Material Requirements Planning 2013
-
Upload
cecilia-yeni -
Category
Documents
-
view
68 -
download
0
description
Transcript of Material Requirements Planning 2013
Material Requirements Planning
Daniel SiswantoTeknik Industri UNPAR
Reference
Fogarty et al., Production and Inventory Management, South-Western Publishing Co., Cincinnati, 1991 (Ch. 10)
Tersine, Richard J., Principles of Inventory and Materials Management 4th ed., Prentice-Hall Inc., 1994 (Ch. 4)
Aggregate Planning
Master Production Scheduling
Material Requirements Planning
Material Requirements Planning (MRP)
Calculates requirements for materials using bills of material, inventory data and MPS.
Makes recommendations to release replenishment orders for material.
U1-10, Fig. 10-1, page 335: MRP overview
MRP, Closed Loop MRP, MRP II
Closed-loop MRP
Planning functionsProduction planning, MPS, capacity requirements planning.
Execution functions Manufacturing control functions of input-output, detailed scheduling and dispatching, anticipated delay reports from plant and vendors: shop floor and purchasing control.
Feedback functionsDescribes the progress of orders being manufactured. Actual production and supplier performances are measured and compared to the plan. closing the loop.
MRP, Closed Loop MRP, MRP II
Manufacturing/Business Resource Planning (MRP II/BRP)
Integrates marketing, finance and operations.Business planning functions.Production planning functions.Master production planning functions.Material requirements planning functions.Capacity requirements planning functions.Execution support systems for capacity and material.
MRP, Closed Loop MRP, MRP II
CL MRP
MRP II
Material Requirements Planning
Calculates the exact quantity, need date and planned order release date
for each of the subassemblies, components and materials required
to manufacture the products listed on the MPS.
Inputs of MRP
Demand information from the MPS.
Bill of material: description of what components go into a finished product.
Production times (or order times) for components.
Current inventory status.
Outputs of MRP
Purchase and production plans: the quantity and timing of orders to be placed.
Product/Bill of Material explosionProcess of breaking up the demand of one end item into demand for many component products.
Basic Processes of MRP
Determine product structure: demand dependencies.
Netting.
Lead time offsetting.
Determine product structure
Demand dependencies Establish end item, subassembly, component and purchased material gross number relationships.
Product structureRepresents the relationships of end item and its components.It can be shown in graphic form describing the product structure levels: End item is set at level 0. Its immediate components are at level 1. Its immediate components are at level 2. Level 3, level 4…and so on.
Vertical and horizontal dependencies
U1-10, Fig. 10-4: Dependencies
U1-10, Fig. 10-3, page 338: Simple and multilevel product structures
Netting
Is the process of calculating net requirements. Considers the effect of current inventories.
Ex. Demand for lamps: 25 units.
Inv
LampsBase assy (1)Shafts (1)Tubing (2)
374
16
Netting
25-3 = 2222-7 = 1515-4 = 1122-16 = 6
Simple
25-3 = 2225-7 = 1825-4 = 21
50-16 = 34
How long does it take to manufacture (or purchase) the items?
Lead Time Offsetting
Lead time Is the time required to either manufacture or purchase the components.
Ex. Order shipment date: week 27.
Lead time (weeks)
LampsBase assyShaftsTubing
2 123
Order placed
Week 25Week 24Week 22Week 19
MRP CHART
U1-10, Tab. 10-1, page 342: MRP chart
Time periods (time buckets)Basic planning periods, commonly in weeks.
Gross requirements (GR) For end items : represent the MPS. For lower-level items : represent quantities
needed in each period to ensure maintenance of the MPS.
GRt = parent item’s PORlt x quantity required for each parent.
Beginning inventory (BI)Number of items in the inventory at the beginning of the period. Comes from inventory records.
Scheduled receipts (SR)Orders already released (from earlier decisions).
Projected on hand (POH)The inventory balance projected out in the future.
POHt = PORct + SRt + POHt-1 – GRt
Net requirements (NR) Quantity actually needed to be received or
produced in a particular period. Exist when projected on hand is less than safety
stock. NRt = GRt – SRt – POHt-1
Planned order receipts (PORc) The quantity to be received or produced in a particular period. Indicates the order quantity ( lot sizing) and the reception period of the order.
Planned order release (PORl)Indicates the order quantity and period in which the production (or purchase) request has to be released.
PORlt = PORct+L
Time Conventions
GRSRPOHNRPORcPORl
Needed by end of periodNeeded by end of periodEnding inventoryNeeded by end of periodNeeded by end of periodNeeded by end of period
Low Level Coding
What happen if some items are required at more than one level in the BOM?
Net requirements adding GR for the item through the lowest level found in BOM
low level coding
Y
C
F E G H
A D
Level 0
1
2
3
E
EEE
B
LT =1
LT =2
LT =1
LT =1LT =1
LT =1
LT =1
LT =4
LT =3LT =2
LT =3LT =1 LT =4
Low level coding
Pegging
Families of end products sometimes have a common component.
When the component is short in quantity, what is the impact on the end products? Which end product will suffer the shortness?
PeggingThe process of keeping track of parents and offsprings.
U1-10, page 356: Pegging
Lot Sizing
Affects inventory levels, setup and ordering costs, capacity requirements and capability, and delivery.
Lot size decision Affected by: Number of levels in BOM Setup/order cost Carrying cost The use of joint orders and manufacturing cells The low level code of a given item
Lot sizing criterion Preparation costs Carrying costs
Lot Sizing Method
U1-10, Tab. 10-3, page 345: Fixed lot size
Fixed Lot Size
Lot For LotOrders can be for any quantity (equals to demand quantity).Holding cost , ordering cost .
U1-10, Tab. 10-4, page 346: Lot for lot
Least Unit CostSelecting lot size and release time with the smallest per unit cost.
Period
t Tot Demand
IncrementalHolding Cost
Cum.HC
Total Cost TC per unit
1 1 75 75x0x$1= $0 $0 $100+$0 = $100
$100/75= $1,33
Period 1 2 3 4 5 6
Demand
75 0 33 28 0 10
2 75 0 0 100 1,33
3 108 33x2x$1=66 66 166 1,54
3 3 33 0 0 100 3,03
4 61 28 28 128 2,10
5 61 0 28 128 2,10
6 71 30 58 158 2,22
S = $100/order, h = 2%, C = $50/unitInitial Inventory = 0
Period 1 2 3 4 5 6Demand 75 0 33 28 0 10Order Quantity 75 61 10
Ending Inventory 0 0 28 0 0 0
Period Order Quantity Determining lot size by combining a fixed
number of period requirements.
HD
2SPOQ
S = ordering cost D = demand per period H = holding cost
This approach does not minimize ordering and carrying cost, but frequently it is less costly than ordering each period or arbitrarily selecting a fixed order period.
U1-10, Tab. 10-9, page 351: POQ
Safety Stock
Why needed?MPS is not fixed for the lead time period.Uncertainty in forecasting demand.Uncertainty in delivery of purchased and manufactured materials: late delivery, wrong quantity.
Impacts:
Raising the average inventory level
Anticipating unexpected demand increases or time advancements.
Safety Lead Time
Overstating the lead time
Early actual deliveries
Used to satisfy changed demand
Uncertainty Requirement
In demand quantity
In timing of demand
Safety stock
Safety lead time
MRP System Output
It is important that the MRP system output (report, chart, etc) clearly distinguish between safety stock requirements and upper level requirements.
Replenishing safety stock is not a legitimate cause for special orders (expediting, broken setups, overtime, etc) because special orders is expensive Manual intervention: Firm Planned Order
Firm Planned Orders
The difficulty in establishing lot sizes: the lot size decision results in requirement for items at all lower levels.
U1-10, page 354-355: Motor Assy Example
Manual intervention by a production scheduler :1. Expedite the past due order2. Change the lot size for the motor assemblies3. Introduce a Firm Planned Order
Firm Planned OrderIs an order entered by the planner that supersedes the computer’s MRP logic
FPO also can be used when the planner believes the lead time can be compressed (when the planner set the bigger quantity).
U1-10, Tab. 10-11 page 355: FPO
MRP Basic Considerations
Data accuracy and dependenciesRealistic MPSSystem processing
Managing changeNet change versus schedule regeneration