Line Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
-
Upload
iain-sanders -
Category
Technology
-
view
744 -
download
1
Transcript of Line Upgrade Deferral Scenarios for Distributed Renewable Energy Resources
SCENARIOS FOR DE INVESTMENT AS AN ALTERNATIVE TO LINES UPGRADES
– RURAL CASE STUDIES
12th Feb 2007
Sustainable Innovative Solutions Ltd.
Dr. Iain Sanders
2
Summary
This study considers the value of Distributed Energy (DE) in deferring or eliminating line capacity-based upgrades.
It assumes a combination of fuel-based DE, e.g. diesel gensets or fuel cells in combination with intermittent Renewable Energy (RE) to ensure that normal supply reliability can be delivered at all times.
Both the value and costs of the combinations are clearly identified.
The net results are almost always positive in comparison with line upgrades for capacity reasons.
3
MainPower Lyndon (ML) line
MainPower Lyndon (ML) line
MainPower Lyndon (ML) line
Predicted Load Duration Curve
TypicalExample
2003 Load Duration Curve for Lyndon Line
0
10
20
30
40
50
60
70
80
90
1001
227
454
680
907
1133
1360
1586
1813
2039
2266
2492
2719
2945
3172
3398
3625
3851
4078
4304
4531
4757
4984
5210
5437
5663
5890
6116
6343
6569
6796
7022
7249
7475
7702
7928
8155
8381
8608
Cummulative Hours of the Year
Cap
acity
(kW
) 60kW BASE-CASE USED FOR LOAD DURATION PROJECTIONS
80kW MAXIMUM STANDARD OPERATING CAPACITY THRESHOLD
2003 Load Duration Curve for Lyndon Line
0
10
20
30
40
50
60
70
80
90
1001
227
454
680
907
1133
1360
1586
1813
2039
2266
2492
2719
2945
3172
3398
3625
3851
4078
4304
4531
4757
4984
5210
5437
5663
5890
6116
6343
6569
6796
7022
7249
7475
7702
7928
8155
8381
8608
Cummulative Hours of the Year
Cap
acity
(kW
) 60kW BASE-CASE USED FOR LOAD DURATION PROJECTIONS
80kW MAXIMUM STANDARD OPERATING CAPACITY THRESHOLD
Firm DE
2003 Load Duration Curve for Lyndon Line
0
10
20
30
40
50
60
70
80
90
1001
227
454
680
907
1133
1360
1586
1813
2039
2266
2492
2719
2945
3172
3398
3625
3851
4078
4304
4531
4757
4984
5210
5437
5663
5890
6116
6343
6569
6796
7022
7249
7475
7702
7928
8155
8381
8608
Cummulative Hours of the Year
Cap
acity
(kW
) 60kW BASE-CASE USED FOR LOAD DURATION PROJECTIONS
80kW MAXIMUM STANDARD OPERATING CAPACITY THRESHOLD
2003 Load Duration Curve for Lyndon Line
0
10
20
30
40
50
60
70
80
90
1001
227
454
680
907
1133
1360
1586
1813
2039
2266
2492
2719
2945
3172
3398
3625
3851
4078
4304
4531
4757
4984
5210
5437
5663
5890
6116
6343
6569
6796
7022
7249
7475
7702
7928
8155
8381
8608
Cummulative Hours of the Year
Cap
acity
(kW
) 60kW BASE-CASE USED FOR LOAD DURATION PROJECTIONS
80kW MAXIMUM STANDARD OPERATING CAPACITY THRESHOLD
Firm DE
What is Line Upgrade Deferral?
Primary objective for DE to meet peak load requirements
4
Using integrated distributed energy technologies, some technologies may be owned & controlled by the networks, and some technologies may be owned & controlled by the customers
C u sto m e r E ff ic ie n cy
C e n tr a l G e n e r a tio n
T o d a y 's T o d a y 's C en tr a l U tilityC e n tr a l U tility
T o m o rro w 's T o m o r ro w 's D is tr ib u ted U tility ?D is tr ib u ted U tility ?
R e m o teL o a d s
W in d
P V
G e n se t
F u e l C e ll
B a tte r y
C u sto m e r s
C e n tr a l G e n e r a tio n
© 2 0 0 2 D is tr ib u te d U til ity A sso c ia te s1
M ic r o tu r b in e
Can Costly Upgrades Be Prevented? 15
C u sto m e r E ff ic ie n cy
C en tr a l G e n e r a tio n
T o d a y 's T o d a y 's C e n tr a l U tilityC e n tr a l U tility
T o m o r ro w 's T o m o r ro w 's D is tr ib u ted U tility ?D is tr ib u ted U tility ?
R em o teL o a d s
W in d
P V
G e n se t
F u e l C e ll
B a tte r y
C u sto m e r s
C en tr a l G e n e ra tio n
© 2 0 0 2 D is tr ib u te d U til ity A sso c ia te s1
M ic r o tu r b in e
5
Distributed Energy Benefits
Support adoption of environmentally friendly alternatives, providing carbon credits.
Provide supplementary revenue to farmers. Remove burden of costly infrastructure upgrades on tax-
/rate-payers. Reduce risk of failure of over-loaded transmission &
distribution lines. Promote energy-efficiency and development of alternative
energy resources. Only pay for what is required using modular distributed
energy (DE) technologies. Provide additional revenue / savings for network operators
6
Motivation for Research It is getting harder for Networks to cover O&M and
replacement costs on infrastructure: Increasing population hot spots increase rural demand putting
pressure on existing rural networks Most rural network infrastructure is old, nearing the end of its normal
life, making O&M costly and in urgent need of replacement Preventive O&M is no longer affordable, resulting in more severe and
costly failures when they happen New Zealand is rich in alternative energy resources which
could make a substantial contribution only through these techniques
Local communities are keen to develop natural resources for long-term sustainable development of the region
Potential for DE technology to reduce peak demand and therefore extend the life of the ageing network infrastructure
Opportunities for islanded operations to deliver higher reliability at lower service costs – self-healing / interactive microgrids
7
Network asset data provided by:
Eastland NetworksMainPowerOrion Networks
These organisationswere closely involvedwith deriving the costingmodels and economicanalysis methodologies
8
Main Case Study – a section of the Eastland Network was chosen –
The Ruatoria 11kV Feeder from the Ruatoria 50/11kV Substation
Main Case Study – a section of the Eastland Network was chosen –
The Ruatoria 11kV Feeder from the Ruatoria 50/11kV Substation
Eastland Network
Te Puia is fed from
Tokomaru Bay
50/11kV line
TOLAGA BAYINPORT
TOKOMARU BAY INPORT
RUATORIA INPORT
TE ARAROAINPORT
GISBORNEINPORT
Te Puia is fed from
Tokomaru Bay
50/11kV line
TOLAGA BAYINPORT
TOKOMARU BAY INPORT
RUATORIA INPORT
TE ARAROAINPORT
GISBORNEINPORT
FOCUS
9
Ruatoria Feeder Profile Trends
10
Ruatoria Feeder Growth Scenarios Explored• Actual growth rate = 1.5% per year
• To illustrate impact of DE, growth projections of:
1.75, 5 & 10% per year were investigated
• Peak load capacity threshold of 1600kW
selected to illustrate method
• Threshold represents capacity
above which line is overloaded
11
Ruatoria Load Growth ScenarioAverage Load Versus Peak Load for 10% Load Growth of Ruatoria Feeder
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Year
Tota
l Loa
d (k
W)
Average (kW)Maximum (kW)
Threshold (kW)
Peak load DE requirementPeak load DE requirement
12
Direct & Indirect Annual O&M Costs (Derived from Asset Management Plan and Asset Accounting Spreadsheets)
Direct Costs = $935 / km / Year Indirect Costs = $66 / Connection / Year
Hypothetical cost of reinvestment once existing infrastructure is replaced Annual reinvestment cost = {ODRC x 2} / 40 (lifetime) ODRC = Optimized Depreciation Replacement Cost
333No. of Connections
$40,678.0020.000Ruatoria: H. RuatoriaAnnual O&M CostsLength (km)FEEDER
333No. of Connections
$40,678.0020.000Ruatoria: H. RuatoriaAnnual O&M CostsLength (km)FEEDER
Total Return = Annual O&M Costs + Annual Reinvestment
$40,678.00Annual O&M Costs
$74,028.00$33,350Ruatoria: H. RuatoriaTotal Annual RequiredReinvestment / Yr.FEEDER
$40,678.00Annual O&M Costs
$74,028.00$33,350Ruatoria: H. RuatoriaTotal Annual RequiredReinvestment / Yr.FEEDER
13
Grid Upgrade Deferral Assumptions for 10% Growth Rate
Note(1): Planning Horizon = Furthest Extent of Asset Investment (max. = 100).Note(2): Deferral time = Duration of DER project (1 to 30 years (max)).
Parameters Variable UnitsFeeder Capacity Threshold, C(T) 1,600.0 kWNetwork Finite Planning Horizon, n 40.0 years Note(1)(Max.) Network Investment Deferral Time, Dt 20.0 years Note(2)Utility Cost of Capital (Borrowing), r 10.0% as shownInflation Rate Net of Technology Progress, i 3.0% as shownCapacity Deferred By Dt Years 6,473.0 kWPW Marginal Distribution Capacity Cost, MDCC $739,063.44 as shownPW MDCC ($/kW/Yr) $99.37 $/kW/YrPW MDCC ($/kWh/Yr) $0.0807 $/kWh/Yr
To illustrate the methodology and impacts, the 10% loadgrowth rate scenario is chosen in this presentation
14
Assumed DE Capital CostsHydro & Wind Capital Cost: O&M = 2% of Capital Cost / YearPV & SHW Capital Cost: O&M = 0.5% of Capital Cost / Year
Diesel Genset Capital Cost: O&M = 5% of Capital Cost / Year
$100
$1,000
$10,000
$100,000
0 1 10 100 1,000 10,000
Size, kW
Cap
ital C
ost,
$/kW
HydroWindPhotovoltaicSolar Hot WaterGensetLog. (Photovoltaic)Log. (Hydro)Log. (Wind)Log. (Solar Hot Water)Log. (Genset)
15
Inputs to the Model:RE Supply Profiles are required
Higher the detail, the better the accuracy of the costs predicted
Supply factor curves, derived from recorded time sequence data
Local DE supply is used to support capacity shortfall in the distribution system
RE is the preferred local DE supply option to make up the peak load shortfall, with fueled DG (e.g. diesel genset) making up the balance
16
Flow-of-River Hydro Electric Power
1815
2229
3643
5057
6471
7885
9299
106113
120127
134141
148155
162169
176
0:30 2:00 3:30 5:00 6:30 8:00 9:30
11:0
0
12:3
0
14:0
0
15:3
0
17:0
0
18:3
0
20:0
0
21:3
0
23:0
0
0
200
400
600
800
1,000
1,200
Flow
(m3/
s)
Day of Year /...
Time of Day
1/2 Hourly Water Flow (in cubic metres per second) for an Actual River for Day 1 to 182 of a Normal Calendar Year
0.00-200.00 200.00-400.00400.00-600.00 600.00-800.00800.00-1000.00 1000.00-1200.00
17
HEP Supply Factor for RiverflowHEP Supply Curve
0.000
0.100
0.200
0.300
0.400
0.500
0.600
0.700
0.800
0.900
1.000
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Percentage of Max. Capacity Available
Supp
ly F
acto
r (A
vera
ge D
eliv
ered
/Tur
bine
Rat
ing)
18
Wind Turbine Generator (WTG) Half-Hourly Profiles
1815
2229
3643
5057
6471
7885
9299
106113
120127
134141
148155
162169
176
0:30 2:00 3:30
5:00 6:30 8:00 9:30
11:0
0
12:3
0
14:0
0
15:3
0
17:0
0
18:3
0
20:0
0
21:3
0
23:0
0
0100200
300400500
600700800
9001000
1100
Cap
acity
(kW
)
Time of Day
1/2 Hourly Load Profile for 1 MW WTG for Day 1 to 182 of a Normal Calendar Year (Annual Wind Speed = 6m/s)
0-100 100-200 200-300 300-400400-500 500-600 600-700 700-800800-900 900-1000 1000-1100
19
Photovoltaic Half-Hourly Profiles
1815
2229
3643
5057
6471
7885
9299
106113
120127
134141
148155
162169
176
0:30 2:00 3:30 5:00 6:30 8:00 9:30
11:0
0
12:3
0
14:0
0
15:3
0
17:0
0
18:3
0
20:0
0
21:3
0
23:0
0
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
Cap
acity
(kW
)
Time of Day
1/2 Hourly Load Profile for 1 kW PV System for Day 1 to 182 of a Normal Calendar Year
0.00-0.10 0.10-0.20 0.20-0.30 0.30-0.400.40-0.50 0.50-0.60 0.60-0.70 0.70-0.800.80-0.90 0.90-1.00
20
Solar Hot Water Contribution to Electrical Heating Demand
0:001:00
2:003:00
4:005:00
6:007:00
8:009:00
10:0011:00
12:0013:00
14:0015:00
16:0017:00
18:0019:00
20:0021:00
22:00
23:00
0
0.5
1
1.5
2
kW E
lect
rical
Hot
W
ater
Equ
ival
entTime of Day
Month of Year
Heating Profiles Contributed by a 4m2 Solar Hot Water System
0-0.5 0.5-1
1-1.5 1.5-2
The Solar Hot Water profile is significantly different to the PV profile because it is assumed that electrical water heating (the load that is replaced by SHW) takes place during the off-peak period: 11pm to 7am (used in ripple-relay control of domestic water cylinders (boilers) in many parts of NZ.
21
Results: Net DE Cost-Benefit
Total costs – capital investments, maintenance, operating costs and fuel costs etc., calculated as a net present value (NPV) for both the renewable and fuel-based DE options.
Total benefits – line upgrade deferral, transmission savings, grid-supporting and non-grid energy production less loss of distribution earnings to the network from using local energy, calculated as a NPV for both renewables and fuel-based DE.
NPVs calculated over a 20-year project lifecycle, assuming a 10% utility cost of capital interest rate, and a 3% inflation rate net of technology progress.
22
RE-Genset Cost-Benefit AnalysisComparison of Net-Benefits and Net-Costs from Various RE-Genset Combinations
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
$9,000,000
$10,000,000
20Gen
/80Hyd
ro B
enefit
20Gen
/80Hyd
ro C
ost
20Gen
/80W
ind Ben
efit
20Gen
/80W
ind Cos
t
20Gen
/80PV B
enefit
20Gen
/80PV C
ost
20Gen
/80SHW
Ben
efit
20Gen
/80SHW
Cos
t
50Gen
/50Hyd
ro B
enefit
50Gen
/50Hyd
ro C
ost
50Gen
/50W
ind Ben
efit
50Gen
/50W
ind Cos
t
50Gen
/50PV B
enefit
50Gen
/50PV C
ost
50Gen
/50SHW
Ben
efit
50Gen
/50SHW
Cos
t
80Gen
/20Hyd
ro B
enefit
80Gen
/20Hyd
ro C
ost
80Gen
/20W
ind Ben
efit
80Gen
/20W
ind Cos
t
80Gen
/20PV B
enefit
80Gen
/20PV C
ost
80Gen
/20SHW
Ben
efit
80Gen
/20SHW
Cos
t
100G
en B
enefi
t
100G
en C
ost
RE-Genset Combination
NPV
of B
enef
it / C
ost
Renewable Benefit – Cost of distribution revenue loss
Genset Benefit – Cost of distribution revenue loss
Renewable Cost
Genset Cost
23
RE-Genset Cost-Benefit AnalysisAnnualised Return on Investment (ROI) from Investing in Different RE-Genset Combinations
-2.0%
-1.0%
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%
20Gen/80Hydro Benefit
20Gen/80Wind Benefit
20Gen/80PV Benefit
20Gen/80SHW Benefit
50Gen/50Hydro Benefit
50Gen/50Wind Benefit
50Gen/50PV Benefit
50Gen/50SHW Benefit
80Gen/20Hydro Benefit
80Gen/20Wind Benefit
80Gen/20PV Benefit
80Gen/20SHW Benefit
100Gen Benefit
RE-Genset Combination
RO
I / Y
r, A
nnua
lised
ove
r 20
Year
s (%
)
Net Cost
Net Benefit
24
R.E. Only Cost-Benefit for Different RatiosNet RE Cost-Benefit from Different Renewable Ratios in the Genset-Renewable DE Mix
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
$9,000,000
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
Percentage of Renewable Present
Net
Cos
t-Ben
efit
in N
PV (O
ver 2
0 Ye
ars)
Hydro-BenefitWind-BenefitPV-BenefitSHW-BenefitHydro-CostWind-CostPV-CostSHW-Cost
Benefit
Cost
Benefit
Cost
25
Total D.E. Cost-Benefit for Different Ratios
Net DE [RE+Genset] Cost-Benefit from Different Renewable Ratios in the Genset-Renewable DE Mix
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
$9,000,000
$10,000,000
$11,000,000
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
Percentage of Renewable Present
Net
Cos
t-Ben
efit
in N
PV (O
ver 2
0 Ye
ars)
Hydro-DE CostWind-DE CostPV-DE CostSHW-DE CostHydro-BenefitWind-BenefitPV-BenefitSHW-Benefit
Benefit
Cost
Benefit
Cost
26
Line Upgrade Deferral Valuation Methodologies Used
Two different methods were used to calculate the value provided by deferring line upgrades for capacity reasons.
Both methods calculated the network capacity requirements from D.E. for every half-hour over a 20-yr lifetime.
Capacity valuation is based on the peak (maximum) capacity delivered by D.E. each year (benefits fuel-driven D.E. systems).
Energy valuation is based on the total (sum) energy delivered by D.E. each year (benefits R.E.-driven D.E. systems).
Net Present Valuation (NPV) of Capacity is greater in the early years, while NPV of Energy is greater in the latter years.
Overall, the energy NPV over the 20-yr project lifetime is greater than the capacity NPV.
27
Comparison of kW- vs. kWh-driven Support
Comparison of Net Benefit from Capacity-Driven vs. Energy-Driven Line Upgrade Deferral
-$2,000,000
-$1,000,000
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
kW-Focus kWh-Focus
NPV
for L
ifetim
e Be
nefit
Disc. Distribution (kWh)
Disc. Grid-Supporting Energy (kWh)Disc. Trans. Saving (kW)Disc. Upgrade Deferral (kW)
Line upgrade deferral value based on kW capacity valuation methodology
Line upgrade deferral value based on kWh energy valuation methodology
Relates to energy supplied only during peak
periods related to grid-support
Distribution feeder peak load
reduction corresponding to
GXP peak load reduction
Distribution revenue lost
Peak period kW capacity valuation for line
upgrade deferral
Peak period kWh
energy valuation for line
upgrade deferral
28
Key Points Identified
Despite greater discounting of long-term capacity / energy benefits, the overall (summation) financial benefit of discounted kWh energy valuation methodology is greater than the discounted kW capacity valuation methodology.
This implies minimum-cost to network-operated DE with capacity-driven valuation (e.g. large-scale DE with Orion).
This implies maximum-benefit to customer-operated DE with energy-driven valuation (e.g. small-scale DE with Orion).
29
Energy NPV Time-series for Line Upgrade Deferral
NPV of energy delivered for line upgrade deferral, transmission savings at GXP, wholesale energy sold (providing grid-support) and loss of distribution earnings were calculated and compared for each year, using 100% diesel genset D.E. as the base-case.
Other D.E. systems with a renewable energy component, also include NPV of surplus wholesale energy sold and loss of distribution earnings, notrelated to line upgrade deferral.
30
100/0% Genset-RE DE AnalysisLine Upgrade Deferral Met By 100% Genset and 0% Renewable (RE)
-$200,000
-$100,000
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
$900,000
$1,000,000
$1,100,000
$1,200,000
$1,300,000
$1,400,000
$1,500,000
$1,600,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
No. of Years Line Upgrade Deferred
Net P
rese
nt V
alue
of N
et A
nnua
l DE
Bene
fit
Gen Distribution Loss (kWh)Gen Grid-Supporting Energy (kWh)
Gen Trans. Saving (kW)Gen Upgrade Deferral (kWh)
Peak period kWh energy valuation for line upgrade
deferral
Example: 50/50% Fuel-Driven Diesel Genset-Renewable DE Ratio
• A comparison of different renewable
to fuel-driven (diesel) genset ratios
was made: 0/100%, 20/80%,
50/50% and 80/20% based upon the
actual kW sizing (name-plate) of
the individual DE systems.
The annual installation of
D.E. capacity matches the
shortfall in distribution
system capacity.
32
50/50% Genset-Hydro DE AnalysisLine Upgrade Deferral Met By 50% Genset and 50% Hydro DE
-$200,000
-$100,000
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
$900,000
$1,000,000
$1,100,000
$1,200,000
$1,300,000
$1,400,000
$1,500,000
$1,600,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
No. of Years Line Upgrade Deferred
Net P
rese
nt V
alue
of N
et A
nnua
l DE
Bene
fit
RE Non-Grid-Supporting Energy (kWh)Gen Distribution Loss (kWh)
RE Distribution Loss (kWh)Gen Grid-Supporting Energy (kWh)
RE Grid-Supporting Energy (kWh)
Gen Trans. Saving (kW)RE Trans. Saving (kW)Gen Upgrade Deferral (kWh)
RE Upgrade Deferral (kWh)
33
50/50% Genset-Wind DE Analysis Line Upgrade Deferral Met By 50% Genset and 50% WTG DE
-$200,000
-$100,000
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
$900,000
$1,000,000
$1,100,000
$1,200,000
$1,300,000
$1,400,000
$1,500,000
$1,600,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
No. of Years Line Upgrade Deferred
Net P
rese
nt V
alue
of N
et A
nnua
l DE
Bene
fit
RE Non-Grid-Supporting Energy (kWh)Gen Distribution Loss (kWh)
RE Distribution Loss (kWh)Gen Grid-Supporting Energy (kWh)
RE Grid-Supporting Energy (kWh)
Gen Trans. Saving (kW)RE Trans. Saving (kW)Gen Upgrade Deferral (kWh)
RE Upgrade Deferral (kWh)
34
50/50% Genset-PV DE AnalysisLine Upgrade Deferral Met By 50% Genset and 50% PV DE
-$200,000
-$100,000
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
$900,000
$1,000,000
$1,100,000
$1,200,000
$1,300,000
$1,400,000
$1,500,000
$1,600,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
No. of Years Line Upgrade Deferred
Net P
rese
nt V
alue
of N
et A
nnua
l DE
Bene
fit
RE Non-Grid-Supporting Energy (kWh)Gen Distribution Loss (kWh)
RE Distribution Loss (kWh)Gen Grid-Supporting Energy (kWh)
RE Grid-Supporting Energy (kWh)
Gen Trans. Saving (kW)RE Trans. Saving (kW)Gen Upgrade Deferral (kWh)
RE Upgrade Deferral (kWh)
35
50/50% Genset-SHW DE AnalysisLine Upgrade Deferral Met By 50% Genset and 50% SHW DE
-$200,000
-$100,000
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
$900,000
$1,000,000
$1,100,000
$1,200,000
$1,300,000
$1,400,000
$1,500,000
$1,600,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
No. of Years Line Upgrade Deferred
Net P
rese
nt V
alue
of N
et A
nnua
l DE
Bene
fit
RE Non-Grid-Supporting Energy (kWh)Gen Distribution Loss (kWh)
RE Distribution Loss (kWh)Gen Grid-Supporting Energy (kWh)
RE Grid-Supporting Energy (kWh)
Gen Trans. Saving (kW)RE Trans. Saving (kW)Gen Upgrade Deferral (kWh)
RE Upgrade Deferral (kWh)
Influence of Carbon Tax and Fuel Costs on Diesel Price
• Base-case assumes an annual increase of 2% / year in the
price of diesel, with a starting price of: $1.00 / litre.
• More dramatic (exaggerated) fuel price increases of:
5 & 10% / year are included to account for
potential scarcity of fuel at some
future date.
• Initial fuel starting prices of $1.50
& $2.00 / litre are also considered
to account for potential carbon taxing.
(Fuel price includes an assumed carbon tax component).
37
Comparison of Net-Benefits and Net-Costs from Various RE-Genset Combinations
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
$9,000,000
$10,000,000
20Gen
/80Hyd
ro B
enefit
20Gen
/80Hyd
ro C
ost
20Gen
/80W
ind Ben
efit
20Gen
/80W
ind Cos
t
20Gen
/80PV B
enefit
20Gen
/80PV C
ost
20Gen
/80SHW
Ben
efit
20Gen
/80SHW
Cos
t
50Gen
/50Hyd
ro B
enefit
50Gen
/50Hyd
ro C
ost
50Gen
/50W
ind Ben
efit
50Gen
/50W
ind Cos
t
50Gen
/50PV B
enefit
50Gen
/50PV C
ost
50Gen
/50SHW
Ben
efit
50Gen
/50SHW
Cos
t
80Gen
/20Hyd
ro B
enefit
80Gen
/20Hyd
ro C
ost
80Gen
/20W
ind Ben
efit
80Gen
/20W
ind Cos
t
80Gen
/20PV B
enefit
80Gen
/20PV C
ost
80Gen
/20SHW
Ben
efit
80Gen
/20SHW
Cos
t
100G
en B
enefi
t
100G
en C
ost
RE-Genset Combination
NPV
of B
enef
it / C
ost
Renewable Benefit – Cost of distribution revenue loss
Genset Benefit – Cost of distribution revenue loss
Renewable Cost
Genset Cost
Base Case: $1.00/l inc. at 2%/yr
38
Starting Price: $1.00/l inc. at 5%/yrComparison of Net-Benefits and Net-Costs from Various RE-Genset Combinations
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
$9,000,000
$10,000,000
$11,000,000
20Gen
/80Hyd
ro B
enefit
20Gen
/80Hyd
ro C
ost
20Gen
/80W
ind Ben
efit
20Gen
/80W
ind Cos
t
20Gen
/80PV B
enefit
20Gen
/80PV C
ost
20Gen
/80SHW
Ben
efit
20Gen
/80SHW
Cos
t
50Gen
/50Hyd
ro B
enefit
50Gen
/50Hyd
ro C
ost
50Gen
/50W
ind Ben
efit
50Gen
/50W
ind Cos
t
50Gen
/50PV B
enefit
50Gen
/50PV C
ost
50Gen
/50SHW
Ben
efit
50Gen
/50SHW
Cos
t
80Gen
/20Hyd
ro B
enefit
80Gen
/20Hyd
ro C
ost
80Gen
/20W
ind Ben
efit
80Gen
/20W
ind Cos
t
80Gen
/20PV B
enefit
80Gen
/20PV C
ost
80Gen
/20SHW
Ben
efit
80Gen
/20SHW
Cos
t
100G
en B
enefi
t
100G
en C
ost
RE-Genset Combination
NPV
of B
enef
it / C
ost
RE Benefit
Diesel Benefit
RE Cost
Diesel Cost
39
Starting Price: $1.00/l inc. at 10%/yrComparison of Net-Benefits and Net-Costs from Various RE-Genset Combinations
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
$9,000,000
$10,000,000
$11,000,000
$12,000,000
20Gen
/80Hyd
ro B
enefit
20Gen
/80Hyd
ro C
ost
20Gen
/80W
ind Ben
efit
20Gen
/80W
ind Cos
t
20Gen
/80PV B
enefit
20Gen
/80PV C
ost
20Gen
/80SHW
Ben
efit
20Gen
/80SHW
Cos
t
50Gen
/50Hyd
ro B
enefit
50Gen
/50Hyd
ro C
ost
50Gen
/50W
ind Ben
efit
50Gen
/50W
ind Cos
t
50Gen
/50PV B
enefit
50Gen
/50PV C
ost
50Gen
/50SHW
Ben
efit
50Gen
/50SHW
Cos
t
80Gen
/20Hyd
ro B
enefit
80Gen
/20Hyd
ro C
ost
80Gen
/20W
ind Ben
efit
80Gen
/20W
ind Cos
t
80Gen
/20PV B
enefit
80Gen
/20PV C
ost
80Gen
/20SHW
Ben
efit
80Gen
/20SHW
Cos
t
100G
en B
enefi
t
100G
en C
ost
RE-Genset Combination
NPV
of B
enef
it / C
ost
RE Benefit
Diesel Benefit
RE Cost
Diesel Cost
40
Return on Investment of D.E. Systems
A comparison of the annual ROI for different Diesel-Renewable D.E. system combinations (hybrids) was compared.
These systems show the influence of increasing the diesel fuel component of the total D.E. mix from 20% to 100% of the capacity requirement for line upgrade deferral each year.
Raising the initial fuel price and accelerating the annual price increase has a significant influence on the optimum diesel-renewable energy mix.
41
ROI / yr for Genset-Hydro DE SystemsInfluence of Hydro on Rising Diesel Prices
-2%
0%
2%
4%
6%
8%
10%
20% 30% 40% 50% 60% 70% 80% 90% 100%
Percentage of Capacity Supplied by Diesel
Ann
ual R
etur
n on
Inve
stm
ent (
RO
I)
Hydro ($1.00@2%/yr)
Hydro ($1.50@2%/yr)
Hydro ($2.00@2%/yr)
Hydro ($1.00@5%/yr)
Hydro ($1.50@5%/yr)
Hydro ($2.00@5%/yr)
Hydro ($1.00@10%/yr)
Hydro ($1.50@10%/yr)
Hydro ($2.00@10%/yr)
Optimum ROI for $1.00 & 2%/yr inc. $1.50 & 2%/yr inc. $1.00 & 5%/yr inc.
Optimum ROI for $2.00 & 2%/yr inc. $1.50 & 5%/yr inc. $2.00 & 5%/yr inc. $1.00 & 10%/yr inc. $1.50 & 10%/yr inc. $2.00 & 10%/yr inc.
42
ROI / yr for Genset-Wind DE SystemsInfluence of Wind on Rising Diesel Prices
-2%
0%
2%
4%
6%
8%
10%
20% 30% 40% 50% 60% 70% 80% 90% 100%
Percentage of Capacity Supplied by Diesel
Ann
ual R
etur
n on
Inve
stm
ent (
RO
I)
Wind ($1.00@2%/yr)
Wind ($1.50@2%/yr)
Wind ($2.00@2%/yr)
Wind ($1.00@5%/yr)
Wind ($1.50@5%/yr)
Wind ($2.00@5%/yr)
Wind ($1.00@10%/yr)
Wind ($1.50@10%/yr)
Wind ($2.00@10%/yr)
Optimum ROI for $1.00 & 2%/yr inc. $1.50 & 2%/yr inc. $1.00 & 5%/yr inc.
Optimum ROI for $2.00 & 2%/yr inc. $1.50 & 5%/yr inc. $2.00 & 5%/yr inc. $1.00 & 10%/yr inc. $1.50 & 10%/yr inc. $2.00 & 10%/yr inc.
43
ROI / yr for Genset-PV DE SystemsInfluence of PV on Rising Diesel Prices
-4%
-2%
0%
2%
4%
6%
8%
10%
20% 30% 40% 50% 60% 70% 80% 90% 100%
Percentage of Capacity Supplied by Diesel
Ann
ual R
etur
n on
Inve
stm
ent (
RO
I)
PV ($1.00@2%/yr)
PV ($1.50@2%/yr)
PV ($2.00@2%/yr)
PV ($1.00@5%/yr)
PV ($1.50@5%/yr)
PV ($2.00@5%/yr)
PV ($1.00@10%/yr)
PV ($1.50@10%/yr)
PV ($2.00@10%/yr)
Optimum ROI for all scenarios
44
ROI / yr for Genset-PV DE SystemsInfluence of PV on Rising Diesel Prices
-4%
-2%
0%
2%
4%
6%
8%
10%
20% 30% 40% 50% 60% 70% 80% 90% 100%
Percentage of Capacity Supplied by Diesel
Ann
ual R
etur
n on
Inve
stm
ent (
RO
I)
PV ($1.00@2%/yr)
PV ($1.50@2%/yr)
PV ($2.00@2%/yr)
PV ($1.00@5%/yr)
PV ($1.50@5%/yr)
PV ($2.00@5%/yr)
PV ($1.00@10%/yr)
PV ($1.50@10%/yr)
PV ($2.00@10%/yr)
Optimum ROI for all scenarios
45
Conclusions
Future fuel price volatility and uncertainty with availability of supply and global warming taxation indicates a preference to at least combine diesel with a renewable component to minimize risk.
Some scenarios, e.g. hydro and wind, indicate best annual ROI includes a 20-80% renewable energy component.
This methodology demonstrates that the accumulated benefits of localized distributed energy (kWh) and capacity (kW) support exceed the costs.
AN investment strategy to replace line capacity upgrades with D.E. also offers a trade-off between direct ROI and intermittent renewable energy.
Net benefits and costs will vary with differing stakeholder / user-operator perspectives.
This analysis shows that for load growth scenarios, distributionnetworks should seriously consider a D.E. investment strategy.
Way Forward
• Identify distribution networks with capacity constraints and increasing customer demand.
• Facilitate collaborative research and development amongst networks with complimentary interests.
• Encourage the Electricity Commission & Transpower to work together with distribution networks to standardize such proceedings and establish industrial best practice.
• Develop a regulatory framework which encourages a decentralised approach to infrastructure development.