PROJECT STATUS
Budgeted Amount
Cost Savings
GMP Total
Amount Billed
Through February
% Comp
Owner's Contingency
Contractor Contingency
$10,800,000 $83,599 $10,716,401 $4,973,435 46% $53,684 $204,250
SCHEDULE
August September October November December January February March April May June July August September October
New School for Loraine ISD2012 2013
Star
t Con
stru
ction
Cons
truction Co
mplete
Painting & Finishout
Interior Drywall & Ceilings
Mechanical & Electrical SystemsPunchlist & Closeout
Present Date
Excavation & Earthwork
Structural Steel Erection
Underground Plumbing and Electrical Rough-In
Flooring & Specialties
Demo & Abatement of Old Gym
Roofing
Gym Flooring & Bleacher Seating
Glass & Glazing
Mobilize, Bid and Contract Procurement
Building Foundations
Masonry
Exterior Framing & Sheathing
Demo Old School & Pour Concrete Drive
Ag. Shop Remodel
Block fill in Locker Rooms and Gymnasium is Underway Steel Erection is Complete Interior Masonry is Complete Except at Stage and Ramp Exterior Sheathing is 98% Exterior Brick Veneer is 70% Interior and Exterior Framing is 98% except furr downs Mechanical and Electrical Rough-in is 80% Roof is 95% Dried-in Bleachers are Poured Tie-in to Ag. Building is Framed, Sheathed, and Dried in HS/ Jr. High Cabinets are finished and ready to install
SCHEDULE STATUS
Basketball Goals will be Installed Windows and Entrances Will Be Completed Cabinet Finishing and Installation Will Continue Tape/Bed/Paint Will Continue Concrete at Stage will be Completed Steps at Gymnasium Bleachers will be Poured Concrete will be Poured to Existing Gymnasium Roofing Sheetmetal will Continue Sheetrock Installation will Continue
LOOKING AHEAD