Transcript of lecture 1-theory_QS, measurement, BQ, SMM

Page 1: lecture 1-theory_QS, measurement, BQ, SMM

QS, MEASUREMENT, DOCUMENTATION,

SMM

Prepared by:Prepared by:

Ms. Noorhidayah Sunarti

School of Quantity Surveying & Construction Management

Page 2: lecture 1-theory_QS, measurement, BQ, SMM

Contents:Contents:

General QS services Measurement process Attributes of QS Traditional preparation of BQ Modern preparation of BQ Standard Methods of Measurement

Page 3: lecture 1-theory_QS, measurement, BQ, SMM

QS Services

In general;QS offers its clients (developer/owner, consultant, contractor or sub contractor) a wide range of professional services in the areas of project/ construction management, quantity surveying, cost/ contract /claim/ planning solutions according to their requirements in a most cost effective and efficient manner.

QS  is managed by a group of highly qualified and experienced professionals providing Project management, Construction Cost Consultancy, Estimation,  Quantity Take-off, Construction Cost Databases, Specification and Construction Material  Databases etc.

Page 4: lecture 1-theory_QS, measurement, BQ, SMM

The Measurement Process / Quantity Take-off

The main purpose measurement process is to produce quantity for the measured works to prepare for Bills of Quantities.

A Bill of Quantities is prepared for tendering purposes.

Using BQ, contractor is able to price the work with a minimum effort.

The quantification of the work is done either by the main contractor, subcontractor, or package contractor.

Page 5: lecture 1-theory_QS, measurement, BQ, SMM

Attributes of a Quantity Surveyor

Ability to describe clearly, fully and precisely the requirements of the designers and arrange the

Bills of Quantities.

The contractor’s estimator can quickly, easily and accurately arrive at the estimated cost of

the work.

??????

Page 6: lecture 1-theory_QS, measurement, BQ, SMM

Attributes of a Quantity Surveyor

Ability to describe clearly, fully and precisely the requirements of the designers and arrange

the Bills of Quantities.

The surveyor must be:

• careful and accurate in making calculations

•having systematic and orderly mind

•be able to visualize the drawings and details

How to How to achieve this ?achieve this ?

Page 7: lecture 1-theory_QS, measurement, BQ, SMM

Divisions of bill preparation

Traditionally, the preparation of BQ divides into 2 distinct stages:

1. The measurement of the dimensions and the compilation of the descriptions from the drawings and specification. This process commonly known as taking-off .taking-off .

2. The preparation of the bill. o This involves the calculation of volumes, areas, etc

((squaring the dimensions).squaring the dimensions). o Then followed by entering the descriptions and the

squared dimensions on the an abstract sheet (abstracting)(abstracting) to collect similar items together and present them in recognized bill order.

o From this abstract, the draft bill was written (billing). (billing).

Page 8: lecture 1-theory_QS, measurement, BQ, SMM

Development of bill preparation

The utilization of computerized system is become more integrated for direct input of quantities sand formulation of descriptions through the use of standard libraries of descriptions, and the lengthy collating and the bill preparation processes is carried out automatically. WinQs CatoPro MasterBill QS Elite Snape Vector, etc

Page 9: lecture 1-theory_QS, measurement, BQ, SMM

TOPIC:Measurement & Bills of

Quantity

Prepared by:Ms Noorhidayah Sunarti

[email protected]

Page 10: lecture 1-theory_QS, measurement, BQ, SMM

The Measurement Process / Quantity Take-off

The main purpose measurement process is to produce quantity for the measured works to prepare for Bills of Quantities.

A Bill of Quantities is prepared for tendering purposes (selection process to contract an eligible contractor for the project).

Using BQ, contractor is able to price the work with a minimum effort.

The quantification of the work / measurement / taking-off is done either by the QS consultant (Client), QS of main contractor or subcontractor or Estimator.

Page 11: lecture 1-theory_QS, measurement, BQ, SMM

The Measurement of Quantities The Measurement of Quantities for Building Works for Building Works

Main objective: To produce the document for the list of quantities

(bills of quantity). The quantities meaning the estimated amount of building works / trade works for specific building elements.

The quantities needed to ensure the exact amount of trade works in completing the building / project.

The measurement is based on the principles and rules of measurement set up in manual of STANDARD METHODS OF MEASUREMENT FOR BUILDING WORKS.

Page 12: lecture 1-theory_QS, measurement, BQ, SMM

Standard Methods of Measurement Standard Methods of Measurement (SMM)(SMM)

Function:

To standardize the method of preparing the measurement for building works and civil engineering works. Contains of rules and principles of measurement.

Malaysian Standard Methods of Measurement for Building works. (SMM2) – Institution of Surveyors

Malaysia (ISM) (adapted from SMM by RICS(UK)

Malaysian Standard Method of Measurement for civil engineering works (CESMM) – CIDB (adapted from CESMM by ICE / FCEC(UK)

Page 13: lecture 1-theory_QS, measurement, BQ, SMM

Standard Methods of Measurement for Building Works (SMM)

Set out rules for the measurement and description of building works.

SMM2 is a document that provides not only a uniform basis for measuring building work but also embodies the essentials of good practice.

Without using it, a set of rules the quality of BQ can vary widely.

Page 14: lecture 1-theory_QS, measurement, BQ, SMM

Malaysian Standard Method of Measurement for Civil Engineering Works (CESMM)

To be used in conjunction with the Conditions Of Contract for Civil Engineering Works.

Does not deal with the preparation of BQ for mechanical & electrical engineering work, building work or work which is seldom encountered in civil engineering contracts.

If any such work to be included in the contract, such work shall be measured in accordance with their respective SMM and shall be stated in the Preambles to the BQ.

Page 15: lecture 1-theory_QS, measurement, BQ, SMM

The Bills of quantity prepared by Quantity Surveyor based on measurement from the construction drawings / building plans and specification prepared by the designers/ engineers.

This document were itemized all the quantities for each categories of works applied in constructing the buildings. E.g. building works, mechanical, electrical works, civil, structural works, infrastructure works, etc.

The contractor will priced /estimate all the works associated in completing the buildings during pre-construction stage.

The Bills of QuantitiesThe Bills of Quantities

Page 16: lecture 1-theory_QS, measurement, BQ, SMM

BQ is part of legal tender / contract document which will be used to bind the agreement between the client and the contractor in terms of:

Detailed of construction works to be done on-site – building works, infrastructure works, building services works, water & sewerage systems, etc.

The materials used – standard / quality

The standard workmanship /construction methods,

The needs / requirements of the builders on-site in implementing the jobs on–site – e.g. temporary offices, storage, shelter / hostel for workers

The Bills of QuantitiesThe Bills of Quantities

Page 17: lecture 1-theory_QS, measurement, BQ, SMM

Advantages of using BQAdvantages of using BQ

According to Seeley (1997),

Avoids the need of for all of the tendering contractors to measure the quantities of work themselves before preparing an estimate. (if yes, wasteful duplication of efforts and an increase in Contractor’s overhead).

BQ prepared in accordance to SMM ensure that an adequate description of work in a recognized format is given to all tendering Contractors and all tender on the same basis.

The detailed breakdown of the contract sum (in BQ format) permits proper financial management of the contract.

Page 18: lecture 1-theory_QS, measurement, BQ, SMM

Disadvantages of using Disadvantages of using BQBQ

The absence of BQ leads to greater variability, increase risk in estimating and consequently more disputes.

Page 19: lecture 1-theory_QS, measurement, BQ, SMM

The binding parties of a The binding parties of a ContractContract

ClientClient: has intention to build building- developer, owner, funder, etc.

ContractorContractor: a person / company who has expertise & experience to build building / infrastructure works, water and sewerage system and install the building services- electrical, mechanical.

Page 20: lecture 1-theory_QS, measurement, BQ, SMM

Basic contents of typical Basic contents of typical contract documentscontract documents

Conditions of contract Contract drawings Specification Preambles Bills of quantities Schedule of rates

Page 21: lecture 1-theory_QS, measurement, BQ, SMM

Purpose / Objectives / RolesPurpose / Objectives / Roles

Project stages Explanation

PRE- CONTRACT

(before official

contract signed

between client –

contractor)

Tendering stage

To enable the contractor to tender to a project & price the described works.

To control in ordering materials and assessing the labour requirement for the contract.

POST-CONTRACT

(contract signed and

the selected contractor

started their works till

completion stage)

Construction stage

Provides basis for valuation of variation work and adjustments for the final account.

Provides basis for valuation of monthly progress payment referring to the working progress on site.

Project completed

After being priced, it provides a good basis for cost analysis which subsequently will be used in future contract especially for cost planning works. (cost data)

Page 22: lecture 1-theory_QS, measurement, BQ, SMM

Types of Bill of QuantityTypes of Bill of Quantity

Types of Bill similarities differences

Fixed price/ lump

sum

The architects and engineers prepare detail construction drawings.QS measures the quantities in detail based on the construction drawingThe QS prepare BQ based on the measurement.Virtual completion of the design proceeds the signing of the contract.

Both the quantities and unit rates form part of the contract A detail breakdown of all the quantities is shown in the BQThe empty bill is supplied to the contractors to tender / price the described works/ project.

Approximate The QS prepares BQ but subjected to later adjustment.Only unit rates form part of the contract.The signing of the contract and beginning of the project may proceed before the whole design is complete.The empty bill is supplied to the contractors to tender / price the described works/ project.

Drawings and

specification

The contractors are supplied with drawings with full specifications.No empty bill is supplied to the contractors.The contractors prepare their own BQ.Suitable for small project (less than RM500,000)

Page 23: lecture 1-theory_QS, measurement, BQ, SMM

Basic contents of Bills of Basic contents of Bills of QuantitiesQuantities

Preliminaries Specifications of materials and

workmanship Preambles (only in Bill of Approx Qtty)

Measured works bill Schedules of rates (only in Bill of Approx

Qtty)

Page 24: lecture 1-theory_QS, measurement, BQ, SMM

PreliminariesPreliminaries

It must: Contain a definition of the scope of worksdefinition of the scope of works and

details of the proposed form of contract / details of the proposed form of contract / project.project.

Contain a detailed description of the administrative mechanism / temporary facilities to implement the contract / project.

Contain list of drawings and any special instructions to the contractor – highlighting the method of pricing and presenting tenders and other site information.

Page 25: lecture 1-theory_QS, measurement, BQ, SMM

SpecificationSpecification

A concise description of materials and workmanship, standard or quality of workmanship.

It must convey the architect and engineer’s requirements.

Page 26: lecture 1-theory_QS, measurement, BQ, SMM

Measured worksMeasured works Includes detailed descriptions of building, mechanical

and electrical works presented in accordance with SMM.

This enables the contractors’ estimator / QS to price individual item of work.

This section also includes Prime cost sum (P.C) and Provisional sum (Prov. sum)

P.C. sum – used for works to be carried out by nominated sub-contractors, statutory authorities or for goods to be supplied by nominated suppliers.

Prov. Sum - used for works which cannot be fully detailed or for costs which are unknown at the time bills are prepared.

Page 27: lecture 1-theory_QS, measurement, BQ, SMM

PreamblesPreambles

Define the rules governing the method of measurement of the works and contain instruction as to what is to be included within unit rates and/or lump sum prices.

The preambles do not define the scope of works.

Page 28: lecture 1-theory_QS, measurement, BQ, SMM

Schedule of Rates

Consists of unit of works that are grouped according to trade and work content and are presented in tubular form.

Each table is referred as ‘schedule’.

The schedule of rates comprises a number of schedules that when combined, cover all items of work likely to be encountered in the contract.

Page 29: lecture 1-theory_QS, measurement, BQ, SMM

Divisions of bill preparation

Traditionally, the preparation of BQ divides into 2 distinct stages:

1. The measurement of the dimensions and the compilation of the descriptions from the drawings and specification. This process commonly known as taking-off .taking-off .

2. The preparation of the bill. o This involves the calculation of volumes, areas, etc

((squaring the dimensions).squaring the dimensions). o Then followed by entering the descriptions and the

squared dimensions on the an abstract sheet (abstracting)(abstracting) to collect similar items together and present them in recognized bill order.

o From this abstract, the draft bill was written (billing). (billing).

Page 30: lecture 1-theory_QS, measurement, BQ, SMM

Traditional Techniques of BQ Traditional Techniques of BQ preparationpreparation

Process Description of worksMeasuring / taking-off

QS will analyze the drawings / plan received from engineers’ / architect.Prepare query list (if necessary)Measuring from drawings and entering the dimensions on to specially ruled dimension paper

Working up / squaring

Calculating and totaling the area, length, volume, numbers, item of the dimensions to obtain the exact quantities for each measured item in the dimension sheet.

Transfer to abstract sheet

Collecting the totals form dimension paper on to an abstract to produce a final total for each individual description.

Billing Reproducing the items from the abstract on to bill paper in draft form ready for typing.

Page 31: lecture 1-theory_QS, measurement, BQ, SMM

Preparation of billingitem description Qty unit rate amount

1.0 Supply to site 125mm x 125mm pressure treated timber piles of 6m lengths with provisions of galvanized mild steel anti split rail at both ends.

320 NR RM100.00 RM32,000.00

2.0 Drive 125mm x 125mm timber piles to required depth

1,920 M RM12.00 RM23,040.00

3.0 100mm thick Grade 15 lean concrete.

115 M2 RM18.00 RM2,070.00

4.0 Grade 35 concrete at brick retaining wall

8 M3 RM180.00 RM1,440.00

5.0 Bringing to and removing from site all plant required for this section of the work

ITEM RM1,800.00 RM180.00

Page 32: lecture 1-theory_QS, measurement, BQ, SMM

Development of bill preparation

The utilization of computerized system is become more integrated for direct input of quantities sand formulation of descriptions through the use of standard libraries of descriptions, and the lengthy collating and the bill preparation processes is carried out automatically. WinQs CatoPro MasterBill QS Elite Snape Vector, etc

Page 33: lecture 1-theory_QS, measurement, BQ, SMM

SETTING DOWN SETTING DOWN DIMENSIONDIMENSION

Prepared by:Ms Noorhidayah [email protected]

Page 34: lecture 1-theory_QS, measurement, BQ, SMM

Dimension Paper Dimension are taken / measure from

the drawings by the taker-off. Column 1 = timesing / timesing /

dotting on column dotting on column (where multiplication and addition of the dimensions can be recorded)

Column 2 = dimension dimension columncolumn (in which the measurements are set down as taken from drawings and normally expressed in two decimal point.

Column 3 = squaring columnsquaring column (in which are set out the calculated volumes, areas, etc)

Column 4 = description description columncolumn (in which is written the description of the work to which the dimensions apply.

Column 5 = Waste Waste (in which preliminary calculations / sketches are made/ shown)

1 2 3 4 5

Page 35: lecture 1-theory_QS, measurement, BQ, SMM

Units of Measurement

Cubic measurement = m3 Square or superficial measurement = m2 Linear measurement = m Enumerated items – Nr/ Nos. Items

Page 36: lecture 1-theory_QS, measurement, BQ, SMM

Expressions of Measurement / Rules in setting down the dimension

The dimension are normally expressed to two decimal points. It is important that the insertion of the horizontal lines which determines whether the dimension is intended as linear, superficial, or cubic measurement.

Page 37: lecture 1-theory_QS, measurement, BQ, SMM

Rules in setting down the dimension:

Timesing

Page 38: lecture 1-theory_QS, measurement, BQ, SMM

Rules in setting down the dimension:

Dotting-on

Page 39: lecture 1-theory_QS, measurement, BQ, SMM

Rules in setting down the dimension:

Alterations in dimensions

Reminder:

•Deletions with correcting fluid are not encourage.

•It is best to nil entirely and write out again the dimensions.

Page 40: lecture 1-theory_QS, measurement, BQ, SMM

Rules in setting down the dimension:

Anding-on

Note: Anding-on , deductions shall be in similar form of dimension.

Page 41: lecture 1-theory_QS, measurement, BQ, SMM

Rules in setting down the dimension:

Deductions

Where a deduction is to be made, the description is preceded by Deduct which is often abbreviated to Ddt.

An example as follows: