BIG Structural Engineering Corporation The "BIG" engineering project Bigger is better, because it reflects our profit motives“ By: Mark Blum University of British Columbia Project Management PM TOOL KIT ASSIGNMENT: Course IL821W14A

Transcript of Mark blum ubc tool box execution - powerpoint presentation

Page 1: Mark blum   ubc tool box execution - powerpoint presentation

BIG Structural Engineering Corporation

The "BIG" engineering project Bigger is better, because it reflects our profit motives“

By: Mark BlumUniversity of British Columbia

Project ManagementPM TOOL KIT ASSIGNMENT: Course IL821W14A

Page 2: Mark blum   ubc tool box execution - powerpoint presentation

Executive Summary & Background

This presentation is with regards to, the current budget and schedule overruns in,

“The BIG Engineering project” utilizing Earned Value Analysis.

Earned Value Analysis (EVA); has been used by the U.S. Defence Department since the 1960s and they have found it to be an accurate forecasting tool. Their statistical analysis has shown that once a project is 10% complete, the overrun at completion will not be less than the current overrun.

They also found that once a project is 20% complete, the (CPI) Cost Performance Index does not vary from its current value by more than 10%*.

* QUOTE: UBC Project Management Course Manual

This project is currently over budget regarding it’s, C.P.I and other key indicators.

- Something needs to be done to change this course …

Page 3: Mark blum   ubc tool box execution - powerpoint presentation

Section IThis project is behind schedule and over budget as of the end of 1Q10.

The project is 25% complete, this means we need to achieve overall savings

during the remaining 75% of the project. -How do we do this?

This meeting is to review options Actual and projected cost comparisons

@ 24% completion of Project

V.A.C (Current "Variance at completion" -$168,618.40

A.C (Actual cost to date) 629522

(Schedual Variance) -Over budget. -

248660

E.A.C (Estimated Cost @ completion)

1988478.4

AC (Actual cost todate)

SV (SchedualVariance) -Overbudget.

EAC (EstimatedCost @ completion)

VAC (Current"Varance atcompletion"

Page 4: Mark blum   ubc tool box execution - powerpoint presentation

Making Sense of Dollars and Cents

$0.00

$100,000.00

$200,000.00

$300,000.00

$400,000.00

$500,000.00

$600,000.00

$700,000.00

$800,000.00

$900,000.00

Planned Value - PV (BCWS) Earned Value - EV (BCWP) AC (ACWP)

Series1

Column #1Planned Value PV (BCWS)

Cumulative, budgeted cost of work scheduled

(How much money we budgeted) which is: $824,800.00

Column #2Earned Value - EV (BCWP )

Cumulative budgeted cost of work performed or Earned Value.

(This is what is paid for and completed). which is: $576,140.00

Column #3Actual Cost (ACWP)

Cumulative actual cost of work performed or (What we paid for so far)

which is $629,522.00

Page 5: Mark blum   ubc tool box execution - powerpoint presentation

Current Project Status

I have conducted an analysis of the projects progress to date, to determine the reason, costs and the schedule are

exceeding expectations and underperforming.

1. The Schedule Performance Index is 0.7, and there is a cost Variance of 0.92.

( anything less than 1 is over budget)2. The schedule variance is $248, 660.00 Dollars over budgeted

allocations.

3. The cost Variance is $53,382.00 Dollars over budgeted allocations.

WHY ?

Page 6: Mark blum   ubc tool box execution - powerpoint presentation

Earned Value Analysis tracks money expended compares it to budgeted allocations for actual performance.

E.V.A. is a very good way to monitor progress; - and to be proactive.

When resource allocations have not been fulfilled, as planned or budgeted for:

• This unfulfilled work, causes budgetary deficiencies and cost overruns. • In this project, the categories of Design / Planning / Control and Scope are not in compliance with

the plan.

• In this project “TASKS” are showing very low resource utilization compliance, with planned results and particularly scheduled results pointing towards exceeding both the scheduled and budget projections.

• When “Planned value” and “Actual cost” are not equal, this creates budgeted cost overruns.

• This is due to non performance as per my analysis caused by the under performance of resources. • In a domino effect; This affects both earned value, and critical schedules to complete the project.

• You can see from the Ms. Project budget cost over runs are due largely do to scheduling issues, or in simpler terms;

-Work is not being performed as schedule by resources.

Page 7: Mark blum   ubc tool box execution - powerpoint presentation

Summary of Calculations Note: *These values have been rounded off.

Earned Value Calculations*PV = Planned Value $825,000AC = Actual Cost to date $630,000EV = Earned Value – What is completed

$576,000

SV = Schedule Variance ($249,000)CV = Cost Variance ($53,000)SPI = Schedule Performance Index

.70

CPI = Cost Performance Index .92EAC = Estimate at completion $2,000,000VAC = Variance at completion ($169,000)BAC = Budget at completion $1,819,000ETC = Estimate at completion $1,676,000

Page 8: Mark blum   ubc tool box execution - powerpoint presentation

Section II

Specific Solutions

What is the essence of the issue?

It appears we have an issue with resource non-performance causing budget overruns.

Delays in getting work (tasks), done

on time as scheduled, are going to result cost increases given current projections, if corrective action is not taken as soon as possible.

Resources not availing themselves to the project, are therefore causing delays and increased costs.

How do we rectify this problem?

It is critical that all departments :implement the resources necessary

for the project tasks suffering from non conformity in order to succeed according to our plan, to bring the project back on track, so that we can achieve project completion both;

On Time & On Budget.

Page 9: Mark blum   ubc tool box execution - powerpoint presentation

Specific Solutions

How should we proceed proactively / concretely and prevent the projected cost over runs?

After this meeting, I will supply a list of resources that are under performing to each department by email.

1. I will be sending an excel spread sheet by email after this meeting to each affected senior manager explaining these areas are under performing. The yellow highlighted areas are an itemized list for each task/resource that is non conforming.

2. You can forward this to each of the affected department managers, and determine the reason for non performance, and how this can be overcome and to allocate the specified non-performing resources on a priority bases.

3. This list will enable you to address the problems with resources that are causing these budgetary overruns due to non performance, so that we can bring the project back on track.

What are the costs of these

recommendations ?

These recommendations will not change the projects scope, but rather bring the budgets and time schedule back in line with the allocations.

It is critical that the change control committee approve the requirement that resources be allocated without further delay to bring the project back on track with the allocated budgets and expedite the performance of all resources towards their fulfillment.

Page 10: Mark blum   ubc tool box execution - powerpoint presentation

Section IIIDecisions - management needs to make

Actions needed

I am confident that each department will make the adjustments necessary

to allocate resources once I provide this listing and you have seen the listing of non performers. You can now pin point where you need to take action and

where are the compliance issues, provide motivation, to either meet or exceed

the expectations of our plan in the spirit of true team work. Thank you!