Ch-7 Assembly Line Balance

download Ch-7 Assembly Line Balance

of 42

Transcript of Ch-7 Assembly Line Balance

  • 8/11/2019 Ch-7 Assembly Line Balance

    1/42

    Balance 1

    Assembly Line Balance

  • 8/11/2019 Ch-7 Assembly Line Balance

    2/42

    Balance 2

    Assembly analysis

    Assembly Chart

    It shows the sequence of operations in puttingthe product together. Using the exploded drawing

    and the parts list, the layout designer will diagramthe assembly process.

    The sequence of assembly may have severalalternatives.

    Time standards are required to decide whichsequence is best. This process is known as assemblyline balancing.

  • 8/11/2019 Ch-7 Assembly Line Balance

    3/42

    Balance 3

    The Assembly Chart

    The ass

    embly chartof a toolbox

  • 8/11/2019 Ch-7 Assembly Line Balance

    4/42

    Balance 4

    Time Standards Are Required for Every Task

  • 8/11/2019 Ch-7 Assembly Line Balance

    5/42

    Balance 5

    Plant Rate and Conveyor Speed

    Conveyor speed is dependent on the number andunits needed per minute, the size of the unit, thespace between units. Conveyor belt speed is

    recorded in feet per minute.

    Example:

    Charcoal grill are in cartons 30X30X24 incheshigh. A total of 2,400 grills are required everyday.

  • 8/11/2019 Ch-7 Assembly Line Balance

    6/42

    Balance 6

    Plant Rate and Conveyor Speed

  • 8/11/2019 Ch-7 Assembly Line Balance

    7/42Balance 7

    Assembly line balancing

    The purpose of the assembly line balancing technique is:

    1. To equalize the work load among the assemblers2. To identify the bottleneck operation3. To establish the speed of the assembly line4. To determine the number of workstations5. To determine the labor cost of assembly and packout6. To establish the percentage workload of each operator7. To assist in plant layout8. To reduce production cost

    The assembly line balancing technique builds on:The assembly chart;Time standards;Takt time (minutes/piece) (Plant rate, R value,

    Pieces/minutes).

  • 8/11/2019 Ch-7 Assembly Line Balance

    8/42Balance 8

    Initial assembly line balancing of toolbox

    Takt time (for 2,000 units per shift, considering 10%

    downtime and 80% efficiency) = .173 minutes per unit.

  • 8/11/2019 Ch-7 Assembly Line Balance

    9/42Balance 9

    Assembly line balancing

    1. Cost of balancingSubassemblies that cost too high can be taken off the

    line.

    SA3 could be taken off the assembly line and handledcompletely separate from the main line and we can save money.SA3 .250 = 240 pieces per hour and .00417 hour each. If balanced,the standard would be 180 pieces per hour and .00557 hour each.

    .0057 balanced cost

    - .00417 by itself cost.00140 savings hour per unit

    X 500,000 units per year700 hours per year

    @ $15.00 per hour

    = $10,500.00 per year savings

  • 8/11/2019 Ch-7 Assembly Line Balance

    10/42

    Balance 10

    Assembly line balancing

    Subassemblies that can be taken off the line must be:

    1. Poorly loaded. The less percent that is loaded.For example, a 60 percent load on the assembly

    line balance would indicate 40 percent lost time.If we take this job off the assembly line (not tiedto the other operators), we could save 40 percentof the cost.

    2. Small parts that are easily stacked and stored.3. Easily moved. The cost of transportation and the

    inventory cost will go up, but because of betterlabor utilization, total cost must go down.

  • 8/11/2019 Ch-7 Assembly Line Balance

    11/42

    Balance 11

    Assembly line balancing

    2. Improvement of assembly lineImprove the busiest (100 percent) workstation first.

    (a) The busiest workstation is P.O. It has .167 minute of work to doper packer. The next closest station is A1 with .155 minute ofwork. As soon as we identify the busiest workstation, we identify

    it as the 100 percent station, and communicate that this timestandard is the only time standard used on this line from nowon. Every other workstation is limited to 360 pieces per hour.Even though other workstations could work faster, the 100percent station limits the output of the whole assembly line.

    (b) The total hours required to assemble one finished toolbox is.06960 hour. The average hourly wage rate times .06960 hourper unit gives us the assembly and packout labor cost. Again,the lower this cost is the better the line balance is.

  • 8/11/2019 Ch-7 Assembly Line Balance

    12/42

    Balance 12

    Assembly line balancing

  • 8/11/2019 Ch-7 Assembly Line Balance

    13/42

    Balance 13

    Assembly line balancing

  • 8/11/2019 Ch-7 Assembly Line Balance

    14/42

    Balance 14

    Assembly line balancing

    2. Improvement of assembly lineImprove the busiest (100 percent) workstation first.

    Look at the 100 percent station (P.O.).

    If we add a fourth packer, we will eliminate the 100 percent stationat P.O.

    Now the new 100 percent (bottleneck station) is A1 (93 percent).By adding this person, we will save 7 percent of 25 people or 1.75people and increase the percent load of everyone on the

    assembly line (except P.O.). We might now combine A1 and A2,and further reduce the 100 percent.

    The best answer to an assembly line balance problem is thelowest total number of hours per unit. If we add an additional

    person, that persons time is in the total hours.

  • 8/11/2019 Ch-7 Assembly Line Balance

    15/42

    Balance 15

    Step-by-step procedure for completing theassembly line balancing form

  • 8/11/2019 Ch-7 Assembly Line Balance

    16/42

    Balance 16

    Step-by-step procedure for completing theassembly line balancing form

    9. R valueThe R value goes behind each operation. The plant rate is thegoal of each workstation, and by putting the R value on eachline (operation), one keeps that goal clearly in focus.

    10. Cycle timeThe time standard.

    11. Number of stations

    12. Average cycle time

    Rtimecyclestationsofnumber

    stationsof#

    timecycletimecycleave.

  • 8/11/2019 Ch-7 Assembly Line Balance

    17/42

    Balance 17

    Step-by-step procedure for completing theassembly line balancing form

    13.Percentage load:

    The percentage load tells how busy each workstation is

    compared to the busiest workstation.

    The highest number in the average cycle time column 12 is

    the busiest workstation and, therefore, is called the 100 percentstation.

    Now every other station is compared to this 100 percent

    station by dividing the 100 percent average station time into

    every other average station time. The percent load is an

    indication of where more work is needed or where cost

    reduction efforts will be most fruitful. if the 100 percent station

    can be reduced by 1 percent, then we will save 1 percent for

    every workstation on the line.

  • 8/11/2019 Ch-7 Assembly Line Balance

    18/42

    Balance 18

    Step-by-step procedure for completing theassembly line balancing form

    13.Percentage load:

    Example: percent load of the toolbox assembly line balance

    In Figure 4-11, the average cycle times reveals that .167 is the

    largest number and is designated the 100 percent workstation.

    The percentage load of every other workstation is determined by

    dividing .167 into every other average cycle time:

    Operation SSSA1 = .153 / .167 = 92 percent

    SSA1 = .146 / .167 = 87 percent

    SSA2 = .130 / .167 = 78 percent

    and so on.

  • 8/11/2019 Ch-7 Assembly Line Balance

    19/42

    Balance 19

    Step-by-step procedure for completing theassembly line balancing form

    14.Hours per unit:

    Example: Hours per unit of the toolbox assembly line balance

    The .167 time standard is for one person, if considering the peoplenumber, the hour per unit will be:

    Two people = .00557 hour per unit

    Three people = .00835 hour per unit

    Four people = .01113 hour per unit

    hourperminutes60

    timecycleaverage%100h.p.u.

    unitperhour.0027860

    .167h.p.u.

  • 8/11/2019 Ch-7 Assembly Line Balance

    20/42

    Balance 20

    Step-by-step procedure for completing theassembly line balancing form

    15. Piece per hour:Inversion of hours per unit.

    16. Total hours per unitSum of the elements in column 14. For this example is .0696hour.

    17. Average hourly wage rate, say $15 per hour

    18. Labor cost per unit

    Total hours X average hourly wage

    19. Total cycle timeIt tells us what a perfect line balance would be.Our example 3.494 minutes divided by 60 minutes per hour

    equals .05823 hour per unit.

  • 8/11/2019 Ch-7 Assembly Line Balance

    21/42

    Balance 21

    Efficiency of the assembly line

    %100balanceline1000perhoursofSum

    1000perhoursofSumefficiencyLine

    %100balancelineunitperhoursofSum

    unitperhoursofSumefficiencyLine

    or

    For our example:

    %84%100

    0.06960

    0.05823efficiencyLine

  • 8/11/2019 Ch-7 Assembly Line Balance

    22/42

    Balance 22

    Analysis of single model assembly lines

    shw

    ap

    HS

    DR

    50

    Production Rate is given by

    where Rp= average hourly production rate, units/hr;

    Da= annual demand, units/year;

    Sw= number of shifts/week;

    Hsh= hrs/shift.

    This equation assume 50 weeks per year.

  • 8/11/2019 Ch-7 Assembly Line Balance

    23/42

    Balance 23

    Analysis of single model assembly lines

    p

    c

    R

    ET60

    The cycle time can be determined as

    where Tc= cycle time of the line, min./cycle;

    Rp= production rate, units/hr;

    E = line efficiency;

  • 8/11/2019 Ch-7 Assembly Line Balance

    24/42

    Balance 24

    Analysis of single model assembly lines

    The cycle rate can be determined as

    where Rc= cycle rate, cycles/hr;

    Tcis in min./cycle;

    Line efficiency E therefore defined as:

    cc T

    R60

    p

    c

    c

    p

    T

    T

    R

    RE

  • 8/11/2019 Ch-7 Assembly Line Balance

    25/42

    Balance 25

    Analysis of single model assembly lines

    The number of workers on the line can bedetermined as

    where w= number of workers on the line;

    WL = workload to be accomplished in a given time period.

    AT= available time in the period.

    AT

    WLw

    wcpTRWL TWc = work content time, min/piece.

  • 8/11/2019 Ch-7 Assembly Line Balance

    26/42

    Balance 26

    Analysis of single model assembly lines

    Using the previous equation, we also have

    The available time in the period,AT.

    c

    wc

    T

    ETWL60

    AT = 60E

    Substitute these terms for WL and AT into wequation, we can state:

    c

    wc

    TTw integerminimun*

    If we assume one worker per station, then this ratio alsogives the theoretical minimum number of workstations onthe line.

  • 8/11/2019 Ch-7 Assembly Line Balance

    27/42

    Balance 27

    Analysis of single model assembly lines

    Example

    A small electrical appliance is to be produced on a singlemodel assembly line. The work content of assembling theproduct has been reduced to the work elements listed intable below along with other information. The line is to bebalanced for an annual demand of 100,000 units per year.The line will be operated 50 weeks/yr, 5 shifts/wk, and 7.5hrs/shift. Manning level will be one worker per station.Previous experience suggests that the uptime efficiency for

    the line will be 96%, and repositioning time lost per cyclewill be 0.08 min. Determine (a) total work content timeTwc, (b) required hourly production rate Rpto achieve theannual demand, (c) Cycle time, and (e) service time Tstowhich the line must be balanced.

  • 8/11/2019 Ch-7 Assembly Line Balance

    28/42

    Balance 28

    Analysis of single model assembly lines

    Example

  • 8/11/2019 Ch-7 Assembly Line Balance

    29/42

    Balance 29

    Analysis of single model assembly lines

    Example

  • 8/11/2019 Ch-7 Assembly Line Balance

    30/42

    Balance 30

    Analysis of single model assembly lines

    Solution:

    units/hr33.53)5.7)(5(50

    000,100pR

    (b) The production rate is:

    (c) The cycle time Tcwith an uptime efficiency of 96% is:

    (a) The total work content time is:

    Twc= 4.0 min.

    .min08.133.53

    )96.0(60CT

  • 8/11/2019 Ch-7 Assembly Line Balance

    31/42

    Balance 31

    Analysis of single model assembly lines

    Solution:

    43.7intmin* c

    wc

    TTw

    (e) The average service time against which the line mustbe balanced is:

    (d) The theoretical minimum number of workers is given by:

    .min00.108.008.1 Rcs TTT

  • 8/11/2019 Ch-7 Assembly Line Balance

    32/42

    Balance 32

    Analysis of single model assembly lines

    The objective in line balancing is to distributethe total workload on the assembly line asevenly as possible among the workers

    w

    1i

    s )minimizeor)(minimize siwcs T(TTwT

    subject to:

    ikek(1) sTT

    and

    (2)all precedence requirements areobeyed.

  • 8/11/2019 Ch-7 Assembly Line Balance

    33/42

    Balance 33

    Analysis of single model assembly lines

    The algorithms are:

    1) Largest Candidate Rule

    2) Kilbridge and Wester method

    3) Ranked positional weights

  • 8/11/2019 Ch-7 Assembly Line Balance

    34/42

    Balance 34

    Largest Candidate Rule

    Step 1:Rank the Teks in the descending order.

    Step 2:Assign the elements to the worker at first stationby starting at the top of the list and selecting the firstelement that satisfies precedence requirements and doesnot cause the total sum of Tek at that station to exceed theallowable Ts; when an element is selected for assignmentto the station, start back at the top of the list forsubsequent assignments.

    Step 3: when no more element can be assigned withoutexceeding Ts, then proceed to the next station.

    Step 4:repeat steps 2 and 3 for as many additionalstations as necessary until all elements have beenassigned.

  • 8/11/2019 Ch-7 Assembly Line Balance

    35/42

    Balance 35

    Largest Candidate Rule

    Work elements sorted in descending order

  • 8/11/2019 Ch-7 Assembly Line Balance

    36/42

    Balance 36

    Largest Candidate Rule

    Solution:

    The largest candidate algorithm is carried out as presentedin table below. 5 workers and stations are required in thesolution. Balance efficiency is computed as:

    8.0)0.1(5

    0.4

    s

    wc

    wT

    TE

  • 8/11/2019 Ch-7 Assembly Line Balance

    37/42

    Balance 37

    Largest Candidate Rule

    Work elements assigned to stations by LCR

  • 8/11/2019 Ch-7 Assembly Line Balance

    38/42

  • 8/11/2019 Ch-7 Assembly Line Balance

    39/42

    Balance 39

    Analysis of single model assembly lines

    Kilbridge and Wester method

  • 8/11/2019 Ch-7 Assembly Line Balance

    40/42

    Balance 40

    Analysis of single model assembly lines

    Ranked positional weights

  • 8/11/2019 Ch-7 Assembly Line Balance

    41/42

    Balance 41

    Analysis of single model assembly lines

    Ranked positionalweights

    Kilbridge andWester method

    Largest CandidateRule

  • 8/11/2019 Ch-7 Assembly Line Balance

    42/42

    Analysis of single model assembly lines

    Automation, Production Systems, andComputer-Integrated Manufacturing, ByMikell P. Groover, 3rdedition, c2008.

    Manufacturing Facilities Design and MaterialHandling, By F. E. Meyers and M. P. Stephens,4th Edition, Prentice-Hall, Inc., 2010