M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin

Transcript of M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012...

Page 1: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

M1 Project (West Gate Freeway Section)Completion of cadastral and land tenure itemsMarch 2012

Presented by Glen Franklin

Page 2: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

– Background of the M1 Project

– Stages of the project

– Completion of cadastral and land tenure items

• Scope the remaining items

• Staging and priorities

• Progress

• Expected completion

– Questions

M1 Project (West Gate Freeway Section)

Page 3: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Background video

M1 Project (West Gate Freeway Section)

Page 4: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

The $1.39 billion ‘Monash-Citylink-West Gate’ M1 upgrade is the largest statefunded road project in Victoria’s history. Stretching 75km from Werribee to Narre Warren, it delivers a safe and efficient fourlane freeway that is Melbourne’s transport spine.

The project was split into four main pieces, and the 6.2km West Gate Freeway section through the CBD is relatively short in length. Yet it more than makes up for it in complexity, and an alliance of five groups delivered the project.

Background

Page 5: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

To call this a brownfield site is a major understatement – the working parameters are tight and the existing roadways carry more than 160,000 vehicles every day.

New bridges, ramps, pillars and pavement contribute to a smoother and smarter traffic flow for the many motorists using this vital link.

Special legislation was created for the project. Schedule 5A was added to the Road Management Act 2004 that included:– Limits of the project– Acquisition of land– Surrender and Divesting of land

Background (cont.)

Page 6: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Redevelopment Project area - LEGL plans

Page 7: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Stages of the project

Page 8: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

West Gate Freeway section

Page 9: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Stages of the project

DEVELOPMENT & PLANNING

Ongoing MANAGEMENT

AS BUILT

PRE-CONSTRUCTION

DESIGN & CONSTRUCTION

Renovate Transportation Corridor

Page 10: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

OpeningEverything finished ?????

Page 11: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Items that have been completed:– Aerial Photography– Control Survey Plan– Feature surveys– Laser Scanning of structures– Acquisition Survey Plans– Notice of Acquisition gazettals– Plans of Subdivision and creation of

easements– Governor in Council gazettals– etc

Completion of cadastral and land tenure items

Page 12: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Complete land status and ownership search was completed. Interesting items:– Stratum titles owned by Roads Corporation– Discontinuations vested in Roads Corporation (titles

still exist)– Discontinuations completed under Project

Development and Construction Management Act 1994

– Temporary Railway purposes reserves where a Crown Lease has been issued

– A title for 1m2

– Cancelled titles that should still exist– Multiple interests in land (and stratum)– Etc

Scope the remaining items

Page 13: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Summary of actions was created. For example:– Show existing West Gate Freeway declaration– Show the extent of the existing Crown Leases– Field survey to confirm the new structures were

located within the acquisition and proposed freeway declaration boundaries

– Plans of Subdivision– Plans for Creation of Easement– Defining the surplus land that is no longer required

for future road projects– Amending Crown leases to remove the acquired land– Show extent of temporary reserves to be revoked

Scope the remaining items (cont)

Page 14: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Staging and priorities

Stage Main Issue Priority

Southern Link to Clarendon Street Surplus land & Crown lease

4

Clarendon Street to Whiteman Street Crown Leases 2

Whiteman Street to Normanby Road VicTrack 3

Normanby Road to Montague Street Convention Centre

1

Montague Street to Western Link Land Status 7

Western Link to Todd Road Land Status 6

Todd Road To Williamstown Road Land Status 5

Page 15: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Normanby Road to Montague Street

Progress – Convention Centre

Task Status

As Built survey Completed

VicRoads Survey Plan Completed

Governor in Council In progress

Declaration, Revocation & Discontinuation In progress

Title Plan In progress

Crown Grant Conditions Final draft

Issuing of titles To be commenced

Planning Scheme Amendment To be commenced

Memorandum of Understanding Final draft

Page 16: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Normanby Road to Montague Street

– Pictures of the site

– Survey documents/plans produced

Progress – Convention Centre

Page 17: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Clarendon Street to Whiteman Street

Progress – Crown Leases

Task Status

As Built survey Completed

VicRoads Survey Plan – Amendments Final draft

Declaration, Revocation & discontinuation To be commenced

New OP’s In progress

Surrender of Crown Leases To be commenced

Issuing of new Crown Leases To be commenced

Planning Scheme Amendment To be commenced

Page 18: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Clarendon Street to Whiteman Street

– Survey documents/plans produced

Progress – Crown Leases

Page 19: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Late 2012, depending upon the resources allocated

Expected completion

Page 20: M1 Project (West Gate Freeway Section) Completion of cadastral and land tenure items March 2012 Presented by Glen Franklin.

Email: [email protected] Phone: (03) 9854 2026

Acknowledgements

Questions / Queries

M1 Project – West Gate Freeway Alliance Various survey companies Office of the Surveyor General