Lecture 06 project_cost_management
-
Upload
sayed-ahmed -
Category
Technology
-
view
29 -
download
0
Transcript of Lecture 06 project_cost_management
PROJECT MANAGEMENT, PMI APPROACH (PMP)PROJECT COST MANAGEMENT
Sayed AhmedBSc. Eng. in CSc. & Eng. (BUET, Bangladesh)MSc. in CSc. (University of Manitoba, Canada)http://sayed.JustEtc.nethttp://www.JustETC.net
[email protected], www.justEtc.net1
Just E.T.C for Business, Education, Technology, and Entertainment Solutions
Resources:Book: PMP in Depth by Dr. Paul Sanghera Book: The PMP Exam, How to Pass on Your First Try By Andy CroweProject Management Lessons in Undergraduate StudyWork Experience
2
[email protected], www.justEtc.net
WHAT DOES COST INVOLVE? Costing Involves
Cost to purchase, develop i.e. to have the system
Operation cost Cost to disposal
Value Engineering Get the most from a project
Decrease cost Increase value Increase quality Shorten schedule Keep project scope not reduced
3
[email protected], www.justEtc.net
COST ESTIMATING When cost estimation is done?
After project scope is defined and work breakdown structure is created But may be performed again and again
over the total life cycle
4
[email protected], www.justEtc.net
COST ESTIMATING Tools
Analogous Estimating Based on the similar actual projects
Bottom up estimating Estimate cost for each activity and sum them - time
consuming Parametric Estimating
1 mile road construction needs $400,000. So 10 miles will require $10*400,000
Reserve Analysis A buffer cost against slippage on the project
Cost of Quality Costs required in order to get quality
Output Activity Cost Estimates
5
[email protected], www.justEtc.net
COST BUDGETING Cost Budgeting
Maps costs and dates How much will be spent on what and when Also, termed Cost Baseline
When is cost budgeting done? After
activities are defined and scheduled Activity durations and resource requirements are also
estimated
6
[email protected], www.justEtc.net
COST BUDGETING Tools
Cost Aggregation Activity level costs should be aggregated to the work level
where they will be measured, managed, and controlled Reserve Analysis
Financial reserve to protect projects against cost overrun Parametric Estimating
Use simple straight forward formulas Funding Limit Reconciliation
Comply with the project funding Many times funds are allocated even before the scope is
defined Output
Cost Baseline Project Funding requirements
7
[email protected], www.justEtc.net
COST CONTROL Cost Control
Monitoring, controlling, adjusting costs When is it performed?
Over the whole life cycle Bi-weekly or monthly analysis may be done
Tools Cost Change Control System
How the cost baseline may be changed Performance Measurement Analysis
Calculate Earned Value, Planned Value, Actual Cost, Estimate to complete, Estimate at Completion, Cost Performance Index and similar
to measure performance and control costs based on these Forecasting
Use current and previous cost values to estimate future costs Variance Management
9
[email protected], www.justEtc.net
COST MANAGEMENT TERMS Earned Value
The value the spent money brought to the project Just like double entry accounting system
for every debit to an account there is a corresponding credit Budgeted at Completion (BAC)
How much was originally planned for this project Planned Value (PV)
Calculates how much of the project should be complete at a certain date according to the plan
Planned Value = Planned%complete*BAC Earned Value (EV)
How much is actually done during a period EV=Actual%Complete*BAC
Actual Cost Money spent over the period
10
[email protected], www.justEtc.net
COST MANAGEMENT TERMS Cost Variance (CV)
Difference between planned cost and actual cost. CV = EV – AC
Schedule Variance (SV) Difference between the planned schedule and actual schedule (as:Where the project is in the schedule). SV=EV-PV
Cost Performance Index (CPI) The rate at which the project cost is performing regarding cost
expectations CPI is done for a given period of time. CPI = EV/AC
Cumulative CPI It's the CPI from the project start time to a particular point in
time. CCPI = CEV/CAC
11
[email protected], www.justEtc.net
COST MANAGEMENT TERMS Schedule Performance Index (SPI)
The rate at which the project is performing in respect of schedule expectations up to a point in time
SPI=EV/PV Estimate at Completion (EAC)
Forecast the total cost at project completion based on the project performance up to a point in time.
EAC = BAC/CCPI Estimate to Completion (ETC)
How much more will be spent to complete the project based on past performance.
Variance at Completion (VAC) Difference between what was budgeted and what will actually be
spent. VAC = BAC - EAC
12
[email protected], www.justEtc.net
PROJECT COST MANAGEMENT Project managers need to calculate these
values to get a good understanding of the project cost
He can get answers to questions like How much is spent? How much more are required? Is the project progress satisfactory in terms of
cost? These will ultimately help in project cost
control