Managing contracts and relationships in procurement and...

7
D5/November 2014 Diploma in procurement and supply Managing contracts and relaonships in procurement and supply Date Monday 17 November 2014 Time Start 14:00 End 17:00 Duraon 3 hours QUESTION PAPER INSTRUCTIONS FOR CANDIDATES This examinaon has FOUR compulsory quesons worth 25 marks each. 1. Do not open this queson paper unl instructed by the invigilator. 2. All answers must be wrien in the answer booklet provided. 3. All rough work and notes should be wrien in the answer booklet. QP04

Transcript of Managing contracts and relationships in procurement and...

Page 1: Managing contracts and relationships in procurement and …zeritenetwork.com/wp-content/uploads/2018/12/D5_November...D5/November 2014 Diploma in procurement and supply Managing contracts

D5/November 2014

Diploma in procurement and supply

Managing contracts and relationships in procurement and supply

Date Monday 17 November 2014

Time Start 14:00 End 17:00 Duration 3 hours

QUESTION PAPERINSTRUCTIONS FOR CANDIDATES

This examination has FOUR compulsory questions worth 25 marks each.

1. Do not open this question paper until instructed by the invigilator.

2. All answers must be written in the answer booklet provided.

3. All rough work and notes should be written in the answer booklet.

QP04

Page 2: Managing contracts and relationships in procurement and …zeritenetwork.com/wp-content/uploads/2018/12/D5_November...D5/November 2014 Diploma in procurement and supply Managing contracts
Page 3: Managing contracts and relationships in procurement and …zeritenetwork.com/wp-content/uploads/2018/12/D5_November...D5/November 2014 Diploma in procurement and supply Managing contracts

Page 3 of 8 D5 Exam Questions November 2014

QUESTIONS

You are advised to spend 45 minutes on each question.

Q1 Describe FIVE sources of added value that can be achieved through supply chain relationships. (25 marks)

Q2 (a) Outline FIVE areas where the standard contract terms of a buyer and a seller are likely to be different. (15 marks)

(b) Explain the following in relation to non-performance of a contract:

(i) Substantial performance (ii) Acceptance of partial performance. (10 marks)

Q3 (a) Explain the role of ‘information assurance’ (IA) in managing contractual risk. (10 marks)

(b) Describe THREE tasks that might be undertaken by a contract manager as part of their contract administration duties. (15 marks)

Q4 (a) Explain THREE measures that might be included within a balanced scorecard. (15 marks)

(b) Explain ONE methodology for relationship assessment that can be employed by purchasers and suppliers. (10 marks)

END OF QUESTION PAPER

Page 4: Managing contracts and relationships in procurement and …zeritenetwork.com/wp-content/uploads/2018/12/D5_November...D5/November 2014 Diploma in procurement and supply Managing contracts

Page 4 of 8 D5 Exam Questions November 2014

BLANK PAGE

Page 5: Managing contracts and relationships in procurement and …zeritenetwork.com/wp-content/uploads/2018/12/D5_November...D5/November 2014 Diploma in procurement and supply Managing contracts

Page 5 of 8 D5 Exam Questions November 2014

BLANK PAGE

Page 6: Managing contracts and relationships in procurement and …zeritenetwork.com/wp-content/uploads/2018/12/D5_November...D5/November 2014 Diploma in procurement and supply Managing contracts

Page 6 of 8 D5 Exam Questions November 2014

BLANK PAGE

Page 7: Managing contracts and relationships in procurement and …zeritenetwork.com/wp-content/uploads/2018/12/D5_November...D5/November 2014 Diploma in procurement and supply Managing contracts