Line Of Balance Dr. Ahmed Elyamany

Transcript of Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize...

Page 1: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Line Of BalanceDr. Ahmed Elyamany

Page 2: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Intended Learning Outcomes

•Define the principles of Line of Balance (LOB)

•Demonstrate the application of LOB

•Understand the importance of LOB

•Understand the process of applying LOB

2

Page 3: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Location Based Management

•LBM is a production control system that integrates planning, scheduling, and control.

•Tasks are defined by production rates,

resource consumption and quantities.

•The placement and interrelated dependencies of tasks are defined by technical dependencies, locations, and continuity requirements.

3

Page 4: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Location Based Management

�Is a scheduling and control technique that is believed to offer advantages in building construction compared with CPM and PERT.

�LBM includes important aspects that are omitted in CPM and PERT such as continuous work flow and location constraints.

4

Page 5: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Location Based Management

•LBM combines production rates, quantities, and resource consumption

in specific locations to estimate the duration of tasks.

•In LBM, similar activities are collected in tasks and displayed as a single line (production lines or flow lines) over multiple locations.

5

Page 6: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Location Based Management

The result allows schedulers and

managers to evaluate whether

construction crews can perform their

work undisturbed by aligning rates

of production.

6

Page 7: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Activity-basedversus

location-basedscheduling and control

7

Page 8: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

�Construction scheduling and control is divided into two main methodologies:

�Activity-based and Location-based.

�Activity-based methods include The critical path method (CPM) and the program evaluation and review technique (PERT).

�Activity-based methods depend solely on technical relationships between activities in the schedules governed by technical constraints.

•Activity-based methods highlight the activities that should be considered critical

8

Page 9: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Activity-basedmethods criticism

•Do not include any algorithm, calculation, or consideration for solving the practical

organization problems of the on-site production process.

•The assumptions that unlimited resources

are available and that personnel can be

hired and fired freely are erroneous

9

Page 10: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Activity-basedmethods criticism

•Were never intended for projects that are sensitive to resource limitations and continuous workflow because the methods originated in the aerospace and military industries.

•Lacking work continuity and learning effects

10

Page 11: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Activity-basedmethods criticism

•Does not contain elements that ensure a smooth procession of crews from unit (Location) to unit with no conflict and no idle time for workers and equipment.

•Difficult to manage on repetitive projects, due to discrete management of similar activities in different locations.

11

Page 12: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Activity-basedmethods criticism

•Many attempts to solve the short comings of

the original CPM and PERT techniques:•Resource leveling

•Optimization of cost and time relationships.

•Communicative abilities of CPM addressed by linking CPM schedules with 3D modeling of building components.

•Improving health and safety procedures and flow optimization through lean construction

principles.12

Page 13: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

location-based methods

�line of balance scheduling,

�linear scheduling method,

�vertical production method,

�Repetitive project model,

�velocity diagrams,

�time space scheduling,

�Construction planning technique,

�time Location Matrix Model,

�disturbance scheduling

�horizontal and Vertical logic scheduling

13

Contains numerous methods that only differ

slightly from modern LBM. These include:

Page 14: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

14

Activity Based Schedule (CPM)

Location Based Schedule

Many

activities

Page 15: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Location Based Management

Working at the same time and in

the same location negativelyaffects the work of construction crews because technical

constraints are not respected.

15

Page 16: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Location Based Management

The location-based schedule

illustrates areas not utilized for production, allowing the project

manager to exploit vacant areas

of the build site by moving work

crews to those locations.

16

Page 17: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Location Based Management

The location-based schedule illustrates productivity problems.

The flow lines reveal tasks that are

completed at a comparatively slower

rate, which not only affects a project’s

lead-time; it can also result in

discontinuous production.

17

Page 18: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Location Based Management

18

Time

LocationHigh productivity rate

Low productivity rate

Page 19: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Line of Balance (LOB)

•Definition

A simple diagram to show location and time at which a certain crew will be working on a given operation.

�Is a Good Visual tool that lets us see if a construction program can be achieved with the minimum waiting time between tasks

19

Page 20: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Line of Balance (LOB)

•Is a scheduling methodology to

optimize resources used.

•Resources are used to balance

out tasks by adding additional

crews to slower tasks.

•The fully aligned schedules contain no float. 20

Page 21: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

21

Partially balanced schedule

Fully balanced schedule

Original Schedule using one crew for each task

Page 22: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Line of Balance (LOB)

•Is primarily used on projects that have repeated elements like Highways, Pipelines, High-rise buildings, hotel bedrooms, bridge etc.

22

Page 23: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Benefits of LOB

�Continuous resource use

�Less starts and stops

�Crews will develop a learning momentum

�Improve productivity by 20 %

�Save money and time

�Faster scheduling process

�Good Visual control

23

Page 24: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Activity-based VS

Location-based

24

Page 25: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Activity-based

•30 floors, 4 activities in each location = 120 activities

•Formwork-reinforcement-pouring on the same floor = 60 links

•Pouring – formwork next floor = 29 links

•Pouring – finishes two floors below = 28 links

•Internal links in finishes to prevent resource overlapping = 29 links

•Total: 120 CPM activities, 266 links25

Page 26: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Activity-based

26

Formwork

Floor 1

Reinforcement

Floor 1

Pouring Conc.

Floor 1

Finishing

Floor 1

Formwork

Floor 2

Reinforcement

Floor 2

Pouring Conc.

Floor 2

Finishing

Floor 2

Formwork

Floor 3

Reinforcement

Floor 3

Pouring Conc.

Floor 3

Finishing

Floor 3

Page 27: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Location-based

•4 tasks flowing through locations

•4 links between activities

•4 links inside activities

•Total: 4 tasks, 8 link

�Less tasks

�Less links

27

Page 28: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Location-based

28

Time

Units

3

2

1

30

.

.

.

.

Page 29: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Superior project control

•Easy to interpret

•Clear uncomplicated displays

•Simple to manage

•Easy to monitor

•Effortless progress updates

•Effective control

29

Page 30: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

LOB Calculations

•The objective of using LOB is to achieve a resource-balanced

schedule by determining the suitable crew size and number of crews to employ in each repetitive activity.

30

Page 31: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

LOB Calculations

•This is done such that: 1. the units are delivered with a rate

that meets a pre-specified deadline

2. the logical CPM network of each unit is respected

3. crews’ work continuity is maintained.

31

Page 32: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

LOB Calculations

•The analysis also involves determining the start and finish

times of all activities in all units and the crews’ assignments.

32

Page 33: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

LOB Diagrams

1. Production Diagram

Shows the relationships of the activities for a

single unit.

33

A

B

C D E

Page 34: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

LOB Diagrams

2. Objective Diagram

Used to plot the planned or actual number

of units produced vs. time.

34

Time

A B C D E

40

51

16

10

B

C D E

A

Progress DiagramObjective Diagram

20

3028

Actual

Page 35: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

LOB Diagrams

3. Progress Diagram

Shows the number of units for which the

activity has completed .

3535

Time

A B C D E

40

51

16

10

B

C D E

A

Progress DiagramObjective Diagram

20

3028

Actual

Page 36: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Drawing the LOB Schedule

Time

Units

n

.

.

1

n - 1

t0 tf

R

tf

R= (n – 1)/(tf – t0)

Page 37: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Drawing the LOB Schedule

•Similar rates � parallel lines

•Different rates � lines not parallel

•Conflict points � at the last or first unit

Page 38: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

LOB Calculations

•The CPM-LOB formulation involve:•Crew synchronization

•Calculating resource needs

•Drawing the LOB schedule

38

Page 39: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Crew Synchronization

•A simple relationship between the duration taken by a crew in one unit (D) and the number of crews (C) to employ in a repetitive activity

39

Page 40: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Crew Synchronization

•Slope of the shaded triangle in becomes:

R = 1 / (D / C) Then: C = D x R

40

Crew 3

RCrew 1

Crew 2

RTime

Units

3

2

1

1 2 30D/C D/C D/C

Page 41: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Calculating Resource Needs

•Ri = (n – 1) / (Tf – T0)

•Ci = Di x Ri

•Cai = Round Up (Ci)

•Rai = Cai / Di

41

Page 42: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

B

Calculating Resource Needs

42

Time

Unitsn

.

.

.

2

1

A DC n - 1

C(2)

B(5)

D(5)A(5)

TF=3 C(2)

B(5)

D(5)A(5)

TF=3

C C

Page 43: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Example

43

A

B

C D E

N=61 units

Required ; draw LOB at month 16

Activity A B C D E

Production rate 3 5 5 3 1

No of crews 9 30 10 9 2

Page 44: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Example

•R = 1 / (D / C)

•D = C/R

44

Activity A B C D E

Production rate 3 5 5 3 1

No of crews 9 30 10 9 2

Duration 3 6 2 3 2

Page 45: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Example

45

0 3

A

3 3 6

0 6

B

0 6 6

6 8

C

6 2 8

8 11

D

8 3 11

11 13

E

11 2 13

0 0

Start

0 0 0

Page 46: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Example

For A: R=3, t0=3,

46

Time

Units

61

.

.

.

.

.

.

.

1

tf=3+(61-1)/3=23

For B: R=5, t0=6, tf=6+(61-1)/5=18

For C: RC=RB>RA, buffer from top

t0=25-(61-1)/5=13R=5, tf=23+2=25,

B

C

For D: R=3, t0=13+3=16, tf=16+(61-1)/3=36

For D: R=1, t0=16+2=18, tf=18+(61-1)/1=78

0 10 20 30 40 50 60 70 80

D E

18

3 6 13 1618

23 25 36 78

A

Page 47: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Example

For A: R=3, t0=3,

47

Time

Units

16=3+(x -1)/3, x=40

For B: R=5, t0=6, 16=6+(x -1)/5, x=51

For C: R=5, t0=13, 16=13+(x -1)/5, x=16

For D: R=3, t0=16,

For E: x=0

A B C D E

40

51

16

10

B

C D E

A

16=16+(x -1)/3, x=1

Progress Diagram Objective Diagram

20

3028

Actual

Planned

Page 48: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Example

48

B

C D E

A

Page 49: Line Of Balance - Weebly...Line of Balance (LOB) •Is a scheduling methodology to optimize resourcesused. •Resources are used to balance out tasksby adding additional crews to slower

Thanks