MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

16
Reducing Engine Room Overhauling Height Using an MAN B&W Double-Jib Crane

Transcript of MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

Page 1: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

Reducing Engine RoomOverhauling HeightUsing an MAN B&W Double-Jib Crane

Page 2: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...
Page 3: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

Content

Introduction .................................................................................................5

Working Principles .......................................................................................6

Required Overhauling Heights and Crane Capacities .....................................8

Further Reductions of Required Overhauling Height ......................................9

Lifting Procedures for Main Components of the Engine ............................... 10

Exhaust valve ....................................................................................... 10

Cylinder cover complete with exhaust valve ........................................... 10

Piston with rod and stuffing box ............................................................ 11

Cylinder liner with cooling jacket ................................................................................11

Closing Remarks ........................................................................................ 12

Page 4: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...
Page 5: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling Crane 5

MAN B&W Double-Jib Crane Low-headroom Engine Overhauling Crane

Introduction

In the process of selecting engines for a

ship, the height required for overhauling

purposes is a significant parameter.

For a normal single hook engine room

crane, the total building-in height re-

quired for the engine in an engine room,

measured from the centreline of the

engine’s crankshaft to the underside of

the deck beam, depends on the:

� height from the crankshaft to the lift-

ing point in the overhauling tool at-

tached to the component to be over-

hauled,

� necessary additional height for com-

ponent withdrawal,

� height from the crane hook to the

deck beam with the crane hook in

the top position (building-in height of

the engine room crane).

In the late 1970s, MAN Diesel & Tur-

bo in Copenhagen conducted an inve-

stigation into the building-in heights of

engine room cranes, and found that,

at that time, all engine room cranes

on the market required far too much

headroom.

We therefore decided to develop a par-

ticularly low-headroom crane, for which

we were granted patents in many coun-

tries. The further development of this

crane led to the ‘MAN B&W double-jib

crane’.

Fig. 1: MAN B&W double-jib crane installed on board

Page 6: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling Crane6

Working Principles

The MAN B&W double-jib crane is

equipped with two crane hooks and is

designed to match the standard over-

hauling tools for the engine. The hoist

arrangement for each hook is carried

by a separate beam.

The crane offers ample space between

the beams for the components to be

overhauled. Fig. 1 shows an MAN B&W

double-jib crane installed on board a

ship.

When both crane hooks are used, they

are attached to the overhauling tool at

a position well below the top of the en-

gine component to be overhauled, so

that the top of the component can be

lifted above the crane hook, up through

the crane structure.

When pistons are pulled, they can be

lifted right up to the underside of the

deck beams, thus utilising the entire

engine room height. Records show that

the time it takes to overhaul a cylinder

unit using the double-jib crane is the

same as with a conventional crane.

In order to ensure the availability of

cranes built to our quality standards at

a competitive cost, we have signed an

approbation agreement with the spe-

cialist company Danish Crane Building

A/S.

Today, Danish Crane Building both

manufactures and markets the above-

mentioned concept.

The installation dimensions of the MAN

B&W double-jib cranes appear in Figs.

2 and 3.

Working Principles

The MAN B&W Double-Jib Crane isequipped with two crane hooks and isdesigned to match the standard over-hauling tools for the engine. The hoistarrangement for each hook is carriedby a separate beam. Between thebeams there is ample space for thecomponents to be overhauled. Fig. 1shows an MAN B&W Double-Jib Craneinstalled on board a ship.

When both crane hooks are used, theyare attached to the overhauling tool at

a position well below the top of the en-gine component to be overhauled, sothat the top of the component can belifted above the crane hook, up throughthe crane structure.

When pistons are pulled, they can belifted right up to the underside of thedeck beams, thus utilising the entireengine room height. Records showthat the time it takes to overhaul a cyl-inder unit using the double-jib crane isthe same as with a conventional crane.

In order to ensure the availability ofcranes built to our quality standards ata competitive cost, we signed an ap-probation agreement with the specialistcompany Danish Crane Building A/S.

Today, Danish Crane Building bothmanufactures and markets theabove-mentioned concept.

The installation dimensions of theMAN B&W Double-Jib Cranes appearin Figs. 2a, 2b, 3a and 3b.

4

D

Deck beam

Chain collecting box

LSmin/Smax

D

K

H

J

Am

in/A

max

C

Bmin/BmaxBmin/Bmax

EF

G

M

Fig. 2a: MAN B&W Double-Jib Crane – electrically operated, for dimensions see Fig. 3

The MAN B&W Double-Jib Crane ismanufactured and marketed by:

Danish Crane Building A/SPostbox 54, Østerlandsvej 2DK-9240 Nibe, DenmarkTelephone No.: +45 98 35 31 33Telefax No.: +45 98 35 30 33

Fig. 2a: MAN B&W double-jib crane – electrically operated

Page 7: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling Crane 7 5

90

Deck beam

Min/Max 1200/3300 350

Min/Max 1900/400090

750

350

240

10

250

250

750

Fig. 2b: MAN B&W Double-Jib Crane – manually operated, capacity 2 x 0.5 ton (for extremely low headroom, see page 10)

Fig. 3: MAN B&W double-jib crane – manually operated, capacity 2 x 0.5 ton

Page 8: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling Crane8

Required Overhauling Heights and Crane Capacities

Fig. 4 illustrates an engine room equip-

ped with a normal crane (on the left)

and one where the distance from the

centreline of the crankshaft to the un-

derside of the deck beam is too small

for a normal crane to be used (on the

right). The hatched area represents en-

gine room heights that require the use

of an MAN B&W double-jib crane in-

stead of a normal crane.

Dimension H3 in Fig. 4 is the mini-

mum building-in height required when

using an MAN B&W double-jib crane.

If an additional height (dimension D) is

available, it will be possible to pull up

the exhaust valve without removing any

exhaust valve studs.

It is important to note that dimension

H3 is measured from the centreline of

the crankshaft to the underside of the

deck beam, whereas dimension H1,

H2 (for the normal engine room crane)

is measured from the centreline of the

crankshaft to the crane hook.

Therefore, when comparing dimensi-

ons H, the building-in height of a nor-

mal engine room crane must be added

to the dimensions H1 and H2.

The capacities of the MAN B&W dou-

ble-jib cranes for the respective en-

gines, should be strictly observed.

The cranes are designed to match the

engine’s standard tools in all details, as

a specially designed supplement to the

range of engine overhauling tools, and

their design is continuously being up-

dated along with the tools they match.

If, for example, a larger crane capacity

than that specified for a certain engine

type were selected, this would involve

a risk that the crane hook dimensions

and chain angles might not fit the tools

for the engine.

To guard against any mishaps in the

event of such an attempt being made,

the crane is equipped with a slip-cou-

pling that will prevent it from lifting.

The crane hook travelling area must co-

ver at least the full length of the engine

and a width in accordance with dimen-

sion A given on the drawing, see the

cross-hatched area.

It is furthermore recommended that

the engine room crane can be used for

transport of heavy spare parts from the

engine room hatch to the spare part

stores and further on to the engine.

The crane hook should at least be able

to reach down to a level correspond-

ing to the centreline of the crankshaft.

MAN B&Wdouble-jibcrane

Normalcrane

Deckbeam

Centrelinecrankshaft

H3

1)

Centrelinecrankshaft

Deckbeam

Deck

Deck

H1/

H2

1)

A A

D2)

1) With minimum overhauling height (H1, H2, H3), one cylinder cover stud has to beremoved to allow the stuffing box, mounted around the piston rod, to passbetween the remaining studs

2) The hatched area shows the height where an MAN B&W double-jib cranehas to be used

Fig. 4: Engine room height, component mass and crane capacity

Page 9: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling Crane 9

Further Reductions of Required Overhauling Height

The piston with rod and stuffing box

is the component assembly that re-

quires the most headroom for over-

hauling purposes. The total overhauling

height is given by dimension H3 in Fig.

4. Dimension H3 is the necessary mi-

nimum distance from the centreline of

the crankshaft to the underside of the

deck beam for a tilted piston, including

a safety margin. Fig. 5 shows the lifting

procedure for a tilted piston, and Fig.

6 shows an MAN B&W engine installed

in an engine room with restricted head-

room.

If an appropriate spacing of the deck

beams has been selected, and the lo-

cation of the main engine is such that

the pistons can be pulled up between

the deck beams, the building-in height

can, in some cases, be reduced even

more.

The reason is that this will allow the

useof the space in between the deck

beams, i.e. increase the available head-

room. In an engine room with an extre-

mely low headroom, where even the

electrically operated double-jib crane

cannot be used, the small manually

operated double-jib crane, shown in

Fig. 3, can in some cases perform the

job.

The standard version of this crane is

available with a capacity of 2 x 0.5 ton,

which suits the requirements of the

L35, S35 and S26 type engines. This

type of crane has an even lower buil-

ding in height than the electrically dri-

ven double-jib crane and, furthermore,

it is able to elevate the crane hooks clo-

ser to the deck beam than is the elec-

trically driven double-jib crane.

The manually operated double-jib crane

therefore permits a further slight reduc-

tion of the necessary headroom in the

engine room.

Crane railsCylinder linerwith cooling jacket

Cylinder covercomplete withexhaust valve

Piston with rodand stuffing box

Exhaustvalve

Fig. 6: Engine room arrangement with restricted headroom

Fig. 5: Tilted lift of piston using the MAN B&W double-jib crane

Deck beam

Centrelinecrankshaft

MAN B&Wdouble-jibcrane

Page 10: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling Crane10

Lifting Procedures for Main Components of the Engine

When the heaviest and most space-

demanding components of the engi-

ne are to be lifted using the double-jib

crane, the procedure differs somewhat

from the one used for a standard crane

with only one crane hook.

Details of the lifting procedure for each

of the components listed below will be

described and illustrated:

� Exhaust valve

� Cylinder cover complete with ex-

haust valve

� Piston with rod and stuffing box

� Cylinder liner with cooling jacket.

Exhaust valve

The exhaust valve is lifted using only

one of the crane hooks of the double-

jib crane. The hydraulically tightened

nuts on the exhaust valve studs are

loosened and the connected pipes are

removed. The exhaust valve studs are

unscrewed. In most cases it is sufficient

to unscrew only one or two studs.

One crane hook is attached to the eye

bolt on the exhaust valve top, and the

exhaust valve with unscrewed studs

can be lifted off the cylinder cover, see

Fig. 7.

However, if more than the minimum

building-in height of the MAN B&W

double-jib crane is available, see height

D in Fig. 4, the exhaust valve can be

lifted off the cylinder cover without the

need for removing any exhaust valve

studs, see Fig. 8.

Cylinder cover complete with

exhaust valve

Both hooks of the double-jib crane are

required for removal of the cylinder co-

ver. The two extension studs with eye

bolts are screwed into the threaded ho-

les in the cylinder cover, see Fig. 9.

The cylinder cover is loosened, and the

connected pipes are removed.

The two crane hooks are attached to

the eye bolts mounted in the extension

studs, and the cylinder cover with ex-

haust valve can be lifted away.

Fig. 7: Lift of exhaust valve with unscrewed studs (minimum lifting height)

Fig. 8: Lift of exhaust valve without removal of exhaust valve studs

Fig. 8: Lift of cylinder cover complete with ex-haust valve

Eyebolt

Eyebolt

Extensionstud

Eyebolt

Page 11: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling Crane 11

Piston with rod and stuffing box

The procedure for lifting the piston with

rod and stuffing box is in two stages,

with both hooks of the double-jib crane

being used in the second stage. If the

building-in height is restricted, one cy-

linder cover stud will have to be remo-

ved to allow the stuffing box, mounted

around the piston rod, to pass between

the remaining studs.

First, one of the crane hooks is atta-

ched to the lifting tool, which has been

mounted on the piston crown, see Fig.

10. Next, the piston is lifted high en-

ough to provide ample room over the

cylinder cover studs.

The collar ring is mounted on the piston

rod in such a position that the space-

rs on the collar ring lie true against the

piston. The intermediate supports are

placed on top of the cylinder cover

studs. The piston is then lowered until

the collar ring rests firmly on the inter-

mediate supports.

Both crane hooks are attached to the

collar ring, thereby allowing the piston

to be tilted out of the cylinder liner, see

Fig. 11. Then the piston is lifted as high

as possible, and the crane is moved in

athwartship direction while simultane-

ously tilting the piston. The piston rod

must be kept clear of the cylinder liner

and the cylinder cover studs during the

tilting operation.

If permitted by the space conditions,

the piston is straightened up again and

taken to the cut-out in the gallery for

overhauling.

Cylinder liner with cooling jacket

Both crane hooks of the double-jib

crane are to be used for dismantling

of the cylinder liner with cooling jacket

from the engine.

Depending on the available height in

the engine room, a number of cylinder

cover studs may have to be removed.

After removal of the required number

of cylinder cover studs, the two lifting

screws are fitted horizontally in the

threaded holes in the cylinder liner, see

Fig. 12.

The crane hooks are attached to the

lifting screws, and the liner is lifted as

high as possible. Note that the top of

the liner will go up between the chain

boxes of the crane. Finally, the crane is

run athwartships.

It may be necessary to tilt the liner

slightly to pass above the fuel pump.

Fig. 10: Piston with tools Fig. 11: Tilted lift of piston Fig. 12: Lift of cylinder liner with cooling jacket

Intermediatesupport

Spacer

Collarring

Lifting toolfor piston

Collarring

Lifting andtilting screw

Page 12: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling Crane12

Closing Remarks

As described and illustrated in this pa-

per, the overhauling procedure using a

double-jib crane differs somewhat from

the procedure with a standard single

hook crane.

However, time studies carried out on

board show that this does not affect the

total time spent on overhauling.

The MAN B&W double-jib crane has

been in production since 1979, and it

has proved to be a successful exten-

sion of the engine‘s overhauling tools

in numerous engine room installations

with restricted headroom.

Page 13: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...
Page 14: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...
Page 15: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...
Page 16: MAN B&W Double-Jib Crane – Low-headroom Engine Overhauling ...

MAN Diesel & TurboTeglholmsgade 412450 Copenhagen SV, DenmarkPhone +45 33 85 11 00Fax +45 33 85 10 [email protected]

MAN Diesel & Turbo – a member of the MAN Group

All data provided in this document is non-binding. This data serves informational purposes only and is especially not guaranteed in any way. Depending on the subsequent specific individual projects, the relevant data may be subject to changes and will be assessed and determined individually for each project. This will depend on the particular characteristics of each individual project, especially specific site and operational conditions. Copyright © MAN Diesel & Turbo. 5510-0062-01ppr Sep 2014 Printed in Denmark