Lecture 3 Screening & Sedimentation_1.ppt
description
Transcript of Lecture 3 Screening & Sedimentation_1.ppt
Screening and Sedimentation
Some of the material in the lecture slides is adapted from several textbooks and electronic resources
Flow Diagram of a WWTP
Treatment LevelsTreatment Level
Description
Preliminary Removal of wastewater constituents such as rags, sticks, floatables, grit, and grease that may cause maintenance or operational problems with the treatment operations, processes, and ancillary systems
Primary Removal or portion of the suspended solids and organic matter from wastewater
Secondary Removal of biodegradable organic matter (in solution or suspension) and suspended solids. Disinfection is also typically included in the definition of conventional secondary treatment
Tertiary Removal or residual suspended solids (after secondary treatment), usually by granular medium filtration or microscreens. Disinfection is also typically a part of tertiary treatment. Nutrient removal is often included in this definition
Advanced Removal of dissolved and suspended materials remaining after normal biological treatment when required for various water reuse applicationsLevels of Wastewater Treatment
Adapted from MEDAWARE ME8/AIDCO/2001/0515/59341-P033, Task 4: Urban Wastewater Treatment Technologies Part I, December 2004
ScreeningThese are
Physical processesInexpensiveCan be incorporated into WWT operations
Location of screens and bar racks – where??
Located at intakes from rivers, lakes and reserviors for water treatmentLocated at the well into which main trunk sewer discharges for WWTSometimes near pumping stations
What’s their function?Remove coarse solids, sticksWhy??
To avoid damage to pumps or clog downstream sections (pipes and channels)
ScreeningSpacing of screen bars can have
Coarse openings, 50-150 mmMedium, 20-50 mmFine screens, with an opening of 10 mmLess as proposed by few researchers
Critical limits for screensVelocity in the approach channel to the screens should not be <0.6 m/sDepth to width in the approach channel ranges from 1 to 2
Installation of screensWith an inclination?
To facilitate the removal of debris
Typical bar racks or bar screens Bar Racks (or bar screens):
Bar racks consist of bars spaced 10 to 50 mm apart and are usually mechanically cleaned. The screens are placed in rectangular channels.
The raking, done by means of endless chains on sprockets, moves the debri (screenings) upward and drops in a collection bin.
The screenings are odorous and also attract flies.
They are disposed by incineration or land filling or by returning to the wastewater flow after shredding (using comminutors).
Head Loss
Head loss through the screensIs a function of the flow velocity and the openings
∆h and h1 – h2 = [vSc2 - v2]/ (2gCd
2) from Bernoulli’s equation, where
h1 and h2 are upstream and downstream depths of flow,
Cd is the discharge coefficient (typical value ~0.84),
v and vSc are upstream velocity and velocity of flow through the screen
Orifice equation is often used
Water profile through the screen
Head Loss and Cleaning
Open area is often reduced by the space taken by the mesh
Screens to be manually cleanedThe area should be 50% of the open area (the half clogged condition)Head loss is estimated at the maximum flow condition
Cleaning of screensBy hand or automatically
Screenings areNon-putresciblecollected and hauled away to incinerator or landfill disposal site
Screens at WWTCoarse screens (with openings of 50-150 mm)
Used ahead of wastewater pumps
Openings of 25 mm are suitable for most other devices or processes
Installed at the beginning of the treatment plant after the water is pumped from the trunck sewer or influent wet well
Which are protected by coarse bar racks
Medium to large installations, mechanically cleaned screens are used
to reduce labor costsfor better flow conditionsimprove capture
Screening
Coarse screens
6-150mm
Microscreens <50μm
Fine screens <6mm
Manually cleaned
Mechanically cleaned
Static wedgewire
Drum Step
Chain-driven Reciprocating rake
Catenary Continuous belt
FIGURE 8: Definition Sketch for Types of Screens Used In Wastewater Treatment Source: Metcalf & Eddy, 2003
Types of Screens
Screening Volume Variation
This is a design chart based on data collected from several installations (around 133) in the US (showing volume variation with bar opening)
Coarse Screenings Characteristics
This tabular information provides information on screenings collected from separate and combined sewer systems. Combined sewers can produce several times the amount of screenings collected from separate sewer areas during storm flows (peak collection can vary as high as 20:1 on an hourly basis
Sedimentation / Clarification
Removal of particulate matter, chemical floc, and precipitates from suspension through gravity settling
Design variables include detention time, overflow rate, weir loading, and horizontal velocity
Basins Rectangular (more common) or circular Upflow or radial flow
What is it?Physical separation of suspended material from a water by the action of gravity
Sedimentation
Inlet – evenly distributes the flow across x-sectional area
~ 25% of tank in theory
Settling – gravity settling
Outlet – remove effluent
Sedimentation Basin Zones
Sedimentation Basin Zones
Sludge storage – holds settled material
~ 75% of the settable solids may settle in the first 1/5 portion of the tank
Depth for sludge storage should be about 0.3m near the outlet and 2m near the inlet
~ 1 to 10% slope
1% for mechanically cleaned5 to 10% for manually cleaned
Primary Sedimentation Basins
Design principlesBasic design principles evolved for sedimentation in water treatment apply for wastewater treatment also.The solids settling at the bottom of the sedimentation basin (referred to as primary sludge) is removed by mechanical scrapers. Grease and oil which float to the surface are removed by a skimming system.
Surface loading is the controlling parametertypical values ranging from 25 to 50 m3/m2.d
Detention time: 1.5 to 2.5 h
Weir loading: 120 - 200 m3/m.d
Depth: 2 - 5 m (~3.5 m)
Length to width ratio for rectangular basins: 3 to 5:1
Efficiency of primary settling basins: Suspended solids removal: 50 - 60% BOD removal: 30 - 35%
Sedimentation Types What is it?
Physical separation of suspended material from a water by the action of gravity
Settling properties of particles are often categorized into one of three classes:
Type I - particles settle discretely at a constant settling velocity (i.e., no flocculation)
Type II - particles flocculate during sedimentation (since they flocculate their size is constantly changing (i.e., vs is )
Type III - particles settle as a mass (i.e., lime softening)
Hindered settling - Particle concentration is sufficiently high to cause particles to settle as a structured mass
Compression settling - Particle concentration in the lower regions of the basin are sufficiently high to provide structural support for particles above
Type I - Discreet Settling
Particles settle
without significant inter-particle interaction due to low concentration of particles
Analysis is by use of Stokes' equation
Application is typically grit removal
Type II Flocculant settling
Particles agglomerate, thus increasing their size during the sedimentation process
Analysis is by empirical method using laboratory sedimentation data
Flocculant sedimentation is usually the dominant process in
primary clarification, settling following attached growth bioprocesses and water treatment clarification
Type III Hindered and Compression Settling
Hindered settling Particle concentration is sufficiently high to cause particles to settle as a structured mass
Compression settling Particle concentration in the lower regions of the basin are sufficiently high to provide structural support for particles above
Analysis for these types are done usingboth empirical and theoretical methods
Hindered and compression settling usually dominant in activated sludge final clarifiers and sludge thickening tanks
Sedimentation
A discrete particle's velocity can be described by an explicit equation developed by Stokes.
What is the key parameter needed prior to designing a basin?
Settling velocities of particles must be known
Physical properties determine the settling velocities
Forces Acting on a particle
FF
F
What are the three forces acting on a particle settling in water or another fluid?
Type I Analysis
Fd = the drag, acting in the upward direction as the particle settles
Fb = the buoyancy due to the water displaced by the particle, acting in the upward direction
Fg = the gravitational force, acting in the downward direction
FdFb
Fg
Type I Analysis
Fg = mp g [Gravity term]g = gravitational constant, [9.8 m/s2]
mp = particle mass, [Kg]
F + F = F bdg
][ termDragVAC2
1 = F 2
wdd Cd = drag coefficient, dimensionless
A = particle cross-sectional area, [m2]
w = density of water, [Kg/m3]
V = velocity, [m/s]
The buoyant force acting on the particle is: [Buoyancy
term]
mw = mass of water displaced, [Kg]
gm = F wb
gV + vAC2
1 = gV pw
2wdpp
Fg
FbFD
When above three relationships are substituted into the overall force balance equation, one can get
wd
pwp 2
1
AC
gV) - 2( = V
Stokes Equation
wd
pwp 2
1
C
gd) - (
3
4 = V
Solving for the settling velocity, V,
If we assume a spherical particle (the assumption is reasonably accurate), the relationships for particle area and volume can be used, yielding:
Stoke’s Law
Using the previous relationships, the particle settling velocity can be estimated
as a function of the properties of the particle and water, and the particle diameter
This relationship is known as Stokes' Law, and the velocity is known as the Stokes' velocity.
It is the terminal settling velocity for a particle.
18
gd) - ( = V
2wp
p
Grit RemovalTypical grit chambers are designed to retain particles with a diameter greater than 0.21 mm or 0.0083 in.
The vertical velocity of water in a grit chamber or settling basin is often termed the overflow rate.
Although it is a velocity, it is usually expressed as m3/m2-day or Gal/ft2-day.O/F = overflow rate (velocity), [m3/m2-day]
Q = flow rate, [m3/day]A = clarifier area, [m2]
18
gd) - ( = V
A
Q = O/F
2wp
p
Application
To remove a specific size particle
set its Stokes' velocity equal to the overflow rate.
Example
Estimate the settling velocity of sand (density = 2650 Kg/m3) with a mean diameter of 0.21 mm.
Assume the sand is approximately spherical. (Sand is not spherical but the assumption works well.)
Using a scale up factor of 1.4 to account for inlet and outlet losses, estimate the area required for a grit chamber to remove the sand if the flow rate is 0.10 m3/sec.
From a table providing the properties of water:
the density of water at 20°C is 998 Kg/m3. the viscosity of water at 20°C is 1.01 x 10-3 N-sec/m2 (Newton = Kg-m/s2).
Solution Cont’d
Use Stokes' settling velocity
Calculate the overflow rate
(3.9 cm/sec)
Estimate the area required for the grit chamber
(3.6 m2) - the area required for the grit chamber to remove 0.21 mm grit from the wastewater.
Grit Chamber Grit
Inert and inorganic material (sand, gravel, road grit, metal pieces, bone chips, glass pieces, etc) in the wastewater
FunctionTo protect equipment from abrasion (for pumps and other mechanical devices), to prevent pipe clogging, and to prevent accumulation in settling basin, digestors, etc.
Design principle: The grit chamber must be designed to remove only grit and not organic matter. Organic matter will be kept in suspension, and any organic matter that might settle must be resuspended by scour.
Grit with a specific gravity of 2.65 has a settling velocity of 30 mm/s.
Organic particle with a specific gravity of 1.10 has a settling velocity of 3 mm/s.
The design of a grit chamber exploits the difference in settling velocities of these particles.
Horizontal-flow, grit chambers
In a horizontal-flow, velocity controlled grit chamber, the velocity of wastewater flow is maintained at 0.30 m/s so that only grit will settle out. This grit chamber will have to be designed to maintain constant velocity of 0.3 m/s.
Maintaining a constant velocity of 0.3 m/s can be achieved in:
a channel of parabolic cross-section, controlled by a downstream standing wave flume, or a channel of rectangular cross-section, controlled by a proportional-flow weir at the outlet
The grit chambers are narrow channels also with a length to depth ratio of 20:1. The detention time is about 1 min.
Aerated grit chambers are also used for grit removal.
The grit, removed by mechanical collectors, is disposed of by burial or used as a fill material. If it still contains organic material, it is sent to sanitary landfills.
Horizontal Flow Grit Chamber
Scraper mechanism moves grit to center for removal
In order for grit to be removed in a horizontal flow grit chamber, it must reach the bottom of the chamber (or tank) before the flow carrying it reaches the exit. Thus removal of a particle is dependent on
its settling velocity,
the flow rate into the tank,
the basin or tank size.
Sedimentation Design
t = V / Qvo = Q / A
vo = Overflow Rate (gal/day)A = Total Surface Area (ft2)
If vs > vo particles will settle!
Sketch for an ideal, horizontal flow, rectangular basin
H - effective depth of the settling zonevf – longitudinal velocity of the waterB – width of the basinv1 and v0 – settling velocities applied to different particles entering at the top of basin
v2 – applies to a particle entering the settling zone at a height h, above the sludge zone
Sedimentation Design
Design volume must be related toThe influent flow rate and particle settling velocityParticle that takes the longest time to remove will be the one that enters at the top of the effective zoneVo = Design settling velocity = Q/A
Implying that design is independent of the depth and depends only on the surface overflow or loading rate
If particle velocity < vo it will eventually exit with the effluent overflowing from the basinIf particle velocity> vo it will be removed after being introduced into the basin regardless of the residence time of water in the basin
Sketch for an ideal, horizontal flow, rectangular basin
Vf
D
L
Settling Velocities & Limits
What minimum settling velocity is required to remove a grit particle entering the chamber at the water surface?
Settling Velocities and Limits
What minimum settling velocity is required to remove a grit particle entering the chamber at the water surface?
Vf
D
L
Vc
Vr
Vf
D
L
Settling Velocities and Limits
What happens when a particle with a settling velocity of Vc enters at some level below the water surface?
D
L
Settling Velocities and LimitsWhat happens when a particle with a settling velocity of Vc enters at some level below the water surface? It will impact before the end of the chamber.
Vc
Vr
Vf
Vf
D
L
Settling Velocities and Limits
What happens when a particle with a settling velocity of less than Vc enters at the water surface?
V<VcVp
Vf
D
L
Settling Velocities and Limits
What happens when a particle with a settling velocity of less than Vc enters at the water surface?It will not be removed.
V<VcVp
D
L
Settling Velocities and Limits
What happens when a particle with a settling velocity of less than Vc enters at a point below water surface?It is dependent on depth and settling velocity.
Vf
V<VcVp
Vf
V<VcVp
Vf
V<VcVp
Vf
V<VcVp
Vf
V<VcVp
{No
Vf
V<VcVp
Vf
V<VcVp
Vf
V<VcVp
Vf
V<VcVp
{Yes
D
L
Settling Velocities and Limits
What happens when a particle with a settling velocity of less than Vc enters at a point below water surface?It is dependent on depth and settling velocity.
Vf
V<VcVp
Vf
V<VcVp
Vf
V<VcVp
Vf
V<VcVp
Vf
V<VcVp
{No
Vf
V<VcVp
Vf
V<VcVp
Vf
V<VcVp
Vf
V<VcVp
{Yes
Horizontal Flow Grit Chamber
{{
No
Yes
Vf
Vr
Vp
VcD
L
Grit Chamber RemovalAny particle with a critical settling velocity greater than or equal to Vc will always be removed before exiting the chamber. Particles with velocities less than Vc will be removed only partially.
{{
No
Yes
Vf
Vr
Vp
Vc D
L
Grit Chamber RemovalLet us suppose a particle has a settling velocity of Vc as it enters the chamber.
If the entry point is near the bottom of the chamber, it will be removed. If it is near the top of the tank it will not be removed.
{{
No
Yes
Vf
Vr
Vp
VcD
L
Example: Grit Chamber Design
Design a grit chamber to remove sand particles (p = 2650 kg/m3) with a mean diameter of 0.21 mm. The wastewater flow is 10,000 m3/d. A velocity of 0.3 m/s will be automatically maintained, and the depth must be 1.5 times the width at maximum flow.
Assumptions:
The sand is spherical and the temperature of the wastewater is 20oC.
Example: Grit Chamber Design
Calculate settling velocity0.039 m/s
Calculate the cross-sectional area0.39 m2
Calculate the width and depth0.51 m and 0.76 m
Determine the detention time required for a particle to fall the entire tank depth
19.4 s
Determine the length to achieve this detention time
5.8 mThe tank must have dimensions
W = 0.51 m, D = 0.76 m, L = 5.8 m
Example: Grit Chamber Design
Calculate the cross-sectional area
v
QAx
s
min
min
d
m
s
d
m3
6014403.0000,10xA
2m 39.0xA
Example: Grit Chamber Design
Calculate the width and depth
25.15.1 WWWAx
m 51.05.1
39.0
5.1
5.05.0
xA
W
m 76.05.151.05.1 WD
Example: Grit Chamber Design
Determine the detention time required for a particle to fall the entire tank depth
Determine the length to achieve this detention time
Thus, the tank must have dimensions
W = 0.51 mD = 0.76 mL = 5.8 m
s m/s
m 4.19
039.0
76.0
sd v
Dt
m m/s s 85304.19 ..vtL d
Grit Chamber RemovalWe can calculate the fraction removed for any given particle size (and thus settling velocity). The velocity vectors depicting this can be shown graphically. Removal rate calculations will now be developed.
The vertical velocity of water in a sedimentation basin, V, is a function of the volumetric flow rate, Q, and the area of the basin, A, or, Vc = Q/A
However, the volumetric flow rate is also equal to the basin volume, V, divided by the detention time , or, Q =V/θ
Vc = V/Aθ
Since V/A is the basin height (or depth), Vc =h/θ
meaning that the critical settling velocity in a sedimentation basin is a function of the basin depth, h, and the hydraulic detention time, .
Grit Characteristics
Grit is composed of a variety of particle sizes
Particle settling velocity varies with particle density and size
Determine the size distribution and settling velocities
Screening Grit
The grit is placed in a screening device with successively smaller screen sizes
As the screens and grit are vibrated, grit passes through successive screens until it is retained on a screen with openings smaller than the grit
Each fraction can then be weighed to determine its contribution
Settling Velocities
The mean settling velocity of each fraction can then be determined by experiment or Stokes' Law
Grit RemovalTo calculate the fraction of grit removed we note that all grit particles with a settling velocity equal to or greater than Vc are removed, or
t
cpcp m
VVm1VVR
Where R is the removal contribution for particles with a settling velocity greater than or equal to the critical settling velocity, Vc
m is the mass fraction with a settling velocity greater than or equal to the critical settling velocity, vc
A fraction, but not all, of the grit particles with a settling velocity less than Vc are also removed
Grit RemovalFor each size fraction, the removal is equal to the ratio of the average particle velocity divided by the critical removal velocity, or (VP/VC)
The fractional removal of particles with a settling velocity less than Vc is then:
Since both Vc and mt are constants, they can be removed from the summation, yielding:
The total removal is then the sum of the two fractions, or:
The application of this is demonstrated in the example to follow.
t
in
1i c
i,pcp m
m
V
VVVR
n
1iii,p
tccp mV
mV
1VVR
n
1iii,p
tct
cpmV
mV
1
m
VVmR
Sedimentation Designh/H < v/vo Fractional removal h/H = v/vo
Proposed by Bharagave and Rajgopal (1989),J. Environ Eng Div., ASCE, pp. 1191-1198.
U is the ratio of sizes through which 60 and 10% by wt of the particles pass
(the size through which 10% by wt of the particles pass)
Sedimentation Design
Sedimentation Design
U is the ratio of sizes through which 60 and 10% by wt of the particles pass
P10 is the size through which 10% by wt of the particles pass
Design Continued
Weir loading – divide the average daily quantity of flow by the total effluent weir length (gal/d.ft)
________________________________ Type of Flow Weir Loading
______________ _________m3/d•m ____Light alum floc – low TU 143 – 179Heavy alum floc – high TU 179 – 268Heavy floc from lime softening 268 – 322_____________________________________
Sedimentation Rules of Thumb
Detention time 4 hours
Horizontal velocity 0.5 ft/min
Max weir loading 20,000 gal/day•ft
vo between 500 - 800 gal/day •ft2
vs > vo
Sedimentation Concepts
Two critical variables in the design of sedimentation basins are vs and vo
If vs > vo, particles will settle
For design, find vs and let vo = 80% vs
P = 100 vs / vo
P = % of particles removed
It is best to determine vs based on sedimentation lab data
ExampleEstimate the amount of grit removed from a grit chamber with an inflow of 12,500 m3/day and effective area of 5 m by 5 m (or 25 m2). A sieve analysis with approximate settling velocities is shown in the following table.
Weight Fraction
Settling Vel., m/min
0.02 0.05 0.05 0.15 0.05 0.2 0.1 0.3 0.1 0.4 0.2 1 0.2 2
0.28 4
Solution
First, we need to calculate the critical settling velocity:
Vc = 0.35 m/min
Note that the weight fractions with settling velocities greater than 0.35 m/min will be removed completely.
Next, calculate the fractional removal:
Grit removal of 92%.
n
1iii,p
tct
cpmV
mV
1
m
VVmR
daym
m500
m25
day
m500,12
A
QV
2
3
2
3
c
min
m35.0Vc
Solution
First, we need to calculate the critical settling velocity:
Settling Velocities
Weight Fraction
Settling Vel., m/min
Comment
0.02 0.05 V<Vc; Fract. removed 0.05 0.15 V<Vc; Fract. removed 0.05 0.2 V<Vc; Fract. removed 0.1 0.3 V<Vc; Fract. removed 0.1 0.4 V>Vc; All removed 0.2 1 V>Vc; All removed 0.2 2 V>Vc; All removed 0.28 4 V>Vc; All removed
Settling Velocities
Weight Fraction
Settling Vel., m/min
Fraction Removed
0.02 0.05 0.00288 0.05 0.15 0.0216 0.05 0.2 0.0288 0.1 0.3 0.0864 0.1 0.4 0.1 0.2 1 0.2 0.2 2 0.2 0.28 4 0.28
Sum = 0.92
n
1iii,p
tct
cpmV
mV
1
m
VVmR
Solution
Note that the weight fractions with settling velocities greater than 0.35 m/min will be removed completely.
Next, calculate the fractional removal:
n
1iii,p
tct
cpmV
mV
1
m
VVmR
]3.01.02.005.0
15.005.005.002.0[0.135.0
10.1
28.02.02.01.0R
92.014.078.0R
Solution
Thus, a grit removal of 92%
Weight Fraction
Settling Vel., m/min
Fraction Removed
0.02 0.05 0.00288 0.05 0.15 0.0216 0.05 0.2 0.0288 0.1 0.3 0.0864 0.1 0.4 0.1 0.2 1 0.2 0.2 2 0.2 0.28 4 0.28
Sum = 0.92
n
1iii,p
tct
cpmV
mV
1
m
VVmR
Horizontal Flow Grit Chamber
Typical loading parameters are:
Detention time of 45 to 90 s at peak flow
Horizontal velocity of 0.8 to 1.3 ft/s
Head loss 30 to 40% of channel depth
Aerated Grit Chamber
Another common method of removing grit is the aerated grit chamber.
The water enters a concrete basin with aerators along one side at the bottom.
The critical design parameters for an aerated grit chamber are:
a detention time of 2 to 5 minutes at peak flow and
an air supply of 2 to 5 ft3/min-ft of chamber length
Air in
Aerated Grit Chamber
Air induces a spiral flow through the chamber
Grit falls out beneath the aerator in a collection channel
Aerated Grit Chamber
Aerated grit chambers have the following typical physical size restrictions:
a length of 25 to 65 ft.depth of 7 to 15 ft.width of 8 to 25 ft.length to width ratio of 3:1 to 5:1width to depth ratio of 1:1 to 5:1
A plant with a peak flow of less than 3 MGD will be over designed.
Example: Aerated Grit Chamber
Estimate the volume of an aerated grit chamber for Carbondale’s Southeast WWTP. Assume a detention time of 3 minutes at a peak flow of 12 MGD.
To complete the design, the length, width, depth and air requirements must also be calculated.
QθV
min60hr
hr24d
min3d
Gal10x12V 6
3ft3340Gal000,25V
Flocculant SettlingFlocculant or Type II settling occurs when particle concentrations are sufficiently high that particles collide and agglomerate as they settle.
As a result of this agglomeration process, the particle size distribution, as well as effective density, does not remain constant but instead, changes with depth.
Thus, Stoke’s Law is difficult to apply.
Flocculant Settling Cont’dNo straightforward analytical solution to this type of settling has been developed.
Flocculant settling is usually analyzed by empirical means using laboratory data obtained from column settling experiments.
Such experiments yield the suspended solids concentrations at various depths over the anticipated settling time.
Settling column description
at least 8 in. in diameter approximately the same depth as the anticipated sedimentation basin
h 0
h 1
h 2
h 3
h 4
h 5
h 6
h 7
h 0
h 1
h 2
h 3
h 4
h 5
h 6
h 8
h 7
Scale Up Factors
When column settling data is used to size a sedimentation basin (primary, secondary, or thickening)
the final calculated area or detention time is usually multiplied by a scale-up factor of 1.25 to 1.5
Why?? to allow for the less than ideal settling which occurs in a “real” basin.
[See Wastewater Engineering, M&E]
Sampling ProcedureA sample of the wastewater to be treated is placed in the column and initially mixed.
An initial set of data is taken from the sampling ports and analyzed to determine the starting solids concentration as well as the initial uniformity of the solids.
At time intervals thereafter, the ports are sampled to determine the suspended solids concentration. This process is continued for approximately two to three hours.
The data collected then provides a history of the suspended solids concentration versus time for different heights in the column.
This information, in turn, can then be used to estimate the basin suspended solids removal versus time.
h 0
h 1
h 2
h 3
h 4
h 5
h 6
h 7
h 0
h 1
h 2
h 3
h 4
h 5
h 6
h 8
h 7
Flocculant Analysis
If we look at one sampling port on the column, h1, the initial suspended solids concentration is TSSh1-0.
If, in fact, the entire column has a uniform initial TSS concentration, then it is TSS0 at all heights.
At some later time, t, the concentration at sampling point h1 is then TSSh1-t.
h 0
h 1
h 2
h 3
h 4
h 5
h 6
h 7
h 0
h 1
h 2
h 3
h 4
h 5
h 6
h 8
h 7
%100x
TSS
TSSTSSR%
0
t,1h0t,1
%100x
TSS
TSSTSSR%
0
t,2h0t,2
Flocculant Analysis
The removal at that point during time t is then:
The removal at height h2 is
The average removal from h1 to h2 is then:
2
R%R%R% t,2t,1
t,1h
2
R%R%x
h
h
R%xh
hR%
t,2t,1
T
1
t,1hT
1t,1h
Flocculant AnalysisThe contribution this element has to the overall removal at time t is the removal multiplied by the fraction of the total height it represents, or, where hT is the total basin height
Flocculant SettlingThe total removal at any time t is the sum of the removals at each height segment, or,
n
i
titi
T
it
RR
h
hR
0
,1,
2
%%%
Typical Removal Curves
Primary Sed. Design Information
Min Max Typ.
Detention time at average flow, hr
1.5 2.5 2.0
Overflow rate at average flow, Gal/ft2-day
800 1200 1000
Overflow rate at peak flow, Gal/ft2-day
1000 3000 2500
Weir loading, Gal/ft-day
10,000 40,000 25,000
Typical Circular Primary Basin Sizes
Range Typical
Depth, ft 10 to 15 12 to 13
Diameter, ft. 10 to 300+ 40 to 100
Bottom slope, in/ft.
.75 to 2 1
Scraper tip speed, ft/min
6 to 12
Example: Analysis of Flocculant Settling Data
Design a primary settling system for a wastewater plant with an average flow of 3.2 MGD and a peak flow of 9 MGD.
Use two identical circular primary clarifiers, each to receive one-half of the flow. The basins should remove at least 65% of the solids at average flow.
Specify the depth and diameter. Check the weir loading. The data below was obtained from a settling column similar to the one shown previously.
After the basins are sized, recalculate the actual removal at both average and peak flows.
Settling Column Data
Suspended Solids Data (mg/L) at IndicatedTime (min) and Height
Station Ht.,m
0, min 30, min 60, min 90, min 120, min
h0 4 178 N/A N/A N/A N/Ah1 3.5 198 95 62 40 33h2 3 190 120 85 60 42h3 2.5 192 125 102 71 54h4 2 192 128 110 85 66h5 1.5 188 137 120 95 76h6 1 194 144 128 102 79h7 0.5 201 149 130 109 87h8 0 196 154 132 110 91
Process OverviewStep1 : Estimate the removal at different times and heights.
Step 2: Next construct the removal vs. time graph.
Step 3: Estimate the detention time required.
Step 4: Use the standard design criteria to determine the area and depth.
Solution
The first step is to calculate an average or initial TSS concentration, TSS0.
The next step is to use this TSS0 value to determine the TSS removal as a percentage.
These calculations are ideally suited to a spreadsheet analysis, although they can be done equally well by hand given the time.
L/TSSmg192n
TSS
TSS
n
1ii
0
Sample Calculations
The average initial TSS concentration is:
Removal at 4 m,30 min
Since any particles in the water will have a finite settling velocity, in theory, they should settle below the top of the basin at any finite time. Thus, the removal at the top of the basin at any finite time is 100 percent.Suspended Solids Data (mg/L) at Indicated
Time (min) and HeightStation Ht.,
m0, min 30, min 60, min 90, min 120, min
h0 4 178 N/A N/A N/A N/Ah1 3.5 198 95 62 40 33h2 3 190 120 85 60 42h3 2.5 192 125 102 71 54h4 2 192 128 110 85 66h5 1.5 188 137 120 95 76h6 1 194 144 128 102 79h7 0.5 201 149 130 109 87h8 0 196 154 132 110 91
%5.37
%100xL/mg192
L/mg120L/mg192
%100xTSS
TSSTSSR%
0
min30,m30min30,m3
Removal at 3 m, 30 min
%5.50
%100xL/mg192
L/mg95L/mg192
%100xTSS
TSSTSSR%
0
min90,m5.10min90,m5.1
Removal at 1.5 m, 90 min
Removal Summary
% Removal at Indicated Time (min) and Height
Station ColumnHt., m
0 30 60 90 120
h0 4 7.5% 100.0% 100.0% 100.0% 100.0%
h1 3.5 -2.9% 50.4% 67.5% 79.2% 82.9%
h2 3 0.8% 37.5% 55.8% 68.8% 77.9%
h3 2.5 0.0% 35.0% 46.7% 62.9% 72.1%
h4 2 0.0% 33.3% 42.5% 55.8% 65.8%
h5 1.5 2.1% 28.8% 37.5% 50.5% 60.4%
h6 1 -0.8% 25.0% 33.3% 46.7% 58.8%
h7 0.5 -4.6% 22.5% 32.5% 43.3% 54.6%
h8 0 -2.1% 19.6% 31.3% 42.5% 52.5%
Average Removal = 0.0% 39.1% 49.7% 61.1% 69.4%
Removal Curve
Estimating Detention Time
The previous graph indicates a detention time of approximately 103 minutes.
Using a scale up factor of 1.25 the actual detention time is:
hr15.2min129
min10325.1
SF
actual
actual
columnactual
Basin Volume
The total basin volume required is then:
3
36
ft300,38V
Gal48.7ft
hr24day
hr15.2dayGal
102.3V
QV
Since there will be two basins, the volume of each is 19,200 ft3.
Question
We now know the volume. How do we determine the diameter (or surface area) and the depth?
We use the standard overflow rates to estimate an area at both average flow and peak flow. We choose the larger area. We can then calculate the diameter and depth.
Basin Area
Initially assuming the maximum overflow rate at both average and peak flows:
Q = AV = A x OFR
2avg
2
6
avg
ft2670A
dayft
Gal1200
dayGal
102.3
OFRQ
A
Min Max Typ.
Detention time ataverage flow, hr
1.5 2.5 2.0
Overflow rate ataverage flow,Gal/ft2-day
800 1200 1000
Overflow rate atpeak flow, Gal/ft2-day
1000 3000 2500
Weir loading,Gal/ft-day
10,000 40,000 25,000
Basin Area
And, for the peak flow:
2avg
2
6
peak
ft3000A
dayft
Gal3000
dayGal
109
OFRQ
A
Note, if the peaking factor is 2.5, the two areas will be equal.
Min Max Typ.
Detention time ataverage flow, hr
1.5 2.5 2.0
Overflow rate ataverage flow,Gal/ft2-day
800 1200 1000
Overflow rate atpeak flow, Gal/ft2-day
1000 3000 2500
Weir loading,Gal/ft-day
10,000 40,000 25,000
Basin Diameter
The larger area is 3000 ft2, so we must use it. Each basin will be one-half the total area, or 1500 ft2. This corresponds to a diameter of:
ft7.43D
ft9.21ft1500A
r
rA
2
2
One can round this to a standard diameter of 45 ft.
2
2
2
ft1590A
ft5.22A
rA
Basin Diameter
A diameter of 45 ft. results in an actual area of:
Basin Depth
We will now use the area and required volume to calculate the minimum depth:
ft07.12d
ft1590
ft200,19AV
d
dAV
2
3
One can round this to 13 ft. to maintain the required detention time.
Recheck of Parameters
Actual detention time at average flow is:
hrs3.2
hr24day
Gal48.7ft
dayGal
106.1
.ft13.ft5.22
Qdr
QV
36
2
2
Recheck of Parameters
Actual detention time at peak flow is:
min49hrs083.0
hr24day
Gal48.7ft
dayGal
105.4
.ft13.ft5.22
Qdr
QV
36
2
2
No established standard, but some consulting firms will not design below one hour at peak.
Recheck of Parameters
Actual overflow rate at average flow:
ft1006OFR
ft1590
dayGal
106.1
AQ
OFR2
6
Min Max Typ.
Detention time ataverage flow, hr
1.5 2.5 2.0
Overflow rate ataverage flow,Gal/ft2-day
800 1200 1000
Overflow rate atpeak flow, Gal/ft2-day
1000 3000 2500
Weir loading,Gal/ft-day
10,000 40,000 25,000
Average flow of 3.2 MGD and a peak flow of 9 MGD
Recheck of Parameters
Actual overflow rate at peak flow:
ft2830OFR
ft1590
dayGal
105.4
AQ
OFR2
6
Min Max Typ.
Detention time ataverage flow, hr
1.5 2.5 2.0
Overflow rate ataverage flow,Gal/ft2-day
800 1200 1000
Overflow rate atpeak flow, Gal/ft2-day
1000 3000 2500
Weir loading,Gal/ft-day
10,000 40,000 25,000
Average flow of 3.2 MGD and a peak flow of 9 MGD
Recheck of Parameters
Weir loading rate:
dayft/Gal800,31WLF
.ft45d
Gal105.4
WLF
D
Q
L
QWLF
6
pp
Estimated RemovalTo estimate the removal, first recall we multiplied the required area/detention time, by a scale-up factor of 1.25. To re-estimate the removal at average and peak flows, we must “remove” the safety factor.
min11025.1min138
min4025.1min49
25.1
avg,corrected
peak,corrected
designcorrected
Removal Curve
Estimated Removal
From the removal graph,
Flow Removal
Average flow 67%
Peak flow 44%
Summary
Parameter Values
Number of units
Diameter
Depth
2
45 ft
13 ft
Hindered and Compression Settling
Hindered settling occurs
when the number of particles is sufficiently high that they settle as a structured mass.
Compression settling occurs
where particle numbers are so high that particles above can only settle if lower particles are further compressed—the lower particles actually support upper particles.
Hindered and Compression Settling
Hindered and compression settling occurs only in the lower regions of sedimentation basins. It is rate determining step
in most secondary sedimentation basins receiving activated sludge
in gravity thickening used to concentrate waste primary sludge and sometimes waste activated sludge.
Hindered and Compression Settling
Hindered and compression settling are normally analyzed together. The two most common methods of analyzing hindered and compression settling are
the solids flux method and
the Talmadge and Fitch method
Column Settling
00.5
11.5
22.5
0 30 60Time, min
Set
tlin
g D
ista
nce
, m
Flocculent
Hindered Compression
Solids Flux Method
Flux is a mass crossing a boundary or area.
The solids flux method used to analyze sedimentation processes can be developed
by studying the mass of solids passing an arbitrary plane within a sedimentation basin.
Solids FluxThe mass of solids passing the arbitrary plane increases with increasing inlet solids concentration to some limiting value and then decreases rapidly.
This decrease past some maximum inlet solids concentration is caused by the structure of the solids at the bottom of the tank preventing the rapid settling of the solids above.
Solids Flux
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
0 5 10 15Concentration, g/L
So
lid
s F
lux
, K
g/m
2-h
r
@ low concentration – low flux due to less solids@ high concentration – low flux due to extreme hindered settling
Solids Flux
This maximum point is termed the limiting solids flux. Let us develop the equations to describe this process, solve the system, and determine that limiting or maximum solids flux.
Ai
Vp Ci
Solids FluxAn arbitrary area, Ai, with solids of concentration Ci, and velocity Vi crossing the plane.
Solids FluxThe solids flux, Gi, is the concentration times the velocity, or
ipi CVG
Gi = solids flux, mass/area-time
Vp = particle velocity, length/time
Ci = particle concentration, mass/volume or mass/length3
Ai
Qu
Qi+Qu
Qi
Solids Flux
Ai
Qu
Qi+Qu
Qi
QuestionWhat is the fluid velocity at the plane Ai?
i
uf
fiu
A
QV
VAQ
uit GGG
uiiit VCVCG
Solids Flux
Note from fluid mechanics that
A
QV
i
ui
i
iit A
QC
A
QCG
Then,
L
iuii G
CQQA
Solids FluxIf we use the maximum or limiting solids flux, GL, with the inlet solids concentration, we obtain the following
Which is the minimum area required for settling
Solids Flux
The solids have two velocity components:
A gravity component due to the movement of solids as they settle in the tank
A fluid component due to fluid being pumped out the bottom of the tank (bulk fluid movement)
Solids Flux vs Concentration
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
0 5 10 15
So
lid
s F
lux
, Kg
/m2
-hr
Concentration, g/L
Gravity flux – solids transport by gravity
Pumped flux-Underflow withdrawalIncreases the downward movement of solids
Total flux
Limiting flux
Solids transmitting capacity of each layer varies with the concentration of the layerOverall or total flux has a minimum & maximum Minimum point determines the design area of the clarifierMinimum solids handling capacity of the suspension is the limiting flux
Solids Flux
Recall that a scale up factor of 25% to 50% is applied to the area based on column settling data. Or, the area is multiplied by 1.25 to 1.50. See page 228 of M&E, 3rd. Edition.
Example: Solids FluxAn activated sludge wastewater treatment plant currently has an average flow of 2.5 MGD. The aeration basin reactor solids concentration is 2500 mg/L and the desired underflow concentration is 13,000 mg/L. You may assume that the recycle flow will never exceed 50% of the plant flow.
Determine the total secondary settling basin area required and the diameter if two identical basins are utilized.
Example: Solids Flux
Let’s convert the flow to metric;
hr
m394Q
hr24
d
L10
m
Gal
L78.3
d
Gal105.2Q
3
i
3
36
i
The recycle flow is half this, or;
hr
m197Q
3
u
Example: Solids FluxFrom the solids flux graph in the spreadsheet the limiting solids flux is 4.9 Kg/m2-hr. The required area is then:
hrm
Kg9.4
g10
Kg
m
g2500
hr
m197
hr
m394
A
G
CQQA
2
33
33
i
L
iuii
Example: Solids Flux
The minimum required area is then;
22i ft3240m301A
A scale up factor of 1.25 to 1.50 (25% to 50%) is usually used for the area determined by column settling studies. Thus,
22i ft4375ft324035.1A
Example: Solids Flux
This yields a surface overflow rate of;
dayft
Gal571RateF/OV
ft4375d
Gal105.2
A
QV
2
2
6
i
i
Which is within the acceptable range of 400 to 800 Gal/ft2-day. Note that overflow rates are based on plant flow excluding recycle.
Example: Solids Flux
To calculate the area:
ft8.52D
ft4.26ft2190
r
rft21902
ft4375A
2
222
b
Question
What size units would be selected?
Round up to the next available size.
Some manufacturers only provide specific sizes, typically in 5 ft. increments.
Others, may provide any requested size in 1 ft. increments.
Assuming 5 ft. increments, the actual diameter would then be 55 ft. So, two units, 55 ft. in diameter are required.