MARDIE PROJECT PILOT EVAPORATION POND TRIAL · 2018-10-10 · • set the bund wall height of 4.2m...
Transcript of MARDIE PROJECT PILOT EVAPORATION POND TRIAL · 2018-10-10 · • set the bund wall height of 4.2m...
MARDIE PROJECT PILOT EVAPORATION POND TRIAL
APPENDIX 3A (PROPOSED ACTIVITIES)
WORKS APPROVAL APPLICATION: CATEGORY 14:
AUGUST 2018
1 SYNOPSIS
This document presents information required for:
An application for a Works Approval for a Category 14: Solar salt manufacturing: premises on
which salt is produced by solar evaporation.
This document has been prepared for submission to the Department of Water and Environmental
Regulation.
Table of Contents
1 Synopsis .................................................................................................................. 2
1 Premise Details ....................................................................................................... 1
1.1 Applicant / Occupier Details .................................................................................... 1
2 Introduction ............................................................................................................. 1
2.1 Project .................................................................................................................... 1
2.2 Purpose .................................................................................................................. 1
3 Premise Details ....................................................................................................... 2
3.1 Legal Land Description ........................................................................................... 2
3.2 Prescribed Premise Location and Coordinates ....................................................... 3
4 Description of Existing Environment .................................................................... 6
4.1 Flora and Vegetation .............................................................................................. 6
4.2 Fauna and fauna habitats ....................................................................................... 7
4.3 Geology .................................................................................................................. 7
4.4 Topography and Soils ............................................................................................. 8
4.5 Climate ................................................................................................................... 9
4.6 Surface Hydrology ................................................................................................ 11
4.7 Ground Water ....................................................................................................... 12
5 Stakeholder Engagement ..................................................................................... 12
6 Prescribed Premise Category .............................................................................. 13
6.1 DWER Approvals .................................................................................................. 13
6.2 Documents associated with this proposal ............................................................. 13
6.3 Other Relevant Licenses / Permits ....................................................................... 14
6.3.1 DMIRS ..................................................................................................................... 14
6.3.2 Local Government ................................................................................................... 14
7 Proposal Description ............................................................................................ 15
7.1 Trial Evaporation Pond Project Objectives ........................................................... 15
7.2 Scope and scale of proposed activities ................................................................. 15
7.2.1 Key Characteristics .................................................................................................. 15
7.3 Pilot Evaporation Project Location ........................................................................ 16
7.4 Pilot Evaporation Ponds ....................................................................................... 18
7.4.1 Size ......................................................................................................................... 18
7.4.2 Construction Method ................................................................................................ 19
7.4.3 Source of Construction Materials ............................................................................. 20
7.4.4 Operational Management Plan ................................................................................ 21
7.5 Key Infrastructure & Equipment ............................................................................ 22
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 4
7.6 Unique processes to be tested ............................................................................. 22
7.7 Conservation Areas .............................................................................................. 22
7.8 Sensitive Receptors / Separation Distances ......................................................... 23
7.9 Commissioning ..................................................................................................... 23
8 Environmental management ................................................................................ 24
8.1 Process Emissions ............................................................................................... 24
8.2 Gaseous and Particulate Emissions ..................................................................... 24
8.3 Dust Emissions ..................................................................................................... 24
8.4 Odour Emissions .................................................................................................. 25
8.5 Noise Emissions ................................................................................................... 25
8.6 Discharges to Water ............................................................................................. 25
8.6.1 Stormwater Control / Emissions ............................................................................... 25
8.6.2 Surface Water Management .................................................................................... 25
8.7 Discharges to Land ............................................................................................... 26
8.8 Solid and Liquid Waste Management ................................................................... 27
8.9 Light Emissions ..................................................................................................... 27
8.10 Hydrocarbon/Chemical Storage ............................................................................ 28
8.11 Contaminated Sites .............................................................................................. 28
8.12 Other Emissions and Discharges .......................................................................... 29
9 Incident Response ................................................................................................ 29
9.1 Seawater Spill Response ...................................................................................... 29
9.2 Incident Response ................................................................................................ 29
9.3 Complaints ............................................................................................................ 30
10 Risk Assessment .................................................................................................. 31
10.1 Risk Assessment Process .................................................................................... 31
11 Cost of project ....................................................................................................... 32
12 Appendix ................................................................................................................ 33
Mardie Project – Pilot Evaporation Pond Trial 1
1 PREMISE DETAILS
1.1 Applicant / Occupier Details
The occupier (Company) of the land subject to this Works Approval application / Licence to
Operate application is:
Mardie Minerals Pty Ltd
ACN: 152 574 457
Level 1, 15 Rheola Street
West Perth, Western Australia.
Mardie Minerals Pty Ltd is a wholly owned subsidiary of BCI Minerals Limited (ABN 21 120 646
924).
The contact person for this Works Approval application is:
Mr Michael Klvac
General Manager Corporate Affairs
BCI Minerals Limited
Phone: +61 8 63113406
Mobile: 0438 268 877
Fax: +61 8 6311 3449
Email: [email protected]
Mardie Project – Pilot Evaporation Pond Trial 1
2 INTRODUCTION
2.1 Project
The Mardie Project aims to produce 3.5 million tonnes per annum (Mtpa) of high purity industrial
grade sodium chloride (salt) from seawater via solar evaporation, crystallisation and raw salt
purification. Through the crystallisation and processing of remaining bitterns, the Project will also
produce 75 thousand tonnes per annum (ktpa) of fertiliser grade SOP.
This trial program of works is to construct a nominal 1:10,000 scale system of ponds and
crystallisers to confirm the evaporation rates at each stage of the solar evaporation process on the
site at the same time recording atmospheric conditions and to prepare raw salts for pilot scale
processing off-site.
2.2 Purpose
The purpose of this document to apply for a Works Approval (WA) under Part V of the
Environmental Protection Act 1986 as prescribed under Section 54(1)(a) and Section 57(1)(a)
respectively of the Environmental Protection Regulations 1987,. This document therefore provides
the necessary information to support:
1. An application for a Works Approval; Category 14: Solar salt manufacturing: premises on
which salt is produced by solar evaporation under Schedule 1, Part 1 of the Environmental
Protection Regulations 1987
The WA Category 14 capacity being applied for is outlined in Table 1 below.
Table 1 WA and LTO Design Capacities
Category Number Category Description Production or Design
Capacity
14
Solar salt manufacturing:
premises on which salt is
produced by solar evaporation
NaCl 350 tpa
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 2
3 PREMISE DETAILS
3.1 Legal Land Description
The Project is owned 100% by Mardie Minerals Pty Ltd, a wholly owned subsidiary of BCI Minerals
Limited (BCI). The current tenement status is shown on Table 2.
Table 2- List of Mardie Tenements
Tenement Id Area (km2)
Current Holder Application
Date Grant Date Expiry Date
E08/1849 134.4 Mardie Minerals Pty Ltd 22-Feb-08 21-Nov-08 20-Nov-18
E08/2741 60.8 Mardie Minerals Pty Ltd 24-Jun-15 10-Feb-16 09-Feb-21
The tenements are indicated regionally on Figure 1, which also includes the native title claim
areas. The tenement overlies the Mardie Pastoral lease (Crown Lease CL453-1984) owned by
Citic Pacific Limited.
Current access to the site is from Northwest Coastal Highway and then the Mardie Station access
track.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 3
Figure 1- Mardie Tenements Regional Location
3.2 Prescribed Premise Location and Coordinates
The proposed premise is located in Western Australia’s Pilbara coast, midway between the towns
of Dampier and Onslow. Current access to the site is from Northwest Coastal Highway and then
the Mardie Station access track. See Figure 2 for details of the actual premise boundary.
Mardie Project – Pilot Evaporation Pond Trial 4
Figure 2 Proposed Prescribed Premise Boundary
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 5
Figure 3 – Proposed Pilot Evaporation pond boundary
Mardie Project – Pilot Evaporation Pond Trial 6
4 DESCRIPTION OF EXISTING ENVIRONMENT
4.1 Flora and Vegetation
A total of 17 land cover types have been mapped for the Mardie Project, including 14 terrestrial
vegetation types. The Mardie Project is dominated by unvegetated algal mat and mudflat/salt flats.
The Trial Pond study area is also dominated by unvegetated mudflat/saltflat (Figure 3a) and to a
lesser extent Spinifex (Triodia spp.) steppe (Figure 3b), Prosopis (mesquite) shrubland (Figure 3c)
and Shrublands over Triodia spp. grasslands (Figure 3d). Mesquite is a Weed of National
Significance (WoNS) and the mesquite infestation at Mardie station is recognised as the largest
single infestation in Australia (Astron 2014; NHT 2003).
Figure 4 Vegetation types present within the Trial Pond study area
More detail on flora and vegetation can be found in the report prepared by Phoenix Environmental
Sciences (Attachment 4A)
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 7
4.2 Fauna and fauna habitats
Fourteen fauna habitats (Table 3) have been recognised for the Mardie Project, including four within
the Trial Pond study area. Fauna habitat within the Trial Pond study area is also dominated by
mudflat/saltflat, spinifex grassland and Prosopis shrublands (Figure 3). None of these habitats are
restricted within the Mardie Project or indeed regionally.
Table 3 Fauna habitat types Mardie Project and Trial Pond study areas
More detail on fauna and fauna habitats can be found in the report prepared by Phoenix
Environmental Sciences (Attachment 4A)
4.3 Geology
Regional geology is well mapped and as part of the Mardie Project detailed investigations have been
undertaken within the project area. The white area is clay to surface with or without a salt crust. The
light is unconsolidated alluvium consisting of beach sands and fine gravels. The Orange area is an
alluvium of clay, gravels and fine sands interspersed. The materials are loosely agglomerated in
some zones.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 8
Figure 5 - Geology Map of Area
4.4 Topography and Soils
The area is very flat between 1.25m and 2.0m AHD over the entire mud/salt flats. Within the flats
the occasional island rises to a nominal RL of 4.4m AHD, the eastern edge of the mudflats
presents as a rise to approximately 4.5m AHD.
Figure 6 is a photo of the Error! Reference source not found. proposed pilot evaporation trial pond
area. The photo was captured from the raised island which is nominally 2m above the brown/white
clay. The gray scree consists of loose gravel rocks which overlay brown clays. The hypersaline
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 9
ground water is approximately 500mm below the clay surface. The quad bike tracks indicate the
direction of the proposed access track, in the distance on the slightly raised ground is a mixture of
spinifex and the declared pest (C2 control classification, DPIRD 2018) Prosopis sp1. (Mesquite).
Figure 6 - Proposed pilot evaporation pond area
4.5 Climate
The Mardie regional climate is classed by the Bureau of Meteorology (BoM) as ‘Grassland’
characterised by year-round hot weather. Rains occur predominately in the first half of the year
with summer rainfall related to tropical lows including cyclones and ex-tropical cyclones. Winter
rains are typically the result of the northern extent of large southern fronts. The Mardie Project has
undertaken detailed analysis of the BoM data and installed in wet and dry bulb temperature
loggers within the project footprint. Figure 7 indicates the long term mean rainfall and evaporation.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 10
Figure 7 - Monthly Mean Rainfall and Evaporation
Figure 8 indicates the long term monthly mean maximum and minimum temperatures and the wind
speed at 9.00am and 3 pm.
Figure 8 - Mean Monthly Max, Min temperature and wind speed
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 11
Wind roses for 9:00am and 3:00pm at Mardie Station are shown on Figure 9. These indicate
morning Southerly to Easterly winds followed by afternoon Westerly to Northerly winds. The winds
will on average change the air over the solar ponds every 30 minutes reducing the impact of the
ponds on local relative humidity.
Figure 9 - Mardie Station Wind Roses
Figure 10 - Australian pan evaporation data
4.6 Surface Hydrology
A surface hydrology study has been completed as part of the Mardie Project Prefeasibility study.
The work included:
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 12
• a hinterland drainage study based on storm events and the impacts on the project area
• coastal inundation study based on tidal inundation of the project footprint.
The results of these studies have been used to:
• set the bund wall height of 4.2m AHD for a ARI of 1:100 year
• select the rock armor for bund wall protection, and
• design the project to allow east-west movement of flood waters without impacting the
Mardie project.
The studies have been used to select the site for the trial ponds ensuring that the ponds area
protected from both land and sea inundation and the site infrastructure is installed above the
maximum flood level.
The proposed pilot evaporation ponds have been situated on the east side of a mud flat island with
a 4.2m AHD high bund wall around the outside perimeter that will protect the ponds from storm
surge. Surface water from the east will flow around the pond structure and out onto the mud flats.
4.7 Ground Water
Samples of water from the mud flats have been collected and analysed which confirmed the water
table is between 0.3m and 0.8m below the surface the with salinity varying between 130,000uS/cm
and 210,000uS/cm, or up to 3 times the salinity of Mardie seawater which averaged 69,000 uS/cm.
No impact to the ground water is anticipated from a seawater pipeline leak because the mudflats
are regularly inundated by seawater at high tide.
No impact to the ground water salinity is anticipated from the pond area from seepage because:
• Ponds P1 to P7 are unlined and contain concentrated sea water which averaged will not
exceed the salinity of the underlying ground water.
• Pond P8 and all the crystallisers will be lined with a HDPE membrane preventing leakage.
5 STAKEHOLDER ENGAGEMENT
BCI has undertaken the following stakeholder consultation in regards to the Project with the
following stakeholders:
Table 4 Stakeholder Engagement
Stakeholder Discussion Outcome / Actions
Yaburara and Mardudunera People
Completed discussion with YM People CEO (Amanda Wheeler) regarding Project rationale, No objections were raised.
Completed heritage survey
Engaged in on-going discussions
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 13
Shire of Roebourne/City of Karratha
General discussion outlining the Project rationale and implementation activities. No objections were raised.
Initial discussions completed
DWER – EPA
Email discussion held regarding approvals required for the Pilot Evaporation Pond Trial Project. No approvals required under Part IV of EP Act. Discussion held with Vanessa Robinson and Peter Tapsell.
Discussion regarding applying for works approval and applying for Licence to Operate (LTO)
BCI to discuss project with DWER and DMIRS to gain Part V approval and Mining Act Approval
DMIRS
Overview of Mardie Project given and overview of trial pond project.
Agreed that work could be completed under a POW-E and Part V EP Act Approvals.
Discussion held with Danielle Risby and Matt Boardman
BCP to submit a POW and accompanying letter to Matt Boardman
Mardie Station On-site meetings, telephone and email discussions
Pilot evaporation pond works scheduled to minimise impact on station, Access through the station agreed with map signposting and instructions prepared.
Pilbara Mesquite Management Committee
Control of impacted mesquite during clearing, construction and operation
Works will use best practice clearing and control methods.
No objections or concerns were raised by any of the above stakeholders, providing the appropriate
approvals are granted. Please refer to Section 6.3 Other Relevant Licences/Permits for more
information on additional approvals.
6 PRESCRIBED PREMISE CATEGORY
6.1 DWER Approvals
No Part IV approvals required. Part V of EP Act approvals outlined in this submission
6.2 Documents associated with this proposal
The following documents related to the Project are outlined in the table below and are available on request.
Table 5 Site Surveys and assessments
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 14
Factor Study area Study effort
Vegetation Full Project and trial ponds Two-season, Level 2 survey. Local impact assessment report
Terrestrial Vertebrate Fauna
Full Project and trial ponds Habitat assessments; targeted surveys
Full Project and trial ponds Habitat assessments; targeted surveys
ASS Full Project and trial ponds Static testing of drill samples, Leachate, waste fines and process liquor
6.3 Other Relevant Licenses / Permits
6.3.1 DMIRS
POW No. 75407 and PMP No. PM450-316706 have been submitted. The quantity of diesel and minor other fuels stored on site will not require a Storage of Dangerous Goods Licence (DGL).
6.3.2 Local Government
Any applicable Local Government approvals required will be obtained from the Shire of Roebourne prior to commencement of construction. The Project and the proposed operations outlined in this application will be constructed and operated in accordance with approvals issued under the Mining Act 1978. As such, this infrastructure will not be subject to the Planning and Development Act 2005 or any other local government planning by-laws.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 15
7 PROPOSAL DESCRIPTION
7.1 Trial Evaporation Pond Project Objectives
The purpose of the proposed works is to:
• confirm the evaporation rates at each brine density stage during solar concentration and
crystallisation;
• calibrate the results using recorded atmospheric conditions to long term BOM records;
• provide raw salt product samples for laboratory and pilot processing trials; and,
• produce samples of the resultant waste bitterns for characterisation.
7.2 Scope and scale of proposed activities
7.2.1 Key Characteristics
This works approval application relates to a pilot trial for the production of salt (NaCl), mixed
potassium salts for further processing into Sulphate of Potash (K2SO4) and waste bitterns for
characterisation.
Details of key characteristics relevant to Category 14 prescribed premises activities are
summarised in Table 6.
Table 6 - Key Characteristics
Project Element Description
Operational Purpose Pilot seawater solar evaporation trials
Location of Operations
Nominally 122km southwest of Karratha
Annual Production 350t of raw NaCl salt and 7.5t of mixed potassium and magnesium salts
Project Duration 24 months
Processing Method Solar evaporation of seawater
Tailings No tailings will be produced
Waste 60t of mixed NaCl and Magnesium salts
Reagents and Fuels
Diesel will be used to fuel the generators for supply of power and mobile equipment. Small amounts of unleaded fuel will be used in quad bikes used to access the seawater pump and periodically check the pipeline. No reagents will be used in the process.
Product Transport Product will be transported to Perth in 1 tonne bulka bags, IBC’s or sealed 20l plastic drums
Workforce 1-2 people, who will be accommodated at the local pastoral station or at Fortescue roadhouse village
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 16
Seawater abstraction Nominally 22,000m3 over 12 months
Other water requirements
Nil, provided via RO plant attached to pilot program
Power Requirements Nominal demand of 7.5 KVA provided by diesel generators for pumps and site laboratory
Estimated ground disturbance
3.2ha for the pond area. The sea water pipeline will be laid on the surface and removed on completion
7.3 Pilot Evaporation Project Location
The pilot evaporation trial access track will commence on a local station track at the north western
corner of E08/2740 and then continue north along the boundary of lease E08/1849 until it reaches
the trial site as indicated on Figure 11.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 17
Figure 11 - Pilot Evaporation Project Location
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 18
7.4 Pilot Evaporation Ponds
7.4.1 Size
The proposed trial evaporation ponds will be contained within a bunded area 180m long by 120m
wide as indicated in Figure 12.
Figure 12 - Pilot Evaporation Pond Layout
The disturbance area will extend up to 40m outside the bund wall for the purpose of operating a
dozer and grader, allowing sufficient room to level the area, remove gravel scree and obtain
natural clays for wall and pond floor construction.
Table 7 lists the pond dimensions.
P5
P1
P2
P6
P7 P8C1 A
C2 A
C3 C4
C5C6
C7 C8 C9 C10
C11
Seawater
150
m
P3 P4
P
P
C2 B
C1
B
Lab
Store
Ge
n
Pan evaporators
Access track
160 m
P
P
Generator , RO Plant, fuel
natural island bank, 2.5m high
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 19
Table 7 - Pilot pond internal dimensions
The flat top of pond walls will be 2m wide with access ramps formed to allow safe operating access.
7.4.2 Construction Method
The area selected is within the proposed crystalliser area of the Mardie project and the intention is
to use and test local materials to validate broad area geotechnical testwork completed during the
Prefeasibility study. The bund wall construction consists of:
• Removal of highly permeable gravels from the surface and covering underlying clay
nominally 400-700mm below the surface.
• Construction of a bund wall clay core from the exposed clay base nominally 2m high
Pond Length
(m) Width
(m) Area (m2)
Fill Volume (m3)
P1 50 26 1292 650
P2 50 29 1457 730
P3 50 26 1300 650
P4 40 25 1000 500
P5 40 23 924 460
P6 40 12 482 250
P7 20 15 305 150
P8 18 12 209 100
C1 20 19.5 390 195
C2 20 19.5 390 195
C3 10 7.3 73 37
C4 10 6.6 66 33
C5 10 6.1 61 31
C6 10 5.3 53 27
C7 10 4.6 46 23
C8 10 7.2 72 36
C9 10 11.5 115 58
C10 10 11.6 116 58
C11 10 9.6 96 48
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 20
• Cover of the clay core using local gravels and fines materials blended to from a
compactable general fill material
• Lining of the outside of the bund wall with locally won light weight rock armour.
The internal pond walls for ponds P1 to P7 will be constructed similar to the external wall with the
top of wall height nominally 1m lower.
Crystallisers C1 to C11 will be lined with 1mm HDPE to allow the precipitated salts to be collected
for analysis.
Figure 13 indicates the proposed bund wall cross section and internal pond walls.
Figure 13 - external bund wall and internal pond wall sections
Pumps and weirs are located to control the flow of brine between the ponds. There are placed to
represent to proposed full scale operation.
The pan evaporators will be fabricated from stainless steel to BOM specifications and placed on
timber pallets.
7.4.3 Source of Construction Materials
Geotechnical work completed during the PFS and subsequent site inspection indicates the
selected site will have gravel/sand scree up to 600mm deep overlaying clay. The scree will be
graded into a stock pile windrow and blended and used as general fill to construct the bund wall.
Underlying clays will be excavated and used to build the clay core.
Clay Core
Compacted road base
General fill
Rock armor layer
Gravel Layer - removed to underlying clay to form core seal
1.4m0.5m
Average water level
Internal wall
Underlying Clay
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 21
Around the raised dune there is loosely agglomerated rock, which is proposed for the bund wall
armour rock. The material will be extracted using mechanical equipment without the need for
explosives.
7.4.4 Operational Management Plan
The Mardie Project pilot test work program has been developed to validate key PFS assumptions including:
• Collection of detailed weather parameters on a 30 minute interval basis
• Analysis of site specific evaporation rates for evaporation ponds and crystallisers
• Confirm civil construction techniques
• Produce crystallised salt samples for salt purification and SOP process plant testwork; and
• Produce raw salt product samples.
Once the ponds have been constructed seawater from the ocean will be pumped into ponds P1 to
P8 filling them to a depth of 500mm. As evaporation occurs brine densities will increase in each
pond. As each pond density reaches its design density it will be maintained by transferring brine
from up and down stream ponds which will be representative of the proposed continuous flow
design incorporated in the Mardie Project eight pond concentrator system. Pond 8 will have a brine
density just lower than when NaCl begins to precipitate. At this point it will be transferred into
Crystallisers where in C1 and C2 high purity NaCl is precipitated. The layout indicated two parallel
C1 and C2 Crystallisers. This is to allow 50% of the crystalliser to be drained to C3 and allow the
NaCl to be dry harvested by hand and using a bobcat. This will be representative of the high purity
raw salt from the proposed Mardie Project.
The brine is then transferred to the down stream crystallisers C3 to C11 and will follow the same
process. Because the volumes are much reduced a single crystalliser is proposed at the stage.
The precipitated salts at each crystalliser stage will be representative of the proposed Mardie
Project solar evaporation stages.
The continuous flow of brine through the ponds and crystallisers will be monitored daily and
seawater added into pond P1 to retain pond levels. This will be completed using a small
submersible electric pump and nominal 4.8km long 75dia HDPE pipeline.
After 12 months operation the predicted tonnes of salts listed in the key characteristics will be
produced.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 22
The control pan evaporators will be filled with brine artificially concentrated (using heat lamps in a
laboratory) to the design density of each pond and crystalliser. Daily the net evaporation will be
recorded in each pan and the pan will be filled to the original starting level.
7.5 Key Infrastructure & Equipment
The key infrastructure associated with and supporting the proposed pilot trial ponds includes:
• Laboratory sea container and test equipment – used to complete daily site tests for each
pond brine to ensure that the system is operating within proposed design tolerances.
• Storage sea container – used to store tools and maintenance equipment.
• Diesel powered generator and bunded fuel tank – used to provide power to the laboratory
equipment and room and brine pumps.
• Seawater pump, local diesel generator and 4.8km 75mm dia HDPE pipeline.
• Water tanks – for storage of seawater ready for decant into pond 1 and to supply the RO
plant.
• Nominal 20 l/hr self-contained reverse osmosis for provision of fresh water to fill pan
evaporators, operate the laboratory and general washdown.
• Fresh water storage tank and dispensing pump.
• Mobile equipment – bobcat for minor pond maintenance, quad bike for seawater pump
and pipeline operation, 4WD vehicle for general use and out-loading of raw salts.
• Portable pump used as standby for pond to pond transfers and storm water management.
7.6 Unique processes to be tested
The pilot trials will test the solar evaporation of seawater to a brine density of 1.328, well past the
density of bitterns discharged from solar pond operations along the Western Australian coast,
which are typically around 1.25. Between the density of 1.25 and 1.328 little work has been
completed for coastal salt operations and this will be a unique process. This kind of evaporation
work has never been completed for the Mardie area and even fresh water pan evaporation records
are not included at the Mardie BOM site.
7.7 Conservation Areas
The Project area is not located within:
• an Environmentally Sensitive Area (ESA) as listed under the Environmental Protection
(EP) Act 1986.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 23
• a ‘specified ecosystem’ as described in the Department of Environment Regulation
(DER), Environmental Siting Guidelines (2016)
• Conservation Reserve/ DBCA managed land (including Threatened or Priority
Ecological Community), Ramsar Site, Significant/ Nationally Important Wetland or a
Bush Forever Site. The nearest known specified ecosystem is Fortescue River delta.
This specified ecosystem is not proposed to be impacted by pilot trial ponds
development or disturbance foot print.
7.8 Sensitive Receptors / Separation Distances
No Threatened Ecological Communities (TECs) or Priority Ecological Communities (PECs) occur
within, or adjacent to the trial pond survey area. The only potential sensitive receptor within the
vicinity of the Project is the Mardie Pastoral station accommodation facilities for the Project
construction and operational employees and contractors.
During construction and initial operations of the trial pond, employees and contractors will be
accommodated at the Fortescue Roadhouse, approximately 35km from the proposed premises.
The EPA Guidance Statement 3. Separation Distances between Industrial and Sensitive Land
Uses (EPA 2005) doesn’t delineate a separation distance for salt evaporation activities. However,
Appendix 1, Table 1 did determine that there is a ‘Specified Ecosystem’ across the project area;
namely # 31. Acid Sulfate Soils (ASS) Risk Area (map, Pilbara Coastline Department of
Environment Regulation). An assessment for ASS was undertaken by Stantec (Stantec, 2017),
conducted in accordance with the Department of Environment Regulation (DER) 2015 Guidelines
for Identification and Investigation of Acid Sulfate Soils and Acidic Landscapes (DER, 2015). The
outcome of the assessment determined that due to the low ASS risk of surface soils within the
Project area, further investigations into the presence of ASS is not considered necessary, unless
disturbance is planned at greater depths (>1 mbgl). Therefore, no risk from ASS is expected due to
construction or operational activities of the proposed test ponds.
Furthermore, BCI will ensure that the proposed premise location will not impact sensitive receptors
within the Project locality, i.e. Mardie Station.
During operations, all employees and contractors for the Project will be accommodated at the
abovementioned Fortescue Roadhouse.
7.9 Commissioning
It is requested that commissioning of the trial ponds be undertaken under the Works Approval and
prior to submission of the required Compliance Document and granting of a Licence to enable
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 24
various components to be trialed and tested. This will enable testing of equipment whilst the
licence is being assessed.
Commissioning will consist of two stages, pre-commissioning and load commissioning and is
expected to take a maximum of three months. Pre-commissioning will consist of the electrical and
mechanical testing of the equipment. This will involve running or live testing all items of equipment
to confirm that they operate as per their intended function.
The system will then go through the load commissioning stage; namely the test ponds will be
operated to test and confirm all control functions including pumps and generators are working
correctly.
8 ENVIRONMENTAL MANAGEMENT
Emissions, Discharges and Waste will be responsibly managed as described in the following
sections.
8.1 Process Emissions
There are no planned process emissions from the pilot evaporation pond trials.
The pilot evaporation pond trials will use solar evaporation to reduce seawater to solids and a
small residue brine. The solid salts will remain in each pond forming part of the seepage and
bearing capacity testwork. Solids for off-site testwork will be dry harvested and placed in drums for
transport to laboratories. The residue liquor will be transferred to containers and be analyzed off
site for potential byproducts.
8.2 Gaseous and Particulate Emissions
Diesel generators will be used at the seawater pump and pilot evaporation ponds to generate
electrical power. The estimated operating demand at the seawater pump is 1.8kW and at the Pilot
evaporation ponds is 4.2 kW. Based on the manufacturers energy consumption and emissions
data the resultant emission of CO2 will be 3.4kg/hr, estimated to be 34kg of CO2 per day.
8.3 Dust Emissions
The Project will be situated a minimum of 9km away from Mardie Station. Based on the
configuration of the operations, there are no significant environmental receptors that are likely to
be affected by any dust that is generated through the Project activities.
Water trucks will be used on roads to suppress dust, if required. Visual dust monitoring will be
used to confirm that controls are effective or as a basis for implementing corrective action.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 25
8.4 Odour Emissions
The Project will not emit any odour.
8.5 Noise Emissions
Water pumping activities, and power generation, will produce additional noise levels. However,
given that there are no sensitive receptors in proximity to the Project noise is not expected to be an
issue.
BCI understands that the Environmental Protection (Noise) Regulations 1997 apply. BCI will:
• Use equipment, machines and vehicles that would be the quietest, reasonably
available, consistent with operational requirements that would be routinely maintained
to ensure the effectiveness of noise suppression systems and equipment.
• Inform all personnel (including contractors) through site inductions of their
responsibilities and the importance of managing noise levels during the construction
phase and ongoing operations.
All construction and operations will be expected to comply with the Environmental Protection
(Noise) Regulations 1997 (noting that Clause 13 of the Regulations covers construction noise and
how it is managed through the Regulations).
8.6 Discharges to Water
There will be no discharges to water from the Project. The Project is regularly inundated with
seawater, so any potential discharges will be diluted.
8.6.1 Stormwater Control / Emissions
Rain falling directly into ponds will naturally evaporate. Rain falling inside the perimeter bund but
outside the ponds will evaporate or seep into the ground, identical to the current natural situation.
Should an unusual or extreme rain event occur water collected in the pond area will gravitate to a
sump where it will be tested before it is pumped over the bund wall into the environment, in this
type of extreme event the entire Mardie region is likely to be flooded and the mudflats under water.
8.6.2 Surface Water Management
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 26
The Pilot Evaporation ponds have been located against an existing naturally formed raised island
on the mud flats. The mud flat component is periodically inundated via two mechanisms:
• Tidal cycles, and
• Extreme rainfall events (cyclones).
Under normal tide cycles the area will be inundated for short periods on the highest tides several
times per month. The depth of seawater at hightide will not exceed 100mm unless there is an
extreme storm surge associated with the high tide. Measures to protect against an extreme event
include:
• construction of a perimeter bund wall with a top level set at the calculated 1:100 ARI.
• positioning of the ponds to the east side of the naturally occurring island away from direct
impact of ocean storm events,
• protection of the outside of the perimeter bund wall with rock material, to protect against
erosion
• installation of supporting infrastructure on the top of the island above the inundation level
of an extreme event
• installation of the seawater pump generator on raised ground above the calculated storm
inundation water level.
An extreme rainfall event can be associated with a cyclone. In these events surface water can flow
from the higher land to the east down onto the mudflats. The pilot evaporation ponds have been
positioned to allow any surface flow to pass along the natural creek lines either side of the
perimeter wall. Rock protection has been included to eliminate wall erosion.
Management measures will include:
• Any evidence of erosion, disturbance to natural drainage flow or impact on vegetation
must be reported to the Project Manager and be remediated as required;
• Site surfaces will be shaped to allow for natural drainage and to avoid pooling or
ponding on site;
• Disturbance will be minimized.
8.7 Discharges to Land
There will be no discharges to land from the Project.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 27
8.8 Solid and Liquid Waste Management
Solid and liquid wastes generated from construction and ongoing operations may include:
• Inert wastes such as glass, paper, cardboard, wood, bricks, concrete, plastics, scrap
metal, obsolete or expired equipment (e.g. transformers, pumps and pipes);
• Domestic waste including the generation of putrescibles (e.g. kitchen scraps), non-
recyclable packaging and non-hazardous liquids;
• Sewage and wastewater from toilets and onsite ablutions; and
• Hydrocarbon waste generated from fuel spills.
BCI has an obligation to manage waste disposal in accordance with the Environmental Protection
Regulations 1987 and the Environmental Protection (Controlled Waste) Regulations 2004. These
regulations govern the general control of pollution and outline obligations regarding the
transportation and disposal of ‘controlled’ wastes.
BCI will implement the following management measures in regards to waste storage and disposal:
• Disposing of putrescible and inert waste to an appropriately licensed facility (off site),
• Collecting and treating ablution effluent prior to removal from site by approved
controlled waste carrier; and
• Maintaining and servicing equipment regularly.
8.9 Light Emissions
Additional lighting will be required to service the Project. Given the distance to the nearest
sensitive receptor, nuisance light is not expected to be an issue. There is potentially some impact
to local fauna from additional light emissions.
Managing impacts of light overspill on fauna during construction and operations will be conducted
through the implementation of the following management strategies:
• All external lighting will be targeted where possible, using shields and directional
lighting to minimise light spill beyond the required work area; and
• External lighting will use, where possible, red or low pressure sodium lights. Bright
white lights such as mercury vapour, metal halide or florescent will be avoided where
possible.
The design of these systems will be such that light spill to the surrounding environment will be
minimised as far as practicable.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 28
8.10 Hydrocarbon/Chemical Storage
The design and construction of tanks, pipes and bunding will comply with all relevant regulations
under the Dangerous Goods Act 2004 (WA) to prevent and/or manage spills. Hydrocarbons and
chemicals will be stored in bunded areas. The bund will be constructed in an impervious material
to comply with Australian Standard (AS) 1940 – 2004 ‘The Storage and Handling of Flammable
and Combustible Liquids’ with a minimum retention capacity of 110%. Bunded areas will be
regularly maintained by inspecting the integrity of the bund, regularly cleaning out of the bund and
checking that any valves are sealed and kept in the closed position;
The following measures are proposed to be implemented to manage and mitigate potential issues
associated with hydrocarbon and chemicals handling during construction and operations at the
Project:
• Separation of hydrocarbon materials from other facilities and people, segregation from
stored dangerous goods, placarding, providing firefighting equipment at hydrocarbon
and chemicals storage and handling areas.
• Vehicles will be refuelled by a mobile fuel truck utilising drip trays;
• The diesel fuel will be pumped and not gravity fed into vehicles/generators and the
pump will be installed with a shut off device, so that the pump can be shut off in case of
an emergency. The shut off device will be easily accessible and clearly identified;
• The Project area will be equipped with spill kits and equipment that will be regularly
monitored and maintained. The kit will include sufficient quantities absorbent materials,
equipment for recovering spilled materials, containers for recovered materials and
personal protective equipment;
• In the case that a spill occurs, it will be reported immediately to the Site Manager and
the area around the spill will be isolated and mopped up using the spill response kit and
equipment;
• The waste from the spill will be stored separately and isolated, until the spill waste is
collected and disposed by a licensed contractor; and
• All site personnel will be made aware of the hydrocarbon management strategies
through training at inductions and ‘tool-box’ meetings.
8.11 Contaminated Sites
No known contaminated sites exist within the proposed premise boundary. The works proposed
are also unlikely to give rise to any contamination given the safeguards proposed in this document.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 29
8.12 Other Emissions and Discharges
There are no further anticipated impacts to groundwater, soil hygiene, visual impact, flora and
fauna as the result of the implementation of this proposed works approval and ongoing operations.
No increase in the risk of incidents which may cause harm to the environment (or personnel) is
anticipated to occur because of the installation and operation of the trial ponds that have not been
considered in the risk assessment (See Section 11 for more details).
All management of emissions and discharges will be considered in line with the surrounding
receiving environment and implemented in line with approval guidelines and associated industry
best practice.
9 INCIDENT RESPONSE
9.1 Seawater Spill Response
Seawater could spill due to a leak in the seawater pipeline or a breach of the perimeter bund wall
and the internal pond walls.
A leak from the seawater pipeline is considered the most likely of the two events. Operational
protocols include a daily inspection. In additional the system has high and low pressure safety
switches and flow meter to confirm that the pump only operates when required and when the pump
is operating that water is flowing into the storage tank. The method of control will limit the volume
of a spill and corrective action would be undertaken to fix a leak if one occurs. The pipeline route
is across the mudflats which are inundated by seawater several times per month at high tide and
wherefore a small leak is unlikely to have any impact.
A breach of the perimeter bund wall has been considered by the project risk committee as the
major cause of a potential breach is a result of a severe cyclone where the damage is cause by
excessive wind and a storm surge at high tide. The bund wall design has been designed to protect
against a 1:100 ARI event. The response to the cyclone is to evacuate area project until it is safe
to return. I full evaluation of the project would be undertaken on return to the site and corrective
measures instigated.
9.2 Incident Response
If a potential pollution incident occurs (e.g. hydrocarbons spill), the Site Manager will be notified,
the activity causing the problem will cease and an investigation will be initiated immediately. The
following corrective action will be taken as soon as practicable:
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 30
• Recording of the date, time and reason for the incident;
• Estimation of the period over which the incident occurred;
• Determination of the extent of the emissions or discharges over that period and
potential or known environmental consequences;
• Establishment and implementation of corrective action taken or planned to mitigate
adverse environmental consequences; and
• Establishment of a corrective action to prevent a recurrence of the incident.
The Site Manager will advise DWER within 24 hours of becoming aware of an incident which may
have resulted in emissions which exceeded works approval limits.
The Project will be equipped with spill kits and spill response equipment that will be regularly
maintained. The kits include absorbent materials, equipment for recovering spilled materials,
containers for recovered materials and personal protective equipment. In the event of a fuel or
chemical spill, the spill will be contained and the source will be isolated and recovered immediately
using absorbent materials, which will then be placed in disposable drums or containers onsite.
Any contaminated soil or absorbent material resulting from a fuel or chemical spill will be removed
by a licensed contractor to an authorised waste disposal site. Where necessary, validation
sampling will be undertaken to verify that all contaminated soil has been removed. All spills that
may cause a significant environmental impact will be reported to the DWER as soon as
practicable.
All site personnel will be trained in the site’s procedure to follow in the event of a hydrocarbon spill
Once the incident has been investigated, the Site Manager will advise DWER in writing of the
status of corrective actions implemented to address the problem.
9.3 Complaints
The Project will record any complaints in the BCI Complaints Register. If a complaint is received, it
is most likely to be from an adjoining landholder, either the pastoralist from Mardie Station or
another lease holder. Records of any correspondence and dealing with the complainant will be
maintained.
Should a complaint be received, the Project Manager will contact any complainants that have
concerns related to the environmental issues and determine the nature of the issue. The Project
Manager will take steps to ensure that any identified impacts are addressed. If the issue relates to
matters covered by the licence issued under Part V of the EP Act, the Project Manager will advise
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 31
DWER of a valid complaint and advise in writing the corrective actions implemented to address the
problem.
10 RISK ASSESSMENT
BCI has completed a risk assessment of the pilot test pond activities proposed under this works
approval application and is offered to assist DWER with its own assessment.
Information on the biophysical setting within which the trial would take place is provided in Section
7.
Selected technical studies used to prepare the “Existing Conditions” summary are appended to the
works approval as Attachments 3C1 and 3C2.
10.1 Risk Assessment Process
The risk process was sourced from DER Guidance Risk Assessments - Part V, Division 3,
Environmental Protection Act 1986 (February 2017).
A risk register with further details on inherent and residual risk assessments for construction and
operations of the Mardie trial ponds is presented in Attachment 8A of the works approval
application.
DWER – Works Approval Appendix 3A
Mardie Project – Pilot Evaporation Pond Trial 32
11 COST OF PROJECT
The estimated capital cost of the project is highlighted in Table XX
Cost of Facilities
Prescribed Premise Capital Cost
Mobilisation costs $30,000
Construction costs of ponds $325,000
Laboratory costs $125,000
Total costs $480,000
Mardie Project – Pilot Evaporation Pond Trial 33
12 APPENDIX
Appendix A - Mardie Trial Pond PoW Memo PhoenixEnvSci Appendix B - Stantec ASS Investigation