Mariposa Pump Station
Transcript of Mariposa Pump Station
Mariposa Pump Station
Civic Design Review - Phase 1 | 06.19.2017 | Page 5
PROJECT LOCATION
Project Site
MARIPOSA STREET
THE RAMP
SF BOATWORKS
CRANE COVE PARK (FUTURE)
MISSION BAY PARK 24 (FUTURE)
MISSION ROCKRESORT
ILLI
NO
IS S
TREE
T
TERR
Y A
FRAN
COIS
BLVD
PROJECT SITE
3RD
STR
EET
O 50’ 100’ 200’ n
Mariposa Pump Station
Civic Design Review - Phase 1 | 06.19.2017 | Page 9
Existing Site
MARIPOSA STREET
ILLI
NO
IS S
TREE
T
TERR
Y A
FRAN
COIS
BLVD
BOATWORKS FENCE
EXISTING FENCE
O 8’ 16’ 32’ nn
PUMP STATION
MAINTENANCEYARD
SAN FRANCISCOBOATWORKS
THE RAMPDRIVEWAY & PARKING
Mariposa Pump Station
Civic Design Review - Phase 1 | 06.19.2017 | Page 10
Site Plan
MARIPOSA STREET
ILLI
NO
IS S
TREE
T
TERR
Y A
FRAN
COIS
BLVD
FENCE EXTENTS
RESTORED RAMP FENCEBOLLARDS & GRAVEL
VEHICLE GATE
FRONTAGE PLANTING
FRONTAGE PLANTING
BOATWORKS FENCE
MAN GATE
O 8’ 16’ 32’ nn
PUMP STATION
MAINTENANCEYARD
SAN FRANCISCOBOATWORKS
THE RAMPDRIVEWAY & PARKING
VEHICLE DRIVEWAY
BLUE GREENWAYPLANTING AREA
Mariposa Pump Station
Civic Design Review - Phase 1 | 06.19.2017 | Page 11
First Floor Plan
ELECTRICAL ROOM
nO 2’ 4’ 8’ 12’
WET WELL
RESTROOM
DN DN DN
DN
UP
Mariposa Pump Station
Civic Design Review - Phase 1 | 06.19.2017 | Page 12
Building SectionsO 4’ 8’ 16’ 24’
WET WELL
PUMP ROOM
ELECTRICAL ROOM
PUMP ROOM
ELECTRICAL ROOM
FIRST FLOOR2’-0”
BASEMENT-19’-0”
ROOF16’-0”
T.O. PARAPET21’-0”
Mariposa Pump Station
Civic Design Review - Phase 1 | 06.19.2017 | Page 19
View 3Sheet Title
Building Design & Construction
Project Name
Presentation Name | XX.XX.XXXX | Page 4
Sheet Title
Building Design & Construction
Project Name
Presentation Name | XX.XX.XXXX | Page 9
MARIPOSA ST
ILLI
NO
IS S
T
TERR
Y A
FRAN
COIS
BLVD
Previous Scheme - Conceptual Design April 2017
Mariposa Pump Station
Civic Design Review - Phase 1 | 06.19.2017 | Page 20
Exterior ElevationsSheet Title
Building Design & Construction
Project Name
Presentation Name | XX.XX.XXXX | Page 9
O 4’ 8’ 16’
WEST ELEVATIONEAST ELEVATION
SOUTH ELEVATION NORTH ELEVATION
FIRST FLOOR2’-0”
ROOF16’-0”
GRADE LEVEL0’-0”
T.O. PARAPET21’-0”
Mariposa Pump Station
Civic Design Review - Phase 1 | 06.19.2017 | Page 21
Materials Palette
18”12”
CONCRETE
METAL 1THE GARLAND COMPANY, INC. PEWTER
WEST ELEVATION
NORTH ELEVATION
LIGHT FIXTURE 2BEGA 66 852
LIGHT FIXTURE 1UNA UA
DIMENSIONAL METAL SIGNAGEPIN-MOUNTED
(DOORS, RAILING, FENCE, GATES)