Leon - Overview
-
Upload
leon-de-roock -
Category
Documents
-
view
98 -
download
0
Transcript of Leon - Overview
HUGENOTE TUNNEL
WORK EXPERIENCE
LEON DE ROOCK
1. Tunnel History
2. Technologies Used – My Involvement/Duties
a. Lighting
b. Fire Systems
c. PLC
d. Networks
e. Ventilation
f. Electrical HT Switchgear
g. SOS
h. CCTV
i. Traffic Control Systems
j. Toll Plaza Systems
k. Water systems
l. Health and Safety (HSE)
3. Achievements
4. Projects/Project Management
5. CV
Index
The entire tunnel is fitted out with fluorescent 4ft tubes and
there are three fluorescent tubes per phase with every tenth
light fitting that are an ups fitting.
During normal operations both sides are set at 65
percentage of the lumination setting where as during
emergency conditions the lamination is set at 100 percent.
The adaptation lightning system at the entrance/exit to
tunnel controls the lights so that the human eye can adapt
easily to different light levels inside the tunnel.
Here the systems were maintained are repairs were done
accordingly.
These systems are now absolute and as technical manager
with consultant engineer for SANRAL, we were busy in the
process of evaluating and procuring new systems and led
fittings from BECA/Schneider for replacement for existing
systems.
The tunnel in length are about 4Km, thus the tunnel are
splitted in half and each half are controlled by separated fire
control panels which in turn communicates with each other
and relay fire conditions to the plc’s to control the ventilation
system.
Heat detectors with a double knock are used and are
situated throughout the tunnel at 15m intervals.
The system is hardwired as well as Scada controlled to allow
redundancy in case of any failure due to server or network
issues.
This year capital work projects will commence to upgrade
the fire system as it also has come to end of life.
As technician I did all the , software setup and
maintenance on system.
The tunnel is controlled by Siemens S7 package and was one
of the first sites that operated on the S7 system in South
Africa.
The plc network consists of fibre optic profibus system. All the
plant variables and inputs are relayed to plc’s and then
process and displayed on a Scada system in the tunnel
control room via operator workstations.
My duties here were to repair and maintain the system at all
times as this were the hart beat of the tunnel.
Each cross connection in the tunnel was fitted with network
switches and is linked with each other by means of a
redundant fibre optic network.
As single fibre optics were installed in the tunnel, the tunnel
also still used multimode as existing systems still has to be
accommodated to interface with present systems.
Here I installed and setup network switches and created
Vlan’s to accommodate new CCTV, SOS and well as
management systems to integrate with servers to allow
functionally.
The tunnel is equipped with two 400KW fresh air and two
1000KW exhaust fans.
The fresh air fans have a two speed controlled operation and
blades can be controlled between 13-45 degrees.
The exhaust fans are mainly used in fire emergency
conditions as well in cases where poor visibility in the tunnel
requires urgent intervention.
As the technician the electronic side of this system was my
responsibility and together with the electrician and
mechanical fitter to do repairs and to keep the operation of
the ventilation system at a 100 percent availability.
The power inside the tunnel consists of various high and low
voltage distribution power networks.
Primarily the tunnel is fed via two Eskom 11Kv power feeding
cables with a backup feeder overhead line from Paarl
municipality.
The ventilation fan’s inside the tunnel operates on 6.6KV
power source via high voltage transformers.
In this field my work was only limited to inputs and outputs
signals that were fed to the plc’s.
I further have competency by operating High voltage
switchgear switching up to 22KV.
Here I also assisted the HT engineer (appointed by SANRAL)
in protection trips, signal injection and testing of all relevant
alarm conditions.
The tunnel was equipped with a new SOS system working in
conjunction with a public address system.
It is an Ethernet base system and was interface onto the fibre
optic network.
I installed all the hardware equipment up to where the
appointed supplier setup and commissioned the system.
The tunnel has come a long way since the days of cctv
video. I started out by only using pal cameras, then
interfacing pal cameras with ip video converters and lately
moving towards video management ip systems.
Currently the tunnel operates on a Bosch video
management system.
Since the network was upgraded, the demand for CCTV
coverage throughout the tunnel was a high priority.
Another 50 cameras was added for monitor and security
surveillance. Here I installed, setup and commissioned the
entire CCTV system.
Certain cameras that monitored slow moving, deceleration
and stop vehicle detection via the Trafficon system had to
be interface with new Bosch system.
Each incident that are alarmed will trigger a traffic plan that
in turn will switch certain traffic signals, variable messages
signs within the tunnel.
Traffic system such as the Trafficon system is the hard of
operation in relaying correct incidents to alarm and keeps
the operator at all times updated with traffic flow,
congestions as well as any breakdowns in the tunnel.
Here I maintained, setup and repaired all traffic control
systems to a point of 100 percent availability.
Part of the Huguenot Tunnel operations is the collection of
toll fees. Auto vehicle classifications systems were used to
classify different class of vehicles for correct collection of
monies.
Although the toll plaza operation went through different toll
collection systems through the years, the operations and
method of software and hardware integration remains the
same principal of operation
Systems were maintained by me and to allow full toll lane
availability for traffic toll collection at all times.
As the possibility of fire condition in the tunnel at any time the
tunnel fire hydrant system are fed by two reservoirs up the
mountain on either side of the mountain that will provide
enough water pressure for fire extinguishment.
My responsibilities were to check and maintain all electronic
valves and reservoir level indication transmitters/sensors
within the water system.
As health and safety is an important aspect in the tunnel
operations, the company strived for zero harm tolerance in
the work environment.
As a Health and Safety committee member my
responsibilities was to oversee all HSE matters regarding sub-
contractors that were onsite.
Here I implemented a Safety file system where all the
contracted and non-contracted contractors where listed
and recorded.
Risk assessments were done for each contractor that was
onsite in their scope of work. Regular HSE meetings were held
to involved contractors in safe working practices.
Huguenot tunnel operations received 100 percent external
audit report for five consecutive months.
In my job as maintenance technician, the ability to provide
the availability of all systems at any time to the operations of
the tunnel and toll plaza, were great achievements as I
strived for perfection.
As Technical Manager my achievements were to complete
all projects and projects within budgets for SANRAL. There
were challenges, but through dedicated work I have
achieved it.
In my work environment to communicate with different
workforce personal, civil and technical to interact and work
together as a team was a great achievement as well.
As the technical manager in collaboration with SANRAL and
the engineer representing SANRAL for the Huguenot tunnel
we discuss future projects and the implementation of
upgrading systems.
SANRAL will allocate budgets for certain projects as well as
capital works. Once projects were decided on, I will source
and do pricing on systems that will fit the criteria. Some of the
projects were civil; here I only oversee these projects on
behalf of SANRAL.
The latest project was to extent the street lighting from the
existing streetlights to over the VIADUCT Bridge with LED light
fittings from BECA/Schneider.
As the bridge lights had to be at a 45 degree angle to the
road surface to illuminate the roadway, the challenge was
to illuminate the bridge in a way that the eco environment
was not compromised.
SEE CV for other projects.