MAUA SHIPYARD
SITES LOCATION
OPEN SEAS
EISA
BRAZIL
RIO DE JANEIRO
1846 Investment of the new shipyard.1850 - 1961 Delivered 72 ships = 36 military vessels + 36 merchant ships.1963 New investments1965 - 1988 Delivered 130 merchant ships2000 Re-activation with the offshore platforms
HISTORY: MAUÁ IS FIRST SHIPYARD OF BRAZIL
Baron of Mauá
P1 First Brazilian platform
SITE 1 – PONTA D’AREIA
DRY DOCK L: 167 mB: 22.5 m
L: 238 m B:40.5 m
SLIPWAY FLOATINGCRANE
2050 ton
SITE 2 – ILHA DO CAJÚ
SITE 4 – ESTALEIRO NAVAL SYNERGY(On re-activation)
June 09June 09
SITE 4 – ESTALEIRO NAVAL SYNERGY(On re-activation)
Area 34 000 m2Area 34 000 m2
STAFF
SENIOR MANAGER 13ENGINEER 68TECHNICIANS 157SUPPORT 8
TOTAL 246
SHOP DRAWING & SCOPE CONTROL
PRODUCTION SUPPORT
INTEGRATION & COMISSIONINGINSPECTION & DIAGNOSIS
PROCUREMENT & DILIGENCY
SOFTWARES LICENSES
PDS – 3DSmart Plan PID 2DSmart Plan Instrumentation 2DSmart Plan Review 3DSmart Plan Support Modeller 3DPRO II – Process SimulationGT Strudl CEASER IIAuto CAD MicrostationTecno Metal para Shop DrawingPV – Elite/Tank Primavera/MS ProjectAARTETriforma TRIBON
■ ENGINEERING - TOTALLY INTEGRATED
MAIN ACTIVITIES
BASIC & DETAILED DESIGN
■ LOCAL AND INTERNATIONAL PROCUREMENT
MAIN ACTIVITIES
■ PORT TERMINAL
Private Port integrated into the industry logistics
Own staff (no port union);
Customs clearance;
Special customs – “DAC” (storage certified customs);
Equipments to load / unload heavy cargo
Stuffing and stripping of containers;
Unique EDC (Environmental Defense Center) in the Guanabara Bay.
■ RIG REPAIR & RIG UPGRADES
■ SHIP REPAIR
■ QSHE QUALITY (ISO 9001/2000)Certified since 2002
SAFETY
&
HEALTH (Following OHSAS 18.001)
ENVIRONMENT(ISO 14001/2004)Certified since 2005
Non Lost Time Accident
P54 over 6.000.000 mh
PMXL1 over 5.000.000 mh
MAIN CONTRACTS - OFFSHORE
FPSO# ton # ton # ton
MODULES 13 16.560 7 5.350 14 15.930
OFFICE 1 1.030 1 1.040
OIL SEPARATION 2 2.810 2 3.500
MANIFOLDS 2 2.490 2 780 2 1.360
GAS COMPRESSION 2 2.770 2 2.140
UTILITIES 2 1.950 1 1.470 1 1.760
POWER GENERATION 2 2.750 2 2.930
ELECTRICAL 2 1.880 2 1.040 1 1.040
PIPE RACK 1 1.420
SULPHATE REMOVAL 1 1.030 1 1.300
GAS TREATMENT 1 640
FLARE TOWER/SYS 490 1 220
P43 P50 P54
FPSO# ton
MODULES 14 16.630
OIL SEPARATION 2 2.810
MANIFOLDS 2 2.490
GAS COMPRESSION 2 2.770
UTILITIES 2 1.950
POWER GENERATION 2 2.750
ELECTRICAL 2 1.880
PIPE RACK 1 1.420
LAYDOWN 70
FLARE TOWER/SYS 1 490
P48
TOPSIDE CONSTRUCTION
HULL INTEGRATION
COMMISSIONING
TOPSIDE CONSTRUCTION
P-43 P-43
P-50P-50
P-54P-54
MAIN CONTRACTS - OFFSHORE
FIXED PLATFORM# ton
MODULES 2 11.750
MODULE 1 1 4.930
PROCESS 3.850
POWER GENERATION 560
MEG REGENERATION 520
MODULE 2 1 6.820
UTILITIES 4.900
ACOMODATION 1.920
JACKET AND PILES 14.650
PMXL 1
TOPSIDE AND JACKET CONSTRUCTION
OFFSHORE HOOK UP
COMMISSIONING
Module Construction - from 2002 to 2008Number 50 modulesTotal weight 66.220 tonAverages 1.324 ton / module
7 modules / year
MAIN CONTRACTS - REPAIR AND UP GRADE
DRYDOCK AFLOAT TOTAL
2002 23 30 53
2003 24 16 40
2004 28 21 49
2005 25 18 43
2006 26 15 41
2007 34 4 38
2008 32 7 39
Atlantic Zephir
- OCT South Atlantic
Leo Segerius
Olinda Star, Roger Eason and Ocean Clipper
Paul Wolff
PROJECT MANAGEMENT - RELEVANT REMARKS
■ METHODOLOGY
PMO
BOARD
DEPARTMENTS
PROJECT
MANAGER
SUBCONTRACT
CLIENT