritanian Ouguiya (MRO)
UA1 = USD 1.51
UA1 = EUR 1.14
UA1 = MRO 459.1
Fiscal Year
1 January - 31 December
ii
Acronyms and Abbreviations
ADF
AFD
AfDB
African Development Fund
French Development Agency
African Development Bank
ARMP Procurement Regulatory Agency
CPW Construction and Public Works
CEDAW
CIB
Convention on the Elimination of All Forms of Discrimination against Women
Consolidated Investment Budget
CNCMP National Procurement Control Commission
CPMPSEF
CRC
Economy and Finance Sectors Procurement Commission
Conventions on the Rights of the Child
CSMP Procurement Sector Commission
DAD
DGPESD
DGPI
DGPPI
DGPSP
DMRCAE
DSEPP
EUD
FAO
GAP
GBS
GCF/TFPs
GDP
GII
GVT
HDI
IAS
IGF
IMF
LC
LCB
LDC
LFI
LOLF
MAED
MAFO
MDG
MIC
MTBF
MTEF
Development Assistance Data
Directorate General of Economic Policies and Development Strategies
Directorate General of Investment Programming
Directorate General of Investment Projects and Programmes
Directorate General of the Private Sector
Department of Resource Mobilization and External Aid Coordination
Department of Projects and Programmes Monitoring and Evaluation
European Union Delegation
Financial and Accounting Officer
Governance Action Plan
General Budget Support
Global Consultation Framework for Technical and Financial Partners
Gross Domestic Product
Gender Inequality Index
Government
Human Development Index
International Auditing Standards
General Inspectorate of Finance
International Monetary Fund
Local Currency
Local Competitive Bidding
Least Developed Countries
Initial Finance Law
Organic Law on Finance Laws
Ministry of Economic Affairs and Development
Bank’s Field Office in Morocco
Millennium Development Goals
Middle Income Countries
Medium Term Budget Framework
Medium Term Expenditure Framework
NA
NGO
Not Applicable
Non-Governmental Organization
PIMSP Public Investment Management Support Project
iii
PARPEF Economic and Financial Planning Strengthening Support Project
PCR
PHS
PIP
Project Completion Report
Permanent Household Survey
Public Investment Programme
PMT
PRSP
RBCSP
SC
Project Management Team
Poverty Reduction Strategic Paper
Results-Based Country Strategy Paper
Steering Committee
SDRFP
SIG
SME
Public Finance Reform Master Plan
Integrated Procurement Management Information System
Small and Medium-size Enterprise
SNIG
STC
National Strategy for Institutionalizing Gender
Sector Technical Committee
TFP Technical and Financial Partners
TOR Terms of Reference
TTG
UA
UNDP
US
USD
WB
Technical Thematic Group
Unit of Account
United Nations Development Programme
United States
United States Dollar
World Bank
iv
Project Information
Client Information
BORROWER: Islamic Republic of Mauritania
EXECUTING AGENCY: Directorate General of Investment Projects and Programmes
(DGPPI) at the Ministry of Economic Affairs and Development (MAED)
Financing Plan
Source Amount (UA) Instrument
ADF
0.74 million
Grant GOVERNMENT 0.86 million
TOTAL COST 1.60 million
Key ADF Financial Information
Loan /Grant Currency
UA
Interest Type * NA
Interest Rate Margin* NA
Commitment Fee * NA
Service Charge NA
Tenor NA
Grace Period NA
FRR, NPV (baseline scenario) NA
ERR (baseline scenario) NA
Period – Main Milestones (Expected)
Preparation Mission
April 2013
Concept Note Approval July 2013
Appraisal Mission July 2013
Project Approval September 2013
Effectiveness January 2014
Completion 31 December 2016
Last Disbursement 30 June 2017
v
PROJECT SUMMARY
Project
Overview
Project Name : Public Investment Management Support Project (PIMSP)
Geographic Scope : Nationwide
Project Period : 36 months (January 2014 – December 2016)
Project Cost: UA 1.6 million (0.74 million from ADF and UA 0.86 million
from the Government)
Project
Goals
The objective of PIMSP to improve public investment efficiency for strong and inclusive economic
growth. Its operational objectives are to: (i) improve public investment programming and linkages
between the various programming tools and the PRSP, and (ii) capacity building for identification,
development, implementation, and monitoring and evaluation of public investment projects. The
project comprises two components: (i) Improvement of public investment management, and (ii)
Project management and coordination.
Needs
Assessment
Mauritania’s major challenge is to ensure inclusive and sustainable economic growth for effective
poverty reduction. Better public investment management and promotion of gender equality and equity
are the main thrusts for anchoring Mauritania’s medium and long-term development. The key
challenges to be addressed for efficient public investments performance will mainly concern: (i)
improvement of public investment programming in light of PRSP priorities, (ii) gender mainstreaming
in PIP, planning, and monitoring and evaluation of public policies, (iii) efficiency of the various
phases of the project chain, namely identification, preparation and implementation, and (iv)
strengthening of project implementation monitoring and evaluation, (v) capacity building for DGPPI
responsible for steering the public investment programme.
Targeted
Beneficiaries
The project’s direct beneficiaries are: (i) MAED structures in charge of managing the Public
Investment Programme and monitoring the PRSP, (ii) Officers of Ministries whose project design and
appraisal capacities will be strengthened, and (iii) civil society whose capacity will be strengthened
and their views taken into account through their involvement in some project activities. PIMSP’s
indirect beneficiaries are the Mauritanian population as a whole. Women, as well as youths and other
vulnerable groups, will benefit from public investment projects and specific budget allocations thanks
to budgeting consistent with PRSP priorities.
Outcomes
and Impact
The expected outcomes of the project are: (i) in the short term, better investment budget allocation and
execution based on PRSP priorities (gender mainstreaming and employment) and improved public
resources absorptive capacity, and (ii) in the longer term, more inclusive economic growth that will
help to reduce gender inequalities.
Bank’s
Added
Value
The project comes at a time when the Government is seeking to substantially increase capital
expenditure to meet the country’s infrastructure needs. To that end, the project will help to improve its
public resources absorptive capacity by removing key public investment management bottlenecks.
PIMSP implementation will enhance public investment management efficiency for better allocation of
the Government’s financial resources to projects that enhance inclusive and sustainable growth.
Knowledge
Building
Several knowledge types will be built through implementation of this project, in particular: (i) the
technical capacity of DGPII at MAED will be enhanced through the different methodological guides
to be prepared, (ii) the other Ministries will benefit from best practices in public investment
management through training sessions on the various methodological guides (MTEF preparation,
maturation/ monitoring/evaluation of public investment projects) to be organized under the project.
vi
Results-Based Logical Framework Country and Project Name : Mauritania –Public Investment Management Support Project (PIMSP)
Project Goal : Improve public investment management efficiency for strong and inclusive economic growth
RESULTS CHAIN
PERFORMANCE INDICATORS MEANS OF
VERIFICATION RISKS/ MITIGATION MEASURES
Indicator (including
CSI)
Baseline
Situation TARGET
IMP
AC
T
Economic growth
more inclusive by
mainstreaming
gender and
employment
Average annual GDP
growth rate
6.9% in 2012 8% in 2018 MAED’s
macroeconomic
framework
Risk 1: Security risk at regional level due to
overall situation in the Sahel.
Mitigation measure No.1: The Authorities
are determined to reconcile development and
security priorities by continuing reforms and
strengthening security
.
Risk 2. Political instability
Mitigation measure No.2. The presidential
election in July 2009 facilitated the return to
democracy and the TFP re-engagement with
the government. The continuation of national
dialogue launched in 2011 and the prospect
of presidential elections in 2014 should
strengthen political stability.
Risk 3. Lack of financing for implementation
of the poverty reduction strategy.
Mitigation measure No. 3. The project
supports capacity building activities of the
DGPPI for better donor coordination and
resource mobilization.
Following the Brussels Roundtable, a State-
TFPs group was established to follow up
pledges (98.9% of commitments were
mobilized as at 19 June 2013).
Risk 4. Lack of involvement of stakeholders
Mitigation measure No. 4. The
establishment of a steering committee
including all project beneficiaries, the private
sector and civil society will foster the
participation of all stakeholders.
Risk 5. Weak capacity of the administration
for the implementation of project activities
and risk of poor fiduciary and procurement
management
Mitigation Measure No. 5. The training
activities under the project and supporting the
PMT will offset this risk. The project
involves the recruitment of two experts in
financial management and procurement on a
competitive basis to support the project
management unit. Monitoring the
implementation of the project will be
enhanced through regular supervision
missions of the Bank experts who will
provide, if needed, technical support for the
timely execution of the project.
Human Development
Index (HDI) adjusted to
inequalities
0.306 in 2012 0.315 in 2018 UNDP Human
Development Report
OU
TC
OM
ES
Impact I: The
investment budget
is allocated and
executed according
to PRSP priorities (
by mainstreaming
gender and
employment)
Pro-poor expenditure
against overall
expenditure
45% in 2012 50% in 2016 Ministry of Finance
and MAED Data
Gender Inequality
Index (GDI)
0.643 in 2012 0.623 in 2016 UNDP Human
Development Report
Impact II: The
absorptive capacity
of resources is
improved.
Annual rate of
execution of public
investment
60% in 2012 70% in 2016 Ministry of Finance
and MAED Data
RE
SU
LT
S
COMPONENT I : IMPROVEMENT OF PUBLIC INVESTMENT MANAGEMENT
I.1.1. MTEF
development
capacity is
enhanced
I.1.1. Availability of a
methodological guide
for MTEF preparation
Lack of guide for
MTEF
preparation
A methodological
guide for MTEF
preparation is available
before end - 2014
Annual report on the
implementation of the
public finance reform
master plan (SDRFP)
Project
Implementation
Reports
I.2.1. Gender and
employment
mainstreaming in
programming and
preparation of the
investment budget
I.2.1 Availability of a
methodological guide
for maturation of
projects to be included
in the PIP with gender
and employment-related
indicators
Lack of a
methodological
guide for
maturation of
projects to be
included in the
PIP
Availability of a
methodological guide
for maturation of
projects to be included
in the PIP before end-
2014
Project
Implementation
Reports
I.2.2. Public
investment
programme
monitoring is
enhanced
I.2.2. Availability of a
methodological guide
for public investment
project monitoring
Lack of a
methodological
guide for public
investment
project
monitoring
Availability of a
methodological guide
for project monitoring
before end-2014
Project
Implementation
Reports
I.2.3. Public
investment
programme
evaluation is
improved
I.2.3. Availability of a
methodological guide
for public investment
project evaluation
Lack of a
methodological
guide for project
evaluation
Availability of a
methodological guide
for project evaluation
before end-2014
Project
Implementation
Reports
I.2.4. Ministry
employees are
trained in project
design, monitoring
and evaluation
I.2.4. Number of
persons trained (number
of women trained)
- 140 persons (including
50 women) at end -
2014
Project
implementation
Reports
vii
KE
Y A
CT
IVIT
IES
COMPONENTS RESOURCES
COMPONENT I: IMPROVEMENT OF PUBLIC INVESTMENT MANAGEMENT
- Technical assistance activities: Recruitment of national and international experts and
consulting firms
- Human capacity building activities: training
- Physical capacity building activities Computer and office equipment
COMPONENT II: PROJECT MANAGEMENT AND COORDINATION
- Logistics, monitoring and evaluation, annual audits
Resources
Component I: UA 1.21 million
Component II: UA 0.30 million
Contingencies: 0.09
Total: UA 1.6million (0.74 million from ADF and UA 0.86 million
from the Government)
viii
Project Implementation Schedule
2013 2014 2015 2016
Activities/Month S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Prior to start-up
Board presentation
Grant effectiveness
Appointment of Coordinator and Deputy
Coordinator
Establishment of the Project Team
Preparation of procedures manual
Project launching mission
Equipment and supplies
Office and computer equipment
Accounting software
Consultants
Preparation of bidding documents and short lists
Invitation for bids, analysis and award
Firm for preparation of public investment management tools and instruments and training of
senior staff
Design an IS for PRSP implementation
Design and installation of an electronic archiving
system for financing agreements
Design of commitments tracking system
Trilingual translation agency (French, Arabic,
English)
Financial and Accounting Officer
Procurement Expert
Monitoring/Evaluation Expert
Gender Expert for PRSP monitoring/evaluation
Computer Expert for DAD system administration
Miscellaneous
Operating costs
Supervision missions
Mid-term review
PSC meeting
Completion mission
Audits
Annual account audit
Final account audit
1
REPORT AND RECOMMENDATION BY MANAGEMENT CONCERNING
A PROPOSAL FOR AN ADF GRANT TO MAURITANIA FOR THE FINANCING
OF THE PUBLIC INVESTMENT MANAGEMENT SUPPORT PROJECT
This proposal submitted to the Board for approval concerns the award of an ADF grant
amounting to UA 0.74 million to the Islamic Republic of Mauritania for the financing of the
Public Investment Management Support Project (PIMSP). It is an institutional support project
to enhance the public investment management capacity of the Ministry of Economic Affairs
and Development (MAED). The project goal is to improve public investment efficiency so as
to ensure strong and inclusive economic growth. Its operational objectives are to: (i) improve
public investment programming and linkages between programming tools and the Poverty
Reduction Strategy Paper (PRSP), and (ii) strengthen capacities in public investment project
identification, preparation, implementation, and monitoring-evaluation. The expected
outcomes are: (i) in the short-term, improved investment budget allocation and execution
based on PRSP priorities (by mainstreaming gender and employment) and improved public
resources absorptive capacity, and (ii) in the longer term, more inclusive economic growth
that would help to reduce gender inequalities.
I. STRATEGIC THRUST AND RATIONALE
1.1 Project Linkages with Country Strategy and Objectives
1.1.1 The 2011-2015 Poverty Reduction Strategy Paper (PRSP III), which focuses on
achieving the MDGs by 2015, is the main reference document for Mauritania’s technical and
financial partners. It outlines the key short and medium- term development strategies and
centres on the following four areas: (i) acceleration of growth and stabilization of the
macroeconomic framework, (ii) anchoring of growth pro-poor economic concerns, (iii)
human resource development and expansion of basic services, and (iv) improvement of
governance and capacity building. With regard to economic governance, the Government has
set the following specific objectives: (i) ensure efficient and transparent public resources
management and combat all forms of corruption and mismanagement, (ii) strengthen public
investment planning and programming, and (iii) develop the statistics and information
systems. Within this framework, the Mauritanian Government has developed a five-year
(2012-2016) reform master plan for its public finance management system, which aims to
contribute towards achieving the objective of the 4th
Thrust of PRSP III. The planned reforms
are expected to increase tax revenue, control non-poverty-related current expenditure,
improve the preparation and execution of Finance Laws, as well as enhance budget
information dissemination and public spending quality.
1.1.2 Mauritania’s Results-Based Country Strategy Paper (RBCSP) for the 2011-2015
period is closely linked to PRSP III. The Bank’s assistance strategy is centred on the
following two pillars: (i) reinforcement of infrastructure, and (ii) improvement of economic
and financial governance. The second pillar is in line with the 4th
Thrust of the PRSP.
Through this pillar, the Bank supports implementation of reforms and institutional capacity
building for the public administration to improve public resource management and the quality
of public services. The Bank’s objective under this pillar is to promote macroeconomic
stability and sustain growth by supporting the Government's efforts to improve public finance
management, modernize the administration, enhance its capacity, and improve the business
climate.
2
1.1.3 The project is consistent with the 4th
Thrust of PRSP III and the guidelines of Pillar II
of Mauritania’s RBCSP. It also falls within the framework of consolidating and deepening
public finance reforms, particularly those concerning public investment management.
Strengthening the administration’s capacity in defining and implementing development
policies, programming, implementation, and monitoring/evaluation of public investment
projects is a major challenge for public spending efficiency. Furthermore, the project is
consistent with the guidelines of the Bank’s Strategy (2013-2022), particularly those relating
to strengthening governance. Indeed, the project seeks to create conditions conducive to
economic recovery through more efficient and credible public finance management. It is also
in line with the Bank's strategy on Governance.
1.2 Rationale for Bank Involvement
1.2.1 Political, economic and social context: Mauritania has gone through a period of
political instability, notably with two military coups in 2005 and 2008. The June 2009 Dakar
Agreements facilitated a return to constitutional order, leading to the July 2009 presidential
election and resumption of international cooperation. New presidential elections are scheduled
for 2014. As regards the economy, Mauritania has recorded good macroeconomic
performance, with a real GDP growth rate of 5.3% over the past three years from 2010 to
2012. After a slight slowdown to 3.9% in 2011 following the major drought that affected the
entire Sahel region, the real GDP growth was given fresh impetus in 2012, with a rate of 6.9%
(8% excluding the extractive industries), driven mainly by the dynamism of the construction
and public works sector supported by major public investments and the investment
programmes of mining companies. In 2012, the inflation rate was only 3.4%, well below
projections. The country recorded a positive budget balance of 2.8% of GDP in 2012, despite
increased spending from own resources, particularly for major emergency social programmes.
This performance is due mainly to considerable tax collection efforts, substantial
improvement in mining revenue, and control of non-essential spending. At the social level,
Mauritania made significant progress in some of the MDGs, particularly those relating to
education, access to drinking water, and control of HIV/AIDS, malaria and tuberculosis.
Conversely, in other areas, despite the progress made, the results remain inadequate.
According to the most recent data from the 2008 Permanent Household Survey (PHS), overall
poverty stands at approximately 42%, well above the target of 25% by 2015. Poverty is
largely a rural phenomenon, with a rate of 59.4% in 2008. The country is also lagging behind
for other MDGs such as health, environment, employment and some aspects of gender
disparity,1 hence the need to continue supporting effective implementation of its poverty
reduction strategy. Mauritania’s key challenge is to ensure inclusive and sustainable economic
growth. The most recent data from the 2008 PHS puts the unemployment rate at 31.2%. The
challenge of creating jobs will be even greater for several years, given the persistent high
1 Source : Statistics Department of AfDB
The primary school completion rate increased from 29% in 1990 to 79.2% in 2011
The female/male ratio in primary school improved from 83.5% in 1990 to 91.0% in 2011
The percentage of the population having access to safe water improved from 50% in 1990 to 58% in 2011
The overall HIV prevalence (% of population aged 15-49) improved from 4% in 1990 to3.6% in 2011
The maternal mortality rate (per 100000) remains high, moving from 1100 in 1990 to 840 in 2011
The percentage of the population with access to improved sanitation facilities remains low, dropping from 36% in 1990 to 31% in
2011
The employment/ population aged 15 and over ratio remains weak, moving from 52.3% in 1990 to 51.8% in 2011
The female literacy rate (% of women aged 15-24 years) remains high, moving from 62.5% in 1990 to 65.3% in 2011
3
increase in the working population. New labour market arrivals will stay above the 3% growth
rate. To meet this challenge, it is vital to mainstream job creation in all public policies. The
project supports the inclusion of job creation in the various methodological guides to public
investment programming, as well as the maturation, monitoring and evaluation of public
investment projects.
1.2.2 The project comes at a time when the government is seeking to significantly increase
capital expenditure to meet the country’s infrastructure needs. The country’s current financial
situation is marked by high Treasury account balances, increased revenue mobilization and
exceptional external support that have helped to generate substantial resources. The public
investment expenditure more than doubled between 2009 and 2012 from MRO 51.8 billion to
MRO 128.5 billion. However, both the government and TFPs are aware of Mauritania’s weak
absorptive capacity. Indeed, the public investment disbursement rate scarcely exceeds 60%.
The project will help improve the public investment management capacity by removing major
bottlenecks in the design, implementation, monitoring and evaluation of public investment
projects. This will improve the public resources absorptive capacity. The World Bank’s 2011
public expenditure review, conducted in collaboration with other technical and financial
partners, revealed significant shortcomings in public investment management, in particular:
the lack of preliminary screening of projects based on the PRSP strategic guidelines, the lack
of standardized formal project appraisal, the weak public procurement system, the lack of a
comprehensive project database, and the poor monitoring and evaluation of projects. At the
operational level, the different departments of DGPPI at MAED lack technical and material
capacity to perform their duties, and do not work in an integrated and coordinated manner. A
detailed description of the institutional framework for public investment management, its
weaknesses and challenges is provided in Technical Annex A2.
1.2.3 Given the huge development challenges to be addressed, the Mauritanian
government has decided to restore the medium-term budgeting principle. To that end, various
budget programming tools have been developed by the government: MTEF, PIP,
Consolidated Investment Budget (CIB) and the Finance Law. The Medium-Term Expenditure
Framework is a document that summarizes all operating and investment expenses for a 3-year
rolling period (overall MTEF). It is the main tool that provides the linkage between the PIP
and the PRSP. In 2011, MAED started to develop an overall MTEF covering the 2012-2014
period to serve as basis for preparation of the 2012 and 2013 annual budgets. A steering
committee was set up for that purpose. However, the preparation of the MTEF never
materialized due to lack of an appropriate methodology and human capacity to carry through
the exercise. Thanks to the availability of a methodological guide for MTEF development and
the training of officers of various departments on this guide, the project will strengthen
MAED capacity in developing overall MTEFs and the capacity of sector ministries in
developing sector MTEFs. Mastery of the MTEF as a tool for programming medium-term
expenditure by the State should enable it to secure sustainable resources for public
investment. Furthermore, operationalizing annual monitoring of PRSP III implementation
requires adopting a new and more appropriate monitoring system. The project will support the
design of an information system for monitoring PRSP III implementation. The use of this
system will facilitate production of PRSP implementation progress reports. Finally, the
project promotes responsible control of public action by involving civil society in some
activities (steering committee, field missions for physical monitoring and evaluation of
projects, and training activities).
4
1.2.4 The persistence of relations of inequality and lack of equity remain an obstacle to the
country’s sustainable development. Beyond the significant progress made in terms of
women’s political representation (introduction of quotas for women on electoral lists), gender
disparities and inequalities persist in the country as regards women's access to basic social
services and productive resources, participation in economic life, and reproductive health. The
Government is aware of these issues and has undertaken various actions, including the
formulation of a National Gender Institutionalization Strategy (SNIG). Mauritania faces
difficulties in operationalizing SNIG in the country, in particular, the lack of financial
resources, weak technical and operational capacity of public structures tasked with promoting
SNIG in the development of policies and programmes, monitoring their implementation, and
monitoring and evaluation. The virtual absence of gender disaggregated statistics hampers the
conduct of gender-sensitive monitoring and evaluation to measure the impact of the policies
implemented and inform policy makers to reduce discrepancies or correct inequalities
between men and women and boys and girls. Overall, planning and budgeting are not gender
sensitive. The project supports the recruitment of a Gender Expert to provide technical
support to MAED in the implementation of the gender institutionalization strategy.
Specifically, the gender expert will provide technical support for gender mainstreaming in
planning, monitoring and evaluation of public policies and the public investment programme.
1.3 Aid Coordination
1.3.1 External aid coordination is one of the top priorities of PRSP III. In this area, the
priority actions include: (i) support for public investment programming and establishment of
efficient operational mechanisms to ensure proper management of national commitments
under financing agreements and investment programming, (ii) better coordination of external
aid, including the establishment of permanent monitoring and coordination structures, (iii)
development of an integrated information system for external assistance, (iv) dissemination of
reports relating to such assistance, and (v) establishment, in accordance with the Paris
Declaration, more efficient mechanisms for joint management of programmes and projects
with technical and financial partners. Following the June 2010 donor roundtable in Brussels, a
State-TFP Coordination Committee for official development assistance and monitoring
mobilization of funds was set up. It is chaired by the Minister of Economic Affairs and
Development. To make an effective and coordinated contribution to the country’s
development, donors have created a two-tier internal consultation framework: an overall level
and a sector level. Ten (10) Clusters (Clusters/TFPs), including a Governance Group
(Governance Cluster), meet at the technical level chaired by previously designated leaders.
1.3.2 The Sector Group on Governance which comprises all the TFPs, including the Bank,
meets regularly to coordinate donor support. Despite the absence of an office in Nouakchott,
the Bank participates actively in periodic meetings of the group, and is kept regularly
informed of the group’s work. Assignment of the technical responsibility for monitoring the
Bank's projects in Mauritania to MAFO in 2012 should further strengthen the presence of
Bank experts in the various sector TFP coordination meetings. TFP supports in the areas
covered by the project are presented in Table 1.1 below. A detailed description of these
projects is given in Technical Annex A3 (Donor support). The PIMSP complements these
TFP interventions, strengthening planning, design, implementation, and monitoring-
evaluation of public investment projects. Improving transparency and efficiency in public
procurement, which is an important component in the execution of public investment projects,
is covered by the support of other technical and financial partners (World Bank and AFD).
5
However, the Bank supported procurement through an operation in 2011 with resources from
the Governance Trust Fund.
Table 1.1
Key TFP Projects in Areas Covered by the Project Technical
and
Financial
Partners
Projects and Costs
Areas Covered
European
Union
Delegation
Budget Support Programme to
establish the Poverty Reduction
Strategy Framework in Mauritania
(GBS PRSP III)
EUR 46 million in 2013-2015 (EUR
40 million for general budget
support and EUR 6 million for
institutional support). Ongoing
Institutional support is intended to: (i) provide specific
support for the PRSP monitoring mechanism, (ii)
operationalize the public finance reform master plan,
(iii) strengthen the national and sector statistics
production system, and (iv) provide multi-sector
technical assistance.
World Bank
Public Sector Capacity Building
Project
USD 13.0 million (USD 750,000 to
support transparency in public
procurement). Ongoing
In public procurement, the project supports: (i) funding
of public awareness campaigns and dissemination of the
new regulatory framework for procurement (done), (ii)
funding of an individual consultant to diagnose
constraints and assess capacity building needs of
institutions emerging from the public procurement
reform (done), (iii) financing of a few days’ retreat to
review the draft standard documents (done), (iv)
procurement of some computer equipment and office
furniture for structures resulting from the reform
(ARMP-CNCMP and CSMP) (ongoing), (v) selection of
a firm to provide technical assistance and training to
structures resulting from the reform (selection ongoing).
UNDP Capacity building support for
inclusive growth
USD 5.05 million in April 2013-
December 2016.
Planned
Led by MEAD, the project will contribute to
development of PRSP and MDG planning and
monitoring/evaluation tools, as well as enhancement of
the capacity of the national statistical system to collect,
process, analyze and disseminate disaggregated and
gender-sensitive data.
UNDP Technical assistance:
USD 600,000 support in 2011-2012
Ongoing
USD 153,056 support in 2013-2015.
Planned
Technical assistance from "Synergy International
System, Inc." for establishment of Database
Development Assistance (DAD) software. DAD is an
automated information management system designed to
improve the efficiency and transparency of the planning
and coordination of national development and
reconstruction activities in the country. In additional, it
is a powerful tool for documentation and analysis of aid
flows. The system is the main database and data entry
and reporting system for the Government, donors and
NGOs, providing easy access to development data.
AFD Technical assistance:
EUR 87,000 Ongoing
Support for implementation of the new Public
Procurement Code (finalization of Standard Bidding
Documents).
6
II. PROJECT DESCRIPTION
2.1 Project Components
2.1.1 The objective of PIMSP to improve public investment efficiency for strong and
inclusive economic growth. Its operational objectives are to: (i) improve public investment
programming and linkages between programming tools and the PRSP, and (ii) capacity
building for identification, preparation, implementation, and monitoring and evaluation of
public investment projects.
2.1.2 The project comprises two key components: (i) improvement of public investment
management, and (ii) project management and coordination. The first component aims to
improve economic planning and strengthen the identification, preparation, implementation,
monitoring and evaluation of public investment projects. The second component seeks to
support project management and strengthen the capacity of DGPPI, which is responsible for
project implementation monitoring and evaluation to ensure proper implementation of the
various project activities. The DGPPI comprises three departments: (i) the Department of
Investment Programming, (ii) the Department of Resource Mobilization and External Aid
Coordination, and (3) the Department of Project and Programme Monitoring and Evaluation.
A detailed description of the project activities is provided in Technical Annex C1.
7
Table 2.1
Project Components and Activities Name of
Components
Cost
Estimate
(UA million)
Component Description
Component I :
Improvement of
public investment
management
1.21UA M This component comprises two (2) sub-components:
Sub-component I.1: Improvement of public investment programming in line with
PRSP priorities
• Development of a methodological guide for developing MTEF and training Ministry
officials on the development of the MTEF tool;
• Recruitment of a Gender Expert for technical support to thematic groups to include
gender among selected PRSP indicators, technical support to strengthen the
operational capacity of senior staff of the Directorate General for Economic Policies
and Development Strategies (DGPESD) in gender-sensitive monitoring and
evaluation, and support gender mainstreaming in the PIP;
• Support for the Directorate responsible for monitoring the PRSP to design a reliable
and automated information system that will provide indicators for monitoring PRSP
III implementation;
Sub-component I.2: Capacity building in the identification, development,
implementation, monitoring and evaluation of projects and public investment
projects and programmes
• Preparation of an operating procedures manual and methodological guides
(Methodological Guide for maturing projects to be included in the PIP,
methodological guide for monitoring public investment projects and methodological
guide for public investment project evaluation) taking into account the gender and
employment dimensions; and training of employees of MAED and sector ministries on
the operating procedures manual and the different methodological guides;
• Field missions for physical monitoring and evaluation of projects and programmes
(including civil society);
• Capacity building for the Unit responsible for agreements (Hiring a translator for
agreements who will work when needed throughout the project)
• Strengthening of the DAD system for aid management, public investment, and
monitoring and evaluation (recruitment of a computer expert throughout the project
who will be the DAD administrator);
• Design and implementation of a system for electronic filing of financing agreements
and design of a system for monitoring commitments;
• Logistic support (computer hardware, office automation and office furniture) for
DGPPI, DMRCAE (Agreements unit) DGPI (Feasibility Studies Unit) and DSEPP
(Audit Unit).
• Communication activities
Component II :
Project
Management and
Coordination
UA 0.30
million
It comprises: installing the project management team at DGPPI, procurement,
installation of accounting software + training and user’s guide; preparation of a
procedures manual; preparation of interim and annual financial statements; annual
accounts audits; coordination; organization of meetings of the Steering Committee
(two meetings per year); premises for the project team; and logistic support
(transport equipment)
Base Cost UA 1.51
million
Contingencies UA 0.09
million
Total Cost UA 1.60
million
8
2.2 Technical Solutions Adopted and Alternative Solutions Considered
2.2.1 At project preparation, several options were presented, particularly as regards on the
anchoring of the project, the number of structures to be supported, the scale of investments to be
made, and the management of all the constraints in some potentially selected structures. Faced
with all these issues, trade-offs were necessary, so as to: (i) set project objectives to meet targets
compatible with the available financial package, and (ii) take into account synergies with the
other TFP interventions.
Table 2.2
Alternative Solutions Considered and Reasons for Rejection Solution Brief Description
Reason for Rejection
Establishment
of an
independent
project
management
unit
The independent project
management unit would be
responsible for regular
monitoring of
implementation of project
activities.
PIMSP will be implemented by the beneficiary, which will be
the executing agency. The project targets ownership by the
beneficiary and project management cost reduction.
Support to the
Directorate
General for
private sector
promotion
The Directorate-General for
private sector promotion is
mainly responsible for
promoting public-private
partnerships in public
investment projects.
Bank support targets the key structures of MAED in charge of
public investment and the PRSP. The Directorate-General
responsible for private sector promotion has not benefited
from Bank support due to division of roles among donors, the
World Bank having to provide support for the study to
establish the legal and regulatory framework for public-private
partnerships.
Support for
procurement
The public procurement
system has many
weaknesses that hamper
effective and transparent
public investment.
The aspect relating to improved transparency and efficiency in
public procurement is covered by the support of other
technical and financial partners (World Bank and AFD).
However, the Bank had supported procurement through an
operation in 2011 from the Governance Trust Fund resources.
This operation has strengthened the capacity of actors and
institutions involved in the procurement process and the
preparation of standard bidding documents (including standard
appraisal reports and manuals).
2.3 Project Type
PIMSP is an ADF-financed institutional support project seeking to improve public
investment efficiency. Strengthening institutional capacity in public investment management is
essential for the PRSP implementation.
2.4 Project Cost and Financing Arrangements
2.4.1 The total project cost is estimated at UA 1.60 million, comprising UA 0.70 million in
foreign currency (44%) and UA 0.90 million in local currency (56%). These costs include a
6%provision for contingencies per year for foreign exchange and local currency expenditures.
The detailed table of costs is shown in Annex B2 of the Technical Annexes to this report.
Below is a summary table of overall project cost by component.
9
Table 2.3
Project Cost Estimate by Component
Components Cost in USD (thousand) Cost in UA (thousand) As %
FE LC Total FE LC Total
Component 1 : Improvement of
public investment management
783.75 997.35 1781.10 522.78 665.25 1188.03 74%
Component 2 : Project
management and coordination
213.75 269.79 483.54 142.58 179.96 322.53 20%
Total base cost 997.50 1267.14 2264.64 665.35 845.21 1510.57 94%
Contingencies 59.85 76.03 135.88 39.92 50.71 90.63 6%
Total project cost 1057.35 1343.17 2400.52 705.28 895.92 1601.20 100%
NB: The exchange rates used are shown in (page (i)
2.4.2 The ADF contribution will amount to UA 0.74 million (46% project cost) and the
Government will contribute UA 0.86 million (54% of project cost).
Table 2.4
Sources of Financing (UA Thousand)
Source of financing FE Cost in UA LC Cost in UA Total cost in UA As %
ADF - Grant 705.28 37.12 742.40 46%
Government 0.00 858.80 858.80 54%
Total Project Cost 705.28 895.92 1,601.20 100%
10
Table 2.5
Project Cost by Expenditure Category (UA Thousand) Expenditure Categories (Overall) FE Cost LC Cost Total
Cost
% in FE
A. Goods 0.00 96.78 96.78 0%
B. Services 665.35 456.91 1,122.27 59%
C. Operating costs 0.00 291.52 291.52 0%
Total base cost 665.35 845.21 1,510.57 44%
Contingencies 39.92 50.71 90.63
Total Project Cost 705.28 895.92 1,601.20 44%
Table 2.6
Project Cost by Expenditure Category of the Grant (UA Thousand) Expenditure Category (Grant) FE Cost LC Cost Total
Cost
% in FE
A. Goods 0.00 0.00 0.00 0%
B. Services 665.35 35.02 700.37 95%
C. Operating costs 0.00 0.00 0.00 0%
Total base cost 665.35 35.02 700.37 95%
Contingencies 39.92 2.10 42.02
Total Project Cost 705.28 37.12 742.40 95%
Table 2.7
Project Cost by Expenditure Category of the Government’s Counterpart Contribution
(in UA Thousand) Expenditure Category (GVT) FE Cost LC Cost Total
Cost
% in FE
A. Goods 0.00 96.78 96.78 0%
B. Services 0.00 421.89 421.89 0%
C. Operating costs 0.00 291.52 291.52 0%
Total base cost 0.00 810.19 810.19 0%
Contingencies 0.00 48.61 48.61
Total Project Cost 0.00 858.80 858.80 0%
Table 2.8
Expenditure Schedule by Component (in UA Thousand)
Components 2013 -2014 2015 2016 Total
Component 1 : Improvement of public investment
management
642.81 272.61 272.61 1,188.03
Component 2 : Project management and coordination 106.18 108.18 108.18 322.53
Base cost of project 748.99 380.79 380.79 1,510.57
Contingencies 44.94 22.85 22.85 90.63
Total 793.93 403.64 403.64 1,601.20
As percentage of total project cost 50% 25% 25% 100%
2.5 Project Area and Beneficiaries
The project covers Mauritania’s national territory, which has a total population
estimated at 3.5 million inhabitants. The direct project beneficiaries are: (i) MAED structures
responsible for preparing, implementing, monitoring and evaluating the Public Investment
Programme, as well as monitoring the PRSP, (ii) officers of Ministries, whose project design
and monitoring/evaluation capacities will be strengthened (through gender mainstreaming),
and (iii) the civil society, whose capacity will be strengthened and their views taken into
account through their involvement in some project activities. PIMSP’s indirect beneficiaries
are the Mauritanian population as a whole. Improved public investment management,
11
particularly in basic infrastructure (water and sanitation, agriculture and energy), will foster
the development of poverty reduction priority sectors. Women, as well as youths and other
vulnerable groups, will benefit from public investment projects and specific budget
allocations thanks to budgeting consistent with PRSP priorities. In order to reduce gender
inequalities, the project will promote gender mainstreaming in public policies and in the
preparation, implementation and monitoring/ evaluation of the PIP.
2.6 Participatory Approach in Project Identification, Design
and Implementation
At project preparation in April 2013, consultations were held with Public
Administration structures (MAED and Ministry of Social Affairs, Childhood and Family,
Department of Relations with Civil Society) and the private sector (Chamber of Commerce,
Industry and Agriculture of Mauritania). The Department of Relations with Civil Society is
responsible for coordinating relations between the Government, civil society and TFPs, and
developing and implementing a national strategy for civil society promotion. The
consultations continued during the appraisal mission in July 2013. This process has shown
that the project objectives meet the expectations of economic actors. The involvement of all
stakeholders (including the private sector and civil society) will continue during project
implementation through their participation in the Project Steering Committee. The civil
society will also take part in some project activities: training in methodological guides for the
design, monitoring and evaluation of public investment projects, and field missions for the
physical monitoring and evaluation of projects and programmes. The Department of Relations
with Civil Society will coordinate with MAED in appointing civil society stakeholders to
participate in these activities. This project will contribute towards strengthening citizen
control over public action.
2.7 Bank Group Experience and Lessons Reflected in Project Design
2.7.1 The Bank’s current portfolio in Mauritania comprises eleven (11) ongoing
operations, with total commitments of UA 146 million. Its overall performance is satisfactory
with a 2.5 rating. The detailed portfolio status is provided in Annex 2.
2.7.2 Technical Annex B1 presents the key lessons learned from previous projects in the
area of governance and which have been reported in their completion reports2. The
completion report of the Economic and Financial Programming Strengthening Support Project
(PARPEF), which was approved in 2007 and closed in May 2010, shows that the project
achieved average results with a rating of 2 out of 4. Despite the difficulties encountered
during its implementation, its key achievements are: (i) a report on official development
assistance and an LDC exit strategy for PRI were produced, (ii) the simulation model of the
Mauritanian economy was updated to include poverty and oil sector aspects. In addition,
officers were trained in macroeconomic modeling, and management tools were improved. In
2011, the Bank has also financed the finalization of the public finance reform master plan
through a technical assistance mission and an operation trough the governance trust fund
closed in June 2013 that strengthened the capacity of actors and institutions involved in the
procurement process and preparation of standard bidding documents (including standard
2 Poverty Reduction Project (PRP) : Completion Report References - ADF/BD/IF/2006/207
Multi-sector Institutional Support Project(PAIM) :Completion Report References - ADF/BD/IF/2007/84
Strengthening of Economic and Financial Programming Support Project (PARPEF) : Completion Report References -
ADF/BD/IF/2011/19
12
appraisal reports, manuals, etc.); the operation was closed in June 2013. PIMSP will
complement these previous Bank interventions. By strengthening the planning, programming,
implementation and monitoring/evaluation of public investment, it will promote greater
efficiency in public investment management and better allocation of financial resources from
the Government to inclusive and sustainable growth-oriented projects.
2.7.3 PIMSP design takes into account lessons learned from the implementation of
previous projects. First, the implementation problems faced by some institutional support
projects are due to limited capacity of beneficiary structures. Specific capacity building
activities are planned under the project. PARPEF encountered implementation problems that
led to two closing date extensions. To address these risks, the project implementation period
provided is 3 years, which is the final duration of PARPEF. Secondly, the Project
Implementation Unit with a light structure will reduce operating costs, but poses a risk in
terms of fiduciary and procurement management. The issue of this risk was raised in recent
portfolio performance reviews of projects in Mauritania (2011 and 2012). To mitigate the said
risk, two experts, one in financial management and the other in procurement, will be recruited
on a competitive basis to support the project management unit. Thirdly, at project design as
well as implementation monitoring, it is necessary to strengthen the participatory approach by
closely involving all beneficiary Ministries to ensure their support not only for the objectives
but also the procedure that will be followed in the development of activities. The participatory
approach was adopted in the project by involving all beneficiaries in the project design and
implementation. All beneficiaries are members of the Steering Committee to ensure proper
coordination in the implementation of project activities.
2.8 Key Performance Indicators
2.8.1 The key performance indicators identified and the expected outcomes at project
completion are those featured in the results-based logical framework and in Box 1 below. In
the short term, it is expected that the investment budget will be allocated and executed in line
with PRSP priorities (by including the gender and employment dimensions) and that the
resources absorptive capacity will be improved. Indeed, the methodological guides for MTEF
formulation and public investment management to be produced will ensure alignment of the
budget with the PRSP, proper selection of projects for inclusion in the investment budget in
line with their feasibility and impact on gender and employment, proper performance and
monitoring/evaluation of the said projects. The project will help enhance design,
implementation, and monitoring and evaluation capacities for public investment projects. This
will help improve the public resources absorptive capacity. In the longer term, a more
inclusive economic growth is expected, and it will help reduce gender inequalities.
Mainstreaming gender and employment as well as proper implementation of the public
investment programme will promote stronger and more inclusive economic growth.
13
Box 1: Key Performance Indicators Results Indicators
1(one) methodological guide for MTEF preparation is available before end-2014
1(one) methodological guide for project maturation is available before end-2014
1(one) methodological guide for project monitoring is available before end-2014
1(one) methodological guide for project evaluation is available before end-2014
140 persons (including 50 women) persons at end -2014
Outcome Indicators
The poverty-related expenditure to overall expenditure ratio increases from 45% in 2012 to 50% in
2016
The Gender Inequality Index (GII) drops from 0.643 in 2012 to 0.623 in 2016
The annual implementation rate of public investment increases from 60% in 2012 to 70% in 2016.
Impact Indicators
The average annual GDP growth rate rises from 6.9% in 2012 to 8% in 2018
The Human Development Index (HDI) adjusted to inequalities increases from 0.306 in 2012 to 0.315
in 2018
2.8.2 The achievement of results on these indicators will be verified using the data that
will be collected by DGPPI, whose capacities will be strengthened by a monitoring and
evaluation expert to be recruited throughout the project. DGPPI will produce quarterly
progress reports and reports on the project implementation status, which will be produced
during the Bank’s supervision missions. PIMSP performance will be measured by comparing
2012 baseline data with progress made during project implementation and at project
completion.
III. ENVIRONMENTAL AND SOCIAL IMPACTS
3.1 Environmental Impacts
The project has no direct negative effect on the environment given that its activities
are limited to training, technical assistance, studies and the procurement of logistics, including
minor office and computer equipment. Indeed, the project has been classified in Category 3 in
accordance with Bank Guidelines.
3.2 Climate Change
The project activities, which focus on strengthening human and institutional
capacity, have no negative impact on climate change.
3.3 Gender
Mauritania has signed and ratified the Convention on the Rights of the Child (CRC)
and the Convention on the Elimination of All Forms of Discrimination against Women
(CEDAW). Furthermore, at the Millennium Summit, the country undertook to achieve the
eight (8) Millennium Development Goals (MDGs), including Goal No. 3 to promote gender
equality and empower women, with 33% by 2015 (MDG 3). However, persistent relations of
inequality and inequity hamper sustainable development. These imbalances, which concern
the political, economic and legal, social and cultural dimensions, constitute an obstacle to
equal human rights for all, hindering women, who represent more than half of the population,
from fully playing their role in the country’s growth and development process. To reduce this
gender inequality, it is crucial for public policies to include a cross-cutting gender approach to
14
achieve the desired effects. The Government is aware of these issues and has undertaken
various actions, including the formulation of a National Gender Institutionalization Strategy
(SNIG). This project supports the recruitment of a Gender Expert to provide technical support
to the Ministry of Economic Affairs and Development (MAED) in the implementation of this
gender institutionalization strategy. Specifically, the Gender Expert will provide technical
support to thematic groups to mainstream gender in PRSP indicators, technical support to
strengthen the operational capacity of officers of the Directorate General for Economic
Policies and Development Strategies (DGPESD) in gender-sensitive monitoring and
evaluation, and support for gender mainstreaming in the PIP. The expert will ensure gender
mainstreaming in the different methodological guides for investment and MTEF management.
3.4 Social
According to the latest data from the 2008 PHS, overall poverty is approximately
42%. The measures under the project will, on the one hand, help include the PRSP action plan
projects in the investment budget and, on the other hand, ensure more effective coordination
in their implementation. Women, as well as youths and other vulnerable groups, will benefit
from public investment projects and specific budget allocations thanks to budgeting consistent
with PRSP priorities. One of the expected outcomes of the project is an improvement in the
Gender Inequality Index (GII), from 0.643 in 2012 to 0.623 in 2016.
3.5 Involuntary Resettlement
The project will not entail and population displacement.
IV. IMPLEMENTATION
4.1 Implementation Arrangements
4.1.1 Institutional Arrangements
4.1.1.1 The institutional framework for project management is described in detail in
Appendix B3 of Technical Annexes to this report. In accordance with the provisions of the
Paris Declaration on harmonization and alignment of project management with country
systems, the project executing agency is the DGPPI of MAED. It will comprise a
Coordinator, Deputy Coordinator and support staff. The Coordinator will be the Director
General of DGPPI, who will coordinate project activities whose main beneficiaries are the
sub-directorates of DGPPI. The Deputy Coordinator is the Deputy Director-General of
DGPPI who will regularly monitor the implementation of activities and report to the
Coordinator. The project team will be reinforced by a Financial and Accounting Officer, a
Procurement Expert, and a Monitoring and Evaluation Expert who will be recruited on a
competitive basis using ADF resources.
4.1.1.2 The project implementation will be supervised by a Steering Committee (SC) that
will provide guidance. The SC is responsible for supervising and validating project activities.
In this regard, it will: (i) approve project activities, examine the coordinator’s activity report,
and (ii) define performance criteria and thresholds, promote dialogue and consultation
between the partners, and submit to the Project Team all measures for streamlining project
activities. The Steering Committee will hold at least two meetings a year. Its composition is
as follows: the Secretary General of MAED, who will chair the committee, the Director
15
General of DGPPI who will serve as Secretary of the committee, one representative of each
support beneficiary structure, one representative of the private sector, and one representative
of civil society.
4.1.2 Procurement Arrangements
4.1.2.1 All Bank-financed goods and consultancy services will be procured in accordance
with Bank Rules and Procedures for the Procurement of Goods and Works (May 2008
Edition, Revised July 2012), or as appropriate, Rules and Procedures for the Use of
Consultants (May 2008 Edition, Revised July 2012), using the Bank’s standard bidding
documents and requests for proposals.
4.1.2.2 The Economy and Finance Sector Public Procurement Commission (CPMPSEF) will
be responsible for the procurement of goods and services. It will prepare documents in
accordance with Bank procedures and submit no objection requests to the Bank. The
Chairperson, members and staff of the CPMPSEF have procurement skills and experience
gained from projects funded by the various donors. As regards implementing procurement
procedures under the project, the project executing agency and CPMPSEF will be supported
by a consultant, who will be a Procurement Expert recruited under the project.
4.1.2.3 All procurements will be subject to prior approval by the Bank. The procurement
procedures for Bank-financed works, goods and services and the procurement plan are
provided in Technical Annex B4.
4.1.3 Financial Management Arrangements
4.1.3.1 In accordance with the Paris Declaration on aid effectiveness and use of country
systems, the DGPPI of MAED will be responsible for PIMSP implementation, including
financial management. PIMSP appraisal highlighted an initial overall level of fiduciary risk
deemed to be substantial (Technical Annex B5); this level could be moderate through
implementation of the following financial management system proposed and approved by the
Borrower. However, to ensure proper project implementation, including financial
management, the DGPPI will need more skills and tools. The project team will be reinforced
by a Financial and Accounting Officer (FAO), who will ensure efficient and sustainable
financial management. It is recommended that the FAO be recruited, on a competitive basis,
prior to effective project start-up. PIMSP’s budget management system will be put in place by
DGPPI. The budget should include all activities and related expenditures on a rolling annual
basis. It will be incorporated into the PIMSP computerized accounting system to allow for
tracking of budget actuals and making the necessary adjustments. The establishment of a
computerized accounting system, right from project start-up, should allow for tracking of
programme expenditures by source of financing, expenditure category and component and for
the preparation of annual financial statements using accounting software. It will be necessary
to establish an effective internal control system under the responsibility of the Coordinator.
To ensure that the internal control systems remain operational and are efficient, the FAO will
conduct concomitant pre-control and the Inspectorate General of Finance (IGF) will have the
right to verify the application of the procedures in place. The Coordinator and FAO will
participate in fiduciary clinics on financial management organized by the Bank. Given the
level of the overall fiduciary risk, the project will be subject to regular monitoring and
enhanced supervision.
16
4.1.4 Disbursement Arrangements
The ADF grant disbursements under PIMSP will be made in accordance with the
project expenditure schedule and list of goods and services. They will be made using the
direct payment method. The direct payment method will be used to procure services for
amounts exceeding the equivalent of UA 20,000. The audit firm will be paid through the
direct payment method. The first disbursement will be made after grant effectiveness and
fulfillment of the conditions precedent to the first disbursement. Furthermore, a contra
account will be opened in accordance with applicable procedures in the country to receive the
Government’s counterpart contribution. It will be funded in three annual installments
throughout the life of the project. The first tranche will be disbursed upon project
effectiveness. The other two tranches will be disbursed at the start of the fiscal year
respectively.
4.1.5 Audit Arrangements
PIMSP’s external audit will be conducted annually in accordance with International
Auditing Standards (IAS) by an independent audit firm that will be recruited according to
Bank procedures within six months following the first disbursement. The TOR for the
external audit will prepared in compliance with the model proposed by the Bank. The final
audit report, prepared in accordance with International Auditing Standards and comprising an
opinion report and an internal control report, will be submitted to the Bank within six (6)
months following the end of each fiscal year. The first audit report will cover 2014 and will
be submitted to the Bank no later than 30/06/2015.
4.2 Monitoring
4.2.1 Project implementation is expected to span 3 years, from January 2014 to December
2016. The DGPPI will assume primary responsibility for internal monitoring of the
implementation of activities and their impacts. It will, using the format recommended by the
Bank, prepare quarterly and annual progress reports based on the monitoring of indicators of
the project's logical framework. The capacity of DGPPI will be enhanced by a Monitoring and
Evaluation Expert to be recruited under the project.
17
4.2.2 Monitoring by the Bank will be through regular dialogue and enhanced supervision.
The Departments of the Bank responsible for financial management (ORPF2), procurement
(ORPF1) and disbursements (FFCO) will be involved. The implementation schedule is as
follows:
Table 4.1
Monitoring Milestones and Feedback Loop Milestones Responsible Date /Period
Approval of the financing ADF September 2013
Establishment of Project Management Team GVT October 2013
Grant Effectiveness ADF/GVT October 2013
Preparation/Invitation to Bid DGPPI/AfDB November-December 2013
Award/Signature of Contracts DGPPI January 2014
Start of Consultancy Services DGPPI January 2014
Mid-Term Review AfDB/DGPPI June 2015
Physical Project Completion DGPPI December 2016
Completion Mission AfDB/DGPPI December 2016
4.3 Governance
4.3.1 The 2008 PEFA and various diagnoses of Mauritania’s public finance system show
the existence of some weaknesses in performance indicators, particularly in the process of
budget formulation, execution and control. There are also persistent shortcomings in financial
reporting and internal and external auditing. This results in poor donor alignment with the
national system. However, the fiduciary system is expected to gradually improve, especially
in view of the fiscal reform programme initiated by the Government, such as the adoption and
implementation of the public finance management reform master plan prepared with Bank
support.
4.3.2 The project’s governance risk concerns procurement and financial resource
management. These risks will be mitigated through close monitoring of the strict application
of the Bank’s procurement rules and the recommended establishment of an efficient financial
management system. Supervision missions and technical and financial audits will ensure
compliance and consistency between resources committed and services actually provided.
Training sessions organized by the Bank on the project cycle and procurement for the project
team, as well as the technical assistance to be provided for financial management and
procurement will also help improve governance. As regards the Government, the involvement
of MAED in monitoring Bank-financed projects and the establishment of the project steering
committee will strengthen good governance given that the latter has the right to look into
financial resource management and the quality of its outputs.
4.4 Sustainability
The first sustainability factor lies in the Government’s willingness to improve public
investment management for the implementation of its ambitious investment programme. The
second factor is that methodological guides for maturation and monitoring/evaluation of
public investment projects and a methodological guide for MTEF preparation be made
available to the Mauritanian Authorities. Officials from the various Ministries will be trained
on the use of these guides. Acquisition of knowledge and mastery of modern management of
the investment budget will enable beneficiaries to perform their duties better and promote the
dissemination of good practices learned. The project implementation will enhance DGPPI
18
capacity and substantially improve the design and monitoring of public investment projects.
The project will facilitate proper use of public resources to combat poverty more effectively.
4.5 Risk Management
4.5.1 The table below outlines the residual risks (other than those related to governance
and sustainability) as well as mitigation measures.
Table 4.2
Potential Risks and Mitigation Measures Risks Level Mitigation Measures
Security risk at
regional level due to
overall situation in the
Sahel
High There is a major risk due to insecurity in the Sahel, which could reverse national
priorities and delay implementation of project activities. However, the
authorities are determined to reconcile development and security priorities by
continuing with reforms, while strengthening security.
Political
instability
Moderate The presidential election in July 2009 facilitated the return to democracy and re-
engagement of TFPs with the Government. The continuation of national
dialogue launched in 2011 and the prospect of presidential elections in 2014
should strengthen political stability.
Lack of funding for the
implementation of the
poverty reduction
strategy
Moderate The project supports capacity building activities of the Resource Mobilization
Department at DGPPI. Following the Brussels Roundtable, a State-TFP group
was established to track pledges. The situation as at 19 June 2013, prepared by
DGPPI, shows a TFP commitments mobilization level of 98.9%.
Lack of stakeholder
involvement
Moderate The establishment of a Steering Committee comprising all project beneficiaries,
the private sector and civil society will foster the participation of all
stakeholders. The civil society is involved in some project activities.
Weak capacity of the
administration to
implement project
activities and fiduciary
and procurement
management risk
Moderate The training activities under the project and support to the project management
team will mitigate this risk. The project involves the recruitment, on a
competitive basis, of three experts in financial management, procurement and
monitoring and evaluation to support the project management team. Project
implementation monitoring will be enhanced through regular supervision
missions of Bank experts who will provide, if needed, technical support required
for timely implementation of the operation.
4.5.2 The foregoing analysis shows that the project has moderate risk levels.
4.6 Knowledge Building
Several knowledge types will be built through implementation of this project, in
particular: (i) capacity building in public investment programming, design, and
monitoring/evaluation of investment projects through the different methodological guides to
be prepared, (ii) overall MTEF and sector MTEF preparation capacity will be strengthened
through the methodological guide for MTEF preparation, (iii) practices will be disseminated
to other Ministries through the validation and dissemination of studies conducted, the use of
procedures manuals and training sessions that will be organized under the project. Knowledge
will also be acquired with the production of the following reports: reports by technical
assistants, activity reports prepared by the project management team, supervision reports, and
the project completion report.
19
V. LEGAL FRAMEWORK
5.1 Legal Instrument
For the financing of the project with ADF grant resources not exceeding UA 0.74
million, a Grant Protocol Agreement will be signed between the ADF and the Mauritanian
Government.
5.2 Conditions for Bank Intervention
Conditions precedent to effectiveness of the Grant Protocol Agreement
5.2.1 The Grant Protocol Agreement shall become effective on the date of its signature by
the Donee and the Fund.
Conditions precedent to first disbursement of the grant
5.2.2 In addition to grant effectiveness, the first disbursement shall be subject to
fulfillment, by the Donee and to the Fund’s satisfaction, of the following conditions:
(i) Provide the Fund with evidence of the opening of a contra Treasury account to
receive the counterpart contribution of the Donee to the Project;
(ii) Provide the Fund with evidence of funding of the contra account with a
minimum of fifty million Ouguiya (MRO 50,000,000).
Other Conditions
(i) Provide evidence of the Donee’s undertaking to mobilize its full counterpart
contribution under the Project amounting to three hundred and ninety four
million seven hundred and forty thousand Ouguiya (MRO 394 740 000);
(ii) Provide, on an annual basis, evidence of inclusion of the Donee’s annual
counterpart contribution in the Finance Law;
(iii) Submit, to the Fund, an administrative, financial and accounting procedures
manual, deemed acceptable by the Fund, within three (3) months following
effectiveness of this Grant Protocol Agreement.
5.3 Compliance with Bank Policies
5.3.1 This project complies with all applicable Bank policies.
VI. RECOMMENDATION
Management recommends that the Board approves the proposed ADF grant of UA
0.74 million to the Islamic Republic of Mauritania for the purpose and under the terms and
conditions set forth in this report.
Annex I
Comparative Socio-Economic Indicators of Mauritania
Year Mauritania Africa
Develo-
ping
Countries
Develo-
ped
Countries
Basic Indicators
Area ( '000 Km²) 2011 1 031 30 323 98 458 35 811Total Population (millions) 2012 3,6 1 070,1 5 807,6 1 244,6Urban Population (% of Total) 2012 42,0 40,8 46,0 75,7Population Density (per Km²) 2012 3,5 34,5 70,0 23,4GNI per Capita (US $) 2011 1 000 1 609 3 304 38 657Labor Force Participation - Total (%) 2012 31,7 37,8 68,7 71,7Labor Force Participation - Female (%) 2012 26,6 42,5 39,1 43,9Gender -Related Dev elopment Index Value 2007-2011 0,516 0,502 0,694 0,911Human Dev elop. Index (Rank among 186 countries) 2012 155 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2011 23,4 40,0 22,4 ...
Demographic Indicators
Population Grow th Rate - Total (%) 2012 2,3 2,3 1,3 0,3Population Grow th Rate - Urban (%) 2012 3,0 3,4 2,3 0,7Population < 15 y ears (%) 2012 39,5 40,0 28,5 16,6Population >= 65 y ears (%) 2012 2,7 3,6 6,0 16,5Dependency Ratio (%) 2012 73,1 77,3 52,5 49,3Sex Ratio (per 100 female) 2012 101,1 100,0 103,4 94,7Female Population 15-49 y ears (% of total population) 2012 24,9 49,8 53,2 45,5Life Ex pectancy at Birth - Total (y ears) 2012 58,9 58,1 67,3 77,9Life Ex pectancy at Birth - Female (y ears) 2012 60,7 59,1 69,2 81,2Crude Birth Rate (per 1,000) 2012 32,9 33,3 20,9 11,4Crude Death Rate (per 1,000) 2012 9,3 10,9 7,8 10,1Infant Mortality Rate (per 1,000) 2012 71,1 71,4 46,4 6,0Child Mortality Rate (per 1,000) 2012 107,8 111,3 66,7 7,8Total Fertility Rate (per w oman) 2012 4,4 4,2 2,6 1,7Maternal Mortality Rate (per 100,000) 2010 510,0 417,8 230,0 13,7Women Using Contraception (%) 2012 13,9 31,6 62,4 71,4
Health & Nutrition Indicators
Phy sicians (per 100,000 people) 2004-2010 13,0 49,2 112,2 276,2Nurses (per 100,000 people)* 2004-2009 67,2 134,7 187,6 730,7Births attended by Trained Health Personnel (%) 2007-2010 60,9 53,7 65,4 ...Access to Safe Water (% of Population) 2010 50,0 67,3 86,4 99,5Access to Health Serv ices (% of Population) 2000 63,0 65,2 80,0 100,0Access to Sanitation (% of Population) 2010 26,0 39,8 56,2 99,9Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2011 1,1 4,6 0,9 0,4Incidence of Tuberculosis (per 100,000) 2011 344,0 234,6 146,0 14,0Child Immunization Against Tuberculosis (%) 2011 86,0 81,6 83,9 95,4Child Immunization Against Measles (%) 2011 67,0 76,5 83,7 93,0Underw eight Children (% of children under 5 y ears) 2008-2011 15,9 19,8 17,4 1,7Daily Calorie Supply per Capita 2009 2 856 2 481 2 675 3 285Public Ex penditure on Health (as % of GDP) 2010 4,4 5,9 2,9 8,2
Education Indicators
Gross Enrolment Ratio (%)
Primary School - Total 2010-2012 101,0 101,9 103,1 106,6 Primary School - Female 2010-2012 103,9 98,4 105,1 102,8 Secondary School - Total 2010-2012 27,0 42,3 66,3 101,5 Secondary School - Female 2010-2012 24,7 38,5 65,0 101,4Primary School Female Teaching Staff (% of Total) 2011 36,3 43,2 58,6 80,0Adult literacy Rate - Total (%) 2010 58,0 67,0 80,8 98,3Adult literacy Rate - Male (%) 2010 64,9 75,8 86,4 98,7Adult literacy Rate - Female (%) 2010 51,2 58,4 75,5 97,9Percentage of GDP Spent on Education 2008-2011 3,9 5,3 3,9 5,2
Environmental Indicators
Land Use (Arable Land as % of Total Land Area) 2011 0,4 7,6 10,7 10,8Annual Rate of Deforestation (%) 2000-2009 2,7 0,6 0,4 -0,2Forest (As % of Land Area) 2011 0,2 23,0 28,7 40,4Per Capita CO2 Emissions (metric tons) 2009 0,6 1,2 3,1 11,4
Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :
UNAIDS; UNSD; WHO, UNICEF, WRI, UNDP; Country Reports.
Note : n.a. : Not Applicable ; … : Data Not Available.
COMPARATIVE SOCIO-ECONOMIC INDICATORS
Mauritania
May 2013
646668707274767880828486
2004
2005
2006
2007
2008
2009
2010
2011
2012
Infant Mortality Rate( Per 1000 )
Mauritan ia Africa
0
200
400
600
800
1000
1200
1400
1600
1800
2003
2004
2005
2006
2007
2008
2009
2010
2011
GNI Per Capita US $
Mauritan ia Africa
0,0
0,5
1,0
1,5
2,0
2,5
3,0
2004
2005
2006
2007
2008
2009
2010
2011
2012
Population Growth Rate (%)
Mauritania Africa
1
11
21
31
41
51
61
71
2004
2005
2006
2007
2008
2009
2010
2011
2012
Life Expectancy at Birth (years)
Mauritan ia
Africa
Annex II
Table of ADB Portfolio in Mauritania (June 2013)
Project Name Approval
Date
Signature
Date Effectivene
ss
Amount
Source Amount
Disbursed
% Closing
Date
Approved (UA) Disb.
Rating at Last
Supervision
PUBLIC SECTOR OPERATIONS
REGIONAL OPERATIONS (Technical Assistance)
Prefeasibility study
for construction of
Rosso Bridge
30-March-
07
05/04/2007 5-Apr.-
2007 664 575.00 FAPA 0 0.00%
31-Dec.-2012
23-Apr.-08 23-Apr.-08 332 287.00 IPPF-
NEPAD 166143.5 50.00%
PROJECTS
Brakna -West
Irrigation Works 17-Nov.-04 03-June-05
27-July-
2005
2 670 000.00 ADF 2 284 719.00 82.57% 31-Dec.-13
2.76
4 300 000.00 NTF 2 523 670.00 58.69% 31- Dec. -13 2.76
Southern Zone
Rural DWSS
Project
15-Nov.-06 12/01/2007 19-June-07 9 700 000.00 ADF 2 954 620.00 30.46% 31- Dec.-2014
2.38
Capacity building
for micro-finance
actors (PRECAMF)
02-Mar.-07 21-Mar.-07 30-Oct.-07 5 980 000.00 ADF 4 056 832.00 67.84% 31- Dec.-2013
2.44
National Integrated
Rural Water
Programme
PNISER
07-Dec.-12 12-Feb.-13
3 052 000.00 ADF/Loan
0.00%
31/12/2018
2 448 000.00 ADF/Grant
0.00%
2 934 469.00 RWSSI
0.00%
TECHNICAL ASSISTANCE
Water Resources
Integrated
Management
Project (AGIRE)
07-Nov.-07 08-May-08 15-Jan.-09 459 617.97 AWF 459 617.97 100.00% 30-Sept.-13
2.12
Support for
Implementation of
Procurement
Reform
05/05/2011 20-Sept.-11 20-Sept.-11 171 000.00 GTF 171 000.00 100.00% 30-June-13
EMERGENCY ASSISTANCE
Humanitarian
Assistance to Malian
Refugees
10/09/2012 19-Dec.-12 19-Dec.-12 660 000.00 FSS 660 000.00 100.00% 30-June-13
TOTAL PUBLIC
SECTOR 33 371 948.97 17.74% 13 276 602.47 39.78%
PRIVATE SECTOR OPERATIONS WITHOUT STATE GUARANTEE
TECHNICAL ASSISTANCE (TA)
TA to Mauritanie
Leasing 27-Jan.-11 15-Nov.-11 15-Nov.-11 237 000.00 FAPA 0 0.00% 15-Nov.-13
TA to SNIM 01/12/2009 01/12/2009 03-Oct.-11 614 217.00 FAPA 237 701.98 38.70% 31-Dec.-13
PROJECT
SNIM -GUELB II
Extension Project 16-Sept.-09 01/12/2009 02-Oct.-10 111 750 000.00 AfDB 74 716 050.00 66.86% 31-Dec.-13
1.88
TOTAL PRIVATE SECTOR
OPERATIONS WITHOUT STATE
GUARANTEE
112 601 217.00 82.26% 74 953 751.98 66.57%
GRAND TOTAL 145 973 165.97 100% 88 230 354.45 60.44%
Annex III
Key Related Projects Financed by the Bank and Other Development
Partners of Mauritania
Technical and
Financial
Partners
Projects Project Cost Implementat
ion Status
European
Union
Delegation
Budget Support Programme for
establishment of the Poverty
Reduction Strategic Framework
in Mauritania ( GBS PRSF III)
EUR 46 million in 2013-2015 : (i)
EUR 40M for general budget
support (Fixed Tranche of EUR
20M and variable tranche of EUR
20M) ; and (ii) EUR 6M for
institutional support
Ongoing
IMF Extended Credit Facility 77.28 million SDR in 2010-2013 Ongoing
World
Bank
Public Sector Capacity Building
Project
USD 13.0 million (USD 750,000
to support procurement
transparency)
Ongoing
UNDP Capacity Building Support for
Inclusive Growth
USD 5.05 million in April 2013-
December 2016
Expected
UNDP Synergy International System
Inc. Technical Assistance for
installation of the DAD software
(Development Assistance Data
Base)
USD 600,000 support in 2011-
2012
USD 153,056 support in 2013-
2015
Ongoing
Expected
ADF Support for implementation of
the new Public Procurement
Code
EUR 87,000 Ongoing
AfDB Economic and Financial
Programming Improvement
Support Project (PARPEF)
¥ 88,174,250 The project was approved in 2007
and closed in May 2010.
Closed
AfDB Public Procurement Reform
Support to improve the business
climate in Mauritania
USD 274,000 from February 2011
to June 2013
Closed
AfDB Technical Assistance for
finalizing the public finance
reform master plan
Closed
Annex IV
Map of the Project Area
This map has been provided by the staff of the African Development Bank Group exclusively for the use of
the readers of the report to which it is attached. The names used and the borders shown do not imply on the
part of the ADB Group and its members any judgment concerning the legal status of a territory nor any
approval or acceptance of these borders.