Lesson Learn From Mission on Nepal Earthquake 2015
(The Gorkha Earthquake)
Major A K M Shakil Newaz
Director (Ops. & Maint.)
Team Leader
Dilip Kumar Ghose
Vice Principal Member
Md. Tanharul Islam
Senior Station Officer
Member
Md. Hafijur Rahman
Warehouse Inspector
Member
Muhammad Mamun
Warehouse Inspector
Member
![Page 2: Lesson Learn From Mission on Nepal Earthquake 2015 (The Gorkha Earthquake) Lesson Learn From Mission on Nepal Earthquake 2015 (The Gorkha Earthquake)](https://reader036.fdocuments.in/reader036/viewer/2022071718/56649edc5503460f94bec9b5/html5/thumbnails/2.jpg)
Gap Areas between Bangladesh and Nepal
Katmandu Dhaka
Total area Katmandu valley 570 Sq Km Total area Dhaka City 360 Sq Km
Total Population 25 lacs
Total Population 1 core 60 Lacs
Building 220000(approx) Building 400000(approx)
Cylinder Gas
Pipe Gas
Less soft soil area Large soft soil area (65%)
Gap Areas between Bangladesh and Nepal
![Page 3: Lesson Learn From Mission on Nepal Earthquake 2015 (The Gorkha Earthquake) Lesson Learn From Mission on Nepal Earthquake 2015 (The Gorkha Earthquake)](https://reader036.fdocuments.in/reader036/viewer/2022071718/56649edc5503460f94bec9b5/html5/thumbnails/3.jpg)
Gap Areas in Bangladesh following the context of Nepal Earthquake:Katmandu Dhaka
Nepal has National Emergency Operation Center (NEOC)
In Bangladesh, we do not have any full fledged Emergency Operation Center (EOC).
Less number high-rise buildings in Nepal .Only 12 High –rise building (16 storied building )
Mushrooming of high-rise buildings.
Number of open spaces are more in Nepal which are currently used as shelters
Less number of open spaces
Nepal has approved National Dead Body Management Act which was legal support in this earthquake disaster
Need to develop and approve such act
Old building Code 1980. People tend to ignore the building code while constructing new buildings in Nepal.
BNBC-1993. People tend to ignore the building code while constructing new buildings in Bangladesh. .
Gap Areas between Bangladesh and Nepal
![Page 4: Lesson Learn From Mission on Nepal Earthquake 2015 (The Gorkha Earthquake) Lesson Learn From Mission on Nepal Earthquake 2015 (The Gorkha Earthquake)](https://reader036.fdocuments.in/reader036/viewer/2022071718/56649edc5503460f94bec9b5/html5/thumbnails/4.jpg)
Katmandu DhakaThere is no database of Community Volunteers in Nepal
Maintain Database of Community Volunteers
No Industrial area Have number of Industrial area(Garments factory, chemical factory ,boiler etc)
No Designated team . FSCD having Designated USAR Team
No Inter operable communication System
No Inter operable communication system
Retrofit is done in some KPI Not done
Insufficient USAR equipments Insufficient USAR Equipments
Lack of awareness, drill and practice Lack of awareness ,drill and practice
No back up power supply No back up power supply
No back up communication system No back up communication system
Gap Areas between Bangladesh and Nepal
![Page 5: Lesson Learn From Mission on Nepal Earthquake 2015 (The Gorkha Earthquake) Lesson Learn From Mission on Nepal Earthquake 2015 (The Gorkha Earthquake)](https://reader036.fdocuments.in/reader036/viewer/2022071718/56649edc5503460f94bec9b5/html5/thumbnails/5.jpg)
Why was the Earthquake in Nepal on Saturday so deadly
High magnitude-7.8 on the Richter Scale (Most powerful in the region Shallow Hypocenter - Only 11 km below the Ground Cause landslide and Avalanches Significance After shock up to 6.7 on the Richter scale Very old and poor construction Not following the building code(Old building code NNBC-1980) Lack of Quick Response Measurably fail to asses the damage Fail to make the NEOC functional Fail to Organize SAR team Shortage of SAR equipments Lack of Coordination among the stake holder Unplanned relief operation RDC Fail to mobilize the foreign team quickly (custom clearance) Bad weather Fail to clear the supply road in time which delayed to decentralize the resources
![Page 6: Lesson Learn From Mission on Nepal Earthquake 2015 (The Gorkha Earthquake) Lesson Learn From Mission on Nepal Earthquake 2015 (The Gorkha Earthquake)](https://reader036.fdocuments.in/reader036/viewer/2022071718/56649edc5503460f94bec9b5/html5/thumbnails/6.jpg)
Positive aspect of Nepal Earthquake
25Aril was holiday all school ,college ,university n and offices were closed.
No Fire from gas or electricity Earth quake happened on day time Nepal does not have any industrial area Shallow lequiffication happened as because of earth structure There was no heavy traffic in the mobile communication after the
earthquake Nepal government provided free international and local phone calls for
the first one week. The earthquake was not stronger than the seismologist expected NEOC established on 2009 No commodity price hike Community people are the invaluable assets during any Crisis. Retrofit building have performed well.