Loraine Independent School District

13
Loraine Independent School District Campus Improvements Construction Update March 25th, 2013

description

Loraine Independent School District. Campus Improvements Construction Update March 25th , 2013. PROJECT STATUS. PLANS. PLANS. SCHEDULE. SCHEDULE STATUS. Block fill in Locker Rooms and Gymnasium is Underway Steel Erection is Complete - PowerPoint PPT Presentation

Transcript of Loraine Independent School District

Loraine IndependentSchool District

• Campus Improvements• Construction Update• March 25th, 2013

PROJECT STATUS

Budgeted Amount

Cost Savings

GMP Total

Amount Billed

Through February

% Comp

Owner's Contingency

Contractor Contingency

$10,800,000 $83,599 $10,716,401 $4,973,435  46% $53,684 $204,250

 

PLANS

PLANS

SCHEDULE

August September October November December January February March April May June July August September October

New School for Loraine ISD2012 2013

Star

t Con

stru

ction

Cons

truction Co

mplete

Painting & Finishout

Interior Drywall & Ceilings

Mechanical & Electrical SystemsPunchlist & Closeout

Present Date

Excavation & Earthwork

Structural Steel Erection

Underground Plumbing and Electrical Rough-In

Flooring & Specialties

Demo & Abatement of Old Gym

Roofing

Gym Flooring & Bleacher Seating

Glass & Glazing

Mobilize, Bid and Contract Procurement

Building Foundations

Masonry

Exterior Framing & Sheathing

Demo Old School & Pour Concrete Drive

Ag. Shop Remodel

Block fill in Locker Rooms and Gymnasium is Underway Steel Erection is Complete Interior Masonry is Complete Except at Stage and Ramp Exterior Sheathing is 98% Exterior Brick Veneer is 70% Interior and Exterior Framing is 98% except furr downs Mechanical and Electrical Rough-in is 80% Roof is 95% Dried-in Bleachers are Poured Tie-in to Ag. Building is Framed, Sheathed, and Dried in HS/ Jr. High Cabinets are finished and ready to install

SCHEDULE STATUS

Framing At Administration Area

Elementary Corridor

Locker Rooms

Exterior of Library

Junior High and High School Wing

Roof of Science Wing

Basketball Goals will be Installed Windows and Entrances Will Be Completed Cabinet Finishing and Installation Will Continue Tape/Bed/Paint Will Continue Concrete at Stage will be Completed Steps at Gymnasium Bleachers will be Poured Concrete will be Poured to Existing Gymnasium Roofing Sheetmetal will Continue Sheetrock Installation will Continue

LOOKING AHEAD