Master by Eno Aim

40
LAIN-LAIN KREI 25 CM m2 45,000.00 HOLLOW Sliding tebal 2mm, Sliding Pintu J3 btg 50,000.00 2.5 Sliding Pintu J4 btg 65,000.00 4.0 Sliding Pintu J5 btg 65,000.00 Naco per Daun bh 6,000.00 tebal 1,6 m Rolling door 2.5 Rolling Door Besi m2 130,000.00 4.0 Rolling Door Aluminium m2 175,000.00 Awning Aluminium m2 250,000.00 tebal 1,2 m Kusen alumunium 2.5 Kusen Aluminium 4" Putih m' 65,000.00 4.0 Kusen Aluminium 4" Coklat m' 60,000.00 Kusen Aluminium 3" Putih m' 55,000.00 HURUF galvanis 10-12 cm 15,000.00 15 cm 27,500.00 stainless 10-12 cm 25,000.00 H.BLOM 150x150x6,5x10x12 btg 715,000.00 PAGAR BRC * Pagar BRC 90 A2 /lb 205,000.00 * Pagar BRC 120 A2 /lb 240,000.00 * Pagar BRC 175 A3 /lb 445,000.00 * Pagar BRC 190 A3 /lb 450,000.00 * Tiang BRC Lengkap P.90-0 1 1/2' /bt 77,500.00 * Tiang BRC Lengkap P.120-0 1 1/2 /bt 97,500.00 * Tiang BRC Lengkap P.175-0 1 1/2 /bt 110,000.00 * Tiang BRC Lengkap P.190-0 1 1/2 /bt 145,000.00 * BRC Single Gate sg 90 T1 /Unit 245,000.00 * BRC Single Gate sg 120 T1 /Unit 280,000.00 * BRC Single Gate sg 175 T1 /Unit 300,000.00 * BRC Single Gate sg 190 T1 /Unit 345,000.00 * BRC Double Gate sg 90 T1 /Unit 385,000.00 * BRC Double Gate sg 120 T1 /Unit 400,000.00 * BRC Double Gate sg 175 T1 /Unit 410,000.00 * BRC Double Gate sg 190 T1 /Unit 420,000.00

Transcript of Master by Eno Aim

Page 1: Master by Eno Aim

LAIN-LAINKREI 25 CM m2 45,000.00 HOLLOWSliding tebal 2mm, panjang 6m

Sliding Pintu J3 btg 50,000.00 2.5Sliding Pintu J4 btg 65,000.00 4.0Sliding Pintu J5 btg 65,000.00

Naco per Daun bh 6,000.00 tebal 1,6 mm, panjang 6mRolling door 2.5

Rolling Door Besi m2 130,000.00 4.0Rolling Door Aluminium m2 175,000.00

Awning Aluminium m2 250,000.00 tebal 1,2 mm, panjang 6mKusen alumunium 2.5

Kusen Aluminium 4" Putih m' 65,000.00 4.0 Kusen Aluminium 4" Coklat m' 60,000.00 Kusen Aluminium 3" Putih m' 55,000.00

HURUFgalvanis 10-12 cm 15,000.00

15 cm 27,500.00 stainless 10-12 cm 25,000.00

H.BLOM

150x150x6,5x10x12 btg 715,000.00

PAGAR BRC

* Pagar BRC 90 A2 /lb 205,000.00

* Pagar BRC 120 A2 /lb 240,000.00

* Pagar BRC 175 A3 /lb 445,000.00

* Pagar BRC 190 A3 /lb 450,000.00

* Tiang BRC Lengkap P.90-0 1 1/2'' /bt 77,500.00

* Tiang BRC Lengkap P.120-0 1 1/2'' /bt 97,500.00

* Tiang BRC Lengkap P.175-0 1 1/2'' /bt 110,000.00

* Tiang BRC Lengkap P.190-0 1 1/2'' /bt 145,000.00

* BRC Single Gate sg 90 T1 /Unit 245,000.00

* BRC Single Gate sg 120 T1 /Unit 280,000.00

* BRC Single Gate sg 175 T1 /Unit 300,000.00

* BRC Single Gate sg 190 T1 /Unit 345,000.00

* BRC Double Gate sg 90 T1 /Unit 385,000.00

* BRC Double Gate sg 120 T1 /Unit 400,000.00

* BRC Double Gate sg 175 T1 /Unit 410,000.00

* BRC Double Gate sg 190 T1 /Unit 420,000.00

Page 2: Master by Eno Aim

tebal 2mm, panjang 6m55,000.0080,000.00

tebal 1,6 mm, panjang 6m45,000.0060,000.00

tebal 1,2 mm, panjang 6m27,500.0040,000.00

Page 3: Master by Eno Aim

ALAT-ALAT PENGUNCI DAN PENGGANTUNG ALAT - ALAT1. KUNCI TANAM

: Union 1 x slag Bh 35,000.00

: Union 2 x slag Bh 60,000.00

: Yale 1 x slag Bh 35,000.00

: Yale 2 x slag Bh 45,000.00

: Kuda 1 x slag Bh 35,000.00

: Kuda 2 x slag Bh 45,000.00

2. ENGSEL DAN GRENDEL

: Kupu-kupu biasa Bh 3,500.00 6,000.00

: Nylon kupu-kupu Bh 3,500.00

: Espagnoled-dalam negeri Bh 5,000.00

: Grendel tanam luar negeri Bh 40,000.00: Grendel biasa Bh 15,000.00

: pintu koboi bh 20,000.00

ALAT PENGIKAT MUR BAUT ( KUDA-KUDA KAYU ) Kg 15,000.00

PAKU - UKURAN 1' S/D 4' Kg 12,000.00

PAKU - PAYUNG Kg 15,000.00

PAKU - SEKRUP Gros 20,000.00

PAKU - BETON Bh 300.00

MUR BAUT BAJA kg 17,000.00

ANGKUR BAUT bh 10,000.00

LEM KAYU bh 15,000.00

LEM KUNING Kg 9,000.00

bh 64,000.00

PAKU RENG Kg 7,000.00

BENANG BH 2,000.00

PAKU SUMBAT 150.00

KAWAT rol 4,000.00

BENDRAT rol 175,000.00

SKRUP LACI PLUS BH 100.00

SKRUP LACI PLUS BH 125.00

SKRUP KAYU 300.00

Page 4: Master by Eno Aim

ALAT - ALATtang 7,500.00 15,000.00

kikir 7,500.00

meteran 5m 10,000.00

ember 17,500.00

pisau pasah TCT 65,000.00

selang waterpress 10,000.00

cangkul 20,000.00 27,500.00

skrup 20,000.00

sekop 17,500.00

gergaji 17,000.00

linggis 21,000.00

pensil tukang 1,000.00kuas 4' 7,500.00

DIAMOND BARUrel 50 cm huben 8,500.00

rel 40 cm ELCO 8,500.00

engsel sendok HUBEN HT 01 6,500.00

havana 07 (handle) 10,500.00

hava M2D 606 SN 14,000.00

hava 615 300 29,000.00

H 38-100 glos(kaki sofa) 29,000.00

ambalan 500.00

hva 503 400 68,000.00

hava 503 192 48,000.00

magnet lama putih 1,500.00

bracket almar SL 322 10,000.00

pipa wardrobe 50,000.00

kaki sofa YANE H 38 100 glos 29,000.00

magnet lama coklat 1,500.00

engsel sendok EL so 16 5,000.00

paku plastik 150.00

rel laci ELCO panjng 25 cm 6,500.00

Page 5: Master by Eno Aim

BAHAN INSTALASI LISTRIK1. KABEL LISTRIK jenis lampuNYA : NYA 1x1 1/2 mm M' 750.00 1

: NYA 121 1/2 mm M' 1,000.00 : NYA 1x4 mm M' 1,500.00 : NYA 1x6 mm M' 2,500.00

NYY : NYY 2x1 1/2 mm M' 2,500.00 : NYY 2x2 1/2 mm M' 3,500.00 : NYY 2x4 mm M' 4,500.00 : NYY 2x6 mm M' 5,500.00 : NYY 3x1 1/2 mm M' 3,000.00 : NYY x2 1/2 mm M' 4,000.00 2: NYY 3x4 mm M' 5,500.00 : NYY 3x6 mm M' 700.00

NYM : NYM 2x1 1/2 mm M' 1,750.00 : NYM 2x2 1/2 mm M' 2,500.00 : NYM 2x4 mm M' 3,500.00 : NYM 2x6 mm M' 4,500.00 : NYM 3x1 1/2 mm M' 2,500.00 : NYM x2 1/2 mm M' 300.00 : NYM 3x4 mm M' 4,500.00 : NYM 3x6 mm M' 6,000.00

2. SKAKELAR: Out Bauw seri ( broco) Bh 5,750.00 : Out Bauw Engkel (broco) Bh 4,250.00 : In Bauw Seri (broco) Bh 10,000.00 : In Bauw Engkel (broco) Bh 7,500.00

3. FUSE BOX ( SEKERING KASA): 1 Group Bh 18,000.00 : 2 Group Bh 27,500.00 : 3 Group Bh 50,000.00

4. STEKER: Biasa tunggal Bh 10,000.00 : Double Bh 15,000.00 : Kombinasi kecil Bh 20,000.00 : Kombinasi Besar Bh 25,000.00 : T Bh 10,000.00 : T Dengan arder Bh 30,000.00

5. STOP KONTAKArde Outbouw putih Bh 4,500.00 Arde Outbouw hitam Bh 3,500.00 Arde IB Bh 8,000.00 Arde Putar Bh 10,000.00

6. FITTINGFlaon Bh 2,000.00 Gantung Bh 3,500.00 Kap Bh 3,000.00 Kombinasi Bh 3,500.00

Page 6: Master by Eno Aim

jenis lamputradisional + jaringandinding 2 arah 40,000.00 125,000.00duduk 175,000.00 300,000.00gantung 40,000.00 125,000.00

fabrickanspot 125,000.00decostar 100,000.00gantung 250,000.00downlight 100,000.00dinding2 arah 300,000.00

Page 7: Master by Eno Aim

PAVING BLOCK BAHAN CETAK1. SQUARE 1. BUIS BETON

: Abu-abu bh 800.00

: Merah / Hitam bh 900.00

2. HOLLAND

: Abu-abu bh 600.00

: Merah / Hitam bh 700.00

3. UNIDECOR

: Abu-abu bh 750.00

: Merah / Hitam bh 850.00

4. UNI

: Abu-abu bh 700.00

: Merah / Hitam bh 800.00

5. TRIHEX 2. LUBANG ANGIN (ROSTER) PC + PASIR

: Abu-abu bh 600.00

: Merah / Hitam bh 700.00

6. OLYMPIA HEXA

: Abu-abu bh 1,100.00

: Merah / Hitam bh 1,300.00

7. HEXAGONAL

: Abu-abu bh 1,000.00

: Merah / Hitam bh 1,250.00 MARMER

8. CASTLE

: Abu-abu bh 2,100.00

: Merah / Hitam bh 2,600.00

9. TRAPEZ

: Abu-abu bh 1,700.00

: Merah / Hitam bh 2,000.00 GRANIT

10. TRAPEZ GRASS BLOCK

: Abu-abu bh 1,700.00

: Merah / Hitam bh 2,000.00

11. STANDARD GRASS BLOCK

: Abu-abu bh 6,000.00

12. BATACO

bh 1,500.00

Page 8: Master by Eno Aim

1. BUIS BETON

: o 10 cm - 100 cm Bh 10,000.00

: o 20 cm - 100 cm Bh 20,000.00

: o 30 cm - 100 cm Bh 30,000.00

: o 50 cm - 100 cm Bh 50,000.00

: o 60 cm - 100 cm Bh 60,000.00

: o 70 cm - 100 cm Bh 75,000.00

: U 10 cm - 100 cm Bh 10,000.00

: U 15 cm - 100 cm Bh 15,000.00

: U 20 cm - 100 cm Bh 20,000.00

: U 30 cm - 100 cm Bh 30,000.00

: U 50 cm - 100 cm Bh 55,000.00

2. LUBANG ANGIN (ROSTER) PC + PASIR

: 10 X 20 CM Bh 3,000.00

: 20 X 20 CM Bh 3,000.00

: 25 X 25 CM Bh 3,250.00

: 30 X 30 CM Bh 3,500.00

: 15 X 25 CM Bh 3,000.00

: 15 X 30 CM Bh 3,500.00

star white

carara italy 420000

impala black m1 390000

Page 9: Master by Eno Aim

BAHAN PIPA BAHAN SANITAIR1. PIPA PVC 1. KLOSET DUDUK

: Diameter 1/2' Batang 12,000.00

: Diameter 3/4' Batang 13,000.00

: Diameter 1' Batang 14,000.00

: Diameter 2' Batang 20,000.00

: Diameter 2 1/2' Batang 37,000.00

: Diameter 3' Batang 50,000.00 2. KLOSET JONGKOK

: Diameter 4' Batang 75,000.00

: Diameter 6' Batang 80,000.00

: Diameter 8' Batang 90,000.00

: Diameter 10' Batang 125,000.00 3. WASTAFEL PEDESTAL 7,5 LITER

: Diameter 12' Batang 150,000.00

: Diameter 14' Batang 200,000.00

: Diameter 16' Batang 250,000.00 4. WASTAFEL MEJA OVAL

2. KNEE PVC

: Diameter 1/2' Batang 1,500.00

: Diameter 3/4' Batang 2,000.00

: Diameter 1' Batang 3,000.00 5. WASTAFEL GANTUNG BULAT

: Diameter 2 1/2' Batang 3,000.00

: Diameter 3' Batang 3,500.00

: Diameter 4' Batang 4,500.00 6. WASTAFEL GANTUNG SUDUT

3. PIPA GALVANIZED

: Diameter 1/2' - 6 m Batang 30,000.00 7. WASTAFEL GANTUNG SUDUT KECIL

: Diameter 3/4' - 6 m Batang 35,000.00

: Diameter 1' - 6 m Batang 50,000.00 8. WASTAFEL BAK CUCI

: Diameter 1 1/2' - 6 m Batang 65,000.00

: Diameter 2' - 6 m Batang 75,000.00 9. TEMPAT SABUN GANTUNG

: Diameter 2 1/2' - 6 m Batang 85,000.00

: Diameter 3' - 6 m Batang 150,000.00

: Diameter 4' - 6 m Batang 200,000.00 10. TEMPAT SABUN TANAM

4. PIPA MEDIUM

: Diameter 3' - 6 m Batang 40,000.00

: Diameter 4' - 6 m Batang 60,000.00 11. SEPTICTANK ( ETERNIT GRESIK)

Page 10: Master by Eno Aim

BAHAN SANITAIR1. KLOSET DUDUK

: Type C - 4 Bh 175,000.00

: Type C - 5 Bh 540,000.00

: Type C - 13T Bh 105,000.00

: Type C - 14 T Bh 105,000.00

: Type C - 27 Bh 1,200,000.00

2. KLOSET JONGKOK

: Type C Bh 55,000.00

; Type C - 2 Bh 47,500.00

: Type C - 3 Bh 42,500.00

3. WASTAFEL PEDESTAL 7,5 LITER

: Type L - 266 Wdk - 23p Bh 160,000.00

: Type L - 266G - Wsk - 1p Bh 480,000.00

4. WASTAFEL MEJA OVAL

: Type L - 2594 WMK - 38M Bh 780,000.00

: Type L - 2394 WMK - 38 M Bh 630,000.00

: Type L - 2296 WMK - 38M Bh 700,000.00

5. WASTAFEL GANTUNG BULAT

: Type L - 286 WMK - 38M Bh 600,000.00

: Type L - 284 WMK - 38M Bh 600,000.00

6. WASTAFEL GANTUNG SUDUT

: Type L 143 Bh 70,000.00

7. WASTAFEL GANTUNG SUDUT KECIL

: Type L - 80 Bh 70,000.00

8. WASTAFEL BAK CUCI

: 640x130x65 mm Type H-401 Bh 60,000.00

9. TEMPAT SABUN GANTUNG

: 210X110X45 MM/Type H-411 Bh 33,000.00

: 110x109x90 mm/Type H-412 Bh 20,000.00

10. TEMPAT SABUN TANAM

: 109x109x95 mm/Type H-25 Bh 20,000.00

: 220x109x90 mm/Type H-27 Bh 30,000.00

11. SEPTICTANK ( ETERNIT GRESIK)

: 5 Pemakai 500 Liter Unit 161,000.00

: 10 Pemakai 1.000 Liter Unit 205,000.00

Page 11: Master by Eno Aim

BAHAN KACA KAIN,BUSA,KULIT1. POLOS BUSA

: Tebal 2 mm M2 30,000.00 12: Tebal 3 mm M2 40,000.00 6 SM: Tebal 5 mm M2 50,000.00 6 KUNING: Tebal 6 mm M2 75,000.00 4 SM: Tebal 8 mm M2 110,000.00 2 WS: Tebal 10 mm M2 125,000.00

2. ES KABUR: Tebal 2 mm M2 20,000.00: Tebal 3 mm M2 35,000.00: Tebal 5 mm M2 45,000.00

3. RAY BAND: Tebal 3 mm M2 57,000.00: Tebal 5 mm M2 60,000.00: Tebal 8 mm M2 100,000.00: Tebal 10 mm M2 175,000.00

STAINLESS ALUMUNIUMkaki kaki

dim 5 cm bh 25,000.00 dim 5 cm bh

Page 12: Master by Eno Aim

KAIN,BUSA,KULIT KAINblacu m 2,250.00kanvas m 10,000.00

156,000.00 batik m 5,000.0064,000.00 10,000.00

104,000.00 kulit m 45,000.0017,000.00 kain sofa m 36,000.00

40,000.00puring m 1,500.00korea 22,000.00batik m

kw 1kw 2 15,000.00kw 3 9,000.00kw 4 5,000.00

KARETkaret pak 11,750.00

29,000.00 ritsleting bh 1,000.00

Page 13: Master by Eno Aim

BAHAN FINISHING FINISHING LANTAI1. KAYU karpet VOLGUO

: Menie Kg 11,000.00 PARKEET

: Dempul Plamir Kg 11,000.00 kw I

: Amplas/Ambril Lembar 2,500.00 kw II

: Batu apung Bh 6,000.00 vinil jati 0,6 cm

: Cat Dasar Kg 11,000.00

: Cat Emco Kg 21,000.00 karpet BUANA

: Cat Yunior 66 Kg 27,500.00

: Cat Primalin Liter 15,000.00

: Cat deculux Kg 21,000.00

: Cat Siralax Ons 5,500.00

: Spiritus Liter 5,500.00

: Plitur jadi Liter 23,000.00

: Herotex Liter 7,500.00

: aqua politur 35,000.00

: wood filler 10,000.00

: sanding sealer 17,500.00

2. TEMBOK

: Kalkarim Kg 2,500.00

: Kapur Sirih Kg 2,000.00

: Plamir Toto Kg 30,000.00

: Decolith 5 Kg 12,000.00

: Sintex 5 Kg 36,000.00

: Danabrite 5 Kg 47,500.00

: Toto 5 Kg 42,500.00

: Catylac 5 Kg 50,000.00

: Mowilex 5 KG 131,000.00

1 lt 52,400.00

envitex gln 47,000.00 49,000.00

maxilite pail 145,000.00

160,000.00

king kong 110,000.00

gln 20,000.00

3. BESI

: Menie Patana Kg 11,000.00

: Cat Beebrand 1000 Kg 27,500.00

: Cat Toyo Paint Kg 17,500.00

: Thinner A Liter 10,000.00

: Minyak Cat Liter 10,000.00

: Thinner Super Liter 17,000.00

4. LAIN-LAIN

Residu Drum 650,000.00

Fibre Glass (tangki air) 550 L Bh 500,000.00

Fibre Glass (tangki air) 1100 L Bh 750,000.00

Compound 10,000.00

Alkasid 6,000.00

Strimin 6,500.00

alkali primer 16,000.00

Page 14: Master by Eno Aim

FINISHING LANTAIM2 10,000.00

M2 145,000.00

m2 40,000.00rol 35,000.00

m 18,500.00M2 10,000.00

Page 15: Master by Eno Aim

BAHAN PENUTUP ATAP BAHAN LANGIT-LANGIT1. SIRAP

: 100 LEMBAR Pak 110,000.00 1,100.00

2. GENTENG BETON

: GB Warna standart Bh 3,500.00

: GB Warna Special Bh 4,500.00

: GB Warna khusus Bh 5,000.00

: Kerpus Warna standart Bh 5,000.00

: Kerpus Warna special Bh 6,000.00

: Kerpus Warna khusus Bh 7,000.00

3. GENTENG TANAH LIAT

: Vlaam Bh 1,100.00

: Kodok Bh 800.00

: Nok Kerpus Bh 3,000.00

4. GENTENG KACA

: Vlaam 2 mm Bh 2,500.00

: Vlaam 3 mm Bh 4,500.00

: Kodok 2 mm Bh 4,000.00

: Kodok 3 mm Bh 5,000.00

5. ASBES GELOMBANG

ASBES GELOMBANG BESAR DIABES 6 1/2

: 200 x 102 x 5 mm Bh 45,000.00

: 250 x 102 x 5 mm Bh 55,000.00

: 225 x 102 x 5 mm Bh 47,500.00

: 200 x 102 x 6 mm Bh 50,000.00

: 225 x 102 x 6 mm Bh 55,000.00

: 250 x 102 x 6 mm Bh 60,000.00

ASBES GELOMBANG KECIL DIABES 14

: 150 X 105 X 4 mm Bh 28,000.00

: 180 X 105 X 4 mm Bh 30,000.00

: 210 X 105 X 4 mm Bh 34,000.00

: 240 X 105 X 4 mm Bh 38,000.00

: 270 X 105 X 4 mm Bh 40,000.00

: 300 X 105 X 4 mm Bh 45,000.00

6. ASBES PLAT

Djabes Plast

: 100 x 100 x 3 mm Lembar 8,500.00

: 50 X 200 X 3 mm Lembar 10,000.00

: 40 X 200 X 3 mm Lembar 9,000.00

: 60 X 200 X 3 mm Lembar 11,000.00

DJabes Nok

: Kerpus Genteng Pcs 19,000.00

: Stel Genteng Pcs 33,000.00

: Paten Besar Pcs 33,000.00

Nokstei gelombang harflex

: Stel Besar 110 cm Pcs 25,000.00

: Patent Besar 110 cm Pcs 25,000.00

: Plat Besar 110 cm Pcs 25,000.00

7. FIBRE GLASS ( JABES )

: 180 X 92 cm Lembar 25,000.00 ukuran lebar 1 m 25000

: 200 X 92 cm Lembar 27,500.00

: 250 X 92 cm Lembar 30,000.00

: 180 X 105 cm Lembar 32,500.00

: 210 X 105 cm Lembar 36,000.00

: 250 X 105 cm Lembar 50,000.00

8. SENG PLAT

Page 16: Master by Eno Aim

: BJLS 0,18 Lembar 25,000.00

: BJLS 0,20 Lembar 30,000.00

: BJLS 0,28 Lembar 35,000.00

: BJLS 0,30 Lembar 40,000.00

9. SENG GELOMBANG

: BJLS 0,18 panjang 180 cm Lembar 38,000.00

: BJLS 0,20 panjang 180 cm Lembar 30,000.00

: BJLS 0,28 panjang 180 cm Lembar 32,500.00

: BJLS 0,30 panjang 180 cm Lembar 35,000.00

10. METAL ROOF

Metal Roof Colour m2 75,000.00

Nok atas Metal Roof bh 25,000.00

Nok Samping Metal Roof bh 26,000.00

Wall Flashing Metal Roof bh 26,000.00

11. GENTENG LEMBARAN BAHAN SENG

ukuran 180 * 80 cm lbr 42500

Page 17: Master by Eno Aim

BAHAN LANGIT-LANGIT H.BLOM

1. AKUSTIK 150x150x6,5x10x12

: Ukuran 30 x 30 Lembar 25,000.00 8

: Ukuran 30 x 60 Lembar 60,000.00 9

: Ukuran 40 x 40 Lembar 75,000.00 10

2. SOFT BOARD 11

: Ukuran 244x122 Lembar 80,000.00 12

3. HARD BOARD

: Ukuran 4' X 8' Lembar 75,000.00

4. TEAK WOOD

: UKuran 90x210 x 3 mm Lembar 41,000.00

: Ukuran 120x240 x 3 mm Lembar 61,000.00

: Ukuran 90x210 x 4 mm Lembar 72,000.00

: Ukuran 90x 210 x 9 mm Lembar 60,000.00

: Ukuran 90x210 x 12 mm Lembar 75,000.00

: Ukuran 90X210 x 15 mm Lembar 96,000.00

: Ukuran 90x210 x 18 mm Lembar 105,000.00

5. TRIPLEKS

: Ukuran 120x240 x 3 mm Lembar 35,000.00

: Ukuran 120x240 x 4 mm Lembar 42,000.00

: Ukuran 120x240 x 6 mm Lembar 58,000.00

6. MULTIPLEKS

: Ukuran 120 x 240 x 9 mm Lembar 96,000.00

: Ukuran 120 x 240 x 12 mm Lembar 121,000.00

: Ukuran 120 x 240 x 15 mm Lembar 150,000.00

: Ukuran 120 x 240 x 18 mm Lembar 180,000.00

7. ASBES PLAT

: 100 x 100 x 3 mm Lembar 8,500.00

8. GYPSUM

: 100 X200 X 3MM Lembar 60,000.00

9. TRIPLEK SUNGKAI

: 122 144 X 3MM Lembar

jelek - 70,000.00

standar - AA 73,000.00

bagus - FC RED AA 87,500.00

super - FC AA 92,500.00

Page 18: Master by Eno Aim

150x150x6,5x10x12 btg 715,000.00

Genteng Metal Roof m2 75,000.00

Nok Atas Metal Colour bh 25,000.00

Nok Samping Metal Colour bh 26,000.00

wall Flashing bh 26,000.00

PAGAR BRC

* Pagar BRC 90 A2 /lb 205,000.00

* Pagar BRC 120 A2 /lb 240,000.00

* Pagar BRC 175 A3 /lb 445,000.00

* Pagar BRC 190 A3 /lb 450,000.00

* Tiang BRC Lengkap P.90-0 1 1/2'' /bt 77,500.00

* Tiang BRC Lengkap P.120-0 1 1/2'' /bt 97,500.00

* Tiang BRC Lengkap P.175-0 1 1/2'' /bt 110,000.00

* Tiang BRC Lengkap P.190-0 1 1/2'' /bt 145,000.00

* BRC Single Gate sg 90 T1 /Unit 245,000.00

* BRC Single Gate sg 120 T1 /Unit 280,000.00

* BRC Single Gate sg 175 T1 /Unit 300,000.00

* BRC Single Gate sg 190 T1 /Unit 345,000.00

* BRC Double Gate sg 90 T1 /Unit 385,000.00

* BRC Double Gate sg 120 T1 /Unit 400,000.00

* BRC Double Gate sg 175 T1 /Unit 410,000.00

* BRC Double Gate sg 190 T1 /Unit 420,000.00

grc board 9mm lbr 198,000.00

Page 19: Master by Eno Aim

tambahan bahan2 baru

1. glugu cahaya mulia ud.nanang4/6 2 m 7,000.004/6 3 m 11,000.005/7 2 m 8,000.005/7 3 m 12,000.006/12 3 m 27,000.006/12 4 m 36,000.002/3 2 m 3,500.00 1 750.003/10

2. BENGKIRAI5/7 4 m 20,000.006/12 3 m 42,000.00papan bh 4,500.005/7 1 m 4,000.00

3. SENGON4/6 3 m 9,000.00

4. PLYWOOD ARUMBAIwhite ice tree lbr 69,000.00black chesnut lbr 77,500.00red chesnut lbr 90,000.00super sungkai kembang lbr 65,000.00super sungkai lbr 66,000.00megateak lbr 67,500.00eboni lbrsonokeling lbrmega nyatoh lbrcherry lbrwhite oak lbrred oak lbrcolour board lbrgrey lbrleaf lbrbeech lbrjati lbrcombo lbrsungkai lbr

Page 20: Master by Eno Aim

HARGA KUSEN JATIKUSEN JADI 7,000,000.00 M3 50,000.00 M1

ONGKOS PASANG KUSEN 250,000.00 M3

ONGKOS PASANG PINTU 30,000.00 BH

ONGKOS PASANG JENDELA 15,000.00 M3

HARGA DAUN PINTU 320,000.00 M2

HARGA DAUN JENDELA 160,000.00 M2

Page 21: Master by Eno Aim

bahan Page 21

DAFTAR HARGA BAHAN

BAHAN DASAR1. BATU KALI

: Bulat utuh M3 50,000.00

: Bulat belah M3 90,000.00

: Pecah 10/15 M3 95,000.00

: Pecah 5/7 M3 105,000.00

: Pecah 3/5 M3 110,000.00

: Pecah 2/3 M3 120,000.00

2. KERIKIL

: Timbun M3 50,000.00

: Sawur/Koral M3 50,000.00

: Beton 0.5x1 M3 100,000.00

: Beton 1x2 M4 100,000.00

: Beton 2x3 M5 100,000.00

: Biasa M3 75,000.00

: Trasc Giling M3 135,000.00

3. BATU MERAH/BATA

: KW I Bh 190.00

: KW II Bh 170.00

4. PASIR

: Urug M3 30,000.00

: Pasang M3 45,000.00

: Beton (Muntilan) M3 50,000.00

: Tanah Padas M3 25,000.00

5. KAPUR

: Pasang M3 120,000.00

: Sirih M3 2,500.00

6. PORTLAND CEMENT

: Nusantara Zak 32,000.00

: Cibinong Zak 28,000.00

: tiga Roda Zak 28,000.00

: Gresik Zak 28,000.00

: White Cement Zak 65,000.00

BAHAN KAYU1. JATI

: Balok M3 6,500,000.00

: Papan M3

2. KAMPER

: Papan M3 3,700,000.00

: Balok M3 3,300,000.00

3. KRUING

: Papan M3 2,600,000.00

: Balok M3 2,300,000.00

4. MERANTI

: Papan M3 1,750,000.00

: Balok M3 1,300,000.00

5. LANAN

: Papan M3 1,500,000.00

: Balok M3 1,100,000.00

6. DOLKEN

: Sedang 8x10x400 cm Batang 35,000.00

: Kecil 6x7x400 cm Batang 25,000.00

: Besar 10x12x400 cm Batang 40,000.00

: Kayu Cetakan M3 500,000.00

: Kayu bakar M3 125,000.00

7. BENGKIRAI

: Papan M3 3,250,000.00

: Balok M3

8. GLUGU(KAYU KELAPA)

: 5x7x300 Batang 13,000.00

: Balok M3 1,250,000.00

BAHAN PENUTUP DINDING / LANTAI1. UBIN/TEGEL BIASA

: PC polos 30x30 cm M2 18,000.00

: PC polos 20x20 cm M2 15,000.00

: PC warna 30x30 cm M2 23,000.00

: PC warna 20x20 cm M2 20,000.00

: PC Teraso 30x30 cm M2 37,500.00

: PC Teraso 20x20 cm M2 35,000.00

2. TEGEL PLINT

Page 22: Master by Eno Aim

bahan Page 22

: PC warna 10x20 cm Bh 750.00

: Teraso 20x20 cm Bh 1,500.00

3. POLIS UBIN

: Lantai / Badan M2 7,500.00

: Plint M' 6,000.00

: Trap M' 5,000.00

4. ALDAS DECORATIF STONE

: Aldas Decoratif Stone M2 15,000.00

5. UBIN PORSELIN

: Putih 11 x 11 cm Dos 35,000.00

: Warna 11 x 11 cm Dos 45,000.00

: Putih 15 x 15 cm Dos 45,000.00

: Warna 15 x 15 cm Dos 60,000.00

6. MOZAIK PORSELIN

: Diamond 10x20 cm Dos 25,000.00

: Diamond 15x15 cm Dos 27,500.00

: Diamond 20x20 cm Dos 30,000.00

: Diamond 20x25 cm Dos 32,500.00

7. KERAMIK

: Keramik 30 X 30 cm M2 35,000.00

: Keramik 40x40 cm M2 40,000.00

8. VINYL

: rol-rolan 1x2 m M' 37,500.00

9. KARPET 4 meteran

: Classic Bali M2 165,000.00

: Nobel Long Life M2 130,000.00

: Classic Hercules M2 150,000.00

BAHAN BESI1. BESI BETON

: o 4 mm - 12 m Btg 8,000.00

: o 6 mm - 12 m Btg 10,000.00

: o 8 mm - 12 m Btg 25,000.00

: o 10 mm - 12 m Btg 35,000.00

: o 12 mm - 12 m Btg 50,000.00

: o 16 mm - 12 m Btg 76,000.00

: o 19 mm - 12 m Btg 115,000.00

: o 25 mm - 12 m Btg 175,000.00

Besi Kg 6,500.00

2. BESI PLAT

: 3'x6' tebal 0,6 mm Lembar 40,000.00

: 4'x6' tebal 0,8 mm Lembar 80,000.00

: 4'x8' tebal 1,4 mm Lembar 125,000.00

3. BESI PROFIL

: Kanal UNP - 10 cm Batang 125,000.00

: Kanal UNP - 12 cm Batang 180,000.00

: Kanal UNP - 15 cm Batang 330,000.00

: Kanal UNP - 20 cm Batang 525,000.00

: Kanal IWF - 15 cm Batang 625,000.00

: Kanal IWF - 20 cm Batang 930,000.00

4. JARING-JARING BAJA

: Diameter 4 - 15 Kg 8,000.00

: Diameter 6 - 15 Kg 10,000.00

5. BESI SIKU

: L. 40X40X4 Batang 35,000.00

: L. 50X50X5 Batang 56,000.00

: L. 60X60X6 Batang 80,000.00

6. KAWAT

: Harmonika 12x45 mm M2 15,000.00

: Harmonika 12x24 mm M2 14,000.00

: Harmonika 14x30 mm M2 22,500.00

: Harmonika 14x35 mm M2 32,000.00

: Saringan pasir M2 17,500.00

: Kawat Loket M2 22,500.00

: Kawat Duri Rol 55,000.00

: Kawat Ikat Beton/Bendrat Kg 8,000.00

: Kawat Bronjong Kg 10,000.00

7. BESI STRIP

Kg 10,000.00

8. begel 8*8

bh 7,500.00

kg 7,500.00

Page 23: Master by Eno Aim

bahan Page 23

MAHONI

4,500,000.00

btg lbr

20000 17000

5/7 2m

Page 24: Master by Eno Aim

bahan Page 24

dinding

20*30 35,000.00

Page 25: Master by Eno Aim

1 Ukur 1,000.00

2 Uitzet / bouwplank 1,500.00

3 Pembongkaran lantai 18,000.00

4 Pembongkaran dinding 18,000.00

5 Galian tanah pondasi 10,000.00

6 Urugan Kembali 2,500.00

7 Urugan pasir/sirtu bawah pondasi/lantai 7,500.00

8 Pasang batu belah 30,000.00

9 Pas rollag 8,000.00

10 Lantai Kerja 50,000.00

11 pek bata trasram 8,000.00

12 Pas. batu bata 1PC:4Ps 8,000.00

13 Pek.Beton Bertulang 1:2:3 Sloof Struktur 300,000.00

14 Pek.Beton Bertulang 1:2:3 Kolom Struktur 300,000.00

15 Pek beton canopy 300,000.00

16 Plesteran 1Pc:3Ps 4,000.00

17 Plesteran 1Pc:6Ps 4,000.00

18 acian 4,000.00

19 lantai keramik30x30 cm 9,000.00

20 lantai keramik20x20 cm 9,000.00

21 pek rangka atap 6,000.00

22 kusen pintu jendela 250,000.00

23 panil pintu 30,000.00

24 daun jendela 15,000.00

25 Pas genteng 6,640.00

26 kaca 6,000.00

27 cat dinding 7,500.00

28 cat melamin 10,000.00

29 plafon untuk penambahan ruang tidur 6,000.00

30 upah melamin 10,000.00

31

32

Page 26: Master by Eno Aim

A N A L I S A P E K E R J A A N

PEKERJAAN TANAH Membersihkan lahan per 1 M2

0.0050 Mandor Rp 40,000.00 Rp 200.00 0.0500 Tukang kayu Rp 35,000.00 Rp 1,750.00 0.0500 Kep. Tukang kayu Rp 40,000.00 Rp 2,000.00 0.0500 Pekerja Rp 25,000.00 Rp 1,250.00

Rp. 5,200.00 Pemasangan bouwplank per 1 m'

0.0040 kayu (m3) Rp 1,300,000.00 Rp 5,200.00 0.0200 paku (kg) Rp 12,000.00 Rp 240.0000 5,440.00 0.0500 tukang kayu Rp 35,000.00 Rp 1,750.00 0.0500 kep. tukang kayu Rp 40,000.00 Rp 2,000.00 0.0050 mandor Rp 40,000.00 Rp 200.00 0.0500 pekerja Rp 25,000.00 Rp 1,250.00 5,200.00

10,640.00

1 M3 Mengali tanah, dalamnya kurang dari 1 m, tanahnya disebar disekitarnya.

0.4000 Pekerja Rp. 25,000.00 Rp. 10,000.00

0.0400 Mandor Rp. 40,000.00 Rp. 1,600.00

Rp. 11,600.00

1 M3 urugan tanah kembali 0.25 X 5.037,50 2,900.00

1 M3 Mengali tanah untuk tanah keras

0.6250 Pekerja Rp. 25,000.00 Rp. 15,625.00

0.0620 Mandor Rp. 40,000.00 Rp. 2,480.00

Rp. 18,105.00

1 M3 Mengali lumpur

0.8330 Pekerja Rp. 25,000.00 Rp. 20,825.00

0.0830 Mandor Rp. 40,000.00 Rp. 3,320.00

Rp. 24,145.00

1 M3 Mengangkut tanah sejauh 150 M'

0.5160 Pekerja Rp. 25,000.00 Rp. 12,900.00

0.0500 Mandor Rp. 40,000.00 Rp. 2,000.00

Rp. 14,900.00

1 M3 Urugan pasir, termasuk pemadatan dengan menyiram air

1.3000 Pasir Urug (m3) Rp. 30,000.00 Rp. 39,000.00 39,000.00

0.6000 Pekerja Rp. 25,000.00 Rp. 15,000.00

0.3000 tukang batu Rp. 30,000.00 Rp. 9,000.00

0.3000 kep.tukang batu Rp. 40,000.00 Rp. 12,000.00

0.0600 Mandor Rp. 40,000.00 Rp. 2,400.00 38,400.00

Rp. 77,400.00

1 M3 Urugan tanah padas, termasuk pemadatan dengan menyiram air

1.2000 Tanah Padas Rp. 25,000.00 Rp. 30,000.00 30,000.00

0.0300 Pekerja Rp. 25,000.00 Rp. 750.00

0.0100 Mandor Rp. 40,000.00 Rp. 400.00 1,150.00

Rp. 31,150.00

PEKERJAAN PASANGAN 1 M3 pekerjaan lantai kerja

0.8590 koral Rp. 50,000.00 Rp. 42,950.00

5.3685 pc Rp. 32,000.00 Rp. 171,792.00

0.5154 pasir beton Rp. 50,000.00 Rp. 25,770.00 240,512.00

0.6000 Tukang batu Rp. 30,000.00 Rp. 18,000.00

0.0600 Kep. tukang batu Rp. 40,000.00 Rp. 2,400.00

1.5000 Pekerja Rp. 25,000.00 Rp. 37,500.00

0.1500 Mandor Rp. 40,000.00 Rp. 6,000.00 63,900.00

304,412.00

1 M2 Pasangan rollag 1:3

14.000 Batu bata Rp. 190.00 Rp. 2,660.00 0.1120 Pc 40kg Rp. 32,000.00 Rp. 3,584.00 0.0108 pasir pasang Rp. 45,000.00 Rp. 486.00 6,730.00

0.1600 Tukang batu Rp. 30,000.00 Rp. 4,800.00

0.0160 Kep. tukang batu Rp. 40,000.00 Rp. 640.00

0.4800 Pekerja Rp. 25,000.00 Rp. 12,000.00

0.0480 Mandor Rp. 40,000.00 Rp. 1,920.00 19,360.00

26,090.00

1 M3 Pasang Aanstamping (20 cm) - SK SNI T - 02-1991-03

1.2000 Batu belah (m3) Rp. 90,000.00 Rp. 108,000.00 108,000.00

0.7810 Pekerja Rp. 25,000.00 Rp. 19,525.00

0.0780 Mandor Rp. 40,000.00 Rp. 3,120.00

0.3900 tukang batu Rp. 30,000.00 Rp. 11,700.00

0.0390 kep. Tukang batu Rp. 40,000.00 Rp. 1,560.00 35,905.00

Rp. 143,905.00

1 M3 Pasangan batu belah dengan 1 PC : 3 Kp : 10 Ps. SK SNI T-02-1991-03

1.2000 Batu Belah (m3) Rp. 90,000.00 Rp. 108,000.00

1.2300 PC (zak) Rp. 32,000.00 Rp. 39,360.00

0.1200 Kapur (m3) Rp. 120,000.00 Rp. 14,400.00

0.4100 Pasir Pasang (m3) Rp. 45,000.00 Rp. 18,450.00 180,210.00

0.6000 Tukang Batu Rp. 30,000.00 Rp. 18,000.00

0.0600 Kep. Tukang batu Rp. 40,000.00 Rp. 2,400.00

1.5000 Pekerja Rp. 25,000.00 Rp. 37,500.00

Page 27: Master by Eno Aim

0.1500 Mandor Rp. 40,000.00 Rp. 6,000.00 63,900.00

Rp. 244,110.00

1 M3 Pasangan Batu Belah dengan 1 PC : 5 Ps -SK SNI T-02-1991-03

1.2000 Batu belah (m3) Rp. 90,000.00 Rp. 108,000.00

2.3500 PC (zak) Rp. 32,000.00 Rp. 75,200.00

0.4500 Pasir Pasang (m3) Rp. 45,000.00 Rp. 20,250.00 203,450.00

0.6000 Tukang batu Rp. 30,000.00 Rp. 18,000.00

0.0600 Kep. tukang batu Rp. 40,000.00 Rp. 2,400.00

1.5000 Pekerja Rp. 25,000.00 Rp. 37,500.00

0.1500 Mandor Rp. 40,000.00 Rp. 6,000.00 63,900.00

Rp. 267,350.00

1 M3 Pasang Batu Belah dengan 1 PC : 3 Ps SK SNI T-02-1991-03

1.2000 Batu belah (m3) Rp. 90,000.00 Rp. 108,000.00

4.0500 PC (zak) Rp. 32,000.00 Rp. 129,600.00

0.4300 Pasir Pasang (m3) Rp. 45,000.00 Rp. 19,350.00 256,950.00

0.6000 Tukang batu Rp. 30,000.00 Rp. 18,000.00

0.0600 Kep. tukang batu Rp. 40,000.00 Rp. 2,400.00

1.5000 Pekerja Rp. 25,000.00 Rp. 37,500.00

0.1500 Mandor Rp. 40,000.00 Rp. 6,000.00 63,900.00

Rp. 320,850.00

1 M3 Pasang Batu Belah dengan 1 PC : 2 Ps SK SNI T -02-1991-03

1.2000 Batu belah (m3) Rp. 90,000.00 Rp. 108,000.00

5.3250 PC (zak) Rp. 32,000.00 Rp. 170,400.00

0.3400 Pasir Pasang (m3) Rp. 45,000.00 Rp. 15,300.00 293,700.00

0.6000 Tukang batu Rp. 30,000.00 Rp. 18,000.00

0.0600 Kep. tukang batu Rp. 40,000.00 Rp. 2,400.00

1.5000 Pekerja Rp. 25,000.00 Rp. 37,500.00

0.1500 Mandor Rp. 40,000.00 Rp. 6,000.00 63,900.00

Rp. 357,600.00

1 M2 Pasangan Batu bata dengan 1 PC : 3 Kp : 10 Ps tebal 1/2 bata-SK SNI T-031991-03

80.0000 Batu bata (bh) Rp. 190.00 Rp. 15,200.00

0.1450 PC (zak) Rp. 32,000.00 Rp. 4,640.00

0.0046 Kapur (m3) Rp. 120,000.00 Rp. 552.00

0.0140 Pasir pasang (m3) Rp. 45,000.00 Rp. 630.00 21,022.00

0.1600 Tukang batu Rp. 30,000.00 Rp. 4,800.00

0.0160 Kep. tukang batu Rp. 40,000.00 Rp. 640.00

0.4800 Pekerja Rp. 25,000.00 Rp. 12,000.00

0.0480 Mandor Rp. 40,000.00 Rp. 1,920.00 19,360.00

Rp. 40,382.00

1 M2 Pasangan Batu bata dengan 1 PC : 4 Ps tebal 1/2 bata SK SNI T-03-1991-03

80.0000 Batu bata (bh) Rp. 190.00 Rp. 15,200.00

0.4000 PC (zak) Rp. 32,000.00 Rp. 12,800.00

0.0510 Pasir pasang (m3) Rp. 45,000.00 Rp. 2,295.00 30,295.00

0.1600 Tukang batu Rp. 30,000.00 Rp. 4,800.00

0.0160 Kep. tukang batu Rp. 40,000.00 Rp. 640.00

0.4800 Pekerja Rp. 25,000.00 Rp. 12,000.00

0.0480 Mandor Rp. 40,000.00 Rp. 1,920.00 19,360.00

Rp. 49,655.00

1 M2 Pasangan Batu bata dengan 1 PC : 2 Ps tebal 1/2 bata SK SNI T-03-1991-03

80.0000 Batu bata (bh) Rp. 190.00 Rp. 15,200.00

0.6500 PC (zak) Rp. 32,000.00 Rp. 20,800.00

0.0420 Pasir pasang (m3) Rp. 45,000.00 Rp. 1,890.00 37,890.00

0.1600 Tukang batu Rp. 30,000.00 Rp. 4,800.00

0.0160 Kep. tukang batu Rp. 40,000.00 Rp. 640.00

0.4800 Pekerja Rp. 25,000.00 Rp. 12,000.00

0.0480 Mandor Rp. 40,000.00 Rp. 1,920.00 19,360.00

Rp. 57,250.00

1 M' Pek siar 10 mm / sponengan / tali air

0.0970 PC Rp. 32,000.00 Rp. 3,104.00

0.0110 Pasir pasang Rp. 45,000.00 Rp. 495.00 3,599.00

0.1200 Tukang batu Rp. 30,000.00 Rp. 3,600.00

0.0120 Kep. tukang batu Rp. 40,000.00 Rp. 480.00

0.3600 Pekerja Rp. 25,000.00 Rp. 9,000.00

0.0360 Mandor Rp. 40,000.00 Rp. 1,440.00 14,520.00

Rp. 18,119.00

PEKERJAAN PENUTUP LANTAI 1 M2 Lantai keramik 30 x 30 dengan 1 PC : 1/2 Kp : 5 Ps.

1.0000 Keramik Rp. 35,000.00 Rp. 35,000.00

0.4080 PC Rp. 32,000.00 Rp. 13,056.00

0.0030 Kapur Rp. 120,000.00 Rp. 360.00

0.0380 Pasir pasang Rp. 45,000.00 Rp. 1,710.00 50,126.00

0.0800 Tukang batu Rp. 30,000.00 Rp. 2,400.00

0.0080 Kep. tukang batu Rp. 40,000.00 Rp. 320.00

0.2400 Pekerja Rp. 25,000.00 Rp. 6,000.00

0.0120 Mandor Rp. 40,000.00 Rp. 480.00 9,200.00

Rp. 59,326.00

1 M2 Lantai tegel keramik 20 x 20 dengan 1 PC : 2 Kp : 5 Ps BOW-G.69.A

1.0000 Tegel (M2) Rp. 15,000.00 Rp. 15,000.00

0.2000 PC (zak) Rp. 32,000.00 Rp. 6,400.00

0.0160 Kapur Rp. 120,000.00 Rp. 1,920.00

0.0320 Pasir pasang (M3) Rp. 45,000.00 Rp. 1,440.00 24,760.00

Page 28: Master by Eno Aim

0.0800 Tukang batu Rp. 30,000.00 Rp. 2,400.00

0.0080 Kep. tukang batu Rp. 40,000.00 Rp. 320.00

0.2400 Pekerja Rp. 25,000.00 Rp. 6,000.00

0.0120 Mandor Rp. 40,000.00 Rp. 480.00 9,200.00

Rp. 33,960.00

1 M2 Lantai tegel 20 x 20 dengan 1 PC : 3 Ps. BOW-G.69

1.0000 Tegel (M2) Rp. 15,000.00 Rp. 15,000.00

0.2174 PC (zak) Rp. 32,000.00 Rp. 6,956.80

0.0280 Pasir pasang (M3) Rp. 45,000.00 Rp. 1,260.00 23,216.80

0.0800 Tukang batu Rp. 30,000.00 Rp. 2,400.00

0.0080 Kep. tukang batu Rp. 40,000.00 Rp. 320.00

0.2400 Pekerja Rp. 25,000.00 Rp. 6,000.00

0.0120 Mandor Rp. 40,000.00 Rp. 480.00 9,200.00

Rp. 32,416.80

1 M' Pasang tegel Plint 15 X 20 atau 10 x 20 cm dengan 1 PC : 2 Ps BOW-G.68.a

5.0000 Tegel Plint (bh) Rp. 750.00 Rp. 3,750.00

0.0250 PC (zak) Rp. 32,000.00 Rp. 800.00

0.0020 Pasir pasang (M3) Rp. 45,000.00 Rp. 90.00 4,640.00

0.1000 Tukang batu Rp. 30,000.00 Rp. 3,000.00

0.0100 Kep. tukang batu Rp. 40,000.00 Rp. 400.00

0.2000 Pekerja Rp. 25,000.00 Rp. 5,000.00

0.0100 Mandor Rp. 40,000.00 Rp. 400.00 8,800.00

Rp. 13,440.00

1 M2 Lantai tegel 20 x 20 dengan 1 PC : 2 Ps.

1.0000 Tegel Rp. 15,000.00 Rp. 15,000.00

0.7500 PC Rp. 32,000.00 Rp. 24,000.00

0.2500 Pasir pasang Rp. 45,000.00 Rp. 11,250.00 50,250.00

0.0800 Tukang batu Rp. 30,000.00 Rp. 2,400.00

0.0080 Kep. tukang batu Rp. 40,000.00 Rp. 320.00

0.2400 Pekerja Rp. 25,000.00 Rp. 6,000.00

0.0120 Mandor Rp. 40,000.00 Rp. 480.00 9,200.00

Rp. 59,450.00

1 M2 Pasang Keramik dinding 20 x 25 dengan 1 PC : 2 Ps

1.0000 Keramik Rp. 35,000.00 Rp. 35,000.00

0.2000 PC Rp. 32,000.00 Rp. 6,400.00

0.0090 Pasir pasang Rp. 45,000.00 Rp. 405.00 41,805.00

0.3000 Tukang batu Rp. 30,000.00 Rp. 9,000.00

0.0300 Kep. tukang batu Rp. 40,000.00 Rp. 1,200.00

0.5000 Pekerja Rp. 25,000.00 Rp. 12,500.00

0.0500 Mandor Rp. 40,000.00 Rp. 2,000.00 24,700.00

Rp. 66,505.00

1 M2 Pasang Paving Block

50.0000 Paving block (bh) Rp. 1,100.00 Rp. 55,000.00

0.2000 Pasir pasang (m3) Rp. 45,000.00 Rp. 9,000.00 64,000.00

0.2000 Tukang batu Rp. 30,000.00 Rp. 6,000.00

0.0200 Kep. Tukang batu Rp. 40,000.00 Rp. 800.00

0.4000 Pekerja Rp. 25,000.00 Rp. 10,000.00

0.0200 Mandor Rp. 40,000.00 Rp. 800.00 17,600.00

Rp. 81,600.00

PEKERJAAN PLESTERAN 1 M2 Plesteran tebal 15 mm dengan 1 PC : 2 Ps - SK SNI T-03-1991-03

0.2130 PC Rp. 32,000.00 Rp. 6,816.00 0.0170 Pasir pasang Rp. 45,000.00 Rp. 765.00 7,581.00 0.0200 Tukang batu Rp. 30,000.00 Rp. 600.00 0.0020 Kep. tukang batu Rp. 40,000.00 Rp. 80.00 0.0400 Pekerja Rp. 25,000.00 Rp. 1,000.00 0.0040 Mandor Rp. 40,000.00 Rp. 160.00 1,840.00

Rp. 9,421.00 1 M2 Plesteran tebal 15 mm dengan 1 PC : 3 Ps - SK SNI T-03-1991-03

0.1620 PC Rp. 32,000.00 Rp. 5,184.00 0.0190 Pasir pasang Rp. 45,000.00 Rp. 855.00 6,039.00 0.0200 Tukang batu Rp. 30,000.00 Rp. 600.00 0.0020 Kep. tukang batu Rp. 40,000.00 Rp. 80.00 0.0400 Pekerja Rp. 25,000.00 Rp. 1,000.00 0.0040 Mandor Rp. 40,000.00 Rp. 160.00 1,840.00

Rp. 7,879.00 1 M2 Plesteran tebal 15 mm dengan 1 PC : 4 Ps - SK SNI T-03-1991-03

0.1360 PC Rp. 32,000.00 Rp. 4,352.00 0.0200 Pasir pasang Rp. 45,000.00 Rp. 900.00 5,252.00 0.0200 Tukang batu Rp. 30,000.00 Rp. 600.00 0.0020 Kep. tukang batu Rp. 40,000.00 Rp. 80.00 0.0400 Pekerja Rp. 25,000.00 Rp. 1,000.00 0.0040 Mandor Rp. 40,000.00 Rp. 160.00 1,840.00

Rp. 7,092.00 1 M2 Plesteran tebal 15 mm dengan 1 PC : 6 Ps - SK SNI T-03-1991-03

0.0920 PC Rp. 32,000.00 Rp. 2,944.00 0.0230 Pasir pasang Rp. 45,000.00 Rp. 1,035.00 3,979.00 0.0200 Tukang batu Rp. 30,000.00 Rp. 600.00 0.0020 Kep. tukang batu Rp. 40,000.00 Rp. 80.00 0.0400 Pekerja Rp. 25,000.00 Rp. 1,000.00 0.0040 Mandor Rp. 40,000.00 Rp. 160.00 1,840.00

Rp. 5,819.00

Page 29: Master by Eno Aim

1 M2 Plesteran tebal 15 mm dengan 1 PC : 3 kp :10 Ps -SK SNI T-03-1991-030.0460 PC Rp. 32,000.00 Rp. 1,472.00 0.0060 Kapur Rp. 45,000.00 Rp. 270.00 0.0140 Pasir pasang Rp. 45,000.00 Rp. 630.00 2,372.00 0.0200 Tukang batu Rp. 30,000.00 Rp. 600.00 0.0020 Kep. tukang batu Rp. 40,000.00 Rp. 80.00 0.0400 Pekerja Rp. 25,000.00 Rp. 1,000.00 0.0040 Mandor Rp. 40,000.00 Rp. 160.00 1,840.00

Rp. 4,212.00 1 M2 Plesteran tebal 20 mm dengan 1 PC : 2 Ps - SK SNI T-03-1991-03

0.3570 PC Rp. 32,000.00 Rp. 11,424.00 0.0230 Pasir pasang Rp. 45,000.00 Rp. 1,035.00 12,459.00 0.0200 Tukang batu Rp. 30,000.00 Rp. 600.00 0.0020 Kep. tukang batu Rp. 40,000.00 Rp. 80.00 0.1200 Pekerja Rp. 25,000.00 Rp. 3,000.00 0.0120 Mandor Rp. 40,000.00 Rp. 480.00 4,160.00

Rp. 16,619.00

1 M2 Plesteran tebal 20 mm dengan 1 PC : 3 Ps - SK SNI T-03-1991-030.2700 PC Rp. 32,000.00 Rp. 8,640.00 0.0260 Pasir pasang Rp. 45,000.00 Rp. 1,170.00 9,810.00 0.0200 Tukang batu Rp. 30,000.00 Rp. 600.00 0.0020 Kep. tukang batu Rp. 40,000.00 Rp. 80.00 0.1200 Pekerja Rp. 25,000.00 Rp. 3,000.00 0.0120 Mandor Rp. 40,000.00 Rp. 480.00 4,160.00

Rp. 13,970.00 1 M2 Plesteran tebal 20 mm dengan 1 PC : 4 Ps - SK SNI T-03-1991-03

0.2170 PC Rp. 32,000.00 Rp. 6,944.00 0.0280 Pasir pasang Rp. 45,000.00 Rp. 1,260.00 8,204.00 0.0200 Tukang batu Rp. 30,000.00 Rp. 600.00 0.0020 Kep. tukang batu Rp. 40,000.00 Rp. 80.00 0.1200 Pekerja Rp. 25,000.00 Rp. 3,000.00 0.0120 Mandor Rp. 40,000.00 Rp. 480.00 4,160.00

Rp. 12,364.00 1 M2 Plesteran tebal 20 mm dengan 1 PC : 6 Ps - SK SNI T-03-1991-03

0.1560 PC Rp. 32,000.00 Rp. 4,992.00 0.0300 Pasir pasang Rp. 45,000.00 Rp. 1,350.00 6,342.00 0.0200 Tukang batu Rp. 30,000.00 Rp. 600.00 0.0020 Kep. tukang batu Rp. 40,000.00 Rp. 80.00 0.1200 Pekerja Rp. 25,000.00 Rp. 3,000.00 0.0120 Mandor Rp. 40,000.00 Rp. 480.00 4,160.00

Rp. 10,502.00 1 M' Pekerjaan siar pada pasangan batu bata dengan 1 PC : 3 PS

0.0976 PC Rp. 32,000.00 Rp. 3,123.20 0.0110 Pasir pasang Rp. 45,000.00 Rp. 495.00 3,618.20 0.1200 Tukang batu Rp. 30,000.00 Rp. 3,600.00 0.0120 Kep. tukang batu Rp. 40,000.00 Rp. 480.00 0.3600 Pekerja Rp. 25,000.00 Rp. 9,000.00 0.0180 Mandor Rp. 40,000.00 Rp. 720.00 13,800.00

Rp. 17,418.20

PEKERJAAN KAYU 1 M3 Rangka kuda-kuda dengan kayu Jati maks 6m -SK SNI T-11-1993-03

1.1000 Kayu Jati Rp. 6,500,000.00 Rp. 7,150,000.00 3.0000 Baut/Paku Rp. 15,000.00 Rp. 45,000.00

15.0000 Besi Strip Rp. 10,000.00 Rp. 150,000.00 7,345,000.00 18.0000 Tukang kayu Rp. 35,000.00 Rp. 630,000.00 1.8000 Kep. Tukang kayu Rp. 40,000.00 Rp. 72,000.00 6.0000 Pekerja Rp. 25,000.00 Rp. 150,000.00 0.3000 Mandor Rp. 40,000.00 Rp. 12,000.00 864,000.00

Rp. 8,209,000.00 1 M3 Rangka kuda-kuda dengan kayu kelapa maks 6m -SK SNI T-11-1993-03

1.1000 Kayu glugu Rp. 1,250,000.00 Rp. 1,375,000.00 3.0000 Baut/Paku Rp. 15,000.00 Rp. 45,000.00

15.0000 Besi Strip Rp. 10,000.00 Rp. 150,000.00 1,570,000.00 18.0000 Tukang kayu Rp. 35,000.00 Rp. 630,000.00 1.8000 Kep. Tukang kayu Rp. 40,000.00 Rp. 72,000.00 6.0000 Pekerja Rp. 25,000.00 Rp. 150,000.00 0.3000 Mandor Rp. 40,000.00 Rp. 12,000.00 864,000.00

Rp. 2,434,000.00 1 M3 Rangka kuda-kuda dengan kayu Kamper maks 6m -SK SNI T-11-1993-03

1.1000 Kayu Kamper Rp. 3,700,000.00 Rp. 4,070,000.00 3.0000 Baut/Paku Rp. 15,000.00 Rp. 45,000.00

15.0000 Besi Strip Rp. 10,000.00 Rp. 150,000.00 4,265,000.00 18.0000 Tukang kayu Rp. 35,000.00 Rp. 630,000.00 1.8000 Kep. Tukang kayu Rp. 40,000.00 Rp. 72,000.00 6.0000 Pekerja Rp. 25,000.00 Rp. 150,000.00 0.3000 Mandor Rp. 40,000.00 Rp. 12,000.00 864,000.00

Rp. 5,129,000.00 1 M3 Rangka kuda-kuda dengan kayu Bengkirai maks 6m -SK SNI T-11-1993-03

1.1000 Kayu Bengkirai Rp. 3,250,000.00 Rp. 3,575,000.00 3.0000 Baut/Paku Rp. 15,000.00 Rp. 45,000.00

15.0000 Besi Strip Rp. 10,000.00 Rp. 150,000.00 3,770,000.00 18.0000 Tukang kayu Rp. 35,000.00 Rp. 630,000.00 1.8000 Kep. Tukang kayu Rp. 40,000.00 Rp. 72,000.00 6.0000 Pekerja Rp. 25,000.00 Rp. 150,000.00

Page 30: Master by Eno Aim

0.3000 Mandor Rp. 40,000.00 Rp. 12,000.00 864,000.00 Rp. 4,634,000.00

1 M3 Rangka kuda-kuda dengan kayu Jati maks 6-9m -SK SNI T-11-1993-031.1000 Kayu Jati Rp. 6,500,000.00 Rp. 7,150,000.00 3.0000 Baut/Paku Rp. 15,000.00 Rp. 45,000.00

15.0000 Besi Strip Rp. 10,000.00 Rp. 150,000.00 7,345,000.00 20.0000 Tukang kayu Rp. 35,000.00 Rp. 700,000.00 2.0000 Kep. Tukang kayu Rp. 40,000.00 Rp. 80,000.00 6.0000 Pekerja Rp. 25,000.00 Rp. 150,000.00 0.3000 Mandor Rp. 40,000.00 Rp. 12,000.00 942,000.00

Rp. 8,287,000.00 1 M3 Rangka kuda-kuda dengan kayu Kamper maks 6-9m -SK SNI T-11-1993-03

1.1000 Kayu Kamper Rp. 3,700,000.00 Rp. 4,070,000.00 3.0000 Baut/Paku Rp. 15,000.00 Rp. 45,000.00

15.0000 Besi Strip Rp. 10,000.00 Rp. 150,000.00 4,265,000.00 20.0000 Tukang kayu Rp. 35,000.00 Rp. 700,000.00 2.0000 Kep. Tukang kayu Rp. 40,000.00 Rp. 80,000.00 6.0000 Pekerja Rp. 25,000.00 Rp. 150,000.00 0.3000 Mandor Rp. 40,000.00 Rp. 12,000.00 942,000.00

Rp. 5,207,000.00 1 M3 Rangka kuda-kuda dengan kayu Bengkirai maks 6-9m -SK SNI T-11-1993-03

1.1000 Kayu Bengkirai Rp. 3,250,000.00 Rp. 3,575,000.00 3.0000 Baut/Paku Rp. 15,000.00 Rp. 45,000.00

15.0000 Besi Strip Rp. 10,000.00 Rp. 150,000.00 3,770,000.00 26.0000 Tukang kayu Rp. 35,000.00 Rp. 910,000.00 2.6000 Kep. Tukang kayu Rp. 40,000.00 Rp. 104,000.00 8.0000 Pekerja Rp. 25,000.00 Rp. 200,000.00 0.4000 Mandor Rp. 40,000.00 Rp. 16,000.00 1,230,000.00

Rp. 5,000,000.00 1 M3 Gording dengan kayu Jati -SK SNI T-11-1993-03

1.1000 Kayu Jati Rp. 6,500,000.00 Rp. 7,150,000.00 2.2000 Baut/Paku Rp. 15,000.00 Rp. 33,000.00 7,183,000.00 7.0000 Tukang kayu Rp. 35,000.00 Rp. 245,000.00 0.7000 Kep. Tukang kayu Rp. 40,000.00 Rp. 28,000.00 2.4000 Pekerja Rp. 25,000.00 Rp. 60,000.00 0.1200 Mandor Rp. 40,000.00 Rp. 4,800.00 337,800.00

Rp. 7,520,800.00 1 M3 Gording dengan kayu kelapa -SK SNI T-11-1993-03

1.1000 Kayu kelapa Rp. 1,250,000.00 Rp. 1,375,000.00 2.2000 Baut/Paku Rp. 15,000.00 Rp. 33,000.00 1,408,000.00 7.0000 Tukang kayu Rp. 35,000.00 Rp. 245,000.00 0.7000 Kep. Tukang kayu Rp. 40,000.00 Rp. 28,000.00 2.4000 Pekerja Rp. 25,000.00 Rp. 60,000.00 0.1200 Mandor Rp. 40,000.00 Rp. 4,800.00 337,800.00

Rp. 1,745,800.00 1 M3 Gording dengan kayu Kamper -SK SNI T-11-1993-03

1.1000 Kayu Kamper Rp. 3,700,000.00 Rp. 4,070,000.00 2.2000 Baut/Paku Rp. 15,000.00 Rp. 33,000.00 4,103,000.00 5.8000 Tukang kayu Rp. 35,000.00 Rp. 203,000.00 0.5800 Kep. Tukang kayu Rp. 40,000.00 Rp. 23,200.00 1.9400 Pekerja Rp. 25,000.00 Rp. 48,500.00 0.0970 Mandor Rp. 40,000.00 Rp. 3,880.00 278,580.00

Rp. 4,381,580.00 1 M2 Pekerjaan Rangka atap seng

0.0110 Kayu jati m3 Rp. 6,500,000.00 Rp. 71,500.00 0.1000 Baut/paku Kg Rp. 15,000.00 Rp. 1,500.00 73,000.00 0.1000 Tukang kayu Rp. 35,000.00 Rp. 3,500.00 0.0100 Kep. Tukang kayu Rp. 40,000.00 Rp. 400.00 0.1500 Pekerja Rp. 25,000.00 Rp. 3,750.00 0.0075 Mandor Rp. 40,000.00 Rp. 300.00 7,950.00

Rp. 80,950.00 1 M2 Pekerjaan Kaso 5/7dan reng 2/3 -SK SNI T-11-1993-03

0.0150 Kayu Kamper Rp. 2,600,000.00 Rp. 39,000.00 0.1500 Baut/Paku Rp. 15,000.00 Rp. 2,250.00 41,250.00 0.1000 Tukang kayu Rp. 35,000.00 Rp. 3,500.00 0.0100 Kep. Tukang kayu Rp. 40,000.00 Rp. 400.00 0.1000 Pekerja Rp. 25,000.00 Rp. 2,500.00 0.0050 Mandor Rp. 40,000.00 Rp. 200.00 6,600.00

Rp. 47,850.00 1 M2 Pekerjaan Kaso 5/7dan reng 3/4 -SK SNI T-11-1993-03

0.0240 Kayu Kamper Rp. 2,600,000.00 Rp. 62,400.00 0.2500 Baut/Paku Rp. 15,000.00 Rp. 3,750.00 66,150.00 0.1000 Tukang kayu Rp. 35,000.00 Rp. 3,500.00 0.0100 Kep. Tukang kayu Rp. 40,000.00 Rp. 400.00 0.1000 Pekerja Rp. 25,000.00 Rp. 2,500.00 0.0050 Mandor Rp. 40,000.00 Rp. 200.00 6,600.00

Rp. 72,750.00 1 M2 Pekerjaan Kaso 5/7dan reng 3/4Genteng Beton -SK SNI T-11-1993-03

0.0170 Kayu Kamper Rp. 2,600,000.00 Rp. 44,200.00 0.1500 Baut/Paku Rp. 15,000.00 Rp. 2,250.00 46,450.00 0.1000 Tukang kayu Rp. 35,000.00 Rp. 3,500.00 0.0100 Kep. Tukang kayu Rp. 40,000.00 Rp. 400.00 0.1000 Pekerja Rp. 25,000.00 Rp. 2,500.00 0.0050 Mandor Rp. 40,000.00 Rp. 200.00 6,600.00

Rp. 53,050.00 1 M2 Pekerjaan Usuk/Kaso dan reng Jati

Page 31: Master by Eno Aim

0.0150 Usuk Kayu Jati Rp. 6,500,000.00 Rp. 97,500.00 0.0600 Reng kayu jati Rp. 6,500,000.00 Rp. 390,000.00 0.1500 Baut/Paku Rp. 15,000.00 Rp. 2,250.00 489,750.00 0.1000 Tukang kayu Rp. 35,000.00 Rp. 3,500.00 0.0100 Kep. Tukang kayu Rp. 40,000.00 Rp. 400.00 0.1000 Pekerja Rp. 25,000.00 Rp. 2,500.00 0.0050 Mandor Rp. 40,000.00 Rp. 200.00 6,600.00

Rp. 496,350.00 1 M2 Pekerjaan Usuk/Kaso dan reng kelapa

0.0150 Usuk Kayu kelapa Rp. 1,250,000.00 Rp. 18,750.00 0.0600 Reng kayu kelapa Rp. 1,250,000.00 Rp. 75,000.00 0.1500 Baut/Paku Rp. 15,000.00 Rp. 2,250.00 96,000.00 0.1000 Tukang kayu Rp. 35,000.00 Rp. 3,500.00 0.0100 Kep. Tukang kayu Rp. 40,000.00 Rp. 400.00 0.1000 Pekerja Rp. 25,000.00 Rp. 2,500.00 0.0050 Mandor Rp. 40,000.00 Rp. 200.00 6,600.00

Rp. 102,600.00 1 M2 Pekerjaan reng kayu bangkirai

0.0150 Usuk Kayu Bangkirai Rp. 3,250,000.00 Rp. 48,750.00 0.0600 Reng Bengkirai Rp. 3,250,000.00 Rp. 195,000.00 0.1500 Baut/Paku Rp. 15,000.00 Rp. 2,250.00 246,000.00 0.1000 Tukang kayu Rp. 35,000.00 Rp. 3,500.00 0.0100 Kep. Tukang kayu Rp. 40,000.00 Rp. 400.00 0.1000 Pekerja Rp. 25,000.00 Rp. 2,500.00 0.0050 Mandor Rp. 40,000.00 Rp. 200.00 6,600.00

Rp. 252,600.00

PEKERJAAN KUSEN 1 M3 Pekerjaan Kosen Pintu/ Jendela dari kayu jati -SK SNI T-11-1993-03

1.1000 Kayu Jati Rp. 6,500,000.00 Rp. 7,150,000.00 3.0000 Paku Rp. 12,000.00 Rp. 36,000.00

56.0000 Angkur Rp. 10,000.00 Rp. 560,000.00 7,746,000.00 31.0000 Tukang kayu Rp. 35,000.00 Rp. 1,085,000.00 3.1000 Kep. Tukang kayu Rp. 40,000.00 Rp. 124,000.00 9.3000 Pekerja Rp. 25,000.00 Rp. 232,500.00 0.4600 Mandor Rp. 40,000.00 Rp. 18,400.00 1,459,900.00

Rp. 9,205,900.00 1 M3 Pekerjaan Kosen Pintu/ Jendela dari kayu kelapa -SK SNI T-11-1993-03

1.1000 Kayu kelapa Rp. 1,250,000.00 Rp. 1,375,000.00 3.0000 Paku Rp. 12,000.00 Rp. 36,000.00

56.0000 Angkur Rp. 10,000.00 Rp. 560,000.00 1,971,000.00 31.0000 Tukang kayu Rp. 35,000.00 Rp. 1,085,000.00 3.1000 Kep. Tukang kayu Rp. 40,000.00 Rp. 124,000.00 9.3000 Pekerja Rp. 25,000.00 Rp. 232,500.00 0.4600 Mandor Rp. 40,000.00 Rp. 18,400.00 1,459,900.00

Rp. 3,430,900.00 1 M3 Pekerjaan Kosen Pintu/ Jendela dari kayu Kamper -SK SNI T-11-1993-03

1.1000 Kayu Kamper Rp. 3,700,000.00 Rp. 4,070,000.00 3.0000 Paku Rp. 12,000.00 Rp. 36,000.00

56.0000 Angkur Rp. 10,000.00 Rp. 560,000.00 4,666,000.00 24.0000 Tukang kayu Rp. 35,000.00 Rp. 840,000.00 2.4000 Kep. Tukang kayu Rp. 40,000.00 Rp. 96,000.00 7.2000 Pekerja Rp. 25,000.00 Rp. 180,000.00 0.3450 Mandor Rp. 40,000.00 Rp. 13,800.00 1,129,800.00

Rp. 5,795,800.00 1 M3 Pekerjaan Kosen Pintu/ Jendela dari kayu mahoni -SK SNI T-11-1993-03

1.1000 Kayu MAHONI Rp. 4,500,000.00 Rp. 4,950,000.00 3.0000 Paku Rp. 12,000.00 Rp. 36,000.00

56.0000 Angkur Rp. 10,000.00 Rp. 560,000.00 5,546,000.00 24.0000 Tukang kayu Rp. 35,000.00 Rp. 840,000.00 2.4000 Kep. Tukang kayu Rp. 40,000.00 Rp. 96,000.00 7.2000 Pekerja Rp. 25,000.00 Rp. 180,000.00 0.3450 Mandor Rp. 40,000.00 Rp. 13,800.00 1,129,800.00

Rp. 6,675,800.00 1 M2 Pekerjaan Daun pintu/jendela jalusi dari kayu Jati -SK SNI T-11-1993-03

0.0420 Kayu jati Rp. 6,500,000.00 Rp. 273,000.00 0.2000 Lem Rp. 15,000.00 Rp. 3,000.00 276,000.00 4.0000 Tukang kayu Rp. 35,000.00 Rp. 140,000.00 0.4000 Kep. tukang kayu Rp. 40,000.00 Rp. 16,000.00 1.3500 Pekerja Rp. 25,000.00 Rp. 33,750.00 0.0680 Mandor Rp. 40,000.00 Rp. 2,720.00 192,470.00

Rp. 468,470.00 1 M2 Pekerjaan Daun pintu/jendela jalusi dari kayu Kamper -SK SNI T-11-1993-03

0.0420 Kayu Kamper Rp. 3,700,000.00 Rp. 155,400.00 0.2000 Lem Rp. 15,000.00 Rp. 3,000.00 158,400.00 3.0000 Tukang kayu Rp. 35,000.00 Rp. 105,000.00 0.3000 Kep. tukang kayu Rp. 40,000.00 Rp. 12,000.00 1.0000 Pekerja Rp. 25,000.00 Rp. 25,000.00 0.0500 Mandor Rp. 40,000.00 Rp. 2,000.00 144,000.00

Rp. 302,400.00 1 M2 Pekerjaan daun pintu / jendela kaca rangka kayu Jati -SK SNI T-11-1993-03

0.0400 Kayu Jati Rp. 6,500,000.00 Rp. 260,000.00 0.0500 Paku Rp. 12,000.00 Rp. 600.00 0.7500 Kaca 5 mm Rp. 50,000.00 Rp. 37,500.00 298,100.00 2.7000 Tukang kayu Rp. 35,000.00 Rp. 94,500.00 0.2700 Kep. tukang kayu Rp. 40,000.00 Rp. 10,800.00

Page 32: Master by Eno Aim

1.0000 Pekerja Rp. 25,000.00 Rp. 25,000.00 0.0500 Mandor Rp. 40,000.00 Rp. 2,000.00 132,300.00

Rp. 430,400.00 1 M2 Pekerjaan Daun pintu/jendela Panil kayu Jati -SK SNI T-11-1993-03

0.0440 Kayu Jati Rp. 6,500,000.00 Rp. 286,000.00 0.1000 Lem Rp. 15,000.00 Rp. 1,500.00 287,500.00 2.7000 Tukang kayu Rp. 35,000.00 Rp. 94,500.00 0.2700 Kep. Tukang kayu Rp. 40,000.00 Rp. 10,800.00 1.3500 Pekerja Rp. 25,000.00 Rp. 33,750.00 0.0170 Mandor Rp. 40,000.00 Rp. 680.00 139,730.00

Rp. 427,230.00 1 M2 Pekerjaan Daun pintu/jendela Panil kayu Kamper -SK SNI T-11-1993-03

0.0440 Kayu Kamper Rp. 3,700,000.00 Rp. 162,800.00 0.1000 Lem Rp. 15,000.00 Rp. 1,500.00 164,300.00 2.0000 Tukang kayu Rp. 35,000.00 Rp. 70,000.00 0.2000 Kep. Tukang kayu Rp. 40,000.00 Rp. 8,000.00 1.0000 Pekerja Rp. 25,000.00 Rp. 25,000.00 0.0500 Mandor Rp. 40,000.00 Rp. 2,000.00 105,000.00

Rp. 269,300.00 1 M2 Pekerjaan Pintu/Jendela dengan bingkai

0.0400 Kayu BENGKIRAI Rp. 3,250,000.00 Rp. 130,000.00 0.1000 Paku Rp. 12,000.00 Rp. 1,200.00 131,200.00 1.5000 Tukang kayu Rp. 35,000.00 Rp. 52,500.00 0.1500 Kep. Tukang kayu Rp. 40,000.00 Rp. 6,000.00 0.5250 Pekerja Rp. 25,000.00 Rp. 13,125.00 0.0263 Mandor Rp. 40,000.00 Rp. 1,050.00 72,675.00

Rp. 164,300.00

PEKERJAAN PLAFON & LANGIT-LANGIT 1 M2 Pekerjaan Plafon Rangka grid 50 cm x 100 cm kayu Kamper -SK SNI T-11-1993-03

0.0270 Kayu Kamper Rp. 3,700,000.00 Rp. 99,900.00 0.1800 Paku Rp. 12,000.00 Rp. 2,160.00 1.0000 Asbes Rp. 8,500.00 Rp. 8,500.00 110,560.00 0.3500 Tukang kayu Rp. 35,000.00 Rp. 12,250.00 0.0350 Kep. Tukang kayu Rp. 40,000.00 Rp. 1,400.00 0.2100 Pekerja Rp. 25,000.00 Rp. 5,250.00 0.0110 Mandor Rp. 40,000.00 Rp. 440.00 19,340.00

Rp. 129,900.00 1 M2 Pekerjaan Plafon Rangka grid 30 cm x 60 cm kayu Kamper -SK SNI T-11-1993-03

0.0340 Kayu Kamper Rp. 3,700,000.00 Rp. 125,800.00 0.2300 Paku Rp. 12,000.00 Rp. 2,760.00 1.0000 Asbes Rp. 8,500.00 Rp. 8,500.00 137,060.00 0.5000 Tukang kayu Rp. 35,000.00 Rp. 17,500.00 0.0500 Kep. Tukang kayu Rp. 40,000.00 Rp. 2,000.00 0.3500 Pekerja Rp. 25,000.00 Rp. 8,750.00 0.0180 Mandor Rp. 40,000.00 Rp. 720.00 28,970.00

Rp. 166,030.00 1 M2 Pekerjaan Rangka Langit-langit grid 30 cm x 30 cm kayu Kamper -SK SNI T-11-1993-03

0.0380 Kayu Kamper Rp. 3,700,000.00 Rp. 140,600.00 0.2800 Paku Rp. 12,000.00 Rp. 3,360.00 1.0000 Asbes Rp. 8,500.00 Rp. 8,500.00 152,460.00 0.6000 Tukang kayu Rp. 35,000.00 Rp. 21,000.00 0.0600 Kep. Tukang kayu Rp. 40,000.00 Rp. 2,400.00 0.4300 Pekerja Rp. 25,000.00 Rp. 10,750.00 0.0220 Mandor Rp. 40,000.00 Rp. 880.00 35,030.00

Rp. 187,490.00 1 M2 Pekerjaan Papan Listplank 3 x 20 cm Dari Kayu kamper -SK SNI T-11-1993-03

0.0070 Kayu Kamper Rp. 3,700,000.00 Rp. 25,900.00 0.0500 Paku Rp. 12,000.00 Rp. 600.00 26,500.00 0.2000 Tukang kayu Rp. 35,000.00 Rp. 7,000.00 0.0200 Kep. Tukang kayu Rp. 40,000.00 Rp. 800.00 0.1000 Pekerja Rp. 25,000.00 Rp. 2,500.00 0.0500 Mandor Rp. 40,000.00 Rp. 2,000.00 12,300.00

Rp. 38,800.00 1 M2 Pasang plafon GRC 4 mm rangka kayu kruing 0.336 GRC Fiber Flat 4 mm Rp. 60,000.00 Rp. 20,155.87

0.002 Kruing 6/12 Rp. 2,600,000.00 Rp. 5,720.00

0.014 Usuk kayu Kruing 5/7 Rp. 2,300,000.00 Rp. 31,976.39 0.200 Paku Rp. 12,000.00 Rp. 2,400.00 0.075 Compound Rp. 10,000.00 Rp. 750.00 0.075 Alkasid Rp. 6,000.00 Rp. 450.00

0.0250 Strimin Rp. 6,500.00 Rp. 162.50 61,614.76 0.2000 Tukang kayu Rp. 35,000.00 Rp. 7,000.00 0.0200 Kep. Tukang kayu Rp. 40,000.00 Rp. 800.00 0.1000 Pekerja Rp. 25,000.00 Rp. 2,500.00 0.0500 Mandor Rp. 40,000.00 Rp. 2,000.00 12,300.00

Rp. 73,914.76 1 M2 Pekerjaan Papan Listplank 3 x 30 cm Dari Kayu kamper -SK SNI T-11-1993-03

0.0100 Kayu Kamper Rp. 3,700,000.00 Rp. 37,000.00 0.0500 Paku Rp. 12,000.00 Rp. 600.00 37,600.00 0.2850 Tukang kayu Rp. 35,000.00 Rp. 9,975.00 0.0290 Kep. Tukang kayu Rp. 40,000.00 Rp. 1,160.00 0.1430 Pekerja Rp. 25,000.00 Rp. 3,575.00 0.0070 Mandor Rp. 40,000.00 Rp. 280.00 14,990.00

Rp. 52,590.00 1 M2 Pekerjaan Papan Listplank 3 x 20 cm Dari Kayu Jati -SK SNI T-11-1993-03

0.0070 Kayu Jati Rp. 6,500,000.00 Rp. 45,500.00

Page 33: Master by Eno Aim

0.0500 Paku Rp. 12,000.00 Rp. 600.00 46,100.00 0.2000 Tukang kayu Rp. 35,000.00 Rp. 7,000.00 0.0200 Kep. Tukang kayu Rp. 40,000.00 Rp. 800.00 0.1000 Pekerja Rp. 25,000.00 Rp. 2,500.00 0.0500 Mandor Rp. 40,000.00 Rp. 2,000.00 12,300.00

Rp. 58,400.00 1 M2 Pekerjaan Papan Listplank 3 x 30 cm Dari Kayu Jati -SK SNI T-11-1993-03

0.0100 Kayu Jati Rp. 6,500,000.00 Rp. 65,000.00 0.0500 Paku Rp. 12,000.00 Rp. 600.00 65,600.00 0.2850 Tukang kayu Rp. 35,000.00 Rp. 9,975.00 0.0290 Kep. Tukang kayu Rp. 40,000.00 Rp. 1,160.00 0.1430 Pekerja Rp. 25,000.00 Rp. 3,575.00 0.0070 Mandor Rp. 40,000.00 Rp. 280.00 14,990.00

Rp. 80,590.00 1 M2 Pekerjaan Dinding Pemisah Teakwood rangkap rangka kayu Kamper -SK SNI T-11-1993-03

0.0190 Kayu Kamper Rp. 3,700,000.00 Rp. 70,300.00 0.3000 Lem Rp. 15,000.00 Rp. 4,500.00 0.1000 Paku Rp. 12,000.00 Rp. 1,200.00 1.0000 Teakwood Rp. 61,000.00 Rp. 61,000.00 137,000.00 0.6000 Tukang kayu Rp. 35,000.00 Rp. 21,000.00 0.0600 Kep. tukang kayu Rp. 40,000.00 Rp. 2,400.00 0.2000 Pekerja Rp. 25,000.00 Rp. 5,000.00 0.0100 Mandor Rp. 40,000.00 Rp. 400.00 28,800.00

Rp. 165,800.00 Pekerjaan Stutwerk untuk 1m3 balok bebas tinggi s/d 4m BOW hal 332

0.7000 Kayu Rp. 3,700,000.00 Rp. 2,590,000.00 2,590,000.00 10.5000 Tukang kayu Rp. 35,000.00 Rp. 367,500.00 1.0500 Kep. Tukang kayu Rp. 40,000.00 Rp. 42,000.00 3.5000 Pekerja Rp. 25,000.00 Rp. 87,500.00 0.1750 Mandor Rp. 40,000.00 Rp. 7,000.00 504,000.00

Rp. 3,094,000.00

PEKERJAAN BETON 1 M3 pekerjaan lantai kerja

0.8590 koral Rp. 50,000.00 Rp. 42,950.00

5.3685 pc Rp. 32,000.00 Rp. 171,792.00

0.5154 pasir beton Rp. 50,000.00 Rp. 25,770.00 240,512.00

0.6000 Tukang batu Rp. 30,000.00 Rp. 18,000.00

0.0600 Kep. tukang batu Rp. 40,000.00 Rp. 2,400.00

1.5000 Pekerja Rp. 25,000.00 Rp. 37,500.00

0.1500 Mandor Rp. 40,000.00 Rp. 6,000.00 63,900.00

Rp. 304,412.00 1 M3 upah pekerjaan beton

1.0000 Tukang batu Rp. 30,000.00 Rp. 30,000.00 0.1000 Kep. tukang batu Rp. 40,000.00 Rp. 4,000.00 6.0000 Pekerja Rp. 25,000.00 Rp. 150,000.00 0.3000 Mandor Rp. 40,000.00 Rp. 12,000.00 0.0500 Tk kayu Rp. 35,000.00 Rp. 1,750.00 0.1000 kep Tk. Kayu Rp. 40,000.00 Rp. 4,000.00 0.2000 Pekerja bongkar Rp. 25,000.00 Rp. 5,000.00 5.0000 Tukang besi Rp. 34,000.00 Rp. 170,000.00 0.5000 Kep. Tukang besi Rp. 38,000.00 Rp. 19,000.00 6.0000 Pekerja Rp. 25,000.00 Rp. 150,000.00 545,750.00

Rp. 545,750.00 1 M3 pekerjaan beton sloof 7.000 Pc 40kg Rp. 32,000.00 Rp. 224,000.00 0.540 pasir Rp. 50,000.00 Rp. 27,000.00 0.820 Batu Split Rp. 100,000.00 Rp. 82,000.00 120.000 Besi tulangan Rp. 6,500.00 Rp. 780,000.00 2.300 Bendrat Rp. 8,000.00 Rp. 18,400.00 2.416 Meranti 2.20.400 Rp. 17,000.00 Rp. 41,072.00 2.000 Meranti 5.7.400 Rp. 20,000.00 Rp. 40,000.00 0.250 Paku 2" Rp. 12,000.00 Rp. 3,000.00 1,215,472.00 1.000 upah 545,750.00

Rp. 1,761,222.00 1 M3 pekerjaan foot plate 7.80 PC 40kg Rp. 32,000.00 Rp. 249,600.00 0.54 pasir cor Rp. 50,000.00 Rp. 27,000.00 0.82 Batu Split Rp. 100,000.00 Rp. 82,000.00 150.00 Besi tulangan Rp. 6,500.00 Rp. 975,000.00 2.30 Bendrat Rp. 8,000.00 Rp. 18,400.00 2.42 Meranti 2.20.400 Rp. 17,000.00 Rp. 41,072.00 2.00 Meranti 5.7.400 Rp. 20,000.00 Rp. 40,000.00 1.00 Paku 2" Rp. 12,000.00 Rp. 12,000.00 1,445,072.00 1.000 upah 545,750.00

Rp. 1,990,822.00 1 M3 Beton Kolom struktur 7.000 Pc 40kg Rp. 32,000.00 Rp. 224,000.00 0.540 pasir Rp. 50,000.00 Rp. 27,000.00

0.820 Batu Split Rp. 100,000.00 Rp. 82,000.00 220.000 Besi tulangan Rp. 6,500.00 Rp. 1,430,000.00 4.400 Bendrat Rp. 8,000.00 Rp. 35,200.00 6.000 Meranti 2.20.400 Rp. 17,000.00 Rp. 102,000.00 4.905 Meranti 5.7.400 Rp. 20,000.00 Rp. 98,100.00 3.000 Paku 2" Rp. 12,000.00 Rp. 36,000.00 2,034,300.00

Page 34: Master by Eno Aim

1.000 upah 545,750.00 Rp. 2,580,050.00

1 M3 Pek. Beton Kolom Praktis

7.000 Pc 40kg Rp. 32,000.00 Rp. 224,000.00

0.540 pasir Rp. 50,000.00 Rp. 27,000.00

0.820 Batu Split Rp. 100,000.00 Rp. 82,000.00

164.000 Besi tulangan Rp. 6,500.00 Rp. 1,066,000.00 2.200 Bendrat Rp. 8,000.00 Rp. 17,600.00 6.000 Meranti 2.20.400 Rp. 17,000.00 Rp. 102,000.00 4.905 Meranti 5.7.400 Rp. 20,000.00 Rp. 98,100.00 3.304 Paku 2" Rp. 12,000.00 Rp. 39,648.00 1,656,348.00 1.000 upah 545,750.00

Rp. 2,202,098.00 1 M3 Beton balok ring 7.000 Pc 40kg Rp. 32,000.00 Rp. 224,000.00 0.540 pasir Rp. 50,000.00 Rp. 27,000.00

0.820 Batu Split Rp. 100,000.00 Rp. 82,000.00 120.000 Besi tulangan Rp. 6,500.00 Rp. 780,000.00 2.400 Bendrat Rp. 8,000.00 Rp. 19,200.00 6.000 Meranti 2.20.400 Rp. 17,000.00 Rp. 102,000.00 8.250 Meranti 5.7.400 Rp. 20,000.00 Rp. 165,000.00 2.840 Paku 3" Rp. 12,000.00 Rp. 34,080.00 3.000 Paku 4" Rp. 12,000.00 Rp. 36,000.00 1,469,280.00 1.000 upah 545,750.00

Rp. 2,015,030.00 1 M3 Beton Plat kanopy (leuvel) 8 cm 7.000 Pc 40kg Rp. 32,000.00 Rp. 224,000.00 0.540 pasir Rp. 50,000.00 Rp. 27,000.00 0.820 Batu Split Rp. 100,000.00 Rp. 82,000.00 85.00 Besi tulangan Rp. 6,500.00 Rp. 552,500.00 1.700 Bendrat Rp. 8,000.00 Rp. 13,600.00 6.840 Meranti 2.20.400 Rp. 17,000.00 Rp. 116,280.00 6.750 Meranti 5.7.400 Rp. 20,000.00 Rp. 135,000.00 2.000 Paku 2" Rp. 12,000.00 Rp. 24,000.00 1,174,380.00 1.000 upah 545,750.00

Rp. 1,720,130.00

1 M3 Beton Plat lantai 12 cm

7.000 Pc 40kg Rp. 32,000.00 Rp. 224,000.00

0.540 pasir Rp. 50,000.00 Rp. 27,000.00

0.820 Batu Split Rp. 100,000.00 Rp. 82,000.00

115.00 Besi tulangan Rp. 6,500.00 Rp. 747,500.00

2.300 Bendrat Rp. 8,000.00 Rp. 18,400.00

4.125 Meranti 2.20.400 Rp. 17,000.00 Rp. 70,125.00

6.750 Meranti 5.7.400 Rp. 20,000.00 Rp. 135,000.00

2.000 Paku 2" Rp. 12,000.00 Rp. 24,000.00 1,328,025.00 1.000 upah 545,750.00

Rp. 1,873,775.00

PEKERJAAN PENUTUP ATAP 1 M2 Menutup atap dengan genteng kodok/flam/plentong -SK SNI T-13-1993-03

25.0000 Genteng Rp. 1,100.00 Rp. 27,500.00 27,500.00 0.0750 Tukang batu Rp. 30,000.00 Rp. 2,250.00 0.0080 Kep. Tukang batu Rp. 40,000.00 Rp. 320.00 0.1500 Pekerja Rp. 25,000.00 Rp. 3,750.00 0.0080 Mandor Rp. 40,000.00 Rp. 320.00 6,640.00

Rp. 34,140.00 1 M2 Menutup atap dengan genteng beton -SK SNI T-13-1993-03

10.0000 Genteng Rp. 5,000.00 Rp. 50,000.00 0.0300 Paku Rp. 12,000.00 Rp. 360.00 50,360.00 0.1000 Tukang batu Rp. 30,000.00 Rp. 3,000.00 0.0100 Kep. Tukang batu Rp. 40,000.00 Rp. 400.00 0.2000 Pekerja Rp. 25,000.00 Rp. 5,000.00 0.0100 Mandor Rp. 40,000.00 Rp. 400.00 8,800.00

Rp. 59,160.00 1 M' Menutup bubungan dan jurai luar pada genteng kodok -SK SNI T-13-1993-03

5.0000 Genteng bumbung Rp. 3,000.00 Rp. 15,000.000.2700 PC Rp. 32,000.00 Rp. 8,640.000.0320 Pasir Pasang Rp. 45,000.00 Rp. 1,440.00 25,080.00 0.2000 Tukang batu Rp. 30,000.00 Rp. 6,000.000.0200 Kep. Tukang batu Rp. 40,000.00 Rp. 800.000.4000 Pekerja Rp. 25,000.00 Rp. 10,000.000.0020 Mandor Rp. 40,000.00 Rp. 80.00 16,880.00

Rp. 41,960.00 1 M' Menutup bubungan dan jurai luar pada genteng beton -SK SNI T-13-1993-03

3.5000 Genteng beton Rp. 5,000.00 Rp. 17,500.00 0.2700 PC Rp. 32,000.00 Rp. 8,640.00 0.0250 PC warna Rp. 65,000.00 Rp. 1,625.00 0.0320 Pasir Pasang Rp. 45,000.00 Rp. 1,440.00 29,205.00 0.2000 Tukang batu Rp. 30,000.00 Rp. 6,000.00 0.0200 Kep. Tukang batu Rp. 40,000.00 Rp. 800.00 0.4000 Pekerja Rp. 25,000.00 Rp. 10,000.00 0.0020 Mandor Rp. 40,000.00 Rp. 80.00 16,880.00

Rp. 46,085.00 1 M2 Menutup atap asbes semen gelombang 300x105 cm -SK SNI T-13-1993-03

0.3500 Asbes gelombang Rp. 50,000.00 Rp. 17,500.00 2.0000 Angkur baut Rp. 10,000.00 Rp. 20,000.00 37,500.00

Page 35: Master by Eno Aim

0.0670 Tukang kayu Rp. 35,000.00 Rp. 2,345.00 0.0070 Kep. Tukang kayu Rp. 40,000.00 Rp. 280.00 0.1400 Pekerja Rp. 25,000.00 Rp. 3,500.00 0.0070 Mandor Rp. 40,000.00 Rp. 280.00 6,405.00

Rp. 43,905.00 1 M2 Menutup atap asbes semen gelombang 210x105 cm -SK SNI T-13-1993-03

0.5000 Asbes gelombang Rp. 34,000.00 Rp. 17,000.00 2.0000 Angkur baut Rp. 10,000.00 Rp. 20,000.00 37,000.00 0.0670 Tukang kayu Rp. 35,000.00 Rp. 2,345.00 0.0070 Kep. Tukang kayu Rp. 40,000.00 Rp. 280.00 0.1400 Pekerja Rp. 25,000.00 Rp. 3,500.00 0.0070 Mandor Rp. 40,000.00 Rp. 280.00 6,405.00

Rp. 43,405.00 1 M' Menutup bubungan pada atap asbes gelombang (nok stel) -SK SNI T-13-1993-03

2.1000 Bubung asbes Rp. 19,000.00 Rp. 39,900.004.0000 Angkur baut Rp. 10,000.00 Rp. 40,000.00 79,900.00 0.1250 Tukang kayu Rp. 35,000.00 Rp. 4,375.000.1300 Kep. Tukang kayu Rp. 40,000.00 Rp. 5,200.000.0840 Pekerja Rp. 25,000.00 Rp. 2,100.000.0040 Mandor Rp. 40,000.00 Rp. 160.00 11,835.00

Rp. 91,735.00 1 M' Menutup bubungan pada atap asbes gelombang (nok paten) -SK SNI T-13-1993-03

1.0500 Bubung asbes Rp. 33,000.00 Rp. 34,650.00 4.0000 Angkur baut Rp. 10,000.00 Rp. 40,000.00 74,650.00 0.1250 Tukang kayu Rp. 35,000.00 Rp. 4,375.00 0.1300 Kep. Tukang kayu Rp. 40,000.00 Rp. 5,200.00 0.0840 Pekerja Rp. 25,000.00 Rp. 2,100.00 0.0040 Mandor Rp. 40,000.00 Rp. 160.00 11,835.00

Rp. 86,485.00 1 M2 Pekerjaan atap asbes ( bertingkat )

1.0000 Sirap Rp. 110,000.00 Rp. 110,000.00 0.0562 Paku Rp. 12,000.00 Rp. 675.00 110,675.00 0.1125 Tukang kayu Rp. 35,000.00 Rp. 3,937.50 0.0113 Kep. Tukang kayu Rp. 40,000.00 Rp. 450.00 0.2250 Pekerja Rp. 25,000.00 Rp. 5,625.00 0.0113 Mandor Rp. 40,000.00 Rp. 450.00 10,462.50

Rp. 121,137.50 1m2 Metal Roof Colour

1.0000 Metal Roof Colour Rp. 75,000.00 75,000.00 12.0000 Paku Rp. 12,000.00 144,000.00 219,000.00 0.0100 Mandor Rp. 40,000.00 400.00 0.0100 Kep. Tk Batu Rp. 40,000.00 400.00 0.1000 Tk. Batu Rp. 30,000.00 3,000.00 0.2000 Pekerja Rp. 25,000.00 5,000.00 8,800.00

Rp. 227,800.00 1m2 Nok Atas Metal Roof Colour

1.0000 Nok atas Metal Roof Rp. 25,000.00 25,000.00 12.0000 Paku Rp. 12,000.00 144,000.00 169,000.00 0.0200 Mandor Rp. 40,000.00 800.00 0.0200 Kep. Tk Batu Rp. 40,000.00 800.00 0.2000 Tk. Batu Rp. 30,000.00 6,000.00 0.4000 Pekerja Rp. 25,000.00 10,000.00 17,600.00

Rp. 186,600.00

1m2 Nok Samping Metal Roof 1.0000 Nok Samping Metal Roof Rp. 26,000.00 26,000.00

12.0000 Paku Rp. 12,000.00 144,000.00 170,000.00 0.0200 Mandor Rp. 40,000.00 800.00 0.0200 Kep. Tk Batu Rp. 40,000.00 800.00 0.2000 Tk. Batu Rp. 30,000.00 6,000.00 0.4000 Pekerja Rp. 25,000.00 10,000.00 17,600.00

Rp. 187,600.00

1m2 Wall Flashing Metal Roof 1.0000 Wall Flashing Metal Roof 26,000.00 26,000.00 4.0000 Paku 12,000.00 48,000.00 74,000.00 0.0200 Mandor 40,000.00 800.00 0.0200 Kep. Tk Batu 40,000.00 800.00 0.2000 Tk. Batu 30,000.00 6,000.00 0.4000 Pekerja 25,000.00 10,000.00 17,600.00

Rp. 91,600.00

PEKERJAAN TALANGMemasang talang patahan atap per 10 m' - BOW

3.5000 Seng BJLS 0.3 Rp 40,000.00 Rp 140,000.00350.0000 Paku sumbat Rp 150.00 Rp 52,500.00 192,500.00

6.0000 Tukang besi Rp 34,000.00 Rp 204,000.000.6000 Kep. Tk besi Rp 38,000.00 Rp 22,800.003.5000 Pekerja Rp 25,000.00 Rp 87,500.000.1750 Mandor Rp 40,000.00 Rp 7,000.00 321,300.00

Rp. 513,800.00Untuk 1 m' 51,380.00

Memasang talang kantong per 10 m' - BOW5.5000 Seng BJLS 0.3 Rp 40,000.00 Rp 220,000.00

500.0000 Paku sumbat Rp 150.00 Rp 75,000.00 295,000.008.0000 Tukang besi Rp 34,000.00 Rp 272,000.000.8000 Kep. Tk besi Rp 38,000.00 Rp 30,400.00

Page 36: Master by Eno Aim

5.0000 Pekerja Rp 25,000.00 Rp 125,000.000.2500 Mandor Rp 40,000.00 Rp 10,000.00 437,400.00

Rp. 732,400.00Untuk 1 m' 73,240.00

1 M2 Atap seng gelombang BJLS 0.3 per m2 - BOW0.7500 Seng gelombang Rp 35,000.00 Rp 26,250.004.0000 Sekrup kayu Rp 300.00 Rp 1,200.00 27,450.000.2000 Tukang besi Rp 34,000.00 Rp 6,800.000.0200 Kep. Tk besi Rp 38,000.00 Rp 760.000.1500 Pekerja Rp 25,000.00 Rp 3,750.000.0050 Mandor Rp 40,000.00 Rp 200.00 11,510.00

Rp. 38,960.0010 M2 Memasang talang tritisan per 10 m2 - BOW

3.0000 Seng BJLS 0.3 Rp 40,000.00 Rp 120,000.00300.0000 Paku sumbat Rp 300.00 Rp 90,000.00 210,000.00

5.0000 Tukang besi Rp 34,000.00 Rp 170,000.000.5000 Kep. Tk besi Rp 38,000.00 Rp 19,000.003.0000 Pekerja Rp 25,000.00 Rp 75,000.000.1500 Mandor Rp 40,000.00 Rp 6,000.00 270,000.00

Rp. 480,000.00Untuk 1 m2 48,000.00

Memasang talang pembuang air per 10 m2 - BOW2.5000 Seng BJLS 0.3 Rp 40,000.00 Rp 100,000.00

225.0000 Paku sumbat Rp 300.00 Rp 67,500.00 167,500.003.7500 Tukang besi Rp 34,000.00 Rp 127,500.000.3750 Kep. Tk besi Rp 38,000.00 Rp 14,250.002.2500 Pekerja Rp 25,000.00 Rp 56,250.000.1100 Mandor Rp 40,000.00 Rp 4,400.00 202,400.00

Rp. 369,900.00Untuk 1 m2 36,990.00

PEKERJAAN CAT/PLITUR 10 M2 Mendempul, sekali cat dasar - BOW - (1 1/2.K.2+K.30+K.23)

2.2500 Cat dasar Rp. 11,000.00 Rp. 24,750.00 0.8000 Dempul Rp. 11,000.00 Rp. 8,800.00 0.5000 Minyak cat Rp. 10,000.00 Rp. 5,000.00 2.0000 amplas Rp. 2,500.00 Rp. 5,000.00 43,550.00 0.7500 Tukang cat Rp. 32,500.00 Rp. 24,375.00 0.0750 Kep. Tukang cat Rp. 38,000.00 Rp. 2,850.00 0.5000 Pekerja Rp. 25,000.00 Rp. 12,500.00 0.0250 Mandor Rp. 40,000.00 Rp. 1,000.00 40,725.00

Rp. 84,275.00 Untuk 1 m2 8,427.50

1 m2 3x Mengecat tembok0.2500 Cat Rp. 52,400.00 Rp. 13,100.00 0.1400 Dempul Rp. 11,000.00 Rp. 1,540.00 0.5000 Amplas Rp. 11,000.00 Rp. 5,500.00 20,140.00 0.2250 Tukang cat Rp. 32,500.00 Rp. 7,312.50 0.0225 Kep. Tukang cat Rp. 34,000.00 Rp. 765.00 0.2500 Pekerja Rp. 25,000.00 Rp. 6,250.00 0.0250 Mandor Rp. 40,000.00 Rp. 1,000.00 15,327.50

Rp. 35,467.50 1 M2 3x Pekerjaan aqua Plitur sederhana

0.0600 aqua politur Rp. 35,000.00 Rp. 2,100.00 1.8800 Spiritus Rp. 5,500.00 Rp. 10,340.00 1.2000 Batu apung Rp. 6,000.00 Rp. 7,200.00 19,640.00 0.5000 Tukang Plitur Rp. 32,500.00 Rp. 16,250.00 16,250.00

Rp. 35,890.00 1 M2 Pekerjaan cat dasar

0.2250 Cat meni Rp. 11,000.00 Rp. 2,475.00 0.0800 Plamir Rp. 11,000.00 Rp. 880.00 0.0500 Minyak cat Rp. 10,000.00 Rp. 500.00 0.2000 amplas Rp. 2,500.00 Rp. 500.00 4,355.00 0.0750 Tukang cat Rp. 32,500.00 Rp. 2,437.50 0.0075 Kep. Tukang cat Rp. 34,000.00 Rp. 255.00 0.0500 Pekerja Rp. 25,000.00 Rp. 1,250.00 0.0025 Mandor Rp. 40,000.00 Rp. 100.00 4,042.50

Rp. 8,397.50 1 M2 Pekerjaan mengecat 3x serta mengosok dan mendempul.

0.2600 Cat Rp. 52,400.00 Rp. 13,624.000.0500 Minyak cat Rp. 10,000.00 Rp. 500.000.1000 amplas Rp. 2,500.00 Rp. 250.00 14,374.00 0.0700 Tukang cat Rp. 32,500.00 Rp. 2,275.000.0070 Kep. Tukang cat Rp. 34,000.00 Rp. 238.000.0500 Pekerja Rp. 25,000.00 Rp. 1,250.000.0025 Mandor Rp. 40,000.00 Rp. 100.00 3,863.00

Rp. 18,237.00 1 M2 Pekerjaan meni kayu Atap 0.2500 menie Rp. 11,000.00 Rp. 2,750.00 2,750.00 0.2500 Tenaga Rp. 25,000.00 6,250.00 6,250.00

Rp. 9,000.00 1 M2 Pekerjaan cat melamin kayu (pintu,jendela,mebel)

0.500 Cat melamik impra Rp. 15,000.00 Rp. 7,500.00 0.300 Wood Filer Rp. 10,000.00 Rp. 3,000.00 1.250 Thinner ND Super Rp. 17,000.00 Rp. 21,250.00 0.500 Sanding Sealer Rp. 17,500.00 Rp. 8,750.00

Page 37: Master by Eno Aim

2.000 Amplas Rp. 2,500.00 Rp. 5,000.00 45,500.00 1.000 Upah melamin Rp. 10,000.00 Rp. 10,000.00 10,000.00

Rp. 55,500.00 1 M2 Pekerjaan cat duco (dinding)

0.285 Cat duco Rp. 12,000.00 Rp. 3,400.00

0.300 wood filler Rp. 10,000.00 Rp. 3,000.00 0.050 Alkali primer Rp. 16,000.00 Rp. 800.00 0.050 Amplas Rp. 2,500.00 Rp. 125.00 0.200 Kuwas 4" Rp. 7,500.00 Rp. 1,500.00 8,825.00 1.000 Upah cat dinding Rp. 7,500.00 Rp. 7,500.00 7,500.00

Rp. 16,325.00 1 M2 Pekerjaan cat duco (kayu)

0.285 Cat duco Rp. 21,000.00 Rp. 5,900.00

0.300 wood filler Rp. 10,000.00 Rp. 3,000.00 1.250 Thinner ND Super Rp. 17,000.00 Rp. 21,250.00 0.500 Sanding Sealer Rp. 17,500.00 Rp. 8,750.00 0.050 Alkali primer Rp. 16,000.00 Rp. 800.00 0.500 Amplas Rp. 2,500.00 Rp. 1,250.00 0.200 Kuwas 4" Rp. 7,500.00 Rp. 1,500.00

0.075 Compound Rp. 10,000.00 Rp. 750.000.075 Alkasid Rp. 6,000.00 Rp. 450.00 43,650.00

0.2250 Tukang cat Rp. 32,500.00 Rp. 7,300.000.0225 Kep. Tukang cat Rp. 34,000.00 Rp. 700.000.2500 Pekerja Rp. 25,000.00 Rp. 6,250.000.0250 Mandor Rp. 40,000.00 Rp. 1,000.00 15,250.00

Rp. 58,900.00

Page 38: Master by Eno Aim
Page 39: Master by Eno Aim

REKAPITULASI ANGGARAN BIAYA

PROYEK RENOVASI & INTERIOR

BREEZE CAFÉ, JL. KALIURANG

NO URAIAN PEKERJAAN JUMLAH JUMLAH