MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the...

42
MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many, many more

Transcript of MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the...

Page 1: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

1

On behalf of the Commissioning Team

Commissioning of the Main Circuits

And many, many more

Page 2: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

2

Commissioning of the Main Circuits

Introduction Main Circuits

Defined here as >600A nominal

Complexity

History of events Quench Protection Lessons learned

In the Power Converter talk:

– All Energy extraction tested before and OK

– All Quench Protection installed and tested (but for the true signals)

Page 3: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

3

LHC Overview

Page 4: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

4

LHC Overview

Sector 7-8 , May - June

Sector 4-5 , Nov - Dec

Page 5: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

5

Complexity

Page 6: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

6

Complexity

Page 7: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

7

Complexity

Page 8: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

8

“Was man schwarz auf weiss besitzt…”

Page 9: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

9

“Was man schwarz auf weiss besitzt…”

Page 10: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

10

Tests of “Main Circuits”

Sector 7-8 (in total ~22 days for >600A circuits)– Test of D2, Q4, Q5 (~14 days)

• A Puzzle to be solved

– Test of QD, QF (~5 days)– Test of MB (~5 days)

Sector 4-5 (in total 3 days and today magnet tests)– Test of Q6

In 24 days 7 main circuits tested, – 3 of which fully tested

Page 11: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

11

The D2 Q4 puzzle

The MS was cold first (4.4 K), hence the test started there D2

– Start @ 15.5

– 6 kA @ 29.5 (after 4 days of testing)

Q4

– Start @ 30.5 close to nominal quench while changing Beam1 circuit

– Improvement of diagnostics.

– Looking into possible links:

• D2 and Q4 share conductors of a cable (non-conformity)

• Likely movement between the two cables, when Q4-B1 is powered

Slow changes and shaking Q4 and D2 Problem disappeared

Page 12: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

12

First Indication of Linkage between D2 & Q4

D2 Spontaneously Quenches as it

approaches Nominal50 mS later Q5 Trips due to QPS

Imbalance500 mS later Q4 Quenches but Why???

Page 13: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

13

D2, Q5, Q4, 13.June 07

Page 14: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

14

D2 History

69507100

7500

6000 6000

5269

1000

350245

200

120

120910

500100015002000250030003500400045005000550060006500700075008000

Cur

rent

BNL testing LHC D2 L8

First magnet to reach nominal (29.5)

The MS was cold first (4.4 K), hence the test started thereStart @ 15.56 kA @ 29.5 (after 4 days of testing)

D2

See later

Courtesy Glyn Kirby

Page 15: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

15A.Ballarino

D2 at 6000 A (~15 hours run)

Page 16: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

16

QPS trip ?

30.5. at nominal (D2 at 0)

Q4, shares the DFBM with the D2

Courtesy Glyn Kirby

Page 17: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

17

Consists of 2 MQM

Q5

Courtesy Glyn Kirby

Page 18: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

18

The D2 Q4 puzzle

The D2 was quenching when the Q4-B1 was at high value

The Quench was likely in the part, where the power busses are in the DFBM “side-by-side”

Page 19: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

19

The D2 Q4 puzzle

Once the cable where shaken into place, no quench occurred any more

Page 20: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

20

RQ and RB

RQ circuits limited due to high-pot problems

– Chosen was 6500 A max

RB circuit limited by one faulty dipole

– Chosen was 2000 A max

Note that both current levels were conservative. The energy extraction was tested before

Page 21: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

21A.Ballarino

RQD at 6500 A (~15 hours run)

Page 22: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

22

Inductive Discharge Voltage

+1V

Diode Drop -

1.2 Volts

Voltage

going into Coil

Voltage coming out of Coil

Quench Balanc

e Signal (∑) x10

Heaters Fire and

EE Switch Opens Diode

switches ON

at-6 Volts

Diode Performance during 6.5 kA Quench

of Main Quad QD.12R7

Artificial Test Ramp

Up==>

Trip at 100 mV

Quench Driven Polarity Reversa

l

Page 23: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

23

July 4th RB, QF, QD

Page 24: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

24

RQ6.R4, yesterday!!!!

Powered to Nominal 3610 Amps– in Both Apertures

No Spontaneous Quenches No False Quench Detections Lead Provoked Test Quenches

– Symetric & Asymetric

No Problems !

Courtesy Robert Henry Flora

Page 25: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

25

3610 Amp Quench, Q6.L4 (MQY)

Yes, these are two curves!

Both apertures quench identically!

That is to say: inductance, resistance, heaters and heat conduction are identical!

Courtesy Robert Henry Flora

Page 26: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

26

Half Coil Voltages (resistive +inductive)

B1

B2

100 ms

Courtesy Robert Henry Flora

Page 27: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

27

Quench Discharge Rate

Ampsec

dIdt

Magic button

Change of rate as already visible in

the voltage

Courtesy Robert Henry Flora

Page 28: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

28

Discharge Growth Rate

d2Idt2

Ampsec2

Courtesy Robert Henry Flora

Layer jump??

Page 29: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

29

Asymmetric Quench

B1

B2

Courtesy Robert Henry Flora

Page 30: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

30

Quench Discharge Rate

Amp

secdIdt

B1

B2

Courtesy Robert Henry Flora

Page 31: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

31

Quench Protection

The Quench Protection was requested to run in 7-8 at 5 times lower threshold than design

0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0-2.0

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

16.0

U_BB_1

U_B...

t [s]

U_B

B_1

Voltage over the current leads of RQF during a provoked 6.5 kA quench

Page 32: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

32

Quench Protection

The Quench Protection was requested to run at 5 times lower threshold than design

0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0-2.0

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

16.0

U_BB_1

U_B...

t [s]

U_B

B_1

0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0

-0.040

-0.030

-0.020

-0.010

0.000

0.010

0.020

Series1

t [s]

U_B

B_1

No real problem for the main circuits, problems for the corrector circuits

Page 33: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

33

Lessons learned (?)

By now well prepared procedures Highly motivated and well trained people A good team Good software support, displays etc, some minor hick-ups

Circuits without problems are very rapidly tested Several tests possible at the same time

Organization has much improved

Magnets no problem so far Current Leads no problem Energy Extraction no problem (so far) Quench Protection no problem (so far) Bus bars in the DFB can move due to non-conform manufacturing

We need stable testing conditions!

Page 34: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

34

End

Page 35: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

35

Table 1. List of distribution of busbars in DFBAs with NC in 6kA cablingDFB Sect. IR Cable 1 Cable 2 Cable 3 Cable 4DFBAO 7-8 8L cabling not checked cabling not checked cabling not checked cabling not checkedDFBAA 8-1 1L Q9C Q9A Q7B Q10A Q10B Q10C Q7A Q7C Q8B Q8A Q8B Q9BDFBAP 8-1 8R Q8A Q8C Q10C Q9C Q9B Q8C Q7A Q7B Q9A Q10A Q10B Q7CDFBAH 4-5 4R Q7C Q10B Q9B Q9A Q8B Q9C Q8A Q7A Q8C Q7B Q10A Q10CDFBAI 4-5 5L Q8A Q8B Q10B Q7A Q7C Q8C Q9B Q9C Q7B Q10A Q10C Q9A

Table 3. Distribution of busbars in DFBLs with NCDFB Sect. IR Cable 1 Cable 2 Cable 3 Cable 4DFBLA 8-1 1L D2A D2B Q6A Q6B Q6C nu Q4A Q4B Q4C Q5A Q5B Q5CDFBLB 1-2 1R D2A D2B Q6A Q6B Q6C nu Q4A Q4B Q4C Q5A Q5B Q5CDFBLD 4-5 5R D2A D2B Q6A Q6B Q6C nu Q4A Q4B Q4C Q5A Q5B Q5C

Cable NC

Page 36: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

36

Q4-D2 movements

Displacements from J.P.Quesnel, e-mail 12 Feb.’07

Top view

Side view

Q4

D2

D2

Q4

~10 mm

~7mm~7mrad~0.9 mrad

~10 mm

80 kN80 kN

80 kN 80 kN

Page 37: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

37

Photo Gallery

Tack welded stud

Uprooted longitudinal jack

radial jack at end of free movement Bus bar line with fixed point

Page 38: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

38

Magnet or Bus-”pig-tail”

Magnet Quench

190mV

10 ms

19 V/s

D2 Quench Development5269A

31st May @ 16:07 D2,Q5,Q4 Quench

D2 5280A quench24th May @15:53

Q4 training Quench At Nom 3610A

20 ms

50mV

2.5 V/s16 ms

30mV

1.87 V/s

Q4 Quench Development3128A

Q4 Quench Development3610A

D2 Quench at BNL ~7 V/s from 5274 A

(No R.T. leads and bus)

Page 39: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

39

60 to 80 ms Heater delay

Hea

ters

trig

gere

d

20 mV threshold

10ms verification

D2 quench at 5280A 31st May

2.5 V/s

Page 40: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

40

Q4 B1

Q4 B2

Q4 300A Quench / trip

10ms verification

Hea

ters

20 mV threshold 20 mV threshold10ms verification

Hea

ters

Q5 trip at ~3800A due to threshold imbalance after D2 quench

Page 41: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

41

600A

6000 A

13000 A

20K gas

50K With Current

70K No Current

LIQUID Helium covering LTS !!

Level should be correct in each chimney

4.5K liquid in

HT

S

Nominal Operating conditions for HTS leads

600 A, 6000 A & 13000 A

Ref. LHC-DFL-ES- 0001

1. LHe Level (Section 7.6) – In each chimney, it can vary over a length of 4 cm from the bottom end of the lead. LHe level max = 5 cm measured from the bottom end of the lead.

2. Temperature of cooling gas < 25 K (Section 3.2)

From 70 K to 50 K: 1/2 hour before powering?

Before powering: checks according to EDMS 755782 (The commissioning of the DFBs)

Cry

o st

art

Cry

o-m

aint

ain

Page 42: MAC 22, 6. 12. 2007, KHM-AT-MEL, on behalf of the Commissioning Team 1 On behalf of the Commissioning Team Commissioning of the Main Circuits And many,

MA

C 2

2, 6

. 12

. 20

07,

KH

M-A

T-M

EL,

on

beha

lf of

the

Com

mis

sion

ing

Team

42

6KA D2 Pig-Tail 20mV or 50mV threshold

0.000

0.020

0.040

0.060

0.080

0.100

0.120

0 0.1 0.2 0.3 0.4 0.5 0.6

0

100

200

300

400

500

600

700

Voltage over resistive part

Av Temp Cable 1 T(K)

Current / 10

Pig-tail quench simulation

20mV qps threshold, 70ms heater delay , No cooling!! 2cm length of conductor quenched.

From 6000A

Pig-tail quench simulation50mV qps threashold, No cooling!! 2cm length of conductor quenched.

From 6000A

0.000

0.050

0.100

0.150

0.200

0.250

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8

time (s)

Vol

tage

ove

r 2c

m s

ectio

n (V

)

0

100

200

300

400

500

600

700

800

hot s

opt t

emp

& (C

urre

nt /1

0)

Voltage over resistive part

Av Temp Cable 1 T(K)

Current / 10

20 mV 350 K (OK)

70 ms

Too Hot 70 ms

50mV, 70ms heater delay, 6000A, 200mm Pig- Tail

quench

0.00

0.05

0.10

0.15

0.20

0.25

0.30

0.35

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7

0

100

200

300

400

500

600

700

Voltage over resistivepart

Av Temp Cable 1 T(K)

Current / 10

70 ms