Little Paddock Gold Mine Extension
Transcript of Little Paddock Gold Mine Extension
Level 3 69 Cambridge Terrace
PO Box 4071
Christchurch 8140 New Zealand
T: +64 3 365 8455 F: +64 3 365 8477
www.marshallday.com
Project: LITTLE PADDOCK GOLD MINE EXTENSION
Prepared for: Gold and Green Resources Ltd
PO Box 11
Hokitika 7842
Attention: John Wood
Report No.: Rp 001 R01 2013232C
Disclaimer
Reports produced by Marshall Day Acoustics Limited are prepared based on the Client’s objective and are based on a
specific scope, conditions and limitations, as agreed between Marshall Day Acoustics and the Client. Information and/or
report(s) prepared by Marshall Day Acoustics may not be suitable for uses other than the original intended objective.
No parties other than the Client should use any information and/or report(s) without first conferring with Marshall Day
Acoustics.
Copyright
The concepts and information contained in this document are the property of Marshall Day Acoustics Limited. Use or
copying of this document in whole or in part without the written permission of Marshall Day Acoustics constitutes an
infringement of copyright. Information shall not be assigned to a third party without prior consent.
Document control
Status: Rev: Comments Date: Author: Reviewer:
Approved - - 12 July 2013 Aaron Staples Stuart Camp
Approved R01 Additional dwellings and
wheeled loader 16 July 2013 Aaron Staples Stuart Camp
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 3 of 17
EXECUTIVE SUMMARY
Marshall Day Acoustics has assessed potential noise effects from a proposed extension to the Little
Paddock gold mining activity at Blue Spur, near Hokitika. The proposed extension involves utilising
additional plant and equipment and changing the order in which the mine sites will be mined.
We have predicted noise levels at surrounding noise sensitive receivers and confirm that
compliance with the District Plan daytime noise rules can be achieved, provided that the following
noise mitigation measures are implemented:
• Mining activity on site shall only be undertaken between 0700-2100 hours, Monday to Friday,
and 0700-1800 hours on Saturdays;
• All mining equipment must maintain a set back distance of no less than 150 metres from the
nearest façade of dwellings labeled ‘D’ and ‘E’ in Figure 1;
• In the event that a dwelling is constructed on the subdivision to the south of the mine site,
either one of the following noise mitigation measures must be implemented:
1) All mining equipment must maintain a set back distance of at least 100 metres from the
southern boundary of the mine site; or
2) All mining equipment must maintain a set back distance of at least 25 metres from the
southern boundary of the mine site, and earth bunds no less than 3 metres high must be
constructed along the mine site boundary as indicated with a blue line on the noise
contour map for Scenario 2b (Appendix B).
• Mining operations shall utilise the best practicable option to minimise noise at all times. This
includes regular maintenance and replacement of worn parts, maintenance of mufflers,
lubrication of all moving parts to avoid squeaks and squeals, and appropriate operation of all
equipment.
Provided that the above measures are implemented, we anticipate that any noise effects that may
arise from the proposal will be acceptable.
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 4 of 17
TABLE OF CONTENTS
1.0 INTRODUCTION ........................................................................................................................ 5
2.0 SITE & ACTIVITY DESCRIPTION ................................................................................................ 5
3.0 NOISE ASSESSMENT CRITERIA ................................................................................................. 7
3.1 District Plan Noise Rules .......................................................................................................... 7
3.2 World Health Organisation ...................................................................................................... 7
3.3 NZS 6802:2008 Guideline Upper Noise Limits ....................................................................... 8
3.4 Discussion of Noise Assessment Criteria ................................................................................ 8
4.0 NOISE LEVEL PREDICTION METHODOLOGY ........................................................................... 8
4.1 Input Noise Source Levels ........................................................................................................ 8
5.0 PREDICTED NOISE LEVELS ........................................................................................................ 9
6.0 ASSESSMENT OF NOISE EFFECTS .......................................................................................... 10
6.1 Existing Dwellings ................................................................................................................... 10
6.2 Subdivision South of Mine Site .............................................................................................. 10
7.0 RECOMMENDATIONS ............................................................................................................ 11
8.0 CONCLUSIONS ........................................................................................................................ 11
APPENDIX A GLOSSARY OF TERMINOLOGY
APPENDIX B NOISE CONTOUR MAPS
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 5 of 17
1.0 INTRODUCTION
Marshall Day Acoustics has been appointed by Gold and Green Resources Ltd on behalf of
Zalas Creek Mining Ltd to perform an assessment of noise effects for a proposed extension
of the Little Paddock gold mine in Blue Spur, near Hokitika. Marshall Day Acoustics prepared
the original noise assessment for the mine in 2011 (report reference Rp 001 2011358C,
dated 10 October 2011).
This report provides:
• A summary of the proposed mine extension in regard to noise generation;
• A review of appropriate noise assessment criteria;
• Predicted noise levels from the proposed mining operation; and
• An assessment of the potential noise effects at surrounding properties as a result of the
activity.
A glossary of the terminology used in this report is provided in Appendix A.
2.0 SITE & ACTIVITY DESCRIPTION
The Little Paddock gold mine site is located off Blue Spur Road, near Hokitika. The original
Little Paddock gold mine consent, granted in 2011, was to mine the area labelled Mining
Permit 53214 in Figure 1. The original proposal involved two excavators, one dump truck, a
trommel plant and a diesel powered dewatering pump. We understand that the West Coast
Regional Council had specified that ‘Mine Site 2’ (refer to Figure 1) be mined prior to ‘Mine
Site 1’ as part of the original consent.
The proposed mining extension involves utilising additional plant and equipment including
an additional dump truck, excavator, wheeled loader, trommel plant and dewatering pump.
The proposal also seeks to remove the requirement on the order in which the mine sites are
mined, so that ‘Mine Site 1’ can be mined prior to or at the same time as ‘Mine Site 2’. The
additional fixed plant (i.e. trommels and dewatering pumps) and wheeled loader will
operate in the same general location as the existing plant (near ‘Mine Site 1’) and will
benefit from screening provided by existing earth bunds constructed as part of the original
consent.
Hours of operation will continue to be 0700 to 1800 hours Monday to Friday and 0700 to
1200 hours on Saturdays. No mining will take place on Sundays or public holidays.
The dwellings nearest the mine site are indicated in Figure 1. The approximate extent of a
residential subdivision to the south of the mine site is also indicated, however, no dwellings
have been constructed on this land to date. We note that written approval was obtained
from the owners of dwellings D, E and F for the original consent and we understand that
approval could again be obtained if required.
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 6 of 17
Figure 1: Mine site and locality
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 7 of 17
3.0 NOISE ASSESSMENT CRITERIA
It is useful to consider a number of guidance documents in assessing the potential for noise
effects. These documents are discussed in the following sections.
3.1 District Plan Noise Rules
The mine site and surrounding land is zoned Rural under the Westland District Plan. The
District Plan noise rules applicable to the operation of the gold mine are as follows:
Noise
(all activities except forestry, and agricultural activities)
0700 – 2100 hrs Mon – Fri
0700 – 1800 hrs Saturday
55 dB LA10 at any point within the notional
boundary of a residential activity.
All other times including
public holidays
45 dB LA10 at any point within the notional
boundary of a residential activity.
As the mining activity will only operate during daytime hours on Monday to Saturday, the
critical noise limit is 55 dB LA10 at the notional boundary of a residential activity.
3.2 World Health Organisation
World Health Organisation (WHO) Guideline Values for Community Noise (Berglund and
Lindvall, 1999) give guidelines for environmental noise exposure. For community or
environmental noise, the critical health effects (those effects which occur at the lowest
exposure levels) are sleep disturbance and annoyance.
These Guideline Values are the exposure levels that represent the onset of the effect for the
general population.
Table 1: WHO Guideline Values for the critical health effects of community or environmental noise
Specific
Environment
Critical health effect(s) LAeq dBA Time base
(hours)
LAmax dBA
Outdoor living
area
Serious annoyance, daytime & evening
Moderate annoyance, daytime &
evening
55
50
16
16
-
-
Outside
bedrooms
Sleep disturbance, window open
(outdoor values) night-time
45 8 60
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 8 of 17
3.3 NZS 6802:2008 Guideline Upper Noise Limits
The 2008 version of NZS 6802:2008 “Acoustics - Environmental Noise” (N.B. the District Plan
refers to the 1991 version) provides the following guideline upper noise limits for noise
received at or within the notional boundary of any rural dwelling:
• Daytime: 55 dB LAeq(15min)
• Night-time: 45 dB LAeq(15min) and 75 dB LAFmax
3.4 Discussion of Noise Assessment Criteria
The District Plan noise rules are consistent with the WHO Guideline Values and the guideline
upper noise limits provided in the latest version of NZS 6802. We therefore consider that
compliance with the District Plan noise rules at surrounding dwellings will result in
acceptable noise effects.
4.0 NOISE LEVEL PREDICTION METHODOLOGY
To accurately predict noise levels, the noise modelling package SoundPLAN has been used.
Calculations in SoundPLAN are based on ISO 9613-2:1996 “Acoustics – Attenuation of sound
during propagation outdoors – Part 2: General method of calculation”. This method has the
scope to take into account a range of factors affecting the sound propagation including:
• The magnitude of the noise source in terms of sound power;
• The distance between source and receiver;
• The presence of obstacles such as screens or barriers in the propagation path;
• The presence of reflecting surfaces;
• The hardness of the ground between the source and receiver;
• Attenuation due to atmospheric absorption; and
• Meteorological effects such as wind gradient, temperature gradient and humidity.
In ISO 9613, the effect of meteorological conditions is significantly simplified by calculating
the average downwind sound pressure level. The Standard adopts the conservative
approach of assuming that wind is always blowing from the noise sources to the receiver
locations. The equations and calculations also hold for average propagation under a well
developed moderate ground based temperature inversion, such as commonly occurs on
clear, calm nights.
4.1 Input Noise Source Levels
Input noise source data has been based on noise level measurements of similar plant and
equipment operating at other gold mining and gravel extraction operations around New
Zealand. We have used the following sound power levels for the basis of our predictions.
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 9 of 17
Table 2: Sound power levels of mining noise sources used in model
Noise source Sound power level (dB LAw)
Trommel plant (each) 106
Diesel dewatering pump 103
Sykes dewatering pump 94
Excavator (each) 105
Wheeled loader 108
Dump truck (Moxy MT36) 112 (SEL basis)
We have also considered noise from miscellaneous sources such as staff vehicle
movements. These noise sources do not contribute to the overall noise levels and we will
therefore not discuss them further.
5.0 PREDICTED NOISE LEVELS
The challenge in predicting noise levels from a mining operation such as this is that the
activity typically occurs in a very small area of the site at any one time. Hence, noise levels at
neighbouring properties will vary significantly, depending on the separation distance at the
time. To address this, we have modelled a number of scenarios:
• Scenario 1 – Operational area adjacent Blue Spur Road (‘Mine Site 2’)
• Scenario 2a – Operational area 100m from south boundary without additional earth
bunds
• Scenario 2b – Operational area 25m from south boundary with additional 3m high earth
bunds
• Scenario 3 – Operational area in southwest corner of site (worst case scenario for
Dwelling A).
Our predicted noise levels for the scenarios above are summarised in Table 3. For noise
contour maps of these scenarios, refer to Appendix B.
Table 3: Predicted noise levels
Receiver Predicted noise level (dB LA10) at notional boundary:
Scenario 1 Scenario 2a Scenario 2b Scenario 3
Dwelling A 47 45 46 52
Dwelling B 45 40 40 41
Dwelling C 46 40 40 42
Dwelling D 54 35 35 37
Dwelling E 39 33 33 33
Dwelling F 40 33 33 34
Dwelling G 38 35 35 36
Dwelling H 49 48 48 48
Subdivision boundary 50 55 55 55
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 10 of 17
Our predicted noise levels for the above scenarios show that the District Plan noise rule of
55 dB LA10 can be achieved at all existing dwellings. Further analysis shows that all mining
equipment must maintain a set back distance of no less than 150 metres from dwellings D
and E in order to ensure that compliance is achieved at these dwellings at all times. The
construction of earth bunds around mining equipment operating near these dwellings
locations would not significantly reduce the set back distances required from these
dwellings. This is due to the topography in these areas which limit the effectiveness of any
noise barriers.
We have also predicted noise levels at the boundary of the subdivision to the south of the
mine site. Our calculations show that mining activities can achieve the District Plan noise
limit of 55 dB LA10 at the subdivision boundary, provided that a set back distance of 25 m is
maintained from the boundary of the mine site, and earth bunds no less than 3 metres high
are constructed along the mine site boundary as indicated with a blue line on the noise
contour map for Scenario 2b (Appendix B). Alternatively, compliance with the District Plan
noise rules would be achieved without the need for additional earth bunds if a set back
distance of no less than 100 metres from the southern mine site boundary is maintained.
6.0 ASSESSMENT OF NOISE EFFECTS
6.1 Existing Dwellings
Noise emissions from the proposed extension of Little Paddock gold mine will comply with
the District Plan rule of 55 dB LA10 at all times at all existing dwellings, provided that a set
back distance of 150 metres is maintained from Dwellings D and E (refer to Figure 1).
As previously stated, noise levels received at dwellings will vary significantly depending on
the location of the mine at the time. The separation distances between the proposed mining
sites and the existing dwellings in the area are such that noise levels received at most
dwellings will be well below the District Plan noise limit most of the time.
We therefore consider the potential noise effects that may arise at existing dwellings to be
acceptable.
6.2 Subdivision South of Mine Site
We support the option of changing in mining sequence as it would allow the area nearest
the subdivision to be mined first. This may result in mining activity being completed in this
area prior to any houses being occupied in the subdivision.
Our analysis shows that compliance with the District Plan noise rules can be achieved at the
subdivision to the south of the mine site with appropriate noise mitigation measures.
Furthermore, potential subdivision residents will be aware of the noise generation from
existing mining activities that can be expected moving into the area.
We therefore anticipate that any noise effects that may arise at any future dwellings will be
acceptable.
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 11 of 17
7.0 RECOMMENDATIONS
Based on our analysis, we make the following recommendations to ensure that the activity
complies with the District Plan noise rules at all times:
• Mining activity on site shall only be undertaken between 0700-2100 hours, Monday to
Friday, and 0700-1800 hours on Saturdays;
• All mining equipment must maintain a set back distance of no less than 150 metres from
the nearest façade of dwellings labeled ‘D’ and ‘E’ in Figure 1;
• In the event that a dwelling is constructed on the subdivision to the south of the mine
site, one of the following noise mitigation measures must be implemented:
1) All mining equipment must maintain a set back distance of at least 100 metres
from the southern boundary of the mine site; or
2) All mining equipment must maintain a set back distance of at least 25 metres
from the southern boundary of the mine site, and earth bunds no less than 3
metres high must be constructed along the mine site boundary as indicated with
a blue line on the noise contour map for Scenario 2b (Appendix B).
• Mining operations shall utilise the best practicable option to minimise noise at all times.
This includes regular maintenance and replacement of worn parts, maintenance of
mufflers, lubrication of all moving parts to avoid squeaks and squeals, and appropriate
operation of all equipment.
8.0 CONCLUSIONS
Marshall Day Acoustics has assessed the potential noise effects from the proposed
extension to the Little Paddock gold mining operation in Blue Spur, near Hokitika. The
extension involves utilising additional plant and equipment and the option of changing the
order in which the mine sites will be mined.
Noise levels at existing dwellings and the subdivision to the south of the site have been
predicted for a number of scenarios. The results of these predictions and our subsequent
analysis shows that compliance with the District Plan noise rules can be achieved at all
surrounding noise sensitive receivers with appropriate noise mitigation measures. These
measures include maintaining set back distances from dwellings and constructing additional
earth bunds.
Given that the activity will comply with the District Plan noise rules at all times, and that
noise levels will in fact be significantly lower the District Plan limits at the majority of
dwellings in the area, we anticipate that any noise effects that may arise from the proposal
will be acceptable.
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 12 of 17
APPENDIX A GLOSSARY OF TERMINOLOGY
SPL or LP Sound Pressure Level
A logarithmic ratio of a sound pressure measured at distance, relative to the
threshold of hearing (20 µPa RMS) and expressed in decibels.
SWL or LW Sound Power Level
A logarithmic ratio of the acoustic power output of a source relative to 10-12
watts and expressed in decibels. Sound power level is calculated from
measured sound pressure levels and represents the level of total sound
power radiated by a sound source.
dB Decibel
The unit of sound level.
Expressed as a logarithmic ratio of sound pressure P relative to a reference
pressure of Pr=20 µPa i.e. dB = 20 x log(P/Pr)
A-weighting The process by which noise levels are corrected to account for the non-linear
frequency response of the human ear.
LAeq (t) The equivalent continuous (time-averaged) A-weighted sound level. This is
commonly referred to as the average noise level. The suffix "t" represents the
time period to which the noise level relates
LA10 (t) The A-weighted noise level equalled or exceeded for 10% of the
measurement period. This is commonly referred to as the average maximum
noise level. The suffix "t" represents the time period to which the noise level
relates.
LAFmax The maximum A-weighted noise level measured using fast response (hence
‘F’), during a chosen sample period.
SEL or LAE Sound Exposure Level
The sound level of one second duration which has the same amount of
energy as the actual noise event measured.
Usually used to measure the sound energy of a particular event, such as a
train pass-by or an aircraft flyover
Noise A sound that is unwanted by, or distracting to, the receiver.
NZS 6802:2008 New Zealand Standard NZS 6802:2008 “Acoustics – Environmental Noise”
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 13 of 17
APPENDIX B NOISE CONTOUR MAPS
(Provided on following pages)
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 14 of 17
B1 Scenario 1
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 15 of 17
B2 Scenario 2a
This document may not be reproduced in full or in part without the written consent of Marshall Day Acoustics Limited
Rp 001 R01 2013232C Little Paddock Gold Mine Extension ANE Page 16 of 17
B3 Scenario 2b