4/4: Material Requirements Planning

22
4/4: Material Requirements Planning • Dependent inventory model • For in-house inventory planning

description

4/4: Material Requirements Planning. Dependent inventory model For in-house inventory planning. Requirements of MRP. Master production schedule when to make what Bill of Materials: how to make the product Lead times how long it takes to get various components Inventory availability - PowerPoint PPT Presentation

Transcript of 4/4: Material Requirements Planning

Page 1: 4/4: Material Requirements Planning

4/4: Material Requirements Planning

• Dependent inventory model

• For in-house inventory planning

Page 2: 4/4: Material Requirements Planning

Requirements of MRP

• Master production schedule – when to make what

• Bill of Materials: how to make the product

• Lead times – how long it takes to get various components

• Inventory availability

• Scheduled receipts & on-hand inventory

Page 3: 4/4: Material Requirements Planning

Master Production Schedule

• Tells us what is required to meet the production plan.

• Statement of what is to be produced, NOT a forecast of demand.

Gross requirements per day4 5 6 7 8

100 150 100 180

Page 4: 4/4: Material Requirements Planning

Bill of Materials

• A list of quantities of components, ingredients, or materials to make a final product.

• Provides the product structure.EX: A “Blast ‘em, dude” audio kit (A) is made of 2 small tweeter boxes (B) and 3 large woofer boxes (C). Each tweeter is made of two speakers (D) and two shipping boxes (E). Each woofer consists of two boosters (F) and two shipping boxes (E). Each booster is made of a circuit board (G) and a speaker (D).

Page 5: 4/4: Material Requirements Planning

EX: A “Blast ‘em, dude” audio kit (A) is made of 2 small tweeter boxes (B) and 3 large woofer boxes (C). Each tweeter is made of two speakers (D) and two shipping boxes (E). Each woofer consists of two boosters (F) and two shipping boxes (E). Each booster is made of a circuit board (G) and a speaker (D).

A

2B 3C

Page 6: 4/4: Material Requirements Planning

EX: A “Blast ‘em, dude” audio kit (A) is made of 2 small tweeter boxes (B) and 3 large woofer boxes (C). Each tweeter is made of two speakers (D) and two shipping boxes (E). Each woofer consists of two boosters (F) and two shipping boxes (E). Each booster is made of a circuit board (G) and a speaker (D).

A

2B 3C

2D 2E

Page 7: 4/4: Material Requirements Planning

EX: A “Blast ‘em, dude” audio kit (A) is made of 2 small tweeter boxes (B) and 3 large woofer boxes (C). Each tweeter is made of two speakers (D) and two shipping boxes (E). Each woofer consists of two boosters (F) and two shipping boxes (E). Each booster is made of a circuit board (G) and a speaker (D).

A

2B 3C

2D 2E 2F 2E

Page 8: 4/4: Material Requirements Planning

EX: A “Blast ‘em, dude” audio kit (A) is made of 2 small tweeter boxes (B) and 3 large woofer boxes (C). Each tweeter is made of two speakers (D) and two shipping boxes (E). Each woofer consists of two boosters (F) and two shipping boxes (E). Each booster is made of one circuit board (G) and one speaker (D).

A

2B 3C

2D 2E 2F 2E

G D

Page 9: 4/4: Material Requirements Planning

EX: A “Blast ‘em, dude” audio kit (A) is made of 2 small tweeter boxes (B) and 3 large woofer boxes (C). Each tweeter is made of two speakers (D) and two shipping boxes (E). Each woofer consists of two boosters (F) and two shipping boxes (E). Each booster is made of one circuit board (G) and one speaker (D).

A

2B 3C

2D 2E 2F 2E

G D

Note that the numbershere are only relevantto the level above them!

Page 10: 4/4: Material Requirements Planning

A

2B 3C

2D 2E 2F 2E

G D

“Exploded” Product Structure

• Items above a level are PARENTS;• Items below a level are COMPONENTS or

CHILDREN.

Page 11: 4/4: Material Requirements Planning

A

2B 3C

2D 2E 2F 2E

G D

Level 0

level 1

level 2

level 3

Exploded Product Structure: 4 levels.

Page 12: 4/4: Material Requirements Planning

Lead times

• Time required to acquire (purchase, produce, or assemble) an item.

• Manufactured part: lead time made of move, setup, and assembly or run times for each component.

• Purchased part: lead time made of difference between when part is ordered and when it is received.

Page 13: 4/4: Material Requirements Planning

A

2B 3C

2D 2E 2F 2E

G D

Lead timesA 1 wk.B 2C 1D 1E 2F 3G 2

Time-Phased Product Structure

• Rotate BOM below and reflect lead times with time as the X axis.

Page 14: 4/4: Material Requirements Planning

A

2B

3C

2D

2E

2F

2E

G

D

Lead timesA 1 wk.B 2C 1D 1E 2F 3G 2

8 7 6 5 4 3 2 1 0

Time-Phased Product Structure

• Rotate BOM and reflect lead times on X axis.

Page 15: 4/4: Material Requirements Planning

Gross Material Requirements

• Assume we need 50 “Blast ‘em, dude” speaker kits in eight weeks.

• We need to calculate when and how many of each component we need to start making.

Go to spreadsheet

Page 16: 4/4: Material Requirements Planning

Lot sizing

• lot-for-lot (L4L): order exactly the amount you want.

• Lot size required: order in certain amounts (ex. a dozen eggs).

Page 17: 4/4: Material Requirements Planning

Scheduled Receipts & On-Hand Inventory

• Scheduled Receipts:– Units (of any component) that you have

already scheduled to come in at a particular time.

• On-Hand Inventory– Units (of any component) that you already

have in stock (at the beginning).

Page 18: 4/4: Material Requirements Planning

Gross Req. vs. Net Req.

• Gross required is the total amount of a component you need.

• Net required is (Gross)

- (On-hand inventory)

- (Scheduled receipts)

Page 19: 4/4: Material Requirements Planning

Planned Order Receipts & Releases

• Planned Order Receipts:– When you PLAN to RECEIVE what you

ORDERED.

• Planned Order Releases:– When you PLAN to RELEASE what in

an ORDER.

Page 20: 4/4: Material Requirements Planning

MRP: What you need to know

• Master Schedule

• Bill of Materials

• Lead times

• Lot sizes

• Scheduled receipts & on-hand inventory

Page 21: 4/4: Material Requirements Planning

Group Exercise:Create an MRP• You make the PalmPointer, a handy PDA. You have received an

order for 200 units to be shipped in 12 hours. A PalmPointer is made of a LCD screen, 4 buttons, 1 toggle button, and a motherboard. The motherboard is made of 3 processors, 2 clock batteries, and a circuit board. Assembly time for the assemblies are as follows: All parts are L4L except the batteries, which must be ordered in packs of 40. You already have 50 motherboards and 100 processors.– PalmPointer 2 hours LCD screen 1– buttons 2 toggle button 3– motherboard 6 processors 2– batteries 1 circuit board 3

• Create an MRP schedule to determine when to begin assembling each component. Go back to spreadsheet

Page 22: 4/4: Material Requirements Planning

Homework due 4/11

• Download handout at http://adbook.net/teach022/305/hmwk4-4.xls

• There are two problems to be answered.

• Print out problems and turn in ON PAPER – no email submissions.